JP5008437B2 - System work support system - Google Patents

System work support system Download PDF

Info

Publication number
JP5008437B2
JP5008437B2 JP2007085924A JP2007085924A JP5008437B2 JP 5008437 B2 JP5008437 B2 JP 5008437B2 JP 2007085924 A JP2007085924 A JP 2007085924A JP 2007085924 A JP2007085924 A JP 2007085924A JP 5008437 B2 JP5008437 B2 JP 5008437B2
Authority
JP
Japan
Prior art keywords
work
work plan
power outage
server
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2007085924A
Other languages
Japanese (ja)
Other versions
JP2008245476A (en
Inventor
寛 小宇羅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chugoku Electric Power Co Inc
Original Assignee
Chugoku Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chugoku Electric Power Co Inc filed Critical Chugoku Electric Power Co Inc
Priority to JP2007085924A priority Critical patent/JP5008437B2/en
Publication of JP2008245476A publication Critical patent/JP2008245476A/en
Application granted granted Critical
Publication of JP5008437B2 publication Critical patent/JP5008437B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • Y04S10/60

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To solve the problem that a work plan on power interruption is only adjusted in a self-section since documents related to system work in an electric office are generated in respective sections under the control, that adjustment with the other section is not performed and that adjustment is performed by a person adjusting power interruption, who specially takes charge of adjustment of power interruption. <P>SOLUTION: In generation of the documents required for supervisory-controlling a power system, an input content between the documents is used by sharing a database. Thus, business of the respective sections controlling the documents is made efficient. <P>COPYRIGHT: (C)2009,JPO&amp;INPIT

Description

電力系統の監視制御に必要な帳票類の作成等において、データベースの共有化により各帳票間の入力内容を流用することで、業務の効率化を実現する系統作業支援システムに関する。   The present invention relates to a system work support system that realizes business efficiency by diverting input contents between forms by sharing a database in creation of forms necessary for power system monitoring control.

従来から、電気事業所の電力系統に関する停電要求書、確認票、操作票等の系統作業関連の帳票類は、それぞれの系統作業を所管する各課において、別々のシステムで作成されていた。   Conventionally, system work-related forms such as a power outage request form, confirmation sheet, operation sheet, etc. relating to the electric power system of an electric power plant have been created by separate systems in each section having jurisdiction over each system work.

そのため、各課が行う停電に関する作業計画でも、自課内での調整のみが行われ、作業計画の段階における他課との調整はなされておらず、それらの調整は専門に停電の調整を担当する停電調整者により行われていた。   Therefore, even in the work plan related to power outage performed by each section, only adjustment within the own section is performed, and there is no adjustment with other sections at the stage of the work plan, and those adjustments are specially responsible for power outage adjustment. It was done by the coordinator.

そのため、電力会社における作業停電調整を自動的に行うことにより調整者の負担を軽減する技術等が提案されている(例えば、特許文献1を参照)。
特開2003−111276号公報
Therefore, a technique for reducing the burden on the coordinator by automatically performing work blackout adjustment in an electric power company has been proposed (see, for example, Patent Document 1).
Japanese Patent Laid-Open No. 2003-111276

従来の方法では、停電要求内容や操作内容などの同じ情報を、異なる帳票作成者により複数の帳票に重複して入力する必要があり無駄が生じていた。   In the conventional method, the same information such as the power outage request content and operation content needs to be input to a plurality of forms by different form creators, resulting in waste.

また、帳票作成者により帳票の記載内容が統一されていないため、停電調整者の誤認や操作担当者の誤操作を招くおそれがあった。   In addition, since the contents of the form are not unified by the form creator, there is a risk of misrecognition of the power failure coordinator and erroneous operation of the person in charge of the operation.

さらに、停電にかかる作業計画の他課との調整は、すべて停電調整者により行われていたことから、停電調整者の業務量が膨大になるという問題もあった。   Furthermore, since all the adjustments with the other sections of the work plan related to the power outage were performed by the power outage coordinator, there was a problem that the amount of work of the power outage coordinator would be enormous.

本発明は、かかる事情に鑑みてなされたものであり、系統作業関連の帳票の作成を共通のデータベースを利用して行い、各帳票間における入力内容を流用することで、複数の帳票への重複した入力を回避し、帳票の記載内容の統一により停電調整者の誤認や操作担当者の誤操作を防止するとともに、停電調整者の業務の省力化を可能とする系統作業支援システムを提供することを目的とする。   The present invention has been made in view of such circumstances, and creates a system work-related form using a common database, and diverts the input contents between the forms to duplicate multiple forms. To provide a system work support system that avoids mistaken input by the power outage coordinator and misoperation of the person in charge of operation by unifying the contents described in the form and enables labor saving of the work of the power outage coordinator Objective.

本発明の系統作業支援システムは、将来を含む系統状況データを保持し、系統に関する作業を支援する系統作業支援システムであって、端末の表示部に表示した入力領域から停電を伴う作業計画データの入力を取得して、データベースに記憶する作業計画記憶手段と、前記記憶した作業計画データに基づき、作業計画の実施に必要な帳票を作成する帳票作成手段と、を備えることを特徴とする。   The system work support system of the present invention is a system work support system that holds system state data including the future, and supports work related to the system, and includes work plan data with a power failure from an input area displayed on a display unit of a terminal. It is characterized by comprising work plan storage means for acquiring input and storing it in a database, and form creation means for creating a form necessary for execution of the work plan based on the stored work plan data.

ここで「系統状況データ」とは、電力系統の充電、停電、Ry状態、機器の入切等の系統状況を表すデータを意味し、過去の系統状況のデータから将来系統までを連続的に保存する。「作業計画データ」とは、停電を伴う作業計画の担当者、連絡先、電気所、実施日時、対象範囲、作業内容等のデータを意味する。   Here, “system status data” means data representing the system status such as charging, power outage, Ry status, equipment on / off, etc., and continuously storing data from past system status to future system. To do. “Work plan data” means data such as a person in charge of a work plan involving a power outage, contact information, electric station, execution date / time, target range, work content, and the like.

なお、「作業計画の実施に必要な帳票」とは、系統計画に関する帳票、作業計画の実施の起案、関係者への告知、操作手順を定める帳票、作業の実施記録等の書類を意味する。ここでいう「帳票」とは、有形的に紙類等にプリントアウトされた帳票に限定することなく、電子書類等としてファイルに出力されたディジタルデータ等も含むものである。   The “form necessary for the execution of the work plan” means a form such as a form related to the system plan, drafting of the execution of the work plan, notification to related parties, a form for defining an operation procedure, and a work execution record. The “form” here is not limited to forms that are tangibly printed out on paper or the like, but also includes digital data output to a file as an electronic document or the like.

また、本発明の系統作業支援システムは、前記作業計画の実施に必要な帳票は、停電を伴う作業計画の実施を起案するための要求書と、関係者に停電を告知するための確認票と、停電の操作手順を定める操作票を含むことを特徴とする。   In the system work support system of the present invention, the form necessary for the execution of the work plan includes a request form for drafting the execution of the work plan accompanied by a power outage, and a confirmation form for notifying a related person of the power outage. In addition, it includes an operation sheet that defines an operation procedure for power failure.

ここで、帳票の名称については、上記に掲げた名称に限定するものではなく、目的を同じくするものはすべて含まれる。   Here, the names of the forms are not limited to the names listed above, and all forms having the same purpose are included.

さらに、前記作業計画記憶手段は、前記端末の表示部に、作業計画における停電期間の入力領域を表示して、入力された停電期間データを取得するステップと、前記取得した停電期間データに基づき、あらかじめ保持する該期間における系統状況データと、該停電期間の系統状況における作業計画の対象範囲の入力領域を、端末の表示部に表示するステップと、前記作業計画の対象範囲の入力領域に入力された対象範囲データを取得するステップと、前記取得した停電期間データと対象範囲データを、作業計画データとして記憶するステップとを、電子計算機に実行させることを特徴とする。   Further, the work plan storage means, on the display unit of the terminal, displaying the input area of the power outage period in the work plan, obtaining the input power outage period data, based on the acquired power outage period data, The system status data stored in advance in the period and the input area of the target range of the work plan in the system status of the power outage period are displayed on the display unit of the terminal, and input to the input area of the target range of the work plan. The step of acquiring the target range data and the step of storing the acquired power failure period data and target range data as work plan data are executed by an electronic computer.

すなわち、作業計画者による作業計画の停電期間の入力を先行させることにより、あらかじめ保持する将来の系統状況データから、作業計画の停電期間における系統状況データを表示して、作業計画者による該期間の系統状況データに基づいた具体的な作業計画を可能とする。   That is, by inputting the work plan power outage period of the work plan by the work planner in advance, the system status data in the power outage period of the work plan is displayed from the future system state data held in advance, and Enables specific work plans based on system status data.

また「対象範囲データ」とは、作業計画において作業の対象となる設備の情報や、系統における停電範囲の情報を意味する。   The “target range data” means information on equipment that is a target of work in the work plan and information on a power outage range in the system.

なお、前記帳票作成手段により作成される帳票は、前記停電期間における系統状況データを添付図とすることを特徴とする。   The form created by the form creating means is characterized in that the system status data in the power outage period is attached.

すなわち、作業計画の実施の起案に際して添付される図面、関係者に停電を告知する図面、停電の作業手順を定める図面等の帳票に添付される図面は、いずれも同一の図面データに基づいて作成される。   In other words, the drawings attached to the draft of work plan implementation, drawings notifying related parties of power outages, drawings attached to forms that determine work procedures for power outages, etc. are all created based on the same drawing data. Is done.

また、前記作業計画記憶手段により記憶する作業計画が、あらかじめ保持する他の作業計画と同調可能である場合に、関連付けて記憶する作業計画関連付け手段を備え、前記帳票作成手段は、関連付けて記憶された他の作業計画を参照して前記操作票を作成することを特徴とする。   In addition, when the work plan stored by the work plan storage means can be synchronized with another work plan held in advance, the work plan association means stores the work plan in association with each other, and the form creation means is stored in association with each other. The operation slip is created with reference to another work plan.

ここで「他の作業計画と同調可能」とは、すでに記憶されている他の作業計画と同期間に行われる作業計画であって、その性質上一連の作業として実施が可能な作業計画であることを意味する。   Here, “synchronizable with other work plans” is a work plan that is performed in synchronization with another work plan that is already stored, and is a work plan that can be implemented as a series of work due to its nature. Means that.

また「他の作業計画を参照して前記操作票を作成」とは、前記帳票作成手段による操作票の作成では、たとえば「CBを切ってLSを切る」といったように、すでにプログラムされたアルゴリズムにより操作票に記載される操作手順が作成されるが、他の作業計画における作業内容も加えたうえで、アルゴリズムに従って操作手順が作成されることを意味する。   “Create the operation slip with reference to another work plan” means that the creation of the operation slip by the form creation means is based on an already programmed algorithm such as “cut CB and cut LS”. The operation procedure described in the operation slip is created, which means that the operation procedure is created according to the algorithm after adding the work contents in other work plans.

さらに、本発明の系統作業支援システムは、前記作業計画記憶手段の機能と前記帳票作成手段の機能は、複数のサーバ装置が分散して保持し、前記帳票作成手段による帳票の作成は、作業計画の実施において夫々の工程を所管する部門の夫々のシステムサーバから実行され、前記系統状況データと前記作業計画データは、共通のデータベースサーバにおいて一元的に管理がなされ、前記夫々の部門のシステムサーバと、前記共通のデータベースサーバは、ネットワークを介したシステム連係により構成されることを特徴とする。   Furthermore, in the system work support system of the present invention, the function of the work plan storage unit and the function of the form creation unit are held in a distributed manner by a plurality of server devices, and the creation of the form by the form creation unit is a work plan. The system status data and the work plan data are centrally managed in a common database server, and are executed from the system servers of the respective departments. The common database server is configured by system linkage via a network.

すなわち、夫々の部門において運用されるシステムサーバと、共通のデータベースサーバとのシステム連係により、夫々のサーバに機能を分散させつつ系統作業支援システムを構成することができる。   That is, a system work support system can be configured while distributing functions to each server by system linkage between a system server operated in each department and a common database server.

なお、前記ネットワークを介したシステム連係には、設備の監視制御および停電の操作を行う制御所システムを含み、前記帳票作成手段により作成された操作票を、制御所システムに転送する操作票転送手段を備えることを特徴とする。   Note that the system linkage via the network includes a control center system that performs facility monitoring control and power failure operation, and an operation form transfer means that transfers the operation form created by the form creation means to the control center system. It is characterized by providing.

本発明によれば、系統計画者および各課の作業計画者が共通のデータベースを利用して作業計画を行うことで、作業時の系統把握や作業当日の他課の作業内容を参照できるため、停電調整業務の業務量を大幅に低減することができる。   According to the present invention, the system planner and the work planners of each section use a common database to perform work planning, so that the system at the time of work and the work contents of other sections on the work day can be referred to. The amount of adjustment work can be greatly reduced.

また、作業関連帳票の作成において、共通のデータベースを利用することから、帳票作成業務を簡単に行うことを可能にするほか、正確性も向上するため安全作業に繋げることができる。   In addition, since a common database is used in the creation of work-related forms, it is possible to easily perform the form creation work and to improve safety, leading to safe work.

以下、本発明の一実施形態を、図面を参照しながら説明する。
図1は、本実施形態の系統作業支援システムの概要を示したシステム構成図である。本実施形態の系統作業支援システムはシステム連係により構成されており、共通の系統データベース2と、系統データベースを管理する系統サーバ3、それぞれの系統作業に関する帳票作成を行う要求書サーバ4、確認票サーバ5、操作票サーバ6および複数の端末10を、LAN等のネットワーク7で接続する。
Hereinafter, an embodiment of the present invention will be described with reference to the drawings.
FIG. 1 is a system configuration diagram showing an overview of the system work support system of the present embodiment. The system work support system according to the present embodiment is configured by system linkage, and includes a common system database 2, a system server 3 that manages the system database, a request form server 4 that creates a form for each system work, and a confirmation form server. 5. The operation slip server 6 and a plurality of terminals 10 are connected by a network 7 such as a LAN.

なお、全社で一つのシステムを構成する場合には、社内のイントラネット等に接続してデータ伝送を行うことで、それぞれの帳票の承認処理を系統作業支援システム内で実施することが可能となる。   When a single system is configured throughout the company, it is possible to perform approval processing for each form in the system work support system by connecting to an in-house intranet or the like and performing data transmission.

さらに、操作票サーバ6は、F/W(ファイアウォール)等の専用回線8を介して、電気所の設備の監視制御を行う制御所システム9と接続する。   Further, the operation slip server 6 is connected to a control station system 9 that performs monitoring control of facilities in an electric station via a dedicated line 8 such as an F / W (firewall).

また、共通の系統データベース2は、二重化構成として手動によるバックアップも可能としつつ、定期的に自動バックアップを行うことが好ましい。さらに災害等を考慮してバックアップを地理的に離隔させることで、より信頼性を向上させることもできる。   Further, it is preferable that the common system database 2 performs automatic backup regularly while enabling manual backup as a duplex configuration. Furthermore, the reliability can be further improved by geographically separating backups in consideration of disasters and the like.

なお、本実施形態では、システム連係により系統作業支援システムを実現しているが、それぞれの機能を単一のコンピュータに搭載することで、単一のシステムによっても実現することができる。   In this embodiment, the system work support system is realized by system linkage, but can be realized by a single system by mounting each function in a single computer.

図2は、本実施形態の系統作業支援システム1の構成を示したシステム構成図である。
共通の系統データベース2には、系統作業に関する帳票である要求書の作成において、はじめに担当者から停電の作業計画が入力される。その後、系統作業に関する帳票である確認票、操作票がそれぞれの担当者によって作成される。
FIG. 2 is a system configuration diagram showing the configuration of the system work support system 1 of the present embodiment.
In the common system database 2, a power outage work plan is first input from the person in charge when creating a request form that is a form related to system work. Thereafter, a confirmation form and an operation form, which are forms relating to system work, are created by each person in charge.

その後の確認票または操作票の作成においては、帳票作成時に系統データベース2が保持する最新データをダウンロードすることで、作成される確認票または操作票において、自動的に最新の作業計画の内容を反映させることができる。   In the subsequent creation of the confirmation slip or operation slip, the latest data stored in the system database 2 is downloaded when the form is created, so that the contents of the latest work plan are automatically reflected in the created confirmation slip or operation slip. Can be made.

図3は、本実施形態の系統作業支援システム1の機能ブロック図である。
系統作業支援システム1は、管轄の電力系統の系統状況等を保存する系統データベース2、端末10等から系統データベースを変更する際等に使用する系統サーバ3、系統作業に関する作業計画者が、端末10等から要求書を作成する際等に使用する要求書サーバ4、作業計画者が端末10等から確認票を作成する際等に使用する確認票サーバ5、制御所員が端末10等から操作票を作成する際等に使用する操作票サーバ6等を、LAN等の通信ネットワーク7を介して接続することで構成される。
FIG. 3 is a functional block diagram of the system work support system 1 of the present embodiment.
The system work support system 1 includes a system database 2 that stores the system status and the like of the power system under its jurisdiction, a system server 3 that is used when changing the system database from the terminal 10, and the like. The request form server 4 used when creating a request form from the terminal, the confirmation form server 5 used when the work planner creates the confirmation form from the terminal 10 etc., and the control staff receives the operation form from the terminal 10 etc. It is configured by connecting an operation slip server 6 or the like used for creation or the like via a communication network 7 such as a LAN.

また、通信ネットワーク7は、作業計画者や制御所員が系統作業に関する操作を行う端末10等の複数の端末に接続される。   The communication network 7 is connected to a plurality of terminals such as the terminal 10 on which work planners and control staff perform operations related to system work.

なお、操作票サーバ6は、F/W(ファイアウォール)等の専用回線8により、制御所システム9等と接続される。   The operation slip server 6 is connected to the control center system 9 and the like by a dedicated line 8 such as F / W (firewall).

系統データベース2の記憶部23には、系統状況DB231に管轄系統の系統状況を保持する。さらに、作業計画DB232には作業計画のデータ等を保持する。   In the storage unit 23 of the system database 2, the system status of the jurisdiction system is held in the system status DB 231. Further, the work plan DB 232 holds work plan data and the like.

具体的には、系統状況DB231は、管轄系統の設備における充電、停電、Ry状態、機器の入切等の系統状況のデータ(初期値は毎日が基本系統)と、系統運用計画時や作業計画時、停電調整時等において、画面操作により系統の変更作業に用いる系統状況画面のデータとを保持する。ここで系統状況に関するデータは、現在の状況に限らず、過去から将来における系統を連続的に保持する(図4)。   Specifically, the system status DB 231 includes data on system status such as charging, power outage, Ry status, and on / off of equipment in the facilities of the jurisdiction system (initial value is the basic system every day), system operation planning time and work plan The system status screen data used for system change work is maintained by screen operation at the time of power failure adjustment. Here, the data on the system status is not limited to the current status, but continuously holds the system from the past to the future (FIG. 4).

系統状況のデータは、一意の要素番号に基づきノード・ブランチごとに保存される。ただし、ブランチの状態は充停電判定処理によりノードの状態から算出可能であるため、データベースに保存することを要しない。   System status data is stored for each node / branch based on a unique element number. However, since the state of the branch can be calculated from the state of the node by the charge / power failure determination process, it is not necessary to store it in the database.

系統状況のデータの要素番号は、系統状況画面のデータにおける設備のシンボル等と対応し、シンボル等の色や線種等を変更することにより、系統状況を系統図として視覚的に表示する。これにより、所定の期間における系統状況のデータにおいて、設備の状態を示すデータの変更を入力することで、該期間の系統図における設備の表示が自動的に書き換えられる。   The element number of the system status data corresponds to the equipment symbol or the like in the data on the system status screen, and the system status is visually displayed as a system diagram by changing the color or line type of the symbol or the like. Thereby, in the system status data in a predetermined period, by inputting a change in data indicating the state of the equipment, the equipment display in the system diagram in the period is automatically rewritten.

なお、複数の課から同時にアクセスされる場合も考えられることから、系統状況DB231のデータを、たとえば変電所ごとのように、いくつかのパーツに分割してアクセスを排他的に管理することが好ましい。   In addition, since the case where it is accessed simultaneously from several sections is also considered, it is preferable to divide the data of system status DB231 into several parts, for example like every substation, and to manage access exclusively. .

作業計画DB232は、停電の作業計画者が作業実施日の2か月程度前に作成する帳票である後述の要求書を単位として、停電日時、担当者、連絡先、操作要求の内容等の各要素を一元的に保持する(図5)。   The work plan DB 232 has a power outage date / time, a person in charge, contact information, contents of an operation request, etc. in units of a later-described request that is a form created by a power outage work planner about two months before the work implementation date. Keep elements centrally (FIG. 5).

系統サーバ3では、系統データベース2のアクセス管理を行い、系統データベース2を変更する業務は系統サーバ3を介して排他的に行うこととする。すなわち、停電の作業計画者や停電調整者は、端末10等から系統サーバ3を介して、系統データベース2の変更等を行う(作業計画記憶手段321)。   In the system server 3, the access management of the system database 2 is performed, and the task of changing the system database 2 is performed exclusively through the system server 3. That is, a power failure work planner or a power failure adjuster changes the system database 2 from the terminal 10 or the like via the system server 3 (work plan storage unit 321).

なお、系統データベース2の参照のみを行う確認票の作成や操作票の作成等の業務は、系統データベース2が保持するデータの内容を変更するものではなく、排他的に行う必要がないため、系統サーバ3以外の確認票サーバ5、操作票サーバ6等からも、直接アクセスすることができる。   It should be noted that operations such as creation of confirmation slips and operation slips that only refer to the system database 2 do not change the contents of data held in the system database 2 and do not need to be performed exclusively. Direct access is also possible from the confirmation slip server 5 and the operation slip server 6 other than the server 3.

他にも、系統計画者が基本系統を変更する場合においても、同様に系統サーバ3を介して行うこととする。図6、図7、図8には、端末10のモニタ(出力部105)に表示される系統計画の操作画面を例示する。   In addition, even when the system planner changes the basic system, it is performed through the system server 3 in the same manner. 6, 7, and 8 exemplify system plan operation screens displayed on the monitor (output unit 105) of the terminal 10.

系統計画者は、開始画面の「系統計画」の表示を選択することで(図6)、プルダウンメニューが表示されて、系統計画の対象となる日時、電気所等を選択することができる(図7)。これにより系統計画を行う将来の系統画面が表示される。系統画面には、系統における設備がシンボルで表示されて、系統計画者は表示されたシンボルの選択等を行うことで、容易に系統計画の立案を行うことができる(図8)。   The system planner selects the display of “system plan” on the start screen (FIG. 6), and a pull-down menu is displayed to select the date and time, the electric station, etc. that are the targets of the system plan (FIG. 6). 7). As a result, a future system screen for system planning is displayed. On the system screen, facilities in the system are displayed as symbols, and the system planner can easily make a system plan by selecting the displayed symbols and the like (FIG. 8).

なお、系統データベース2は、制御所システムが電力設備の監視制御を行うために保持するデータベースとは異なるものである。すなわち、制御所システムのデータベースではリアルタイムの系統状況を表示することを目的として、機器の容量等のデータを保持するのに対し、本システムの系統データベース2では機器の容量等のデータは保持せずに、将来系統を連続的に保存して、操作内容の検討や停電調整を行うために使用することを目的としている。   The grid database 2 is different from the database held by the control center system for monitoring and controlling the power equipment. That is, the database of the control center system holds data such as the capacity of the device for the purpose of displaying the real-time system status, whereas the system database 2 of this system does not hold the data such as the capacity of the device. In addition, the system is intended to be used for continuously storing the system in the future and examining the operation contents and adjusting the power failure.

ただし、系統データベース2における送電線・変電所等の表示形式は、制御所システムにおけるデータベースの制御画面と同一であって、システムの違いを気にすることなく系統計画等の操作を行うことができる。   However, the display format of power transmission lines, substations, etc. in the system database 2 is the same as the database control screen in the control station system, and operations such as system planning can be performed without worrying about differences in the system. .

系統データベース2の構築にあたっては、制御所システム9等が電力設備の監視制御に用いる先述のデータベースに基づいて行う。具体的には図9に示す。はじめに端末10等からLAN等の通信ネットワーク7を介して系統サーバ3にアクセスし、制御所システム9から設備のデータベースを読み込む(1)。   The construction of the system database 2 is performed based on the above-described database used by the control station system 9 and the like for monitoring and controlling the power equipment. Specifically, it is shown in FIG. First, the system server 3 is accessed from the terminal 10 or the like via the communication network 7 such as a LAN, and the equipment database is read from the control center system 9 (1).

次に系統データベース2の保守業務では、同様に制御所システム9から基となるデータを読み込む。これにより保守業務の効率化が図られ、かつ、制御所システム9が保持する現在データあるいは将来データの使用が可能となるため、正確な作業計画を行うことができる(2)。   Next, in the maintenance work of the system database 2, the base data is similarly read from the control center system 9. As a result, the efficiency of maintenance work is improved, and the current data or future data held by the control center system 9 can be used, so that an accurate work plan can be performed (2).

図10では、端末10等から系統データベース2の系統図を修正する場合のサーバの連係について説明する。はじめに端末10等は、系統サーバ3を介して系統データベース2の系統状況DB231から修正に用いる系統図を参照する(1)。修正された系統図は、系統サーバ3を介して系統データベース2に保存され、複数のサーバからの共用が可能となる(2)。   In FIG. 10, the linkage of servers when the system diagram of the system database 2 is corrected from the terminal 10 or the like will be described. First, the terminal 10 or the like refers to the system diagram used for correction from the system status DB 231 of the system database 2 via the system server 3 (1). The corrected system diagram is stored in the system database 2 via the system server 3 and can be shared by a plurality of servers (2).

要求書サーバ4では、作業計画者が端末10等から作業計画の実施を起案する要求書の作成を行う。要求書とは、停電の作業計画者が作業実施日の2か月程度前に作成する帳票であって、作業計画の実施を起案する書類である。具体的には、作業計画者が要求書に記載した停電要求日時、停電範囲、活近範囲等に基づいて、停電調整者が停電実施可否の判断や同一日実施可能作業等の調整を行う。   In the request document server 4, the work planner creates a request document for drafting the work plan from the terminal 10 or the like. The request form is a document prepared by the work planner for power outage about two months before the work execution date, and is a document for drafting the execution of the work plan. Specifically, based on the blackout request date and time, the blackout range, the near range, etc. described in the request by the work planner, the blackout coordinator determines whether or not the blackout can be performed and adjusts work that can be performed on the same day.

要求書サーバ4の中央演算処理部42には、作業計画記憶手段421、帳票作成手段423等を備える。   The central processing unit 42 of the request server 4 includes a work plan storage unit 421, a form creation unit 423, and the like.

本実施形態では、作業計画者が要求書に記載した内容は、作業計画記憶手段421により、系統サーバ3を介して系統データベース2の記憶部23が備える作業計画DB232に保存される。   In the present embodiment, the content described in the request by the work planner is saved by the work plan storage unit 421 in the work plan DB 232 provided in the storage unit 23 of the system database 2 via the system server 3.

図11、図12、図13には、端末10のモニタ(出力部105)に表示される要求書作成の操作画面を例示する。停電の作業計画者は、開始画面の「停電要求書作成」の表示を選択することで入力画面が表示される(図11)。   11, 12, and 13 exemplify operation screens for request creation that are displayed on the monitor (output unit 105) of the terminal 10. The power failure work planner selects the display of “Create power failure request” on the start screen to display the input screen (FIG. 11).

次に、入力画面において担当者、連絡先等の入力を行い、作業計画の対象となる日時(停電期間)、変電所・送電線等をプルダウンメニュー等で選択することにより、作業計画の停電期間における系統画面を表示する(図12)。系統画面には、系統における設備がシンボル等で表示されて、作業計画者は表示されたシンボル等の選択により、容易に作業計画の立案を行うことができる。   Next, input the person in charge, contact information, etc. on the input screen, and select the date and time (power outage period), substation / transmission line, etc. that will be the target of the work plan from the pull-down menu etc. The system screen is displayed (FIG. 12). The system screen displays the facilities in the system with symbols and the like, and the work planner can easily make a work plan by selecting the displayed symbols and the like.

系統画面の表示では初期値の状態が表示されて(図13)、作業計画者により停電の対象となる範囲および停電の目的とする作業対象の設備を選択する。図14では、送電課での作業計画における操作画面を例示する。なお、本実施形態の操作画面においては、作業対象となる設備を実線で囲み、停電の対象となる範囲を点線で示すこととしている。   In the system screen display, the state of the initial value is displayed (FIG. 13), and the work planner selects the range to be subjected to the power outage and the work target equipment for the purpose of the power outage. In FIG. 14, the operation screen in the work plan in a power transmission section is illustrated. In the operation screen of the present embodiment, the facility to be worked is surrounded by a solid line, and the range to be subjected to a power failure is indicated by a dotted line.

作成された作業計画は、端末10のプリンタ(出力部105)等による要求書のプリントアウトまたは要求書データの出力ファイルとして関係部署に送られて承認を受けることになる(帳票作成手段423)。   The created work plan is sent to the relevant department as a printout of a request form by the printer (output unit 105) or the like of the terminal 10 or as an output file of request form data for approval (form creation means 423).

あわせて作業計画記憶手段421により、端末10等の入力画面に入力された担当者、連絡先、変電所・送電線の名称、および、系統画面において選択入力がなされた作業対象の設備、停電範囲等のデータが系統データベース2の作業計画DB232に保存される。   In addition, by the work plan storage means 421, the person in charge, the contact information, the name of the substation / transmission line entered on the input screen of the terminal 10, etc., and the equipment to be selected and the power outage range selected on the system screen Are stored in the work plan DB 232 of the system database 2.

さらに図15では、発変課(発電・変電課)での作業計画における操作画面を例示する。発変課では、送電課とは異なる設備を作業対象とするため、別個に作業計画を行い、要求書の作成が必要となる。発変課の作業計画においては、すでに送電課により作成された要求書の作業計画を把握して調整を行ったうえで、発変課としての作業計画を行うことができる。   Further, FIG. 15 illustrates an operation screen in the work plan in the power generation / transformation section (power generation / transformation section). In the change-and-change section, equipment different from that in the power transmission section is the work target, so it is necessary to prepare a work plan separately and create a request. In the work plan of the dispatch / change section, the work plan as the dispatch / change section can be performed after grasping and adjusting the work plan of the request already created by the power transmission section.

本実施形態では、図14、図15が示す通り、作業計画にかかるすべての担当者が同一のデータベースにおいて作業計画を行うため、他課の作業を把握したうえで自課の作業計画を行うことから、従来において過大な負担が生じていた停電調整者の業務量の大幅な低減を見込むことができる。   In this embodiment, as shown in FIG. 14 and FIG. 15, all the persons in charge of the work plan perform the work plan in the same database. Therefore, it is possible to expect a significant reduction in the workload of the power failure coordinator who has conventionally caused an excessive burden.

なお、従来においては送電課、発変課、制御課等のそれぞれの作業計画担当課が、他課の作業の把握が不十分のままに要求書を発行していたため、作業計画後に停電調整者による再調整が必要な場合が生じていた。   In the past, each section of the work plan, such as the power transmission section, change section, control section, etc., issued a request form with insufficient understanding of the work of other sections. There was a case where readjustment by was necessary.

停電の作業計画の立案におけるサーバの連係については図16に示す。停電の作業計画においては、端末10等に繋がる要求書サーバ4から、系統サーバ3を介して系統データベース2の系統状況DB231が保持する対象の系統図を参照し、具体的な停電作業の計画を行う(1)(2)。   FIG. 16 shows server linkage in the planning of a power outage work plan. In the power outage work plan, from the request server 4 connected to the terminal 10 or the like, the system diagram DB 231 of the system database 2 via the system server 3 is referred to, and a specific power outage work plan is prepared. Perform (1) (2).

なお、要求書の作成に際して系統データベース2を変更する必要がない場合には、系統サーバ3を介することなく、要求書サーバ4から、直接、LAN等のネットワーク7を介して系統データベース2にアクセスを行い、系統データベース2が保持する系統図等のデータを、入力画面に自動的に反映させることができる。   In addition, when it is not necessary to change the system database 2 when creating the request, the system database 2 is accessed directly from the request server 4 via the network 7 such as a LAN without using the system server 3. It is possible to automatically reflect data such as a system diagram held in the system database 2 on the input screen.

端末10等で作成された作業計画の内容は、端末10等に繋がる要求書サーバ4から、系統サーバ3を介して系統データベース2の作業計画DB232に登録されて、他課の担当者による参照が可能となる。これにより、作業計画を行う課がお互いに他課の作業計画を参考にしながら、自課の作業を計画できる(3)。   The contents of the work plan created by the terminal 10 etc. are registered in the work plan DB 232 of the system database 2 from the request server 4 connected to the terminal 10 etc., and can be referred to by persons in charge in other sections. It becomes possible. Thereby, the section which performs work planning can plan the work of its own section while referring to the work plans of other sections (3).

なお、要求書サーバ4から、系統サーバ3を介して系統データベース2にアクセスすることになるが、端末10等において操作を行う作業担当者に意識させることなくシステム連係を行うように設定することもできる。   Note that the system database 2 is accessed from the request server 4 via the system server 3, but it is also possible to set the system linkage without making the operator in charge operating the terminal 10 or the like aware of it. it can.

また、要求書作成に伴う作業計画においてなされた系統図の変更は、原則的に系統状況DB231の将来系統のデータを変更するものではなく、これらの変更は、要求書の作業計画として作業計画DB232に保存され、作業計画時または後述の停電調整時等においてのみ、操作画面の表示に反映されることになる。その後の停電調整の決定により、系統状況DB231の将来系統のデータが変更される。   In addition, the changes in the system diagram made in the work plan accompanying the creation of the request do not in principle change the data of the future system in the system status DB 231, and these changes are the work plan DB 232 as the work plan of the request. And is reflected on the display of the operation screen only at the time of work planning or at the time of power failure adjustment described later. The future system data in the system status DB 231 is changed by the subsequent determination of power outage adjustment.

なお、停電調整者により同調可能であると判断された場合には、系統システム3が備える作業計画関連付け手段322により関連付けがなされて、系統データベース2に保存される。具体的には、系統データベース2の作業計画DB232において、同調可能な作業計画の相互のデータに相手の要求書のナンバーを保持させる。   If it is determined by the power failure coordinator that the synchronization is possible, the work plan association means 322 provided in the system system 3 associates them and saves them in the system database 2. Specifically, in the work plan DB 232 of the system database 2, the number of the other party's request is held in the mutual data of work plans that can be synchronized.

これにより、後述の操作票システム6の帳票作成手段623により、関連付けがなされた複数の要求書からそれぞれの作業計画データを抽出したうえで、一連の操作手順が記載された操作票の作成を行うことができる。   As a result, a form creation unit 623 of the operation form system 6 described later extracts each work plan data from a plurality of associated request forms, and creates an operation form describing a series of operation procedures. be able to.

図17には、要求書の作成時におけるサーバの連係について説明する。はじめに、作業計画者は端末10等から要求書サーバ4にアクセスし、作業計画記憶手段421により表示される入力画面において、要求書作成に必要な項目を入力する(1)。要求書サーバ4が取得した入力項目は、系統サーバ3を介して系統データベース2に保存される(2)(3)。   FIG. 17 illustrates server linkage when creating a request. First, the work planner accesses the request form server 4 from the terminal 10 or the like, and inputs items necessary for creating the request form on the input screen displayed by the work plan storage means 421 (1). The input items acquired by the request document server 4 are stored in the system database 2 via the system server 3 (2) (3).

停電調整者は、送電課、発変課における作業計画を記載した要求書の作成を受けて、最終的な作業計画に基づく停電を決定する(図18)。停電の決定におけるサーバの連係は、要求書作成と同じ流れにより行われる(図19(1)(2)(3))。また、同調可能作業の要求書の関連付けについても端末10等から行う。   The power failure coordinator receives the creation of a request document describing the work plans in the power transmission section and the change / change section, and determines a power failure based on the final work plan (FIG. 18). The server linkage in determining the power failure is performed in the same flow as the request creation (FIGS. 19 (1), (2), and (3)). In addition, the terminal 10 or the like is also associated with a request for work that can be tuned.

なお、停電調整者による作業は、系統データベース2の系統状況DB231が保持する作業計画の期間の系統図に基づいて行われるが、停電調整の段階では停電が決定しているわけではないので、通常においては作業計画を反映しない系統図が表示される。そのため、入力画面に「停電調整」のボタン等を備え、ボタンの押下等による入力を行うことで、作業計画を反映した系統図を表示するように設定することができる。   The work by the power failure coordinator is performed based on the system diagram of the work plan period held in the system status DB 231 of the system database 2, but the power outage is not determined at the power outage adjustment stage. In, a system diagram that does not reflect the work plan is displayed. Therefore, it is possible to set so that a system diagram reflecting the work plan is displayed by providing a button for “power failure adjustment” on the input screen and performing an input by pressing the button or the like.

ただし、作業計画の期間の系統図において、停電調整中か停電決定後かを、系統図のシンボル等の色や線種を変更することで、視覚的に容易に認識できるように設定することもできる。   However, in the system diagram of the work plan period, it can be set so that it can be easily recognized visually by changing the color and line type of symbols etc. it can.

さらに、作業計画の決定までは、作業計画者(要求書の作成者)により作業計画の内容の変更を行うことができる。一方、停電調整の決定後に停電内容が急遽変更となった場合等には、作業計画者であっても停電調整者の許可を得なければ変更することできないように設定されている。   Furthermore, the contents of the work plan can be changed by the work planner (creator of the request) until the work plan is determined. On the other hand, when the power outage content is suddenly changed after the power outage adjustment is decided, the work planner is set so that it cannot be changed without permission from the power outage adjuster.

次に、確認票サーバ5では、作業計画者が端末10等から作業計画の実施の確認を行う確認票の作成を行う。確認票とは、停電の作業計画者が作業実施日の2週間程度前に作成する帳票で、停電調整で決定した作業計画の内容を基に作成を行い、社内外の関係各所との作業内容の認識を一致させるための書類である。   Next, in the confirmation slip server 5, the work planner creates a confirmation slip for confirming the execution of the work plan from the terminal 10 or the like. A confirmation form is a form created by a work planner for power outages about two weeks before the work implementation date. The confirmation form is created based on the work plan determined by the power outage adjustment, and the work contents with the relevant parties inside and outside the company. It is a document for matching the recognition of

確認票サーバ5の中央演算処理部52には、作業計画記憶手段521、帳票作成手段523等を備える。   The central processing unit 52 of the confirmation slip server 5 includes a work plan storage unit 521, a form creation unit 523, and the like.

帳票作成手段523は、要求書サーバ4の作業計画記憶手段421により系統データベース2の作業計画DB232に保存された担当者、連絡先、変電所・送電線の名称、および、系統画面において選択入力がなされた作業対象の設備、停電範囲等のデータを流用して確認票を作成する。   The form creation means 523 has a selection input on the person in charge, the contact information, the name of the substation / transmission line, and the system screen saved in the work plan DB 232 of the system database 2 by the work plan storage means 421 of the request server 4. Create a confirmation slip by diverting the data of the equipment, power outage range, etc.

また、作業計画DB232に保存されたデータの変更等の登録を行う場合には、入力画面への入力を行うことで、端末10等が繋がる確認票サーバ5から、系統サーバ3を介して系統データベース2の作業計画DB232が保持する作業計画の内容を変更することができる(作業計画記憶手段521)。   In addition, when registering a change or the like of the data stored in the work plan DB 232, the system database is connected from the confirmation form server 5 to which the terminal 10 or the like is connected through the system server 3 by performing input to the input screen. The content of the work plan held in the second work plan DB 232 can be changed (work plan storage means 521).

具体的には、新規に登録される項目は、すでに登録されている要求書のデータに関連付けられた新しいデータとして登録される(作業計画関連付け手段322)。   Specifically, the newly registered item is registered as new data associated with the data of the request form already registered (work plan associating means 322).

図20、図21には、端末10のモニタ(出力部1015)に表示される確認票作成の操作画面を例示する。停電の作業計画者は、開始画面の「作業確認票作成」の表示を選択することで入力画面が表示される(図20)。   20 and 21 exemplify operation screens for creating a confirmation slip displayed on the monitor (output unit 1015) of the terminal 10. The power failure work planner selects the display of “Create work confirmation form” on the start screen to display the input screen (FIG. 20).

次に、入力画面において確認票作成の対象となる作業計画が記載された要求書を選択する。具体的には、日時、担当者、変電所の名称等の検索項目を選択して、検索項目に対応する検索内容のリストを表示する。さらに、検索内容を選択して検索を行うことで検索結果が一覧表示される。表示された要求書のリストから対象とする要求書の選択入力を行う(図21)。   Next, on the input screen, a request document in which a work plan for which a confirmation slip is to be created is described is selected. Specifically, a search item such as date / time, person in charge, and substation name is selected, and a list of search contents corresponding to the search item is displayed. Furthermore, a search result is displayed in a list by selecting a search content and performing a search. The target request is selected and input from the displayed request list (FIG. 21).

作業計画DB232は、要求書ごとにデータを保持するため、要求書を特定することで記載した作業計画の表示を行うことができる。表示された作業計画は、入力画面の「確認票作成」のボタンを押下することで、端末10のプリンタ(出力部105)によるプリントアウトまたは確認票データの出力ファイルとして関係部署に送られて確認を受けることができる(帳票作成手段523)。   Since the work plan DB 232 stores data for each request, the work plan described by specifying the request can be displayed. The displayed work plan is sent to the relevant department as a printout by the printer (output unit 105) of the terminal 10 or as an output file of confirmation form data by pressing the “Create confirmation form” button on the input screen. (Form creation means 523).

なお、確認票は社内外を含む関係各所に停電を告知して、停電の作業内容の認識を一致させるために用いられるが、あらかじめ関係各所の連絡先をデータベースに記憶させることで、入力画面の「確認票作成」のボタン押下と同時に、関係各所に確認票データを送信するように設定することもできる。   Confirmation slips are used to notify the relevant places, both inside and outside the company, of the power outage and to make the recognition of the work content of the power outage consistent. At the same time as pressing the “Create Confirmation Voucher” button, it is possible to send the confirmation voucher data to the relevant places.

これにより、確認票の作成者の業務を簡略化するとともに、さらに迅速に関係各所への停電の告知が可能となる。   This simplifies the work of the creator of the confirmation slip and also makes it possible to notify the relevant power outages more quickly.

確認票作成におけるサーバの連係については図22に示す。はじめに、作業計画者は端末10等から確認票サーバ5にアクセスし、表示される入力画面において確認票作成に必要な作業計画を検索する(1)。   FIG. 22 shows the server linkage in the creation of the confirmation slip. First, the work planner accesses the confirmation slip server 5 from the terminal 10 or the like, and searches for a work plan necessary for creating the confirmation slip on the displayed input screen (1).

この場合には、系統データベース2のデータを入力するものではないので、系統サーバ3を介することなく、確認票サーバ5から直接LAN等のネットワーク7を介して系統データベース2にアクセスを行い、作業計画DB232が保持するデータの内容が入力画面に自動的に反映される。   In this case, since the data of the system database 2 is not input, the system database 2 is accessed directly from the confirmation form server 5 via the network 7 such as the LAN without using the system server 3, and the work plan is obtained. The contents of data held in the DB 232 are automatically reflected on the input screen.

一方、確認票の作成に際して新規登録項目が生じた場合には、確認票サーバ5が取得した入力項目は、系統サーバ3を介して系統データベース2の作業計画DB232に、基となる要求書と関連付けて保存される(2)(3)(作業計画記憶手段521・作業計画関連付け手段322)。   On the other hand, when a new registration item is generated when the confirmation slip is created, the input item acquired by the confirmation slip server 5 is associated with the work request DB 232 of the system database 2 via the system server 3 with the request form as a basis. (2) (3) (work plan storage means 521 / work plan association means 322).

次に、操作票サーバ6では、制御所員が端末10等から停電の作業における操作手順を示す操作票の作成を行う。操作票とは、停電内容に沿った停電操作の内容を、停電日以前にあらかじめ作成する書類である。   Next, in the operation slip server 6, the control staff creates an operation slip indicating the operation procedure in the power failure work from the terminal 10 or the like. The operation slip is a document in which the content of the power outage operation according to the content of the power outage is created in advance before the date of the power outage.

操作票サーバ6の中央演算処理部62には、作業計画記憶手段621、帳票作成手段623、操作票転送手段624等を備える。   The central processing unit 62 of the operation form server 6 includes a work plan storage unit 621, a form creation unit 623, an operation form transfer unit 624, and the like.

帳票作成手段623は、要求書サーバ4の作業計画記憶手段421により系統データベース2の作業計画DB232に保存された担当者、連絡先、変電所・送電線の名称、および、系統画面において選択入力がなされた作業対象の設備、停電範囲等の作業計画のデータを流用して操作票を作成する。   The form creation means 623 has a selection input on the person in charge, contact information, the name of the substation / transmission line, and the system screen saved in the work plan DB 232 of the system database 2 by the work plan storage means 421 of the request server 4. The operation slip is created by diverting work plan data such as the equipment to be worked on and the range of power outage.

また、作成された操作手順等の操作票のデータは、端末10等と繋がる操作票サーバ6から、系統サーバ3を介して系統データベース2の作業計画DB232に保存される(作業計画記憶手段621)。   Further, the created operation sheet data such as operation procedures is stored in the work plan DB 232 of the system database 2 from the operation sheet server 6 connected to the terminal 10 or the like via the system server 3 (work plan storage unit 621). .

図23、図24には、端末10のモニタ(出力部1015)に表示される操作票作成の操作画面を例示する。制御所の停電操作担当者は、開始画面の「操作票作成」の表示を選択することで入力画面が表示される(図23)。   23 and 24 exemplify operation screens for creating an operation slip displayed on the monitor (output unit 1015) of the terminal 10. The person in charge of power outage operation at the control center selects the display of “Create operation sheet” on the start screen to display the input screen (FIG. 23).

次に、入力画面において操作票作成の対象となる作業計画を記載した要求書を選択する。具体的には、日時、変電所の名称等の検索項目を選択して要求書の検索を行うことで、検索結果が一覧表示される。検索項目はすべてを入力することは必要とせず、一部であっても検索を行うことができる。表示された要求書のリストから、対象とする要求書を選択する(図24)。   Next, on the input screen, a request document describing a work plan for which an operation form is to be created is selected. Specifically, a search result is displayed in a list by selecting search items such as date and time, substation name, etc. and searching for a request. It is not necessary to input all search items, and even a part of the search items can be searched. A target request is selected from the list of displayed requests (FIG. 24).

作業計画DB232は、要求書ごとにデータを保持するため、要求書を特定することで記載した作業計画の表示を行うことができる。表示された作業計画は、入力画面の「操作票作成」のボタンを押下することで、あらかじめプログラムされたアルゴリズムに従って操作票を作成し、端末10のプリンタ(出力部105)によるプリントアウトまたは操作票データの出力ファイルを作成することができる(帳票作成手段623)。また、作成された操作票は、制御所員により修正することもできる。   Since the work plan DB 232 stores data for each request, the work plan described by specifying the request can be displayed. The displayed work plan is created by pressing the “Create Operation Sheet” button on the input screen to create an operation sheet according to a pre-programmed algorithm and printed out by the printer (output unit 105) of the terminal 10 or the operation sheet. A data output file can be created (form creation means 623). In addition, the created operation slip can be corrected by the control staff.

また、操作票を作成していない要求書の一覧表示を行うボタンを備え、操作票の作成漏れを防止する機能も有する(図24)。これにより、定期的に一覧表示ボタンを押下して操作票を作成していない要求書の確認を行うことで、さらに安全に操作票の作成を行うことができる。   In addition, a button for displaying a list of request forms for which operation slips have not been created is provided, and a function for preventing omission of creation of operation slips is also provided (FIG. 24). Thus, by periodically pressing the list display button and confirming the request form for which no operation form has been created, the operation form can be created more safely.

なお、帳票作成手段623は作業計画DB232の検索を行い、作業計画を記載した要求書が、作業計画関連付け手段322により他の作業計画と関連付けが行われている場合に、対象となる他の作業計画を検知する。帳票作成手段623は、相互の作業計画を参照しながら操作手順を作成することができる。   The form creation means 623 searches the work plan DB 232, and when the request document describing the work plan is associated with another work plan by the work plan association means 322, the other work to be processed. Detect plans. The form creation means 623 can create an operation procedure while referring to the mutual work plan.

これにより、従来は、複数の要求書や確認票等の内容を確認して操作票を作成していたが、全課の作業が反映された操作手順が作成されることとなるため、これまで操作票の作成に必要であった煩雑な作業を回避することができる。   As a result, in the past, operation sheets were created by checking the contents of multiple requests and confirmation sheets, but since operation procedures reflecting the work of all sections were created, It is possible to avoid the complicated work required for creating the operation slip.

操作票作成におけるサーバの連係については図25に示す。はじめに、制御所の停電操作担当者は端末10等から操作票サーバ6にアクセスして、作業計画記憶手段621により表示される入力画面において、操作票作成に必要な作業計画を検索する(1)。   The server linkage in creating the operation slip is shown in FIG. First, the person in charge of power outage operation at the control station accesses the operation form server 6 from the terminal 10 or the like, and searches the input screen displayed by the work plan storage means 621 for a work plan necessary for creating the operation form (1). .

この場合には、系統データベース2のデータを入力するものではないので、系統サーバ3を介することなく、操作票サーバ6から、直接、LAN等のネットワーク7を介して系統データベース2にアクセスを行い、入力画面に自動的に反映させることができる。   In this case, since the data of the system database 2 is not input, the system database 2 is accessed directly from the operation form server 6 via the network 7 such as a LAN without using the system server 3. It can be automatically reflected in the input screen.

一方、作成された操作票のデータは、操作票サーバ6から系統サーバ3を介して系統データベース2の作業計画DB232に保存される(2)(3)。   On the other hand, the created operation slip data is stored in the work plan DB 232 of the system database 2 from the operation slip server 6 via the system server 3 (2) (3).

なお、操作票サーバ6は操作票転送手段624を備え、作業当日の自動操作を行う制御所システム9に、F/W(ファイアウォール)等の専用回線8を介して操作票を伝送することができる。具体的には、図24の入力画面において「転送」のボタンを押下することで行う。   The operation sheet server 6 includes operation sheet transfer means 624, and can transmit the operation sheet to the control center system 9 that performs automatic operation on the work day via the dedicated line 8 such as F / W (firewall). . Specifically, it is performed by pressing a “transfer” button on the input screen of FIG.

また、操作票の模擬実行や負荷検討等は制御所システム9で実施することとする。系統データベース2からの初期系統の読み込みは、F/W(ファイアウォール)等の専用回線8を介して接続する操作票サーバ6から可能であるが、誤動作等を考慮して制御卓が運用モード時(操作票作成モード時)のみ可能とする。これにより、制御所システムのセキュリティを担保することができる。   In addition, it is assumed that the control station system 9 performs the simulation execution of the operation slip and the load examination. Reading of the initial system from the system database 2 is possible from the operation sheet server 6 connected via the dedicated line 8 such as F / W (firewall), but the control console is in the operation mode in consideration of malfunction etc. ( Only in operation form creation mode). Thereby, the security of a control center system can be ensured.

さらに、操作票を技術課等へ転送する機能を付与する場合は、系統作業支援システム1ではなく、制御所システム9に付与して、シミュレーション等を終了した後に転送を行うこととする。   Furthermore, when the function of transferring the operation slip to the technical section or the like is given, it is given not to the system work support system 1 but to the control center system 9 and transferred after the simulation or the like is completed.

操作票の制御所システム9への転送におけるサーバの連係については図26に示す。はじめに系統データベース2の作業計画DB232に保存した操作票の検索を行い(1)(2)(3)、操作票サーバ6からF/W等の専用回線8を介して、制御所システム9に転送を行う(4)(5)。   The server linkage in the transfer of the operation slip to the control center system 9 is shown in FIG. First, the operation forms stored in the work plan DB 232 of the system database 2 are searched (1) (2) (3), and transferred from the operation form server 6 to the control center system 9 via the dedicated line 8 such as F / W. (4) and (5).

なお、帳票作成手段423、523、623等により作成される要求書、確認票、操作票等の帳票には、それぞれ図面の添付が必要となるが、これらの図面は系統状況DB231が保持する停電の作業計画期間の系統図を参照して作成される。   It should be noted that each of the forms such as the request form, the confirmation form, and the operation form created by the form creation means 423, 523, 623, etc. needs to be accompanied by a drawing, but these drawings are a power failure held by the system status DB 231. It is created with reference to the system diagram of the work plan period.

これにより、従来はそれぞれの担当者が手作業で操作票を作成していたために多くの時間を要していたが、効率的に操作票を作成することが可能となり、さらに各課が同一の図面において作業を行うため、停電調整者の誤認や、操作担当者の誤操作を回避することができる。   In the past, each person in charge created an operation slip manually, which required a lot of time. However, it is possible to create an operation slip efficiently, and each section has the same drawing. Therefore, it is possible to avoid misidentification of the power failure coordinator and misoperation of the operator.

以上の通り、本実施形態の系統作業支援システム1によれば、全課が共通の系統データベース2を利用して作業計画を行うため、他課の作業を把握しやすく、停電調整者の業務量の大幅な低減を図ることができるとともに、正確な停電範囲、作業内容等が把握できることから安全作業に寄与する。   As described above, according to the system work support system 1 of the present embodiment, since all sections use the common system database 2 to perform work planning, it is easy to grasp the work of other sections, and the workload of the power failure adjuster Can contribute to safety work because the power outage range and work contents can be grasped.

また、全課共通の系統データベース2には、系統計画、停電の作業計画等が反映されているため、停電説明業務時にも本システムを使用することができる。加えて、過去から将来までの系統が保存されているため、系統解析などの幅広い業務において有効に活用することができる。   In addition, the system database 2 common to all sections reflects a system plan, a work plan for power failure, and the like, so that this system can be used even during power failure explanation work. In addition, since the system from the past to the future is stored, it can be used effectively in a wide range of tasks such as system analysis.

さらに、システムにより帳票が作成されるため、ヒューマンエラーの確率が大幅に低減でき、事故発生確率を抑制することができる。また、停電要求が決定され次第に確認票が自動作成されるために作成時間を大幅に低減できる。加えて、操作票においても停電調整決定後に作成することができるため、停電作業日に対して十分な余裕をもって制御所員による操作手順の確認を行うことができる。   Furthermore, since a form is created by the system, the probability of human error can be greatly reduced, and the probability of an accident can be suppressed. Moreover, since the confirmation slip is automatically created as soon as a power failure request is determined, the creation time can be greatly reduced. In addition, since the operation slip can be created after determining the power failure adjustment, the operation procedure can be confirmed by the control staff with a sufficient margin for the power failure work day.

なお、タイピング入力ではなく選択式入力を主体とするため、入力内容が作業計画者により統一されていないという事態を回避して、作業計画の内容における関係者の共通認識の醸成が可能となる。   In addition, since the selection type input is used instead of the typing input, it is possible to avoid the situation where the input content is not unified by the work planner, and to foster the common recognition of the parties in the work plan content.

本実施形態の系統作業支援システムの概要を示したシステム概要図である。It is a system outline figure showing an outline of a system work support system of this embodiment. 本実施形態の系統作業支援システムの構成を示したシステム構成図である。It is a system configuration figure showing the composition of the system work support system of this embodiment. 本実施形態の系統作業支援システム1の機能ブロック図である。It is a functional block diagram of the system work support system 1 of this embodiment. 図3の系統データベース2の記憶部23にある系統状況DB231の説明図である。It is explanatory drawing of the system | strain condition DB231 in the memory | storage part 23 of the system | strain database 2 of FIG. 図3の系統データベース2の記憶部23にある作業計画DB232の説明図である。It is explanatory drawing of the work plan DB232 in the memory | storage part 23 of the system | strain database 2 of FIG. 端末10等に表示される本実施形態の系統作業支援システム1の開始画面において、系統計画の選択を表した図である。It is a figure showing selection of a system plan in the start screen of system work support system 1 of this embodiment displayed on terminal 10 grade. 端末10等に表示される入力画面において、対象とする系統計画の選択方法を表した図である。It is a figure showing the selection method of the system plan made into object in the input screen displayed on the terminal 10 grade | etc.,. 系統計画を行う系統画面を、端末10等に表示した図である。It is the figure which displayed the system | strain screen which performs system | strain planning on the terminal 10 grade | etc.,. 系統データベース2を構築する際の、サーバ連係の一例を示した図である。It is the figure which showed an example of the server cooperation at the time of constructing the system | strain database 2. FIG. 端末10等において系統計画を行う際の、サーバ連係の一例を示した図である。It is the figure which showed an example of server cooperation at the time of performing a system plan in the terminal 10 grade | etc.,. 端末10等に表示される本実施形態の系統作業支援システム1の開始画面において、停電要求書作成の選択を表した図である。It is a figure showing selection of power failure request creation on the start screen of system work support system 1 of this embodiment displayed on terminal 10 grade. 端末10等に表示される要求書の入力画面において、作業計画の入力方法を表した図である。It is a figure showing the input method of a work plan in the input screen of the request document displayed on the terminal 10 grade | etc.,. 要求書作成に際して作業計画を行う系統画面の初期値を、端末10等に表示した図である。It is the figure which displayed on the terminal 10 grade | etc., The initial value of the system | strain screen which performs a work plan at the time of request document preparation. 系統画面において、送電課により作業計画を行う例を表した図である。It is a figure showing the example which performs a work plan by the power transmission section in a system | strain screen. 系統画面において、発変課(発電・変電課)により作業計画を行う例を表した図である。It is a figure showing the example which performs a work plan by a dispatch section (power generation / transformation section) in a system | strain screen. 要求書作成において作業計画を行う際の、サーバ連係の一例を示した図である。It is the figure which showed an example of server cooperation at the time of performing a work plan in request creation. 要求書作成を行う際の、サーバ連係の一例を示した図である。It is the figure which showed an example of server cooperation at the time of making a request document. 系統画面において、停電決定を行う例を示した図である。It is the figure which showed the example which performs a power failure determination in a system | strain screen. 要求書作成において停電決定を行う際の、サーバ連係の一例を示した図である。It is the figure which showed an example of server cooperation at the time of making a power failure determination in request creation. 本実施形態の系統作業支援システム1の開始画面において、作業確認票作成の選択を表した図である。It is a figure showing selection of preparation of work check slip in the start screen of system work support system 1 of this embodiment. 確認票の入力画面において、対象要求書の検索方法を表した図である。It is a figure showing the search method of an object request document in the input screen of a confirmation vote. 確認票作成を行う際の、サーバ連係の一例を示した図である。It is the figure which showed an example of server cooperation at the time of performing confirmation voucher creation. 本実施形態の系統作業支援システム1の開始画面において、操作票作成の選択を表した図である。It is a figure showing selection of operation slip creation in the start screen of the system work support system 1 of this embodiment. 操作票の入力画面において、対象要求書の検索方法を表した図である。It is a figure showing the search method of a target request document in the input screen of an operation slip. 操作票作成を行う際の、サーバ連係の一例を示した図である。It is the figure which showed an example of server cooperation at the time of performing operation slip creation. 操作票転送を行う際の、サーバ連係の一例を示した図である。It is the figure which showed an example of server cooperation at the time of performing operation slip transfer.

符号の説明Explanation of symbols

1 系統作業支援システム
2 系統データベース
3 系統サーバ
4 要求書サーバ
5 確認票サーバ
6 操作票サーバ
7 通信ネットワーク
8 専用回線
9 制御所システム
10 端末
21、31、41、51、61、91、101 送受信部
22、32、42、52、62、92、102 中央演算処理部
23、33、43、53、63、93、103 記憶部
24、34、44、54、64、94、104 入力部
25、35、45、55、65、95、105 出力部
231 系統状況DB
232 作業計画DB
321、421、521、621 作業計画記憶手段
322 作業計画関連付け手段
423、523、623 帳票作成手段
624 操作票転送手段
1 System Work Support System 2 System Database 3 System Server 4 Request Form Server 5 Confirmation Form Server 6 Operation Form Server 7 Communication Network 8 Dedicated Line 9 Control Center System 10 Terminals 21, 31, 41, 51, 61, 91, 101 Transmission / Reception Unit 22, 32, 42, 52, 62, 92, 102 Central processing units 23, 33, 43, 53, 63, 93, 103 Storage units 24, 34, 44, 54, 64, 94, 104 Input units 25, 35 , 45, 55, 65, 95, 105 Output unit 231 System status DB
232 Work plan DB
321, 421, 521, 621 Work plan storage unit 322 Work plan association unit 423, 523, 623 Form creation unit 624 Operation form transfer unit

Claims (5)

共通のデータベースサーバと、夫々の部門のシステムサーバと、作業担当者の端末と、を、ネットワークを介して接続し、系統に関する作業を支援する系統作業支援システムであって、
前記共通のデータベースサーバには、
将来を含む系統状況データと、
停電を伴う作業計画の停電期間と、該作業計画における停電の対象範囲と、を含む作業計画データと、
を、保持し、
前記夫々の部門のシステムサーバには、
前記端末の表示部に、作業計画における停電期間の入力領域を表示して、入力された停電期間のデータを取得するステップと、
前記取得した停電期間に基づき、前記端末の表示部に、前記共通のデータベースサーバが保持する該期間における系統状況データと、該系統状況データを構成する設備の選択入力領域を表示するステップと、
前記設備の選択入力領域に入力された対象範囲のデータを取得するステップと、
前記取得した停電期間のデータと対象範囲のデータとを、前記共通のデータベースサーバの作業計画データに記憶するステップと、
を、電子計算機に実行させる作業計画記憶手段と、
前記記憶した作業計画データに基づき、作業計画の実施に必要な帳票を作成する帳票作成手段と、
、保持し、
前記作業計画記憶手段により、前記端末の表示部に表示される前記系統状況データは、前記共通のデータベースサーバに記憶された作業計画データの内容が都度反映させることを特徴とする系統作業支援システム。
A system work support system that connects a common database server, a system server of each department, and a terminal of a worker in charge through a network to support work related to the system,
The common database server includes
System status data including the future ,
Work plan data including a power outage period of a work plan involving a power outage and a target range of the power outage in the work plan;
Hold
The system servers of the respective departments include
On the display unit of the terminal, displaying the input area of the power outage period in the work plan, and obtaining the data of the input power outage period ;
Based on the acquired power outage period, displaying on the display unit of the terminal the system status data in the period held by the common database server, and the selection input area of the equipment constituting the system status data;
Obtaining data of a target range input to the selection input area of the equipment ;
Storing the acquired power outage period data and target range data in the work plan data of the common database server ;
A work plan storage means for causing an electronic computer to execute ,
Based on the stored work plan data, a form creation means for creating a form necessary for carrying out the work plan,
Hold
By the work program storage means, the system status data displayed on a display unit of the terminal, said common line work support system characterized in Rukoto contents of work plan data stored in the database server to reflect each time .
前記作業計画の実施に必要な帳票は、停電を伴う作業計画の実施を起案するための要求書と、関係者に停電を告知するための確認票と、停電の操作手順を定める操作票を含むことを特徴とする請求項1記載の系統作業支援システム。   The form necessary for the execution of the work plan includes a request form for drafting the execution of the work plan involving a power outage, a confirmation form for notifying the parties of the power outage, and an operation form for determining the operation procedure of the power outage. The system work support system according to claim 1. 前記帳票作成手段により作成される帳票は、前記停電期間における系統状況データを添付図とすることを特徴とする請求項1又は2記載の系統作業支援システム。 The system work support system according to claim 1 or 2, wherein the form created by the form creation means includes system status data in the power outage period as an attached diagram. 前記作業計画記憶手段により記憶する作業計画が、あらかじめ保持する他の作業計画と同調可能である場合に、関連付けて記憶する作業計画関連付け手段を備え、
前記帳票作成手段は、関連付けて記憶された他の作業計画を参照して前記操作票を作成することを特徴とする請求項2乃至のいずれか一に記載の系統作業支援システム。
When the work plan stored by the work plan storage means can be synchronized with other work plans held in advance, the work plan storage means includes work plan association means for storing the work plans in association with each other.
The system work support system according to any one of claims 2 to 3 , wherein the form creation unit creates the operation form with reference to another work plan stored in association with each other.
前記ネットワークを介して接続するそれぞれの部門のシステムサーバには、設備の監視制御および停電の操作を行う制御所システムのサーバを含み、
前記帳票作成手段により作成された操作票を、制御所システムのサーバに転送する操作票転送手段を備えることを特徴とする請求項2乃至4のいずれか一に記載の系統作業支援システム。
The system server of each department connected via the network includes a server of a control center system that performs facility monitoring control and power failure operation,
The system work support system according to any one of claims 2 to 4, further comprising operation form transfer means for transferring the operation form created by the form creation means to a server of a control center system.
JP2007085924A 2007-03-28 2007-03-28 System work support system Expired - Fee Related JP5008437B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007085924A JP5008437B2 (en) 2007-03-28 2007-03-28 System work support system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007085924A JP5008437B2 (en) 2007-03-28 2007-03-28 System work support system

Publications (2)

Publication Number Publication Date
JP2008245476A JP2008245476A (en) 2008-10-09
JP5008437B2 true JP5008437B2 (en) 2012-08-22

Family

ID=39916134

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007085924A Expired - Fee Related JP5008437B2 (en) 2007-03-28 2007-03-28 System work support system

Country Status (1)

Country Link
JP (1) JP5008437B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5431380B2 (en) * 2011-02-04 2014-03-05 中国電力株式会社 Power system supervisory control system
JP6604076B2 (en) * 2015-07-29 2019-11-13 東京電力ホールディングス株式会社 Supervisory control system
JP7429217B2 (en) * 2021-11-29 2024-02-07 株式会社バルカー Report management methods, systems, programs, and devices

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003111276A (en) * 2001-09-28 2003-04-11 Kansai Electric Power Co Inc:The Adjustment system for service interruption during working
JP4253146B2 (en) * 2001-10-31 2009-04-08 株式会社東芝 Power plant management system and management method
JP2003259550A (en) * 2002-03-01 2003-09-12 Mitsubishi Electric Corp Adjusting device for power interruption during work
JP4854210B2 (en) * 2005-03-24 2012-01-18 中国電力株式会社 Thermal power generation operation management system

Also Published As

Publication number Publication date
JP2008245476A (en) 2008-10-09

Similar Documents

Publication Publication Date Title
US10170018B2 (en) Cloud based server to support facility operations management
CN101216926B (en) An urban emergency commanding operation system and the corresponding implementation method
CN110706800A (en) Automatic management method and device for equipment maintenance, computer equipment and storage medium
US20120290986A1 (en) Management Of Corporate Entities
CN103700026A (en) Free node transfer processing method for intelligent power grid dispatching
CN111192673A (en) Efficient management method and device for equipment maintenance, computer equipment and storage medium
JP5008437B2 (en) System work support system
JP2008225805A (en) Monitoring control system and position switching method for monitoring control system
KR20150126276A (en) Apparatus and method for safety diagnosis report
CN110689246A (en) Medical equipment maintenance management method and device, computer equipment and storage medium
JP2002063324A (en) Apparatus and method for centralized operation processing
JP6675044B2 (en) Monitoring and control system
JP2004054716A (en) Work management method and display method for work
JP6675043B2 (en) Monitoring and control system
JP5498838B2 (en) Attendance information management device
JPH08147356A (en) Maintenance management device
CN110852578A (en) Mobile operation system for maintenance management
JP4597076B2 (en) Power system blackout work plan setting method and system
JP5431380B2 (en) Power system supervisory control system
JP5145838B2 (en) Organization change information management system, organization change information management method, and organization change information management program
JP6988791B2 (en) Information processing equipment and information processing method
JP5578647B2 (en) Cloud system and cloud system control method
JP2005267011A (en) Data transmission/reception method
CN117544538A (en) Automatic detection method for IT cloud resource pool equipment
CN114204681A (en) Electric power equipment management method based on edge calculation, local management device and system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20100126

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100310

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110520

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110628

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110826

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120522

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120529

R150 Certificate of patent or registration of utility model

Ref document number: 5008437

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150608

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150608

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees