JPH052773B2 - - Google Patents
Info
- Publication number
- JPH052773B2 JPH052773B2 JP20715289A JP20715289A JPH052773B2 JP H052773 B2 JPH052773 B2 JP H052773B2 JP 20715289 A JP20715289 A JP 20715289A JP 20715289 A JP20715289 A JP 20715289A JP H052773 B2 JPH052773 B2 JP H052773B2
- Authority
- JP
- Japan
- Prior art keywords
- slope
- retaining wall
- section
- constructed
- intermediate foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 claims description 13
- 239000010959 steel Substances 0.000 claims description 13
- 238000010276 construction Methods 0.000 claims description 11
- 239000004567 concrete Substances 0.000 claims description 7
- 239000011178 precast concrete Substances 0.000 claims description 7
- 239000000463 material Substances 0.000 description 10
- 239000011083 cement mortar Substances 0.000 description 4
- 238000000034 method Methods 0.000 description 4
- 239000004576 sand Substances 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 239000004568 cement Substances 0.000 description 1
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Piles And Underground Anchors (AREA)
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明は、盛土や傾斜面を掘削した法面にプレ
キヤストコンクリート製のブロツクを積み上げて
擁壁を構築する法面擁壁構築方法に関する。DETAILED DESCRIPTION OF THE INVENTION (Industrial Application Field) The present invention relates to a slope retaining wall construction method in which a retaining wall is constructed by piling up precast concrete blocks on a slope obtained by excavating an embankment or a slope.
(従来の技術)
従来、山岳道路のように傾斜地の中腹を段状に
掘削して道路を構築したり、既に構築されている
道路の山側の原傾斜面を掘削して拡幅する場合等
において、原傾斜面を掘削した法面の崩落を防止
するため、該法面を覆う擁壁が構築されている。(Prior art) Conventionally, when constructing a road such as a mountain road by excavating the middle of a slope in steps, or when widening an already constructed road by excavating the original slope on the mountain side, etc. In order to prevent slopes created by excavating original slopes from collapsing, retaining walls are constructed to cover the slopes.
この種の従来の擁壁には、コンクリートブロツ
クを格子状に組み立てた法枠や、重力式のコンク
リートブロツクを積み上げたものがあり、近年に
おいては縁化を図るため、法枠ブロツク内に植生
を施すものが開発されている。 Conventional retaining walls of this type include a framework made of concrete blocks assembled in a lattice pattern, and a structure made by stacking gravity-type concrete blocks. A method has been developed to do so.
また、急傾斜の法面を安全に覆い崩落を防止せ
んとするために擁壁の構築に先立つて地中アンカ
ーを構築し、これに擁壁を支持させる工法が開発
されている。 In addition, in order to safely cover steep slopes and prevent collapse, a construction method has been developed in which underground anchors are constructed prior to constructing a retaining wall and the retaining wall is supported by these anchors.
(発明が解決しようとする問題点)
このような従来の擁壁の構築は、原傾斜面を掘
削して所定の傾斜の法面を形成の後、その法面の
下側から順次積み上げるものであるため、法面形
成の際に地盤が弱い場合には、地滑りが生じ、一
定以上の傾斜にすることができない。(Problems to be Solved by the Invention) In conventional construction of retaining walls, the original slope is excavated to form a slope with a predetermined slope, and then the walls are built up sequentially from the bottom of the slope. Therefore, if the ground is weak when forming a slope, landslides will occur and it will not be possible to make the slope higher than a certain level.
このため従来は、法面の途中に水平部分を設け
て法面を階段状に複数設ける必要が生じ、このた
め被覆面積が大きくなるという問題があつた。 For this reason, in the past, it was necessary to provide a plurality of slopes in a step-like manner by providing a horizontal portion in the middle of the slope, which caused the problem that the covered area became large.
本発明は上述の如き従来の問題にかんがみ、急
傾斜で長い一面の法面擁壁を安全に構築し得る法
面擁壁構築方法の提供を目的としてなされたもの
である。 The present invention has been made in view of the above-mentioned conventional problems, and aims to provide a method for constructing a slope retaining wall that can safely construct a steeply sloped and long slope retaining wall.
(課題を解決するための手段)
上述の従来の問題を解決し、所期の目的を達成
するための本発明の法面擁壁構築方法の特徴は、
原傾斜面を必要角度の法面に掘削し、該法面に沿
つてプレキヤストコンクリート製の擁壁用ブロツ
クを積み上げて、該法面の表面を被覆する法面擁
壁構築方法において、擁壁を構築しようとする傾
斜面を一定高さづつに区分し、その上方側の一区
分を掘削して所定傾斜の法面を形成し、該区分の
下縁部に一定間隔毎に地中アンカーを構築し、該
地中アンカーに支持させて水平方向の桁状をした
中間基礎を設け、該中間基礎上に順次擁壁ブロツ
クを積み上げて一区分の擁壁を構築し、次いで前
記中間基礎下の次の一区分の傾斜面を掘削して上
述と同様に順次一区分づつ下方に向けて擁壁を構
築して上下に連続した一面の擁壁となすことにあ
る。(Means for Solving the Problems) The features of the slope retaining wall construction method of the present invention for solving the above-mentioned conventional problems and achieving the intended purpose are as follows:
In a slope retaining wall construction method, a retaining wall is constructed by excavating an original slope into a slope with a required angle, piling up precast concrete retaining wall blocks along the slope, and covering the surface of the slope. Divide the slope on which you are going to construct a slope into sections of a certain height, excavate one section on the upper side to form a slope of a specified slope, and place underground anchors at regular intervals on the lower edge of the section. A horizontal girder-shaped intermediate foundation is supported by the underground anchors, and retaining wall blocks are stacked one after another on the intermediate foundation to construct one section of retaining wall. The next step is to excavate the slope of the slope and construct a retaining wall downward one section at a time in the same manner as described above, thereby creating a retaining wall that is continuous vertically.
また上記構築法においては、順次積み上げられ
水平方向に隣り合う擁壁用ブロツク間に上下に連
続した場所打ちコンクリート製の柱状部を形成
し、該柱状部と中間基礎とに連続させてPC鋼材
を挿通し、プレストレスを付与することとしても
よい。 In addition, in the above construction method, vertically continuous cast-in-place concrete pillars are formed between horizontally adjacent retaining wall blocks that are stacked one after another, and prestressed steel is installed in continuity between the pillars and the intermediate foundation. It may be inserted and prestressed.
(作用)
本発明の法面擁壁構築方法では、安定状態にあ
る原傾斜面の低い位置を掘削することなく、上部
より一区画分づつ擁壁が構築され、しかも各区画
の擁壁はそれぞれ地中アンカーにて地盤に定着さ
せた桁状の中間基礎に支持されるため、擁壁を構
築した部分は安定状態となり、地滑りの心配がな
い。このようにして上部より一区画づつ掘削し、
安定化させつつ下部に到るため、急傾斜であつて
も安全に一枚の連続した擁壁が構築できる。(Function) In the slope retaining wall construction method of the present invention, retaining walls are constructed one section at a time from the top without excavating the lower parts of the original slope in a stable state, and each section's retaining wall is Because it is supported by a girder-shaped intermediate foundation anchored to the ground with underground anchors, the area where the retaining wall has been constructed is stable and there is no risk of landslides. In this way, excavate one section at a time from the top,
Since it reaches the bottom while being stabilized, a continuous retaining wall can be safely constructed even on steep slopes.
また、水平方向に隣り合う擁壁ブロツク間に上
下に連続する柱状部を形成し、これに桁状部に連
続されてプレストレスを付与することにより、柱
状部と中間基礎とによつて構成される格子状の枠
が地中アンカーによつて地盤に定着されることと
なり、安定度が増大される。 In addition, by forming vertically continuous columnar parts between horizontally adjacent retaining wall blocks, and applying prestress to this column by continuing with the girder parts, the structure is constructed by the columnar parts and the intermediate foundation. The grid-like frame is anchored to the ground by underground anchors, increasing stability.
(実施例) 次に本発明の実施例を図面について説明する。(Example) Next, embodiments of the present invention will be described with reference to the drawings.
まず、設計段階において、第1図に示すように
原傾斜面1を掘削して形成する法面2を設定し、
その法面を上下に複数の区画H1〜H3に区分す
る。このときの法面2の傾斜及び一区画分の長さ
は、地山の安定度を考慮して決定する。 First, at the design stage, as shown in Fig. 1, the slope 2 to be formed by excavating the original slope 1 is set,
The slope is divided vertically into a plurality of sections H1 to H3 . The inclination of the slope 2 and the length of one section at this time are determined in consideration of the stability of the ground.
次いで第2図に示すように法面2の上方より最
上部の第1区画分H1分だけ原傾斜面1を掘削し、
予め定められた所定傾斜の法面2を形成する。そ
して、その法面2の下部に地中に向けてアンカー
孔3を穿ち、セメントペーストを注入してアンカ
ーコンクリート4を打設するとともに、その中に
PC鋼材からなるアンカー引張材5を挿入して地
中アンカー6を構築する。次いでこの地中アンカ
ー6のアンカー引張材5を貫通させて場所打コン
クリートもしくはプレキヤストコンクリートによ
り、水平方向に延びる桁状をした第一中間基礎7
aを設置する。 Next, as shown in Fig. 2, the original slope 1 is excavated from the uppermost part of the slope 2 by the first section H 1 minute.
A slope 2 having a predetermined slope is formed. Then, an anchor hole 3 is drilled into the ground at the bottom of the slope 2, cement paste is injected, and anchor concrete 4 is placed in the hole.
An underground anchor 6 is constructed by inserting an anchor tension member 5 made of PC steel. Next, the anchor tensile member 5 of this underground anchor 6 is penetrated and cast-in-place concrete or precast concrete is used to construct a first intermediate foundation 7 in the shape of a girder extending in the horizontal direction.
Install a.
次いで、この第一中間基礎7aにアンボンドケ
ーブルからなるPC鋼材8の下端を貫通させて、
縦向きに複数本配置する。このPC鋼材8は、一
筒所に区画H1,H2……の数に応じた本数だけ挿
通しておき、その内の一本を第一中間基礎7aに
定着しておく。 Next, the lower end of the PC steel material 8 made of an unbonded cable is penetrated through this first intermediate foundation 7a,
Arrange multiple pieces vertically. This PC steel material 8 is inserted in a number corresponding to the number of sections H 1 , H 2 . . . in one tube, and one of them is fixed to the first intermediate foundation 7a.
次いで第3図に示すように第一中間基礎7a上
に支持させてプレスキヤストコンクリート製の擁
壁ブロツク9,9…を順次法面に沿つて積み上げ
る。この擁壁用ブロツク9は、第8図〜第11図
に示すように両側壁10,10及び後壁11をコ
状に配置し、底部に前方斜め上向きの底板13が
一体に設けられ、前面及び上面が開放した土受け
空間を有しており、後壁11及び底板13に窓穴
14,15が開口されている。また、両側壁1
0,10の外側には第11図に示すように互いに
隣り合せに接合されることにより背面に蟻溝状の
凹溝17が縦向きに形成される半割溝状部16,
16が形成されている。そして、第一中間基礎7
a上への積み上げには各PC鋼材8が凹溝17内
に挿通されるように配置する。 Next, as shown in FIG. 3, retaining wall blocks 9, 9, . . . made of precast concrete are successively stacked along the slope while being supported on the first intermediate foundation 7a. This retaining wall block 9 has side walls 10, 10 and a rear wall 11 arranged in a U-shape as shown in FIGS. It has a soil receiving space with an open upper surface, and window holes 14 and 15 are opened in the rear wall 11 and the bottom plate 13. Also, both side walls 1
As shown in FIG. 11, on the outside of 0 and 10, there are half groove-like portions 16, which are joined side by side to form a vertically dovetail groove-like groove 17 on the back surface.
16 are formed. And the first intermediate foundation 7
When stacking on top a, each PC steel material 8 is arranged so as to be inserted into the groove 17.
このようにして各擁壁用ブロツク9を第1区画
H1分だけ積み上げた後、その最上部にプレキヤ
ストコンクリート製の天端板18を載せ、これに
各PC鋼材8を貫通させて真すぐに伸ばし、凹溝
17内にセメントモルタル19(第11図に示
す)を注入し、その固化を待つて前述した第一中
間基礎7aに下端を定着したPC鋼材8を天端板
18上から緊張し、プレストレスを付与する。な
お、他のPC鋼材8は下端側を下方に延長させて
おく、あるいはセメントモルタル19の固化前に
上下に動かす等の方法によつてセメントモルタル
19に付着させないようにしてもよい。 In this way, each retaining wall block 9 is divided into the first section.
H After stacking for 1 minute, put a precast concrete top plate 18 on top of it, pass each PC steel material 8 through it and stretch it straight, and add cement mortar 19 (No. 11) into the groove 17. (shown in the figure) is injected, and after waiting for it to solidify, the PC steel material 8 whose lower end is fixed to the first intermediate foundation 7a described above is tensioned from above the top plate 18 to apply prestress. Note that the other PC steel materials 8 may be prevented from adhering to the cement mortar 19 by extending the lower end side downward, or by moving them up and down before the cement mortar 19 solidifies.
このようにして第1区画H1の擁壁を構築後、
第4図に示すようにその下の第2区画H2の法面
1の掘削形成し、第1区画と同様に地中アンカー
6を構築し、これに支持させて第二中間基礎7b
を設置する。 After constructing the retaining wall of the first section H1 in this way,
As shown in FIG. 4, the slope 1 of the second section H2 below is excavated, an underground anchor 6 is constructed in the same way as in the first section, and the second intermediate foundation 7b is supported by the underground anchor 6.
Set up.
次いで第1区画H1において定着させなかつた
PC鋼材8を第二中間基礎7bに挿通し、その内
の一本の下端を定着させ、これが凹溝17内に挿
通される配置に各擁壁用ブロツク9を第一中間基
礎7a下まで積み上げる(第5図に示す)。その
後、凹溝17内にセメントモルタル19を注入
し、その固化を待つて第二中間基礎7bに下端を
定着したPC鋼材8を天端板18上より緊張し、
プレストレスを付与する。 Then, it was not established in the first section H1 .
Insert the PC steel material 8 into the second intermediate foundation 7b, fix the lower end of one of them, and stack each retaining wall block 9 to the bottom of the first intermediate foundation 7a in such a position that it is inserted into the groove 17. (As shown in Figure 5). After that, cement mortar 19 is injected into the groove 17, and after waiting for it to solidify, the PC steel material 8 whose lower end is fixed to the second intermediate foundation 7b is tensioned from above the top plate 18.
Apply prestress.
各区画が多段にわたる場合には、同様にして各
区画毎に順次擁壁を構築する。 If each section has multiple stages, retaining walls are constructed in sequence for each section in the same way.
最下部の第3区画H3においては、第6図に示
すように前述と同様にして原傾斜面1を掘削の
後、法面2の最下部にプレキヤストコンクリート
製もしくは現場打コンクリートによる最下部基礎
20を設置し、これにPC鋼材8の下端を定着さ
せた後、第7図に示すように擁壁用ブロツク9を
積み上げ、凹溝17内にセメントモルタル19を
注入後、PC鋼材8を緊張し、プレストレスを付
与する。このようにして全区画H1〜H3の擁壁を
構築後、各擁壁ブロツク9の土受け空間内に土砂
を詰め、その土砂内に植生する。 In the third section H3 at the bottom, as shown in Figure 6, after excavating the original slope 1 in the same manner as described above, the bottom part of the slope 2 is made of precast concrete or cast-in-place concrete. After installing the foundation 20 and fixing the lower end of the prestressing steel material 8 thereto, stacking retaining wall blocks 9 as shown in FIG. Tense and give prestress. After constructing the retaining walls of all the sections H1 to H3 in this way, the soil receiving space of each retaining wall block 9 is filled with earth and sand, and vegetation is grown in the earth and sand.
(発明の効果)
上述したように本発明の法面擁壁構築方法は、
原傾斜面の上部より一区画づつ地中アンカーに支
持させて擁壁ブロツクによる擁壁を構築するよう
にしたことにより、下側の原傾斜面は掘削されな
い安定した状態のままで上側が擁壁及び地中アン
カーによつて安定化されることとなり、このた
め、急斜面の法面であつても地滑りを生じさせる
ことなく一面として連続した広面積の擁壁が構築
できるこことなつものである。(Effect of the invention) As mentioned above, the slope retaining wall construction method of the present invention has the following effects:
By constructing a retaining wall using retaining wall blocks supported one section at a time by underground anchors from the upper part of the original slope, the original slope on the lower side remains in a stable state without being excavated, and the upper side remains as a retaining wall. The structure is stabilized by underground anchors, and as a result, even on steep slopes, it is possible to construct a continuous retaining wall over a wide area without causing landslides.
図面は本発明の実施例を示すもので、第1図〜
第7図は本発明方法による擁壁構築工程の断面
図、第8図は擁壁ブロツクの平面図、第9図は同
側面図、第10図は第8図中のA−A線断面図、
第11図は擁壁の部分拡大横断面図である。
H1〜H3……区画、1……原傾斜面、2……法
面、6,20……地中アンカー、7a,7b……
中間基礎、8……PC鋼材、9……擁壁用ブロツ
ク、17……凹溝、19……天端板、20……最
下部基礎。
The drawings show embodiments of the present invention, and FIGS.
Fig. 7 is a sectional view of the retaining wall construction process according to the method of the present invention, Fig. 8 is a plan view of the retaining wall block, Fig. 9 is a side view of the same, and Fig. 10 is a sectional view taken along line A-A in Fig. 8. ,
FIG. 11 is a partially enlarged cross-sectional view of the retaining wall. H 1 to H 3 ... section, 1 ... original slope, 2 ... slope, 6, 20 ... underground anchor, 7a, 7b ...
Intermediate foundation, 8...PC steel material, 9... Retaining wall block, 17... Concave groove, 19... Top plate, 20... Bottom foundation.
Claims (1)
に沿つてプレキヤストコンクリート製の擁壁用ブ
ロツクを積み上げて、該法面の表面を被覆する法
面擁壁構築方法において、擁壁を構築しようとす
る傾斜面を一定高さづつに区分し、その上方側の
一区分を掘削して所定傾斜の法面を形成し、該区
分の下縁部に一定間隔毎に地中アンカーを構築
し、該地中アンカーに支持させて水平方向の桁状
をした中間基礎を設け、該中間基礎上に順次擁壁
ブロツクを積み上げて一区分の擁壁を構築し、次
いで前記中間基礎下の次の一区分の傾斜面を掘削
して上述と同様に順次一区分づつ下方に向けて擁
壁を構築して上下に連続した一面の擁壁となすこ
とを特徴としてなる法面擁壁構築方法。 2 順次積み上げられ水平方向に隣り合う擁壁用
ブロツク間に上下に連続した場所打ちコンクリー
ト製の柱状部を形成し、該柱状部と中間基礎とに
連続させてPC鋼材を挿通し、プレストレスを付
与する請求項第1項に記載の法面擁壁構築方法。[Claims] 1. A slope retaining system that covers the surface of an original slope by excavating an original slope into a slope with a necessary angle and stacking blocks for a retaining wall made of precast concrete along the slope. In the wall construction method, the slope on which the retaining wall is to be constructed is divided into sections of a certain height, one section on the upper side is excavated to form a slope of a specified slope, and the lower edge of the section is set at a certain height. An underground anchor is constructed at each interval, a horizontal girder-shaped intermediate foundation is supported by the underground anchor, and retaining wall blocks are stacked one after another on the intermediate foundation to construct one section of retaining wall. Then, the next section of the sloped surface under the intermediate foundation is excavated and a retaining wall is constructed downward one section at a time in the same manner as described above to form a continuous vertical retaining wall. How to build a slope retaining wall. 2 Form vertically continuous cast-in-place concrete columns between horizontally adjacent retaining wall blocks that are stacked one after another, insert prestressing steel continuously between the columns and the intermediate foundation, and apply prestress. A slope retaining wall construction method according to claim 1.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP20715289A JPH0372114A (en) | 1989-08-10 | 1989-08-10 | Method for constructing normal-plane retaining wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP20715289A JPH0372114A (en) | 1989-08-10 | 1989-08-10 | Method for constructing normal-plane retaining wall |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0372114A JPH0372114A (en) | 1991-03-27 |
JPH052773B2 true JPH052773B2 (en) | 1993-01-13 |
Family
ID=16535082
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP20715289A Granted JPH0372114A (en) | 1989-08-10 | 1989-08-10 | Method for constructing normal-plane retaining wall |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0372114A (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20030067053A (en) * | 2002-02-06 | 2003-08-14 | (주) 페니엘이엔씨 | Assembling method for permanent soil nailing |
JP4599322B2 (en) * | 2006-04-11 | 2010-12-15 | 西日本エス・ピー・シー株式会社 | Slope protection structure |
EP2740549B1 (en) * | 2012-12-07 | 2016-04-20 | Primetals Technologies Austria GmbH | Pinch roller of a winding assembly of a rolling mill |
-
1989
- 1989-08-10 JP JP20715289A patent/JPH0372114A/en active Granted
Also Published As
Publication number | Publication date |
---|---|
JPH0372114A (en) | 1991-03-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5582492A (en) | Method and apparatus for an anchored earth restraining wall | |
US4653962A (en) | Retaining wall construction and method of manufacture | |
US5551810A (en) | Retaining wall with an outer face and method of forming the same | |
US4369004A (en) | Earth retaining method and structure | |
JP2000265484A (en) | CONSTRUCTION METHOD FOR UNDERGROUND STRUCTURE BY PCa PILE UNDERGROUND WALL | |
JP2004100157A (en) | Retaining wall structure and its construction method | |
JP2743264B2 (en) | Retaining wall construction | |
JPH052773B2 (en) | ||
US9951493B2 (en) | Precast integral post and retaining wall and method for installing same | |
JP2000144769A (en) | Method of landslide protection work for preparing housing lot | |
JP2641182B2 (en) | Slope stabilization method and slope expansion method | |
JP2787806B2 (en) | Earth retaining wall | |
US5558470A (en) | System and method for adjustably anchoring traffic barriers and wall facing panels to the soldier beams of a wall | |
JP2000257088A (en) | Earth retaining wall and its construction method | |
JP2536376B2 (en) | Foundation structure of shed for road protection | |
JP2523234B2 (en) | Anchor retaining wall | |
JPH01244003A (en) | Lock-shade and construction thereof | |
JPS6178923A (en) | Wall face structure for reinforced earth retaining wall | |
JPH03279501A (en) | Widening of road | |
JP4423390B2 (en) | Construction method of slope protection retaining wall | |
JP4045623B2 (en) | Construction method of reinforced concrete underground floor and underground structure constructed by this method | |
JPH0781274B2 (en) | How to build a beam on an underground wall | |
JPH07102507A (en) | Method for constructing earth retaining wall | |
JPH0663235B2 (en) | Soil retaining method | |
JP2929588B2 (en) | Road extension structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 16 Free format text: PAYMENT UNTIL: 20090113 |
|
LAPS | Cancellation because of no payment of annual fees |