JPH05280013A - Process for forming arch concrete with use of arch-like form timberwork - Google Patents
Process for forming arch concrete with use of arch-like form timberworkInfo
- Publication number
- JPH05280013A JPH05280013A JP10371792A JP10371792A JPH05280013A JP H05280013 A JPH05280013 A JP H05280013A JP 10371792 A JP10371792 A JP 10371792A JP 10371792 A JP10371792 A JP 10371792A JP H05280013 A JPH05280013 A JP H05280013A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- arch
- trusses
- seismic
- section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、アーチ橋等におけるア
ーチコンクリートの施工を、アーチ状型枠支保工を用い
て行う施工法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for performing arch concrete construction on arch bridges and the like by using arch form supports.
【0002】[0002]
【従来の技術】アーチ橋等のアーチコンクリート(アー
チリブ)の施工には、従来、片持張出工法、セントル型
枠支保工、支柱式支保工によるなど各種の方法がある
が、近年は本発明者により開発されたアーチ状型枠支保
工による施工が盛んになってきた。特に、長大なスパン
や扁平なアーチコンクリートの施工には、特開平2−2
40310号、同240311号公報等に記載の支保工
によるものがより効果をあげている。2. Description of the Related Art Conventionally, there are various methods for constructing arch concrete (arch ribs) for arch bridges, etc., such as cantilever projecting method, center form supporting method, and strut type supporting method. Construction by arch-shaped frame support work developed by the workers has become popular. In particular, for the construction of long spans and flat arch concrete, Japanese Patent Application Laid-Open No. 2-2
The effect by the support work described in No. 40310 and No. 240311 is more effective.
【0003】この支保工は、図1,図2に示すように、
アーチコンクリートのスパンを一例として4分割以上に
分割した長さの分割トラス3を互にピン結合4,4して
形成したアーチ状構体aを図3に示すように、施工する
アーチコンクリートCの奥行き方向に併列し、互いに連
結材8,8と斜材9,9により結合し、脚部構造物1,
1に結合5,5するとともに、分割トラス3,3の結合
部を地盤Bに立設した支柱6によって支持した構造のも
のである。As shown in FIGS. 1 and 2, this support work is
As shown in FIG. 3, the depth of the arch concrete C to be constructed is as shown in FIG. Parallel to each other, and are connected to each other by connecting members 8 and 8 and diagonal members 9 and 9.
In this structure, the connecting portions of the divided trusses 3 and 3 are supported by the pillars 6 standing on the ground B as well as being coupled to the first and the fifth.
【0004】それで、アーチコンクリートCの施工は、
上記支保工A上に設置した型枠7上にコンクリートを打
設して行うのであるが、このコンクリートはスパン全長
を同時に打設することは物理的にできないので、図1に
示すように、例えば、コンクリートを一度に打設できる
範囲の区間C1〜C5を設定し、分割打設することになるの
であるが、この分割された区間をどのような順序で打ち
進めるかがまず問題となる。Therefore, the construction of arch concrete C is
This is done by placing concrete on the formwork 7 installed on the support A. However, since it is physically impossible to place the entire span of this concrete at the same time, as shown in FIG. , It is necessary to set the sections C 1 to C 5 within the range where concrete can be poured at one time and to place them in a divided manner. The first problem is how to order these divided sections. ..
【0005】アーチ形コンクリートの打設順序として施
工性のみを考慮して決めるとすれば、両下部から順次上
方に向かって打ち進めるのがよいに決まっている。すな
わち、図1においてまず、C5,C5次にC1,C1そしてC2,
C2,C3,C3最後にC4を打設する順序である。If the construction order of the arched concrete is determined only by considering the workability, it is decided that the arching concrete should be sequentially driven upward from both lower portions. That is, in FIG. 1, first, C 5 , C 5 and then C 1 , C 1 and C 2 ,
The C 2, C 3, C 3 last C 4 is the order of pouring.
【0006】しかしながら、初回打設のC5,C5コンクリ
ートが硬化したあとの他の区間のコンクリート打ちによ
る支保工の変形は、既に硬化している最下部コンクリー
トC5,C5に次々とモーメントを発生させ、すべてのコン
クリートが打設し終わる時には非常に大きいモーメント
が生じコンクリートが破壊することがある。従って一般
に最下部コンクリートは最終打設としなければならな
い。すなわち、初回の打設はC5,C5を飛ばして打ち始め
なければならないのである。そのあとは最後迄順次上方
に向かって打ち進めていけるかといえば必ずしもそうは
いかず、支柱上部付近の硬化したコンクリートにも許容
値をこえるモーメントが生ずることがある。However, the deformation of the support work due to the concrete pouring of the other section after the hardening of the C 5 and C 5 concrete at the first time of placement causes the moments to the already hardened bottom concretes C 5 and C 5 one after another. And when all the concrete has been cast, a very large moment may occur and the concrete may be destroyed. Therefore, in general, the bottom concrete must be the final casting. In other words, the pouring of the first is not to be started out by skipping the C 5, C 5. After that, it may not always be possible to drive upward until the end, and a moment exceeding the allowable value may occur in the hardened concrete near the upper part of the column.
【0007】従って、支柱上部付近も最後打ちとしなけ
ればならない区間となることがある。この場合の打設順
序は第2図に示す様にC1,C1,C2,C2,C3,C3と打設
し、次に飛びこされたC4,C4を詰め最後にC5,C5を打っ
て終わることになる。Therefore, the area near the upper part of the column may also be the last section to be hit. The pouring order when is Da設and C 1, C 1, C 2 , C 2, C 3, C 3 as shown in FIG. 2, then jump strained the C 4, finally stuffed C 4 It ends by hitting C 5 and C 5 .
【0008】[0008]
【発明が解決しようとする課題】上記のように、アーチ
コンクリートの打設では、区分毎のコンクリート打設を
繰返すばかりでなく、飛び飛びに打設するため、その都
度仕切り型枠の設置、撤去を行う必要があることから、
コンクリート打ちの期間が長期にわたることになる。そ
うした場合、地震の多いわが国では、施工中に地震に見
舞われ、支保工が著しく変形したり破壊したりすること
も想定される。As described above, in pouring arch concrete, not only the concrete pouring for each section is repeated, but also the pouring is done in a scattered manner. Therefore, the partition formwork must be installed and removed each time. From what you need to do
The concrete pouring period will be long. In such a case, in Japan, where there are many earthquakes, it is expected that the supports will be significantly deformed or destroyed during the construction.
【0009】アーチ支保工Aが危険となる地震荷重と
は、支保工Aの巾方向(橋軸直角方向)の水平荷重であ
り、それ以外の荷重は問題でないことがわかっている。
地震による水平荷重は物体の重量に地震係数(0、1 とか
0、2 )を乗じた値であるが、支保工Aの上に飛び打ちさ
れた状態のコンクリートが載っている場合、そのコンク
リートの地震による水平荷重のすべては支保工で支えて
やらなければならない。It is known that the seismic load at which the arch support A is dangerous is a horizontal load in the width direction of the support A (direction perpendicular to the bridge axis), and other loads are not a problem.
The horizontal load due to an earthquake depends on the seismic coefficient (0, 1
It is a value obtained by multiplying 0, 2), but if concrete that is in a struck state is placed on support work A, all horizontal loads due to the earthquake of that concrete must be supported by support work. .
【0010】この水平荷重の小さいものは支保工で支え
ることにしてもそれ程のコストはかからないのだが、最
大の荷重となると支保工の補強に非常に高価な費用を要
することになる。最大水平力は最終打設とするアーチ両
最下端部C5,C5を除いたコンクリートのすべてを打ち終
わった時である。この時、アーチコンクリートの全重量
の殆どを対象とした水平荷重が支保工の巾方向にかかる
ことが想定され、この荷重に耐えられる様に支保工を補
強するとなると非常に高価なものとなってしまう。ま
た、支柱上部をあと打ちにする場合も同様に高価な補強
が必要となる。Even if a small horizontal load is supported by the supporting work, it does not cost much, but at the maximum load, the supporting work requires a very expensive cost to reinforce the supporting work. The maximum horizontal force is when all of the concrete except for the bottom ends C 5 and C 5 of both arches, which is the final placement, is finished. At this time, it is assumed that a horizontal load for most of the total weight of arch concrete will be applied in the width direction of the support work, and it will be very expensive to reinforce the support work to withstand this load. End up. Also, when the upper part of the support post is post-cast, similarly expensive reinforcement is required.
【0011】このようなわけで、モーメントの発生をお
さえるため、飛び打ちとなる場合のアーチ支保工の安価
な地震対策が求められることになってきた。For this reason, in order to suppress the generation of moments, it has been required to provide an inexpensive earthquake countermeasure for arch support work in the case of jumping.
【0012】本発明は上記の事情にかんがみなされたも
ので、コンクリートの地震による巾方向の水平荷重を支
保工で受けさせるのではなく、硬化したコンクリート自
身でこれを受けさせるという思想に基づいて問題の解決
を図ろうとするものである。The present invention has been made in view of the above circumstances, and has a problem based on the idea that the horizontal load in the width direction due to the earthquake of concrete is not received by the support work but is received by the hardened concrete itself. It is intended to solve the problem.
【0013】[0013]
【課題を解決するための手段】本発明は、アーチコンク
リートが両最下端部C5,C5から上方に向かって連続して
打設され、それらが硬化すればアーチコンクリートは脚
部構造物1,1に完全に結合された強固な片持梁を構成
していることになるので、硬化したコンクリートの地震
による巾方向の水平荷重はすべてこの片持梁で充分耐え
られる。本発明は最下端部を飛ばしてその上のC1,C1か
らコンクリートを打ち上げて行く場合、最下端部C5,C5
区間に地震に対する所要の支持強さをもつ構造体をコン
クリート片持梁の一部代用部材として配設し、最終打設
となるこの不連続部を埋めて連続した片持梁を形成さ
せ、地震荷重をこの片持梁で支持し、支保工に与える荷
重を著しく減らそうとするものである。また、支柱上部
の最後打設とする区間についても同様の手段を用いて解
決するものである。According to the present invention, arch concrete is continuously cast upward from both lowermost end portions C 5 and C 5 , and when they are hardened, the arch concrete becomes a leg structure 1. Since it constitutes a strong cantilever beam that is completely connected to 1, the horizontal load in the width direction due to the earthquake of hardened concrete can be sufficiently endured by this cantilever beam. In the present invention, when the lowermost end is skipped and concrete is launched from C 1 and C 1 above it, the lowermost end C 5 and C 5
A structure with the required bearing strength against earthquakes is arranged in a section as a part of the concrete cantilever beam substitute member, and the discontinuous part that is the final placement is filled to form a continuous cantilever beam. This cantilever is used to support the load, and the load applied to the support work is to be significantly reduced. Further, the same means is used to solve the last section of the upper part of the column.
【0014】すなわち、請求項1の施工法は、ア−チコ
ンクリ−トCのスパンを適数に分割した長さの分割トラ
スを3,3互に結合4,4して形成したアーチ状構体a
を、複数併列、結合し、各アーチ状構体aの下端を脚部
構造物1,1に結合5,5するとともに、分割トラス
3,3相互の連結部4,4を、地盤Bに立設の支柱6,
6により支持してアーチ状型枠支保工Aを架設し、上記
脚部構造物1には、アーチコンクリートCの巾方向の水
平外力に対抗する耐震構造体Dを、アーチ状型枠支保工
Aの両下端部上に突出して設け、アーチコンクリートC
の当初の打設を、支保工Aの端部にある分割トラス3上
の所要長さ区間C1,C1に、上記耐震構造体Dの先端部と
結合して行い、その後順次上方へとコンクリートを打ち
継いで行き、終わりに、当初打設した区間C1のコンクリ
ートと脚部構造物1との間C5にコンクリートを打設し
て、該コンクリート中に耐震構造体Dを埋設することを
特徴とするものである。That is, in the construction method of claim 1, an arch-shaped structure a is formed by connecting divided trusses having lengths obtained by appropriately dividing the span of the arch concrete C to 3, 3 to each other 4 and 4.
Are connected in parallel to each other, the lower ends of the arch-shaped structures a are connected to the leg structures 1, 1 and 5, and the connecting portions 4 and 4 of the divided trusses 3 and 3 are erected on the ground B. Stanchions 6,
The arch-shaped frame support A is erected by being supported by 6, and the leg structure 1 is provided with a seismic structure D that opposes the horizontal external force of the arch concrete C in the width direction. Protruding on both lower ends of the arch concrete C
The initial placement of the above is performed in the required length sections C 1 and C 1 on the divided truss 3 at the end of the support A by connecting it with the tip of the seismic resistant structure D, and then sequentially upward. To pour concrete, and at the end, pour concrete into C 5 between the concrete in the originally placed section C 1 and the leg structure 1, and bury the earthquake-resistant structure D in the concrete. It is characterized by.
【0015】また、請求項2の施工法は、アーチコンク
リートCのスパンを適数に分割した長さの分割トラス
3,3を互に結合4,4して形成したアーチ状構体a
を、複数併列、結合し、各アーチ状構体aの下端を脚部
構造物1,1に結合5,5するとともに、分割トラス
3,3相互の連結部4,4を、地盤Bに立設の支柱6,
6により支持してアーチ状型枠支保工Aを架設し、上記
脚部構造物1には、アーチコンクリートCの巾方向の水
平外力に対抗する耐震構造体Dを、アーチ状型枠支保工
Aの両下端部上に突出して設け、アーチコンクリートC
の当初の打設を、支保工Aの端部にある分割トラス3上
の所要長さ区間C1,C1に、上記耐震構造体Dの先端部と
結合して行なうとともに、該打設コンクリートのC1先端
部に、上記同様の耐震構造体Dを、該打設コンクリート
C1に近い支柱6上を越えて突設し、ついで、上記分割ト
ラス3に結合した分割トラス3上の所要長さ区間C2に、
該耐震構造体Dの先端部と結合してコンクリートC3を打
設し、その後順次上方へとコンクリートを打ち継いで行
き、終わりに、当初打設した区間C1のコンクリートと脚
部構造物1との間C5及びその後打設した区間コンクリー
トの相互間C4にコンクリートを打設して、該コンクリー
ト中に耐震構造体Dを埋設することを特徴とするもので
ある。Further, in the construction method of claim 2, the arched structure a is formed by connecting the divided trusses 3 and 3 of the length obtained by appropriately dividing the span of the arch concrete C to each other by connecting them 4 and 4.
Are connected in parallel to each other, the lower ends of the arch-shaped structures a are connected to the leg structures 1, 1 and 5, and the connecting portions 4 and 4 of the divided trusses 3 and 3 are erected on the ground B. Stanchions 6,
The arch-shaped frame support A is erected by being supported by 6, and the leg structure 1 is provided with a seismic structure D that opposes the horizontal external force of the arch concrete C in the width direction. Protruding on both lower ends of the arch concrete C
The initial pouring of the concrete is carried out at the required length sections C 1 and C 1 on the divided truss 3 at the end of the support work A by connecting it to the tip of the seismic resistant structure D, and At the tip of C 1 of the
Projected over the pillar 6 close to C 1 , and then in the required length section C 2 on the split truss 3 connected to the split truss 3,
Concrete C 3 is placed in connection with the tip of the seismic resistant structure D, and then concrete is successively spliced upward, and at the end, concrete and leg structure 1 in the originally placed section C 1 are placed. The concrete is characterized in that concrete is poured between C 5 and C 5 and between the section concretes that are subsequently placed C 4 and the seismic structure D is embedded in the concrete.
【0016】[0016]
【作用】本発明の施工法は上記のように構成されてお
り、打設された区間のコンクリートは、耐震構造体に一
体的に結合され、それによって、打設され、硬化したコ
ンクリート部分は、施工途時においても常に脚部構造物
とアーチの巾方向に強固に結合された構造体を保つこと
になり、したがって、アーチコンクリートの施工途時に
おいて地震による大きい水平力を受けた場合にも、硬化
したアーチコンクリートと耐震構造体が一体となってそ
の水平力に抵抗することになるから、アーチコンクリー
トや支保工の変形、破壊防止に寄与することになる。The construction method of the present invention is configured as described above, and the concrete in the cast section is integrally connected to the earthquake-resistant structure, whereby the cast and hardened concrete portion is Even during construction, the leg structure and the structure that is strongly connected in the width direction of the arch will always be maintained, so even when a large horizontal force due to an earthquake is applied during the construction of arch concrete, Since the hardened arch concrete and the earthquake-resistant structure are integrated and resist the horizontal force, it contributes to the deformation and destruction prevention of the arch concrete and the supporting work.
【0017】[0017]
【実施例】以下、本発明の実施例について図面を参照し
て説明する。図1はアーチ状型枠支保工を使用してアー
チコンクリートを施設した状態を示したもので、対向し
た橋台等の脚部構造物1,1に取付台2,2を介してア
ーチ状型枠支保工(以下支保工という)Aの下端をピン
結合5,5して架構し、その支保工Aの上面に型枠7を
設置し、その上にアーチコンクリートCが形成されてい
る。Embodiments of the present invention will be described below with reference to the drawings. Fig. 1 shows a state in which arch concrete is installed by using arch-shaped frame supports. The arch-shaped form is mounted on the leg structures 1, 1 facing each other such as abutments and mounting bases 2, 2. The lower end of a supporting work (hereinafter referred to as a supporting work) A is framed by connecting pins 5 and 5, and a frame 7 is installed on the upper surface of the supporting work A, on which an arch concrete C is formed.
【0018】支保工Aは、アーチコンクリートCのスパ
ンを適数に分割(図1の実施例で4分割)した長さの分
割トラス3,3の所要数(4個)を互いに端部において
ピン結合4して形成したアーチ状構体の複数を、図3に
示すように併列して、連結材8,8と斜材9,9により
結合して形成している。そして、各アーチ状構体aの下
端を取付台2,2にピン結合するとともに、分割トラス
3,3相互のピン結合4,4した連結部を、地盤Bに立
設した支柱6,6により支持した構造となっている。The supporting work A has a required number (4 pieces) of divided trusses 3 and 3 having a length obtained by appropriately dividing the span of the arch concrete C (4 divisions in the embodiment of FIG. 1) at each end with pins. As shown in FIG. 3, a plurality of arch-shaped structures formed by combining 4 are arranged side by side and connected by connecting members 8 and 8 and diagonal members 9 and 9. Then, the lower end of each arch-shaped structure a is pin-connected to the mounting bases 2 and 2, and the connecting portions formed by the pin-connections 4 and 4 of the divided trusses 3 and 3 are supported by the columns 6 and 6 standing on the ground B. It has a structure.
【0019】また、各脚部構造物1には、図4、図5に
示すように、耐震構造体Dが設けられる。この耐震構造
体Dは、H型鋼等の耐力杆材14,14をアーチコンクリー
トCの巾方向に間隔をおいて併列し、それらの先端を連
結杆15により結合するとともに、筋違い16,16により結
合し、各耐力杆材14の基端部を、脚部構造物1の施工の
際そのコンクリート中に埋め込み、耐震構造体Dが支保
工Aの下端部上方に突出するようにして設けられる。そ
して、連結杆15には、アーチコンクリートCの当初打設
されるコンクリート中に埋め込まれて一体結合させるた
めのアンカーボルト17,17が多数突設される。Further, each leg structure 1 is provided with a seismic structure D as shown in FIGS. 4 and 5. In this seismic structure D, load bearing rods 14, 14 such as H-shaped steel are arranged side by side in the width direction of arch concrete C at intervals, and the ends thereof are joined by connecting rods 15 and by braces 16, 16. Then, the base end of each load bearing rod 14 is embedded in the concrete when the leg structure 1 is constructed, and the seismic resistant structure D is provided so as to project above the lower end of the support A. The connecting rod 15 is provided with a large number of anchor bolts 17, 17 embedded in the concrete of the arch concrete C that is initially placed so as to be integrally connected.
【0020】そして、上記支保工Aの架構後は、型枠7
上に鉄筋18,18等所要の配筋を施した後、アーチコンク
リートCのコンクリート打ちがなされる。そのコンクリ
ート打設は、コンクリートの1回の打設範囲を区間とし
て設定し、区間毎に打ち継いで行くが、図1の実施例と
図2の実施例とでは、設定した各区間の打設順序が異な
るようにしている。After the frame of the supporting work A, the form 7
After the required reinforcements such as reinforcing bars 18 and 18 have been applied to the top, arch concrete C is concreted. In the concrete pouring, the range of one pouring of concrete is set as a section, and the sections are successively spliced. However, in the embodiment of FIG. 1 and the embodiment of FIG. The order is different.
【0021】まず、図1の実施例について説明すると、
コンクリートの打設区間を、例えば図示のように、C1,
C2,……C5のように区分し、まず、脚部構造物1と所要
の間隔C5をおいたところ、すなわち、耐震構造体Dの連
結杆15から先の支保工下部の打設区間C1,C1にコンクリ
ートを打設する。それによって、アンカーボルト17,17
はそのコンクリートに埋め込まれ、区間C1のコンクリー
トと耐震構造体DとはアーチコンクリートCの巾方向に
不動に結合されることになる。なお、この場合、図示を
略したが、コンクリートの打設に必要な区切り型枠や側
部型枠、外型枠は適宜設置される。そして、その後は区
間C1,C1に続く区間C2,C3,C4と順次上方に向けてコン
クリートを打ち継いで行き、最後には鉄筋18を脚部構造
物1の軸鉄筋19と結合した後、当初区間C1,C1と脚部構
造物1との間の区間C5,C5にコンクリートを打設し、耐
震構造体Dをそのコンクリート中に埋設する。それによ
って、アーチコンクリートCの全体が形成できることに
なる。First, the embodiment of FIG. 1 will be described.
As shown in the figure, concrete placing section is C 1 ,
It is divided into C 2 , …… C 5 , and first, the leg structure 1 and the required distance C 5 are placed, that is, the lower part of the support work is placed from the connecting rod 15 of the seismic structure D ahead. Concrete is placed in sections C 1 and C 1 . Thereby, the anchor bolts 17, 17
Is embedded in the concrete, and the concrete in the section C 1 and the seismic resistant structure D are fixedly connected in the width direction of the arch concrete C. In this case, although not shown in the drawing, the separator form, the side form, and the outer form required for placing concrete are properly installed. After that, the sections C 1 , C 1 are followed by sections C 2 , C 3 , C 4 and the concrete is successively struck upward, and finally the reinforcing bar 18 is replaced with the axial reinforcing bar 19 of the leg structure 1. After joining, concrete is placed in the sections C 5 and C 5 between the initial sections C 1 and C 1 and the leg structure 1, and the seismic resistant structure D is embedded in the concrete. Thereby, the entire arch concrete C can be formed.
【0022】次に、図2の実施例について説明する。こ
の実施例の場合も、コンクリートの打設区間はさきの実
施例の場合に準じて区間を設定し、打ち継いで行くが、
当初の打設区間C1,C1と次の打設区間C2,C2との間に、
新たに区間C1,C1に近い支柱6,6の上を越える区間
C4,C4を設定する。そして、当初の区間C1,C1のコンク
リート打設に際して、その先端部に上記同様の耐震構造
体Dをその基端部に埋め込んで突設し、その先端部に結
合して次のC2,C2区間のコンクリートを打設するのであ
る。あとは、図1の実施例の場合と同様に、頂部区間C3
コンクリートを打ち継いだ後、C1とC2との間の区間C4,
C4に打設してそのコンクリート中に耐震構造体Dを埋設
する。そして最後に、図1の実施例と同様に、C1区間の
コンクリートと脚部構造物1との間の区間C5,C5にコン
クリートを埋設し、そのコンクリート中に耐震構造物D
を埋設するのである。Next, the embodiment shown in FIG. 2 will be described. Also in the case of this embodiment, the section for placing concrete is set in accordance with the case of the above example, and the sections are spliced.
Between the first placement section C 1 and C 1 and the next placement section C 2 and C 2 ,
New section C 1 , a section over the columns 6 and 6 near C 1
Setting the C 4, C 4. Then, at the time of placing concrete in the initial sections C 1 and C 1 , a seismic resistant structure D similar to the above is embedded in the base end portion at the tip portion thereof to project, and is connected to the tip end portion of the next C 2 it is to concrete is a C 2 sections. After that, as in the case of the embodiment of FIG. 1, the top section C 3
After piling concrete, section C 4 , between C 1 and C 2 ,
And Da設to C 4 embedding the seismic structure D in its concrete. Finally, similarly to the embodiment of FIG. 1, concrete is buried in the sections C 5 and C 5 between the concrete in the section C 1 and the leg structure 1, and the seismic resistant structure D is placed in the concrete.
Is buried.
【0023】耐震構造体Dは、図4、図5の実施例のも
のに限定されることはない。要は、アーチコンクリート
Cの巾方向の大きな水平力に対抗できる強度と剛性の高
い構造とすることである。したがって、図4の構造以外
に各種のものが考えられる。例えば筋違い16,16に代え
て引張線材を斜めに張ることもでき、また、耐力杆材1
4,14と斜めに組合せて構成することもできる。さら
に、耐震構造DとコンクリートCとの結合手段について
も、上記の構造のほか各種の手段を用いることができ
る。そして、それらによる耐震構造体Dは、図6に示す
ように、コンクリートの厚さ方向に複数配設することも
できる。さらに、図7に示すように、鋼板を組合せ溶接
して中空のボックス20を形成し、それを脚部構造物1に
埋込む脚杆21,21と結合した構造のものとすることもで
きる。The seismic resistant structure D is not limited to that of the embodiment shown in FIGS. The point is to have a structure with high strength and rigidity that can withstand the large horizontal force of the arch concrete C in the width direction. Therefore, various structures other than the structure shown in FIG. 4 are possible. For example, instead of the braces 16, 16, tension wire can be stretched diagonally, and the load-bearing rod 1
It can also be constructed by diagonally combining with 4 and 14. Further, as the means for connecting the seismic resistant structure D and the concrete C, various means other than the above structure can be used. Then, as shown in FIG. 6, a plurality of seismic resistant structures D can be arranged in the thickness direction of concrete. Further, as shown in FIG. 7, steel plates may be combined and welded to form a hollow box 20, and the hollow box 20 may be combined with the leg rods 21 and 21 embedded in the leg structure 1.
【0024】[0024]
【発明の効果】以上説明したように、本発明の施工法
は、分割トラスの数個を結合し、その各結合部を地盤に
立設の支柱で支持した支保工を使用するとともに、脚部
構造物に耐震構造体を突設し、その先端部に当初打設区
間のコンクリートを結合した後、順次打設区間毎のコン
クリートを打ち継いで行くようにしたので、コンクリー
トの打設途中において地震が発生し、橋軸直角方向の大
きな水平力が働いたとしても、打設され硬化したコンク
リートは耐震構造体を介して脚部構造物と一体化してい
るため耐震力に優れ、また、支保工への過大な水平力の
作用するのを抑制することができ、地震による変形、破
壊を防止できるので施工中の安定性の向上に優れた効果
を奏するものである。As described above, according to the construction method of the present invention, a plurality of divided trusses are connected to each other, and each supporting portion is supported by the upright pillars on the ground. Since an earthquake-resistant structure was projected on the structure and the concrete in the initial placement section was joined to the tip of the structure, the concrete in each placement section was successively spliced, so an earthquake occurred during the concrete placement. Even if a large horizontal force acts in the direction orthogonal to the bridge axis, the cast and hardened concrete is integrated with the leg structure through the earthquake-resistant structure, which is excellent in earthquake resistance and also supports It is possible to suppress the application of an excessive horizontal force to, and to prevent deformation and destruction due to an earthquake, which is an excellent effect in improving stability during construction.
【図1】本発明施工法の一実施例を示す概略正面図であ
る。FIG. 1 is a schematic front view showing an embodiment of a construction method of the present invention.
【図2】同他の実施例を示す概略正面図である。FIG. 2 is a schematic front view showing another embodiment.
【図3】本発明支保工の概略平面図である。FIG. 3 is a schematic plan view of the support work of the present invention.
【図4】本発明における耐震構造体の一実施例を示す平
面図である。FIG. 4 is a plan view showing an embodiment of the earthquake-resistant structure according to the present invention.
【図5】同正面図である。FIG. 5 is a front view of the same.
【図6】同他の実施例を示す正面図である。FIG. 6 is a front view showing another embodiment.
【図7】同さらに他の実施例を示す平面図である。FIG. 7 is a plan view showing another embodiment of the present invention.
A アーチ状型枠支保工 B 地盤 C アーチコンクリート D 耐震構造体 a アーチ状構体 C1〜C5 コンクリート打設区間 1 脚部構造物 3 分割トラス 4,5 ピン結合 6 支柱 7 型枠 14 耐力杆材 15 連結杆 16 筋違い 17 アンカーボルト 18,19 鉄筋A Arch-shaped frame support work B Ground C Arch concrete D Seismic structure a Arch-shaped structure C 1 to C 5 Concrete placing section 1 Leg structure 3 Split truss 4, 5 pin connection 6 Strut 7 Form frame 14 Bearing rod Material 15 Connecting rod 16 Streak 17 Anchor bolt 18, 19 Reinforcing bar
Claims (2)
割した長さの分割トラスを互に結合して形成したアーチ
状構体を、複数併列、結合し、各アーチ状構体の下端を
脚部構造物に結合するとともに、分割トラス相互の連結
部を、地盤に立設の支柱により支持してアーチ状型枠支
保工を架設し、上記脚部構造物には、アーチコンクリー
トの巾方向の水平外力に対抗する耐震構造体を、アーチ
状型枠支保工の両下端部上に突出して設け、アーチコン
クリートの当初の打設を、支保工の端部にある分割トラ
ス上の所要長さ区間に、上記耐震構造体の先端部と結合
して行い、その後順次上方へとコンクリートを打ち継い
で行き、最後に、当初打設した区間のコンクリートと脚
部構造物との間にコンクリートを打設して、該コンクリ
ート中に耐震構造体を埋設することを特徴とする、アー
チ状型枠支保工によるアーチコンクリートの施工法。1. A plurality of arch-shaped structures formed by mutually connecting split trusses each having a length obtained by appropriately dividing the span of arch concrete, are connected in parallel, and the lower end of each arch-shaped structure is connected to a leg structure. In addition to connecting to the trusses, the joints of the divided trusses are supported by the pillars standing upright on the ground, and the arch-shaped frame support work is erected. Anti-seismic structures are provided projecting on both lower ends of the arched formwork support, and the initial placement of arch concrete is done at the required length section on the split truss at the end of the support. Performed by connecting with the tip of the earthquake-resistant structure, then successively piling the concrete upwards, and finally, placing concrete between the concrete of the originally placed section and the leg structure, Seismic structure in the concrete A method of constructing arch concrete by arch-shaped frame support, which is characterized by burying.
割した長さの分割トラスを互に結合して形成したアーチ
状構体を、複数併列、結合し、各アーチ状構体の下端を
脚部構造物に結合するとともに、分割トラス相互の連結
部を、地盤に立設の支柱により支持してアーチ状型枠支
保工を架設し、上記脚部構造物には、アーチコンクリー
トの巾方向の水平外力に対抗する耐震構造体を、アーチ
状型枠支保工の両下端部上に突出して設け、アーチコン
クリートの当初の打設を、支保工の端部にある分割トラ
ス上の所要長さ区間に、上記耐震構造体の先端部と結合
して行うとともに、該打設コンクリートの先端部に、上
記同様の耐震構造体を、該打設コンクリートに近い支柱
上を越えて突設し、ついで、上記分割トラスに結合した
隣りの分割トラス上の所要長さ区間に、該耐震構造体の
先端部と結合してコンクリートを打設し、その後順次上
方へとコンクリートを打ち継いで行き、終わりに、当初
打設した区間のコンクリートと脚部構造物との間及びそ
の後打設した区間コンクリートの相互間にコンクリート
を打設して、該コンクリート中に耐震構造体を埋設する
ことを特徴とする、アーチ状型枠支保工によるアーチコ
ンクリートの施工法。2. A plurality of arch-shaped structures formed by mutually connecting split trusses each having a length obtained by appropriately dividing the span of arch concrete, are connected in parallel, and the lower end of each arch-shaped structure is connected to a leg structure. In addition to connecting to the trusses, the joints of the divided trusses are supported by the pillars standing upright on the ground, and the arch-shaped frame support work is erected, and the leg structure has a horizontal external force in the width direction of the arch concrete. Anti-seismic structures are provided projecting on both lower ends of the arched formwork support, and the initial placement of arch concrete is done at the required length section on the split truss at the end of the support. This is done by combining with the tip of the seismic resistant structure, and at the tip of the cast concrete, a seismic resistant structure similar to the above is projected over a pillar close to the cast concrete, and then the split truss. On the adjacent split truss connected to In the required length section, concrete is placed in combination with the tip of the seismic resistant structure, and then concrete is successively sewn upward, and at the end, the concrete and leg structure of the section originally placed A method for constructing arch concrete by arch-shaped frame support construction, characterized in that concrete is cast between the concrete and the section concrete that is placed thereafter, and the seismic structure is embedded in the concrete. ..
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP10371792A JPH05280013A (en) | 1992-03-30 | 1992-03-30 | Process for forming arch concrete with use of arch-like form timberwork |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP10371792A JPH05280013A (en) | 1992-03-30 | 1992-03-30 | Process for forming arch concrete with use of arch-like form timberwork |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH05280013A true JPH05280013A (en) | 1993-10-26 |
Family
ID=14361453
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP10371792A Pending JPH05280013A (en) | 1992-03-30 | 1992-03-30 | Process for forming arch concrete with use of arch-like form timberwork |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH05280013A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104099871A (en) * | 2014-06-19 | 2014-10-15 | 中铁十一局集团第二工程有限公司 | Arching structure of high large-span bridge bailey beams and construction method thereof |
CN105033555A (en) * | 2015-08-31 | 2015-11-11 | 南车石家庄车辆有限公司 | Dynamic compactor moving arm combination tool |
-
1992
- 1992-03-30 JP JP10371792A patent/JPH05280013A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104099871A (en) * | 2014-06-19 | 2014-10-15 | 中铁十一局集团第二工程有限公司 | Arching structure of high large-span bridge bailey beams and construction method thereof |
CN105033555A (en) * | 2015-08-31 | 2015-11-11 | 南车石家庄车辆有限公司 | Dynamic compactor moving arm combination tool |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS6114287B2 (en) | ||
JP4691690B2 (en) | Joint structure and joining method of pedestal | |
JP3700102B2 (en) | Building basic structure | |
JP3690437B2 (en) | Seismic reinforcement structure for existing buildings | |
JP2531038B2 (en) | Pillar PC structure | |
JPH05280013A (en) | Process for forming arch concrete with use of arch-like form timberwork | |
JP2001172913A (en) | Elevated bridge and its construction method | |
JP2841252B2 (en) | Construction method of arch concrete by arch form support. | |
JP4364367B2 (en) | Half precast beam | |
JPH06228915A (en) | Strut of elevated bridge, etc., and construction method thereof | |
JPH01290806A (en) | Construction method for bridge | |
JPH0492007A (en) | Composite pier | |
JPH0579017A (en) | Composite bridge pier | |
JP3908816B2 (en) | Construction method of suspended floor slab bridge | |
JP2841253B2 (en) | Construction method of arch concrete by arch form support. | |
JP2000160687A (en) | Construction method for composite structure and precast concrete column | |
JPH0959933A (en) | Filled and coated steel pipe concrete structure and construction method | |
JP2600531B2 (en) | Foundation structure for steel column and its construction method | |
JP6649069B2 (en) | Seismic reinforcement structure | |
KR102515783B1 (en) | Unsupported formwork construction method using socket member | |
KR200265456Y1 (en) | Finger joint structure of top plate on bridge | |
JPS6198864A (en) | Mold frame apparatus for arch concrete | |
JP4347195B2 (en) | Construction method of viaduct foundation using steel pipe column joint element | |
AU746805B2 (en) | A structural element | |
JPH11181807A (en) | Construction method for underground story |