Burying method by honeycomb block

Info

Publication number
JPH0434110A
JPH0434110A JP13992690A JP13992690A JPH0434110A JP H0434110 A JPH0434110 A JP H0434110A JP 13992690 A JP13992690 A JP 13992690A JP 13992690 A JP13992690 A JP 13992690A JP H0434110 A JPH0434110 A JP H0434110A
Authority
JP
Japan
Prior art keywords
honeycomb
blocks
water
levee
shaped blocks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP13992690A
Other languages
Japanese (ja)
Other versions
JP2741628B2 (en
Inventor
Masahiro Okamoto
正広 岡本
Yoshinobu Tsuji
辻 芳伸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP13992690A priority Critical patent/JP2741628B2/en
Publication of JPH0434110A publication Critical patent/JPH0434110A/en
Application granted granted Critical
Publication of JP2741628B2 publication Critical patent/JP2741628B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE:To reduce the cost for construction by sinking honeycomb blocks while piling in the inside of a levee constructed on the off-land border part of a buried section, and laying a sheet on the blocks to form an artificial ground. CONSTITUTION:A levee 1 is constructed on a border part of a offshore buried section in a buried sea area. Honeycomb blocks 2 molded into a honeycomb form are sunk in piled state in the buried section in the inside of the levee 1, and earth is laid on a sheet 3' laid on the blocks 2 to create an artificial ground 4. The levee 1 is formed into water permeable structure, whereby the sea water is penetrated into the blocks 2, and water is purified through the formation of films by microorganisms. Water contamination thus can be prevented.

Description

【発明の詳細な説明】 [産業上の利用分野1 本発明は、ハニカム形状ブロックにより海、湖沼、河川
等の水域の一部を埋め立てる工法に関する。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field 1] The present invention relates to a construction method for reclaiming a part of a water body such as the sea, a lake, a river, etc. using honeycomb-shaped blocks.

[従来の技術] 従来、海岸等の埋立ては、沖合に締切り堤防を築造後、
土砂運搬船による埋立土砂の海上投棄、あるいは浚渫等
によって埋立て地盤を造成し、その後、何等かの軟弱地
盤処理工法(例えばバーチカルドレーン工法)を施して
、埋立て地盤を安定させる工法を採って米だ。
[Conventional technology] Traditionally, land reclamation on the coast, etc. was carried out after constructing a cofferdam offshore.
The reclaimed ground is created by dumping the reclaimed soil at sea using a sand carrier or by dredging, and then some kind of soft ground treatment method (e.g. vertical drain method) is applied to stabilize the reclaimed ground. is.

[発明が解決しようとする課題] しかしながら、上記従来の埋立て工法は、海上投棄ある
いは浚渫時の海域等の汚染、それに対する漁業補償等な
どの問題が大きく、また、軟弱地盤処理工法には多大の
賛用を要する等の問題点があった。
[Problems to be solved by the invention] However, the above-mentioned conventional land reclamation methods have serious problems such as pollution of sea areas during sea dumping or dredging, and compensation for fisheries. There were problems such as the need for support from the public.

本発明は、上記従来の問題点を解決するためになされた
もので、その目的とするところは、工期が短くて1冑が
安価であるばかりでな(、水質汚染を発生せしめる恐れ
のないハニカム形状ブロックによる埋立工法を提供する
ことにある。
The present invention was made in order to solve the above-mentioned conventional problems, and its objectives are not only to shorten the construction period and reduce the cost per unit (but also to create a honeycomb structure that does not cause water pollution). The objective is to provide a reclamation method using shaped blocks.

[!1題を解決するための手a] 本発明のハニカム形状ブロックによる埋立工法は、埋立
て区域の沖合境界部に堤防を構築し、該埋立て区域内に
ハニカム形状ブロックを積み重ねながら沈設し、該沈設
したハニカム形状ブロック上にシートを敷設して人工地
盤を形成することをvf徴とする。
[! A method for solving problem 1] The reclamation method using honeycomb-shaped blocks of the present invention is to construct an embankment at the offshore boundary of a reclamation area, and deposit honeycomb-shaped blocks in the reclamation area while stacking them. The VF feature is the formation of an artificial ground by laying a sheet on top of the sunken honeycomb-shaped blocks.

上記堤防は透水構造にしてもよい。The embankment may have a permeable structure.

[実施例] 以下、本発明の一実施例について図面を参照しながら説
明する。
[Example] Hereinafter, an example of the present invention will be described with reference to the drawings.

まず、第1図に示すように、埋立海域の沖合の埋立区域
の境界部分に堤防1を構築する。
First, as shown in Figure 1, a dike 1 is constructed at the boundary of the reclaimed area offshore of the reclaimed sea area.

続いて、上記堤防1内の埋立て区域内にハニカム形状ブ
ロック2を積み重ね状態に沈設する。
Subsequently, the honeycomb-shaped blocks 2 are deposited in a stacked state in the reclamation area of the embankment 1.

上記ハニカム形状ブロック2は、第2図に示すように、
厚み方向、すなわち垂直方向に多数の六角柱状の透孔、
すなわち貫通ハニカム室2aを形成するようにジオテキ
スタイルのような合成樹脂製不織布材料により成型加工
されたハチの巣状の剛構造体であって、特に厚み方向(
垂直方向)に対する十分な耐圧縮強度を有すると共に大
容量の空隙を有する。したがって、本ハニカム形状ブロ
ック2は発泡スチロールのように水に浮く恐れはない。
The honeycomb-shaped block 2, as shown in FIG.
A large number of hexagonal prism-shaped through holes in the thickness direction, that is, in the vertical direction,
That is, it is a honeycomb-shaped rigid structure formed of a synthetic resin non-woven material such as geotextile so as to form a through honeycomb chamber 2a, especially in the thickness direction (
It has sufficient compressive strength in the vertical direction) and a large volume of voids. Therefore, there is no fear that the honeycomb-shaped block 2 will float on water unlike Styrofoam.

尚、上記ハニカム形状ブロック2を硬質プラスチックに
より成型してもよい。
Incidentally, the honeycomb-shaped block 2 may be molded from hard plastic.

上記ハニカム形状ブロック2は製造・運搬・施工等の都
合にあわせて適宜大きさに成型加工され、埋立て現場に
おいて積み重ね接a−される。この積み重ね接続方法と
しては、例えば、第3図に示すように、接続基板3の上
下に突設した接続突起3aを上下のハニカム形状ブロッ
ク2.2の貫通ハニカム室2aを嵌合させて行う。
The honeycomb-shaped blocks 2 are molded into an appropriate size according to the convenience of manufacturing, transportation, construction, etc., and are stacked and bonded at a landfill site. As shown in FIG. 3, this stacking connection method is carried out, for example, by fitting connection protrusions 3a protruding from the top and bottom of the connection board 3 into through-hole honeycomb chambers 2a of the top and bottom honeycomb-shaped blocks 2.2.

ハニカム形状ブロック2の沈設が完了したら、その上に
シート3′ を敷設する。
After the honeycomb-shaped block 2 has been completely deposited, a sheet 3' is laid thereon.

続いて、上記シート3′の上に盛土をして人工地盤4を
造成する。該人工地盤4の適宜位置には集水桝5を設置
して、排水処理せしめる。尚、上記人工地盤4からの排
水は上記ハニカム形状ブロック2の内部に浸透させても
よく、或は堤防1の外側の海域に排出させてもよい。
Subsequently, an embankment is placed on top of the sheet 3' to create an artificial ground 4. Water collection basins 5 are installed at appropriate positions on the artificial ground 4 to treat wastewater. Incidentally, the drainage water from the artificial ground 4 may be allowed to permeate into the interior of the honeycomb-shaped block 2, or may be discharged to the sea area outside the embankment 1.

尚、上記堤防1を、ハニカム形状ブロックの中に砕石を
埋め込んで、これを積み重ねることにより築造すること
により、透水性にしておき、人工地盤のハニカム形状ブ
ロック2内に海水が侵入できるようにしておくと、ハニ
カム室2aの中に微生物の膜が形成されて、浄化作用を
発揮する。
The embankment 1 is made water permeable by embedding crushed stones in honeycomb-shaped blocks and stacking them, so that seawater can enter into the honeycomb-shaped blocks 2 of the artificial ground. When left in the honeycomb chamber 2a, a microbial film is formed inside the honeycomb chamber 2a, exerting a purifying effect.

[発明の効果1 (1)海等の水域環境を汚染することなく埋立て地盤を
造成することができ、漁業補償等の問題が発生する恐れ
がない。
[Effect of the invention 1 (1) Reclaimed ground can be created without polluting the ocean or other aquatic environment, and there is no risk of problems such as fishing compensation.

(2)ハニカム形状ブロック内部に海水等を侵入せしめ
ることによって、ハニカム室の中に生物膜ができ、微生
物の働きによって水を浄化することができる。
(2) By allowing seawater or the like to enter the honeycomb-shaped block, a biofilm is formed in the honeycomb chamber, and the water can be purified by the action of microorganisms.

(3)海水等の水を排水する必要なく、地盤を構築する
ことができる。
(3) The ground can be constructed without the need to drain water such as seawater.

(4)軟弱地盤処理の必要がない。(4) There is no need to treat soft ground.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明工法による埋立て構築物の断面図、第2
図はハニカム形状ブロックの部分斜視図、第3図はハニ
カム形状ブロックの接続説明図である。 貫通ハニカム室、3・・・接続基板、3a・・・接続突
起、3′・・・シート、4・・・人工地盤。
Figure 1 is a cross-sectional view of a reclaimed structure constructed using the construction method of the present invention;
The figure is a partial perspective view of a honeycomb-shaped block, and FIG. 3 is an explanatory diagram of connections of the honeycomb-shaped block. Penetrating honeycomb chamber, 3... Connection board, 3a... Connection protrusion, 3'... Sheet, 4... Artificial ground.

Claims (1)

【特許請求の範囲】 1、埋立で区域の沖合境界部に堤防を構築し、該埋立て
区域内にハニカム形状ブロックを積み重ねながら沈設し
、該沈設したハニカム形状ブロック上にシートを敷設し
て人工地盤を形成することを特徴とするハニカム形状ブ
ロックによる埋立工法。 2、上記堤防を透水構造にしたことを特徴とする請求項
1に記載のハニカム形状ブロックによる埋立工法。
[Claims] 1. An embankment is built at the offshore boundary of an area by reclamation, honeycomb-shaped blocks are piled up and sunk within the reclaimed area, and a sheet is laid on top of the sunken honeycomb-shaped blocks to create an artificial construction. A reclamation method that uses honeycomb-shaped blocks to form the ground. 2. The reclamation method using honeycomb-shaped blocks according to claim 1, wherein the embankment has a permeable structure.
JP13992690A 1990-05-31 1990-05-31 Landfill method using honeycomb shaped blocks Expired - Fee Related JP2741628B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13992690A JP2741628B2 (en) 1990-05-31 1990-05-31 Landfill method using honeycomb shaped blocks

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13992690A JP2741628B2 (en) 1990-05-31 1990-05-31 Landfill method using honeycomb shaped blocks

Publications (2)

Publication Number Publication Date
JPH0434110A true JPH0434110A (en) 1992-02-05
JP2741628B2 JP2741628B2 (en) 1998-04-22

Family

ID=15256882

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13992690A Expired - Fee Related JP2741628B2 (en) 1990-05-31 1990-05-31 Landfill method using honeycomb shaped blocks

Country Status (1)

Country Link
JP (1) JP2741628B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0455509A (en) * 1990-06-22 1992-02-24 Yokohama Rubber Co Ltd:The Reclaiming structural body
JP2018084487A (en) * 2016-11-24 2018-05-31 日立Geニュークリア・エナジー株式会社 Nuclear facility

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0455509A (en) * 1990-06-22 1992-02-24 Yokohama Rubber Co Ltd:The Reclaiming structural body
JP2018084487A (en) * 2016-11-24 2018-05-31 日立Geニュークリア・エナジー株式会社 Nuclear facility

Also Published As

Publication number Publication date
JP2741628B2 (en) 1998-04-22

Similar Documents

Publication Publication Date Title
JPH0434110A (en) Burying method by honeycomb block
CN218580596U (en) Intertidal zone offshore ecological submerged embankment structure
JP2810925B2 (en) Water purification structure
JPH0296010A (en) Connectable bags
KR101080088B1 (en) Ecological environmental water retention system and construction method thereof
CN214883415U (en) Landscape stack way type ecological revetment structure based on existing vertical retaining wall
CN215562338U (en) Multi-stage storage-regulation hydrophilic ecological bank protection structure based on existing vertical retaining wall
JP4360645B2 (en) How to create an artificial tidal flat
CN208501612U (en) Armored concrete revetment device
JP2001003344A (en) Underwater multi-purpose structure
KR100429370B1 (en) Method for constructing revetment dike using a fiber for public works
JP4350848B2 (en) Artificial tidal flat and its construction method
JPS63156106A (en) Composing unit for water area structure
JP2531328B2 (en) How to build a bank
JP3734778B2 (en) Fish reefs and how to build them
JPS6312182Y2 (en)
CN117618997B (en) Quick treatment system and method for open caisson mud
CN217089174U (en) Be applicable to bionical type imitative rock matter ecosystem of silt matter intertidal zone
JP4606454B2 (en) Construction method of managed revetment
JP2001107333A (en) Poor oxygen water mass infiltration preventive method and poor oxygen water mass infiltration preventive fence
JP2011179204A (en) Revetment panel material for living-object symbiosis, and living-object-symbiotic-type revetment
JP4345099B2 (en) Water purification structure
JP2002018208A (en) Method for treating leakage water in reclaimed land, and the like
JP2002285525A (en) Construction method of revetment/slope of porous concrete
JP3087227B2 (en) Seawater purification structure

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees