[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

JP7213154B2 - Top slab construction method for shaft and top slab structure - Google Patents

Top slab construction method for shaft and top slab structure Download PDF

Info

Publication number
JP7213154B2
JP7213154B2 JP2019114585A JP2019114585A JP7213154B2 JP 7213154 B2 JP7213154 B2 JP 7213154B2 JP 2019114585 A JP2019114585 A JP 2019114585A JP 2019114585 A JP2019114585 A JP 2019114585A JP 7213154 B2 JP7213154 B2 JP 7213154B2
Authority
JP
Japan
Prior art keywords
steel
precast concrete
embedded
top slab
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2019114585A
Other languages
Japanese (ja)
Other versions
JP2021001453A (en
Inventor
吉隆 紀伊
琢郎 小坂
初太郎 梶川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2019114585A priority Critical patent/JP7213154B2/en
Publication of JP2021001453A publication Critical patent/JP2021001453A/en
Application granted granted Critical
Publication of JP7213154B2 publication Critical patent/JP7213154B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

本発明は、立坑(立坑躯体)の地上側開口部を閉塞する頂版の構築方法及びその構造に関する。尚、本発明でいう「頂版」とは立坑の地下側から見た場合であり、地上側から見れば「床版」ということもできる。 TECHNICAL FIELD The present invention relates to a construction method and structure of a top slab that closes an opening on the ground side of a shaft (shaft skeleton). The term "top slab" as used in the present invention refers to the case when viewed from the underground side of the vertical shaft, and can also be referred to as the "floor slab" when viewed from the ground side.

都市部のシールドトンネル工事では、立坑が設けられ、シールド掘進機は立坑の開口を通じて投入され、その後も立坑の開口は資機材の搬入に利用される。トンネル工事用の立坑には、このような発進立坑の他、到達立坑あるいは中間立坑もある。そして、トンネル工事の施工完了後に、立坑の開口は頂版により閉止され、地下側と地上側とがそれぞれ利用可能となる。 In shield tunnel construction in urban areas, a vertical shaft is constructed, the shield machine is put in through the opening of the vertical shaft, and the opening of the vertical shaft is used for bringing in materials and equipment. Vertical shafts for tunnel construction include such starting vertical shafts as well as arrival vertical shafts and intermediate vertical shafts. After the tunnel construction is completed, the opening of the vertical shaft is closed by the top slab, and the underground side and the aboveground side can be used.

特許文献1には、立坑躯体の築造を含むシールドトンネルの工事手順が開示されている。更に、トンネルの施工完了後に、立坑内部構築工事として、立坑内部に床版や柱を下方から上方へ順に型枠支保工を積み立てつつ構築し、コンクリート強度の発現後に型枠支保工を撤去することが開示されている。 Patent Literature 1 discloses a shield tunnel construction procedure including construction of a vertical shaft skeleton. Furthermore, after the construction of the tunnel is completed, as part of the construction work inside the shaft, the floor slabs and columns are built up in order from the bottom to the top with form shoring inside the pit, and the form shoring is removed after the strength of the concrete is achieved. is disclosed.

また、特許文献2には、地下構造物の中床スラブの構築方法として、下階に型枠支保工を施工し、その上に中床スラブ型枠を設置し、その上にコンクリートを打設して、中床スラブを構築する方法が開示されている。 In addition, Patent Document 2 describes a method for constructing a middle floor slab for an underground structure, in which a form shoring is constructed on the lower floor, a middle floor slab formwork is installed above it, and concrete is poured on it. Thus, a method of constructing a mid-floor slab is disclosed.

特開2017-203294号公報JP 2017-203294 A 特開2002-371570号公報Japanese Patent Application Laid-Open No. 2002-371570

立坑(立坑躯体)の地上側開口部を閉塞する頂版の構築に際し、特許文献1、2に示されるような、下側から型枠支保工を設ける方法では、次のような問題がある。
構築する頂版までの高さが高く、開口面積が大きい等の場合、足場や支保工が大掛かりとなり、これらの設置に大量の資材と施工手間がかかる。
また、頂版の構築後は、開口部が閉塞されるため、支保工を地上側から吊上げて撤去することができず、解体して限られた小開口から撤去することになるため、その解体撤去は非常に面倒なものとなる。
When constructing a top slab that closes the ground-side opening of a shaft (shaft skeleton), the method of providing formwork shoring from below, as shown in Patent Documents 1 and 2, has the following problems.
If the height to the top slab to be constructed is high and the opening area is large, the scaffolding and shoring will be large-scale, and installation of these will require a large amount of materials and construction work.
In addition, after the top slab is constructed, the opening is blocked, so the shoring cannot be removed by lifting it from the ground side. Removal would be very troublesome.

本発明は、このような実状に鑑み、立坑(立坑躯体)の地上側開口部を閉塞する頂版の構築に際し、頂版の構築作業、並びに、頂版構築後の作業を簡素化できるようにすることを課題とする。 In view of such a situation, the present invention is designed to simplify the construction work of the top slab and the work after constructing the top slab when constructing the top slab that closes the ground side opening of the shaft (shaft skeleton). The task is to

本発明に係る立坑の頂版構築方法は、
立坑の構築時に、立坑の地上側開口部を挟んで対向する壁体のうち、一方の壁体内に設置される鋼製杭の上端部に、前記対向する方向に突出する第1部材を予め固定し、他方の壁体内に設置される鋼製杭の上端部に、前記対向する方向に突出する第2部材を予め固定する予備工程と、
頂版の構築時に、前記第1部材と前記第2部材との間に第3部材を設置してこれらを連結する架渡し工程と、
前記第3部材を埋設型枠として、この上にコンクリートを打設する工程と、
を含み、
前記第1部材、前記第2部材、及び前記第3部材は、各々が、板状のプレキャストコンクリートと、前記プレキャストコンクリート上に配置されて、前記プレキャストコンクリートの長手方向に延在し、断面下部が前記プレキャストコンクリート内に埋設され、断面上部が前記プレキャストコンクリートの上方に露出する鉄骨と、を含む、鉄骨埋込みパネルであり、
前記架渡し工程では、前記第1部材と前記第3部材、及び、前記第2部材と前記第3部材とを、互いの鉄骨同士で連結することを特徴とする。
The method for constructing the top slab of a vertical shaft according to the present invention includes:
When constructing the shaft, the first member projecting in the opposite direction is fixed in advance to the upper end of the steel pile installed in one of the walls facing each other across the ground-side opening of the shaft. a preliminary step of preliminarily fixing the second member projecting in the opposite direction to the upper end of the steel pile installed in the other wall;
A bridging step of installing a third member between the first member and the second member and connecting them when constructing the top plate;
A step of placing concrete on the third member as an embedded formwork;
including
The first member , the second member , and the third member are each arranged on a plate-shaped precast concrete and the precast concrete, extending in the longitudinal direction of the precast concrete, and having a cross-sectional lower portion a steel frame embedded in the precast concrete, the upper part of the cross section of which is exposed above the precast concrete;
In the bridging step, the first member and the third member, and the second member and the third member are connected by mutual steel frames.

また、本発明に係る立坑の頂版構造は、
立坑の地上側開口部を挟んで対向する壁体のうち、一方の壁体内に設置される鋼製杭の上端部に固定されて、前記対向する方向に突出する第1部材と、
他方の壁体内に設置される鋼製杭の上端部に固定されて、前記対向する方向に突出する第2部材と、
前記第1部材と前記第2部材との間に設置されて、これらに連結される第3部材と、
前記第3部材を埋設型枠として、この上に打設されるコンクリート層と、
を含み、
前記第1部材、前記第2部材、及び前記第3部材は、各々が、板状のプレキャストコンクリートと、前記プレキャストコンクリート上に配置されて、前記プレキャストコンクリートの長手方向に延在し、断面下部が前記プレキャストコンクリート内に埋設され、断面上部が前記プレキャストコンクリートの上方に露出する鉄骨と、を含む、鉄骨埋込みパネルであり、
前記第1部材と前記第3部材、及び、前記第2部材と前記第3部材は、互いの鉄骨同士で連結されることを特徴とする。
Moreover, the top plate structure of the shaft according to the present invention is
a first member fixed to the upper end of a steel pile installed in one of the walls facing each other across the ground-side opening of the vertical shaft and projecting in the facing direction;
a second member fixed to the upper end of a steel pile installed in the other wall and protruding in the opposite direction;
a third member disposed between and connected to the first member and the second member;
a concrete layer placed on the third member as an embedded formwork;
including
The first member , the second member , and the third member are respectively arranged on a plate-shaped precast concrete and on the precast concrete, extend in the longitudinal direction of the precast concrete, and extend in the lower section of the section. is embedded in the precast concrete, and a steel frame whose cross-sectional upper part is exposed above the precast concrete,
The first member and the third member, and the second member and the third member are connected by mutual steel frames.

本発明によれば、壁体側に予め設置された第1部材(又は第2部材)を利用して、第1部材(又は第2部材)と第3部材との連結作業を行うことで、頂版架設作業の効率化を図ることができる。これにより、立坑の内部に大掛かりな足場や支保工を設置したり、頂版構築後にこれらを解体撤去したりする必要がなくなり、頂版の構築作業、並びに構築後の作業を簡素化できる。
また、鉄骨埋込みパネルを頂版の型枠として利用することで、型枠の設置や解体撤去作業も不要となる。
また、鉄骨埋込みパネルを用いることで、現場配筋量(及び配筋手間)を極力低減できる。
According to the present invention, the first member (or the second member) installed in advance on the wall side is used to perform the work of connecting the first member (or the second member) and the third member. Efficiency of plate installation work can be achieved. As a result, there is no need to install large-scale scaffolding or shoring inside the vertical shaft, or to dismantle and remove them after constructing the top slab, thereby simplifying the construction work of the top slab and the work after construction.
In addition, by using the steel embedded panel as the formwork for the top slab, there is no need to install or dismantle the formwork.
In addition, by using the steel-embedded panel, it is possible to reduce the on-site rebar arrangement amount (and rebar arrangement labor) as much as possible.

本発明の一実施形態として立坑の頂版の構築例を示す図A diagram showing a construction example of the top slab of a vertical shaft as one embodiment of the present invention. 頂版の構築手順を示す図Diagram showing the construction procedure of the top slab 頂版構築用の型枠を兼ねる鉄骨埋込みパネルの側面図Side view of a steel embedded panel that doubles as a formwork for constructing the top slab 同上の鉄骨埋込みパネルの要部拡大図Enlarged view of the main part of the same steel embedded panel 図4のV-V断面に相当する鉄骨埋込パネルの1ユニット分の断面図Sectional view of one unit of the steel embedded panel corresponding to the VV section of Fig. 4 同上の鉄骨埋込みパネルが隣り合うユニット間で連結された状態の断面図Sectional view of the same steel frame embedded panel connected between adjacent units 鉄骨埋込みパネルと側方の壁体との連結構造(1)を示す図Diagram showing the connection structure (1) between the steel embedded panel and the side walls 鉄骨埋込みパネルと側方の壁体との連結構造(2-1)を示す図Diagram showing the connection structure (2-1) between the steel embedded panel and the side walls 鉄骨埋込みパネルと側方の壁体との連結構造(2-2)を示す図Diagram showing the connection structure (2-2) between the steel embedded panel and the side walls 鉄骨埋込みパネルと側方の壁体との連結構造(3)を示す図Diagram showing the connection structure (3) between the steel embedded panel and the side walls

以下、本発明の実施の形態について、詳細に説明する。
図1は本発明の一実施形態として立坑の地上側開口部を閉塞する頂版の構築例を示している。
BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, embodiments of the present invention will be described in detail.
FIG. 1 shows a construction example of a top slab that closes an opening on the ground side of a shaft as an embodiment of the present invention.

本例の立坑1は、シールドトンネル工事用の平面視矩形の立坑で、例えば、次のように構築される。
例えばSMW(Soil Mixing Wall)工法により、地上Gから地中に、四方を囲む柱列式の山留壁2を構築し、その壁体内には、所定の間隔で、H形鋼や角形鋼管からなる鋼製杭を建て込む。
The vertical shaft 1 of this example is a rectangular vertical shaft for shield tunnel construction, and is constructed, for example, as follows.
For example, by the SMW (Soil Mixing Wall) construction method, a row-of-column type retaining wall 2 surrounding four sides is constructed from the ground G to the ground. erect steel piles.

山留壁2の構築に際しては、地中連続壁工法を採用してもよく、この場合は、例えば、鋼製連壁の既製品であるボックス形状の鋼製部材を建て込む。このような鋼製連壁も鋼製杭として利用可能である。 When constructing the earth retaining wall 2, a diaphragm wall construction method may be employed. In this case, for example, a box-shaped steel member, which is an off-the-shelf steel continuous wall, is erected. Such a steel continuous wall can also be used as a steel pile.

山留壁2の構築後は、山留壁2で四方を囲われた矩形開口部の内側を掘削し、床付面にはRC(鉄筋コンクリート)製の底版4を施工し、山留壁2の内面には同様にRC製の側壁5を築造することで、有底角筒状の立坑躯体7を構築する。 After constructing the earth retaining wall 2, the inside of the rectangular opening enclosed by the earth retaining wall 2 on all sides is excavated, and a bottom slab 4 made of RC (reinforced concrete) is constructed on the floor surface. Similarly, by constructing side walls 5 made of RC on the inner surface, a vertical pit skeleton 7 in the shape of a bottomed square tube is constructed.

また、本例の立坑1は、シールドトンネル工事用の発進立坑で、シールド機の搬入に用いられ、シールド機により立坑1の底部から水平方向に掘進することで、シールドトンネル8を構築する。シールドトンネル8の構築中、立坑1は、各種資機材(セグメント等)の搬入や掘削土砂の搬出に用いられる。但し、発進立坑に限るものではなく、到達立坑あるいは中間立坑であってもよい。 The vertical shaft 1 of this example is a starting vertical shaft for shield tunnel construction, and is used for carrying in a shield machine. During construction of the shield tunnel 8, the shaft 1 is used for carrying in various materials and equipment (segments, etc.) and for carrying out excavated soil. However, it is not limited to the starting vertical shaft, and may be an arrival vertical shaft or an intermediate vertical shaft.

本例では、シールドトンネル8の完成後に、立坑1(立坑躯体7)の地上側開口部に、これを閉塞するように、頂版9を構築する。立坑1の地上側である頂版9の上を盛土するなどして公園等として利用可能とするためである。また、頂版9下方の立坑空間は、非常階段や共同溝(動力電線、給排水配管、換気口)として利用可能となる。尚、立坑1の地上側開口部は、必ずしも全面が頂版9により閉塞されるわけではなく、少なくとも一部が閉塞される。 In this example, after the completion of the shield tunnel 8, the top slab 9 is constructed at the ground side opening of the shaft 1 (shaft skeleton 7) so as to block the opening. This is to make it possible to use it as a park or the like by embanking the top slab 9 on the ground side of the vertical shaft 1 . In addition, the shaft space below the top slab 9 can be used as an emergency staircase or a common ditch (power lines, water supply and drainage pipes, ventilation openings). Incidentally, the ground-side opening of the shaft 1 is not necessarily entirely closed by the top slab 9, but is at least partially closed.

頂版9の構築方法について、以下に説明する。
先ず、図2及び図3により、概略的に説明する。
A method of constructing the top plate 9 will be described below.
First, a schematic description will be given with reference to FIGS. 2 and 3. FIG.

図2は頂版構築用の型枠を兼ねる鉄骨埋込みパネルを用いた頂版9の構築手順を示す。また、図3は鉄骨埋込みパネルの側面図である。本実施形態では、鉄骨埋込みパネルは、第1部材11、第2部材12及び第3部材13(いずれも梁部材)により構成される。 FIG. 2 shows the construction procedure of the top slab 9 using steel embedded panels that also serve as a formwork for constructing the top slab. Moreover, FIG. 3 is a side view of a steel-embedded panel. In this embodiment, the steel-embedded panel is composed of a first member 11, a second member 12 and a third member 13 (all of which are beam members).

図2(a)は予備工程を示し、立坑1の構築時に実施する。
予備工程では、図2(a)に示すように、立坑1の地上側開口部を挟んで対向する壁体(ここでは山留壁2A、2B)のうち、一方の壁体2A内に設置される鋼製杭3A(図3)の上端部に、前記対向する方向に突出する第1部材11を予め固定し、他方の壁体2B内に設置される鋼製杭3B(図3)の上端部に、前記対向する方向に突出する第2部材12を予め固定する。
FIG. 2(a) shows a preliminary process, which is carried out when the shaft 1 is constructed.
In the preliminary process, as shown in FIG. 2(a), of the walls (here, retaining walls 2A and 2B) facing each other across the ground side opening of the vertical shaft 1, the wall is installed in one wall 2A. The first member 11 protruding in the opposite direction is previously fixed to the upper end of the steel pile 3A (Fig. 3), and the upper end of the steel pile 3B (Fig. 3) installed in the other wall 2B The second member 12 protruding in the opposite direction is previously fixed to the portion.

ここで、図3に示すように、鋼製杭3Aと第1部材11とは、互いの鉄骨同士を添接板31等を介して固定する。また、鋼製杭3Bと第2部材12とは、互いの鉄骨同士を添接板32等を介して固定する。尚、互いの鉄骨同士の固定は添接板によらず、溶接により行ってもよい。 Here, as shown in FIG. 3, the steel pile 3A and the first member 11 are fixed to each other through a splicing plate 31 or the like. Further, the steel pile 3B and the second member 12 are fixed to each other through the splicing plate 32 or the like. The steel frames may be fixed to each other by welding instead of using splice plates.

予備工程において、第1部材11及び第2部材12をそれぞれ鋼製杭3A、3Bに設置することで、これらが、立坑1内に壁体側から張り出すことになるが、例えば、壁体2A、2Bの面内に収まる場合もあり得るし、壁体2A、2Bより開口側に張り出す場合もあり得る。いずれにしても、鋼製杭3A、3Bからの張り出し長を数100mm程度とすることで、立坑開口部への資材搬入等に影響のない程度となる。 In the preliminary process, by installing the first member 11 and the second member 12 on the steel piles 3A and 3B, respectively, they protrude into the vertical shaft 1 from the wall side. It may fit within the plane of 2B, or it may protrude from the walls 2A and 2B toward the opening. In any case, by setting the overhang length from the steel piles 3A and 3B to about several 100 mm, there is no effect on carrying materials into the vertical shaft opening.

図2(b)、(c)は架渡し工程を示し、立坑1の地上側開口を通じてシールド機等の主要資機材の搬出入が完了した後、頂版9の構築時に実施する。主要資機材とは、シールドトンネル工事におけるシールド掘進機や、シールドトンネルの覆工体を構成するセグメント等が該当する。
架渡し工程では、図2(b)及び(c)に示すように、第1部材11と第2部材12との間に、第3部材13を設置して、これらを連結する。
2(b) and 2(c) show the bridging process, which is carried out at the time of construction of the top slab 9 after the main materials and equipment such as the shield machine have been carried in and out through the opening on the ground side of the vertical shaft 1. As shown in FIG. Major materials and equipment include shield machines used in shield tunnel construction and segments that make up the lining of shield tunnels.
In the bridging step, as shown in FIGS. 2B and 2C, the third member 13 is installed between the first member 11 and the second member 12 to connect them.

特に本実施形態では、第3部材13は、3つに分割、すなわち、架渡し方向の左右両端の部材13-1、13-2と、中央の部材13-3とに分割してある。尚、第3部材13の分割数はこれに限られず、立坑開口部の桁方向長さ(鉄骨22の延在方向の長さ)に合わせて増減が可能である。 In particular, in this embodiment, the third member 13 is divided into three, namely, left and right end members 13-1 and 13-2 in the bridging direction, and a center member 13-3. The number of divisions of the third member 13 is not limited to this, and can be increased or decreased according to the length in the girder direction (the length in the extending direction of the steel frame 22) of the shaft opening.

従って、先ず、図2(b)に示すように、第1部材11に第3左端部材13-1を片持ち状態で連結し、同様に、第2部材12に第3右端部材13-2を片持ち状態で連結する。 Therefore, first, as shown in FIG. 2(b), the third left end member 13-1 is connected to the first member 11 in a cantilever state, and similarly, the third right end member 13-2 is connected to the second member 12. Connect in a cantilevered state.

ここで、図3に示すように、第1部材11と第3左端部材13-1とは互いの鉄骨同士を添接板33等を介して固定し、第2部材12と第3右端部材13-2とは互いの鉄骨同士を添接板34等を介して固定する。尚、互いの鉄骨同士の固定は添接板33、34等を介することなく、ボルト・ナットにより直接連結してもよい。 Here, as shown in FIG. 3, the steel frames of the first member 11 and the third left end member 13-1 are fixed to each other via a splicing plate 33 or the like, and the second member 12 and the third right end member 13 are fixed together. -2 fixes the steel frames to each other via the splicing plate 34 or the like. The steel frames may be fixed to each other directly by bolts and nuts without using the splicing plates 33, 34 or the like.

次いで、図2(c)に示すように、第3左端部材13-1と第3右端部材13-2との間に、第3中央部材13-3を設置して、これらを連結する。 Next, as shown in FIG. 2(c), the third central member 13-3 is installed between the third left end member 13-1 and the third right end member 13-2 to connect them.

ここで、図3に示すように、第3左端部材13-1と第3中央部材13-3とは互いの鉄骨同士を添接板35等を介して固定し、第3右端部材13-2と第3中央部材13-3とは互いの鉄骨同士を添接板36等を介して固定する。尚、互いの鉄骨同士の固定は添接板35、36等を介することなく、ボルト・ナットにより直接連結してもよい。 Here, as shown in FIG. 3, the steel frames of the third left end member 13-1 and the third central member 13-3 are fixed to each other via a splicing plate 35 or the like, and the third right end member 13-2 is fixed to each other. and the third central member 13-3 are fixed to each other through splicing plates 36 and the like. The steel frames may be fixed to each other directly by bolts and nuts without using the splicing plates 35 and 36 or the like.

図2(d)はコンクリート打設工程を示し、架渡し工程後に実施する。
コンクリート打設工程では、図2(d)に示すように、少なくとも第3部材13(13-1~13-3)、特に本実施形態では第1~第3部材11~13を埋設型枠として、これらの上に、コンクリートを打設する。また、打設前に、埋設型枠上に必要な配筋をなしてもよい。これにより、第1~第3部材11~13上にコンクリート層14が形成されて、頂版9が構築される。
FIG. 2(d) shows the concrete placing process, which is carried out after the bridging process.
In the concrete placing step, as shown in FIG. 2(d), at least the third member 13 (13-1 to 13-3), particularly the first to third members 11 to 13 in this embodiment, are used as an embedded formwork. , pour concrete over them. In addition, necessary reinforcement may be arranged on the embedded formwork before placing. Thereby, the concrete layer 14 is formed on the first to third members 11 to 13, and the top slab 9 is constructed.

次に、第1部材11、第2部材12、及び、第3部材13(第3左端部材13-1、第3右端部材13-2、及び、第3中央部材13-3)の構造について、図3及び図4~図6により、説明する。 Next, regarding the structures of the first member 11, the second member 12, and the third member 13 (the third left end member 13-1, the third right end member 13-2, and the third central member 13-3), Description will be made with reference to FIGS. 3 and 4 to 6. FIG.

図4は図3の鉄骨埋込みパネルの要部拡大図、図5は図4のV-V断面に相当する鉄骨埋込みパネルの1ユニット分の断面図、図6は鉄骨埋込みパネルが隣り合うユニット間で連結された状態の断面図である。 Fig. 4 is an enlarged view of the essential parts of the steel-embedded panel in Fig. 3, Fig. 5 is a cross-sectional view of one unit of the steel-embedded panel corresponding to the VV cross-section in Fig. 4, and Fig. 6 is between adjacent units of the steel-embedded panel. FIG. 10 is a cross-sectional view of a state connected with .

本実施形態において、鉄骨埋込みパネルは、第1~第3部材11~13により構成される。
本実施形態では、第1~第3部材11~13は、それぞれ鉄骨埋込みパネルであり、第1~第3部材11~13(第1部材11側から順に、第1部材11、第3部材13、第2部材12)が、これらの長手方向に連結されて、1つの大きな鉄骨埋込みパネルが構成される。
In this embodiment, the steel embedded panel is composed of first to third members 11-13.
In this embodiment, the first to third members 11 to 13 are respectively steel embedded panels, and the first to third members 11 to 13 (in order from the first member 11 side, the first member 11, the third member 13 , second member 12) are longitudinally connected to form one large steel-embedded panel.

さらに、本実施形態における第3部材13は、3つに分割されており、詳しくは、第1部材11側から順に、第1部材11、第3左端部材13-1、第3中央部材13-3、第3右端部材13-2、第2部材12が、これらの長手方向に連結されて、1つの鉄骨埋込みパネルが構成される。 Furthermore, the third member 13 in this embodiment is divided into three parts. 3. The third right end member 13-2 and the second member 12 are connected in the longitudinal direction to form one steel embedded panel.

次に、鉄骨埋込みパネルの構造について、図4及び図5を参照して説明する。
鉄骨埋込みパネルは、板状のプレキャストコンクリート21と、プレキャストコンクリート21上に配置されて、プレキャストコンクリート21の長手方向に延在する鉄骨22と、を含む。
Next, the structure of the steel embedded panel will be described with reference to FIGS. 4 and 5. FIG.
The steel frame-embedded panel includes a plate-shaped precast concrete 21 and a steel frame 22 arranged on the precast concrete 21 and extending in the longitudinal direction of the precast concrete 21 .

ここにおいて、鉄骨22は、断面下部がプレキャストコンクリート21内に埋設され、断面上部がプレキャストコンクリート21の上方に露出する。
鉄骨22としては、例えば、H形鋼又はI形鋼が用いられ、これらの一方のフランジ部がプレキャストコンクリート21内に埋め込まれ、他方のフランジ部とウェブ部(その大部分)がプレキャストコンクリート21上に露出する。図5に示すように、鉄骨埋込みパネルにおける鉄骨22は、複数並列に配置されてもよい。1つのプレキャストコンクリート21に対して複数の鉄骨22を埋め込み一体化することで、型枠としての部材強度をより増加させることができる。
Here, the steel frame 22 is embedded in the precast concrete 21 in the lower section and exposed above the precast concrete 21 in the upper section.
As the steel frame 22, for example, H-shaped steel or I-shaped steel is used. exposed to. As shown in FIG. 5, a plurality of steel frames 22 in the steel-frame-embedded panel may be arranged in parallel. By embedding and integrating a plurality of steel frames 22 into one precast concrete 21, the member strength as a formwork can be further increased.

図5に示すように、鉄骨埋込みパネルにおける鉄骨22は、隣り合う鉄骨22同士の連結のため、鉄骨22の延在方向と直交する方向に突出する多数(上下2列)の小鋼材(小梁鉄骨)23(23A、23B)を有している。小鋼材23(23A、23B)は、鉄骨22を構成する大型のH形鋼又はI形鋼のウェブ部に溶接固定した、小型のH形鋼又はI形鋼により構成することができる。 As shown in FIG. 5, the steel frames 22 in the steel-frame-embedded panel include a large number of small steel members (small beams) protruding in a direction perpendicular to the extending direction of the steel frames 22 for connecting the adjacent steel frames 22 . steel frame) 23 (23A, 23B). The small steel members 23 (23A, 23B) can be configured by small H-section steel or I-section steel welded and fixed to the web portion of the large H-section steel or I-section steel forming the steel frame 22 .

鉄骨埋込みパネルは、鉄骨22の延在方向に、第1~第3部材11~13として分割される他、鉄骨22の延在方向と直交する方向にも分割され、図5に示される単位で、ユニット化されている。 The steel frame-embedded panel is divided in the extending direction of the steel frame 22 as first to third members 11 to 13, and is also divided in a direction orthogonal to the extending direction of the steel frame 22, and is divided into units shown in FIG. , are unitized.

図5のパネルユニット(鉄骨埋込みパネルの1単位)は、プレキャストコンクリート21により断面下部が埋設された2本の鉄骨22と、2本の鉄骨22からそれぞれ内側に突出させ、添接板24等で相互に連結された内側小鋼材23Aと、2本の鉄骨22からそれぞれ外側に突出させた外側小鋼材23Bと、を含んで構成される。かかるパネルユニットは、架渡し工程の前に製造され、例えば工場にて製造され、現場に搬入される。 The panel unit (one unit of the steel-frame embedded panel) of FIG. It is composed of inner small steel members 23A connected to each other and outer small steel members 23B projecting outward from the two steel frames 22, respectively. Such a panel unit is manufactured before the bridging process, for example manufactured in a factory and brought to the site.

図6は図5のパネルユニットが隣り合うユニット間で連結された状態を示している。ユニット間の連結は、外側小鋼材23Bを、同一断面形状の連結材25を間に配して行う。
すなわち、架渡し工程においては、隣り合うパネルユニットの外側小鋼材23B同士を、これらの間に連結材25を配した上で、例えば添接板26等を介して連結する。尚、添接板26等によらず、継手を用いて連結してもよい。ここでの連結は、架渡し工程の後であって、コンクリート打設工程の前になされる。
FIG. 6 shows a state in which the panel units of FIG. 5 are connected between adjacent units. The units are connected by interposing the outer small steel members 23B with connecting members 25 having the same cross-sectional shape.
That is, in the bridging step, the outer small steel members 23B of the adjacent panel units are connected to each other via, for example, splicing plates 26 after disposing the connecting member 25 therebetween. It should be noted that joints may be used for connection instead of using the splicing plate 26 or the like. The connection here is made after the bridging process and before the concrete placing process.

本実施形態では、現場での連結作業を容易にするため、外側小鋼材23Bの先端を斜めにして、外側小鋼材23B間に上向きに開(幅広)となる空間を形成し、この空間に逆三角形状(又は逆台形状)の連結材25を上から容易に挿入できるようにしている。尚、先端の角度は限定されず、通常なされるように垂直としてもよい。 In this embodiment, in order to facilitate the connection work on site, the ends of the outer small steel members 23B are slanted to form an upwardly open (wide) space between the outer small steel members 23B. A triangular (or inverted trapezoidal) connecting member 25 can be easily inserted from above. Note that the angle of the tip is not limited and may be vertical as is normally done.

図6ではユニット間の隙間を誇張して描いているが、これはユニットの単位を明確にするためで、実際には隙間が所定の設計寸法内となるように接合する。また、ユニットにおけるプレキャストコンクリート21の接合部それぞれを鍵型にして、接合断面が相欠き継ぎ形状となるようにしてもよい。 Although the gaps between the units are exaggerated in FIG. 6, this is for the purpose of clarifying the units of the units. Also, each of the joints of the precast concrete 21 in the unit may be shaped like a key so that the cross section of the joint has a intermittent joint shape.

次に、上記のような鉄骨埋込みパネルを用いた頂版9の構築方法について、図2の構築手順に沿い、図4~図6を参照して、更に詳しく説明する。 Next, a method of constructing the top slab 9 using the steel-frame embedded panel as described above will be described in more detail along the construction procedure of FIG. 2 and with reference to FIGS. 4 to 6. FIG.

図2(a)に相当する予備工程では、立坑1(立坑躯体7)の構築時に、立坑1の地上側開口部を挟んで対向する壁体(ここでは山留壁2A、2B)のうち、一方の壁体2A内に設置される鋼製杭3Aの上端部に、添接板31等を用い、又は全周溶接して、第1部材11(その鉄骨22)を固定する。他方の壁体2B内に設置される鋼製杭3Bの上端部にも、同様に、第2部材12(その鉄骨22)を固定する。 In the preliminary process corresponding to FIG. 2(a), during the construction of the vertical shaft 1 (the vertical shaft skeleton 7), of the walls facing each other across the ground-side opening of the vertical shaft 1 (here, retaining walls 2A and 2B), The first member 11 (the steel frame 22 thereof) is fixed to the upper end of the steel pile 3A installed in one wall 2A by using a splicing plate 31 or the like or by welding all around. Similarly, the second member 12 (its steel frame 22) is fixed to the upper end of the steel pile 3B installed in the other wall 2B.

第1部材11(及び第2部材12)は、架渡し方向と直交する方向に、2本の鉄骨を単位として、ユニット化されており、ユニット間では外側小鋼材23B同士を連結材25及び添接板26等を介して連結するが、必ずしもユニット化しなくてもよい。 The first member 11 (and the second member 12) are unitized by two steel frames in a direction perpendicular to the bridging direction. Although they are connected via the contact plate 26 or the like, they do not necessarily have to be unitized.

図2(b)、(c)に相当する頂版構築時の架渡し工程では、第3左端部材13-1をクレーン等の揚重機により吊り上げて、第1部材11の延長上に運び、第1部材11と第3左端部材13-1とを添接板33等を介して連結固定する。このとき、第3左端部材13-1は片持ち状態となる。
かかる連結作業は、第1部材11のプレキャストコンクリート21を足場として、すなわち壁体側のプレキャストコンクリート21の上に作業者が乗って、作業することができる。また、壁体2Aから張り出し足場を設置して作業してもよい。第2部材12と第3右端部材13-2の連結も同様に行うことができる。
2(b) and 2(c), the third left end member 13-1 is lifted by a lifting machine such as a crane, carried on the extension of the first member 11, and The first member 11 and the third left end member 13-1 are connected and fixed via a splicing plate 33 or the like. At this time, the third left end member 13-1 is in a cantilever state.
Such connection work can be performed by using the precast concrete 21 of the first member 11 as a scaffolding, that is, by having the worker get on the precast concrete 21 on the wall side. Alternatively, a scaffolding projecting from the wall 2A may be installed for the work. The connection between the second member 12 and the third right end member 13-2 can be performed in the same manner.

また、第3左端部材13-1及び第3右端部材13-2は、架渡し方向と直交する方向に、2本の鉄骨を単位として、ユニット化されており、ユニット間では、外側小鋼材23B同士を連結材25及び添接板26等を介して連結する。この作業は第3左端部材13-1及び第3右端部材13-2のプレキャストコンクリート21をそれぞれ足場として、実施することができる。 In addition, the third left end member 13-1 and the third right end member 13-2 are unitized with two steel frames in a direction perpendicular to the bridging direction. They are connected to each other via a connecting member 25, a splicing plate 26, and the like. This work can be carried out using the precast concrete 21 of the third left end member 13-1 and the third right end member 13-2 as scaffolds.

次に、第3中央部材13-3をクレーン等の揚重機により吊り上げて、第3左端部材13-1と第3右端部材13-2との間に運び、第3左端部材13-1と第3中央部材13-3とを添接板35等を介して連結固定する。
かかる連結作業は、第3左端部材13-1のプレキャストコンクリート21を足場として、すなわち壁体側のプレキャストコンクリート21の上に作業者が乗って、作業することができる。
Next, the third central member 13-3 is lifted by a lifting machine such as a crane, carried between the third left end member 13-1 and the third right end member 13-2, and 3 The central member 13-3 is connected and fixed via a splicing plate 35 or the like.
Such connection work can be performed by using the precast concrete 21 of the third left end member 13-1 as a scaffold, that is, by having the worker get on the precast concrete 21 on the wall side.

同様に、第3右端部材13-2と第3中央部材13-3とを添接板36等を介して連結固定する。
かかる連結作業は、第3右端部材13-2のプレキャストコンクリート21を足場として、すなわち壁体側のプレキャストコンクリート21の上に作業者が乗って、作業することができる。
Similarly, the third right end member 13-2 and the third central member 13-3 are connected and fixed via a splicing plate 36 or the like.
Such connection work can be performed by using the precast concrete 21 of the third right end member 13-2 as a scaffolding, that is, by having the worker get on the precast concrete 21 on the wall side.

また、第3中央部材13-3も、第3左端部材13-1、第3右端部材13-2と同様に、架渡し方向と直交する方向に、2本の鉄骨を単位として、ユニット化されており、ユニット間では外側小鋼材23B同士を連結材25及び添接板26を用いて連結する。この作業は第3中央部材13-3のプレキャストコンクリート21を足場として実施することができる。 In addition, the third central member 13-3, like the third left end member 13-1 and the third right end member 13-2, is unitized with two steel frames in the direction orthogonal to the bridging direction. Between the units, the outer small steel members 23B are connected to each other using connecting members 25 and splicing plates 26. FIG. This work can be carried out using the precast concrete 21 of the third central member 13-3 as a scaffold.

ここにおいて、第1~第3部材11~13(13-1~3)の接合部(分割部)は、図3あるいは図4から解るように、先端を斜めに形成されてもよい。これは壁体側の部材に対し、これに接合する部材(後入れ部材)を吊り下ろして接合する際に、挿入及び接合をしやすくするためである。例えば、第3中央部材13-3の挿入時に、受入れ側(第3左端部材13-1と第3右端部材13-2との間)が逆ハの字状となっていれば、挿入及び接合がしやすくなる。このとき、添接板33~36は、先端部の角度に合わせて平行四辺形に形成するとよい。 Here, as can be seen from FIG. 3 or FIG. 4, the joints (divided parts) of the first to third members 11 to 13 (13-1 to 3) may be formed with slanted tips. This is for facilitating insertion and joining when a member (post-insertion member) to be joined to the member on the wall side is hung and joined. For example, when the third central member 13-3 is inserted, if the receiving side (between the third left end member 13-1 and the third right end member 13-2) has an inverted V shape, insertion and joining easier to clean. At this time, the splicing plates 33 to 36 are preferably formed in a parallelogram according to the angles of the tip portions.

図2(d)に相当するコンクリート打設工程では、第1~第3部材11~13を埋設型枠として、これらの上にコンクリートを打設する。これにより、第1~第3部材11~13上にコンクリート層14が形成されて、頂版9が構築される。 In the concrete placing process corresponding to FIG. 2(d), concrete is placed on the first to third members 11 to 13 as embedded forms. Thereby, the concrete layer 14 is formed on the first to third members 11 to 13, and the top slab 9 is constructed.

コンクリート打設工程では、コンクリートの打設に先立って、型枠上で鉄筋の配筋作業を行うこともある。かかる配筋作業は、第1~第3部材11~13のプレキャストコンクリート21を足場として行うことができる。配筋作業を架渡し工程の後であってコンクリート打設の前に行うことにより、コンクリート打設後に、鉄筋と鉄骨埋込みパネルとがコンクリートにより一体化して、強固な頂版が構築される。
また、埋設型枠として鉄骨埋込みパネルを用いることで、本来配筋すべき鉄筋断面積分を鉄骨の断面積で受け持ち、現場での配筋量(及び配筋手間)を簡素化できるメリットがある。
In the concrete placing process, reinforcing bars may be arranged on the form before concrete is placed. Such bar arrangement work can be performed using the precast concrete 21 of the first to third members 11 to 13 as scaffolding. By arranging reinforcing bars after the bridging process and before placing the concrete, the reinforcing bars and the steel frame-embedded panels are integrated with the concrete after the placing of the concrete, and a strong top slab is constructed.
In addition, by using a steel frame embedded panel as an embedded formwork, there is an advantage that the cross-sectional area of the reinforcing steel that should be originally arranged is covered by the cross-sectional area of the steel frame, and the amount of reinforcing bar arrangement (and the time and effort for reinforcing bar arrangement) can be simplified at the site.

鉄骨埋込みパネルは、長手方向に分割され、幅方向にユニット化されていることから、分割体間やユニット間には隙間(分割等による目地)が生じる。従って、コンクリートの打設に先立って、この隙間はシール材及び/又はコーキング処理により塞ぐ。また隙間が大きくなる部分は鋼材プレートにより塞ぐこともある。 Since the steel-embedded panel is divided in the longitudinal direction and unitized in the width direction, gaps (joints due to division or the like) are generated between divided bodies or units. Therefore, prior to placing the concrete, this gap is closed with a sealing material and/or a caulking treatment. In addition, the portion where the gap becomes large may be closed with a steel material plate.

鉄骨埋込みパネルと桁方向の壁体との連結だけでなく、桁方向と直交する方向の壁体との連結も、矩形の開口部を閉塞するために必要である。第1及び第2部材11、12の取付側の壁体(山留壁2A、2B)と直交する壁体(又は杭体)と、頂版(その鉄骨延在方向に沿う側面)との連結について、つまり、壁体(又は杭体)と第1部材11、第2部材12及び第3部材13それぞれとの連結部については、壁体(杭体)がコンクリート壁又はRC杭(鋼材でない部分)であれば、下記(1)の方法により、鋼製壁又は鋼製杭であれば、下記(2)又は(3)の方法により行う。このとき、桁方向と直交する方向の壁体との取合い連結においても構造体としての応力伝達を期待する場合には(3)の方法が望ましく、(1)又は(2)の方法を選択する場合は、単に壁体と頂版との部材としての一体化のみを目的とする。 In order to close the rectangular opening, it is necessary to connect not only the steel embedded panel and the wall in the girder direction but also the wall in the direction perpendicular to the girder direction. Connection between the wall (or pile body) perpendicular to the wall on the mounting side of the first and second members 11 and 12 (earth retaining walls 2A and 2B) and the top plate (the side along the steel frame extending direction) Regarding the connection between the wall (or pile body) and the first member 11, the second member 12 and the third member 13, the wall (pile body) is a concrete wall or RC pile (non-steel part ), follow the method (1) below, and if it is a steel wall or steel pile, follow the method (2) or (3) below. At this time, if stress transmission as a structure is expected even in the interface connection with the wall in the direction perpendicular to the girder direction, method (3) is desirable, and method (1) or (2) is selected. In this case, the purpose is only to integrate the wall body and the top slab as a member.

(1)図7に示すように、桁方向と直交する方向の壁体(山留壁)2Cを構成するRC杭3Cに、後施工アンカー101を打ち、又はRC杭中に予め埋込んだインサートにより、コンクリート打設工程において打設したコンクリートと一体化させる。 (1) As shown in FIG. 7, post-installed anchors 101 are driven into RC piles 3C that constitute walls (retaining walls) 2C in the direction perpendicular to the girder direction, or inserts embedded in advance in RC piles By this, it is integrated with the placed concrete in the concrete placing process.

(2)図8に示すように、桁方向と直交する方向の壁体(山留壁)2Cを構成する鋼製杭3Cに、現場でスタッド102を溶接する、又は、図9に示すように、鋼製杭3Cに予めカプラー103Aを工場で溶接しておき、現場で鉄筋103Bをねじ込む。そして、これらをコンクリート打設工程において打設したコンクリートと一体化させる。 (2) As shown in FIG. 8, a stud 102 is welded on site to a steel pile 3C that constitutes a wall (earth retaining wall) 2C in the direction perpendicular to the girder direction, or as shown in FIG. , the coupler 103A is previously welded to the steel pile 3C at the factory, and the reinforcing bar 103B is screwed on site. Then, these are integrated with the placed concrete in the concrete placing process.

(3)図10に示すように、桁方向と直交する方向の壁体(山留壁)2Cを構成する鋼製杭3Cから、予め溶接等により鉄骨梁104を張り出しておき、鉄骨埋込みパネル側の小鋼材23Bとの間に連結材105を配置した上で、例えば添接板106等を介して連結する。そして、これらをコンクリート打設工程において打設したコンクリートと一体化させる。
尚、図7~図10に示されているように、桁方向と交差する方向の壁体と鉄骨埋込みパネルとの隙間には、コンクリートの打設に先立って、鋼材プレートなどからなる間詰め型枠110を配置する。
(3) As shown in FIG. 10, a steel beam 104 is protruded in advance by welding or the like from a steel pile 3C that constitutes a wall body (earth retaining wall) 2C in a direction orthogonal to the girder direction, and the steel frame embedded panel side After arranging the connecting member 105 between the small steel members 23B, they are connected via, for example, a splicing plate 106 or the like. Then, these are integrated with the placed concrete in the concrete placing step.
In addition, as shown in FIGS. 7 to 10, in the gap between the wall body and the steel frame embedded panel in the direction crossing the girder direction, an interstitial mold made of a steel plate or the like is placed prior to placing the concrete. A frame 110 is placed.

桁方向と直交する方向の壁体において、コンクリートが露出したコンクリート壁部分と、鋼材が露出した鋼製壁部分とがそれぞれ部分的に存在する場合においても、コンクリート壁部分においては後施工アンカー、インサート等のいずれかを、鋼製壁部分においてはスタッド、カプラー、鉄骨梁等のいずれかを、コンクリート打設工程の前に設置することが好ましい。このとき、突出させた後施工アンカー、インサート、スタッド、カプラー、鉄骨梁等は、第1部材11、第2部材12及び第3部材13それぞれの鉄骨22側の小鋼材23Bと、相互に連結されても、平面視及び立面視において重なり合うように設置されてもよい。 In the wall in the direction perpendicular to the girder direction, even if there are partial concrete wall portions with exposed concrete and steel wall portions with exposed steel material, post-installed anchors and inserts in the concrete wall portion etc., and in the case of steel wall portions, studs, couplers, steel beams, etc. are preferably installed before the concrete placing process. At this time, the projecting post-installed anchors, inserts, studs, couplers, steel beams, etc. are connected to the small steel members 23B on the steel frame 22 side of each of the first member 11, the second member 12, and the third member 13. Alternatively, they may be installed so as to overlap each other in plan view and elevation view.

本実施形態によれば、壁体側の第1及び第2部材11、12とこれらの間に設置される第3部材13は、板状のプレキャストコンクリート21と、プレキャストコンクリート21上に配置されて、プレキャストコンクリート21の長手方向に延在し、断面下部がプレキャストコンクリート21内に埋設され、断面上部がプレキャストコンクリート21の上方に露出する鉄骨22と、を含む、鉄骨埋込みパネルが、その長手方向に3つに分割されたものであり、第1部材11と第3部材13、及び、第2部材12と第3部材13は、互いの鉄骨同士で連結される。 According to this embodiment, the first and second members 11 and 12 on the wall side and the third member 13 installed therebetween are the plate-like precast concrete 21 and the precast concrete 21 are arranged on the precast concrete 21 to a steel frame 22 extending in the longitudinal direction of the precast concrete 21, the lower section of which is embedded in the precast concrete 21, and the upper section of which is exposed above the precast concrete 21; The first member 11 and the third member 13, and the second member 12 and the third member 13 are connected by mutual steel frames.

これにより、壁体側の第1部材11(又は第2部材12)を足場として、第1部材11(又は第2部材12)と第3部材13との連結作業を行うことができ、連結後は、第1~第3部材11~13を足場として、配筋等の作業を行うことができる。従って、立坑底版からの総足場や支保工等の大掛かりな仮設を無くすことができる。また、鉄骨埋込みパネルを用いることで、現場配筋量(及び配筋手間)を極力低減できる。 As a result, the first member 11 (or the second member 12) on the wall side can be used as a scaffold to connect the first member 11 (or the second member 12) and the third member 13. After the connection, , 1st to 3rd members 11 to 13 can be used as a scaffold for work such as bar arrangement. Therefore, large-scale temporary construction such as total scaffolding and shoring from the shaft bottom can be eliminated. In addition, by using the steel-embedded panel, it is possible to reduce the on-site rebar arrangement amount (and rebar arrangement labor) as much as possible.

また、本実施形態によれば、第1~第3部材11~13を埋設型枠として、これらの上にコンクリートを打設するが、鉄骨埋込みパネルを頂版9の型枠として利用することで、型枠の設置や解体撤去作業も不要となる。 Further, according to the present embodiment, the first to third members 11 to 13 are used as embedded forms, and concrete is placed on them. , installation of formwork and dismantling and removal work are also unnecessary.

また、本実施形態によれば、第3部材13は、更に、長手方向に3つに分割され、これらの分割体13-1~3も、互いの鉄骨同士で連結される。このような分割形態とすることで、工場から現場へ搬入可能で、かつ現場での取扱いが容易な寸法に収めることができる。言い換えれば、公道輸送の制約(道交法規制による長さや幅の制限)や、部材重量の制約(部材重量が重くなると過度なスペックの揚重機が必要となる)を受けないようにできる。また、第3部材13の分割数を増やすことで立坑開口部の大スパン化にも対応できる。但し、第3部材13の分割数を増やす場合にも、曲げモーメントが最大となる中央部での分割は避け、分割数を奇数(例えば5つ)とするのが望ましい。 Further, according to this embodiment, the third member 13 is further divided into three in the longitudinal direction, and these divided bodies 13-1 to 13-3 are also connected to each other by their respective steel frames. By adopting such a divided form, it is possible to carry the product from the factory to the site and to store the size in a size that facilitates handling at the site. In other words, it is possible to avoid restrictions on public road transportation (length and width restrictions imposed by road traffic laws) and member weight restrictions (heavy member weights require heavy lifters with excessive specifications). In addition, by increasing the number of divisions of the third member 13, it is possible to cope with an increase in the span of the shaft opening. However, even when the number of divisions of the third member 13 is increased, it is desirable to avoid division at the central portion where the bending moment is maximum, and to set the number of divisions to an odd number (eg, five).

また、本実施形態によれば、第3部材13が3つに分割された場合、壁体側の部材のプレキャストコンクリート21を足場として、壁体側から順に(いわゆる片押し施工で)連結作業を行うことができるため、立坑底版からの総足場や支保工等の大掛かりな仮設を必要としない。 Further, according to the present embodiment, when the third member 13 is divided into three pieces, the precast concrete 21 of the member on the wall side is used as a scaffold, and connection work is performed sequentially from the wall side (by so-called one-sided construction). Therefore, there is no need for large-scale temporary construction such as total scaffolding and shoring from the shaft bottom slab.

また、本実施形態によれば、鉄骨埋込みパネルにおける鉄骨22は、その延在方向と直交する方向に突出する小鋼材23を有し、隣り合う鉄骨22は互いの小鋼材23同士で接合される。
これにより、鉄骨埋込みパネルの鉄骨延在方向と直交する方向(配力方向)の強度を向上させることができる。また、本来配筋すべき配力方向の鉄筋断面積分を、小鋼材23の断面積で受け持つことで、配力方向においても現場配筋量(及び配筋手間)をより削減でき、省人化にも寄与できる。
Further, according to this embodiment, the steel frame 22 in the steel frame embedded panel has the small steel members 23 protruding in the direction perpendicular to the extending direction thereof, and the adjacent steel frames 22 are joined together by the small steel members 23. .
As a result, the strength of the steel-frame-embedded panel in the direction (power distribution direction) orthogonal to the steel-frame extending direction can be improved. In addition, by having the cross-sectional area of the small steel member 23 take charge of the cross-sectional area of the reinforcing bars in the direction in which the bars should be arranged, the on-site bar arrangement amount (and labor for bar arrangement) can be further reduced in the direction of bar distribution, resulting in labor savings. can also contribute to

また、本実施形態によれば、鉄骨埋込みパネルは、並列配置される複数本(本例では2本)の鉄骨ごとに、鉄骨の延在方向と直交する方向に分割されてユニット化されている。このようなユニット化により、総部材数を減らすことができ、工場から現場への搬入効率を上げ、クレーン等による部材架渡し時の揚重手間も減らすことができる。ユニット内で鉄骨22は内側小鋼材23Aを介して連結されており、これにより十分な強度を確保できる。 Further, according to the present embodiment, the steel-frame-embedded panel is divided into units in the direction orthogonal to the extending direction of the steel frames for each of the plurality of (two in this example) steel frames arranged in parallel. . By such unitization, the total number of members can be reduced, the efficiency of transporting the members from the factory to the site can be improved, and the labor required for lifting the members by a crane or the like can be reduced. In the unit, the steel frame 22 is connected via the inner small steel members 23A, thereby ensuring sufficient strength.

また、本実施形態によれば、鉄骨埋込みパネルにおける鉄骨22は、その延在方向と直交する方向に突出する小鋼材23を有し、架渡し工程において、隣り合うパネルユニットの外側小鋼材23B同士を連結する。すなわち、少なくとも第3部材13は、架渡し方向と直交する方向に分割された複数の鉄骨埋込みパネル(パネルユニット)を備え、その各鉄骨埋込みパネル(パネルユニット)における鉄骨22は、その延在方向と直交する方向に突出する小鋼材23を有し、架渡し工程において、隣り合う鉄骨埋込みパネルの外側小鋼材23B同士を連結する。これにより、パネルユニット同士を確実に連結して一体化することができる。 Further, according to this embodiment, the steel frame 22 in the steel-frame-embedded panel has the small steel members 23 protruding in the direction orthogonal to the extending direction thereof, and in the bridging process, the outer small steel members 23B of the adjacent panel units are separated from each other. concatenate That is, at least the third member 13 includes a plurality of steel-frame-embedded panels (panel units) divided in a direction orthogonal to the bridging direction, and the steel frame 22 in each steel-frame-embedded panel (panel unit) extends in the extending direction In the bridging process, the outer small steel members 23B of the adjacent steel-frame embedded panels are connected to each other. As a result, the panel units can be reliably connected and integrated.

次に本発明の他の実施形態について説明する。
上記実施形態では、第1部材11、第2部材12及び第3部材13の全てを鉄骨埋込みパネルにより構成した。
しかしながら、第1部材11及び第2部材12については、プレキャストコンクリート21を有しない、鉄骨のみの構成とし、第3部材13(13-1~13-3)のみを鉄骨埋込みパネルとすることもできる。
Another embodiment of the present invention will now be described.
In the above-described embodiment, the first member 11, the second member 12 and the third member 13 are all made up of steel-embedded panels.
However, the first member 11 and the second member 12 may be configured with only a steel frame without the precast concrete 21, and only the third member 13 (13-1 to 13-3) may be a steel-embedded panel. .

この場合も、壁体側に予め設置された第1部材11(又は第2部材12)を利用して、第1部材11(又は第2部材12)と第3部材13との連結作業を行うことで、頂版架設作業の効率化を図ることができる。また、第3部材13の連結後は、第3部材13を足場として、作業を行うことができる。これによっても、総足場や支保工等の大掛かりな仮設を無くすことができる。 In this case also, the first member 11 (or the second member 12) installed in advance on the wall side is used to perform the connection work between the first member 11 (or the second member 12) and the third member 13. Therefore, the efficiency of the top slab erection work can be improved. Further, after the third member 13 is connected, the work can be performed using the third member 13 as a foothold. This also eliminates large-scale temporary construction such as total scaffolding and shoring.

尚、図示の実施形態はあくまで本発明を概略的に例示するものであり、本発明は、説明した実施形態により直接的に示されるものに加え、特許請求の範囲内で当業者によりなされる各種の改良・変更を包含するものであることは言うまでもない。 It should be noted that the illustrated embodiment is only a schematic illustration of the present invention, and that the present invention, in addition to what is directly indicated by the described embodiment, can also be made by those skilled in the art within the scope of the claims. Needless to say, it includes the improvement and change of

本発明は、立坑(立坑躯体)の地上側開口部を閉塞することを実施例としたが、地中の対向する壁体の上端部を閉塞する頂版であれば、広く展開が可能である。 In the present invention, an embodiment of closing the opening on the ground side of a shaft (shaft skeleton) has been described, but a top slab that closes the upper end of an opposing wall in the ground can be widely used. .

1 立坑
2(2A、2B) 山留壁
3(3A、3B) 鋼製杭
4 底版
5 側壁
7 立坑躯体
8 シールドトンネル
9 頂版
11 第1部材
12 第2部材
13 第3部材
13-1 第3左端部材
13-2 第3右端部材
13-3 第3中央部材
14 コンクリート層
21 プレキャストコンクリート
22 鉄骨(H形鋼又はI形鋼)
23(23A、23B) 小鋼材
24 添接板
25 連結材
26 添接板
31~36 添接板
101 後施工アンカー
102 スタッド
103A カプラー
103B 鉄筋
104 鉄骨梁
105 連結材
106 添接板
110 間詰め型枠
1 Vertical shaft 2 (2A, 2B) Retaining wall 3 (3A, 3B) Steel pile 4 Bottom plate 5 Side wall 7 Vertical shaft skeleton 8 Shield tunnel 9 Top plate 11 First member 12 Second member 13 Third member 13-1 Third Left end member 13-2 Third right end member 13-3 Third central member 14 Concrete layer 21 Precast concrete 22 Steel frame (H-shaped steel or I-shaped steel)
23 (23A, 23B) Small steel material 24 Splicing plate 25 Connecting member 26 Splicing plate 31 to 36 Splicing plate 101 Post-installed anchor 102 Stud 103A Coupler 103B Reinforcement bar 104 Steel beam 105 Connecting member 106 Splicing plate 110 Spacing formwork

Claims (5)

立坑の地上側開口部を閉塞する頂版の構築方法であって、
立坑の構築時に、立坑の地上側開口部を挟んで対向する壁体のうち、一方の壁体内に設置される鋼製杭の上端部に、前記対向する方向に突出する第1部材を予め固定し、他方の壁体内に設置される鋼製杭の上端部に、前記対向する方向に突出する第2部材を予め固定する予備工程と、
頂版の構築時に、前記第1部材と前記第2部材との間に第3部材を設置してこれらを連結する架渡し工程と、
前記第3部材を埋設型枠として、この上にコンクリートを打設する工程と、
を含み、
前記第1部材、前記第2部材、及び前記第3部材は、各々が、板状のプレキャストコンクリートと、前記プレキャストコンクリート上に配置されて、前記プレキャストコンクリートの長手方向に延在し、断面下部が前記プレキャストコンクリート内に埋設され、断面上部が前記プレキャストコンクリートの上方に露出する鉄骨と、を含む、鉄骨埋込みパネルであり、
前記架渡し工程では、前記第1部材と前記第3部材、及び、前記第2部材と前記第3部材とを、互いの鉄骨同士で連結することを特徴とする、立坑の頂版構築方法。
A method for constructing a top slab for closing an opening on the ground side of a vertical shaft, comprising:
When constructing the shaft, the first member projecting in the opposite direction is fixed in advance to the upper end of the steel pile installed in one of the walls facing each other across the ground-side opening of the shaft. a preliminary step of preliminarily fixing the second member projecting in the opposite direction to the upper end of the steel pile installed in the other wall;
A bridging step of installing a third member between the first member and the second member and connecting them when constructing the top plate;
A step of placing concrete on the third member as an embedded formwork;
including
The first member , the second member , and the third member are each arranged on a plate-shaped precast concrete and the precast concrete, extending in the longitudinal direction of the precast concrete, and having a cross-sectional lower portion a steel frame embedded in the precast concrete, the upper part of the cross section of which is exposed above the precast concrete;
A shaft top slab constructing method, wherein, in the bridging step, the first member and the third member, and the second member and the third member are connected by mutual steel frames.
前記架渡し工程では、前記第1部材又は前記第2部材と前記第3部材とを、前記第1部材又は前記第2部材のプレキャストコンクリートを足場として、互いの鉄骨同士で連結することを特徴とする、請求項1に記載の立坑の頂版構築方法。 In the bridging step, the first member or the second member and the third member are connected by mutual steel frames using the precast concrete of the first member or the second member as a scaffold. The method for constructing the top slab of a vertical shaft according to claim 1 . 前記第3部材を構成する鉄骨埋込みパネルは、前記プレキャストコンクリート上に並列配置される複数の鉄骨を備えることを特徴とする、請求項1又は請求項2に記載の立坑の頂版構築方法。 3. The method for constructing the top slab of a vertical shaft according to claim 1, wherein the steel-frame-embedded panel constituting said third member comprises a plurality of steel frames arranged in parallel on said precast concrete. 前記第3部材は、平面視で架渡し方向と直交する方向に分割された複数の鉄骨埋込みパネルを備え、
該複数の鉄骨埋込みパネルの各々における鉄骨は、平面視で該鉄骨の延在方向と直交する方向に該鉄骨から突出する小鋼材を有し、
前記架渡し工程において、隣り合う鉄骨埋込みパネルの小鋼材同士を連結することを特徴とする、請求項3に記載の立坑の頂版構築方法。
The third member comprises a plurality of steel-frame-embedded panels divided in a direction orthogonal to the bridging direction in plan view ,
The steel frame in each of the plurality of steel-frame-embedded panels has a small steel member protruding from the steel frame in a direction orthogonal to the extending direction of the steel frame in a plan view ,
4. The method for constructing the top slab of a vertical shaft according to claim 3, wherein in said bridging step, small steel materials of adjacent steel-frame embedded panels are connected to each other.
立坑の地上側開口部を閉塞する頂版構造であって、
立坑の地上側開口部を挟んで対向する壁体のうち、一方の壁体内に設置される鋼製杭の上端部に固定されて、前記対向する方向に突出する第1部材と、
他方の壁体内に設置される鋼製杭の上端部に固定されて、前記対向する方向に突出する第2部材と、
前記第1部材と前記第2部材との間に設置されて、これらに連結される第3部材と、
前記第3部材を埋設型枠として、この上に打設されるコンクリート層と、
を含み、
前記第1部材、前記第2部材、及び前記第3部材は、各々が、板状のプレキャストコンクリートと、前記プレキャストコンクリート上に配置されて、前記プレキャストコンクリートの長手方向に延在し、断面下部が前記プレキャストコンクリート内に埋設され、断面上部が前記プレキャストコンクリートの上方に露出する鉄骨と、を含む、鉄骨埋込みパネルであり、
前記第1部材と前記第3部材、及び、前記第2部材と前記第3部材は、互いの鉄骨同士で連結されることを特徴とする、立坑の頂版構造。
A top slab structure that closes the ground side opening of the vertical shaft,
a first member fixed to the upper end of a steel pile installed in one of the walls facing each other across the ground-side opening of the vertical shaft and projecting in the facing direction;
a second member fixed to the upper end of a steel pile installed in the other wall and protruding in the opposite direction;
a third member disposed between and connected to the first member and the second member;
a concrete layer placed on the third member as an embedded formwork;
including
The first member , the second member , and the third member are respectively arranged on a plate-shaped precast concrete and on the precast concrete, extend in the longitudinal direction of the precast concrete, and extend in the lower section of the section. is embedded in the precast concrete, and a steel frame whose cross-sectional upper part is exposed above the precast concrete,
The top slab structure of a vertical shaft, wherein the first member and the third member, and the second member and the third member are connected by mutual steel frames.
JP2019114585A 2019-06-20 2019-06-20 Top slab construction method for shaft and top slab structure Active JP7213154B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019114585A JP7213154B2 (en) 2019-06-20 2019-06-20 Top slab construction method for shaft and top slab structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019114585A JP7213154B2 (en) 2019-06-20 2019-06-20 Top slab construction method for shaft and top slab structure

Publications (2)

Publication Number Publication Date
JP2021001453A JP2021001453A (en) 2021-01-07
JP7213154B2 true JP7213154B2 (en) 2023-01-26

Family

ID=73993941

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019114585A Active JP7213154B2 (en) 2019-06-20 2019-06-20 Top slab construction method for shaft and top slab structure

Country Status (1)

Country Link
JP (1) JP7213154B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113882432B (en) * 2021-09-01 2022-09-16 武汉市政工程设计研究院有限责任公司 Rapid construction method for assembled top plate of small-area deep shaft

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000291036A (en) 1999-04-08 2000-10-17 Kumagai Gumi Co Ltd Precast shaft
JP2001193382A (en) 2000-01-14 2001-07-17 Kawatetsu Kizai Kogyo Co Ltd Constructing method for shaft having wall with varied thickness
JP2014181531A (en) 2013-03-21 2014-09-29 Penta Ocean Construction Co Ltd Construction method for earth retaining structure, and earth retaining structure
JP2015074910A (en) 2013-10-08 2015-04-20 Jfe建材株式会社 Mounting structure and mounting method of canopy for vertical shaft

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000291036A (en) 1999-04-08 2000-10-17 Kumagai Gumi Co Ltd Precast shaft
JP2001193382A (en) 2000-01-14 2001-07-17 Kawatetsu Kizai Kogyo Co Ltd Constructing method for shaft having wall with varied thickness
JP2014181531A (en) 2013-03-21 2014-09-29 Penta Ocean Construction Co Ltd Construction method for earth retaining structure, and earth retaining structure
JP2015074910A (en) 2013-10-08 2015-04-20 Jfe建材株式会社 Mounting structure and mounting method of canopy for vertical shaft

Also Published As

Publication number Publication date
JP2021001453A (en) 2021-01-07

Similar Documents

Publication Publication Date Title
KR102208793B1 (en) Under ground structure using column wall and construction method thereof
US20130008125A1 (en) Construction method for new underground structure
JP2004285738A (en) Box girder bridge structure and method of constructing the same
KR101167511B1 (en) Underpass using precast concrete pile and method for constructing the same
KR100634726B1 (en) Slab construction structure of underground structure and slab and underground retaining wall construction method without frame rib
JP7213154B2 (en) Top slab construction method for shaft and top slab structure
JP5764245B2 (en) Construction method of underground structure and underground structure
JP4037187B2 (en) Underground structure construction method and underground structure
KR102298436B1 (en) Vertical concrete structure and method for constructing the same
KR20210004289A (en) Transfer Structure Construction Method Using U-shaped Steel Girder
KR200381303Y1 (en) Form system for joint between retaining wall and slab of basement floor
JP4477467B2 (en) Bridge structure and its replacement method
JP2004131988A (en) Precast block for pier / abutment, pier / abutment using the precast block, and method of construction of pier / abutment
JPS6137692Y2 (en)
KR102244029B1 (en) Rahmen bridge without abuttment and construction method thereof
KR100351135B1 (en) Method of constructing arch ring of steel framed reinforced concrete arch bridge
JP5828986B1 (en) PC formwork material and foundation construction method using the same
KR100456192B1 (en) Composition of precast concrete wall and precast concrete column for outdoor to sustain external force
KR20210119935A (en) Underground structure using strut and method construturing the same
JP5679849B2 (en) Underground structure
JP6827294B2 (en) Segment wall and tunnel lining
JP3319709B2 (en) Construction method of prestressed concrete steel beam
JPH08100464A (en) Connection structure and construction method of structure using it
JP2002332691A (en) Column and beam connection structure
JP7265343B2 (en) steel building

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20220124

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20221021

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20221025

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20221102

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20230110

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20230116

R150 Certificate of patent or registration of utility model

Ref document number: 7213154

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150