JP4231053B2 - Jig for assembling splice plate for connecting upper flange of H-shaped steel frame and assembling method using the same - Google Patents
Jig for assembling splice plate for connecting upper flange of H-shaped steel frame and assembling method using the same Download PDFInfo
- Publication number
- JP4231053B2 JP4231053B2 JP2006025041A JP2006025041A JP4231053B2 JP 4231053 B2 JP4231053 B2 JP 4231053B2 JP 2006025041 A JP2006025041 A JP 2006025041A JP 2006025041 A JP2006025041 A JP 2006025041A JP 4231053 B2 JP4231053 B2 JP 4231053B2
- Authority
- JP
- Japan
- Prior art keywords
- splice plate
- upper flange
- support piece
- jig
- flange
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Joining Of Building Structures In Genera (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
この発明は、フランジを水平に配置して置かれたH型鉄骨の上フランジ上の所定位置に外スプライス板を載せ置いた後、上フランジの下面に、内スプライス板を組み付ける作業において、当該H型鉄骨の上フランジに装着して用いられるスプライス板の組み付け用治具と、これを用いたスプライス板の組み付け方法に関する。 In the present invention, after the outer splice plate is placed at a predetermined position on the upper flange of the H-shaped steel frame in which the flange is horizontally disposed, the H splice plate is assembled to the lower surface of the upper flange. The present invention relates to a jig for assembling a splice plate used by being attached to an upper flange of a mold steel frame, and a method for assembling a splice plate using the jig.
H型鉄骨の端部同士をボルト接合する場合、両鉄骨の上フランジ間を接続するために、上フランジの上面に外スプライス板が、また上フランジの下面に左右一対の内スプライス板がそれぞれ添わされる。これらの上フランジ接続用スプライス板と上フランジとのボルト締め作業は、建設現場において行われるが、鉄骨は、予め加工場においてスプライス板が仮組みされた状態で、建設現場に搬入される。
加工場におけるH型鉄骨に対する上フランジ接続用スプライス板の仮組作業は以下のように行われる。まず、フランジを水平に配置して置かれたH型鉄骨の上フランジ上の所定位置に外スプライス板を載せ置く。鉄骨が大型であると、外スプライス板は、大重量である(例えば27kg)から一人で作業する場合には、クレーンで吊り下ろす。次いで、上フランジの下面に、内スプライス板(例えば12kg)を配置し、ボルト挿通孔を会わせて仮止め用ボルト・ナットで締め付ける。
この作業を一人で容易に行えるようにした内スプライス板(バンド)の仮組具が特許文献1(図7参照)に記載されている。この仮組具は、係止手段とバンド支承部とからなる。係止手段は、正面コの字形の部材であり、上フランジと、その上に載せ置かれた外スプライス板とに覆いかぶさるように装着される。係止手段の両端部に、バンド支承部を具える。仮組作業は以下のように行われる。まず上フランジ上に外スプライス板をボルト孔の位置を合わせて載置し、次に仮組具を鉄骨端側から長手方向に挿入するようにして係止する。次いでバンド支承部上に内スプライス板(バンド)を載置してボルトの位置決めを行い、ボルト・ナットを締め付ける。
Temporary assembly work of the splice plate for connecting the upper flange to the H-shaped steel frame at the processing site is performed as follows. First, the outer splice plate is placed on a predetermined position on the upper flange of the H-shaped steel frame placed with the flange disposed horizontally. If the steel frame is large, the outer splice plate is heavy (for example, 27 kg), so when working alone, it is suspended by a crane. Next, an inner splice plate (for example, 12 kg) is disposed on the lower surface of the upper flange, and the bolt insertion hole is met and tightened with a bolt and nut for temporary fixing.
Patent Document 1 (see FIG. 7) discloses a temporary assembly of an inner splice plate (band) that enables this work to be easily performed by one person. This temporary assembly includes locking means and a band support portion. The locking means is a front U-shaped member and is mounted so as to cover the upper flange and the outer splice plate placed thereon. Band support portions are provided at both ends of the locking means. Temporary assembly work is performed as follows. First, the outer splice plate is placed on the upper flange with the position of the bolt hole aligned, and then the temporary assembly is locked so as to be inserted in the longitudinal direction from the end of the steel frame. Next, the inner splice plate (band) is placed on the band support portion, the bolt is positioned, and the bolt and nut are tightened.
上記従来の仮組具は、鉄骨を跨ぐように装着されるものであるから、比較的大型で大重量のものとならざるを得ないため、作業性が悪いという問題点がある。特に、先に上フランジ上に載置される外スプライス板は、その約半分の長さが、上フランジの端部から庇状に張り出すので、仮組具は、張り出した外スプライス板の先端位置から長手方向に挿入するなどして上フランジの上に装着しなければならず、操作が容易でない。その上、外スプライス板の重心が上フランジの外側にあるので、定位置では外スプライス板が上フランジから落下してしまうから、少なくとも仮組具を装着するまでの間、外スプライス板を上フランジ上に保持しなければならない。この間の作業を一人で行うのは困難である。
したがって、この発明は、鉄骨に対し接続用の内スプライス板を仮組するにあたって、一連の作業を一人で容易かつ安全に行うことができる治具と、これを用いた内スプライス板の新規な組み付け方法を提供することを課題としている。
Since the above-mentioned conventional temporary assembly is mounted so as to straddle the steel frame, it must be relatively large and heavy, and there is a problem that workability is poor. In particular, the outer splice plate that is first placed on the upper flange is about half the length of the outer splice plate that projects from the end of the upper flange. It must be mounted on the upper flange by inserting it in the longitudinal direction from the position, and the operation is not easy. In addition, since the center of gravity of the outer splice plate is outside the upper flange, the outer splice plate falls from the upper flange at a fixed position, so at least the temporary splice plate is attached to the upper flange until the temporary assembly is mounted. Must be held on. It is difficult to work alone during this time.
Accordingly, the present invention provides a jig that can easily and safely perform a series of operations alone when temporarily assembling an inner splice plate for connection to a steel frame, and a novel assembly of an inner splice plate using the jig. The challenge is to provide a method.
この出願の発明においては、上記課題を解決するため、外スプライス板24を載せた上フランジ22の縁部を受け入れる凹部4を備えた断面略コ字状の本体2と、凹部4内に位置する下端が外スプライス板24の上面に当接するように本体2に上下位置調整自在に結合された調整部材3とを具備させて内スプライス板25の組み付け用治具1を構成する。本体2には、外スプライス板24の上面に沿う上部支持片5と、この上部支持片5と平行に対向し上フランジ22の下面に所定の間隔を置いて沿う下部支持片6と、上部支持片5の一端と下部支持片6の一端とを結合する連結片7とを具備させる。本体2の上部支持片5は、垂直に貫通するねじ孔5aを有するものとする。調整部材3には、上部支持片5のねじ孔5aに螺合されるねじ棒8と、このねじ棒8に回転用工具を掛けるためにねじ棒8の上部に設けられた係合部材9と、ねじ棒8の下端に、下部支持片6と対向するように設けられ外スプライス板24の上面に当接する当接部材10とを具備させる。このようにして、上フランジ22の下面と下部支持片6との間隙に挿入される内スプライス板25を支持可能とすることにより、ボルト挿通孔の位置合わせと仮止め用ボルト26の締め付け作業を両手で実行可能とした。
In the invention of this application, in order to solve the above-mentioned problem, the
鉄骨21に対し接続用の内スプライス板25を仮組するにあたって、この発明に係る治具1を用いて、一連の作業を一人で容易かつ安全に行うことができる。この発明に係る治具1は、上フランジ22の片側に装着されるように、小型軽量に構成されるので、装着、取り外し、携帯、移動の操作が極めて容易で、作業効率を大幅に向上させることができるという効果を有する。また、適用する鉄骨21のサイズが変わっても、係合部材9を手動で回転する調整部材3の位置調整のみの簡単な操作で、柔軟にこれに対応することができるという効果もある。
When the
図面を参照してこの発明の実施の形態を説明する。図1は本発明の治具の使用状態を示す斜視図、図2は本発明の治具の使用状態を示す正面図、図3は本発明の治具の正面図、図4は本発明の治具の側面図、図5は本発明の治具の平面図、図6はスプライス板の取付け手順を示す側面図である。 Embodiments of the present invention will be described with reference to the drawings. 1 is a perspective view showing the usage state of the jig of the present invention, FIG. 2 is a front view showing the usage state of the jig of the present invention, FIG. 3 is a front view of the jig of the present invention, and FIG. 5 is a side view of the jig, FIG. 5 is a plan view of the jig of the present invention, and FIG. 6 is a side view showing a procedure for attaching the splice plate.
図1において、21はH型鉄骨で、フランジ22、23を水平に配置して保管場所に積み置かれる。上フランジ22上には、ボルト孔を合わせて所定の位置に外スプライス板24が載せ置かれる。治具1は、外スプライス板24を載せた上フランジ22の縁部に装着される。
In FIG. 1, 21 is an H-shaped steel frame, and the
図1ないし図5において、治具1は、本体2と調整部材3とを具備する。本体2は、外スプライス板24を載せた上フランジ22の縁部を外スプライス板24と共に受け入れる凹部4を備えた断面略コ字状の部材であり、上部支持片5と、下部支持片6と、両片5,6を結合する連結片7とを具備する。上部支持片5は、外スプライス板24の上面に沿うように伸び、垂直方向に貫通するねじ孔5aを有する。下部支持片6は、上部支持片5の下方に、これと平行に対向し、上フランジ22の下面に所定の間隔を置いてこれに沿うように伸びる。連結片7は、上部支持片5の一端と下部支持片6の一端とを結合し、両支持片5,6間に凹部4を形成する。
1 to 5, the
調整部材3は、本体2に対して、上下位置調整自在に結合され、本体2の凹部4内に位置する下端が外スプライス板24の上面に当接するように構成される。調整部材3は、本体2の上部支持片5のねじ孔5aに螺合されるねじ棒8と、このねじ棒8を回転させるためにねじ棒8の上部に設けられた係合部材9と、ねじ棒8の下端に固着された当接部材10とを具備する。当接部材10は、下部支持片6と平行に対向するように設けられ、外スプライス板24の上面に当接するように構成される。
The
上フランジ22の下面と下部支持片6との間隙に内スプライス板25が挿入され、下部支持片6上に支持される。調整部材3は、適用するH型鉄骨のサイズによる上フランジ22及び外スプライス板24の厚さ変化に対応して、例えば、上フランジ22の下面と下部支持片6との間隙寸法が、挿入すべき内スプライス板25の厚さに5mm程度を足した寸法となるよう位置を調整しておくのが好ましい。
An
図6を参照して、内スプライス板25の組み付け作業は以下のように行われる。(1)フランジ22,23を水平に配置して置かれたH型鉄骨21の上フランジ22上の所定位置に外スプライス板24を載せ置く(図5(A))。(2)外スプライス板24を載せた上フランジ22の縁部を凹部4に受け入れるように、組み付け用治具1を上フランジ22に装着し、これによって、重心が上フランジ22の外側にある外スプライス板24を上フランジ22上に静置する(図5(B))。(3)上フランジ22の下面と治具1の下部支持片6との間隙に内スプライス板25を挿入して、下部支持片6上に支持する(図5(C))。(4)外スプライス板24、上フランジ22及び内スプライス板25のボルト挿通孔にレンチを挿入するなどして、位置合わせを行う。(5)ボルト挿通孔に仮止め用のボルト26を挿通してナットで締め付ける(図5(D))。なお、用治具1を上フランジ22に装着した後は、両手が空くので、その後の(3)、(4)、(5)の作業は両手で迅速に行うことができる。ボルト26の締め付けが完了したら、治具1を外してフランジ22の反対側へ装着し、同様に反対側の内スプライス板の組付けを行う。
Referring to FIG. 6, the assembling operation of
この発明の治具は、例えば大型の鉄骨を取り扱う鉄骨加工現場において、H型鉄骨の上フランジの下に、内スプライス板を仮止めする作業に利用される。 The jig of the present invention is used for, for example, a work of temporarily fixing an inner splice plate under an upper flange of an H-shaped steel frame in a steel processing site where a large steel frame is handled.
1 治具
2 本体
3 調整部材
4 凹部
5 上部支持片
5a ねじ孔
6 下部支持片
7 連結片
8 ねじ棒
9 係合部材
10 当接部材
21 H型鉄骨
22 上フランジ
23 下フランジ
24 外スプライス板
25 内スプライス板
26 ボルト
DESCRIPTION OF
Claims (2)
前記外スプライス板を載せた上フランジの縁部を受け入れる凹部を備えた断面略コ字状の本体と、凹部内に位置する下端が外スプライス板の上面に当接するように本体に上下位置調整自在に結合された調整部材とを具備し、
前記本体は、前記外スプライス板の上面に沿う上部支持片と、この上部支持片と平行に対向し前記上フランジの下面に所定の間隔を置いて沿う下部支持片と、上部支持片の一端と下部支持片の一端とを結合する連結片とを具備し、
前記本体の上部支持片は、垂直に貫通するねじ孔を有し、
前記調整部材は、前記上部支持片のねじ孔に螺合されるねじ棒と、このねじ棒に回転用工具を掛けるためにねじ棒の上部に設けられた係合部材と、このねじ棒の下端に前記下部支持片と対向するように設けられ前記外スプライス板の上面に当接する当接部材とを具備し、
前記外スプライス板を載せた上フランジの縁部への装着時に、外スプライス板を上フランジ上に静置させるに十分な重量を有し、
前記上フランジの下面と前記下部支持片との間隙に挿入された内スプライス板を支持可能とすることにより、ボルト挿通孔の位置合わせと仮止め用ボルトの締め付け作業を両手で実行可能としたことを特徴とするH型鉄骨の上フランジ接続用スプライス板の組み付け用治具。 After placing the outer splice plate in place so that one end projects from the end of the upper flange and the center of gravity is outside the upper flange on the upper flange of the H-shaped steel frame with the flange placed horizontally In the operation of assembling the inner splice plate to the lower surface of the upper flange, a jig used by being mounted on the upper flange of the H-shaped steel frame,
Adjustable vertical position of the main body with a substantially U-shaped cross section with a recess that accepts the edge of the upper flange on which the outer splice plate is placed, and the lower end located in the recess abuts the upper surface of the outer splice plate And an adjustment member coupled to
The main body includes an upper support piece along the upper surface of the outer splice plate, a lower support piece that faces the upper support piece in parallel with a predetermined distance from the lower surface of the upper flange, and one end of the upper support piece. A connecting piece that joins one end of the lower support piece,
The upper support piece of the main body has a screw hole penetrating vertically,
The adjustment member includes a screw rod that is screwed into a screw hole of the upper support piece, an engagement member that is provided on an upper portion of the screw rod to hang a tool for rotation on the screw rod, and a lower end of the screw rod A contact member that is provided to face the lower support piece and contacts the upper surface of the outer splice plate,
When mounted on the edge of the upper flange on which the outer splice plate is placed, the outer splice plate has a weight sufficient to allow the outer splice plate to rest on the upper flange;
By making it possible to support the inner splice plate inserted in the gap between the lower surface of the upper flange and the lower support piece, the bolt insertion hole alignment and the fastening operation of the temporary fixing bolt can be performed with both hands. A jig for assembling the splice plate for connecting the upper flange of the H-shaped steel frame.
外スプライス板を載せた上フランジの縁部を前記凹部に受け入れるように前記組み付け用治具を上フランジに装着することによって、重心が上フランジの外側にある外スプライス板を上フランジ上に静置する工程と、By attaching the assembling jig to the upper flange so that the edge of the upper flange on which the outer splice plate is placed is received in the recess, the outer splice plate whose center of gravity is outside the upper flange is placed on the upper flange. And a process of
上フランジの下面と前記組み付け用治具の下部支持片との間隙に前記内スプライス板を挿入して組み付け用治具で支持する工程と、Inserting the inner splice plate into the gap between the lower surface of the upper flange and the lower support piece of the assembly jig and supporting the assembly with the assembly jig;
外スプライス板、上フランジ及び内スプライス板のボルト挿通孔の位置合わせと、前記仮止め用ボルトの締め付け作業を両手で実行する工程と、A step of performing positioning of the bolt insertion holes of the outer splice plate, the upper flange and the inner splice plate with both hands, and tightening of the temporary fixing bolt;
を含むことを特徴とする請求項1に記載の組み付け用治具を用いたスプライス板の組み付け方法。The assembly method of the splice board using the jig | tool for an assembly | attachment of Claim 1 characterized by the above-mentioned.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2006025041A JP4231053B2 (en) | 2006-02-01 | 2006-02-01 | Jig for assembling splice plate for connecting upper flange of H-shaped steel frame and assembling method using the same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2006025041A JP4231053B2 (en) | 2006-02-01 | 2006-02-01 | Jig for assembling splice plate for connecting upper flange of H-shaped steel frame and assembling method using the same |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2007205035A JP2007205035A (en) | 2007-08-16 |
JP4231053B2 true JP4231053B2 (en) | 2009-02-25 |
Family
ID=38484731
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2006025041A Expired - Fee Related JP4231053B2 (en) | 2006-02-01 | 2006-02-01 | Jig for assembling splice plate for connecting upper flange of H-shaped steel frame and assembling method using the same |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4231053B2 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103437289A (en) * | 2013-07-18 | 2013-12-11 | 杭州博数土木工程技术有限公司 | Connected/disconnected flange plate combined structure construction process |
CN104074280A (en) * | 2014-07-25 | 2014-10-01 | 浙江乔兴建设集团有限公司 | Clamping connection structure |
CN104074279A (en) * | 2014-07-25 | 2014-10-01 | 浙江乔兴建设集团有限公司 | Connecting structure applicable to connection of I-shaped steel bars and T-shaped steel bars |
CN104963407A (en) * | 2014-12-05 | 2015-10-07 | 北新集团建材股份有限公司 | Building structure and construction method thereof |
JP7620165B2 (en) | 2021-12-30 | 2025-01-22 | 浙江大学中原研究院 | A method for reducing the amount of chemicals used to preserve the freshness of bayberry after harvest |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102069228B (en) * | 2010-12-28 | 2012-11-07 | 东方电气集团东方汽轮机有限公司 | Milling processing fixture for cylinder clamp ring of large steam turbine and processing method of clamp ring |
CN103290929A (en) * | 2012-03-02 | 2013-09-11 | 青岛理工大学 | A prefabricated steel beam splicing node |
CN103290928A (en) * | 2012-03-02 | 2013-09-11 | 青岛理工大学 | Steel structure beam column assembled rigid node |
CN106363560B (en) * | 2016-11-29 | 2018-10-23 | 中国一冶集团有限公司 | The aerial butt junction location fixture of adjustable and portable formula H profile steel structure |
KR101763801B1 (en) | 2017-02-22 | 2017-08-14 | (주)해성기공 | Temporary assembling jig for lower flange connecting splice plates of h-beam and method of temporary assembling using the same |
CN111502035B (en) * | 2020-05-06 | 2021-05-28 | 无锡锡晟建设有限公司 | Assembled building beam column node connection mechanism |
CN116695876A (en) * | 2023-06-29 | 2023-09-05 | 江苏玖泰电力实业有限公司 | Connecting component is assembled in steel house |
-
2006
- 2006-02-01 JP JP2006025041A patent/JP4231053B2/en not_active Expired - Fee Related
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103437289A (en) * | 2013-07-18 | 2013-12-11 | 杭州博数土木工程技术有限公司 | Connected/disconnected flange plate combined structure construction process |
CN103437289B (en) * | 2013-07-18 | 2015-10-14 | 浙江中隧桥波形钢腹板有限公司 | The disconnected formula frange plate combining structure construction technology of connection |
CN104074280A (en) * | 2014-07-25 | 2014-10-01 | 浙江乔兴建设集团有限公司 | Clamping connection structure |
CN104074279A (en) * | 2014-07-25 | 2014-10-01 | 浙江乔兴建设集团有限公司 | Connecting structure applicable to connection of I-shaped steel bars and T-shaped steel bars |
CN104074279B (en) * | 2014-07-25 | 2016-08-03 | 浙江乔兴建设集团有限公司 | A kind of being applicable to connects drum and the attachment structure of T-steel bar |
CN104074280B (en) * | 2014-07-25 | 2016-08-17 | 浙江乔兴建设集团有限公司 | A kind of clamp connection structure |
CN104963407A (en) * | 2014-12-05 | 2015-10-07 | 北新集团建材股份有限公司 | Building structure and construction method thereof |
CN104963407B (en) * | 2014-12-05 | 2017-11-24 | 北新集团建材股份有限公司 | A kind of building structure and its construction method |
JP7620165B2 (en) | 2021-12-30 | 2025-01-22 | 浙江大学中原研究院 | A method for reducing the amount of chemicals used to preserve the freshness of bayberry after harvest |
Also Published As
Publication number | Publication date |
---|---|
JP2007205035A (en) | 2007-08-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4231053B2 (en) | Jig for assembling splice plate for connecting upper flange of H-shaped steel frame and assembling method using the same | |
JP4384640B2 (en) | A jig for assembling a splice plate for connecting a lower flange of an H-shaped steel frame and a method for assembling a splice plate using the jig. | |
US8322454B2 (en) | Structure for attaching a tool to a frame tube | |
JP6782646B2 (en) | Fixing jig, steel material holding device, and steel material holding method | |
JP2010019055A (en) | Clamping mechanism | |
JP2012012791A (en) | Splice plate attaching jig for h-shaped steel frame | |
JP6340645B1 (en) | Splice plate holding jig | |
JP6250745B1 (en) | Pipe drilling device | |
JP3201474U (en) | Steel frame corner protection jig | |
JP4807827B2 (en) | Chain hanging tool | |
JP5129947B2 (en) | Catch clamp in scaffold fixing device | |
JP2006219823A (en) | Pipe supporting implement and pipe supporting device using it | |
JP6695591B2 (en) | Wrench tool | |
JP2008163697A (en) | Form structure | |
JP2002194897A (en) | Dislocation correcting jig for steel column | |
JP5425657B2 (en) | Steel frame connection bracket | |
JP3142726U (en) | Bracket KS type for scaffolding for mounting concrete feed pipes. | |
EP4116519A1 (en) | Clamp and method | |
JP2007262731A (en) | Handrail for curing opening | |
JPS6330473B2 (en) | ||
JP5130324B2 (en) | Anchor plate support | |
JP3089350U (en) | Clamp bracket | |
JPH08253992A (en) | Structure for mounting panel joint section | |
JP2004328881A (en) | Piping support fixing metal fitting | |
JP2001152555A (en) | Connecting method and joint plate for building unit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20071116 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080319 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080430 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20081106 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20081204 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4231053 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111212 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121212 Year of fee payment: 4 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131212 Year of fee payment: 5 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |