JPH05280026A - Management system for excavation of slope surface and management method thereof - Google Patents
Management system for excavation of slope surface and management method thereofInfo
- Publication number
- JPH05280026A JPH05280026A JP4071607A JP7160792A JPH05280026A JP H05280026 A JPH05280026 A JP H05280026A JP 4071607 A JP4071607 A JP 4071607A JP 7160792 A JP7160792 A JP 7160792A JP H05280026 A JPH05280026 A JP H05280026A
- Authority
- JP
- Japan
- Prior art keywords
- excavation
- slope
- sensor
- positioning device
- site
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、ダム工事の掘削工程等
において有用な法面の掘削システム及び法面の掘削管理
方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a slope excavation system and a slope excavation management method useful in the excavation process of dam construction.
【0002】[0002]
【従来の技術】従来、ダム工事等における法面の掘削に
おいては、掘削しようとする法面の傾斜を示す丁張を設
置した後、地表面に削孔を行い、この削孔にダイナマイ
トを仕掛けて爆破していた。そして、この爆破後、丁張
を基準として油圧ブレーカによる仕上の掘削を実施して
いた。2. Description of the Related Art Conventionally, in the excavation of a slope in a dam construction, etc., after installing a strut showing the slope of the slope to be excavated, a hole is drilled on the ground surface and a dynamite is set on this hole. Had been blown up. Then, after this blasting, finishing excavation was carried out with a hydraulic breaker based on bracing.
【0003】法面の傾斜が変化する点(変化点)まで油
圧ブレーカによる仕上げの掘削が終了すると、この変化
点に新たな傾斜を示す丁張を設置し、その後、同様な操
作を繰り返えされることにより法面の掘削が行われてい
た。When finishing excavation by the hydraulic breaker is completed up to the point where the slope of the slope changes (change point), a tensioner showing a new slope is installed at this change point, and then the same operation is repeated. The excavation of the slope was carried out.
【0004】[0004]
【発明が解決しようとする課題】しかし、従来の掘削方
法においては、ダイナマイトを仕掛けるための削孔長を
正確に把握することができなかった。このため、爆破に
よる掘削の誤差が大きく、設計掘削線近くまで爆破によ
る掘削を行うことが困難であるため、油圧ブレーカによ
る仕上げの掘削量が大きくなり、作業の迅速化を図るこ
とが困難であるといった問題があった。However, in the conventional excavation method, the drilling length for setting the dynamite cannot be accurately grasped. For this reason, the excavation error due to the blast is large, and it is difficult to perform the digging near the design excavation line by the blast. Therefore, the amount of excavation for finishing with the hydraulic breaker is large, and it is difficult to speed up the work. There was such a problem.
【0005】また、変化点の探知や法面の切り残しの有
無の確認のために、観測者が掘削現場から離れた機械点
に出向いて測角や測距を行う必要があったため、作業に
人手や時間を要するといった問題があった。Further, in order to detect a change point and confirm whether or not the slope is left uncut, it is necessary for the observer to go to a machine point away from the excavation site for angle measurement and distance measurement. There was a problem that it took manpower and time.
【0006】さらに、掘削作業全般として現場における
図面の判読や各種の計算が必要となったり、熟練者の勘
にたよらざるを得なくなる場合が多く、作業の効率化が
図れないといった問題があった。Further, there is a problem in that the excavation work generally requires the interpretation of drawings on the site and various calculations, and it is often necessary to rely on the intuition of a skilled person, so that the work efficiency cannot be improved. ..
【0007】本発明は上述した問題点を解決するために
なされたものであり、迅速かつ効率的な掘削工事の実現
を可能にする法面の掘削管理システム及び法面の掘削管
理方法を提供することを目的とする。The present invention has been made in order to solve the above-mentioned problems, and provides a slope excavation management system and a slope excavation management method capable of realizing quick and efficient excavation work. The purpose is to
【0008】[0008]
【課題を解決するための手段】そこで、本発明の法面の
掘削管理システムは、掘削現場に配置されるセンサと、
前記センサの位置を探知する三次元位置決装置と、前記
三次元位置決装置により探知された前記センサの位置及
び予め入力されている設計掘削線の情報に基づいて掘削
管理に必要なデータの解析を行うコンピュータと、前記
掘削現場において前記コンピュータが解析したデーター
を出力するための出力手段とを備えるように構成した。Therefore, the slope excavation management system of the present invention includes a sensor arranged at the excavation site,
A three-dimensional positioning device for detecting the position of the sensor, and analysis of data required for excavation management based on the position of the sensor detected by the three-dimensional positioning device and information on the design excavation line that has been input in advance. And a outputting means for outputting the data analyzed by the computer at the excavation site.
【0009】また、本発明の法面の掘削管理方法は、掘
削現場に配置されるセンサの位置を三次元位置決装置に
より探知し、前記三次元位置決装置により探知された前
記センサの位置と予め入力されている設計掘削線の情報
に基いてコンピュータにより掘削管理に必要なデータを
解析し、前記掘削現場において前記コンピュータが解析
したデーターを出力手段に出力し、前記出力手段に出力
されたデータに基いて法面の掘削を行うように構成し
た。Further, in the slope excavation management method of the present invention, the position of the sensor arranged at the excavation site is detected by the three-dimensional positioning device, and the position of the sensor detected by the three-dimensional positioning device is detected. The data required for excavation management is analyzed by a computer based on the information of the design excavation line that is input in advance, the data analyzed by the computer at the excavation site is output to the output means, and the data output to the output means It was configured to excavate the slope based on the.
【0010】[0010]
【作用】本発明によれば、三次元位置決装置により探知
された掘削現場におけるセンサの位置と予め入力されて
いる設計掘削線の情報に基いて掘削管理に必要なデータ
の解析をコンピュータにより行う。この解析されたデー
ターを掘削現場における出力手段に出力し、現場におけ
るオペレーターはコンピュータにより解析されたデータ
に基いて法面の掘削工事を行う。よって法面の掘削工事
の迅速化、効率化を図ることが可能になる。According to the present invention, the computer analyzes the data necessary for excavation management based on the position of the sensor at the excavation site detected by the three-dimensional position determining device and the information of the previously designed excavation line. .. The analyzed data is output to the output means at the excavation site, and the operator at the site performs excavation work on the slope based on the data analyzed by the computer. Therefore, the excavation work on the slope can be speeded up and made more efficient.
【0011】[0011]
【実施例】以下、図面を参照して本発明の実施例につい
て説明する。図1は、本発明に係る法面の掘削管理シス
テム10を示す。Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 shows a slope excavation management system 10 according to the present invention.
【0012】図1において、この法面の掘削管理システ
ム10は、掘削中の法面に配置されるセンサ11と、こ
のセンサ11の位置を求める三次元位置決装置12とを
備えている。また三次元位置決装置12により求められ
たセンサ11の位置と、予め入力されている設計掘削線
の情報とに基づいて、掘削管理に必要な各種データの解
析を行うコンピュータ13と、掘削現場から三次元位置
決装置12及びコンピュータ13を操作するとともにコ
ンピュータ13が解析したデーターを出力するためのリ
モートコントローラ14とを備えている。In FIG. 1, this slope excavation management system 10 comprises a sensor 11 arranged on the slope during excavation, and a three-dimensional positioning device 12 for determining the position of this sensor 11. In addition, based on the position of the sensor 11 obtained by the three-dimensional positioning device 12 and the information of the design excavation line that has been input in advance, a computer 13 that analyzes various data necessary for excavation management, and the excavation site. The remote controller 14 is provided for operating the three-dimensional positioning device 12 and the computer 13 and outputting the data analyzed by the computer 13.
【0013】この法面の掘削管理システム10におい
て、三次元位置決装置12は三角測量等により座標値が
求められた既知点に設置されている。この三次元位置決
装置12はセンサ11に向かって光波を発する。そし
て、掘削現場に設置されたセンサ11はこの光波を三次
元位置決装置12に反射する。センサ11によって反射
された反射光は三次元位置決装置12により感知され、
三次元位置決装置12においては、この三次元位置決装
置12が設置されている既知点の座標値と反射光に基い
て、センサ11の現在地の座標が求められる。In the excavation management system 10 on the slope, the three-dimensional position determining device 12 is installed at a known point whose coordinate value is obtained by triangulation or the like. The three-dimensional positioning device 12 emits a light wave toward the sensor 11. Then, the sensor 11 installed at the excavation site reflects this light wave to the three-dimensional positioning device 12. The reflected light reflected by the sensor 11 is sensed by the three-dimensional positioning device 12,
In the three-dimensional positioning device 12, the coordinates of the current position of the sensor 11 are obtained based on the coordinate value of the known point where the three-dimensional positioning device 12 is installed and the reflected light.
【0014】このような三次元位置決装置12としては
公知の光波探知機、例えば、ジオジメーター株式会社製
ジオジメーター140T型等を用いることができる。セ
ンサ11としては三次元位置決装置から発せられた光波
を反射する反射プリズムを用いることができる。このセ
ンサ11は、図2に示されるように、棒状部材20の一
端に設けられており、オペレーターは掘削現場において
このセンサ11が設けられた棒状部材20を持って移動
することによりセンサ11を掘削現場において自由に移
動させることが可能である。また、センサ11が棒状部
材の先端に設けられていることにより地表面の凹部でも
センサ11を見通すことが可能になる。As such a three-dimensional position determining device 12, a known light wave detector, for example, Geosimeter 140T type manufactured by Geosimeter Co., Ltd. can be used. As the sensor 11, a reflecting prism that reflects the light wave emitted from the three-dimensional positioning device can be used. As shown in FIG. 2, the sensor 11 is provided at one end of the rod-shaped member 20, and the operator excavates the sensor 11 by moving the rod-shaped member 20 provided with the sensor 11 at the excavation site. It is possible to move freely on site. Further, since the sensor 11 is provided at the tip of the rod-shaped member, it is possible to see through the sensor 11 even in the concave portion on the ground surface.
【0015】コンピュータ13は、メモリ15を備え、
このメモリ15には予め掘削しようとする設計掘削線の
情報が入力されている。また、このコンピュータ13は
三次元位置決装置12に接続されており、三次元位置決
装置12から入力されるセンサ11の現在地と予めメモ
リ15に入力されている設計掘削線の情報に基いて、法
面の掘削管理に必要な情報、例えば、法面の傾斜、削孔
長、設計掘削線上の任意の点とセンサの現在地との関係
等のデーターを数値あるいは画面で出力することができ
るように構成されている。The computer 13 comprises a memory 15,
Information on the design excavation line to be excavated is input to the memory 15 in advance. Further, this computer 13 is connected to the three-dimensional positioning device 12, and based on the current location of the sensor 11 input from the three-dimensional positioning device 12 and the information of the design excavation line previously input to the memory 15, Information required for excavation management of slopes, such as slope of slopes, drilling length, and the relationship between any point on the design excavation line and the current location of the sensor, can be output numerically or on a screen. It is configured.
【0016】本発明に係る掘削管理システム10におい
ては、出力手段としてのリモートコントローラ14によ
り三次元位置決装置12やコンピュータ13から離れた
場所、例えば掘削現場から、三次元位置決装置12やコ
ンピュータ13の繰作や各種データーの読み取りを行う
ことができる。In the excavation management system 10 according to the present invention, the remote controller 14 as the output means operates the remote controller 14 from the three-dimensional positioning device 12 and the computer 13, for example, from the excavation site, to the three-dimensional positioning device 12 and the computer 13. It is possible to read the data and various data.
【0017】このリモートコントローラ14は液晶ある
いはCRT等の表示画面を有し、センサ11の位置と設
計掘削線の関係を平面図、ダム軸方向断面図、ジョイン
ト方向断面図として表示することができる。これによっ
て、掘削現場のオペレーターは、平面図によりセンサの
現在地を、ダム軸方向断面図により削孔長、余掘削量
を、ジョイント方向断面図により法面のジョイント方向
の形状を知ることができる。The remote controller 14 has a display screen such as a liquid crystal display or a CRT, and can display the relationship between the position of the sensor 11 and the design excavation line as a plan view, a dam axial direction sectional view, and a joint direction sectional view. As a result, the operator at the excavation site can know the current location of the sensor from the plan view, the drilling length and excess excavation amount from the dam axial sectional view, and the shape of the slope in the joint direction from the joint direction sectional view.
【0018】次に、本発明に係る法面の掘削管理方法の
概要について、図3を参照して説明する。コンピュータ
13のメモリ15には予め掘削しようとする設計掘削線
の情報が入力される(ステップ101)。Next, an outline of the slope excavation management method according to the present invention will be described with reference to FIG. Information on the design excavation line to be excavated is input to the memory 15 of the computer 13 in advance (step 101).
【0019】三次元位置決装置12は掘削現場のセンサ
11に光波を発し、センサ11はこの光波を反射する。
三次元位置決装置12はセンサ11からの反射光を受信
し、この受信した反射光と三次元位置決装置12が設置
されている既知点の座標に基いてセンサ11の位置の探
知を行う(ステップ102)。The three-dimensional positioning device 12 emits a light wave to the sensor 11 at the excavation site, and the sensor 11 reflects this light wave.
The three-dimensional positioning device 12 receives the reflected light from the sensor 11, and detects the position of the sensor 11 based on the received reflected light and the coordinates of the known point where the three-dimensional positioning device 12 is installed ( Step 102).
【0020】三次元位置決装置12により探知されたセ
ンサ11の位置はコンピュータ13に入力される(ステ
ップ103)。コンピュータ13は、予めメモリ15に
入力されている設計掘削線の情報及び三次元位置決装置
12から入力されたセンサ11の位置に基いて、掘削管
理に必要とされる各種データの解析を行う(ステップ1
04)。The position of the sensor 11 detected by the three-dimensional positioning device 12 is input to the computer 13 (step 103). The computer 13 analyzes various data required for excavation management based on the information of the design excavation line previously input to the memory 15 and the position of the sensor 11 input from the three-dimensional positioning device 12 ( Step 1
04).
【0021】コンピュータ13により解析されたデータ
は掘削現場おけるリモートコントローラ14に出力され
る(ステップ105)。オペレータはこのデータに基い
て各種の作業を行う。The data analyzed by the computer 13 is output to the remote controller 14 at the excavation site (step 105). The operator performs various operations based on this data.
【0022】以下、実際の法面の掘削方法に即して本発
明の法面の掘削管理方法について説明する。図4及び図
5は本発明に係る法面の掘削管理方法を説明するための
図である。The slope excavation management method of the present invention will be described below in accordance with an actual slope excavation method. 4 and 5 are views for explaining the excavation management method for the slope according to the present invention.
【0023】図4及び図5において、設計掘削線AA’
は本発明によって掘削を行う法面の断面を示す。この設
計掘削線AA’は、第1変化点41、第2変化点42、
第3変化点43において折れ曲がっており、各変化点間
41、42、43は直線で結ばれているものとする。4 and 5, the design excavation line AA '
Shows a cross section of a slope for excavation according to the present invention. The design excavation line AA ′ has a first change point 41, a second change point 42,
It is assumed that there is a bend at the third change point 43, and the change points 41, 42, and 43 are connected by a straight line.
【0024】また、図4においては、既に第1変化点4
1までの掘削は終了しており、以下、第1変化点41と
第2変化点42の間の法面44の掘削を行うものとす
る。さらに、これらの変化点41、42、43を見通す
ことができる既知点45には三次元位置決装置12が設
置されている。Further, in FIG. 4, the first change point 4 has already been reached.
The excavation up to 1 has been completed, and hereinafter, the slope 44 between the first change point 41 and the second change point 42 is to be excavated. Further, the three-dimensional positioning device 12 is installed at a known point 45 through which these changing points 41, 42, 43 can be seen.
【0025】折曲法面の掘削管理方法においては、ま
ず、地表面B上の所定位置B1に削孔を行い、この削孔
にダイナマイトを仕掛けて爆破を行う。このとき、本発
明の折曲法面の掘削管理方法においては、センサ11を
削孔に挿入することにより、削孔長と設計掘削線AA’
との関係をダム軸方向断面図として掘削現場におけるリ
モートコントローラ14に表示させることが可能にな
る。In the excavation control method for the bending slope, first, a hole is drilled at a predetermined position B1 on the ground surface B, and a dynamite is set in this hole to explode. At this time, in the excavation management method for the bending slope of the present invention, by inserting the sensor 11 into the drilled hole, the drilled hole length and the designed drilling line AA '.
It is possible to display the relationship with the as a sectional view in the axial direction of the dam on the remote controller 14 at the excavation site.
【0026】この点、従来の方法によれば、削孔は掘削
現場における計算に基いてあるいはオペレーターの勘に
より行われていた。これに比べ、本発明の法面の掘削管
理方法によれば、削孔と設計掘削線との関係を掘削現場
で把握した上で爆破を行うことが可能になる。従って、
設計掘削線近くまで爆破による掘削を行うことが可能に
なり、次に行われる油圧ブレーカによる仕上げの掘削量
を少なくすることができるので、作業の迅速を図ること
が可能になる。In this respect, according to the conventional method, the drilling is performed based on the calculation at the excavation site or the operator's intuition. On the other hand, according to the slope excavation management method of the present invention, it is possible to perform the bombing after grasping the relationship between the drilling hole and the design excavation line at the excavation site. Therefore,
It is possible to perform blasting up to near the design digging line and reduce the amount of digging for finishing by the hydraulic breaker that is performed next time, so it is possible to speed up the work.
【0027】尚、削孔が所定の深さに達していない場合
には、孔を深くすべく更に削孔を行う。この爆破により
新たな地表面Cが形成される。When the drilling has not reached the predetermined depth, further drilling is performed to deepen the drilling. A new ground surface C is formed by this blast.
【0028】この後、第1変化点41から第2変化点4
2に向かって油圧ブレーカで法面44の仕上げの掘削が
行われる。このとき、本発明の掘削管理方法において
は、掘削すべき法面の傾斜、掘削長、周囲の形状予測等
油圧ブレーカによる掘削に必要とされる情報を掘削現場
におけるリモートコントローラ14に表示させることが
でき、オペレータはこの情報に基いて作業を行うことが
可能になるので作業の効率化が実現できる。Thereafter, the first change point 41 to the second change point 4
The excavation of the slope 44 is done with a hydraulic breaker towards 2. At this time, in the excavation management method of the present invention, the information required for excavation by the hydraulic breaker, such as the slope of the slope to be excavated, the excavation length, and the surrounding shape prediction, can be displayed on the remote controller 14 at the excavation site. Since the operator can perform the work based on this information, the work efficiency can be improved.
【0029】尚、本発明の法面の掘削管理方法によれ
ば、現場におけるリモートコントローラ14に法面44
の傾斜を表示させることができるので、法面44の傾斜
を示す丁張は必ずしも必要とされない。従って、丁張の
設置に要する時間の短縮を図ることも可能になる。もっ
とも、第1変化点41あるいは法面44の任意の場所に
丁張を設置すれば、更に確実な作業を行うことができ
る。According to the slope excavation management method of the present invention, the slope 44 is formed on the remote controller 14 at the site.
The inclination indicating the inclination of the slope 44 is not necessarily required because the inclination of the slope can be displayed. Therefore, it is possible to shorten the time required for installing the strut. However, if the tension is installed at an arbitrary position on the first change point 41 or the slope 44, more reliable work can be performed.
【0030】1回の爆破のみでは、油圧ブレーカにより
第2変化点42までの掘削を行うことが困難な場合は、
再び、地表面Cにおける所定位置C1に削孔を行い、こ
の孔にダイナマイトを仕掛けて爆破を行う。この爆破に
よりさらに新たな地表面が形成される。When it is difficult to excavate up to the second change point 42 by the hydraulic breaker with only one blast,
Again, a hole is drilled at a predetermined position C1 on the ground surface C, and dynamite is set in this hole to explode. This blast creates a new ground surface.
【0031】そして、再びリモートコントローラ14に
出力されるデーターに基いて第2変化点42に向かって
油圧ブレーカで法面44の仕上げの掘削が行なわれる。
以下、ダイナマイトによる爆破と油圧ブレーカによる仕
上げの掘削は掘削法面44が第2変化点42に達するま
で必要回数繰り返される。Then, based on the data output to the remote controller 14 again, the excavation of the slope 44 is performed by the hydraulic breaker toward the second change point 42.
Hereinafter, the blasting with the dynamite and the finishing excavation with the hydraulic breaker are repeated as many times as necessary until the excavation slope 44 reaches the second change point 42.
【0032】掘削された法面44が第2変化点42まで
到達した頃を見計らって、作業者はセンサ11と、リモ
ートコントローラ14を持って法面44上を移動し、第
2変化点42の探知を行う。このとき、本発明によれ
ば、センサ11の現在地と第2変化点42との関係を数
値による座標値の差として、あるいは平面図、ダム軸方
向断面図、ジョイント方向断面図として、掘削現場にお
けるリモートコントローラ14に表示されるので、効率
よく第2変化点42を探知することが可能になる。Looking at the time when the excavated slope 44 reaches the second change point 42, the worker moves on the slope 44 with the sensor 11 and the remote controller 14 and moves to the second change point 42. Detect. At this time, according to the present invention, the relationship between the current position of the sensor 11 and the second change point 42 is expressed as a numerical difference in coordinate values, or as a plan view, a dam axial direction sectional view, and a joint direction sectional view at the excavation site. Since it is displayed on the remote controller 14, it becomes possible to detect the second change point 42 efficiently.
【0033】また、掘削された法面44上でセンサ11
を移動させていくことにより、法面44が設計掘削線ど
おりに仕上がっているか否か、の確認が可能である。The sensor 11 is also provided on the excavated slope 44.
It is possible to confirm whether or not the slope 44 is finished according to the design excavation line by moving the.
【0034】本発明による探知の結果、図5に示される
ように、法面の切り残し48があると判断された場合に
は、さらに、法面44の傾斜方向への掘削が続けられ
る。そして、油圧ブレーカによる掘削と、法面の掘削管
理システムを使用した第2変化点42の探知は、仕上げ
の掘削が第2変化点42に達するまで繰り返される。As a result of the detection by the present invention, as shown in FIG. 5, when it is determined that there is an uncut portion 48 on the slope, the excavation of the slope 44 in the inclination direction is further continued. Then, the excavation by the hydraulic breaker and the detection of the second change point 42 using the excavation management system on the slope are repeated until the finish excavation reaches the second change point 42.
【0035】この点、従来の方法によれば、第2変化点
42の探知や、法面44の切り残し48の有無等の作業
状況の確認が必要とされる場合は、法面から離れた機械
点で観測者がタキオメーターを使って視準を行う必要が
あった。これに比べ、本発明によれば、一旦、既知点に
三次元位置決装置12を設置すれば、作業者が掘削され
た法面44で、センサ11とリモートコントローラ14
を持って移動することにより、第2変化点42の探知や
法面44の切り残し48の有無の確認を行うことができ
る。With respect to this point, according to the conventional method, when it is necessary to detect the second change point 42 and to confirm the working condition such as the presence or absence of the uncut portion 48 of the slope 44, it is necessary to leave the slope. At the machine point, the observer had to collimate using the tachometer. In contrast, according to the present invention, once the three-dimensional positioning device 12 is installed at the known point, the sensor 11 and the remote controller 14 are provided on the slope 44 where the worker is excavated.
By moving while holding, it is possible to detect the second change point 42 and confirm the presence or absence of the uncut portion 48 of the slope 44.
【0036】掘削が第2変化点42まで終了すると、以
下、同様な方法で第2変化点42と第3変化点43の間
の法面46の掘削が行われる。尚、本発明は上述した実
施例に限定されるものではなく、適宜変更を加えること
が可能である。例えば、上述した実施例においては、ダ
ム工事における法面の掘削管理システム及び掘削管理方
法について説明したが、本発明はこれに限定されるもの
ではなく、土捨場工事、宅地造成工事、その他の切盛土
工事等においても利用することができる。When the excavation ends up to the second change point 42, the slope 46 between the second change point 42 and the third change point 43 is excavated by the same method. It should be noted that the present invention is not limited to the above-described embodiments, and can be modified as appropriate. For example, although the excavation management system and the excavation management method on the slope in the dam construction have been described in the above-mentioned embodiments, the present invention is not limited to this, and the disposal site construction, the residential land development construction, and other cutting It can also be used for embankment work.
【0037】さらに、上述した実施例においては、既知
点45に設置された三次元位置決装置12により掘削中
の法面44上のセンサ11の位置を求めるものである
が、本発明はこれに限定されるものではなく、例えば、
三次元位置決装置として、汎地球測位システム(GP
S)等の衛星測地システムを用いることも可能である。Further, in the above-described embodiment, the position of the sensor 11 on the slope 44 during excavation is determined by the three-dimensional positioning device 12 installed at the known point 45, but the present invention is not limited to this. It is not limited, for example,
As a three-dimensional positioning device, the Global Positioning System (GP
It is also possible to use satellite geodetic systems such as S).
【0038】[0038]
【発明の効果】以上のように構成した本発明によれば、
法面の掘削工事の迅速化、効率化を図ることが可能な法
面の掘削管理システム及び法面の掘削管理方法を提供す
ることが可能になる効果がある。According to the present invention configured as described above,
There is an effect that it is possible to provide a slope excavation management system and a slope excavation management method capable of speeding up and improving efficiency of slope excavation work.
【図1】 本発明に係る法面の掘削システムの概要を示
すブロック図。FIG. 1 is a block diagram showing an outline of a slope excavation system according to the present invention.
【図2】 センサの外観を示す図。FIG. 2 is a diagram showing an appearance of a sensor.
【図3】 本発明に係る法面の掘削方法の概要を示すフ
ローチャート。FIG. 3 is a flowchart showing an outline of a slope excavation method according to the present invention.
【図4】 法面の掘削方法を説明するための図。FIG. 4 is a diagram for explaining a method of excavating a slope.
【図5】 掘削法面に切り残しが形成されている状態を
示す図。FIG. 5 is a view showing a state where an uncut portion is formed on an excavation slope.
10・・・法面の掘削管理システム 11・・・センサ 12・・・三次元位置決装置 13・・・コンピュータ 14・・・リモートコントローラ 15・・・メモリ 10 ... Excavation management system of slope 11 ... Sensor 12 ... Three-dimensional positioning device 13 ... Computer 14 ... Remote controller 15 ... Memory
Claims (2)
ンサの位置を探知する三次元位置決装置と、前記三次元
位置決装置により探知された前記センサの位置及び予め
入力されている設計掘削線の情報に基づいて掘削管理に
必要なデータの解析を行うコンピュータと、前記掘削現
場において前記コンピュータが解析したデーターを出力
するための出力手段とを備えた法面の掘削管理システ
ム。1. A sensor arranged at an excavation site, a three-dimensional positioning device for detecting the position of the sensor, a position of the sensor detected by the three-dimensional positioning device, and design excavation previously input. A slope excavation management system comprising: a computer that analyzes data required for excavation management based on line information; and an output unit that outputs data analyzed by the computer at the excavation site.
次元位置決装置により探知し、前記三次元位置決装置に
より探知された前記センサの位置と予め入力されている
設計掘削線の情報に基いてコンピュータにより掘削管理
に必要なデータを解析し、前記掘削現場において前記コ
ンピュータが解析したデーターを出力手段に出力し、前
記出力手段に出力されたデータに基いて法面の掘削を行
うことを特徴とする法面の掘削管理方法。2. A position of a sensor arranged at an excavation site is detected by a three-dimensional positioning device, and the position of the sensor detected by the three-dimensional positioning device and information of a design excavation line previously input are used. Based on the computer to analyze the data required for excavation management, output the data analyzed by the computer at the excavation site to the output means, to perform excavation on the slope based on the data output to the output means. A characteristic excavation management method for slopes.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4071607A JPH05280026A (en) | 1992-03-27 | 1992-03-27 | Management system for excavation of slope surface and management method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4071607A JPH05280026A (en) | 1992-03-27 | 1992-03-27 | Management system for excavation of slope surface and management method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH05280026A true JPH05280026A (en) | 1993-10-26 |
Family
ID=13465509
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP4071607A Pending JPH05280026A (en) | 1992-03-27 | 1992-03-27 | Management system for excavation of slope surface and management method thereof |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH05280026A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0814900A (en) * | 1994-07-01 | 1996-01-19 | Mitsui Constr Co Ltd | Device of seeking position of laying finishing stake and method of laying finishing stake by use of the device |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02120685A (en) * | 1988-10-28 | 1990-05-08 | Asanumagumi:Kk | Automatic surveying apparatus |
JPH0363310A (en) * | 1989-07-31 | 1991-03-19 | Taisei Corp | Overall management method for construction work |
-
1992
- 1992-03-27 JP JP4071607A patent/JPH05280026A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02120685A (en) * | 1988-10-28 | 1990-05-08 | Asanumagumi:Kk | Automatic surveying apparatus |
JPH0363310A (en) * | 1989-07-31 | 1991-03-19 | Taisei Corp | Overall management method for construction work |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0814900A (en) * | 1994-07-01 | 1996-01-19 | Mitsui Constr Co Ltd | Device of seeking position of laying finishing stake and method of laying finishing stake by use of the device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5996702A (en) | System for monitoring movement of a vehicle tool | |
US6749029B2 (en) | Automated bore planning method and apparatus for horizontal directional drilling | |
US6437726B1 (en) | Method and apparatus for determining the location of underground objects during a digging operation | |
KR100806258B1 (en) | Control system and the control method to control measuring tunnel internal over break and under break by real-time | |
JP2000155855A (en) | Operation support information system using sense of virtual reality | |
KR101766846B1 (en) | Guide and Control System for Excavating Work | |
US5864060A (en) | Method for monitoring the work cycle of mobile machinery during material removal | |
JP4450352B2 (en) | Drilling management program and drilling management device | |
JP2019158637A (en) | Tunnel construction management system and determination method | |
KR101629716B1 (en) | Coordinate Measuring System for Excavating Work and Method Thereof | |
WO2007069993A1 (en) | Drill rig system | |
JP2008298433A (en) | Prediction method for tunnel final displacement | |
JPH05280026A (en) | Management system for excavation of slope surface and management method thereof | |
JP3482623B2 (en) | Shield machine | |
JP4708558B2 (en) | Position guidance device | |
JP2590014B2 (en) | Survey method for cross section marking of tunnel | |
JPH05239816A (en) | Excavating method for folded slope face | |
JP2873397B2 (en) | Land Survey System | |
JPH0566130A (en) | Automatic searching device for excavator | |
JPH0577343U (en) | Drilling rig | |
JPH1144529A (en) | Method and system for measuring thickness of sprayed concrete | |
JP4460123B2 (en) | Position guidance device for slope formation | |
EP4265880A1 (en) | Drilling sequence data generation device, drilling sequence data generation method, and program | |
KR20030096702A (en) | Methods to measure drilling path and drilling angle of tunnel | |
KR102193830B1 (en) | Apparatus and method for predicting front geological features based on indicatingtendency to change according to measuring data for a blind end in a tunnel |