[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

JP4128887B2 - How to install a three-dimensional crossover viaduct - Google Patents

How to install a three-dimensional crossover viaduct Download PDF

Info

Publication number
JP4128887B2
JP4128887B2 JP2003042265A JP2003042265A JP4128887B2 JP 4128887 B2 JP4128887 B2 JP 4128887B2 JP 2003042265 A JP2003042265 A JP 2003042265A JP 2003042265 A JP2003042265 A JP 2003042265A JP 4128887 B2 JP4128887 B2 JP 4128887B2
Authority
JP
Japan
Prior art keywords
intersection
girder
viaduct
dimensional
diameters
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2003042265A
Other languages
Japanese (ja)
Other versions
JP2004250986A (en
Inventor
昭夫 春日
誠人 亀山
博幸 落合
健一 片
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Mitsui Construction Co Ltd
Original Assignee
Sumitomo Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Mitsui Construction Co Ltd filed Critical Sumitomo Mitsui Construction Co Ltd
Priority to JP2003042265A priority Critical patent/JP4128887B2/en
Publication of JP2004250986A publication Critical patent/JP2004250986A/en
Application granted granted Critical
Publication of JP4128887B2 publication Critical patent/JP4128887B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【0001】
【発明の属する技術分野】
本願発明は、交差点に立体交差高架橋を架設する方法に関するものである。
【0002】
【従来の技術】
従来より、高架橋を架設する際、架設途中の主桁上にガーダを設置し、このガーダを用いて各径間毎に主桁を延長架設していく架設方法が知られている。
【0003】
そして、この架設方法においては、例えば特許文献1にも記載されているように、各径間での延長架設が完了するたびにガーダを一径間分ずつ前方へ移動させるようになっている。
【0004】
【特許文献1】
特開2000−230206号公報
【発明が解決しようとする課題】
しかしながら、上記従来の架設方法においては、交差点を跨ぐ交差部径間に位置する主桁の交差部構成部分を架設する際、ガーダの移動作業時および主桁の架設作業時に、交差する道路の交通規制を行う必要がある。
【0005】
その際、ガーダの移動作業は比較的短時間で行うことができるが、主桁の架設作業は比較的長時間を要するので、交差する道路の交通規制を長期にわたって行うことが必要となる、という問題がある。
【0006】
本願発明は、このような事情に鑑みてなされたものであって、交差点に立体交差高架橋を架設する際、交差する道路の交通規制の必要性を緩和することができる立体交差高架橋の架設方法を提供することを目的とするものである。
【0007】
【課題を解決するための手段】
本願発明は、主桁の交差部構成部分の架設方法に工夫を施すことにより、上記目的達成を図るようにしたものである。
【0008】
すなわち、本願発明に係る立体交差高架橋の架設方法は、
交差点に立体交差高架橋を架設する方法において、
架設途中の主桁上にガーダを設置し、
このガーダを用いて、上記交差点を跨ぐ交差部径間に位置する上記主桁の交差部構成部分を、該交差部構成部分の橋軸方向両側に位置する脚頭部セグメントと共に、上記交差部径間の手前側に隣接する径間において、上記交差部構成部分を構成する複数のプレキャストセグメントおよび上記両脚頭部セグメントを連結配置した状態で、これら連結配置された複数のプレキャストセグメントおよび両脚頭部セグメントに対して、各セグメント相互間の目地工を行うとともにPC鋼材の挿入および緊張を行うことにより、予備的に架設した後、
この交差部構成部分を上記交差部径間に移動させ
その後、上記交差部径間の手前側に隣接する径間における上記主桁の延長架設を行う、ことを特徴とするものである。
【0009】
上記「ガーダ」の長さや設置本数等の具体的構成については特に限定されるものではない。
【0010】
上記「交差部構成部分」の具体的な構成については特に限定されるものではなく、また、この交差部構成部分を「交差部径間に移動させる」ための具体的な方法についても特に限定されるものではない。
【0011】
【発明の作用効果】
上記構成に示すように、本願発明に係る立体交差高架橋の架設方法は、交差点に立体交差高架橋を架設する際、架設途中の主桁上にガーダを設置し、このガーダを用いて、主桁の交差部構成部分をその橋軸方向両側に位置する脚頭部セグメントと共に、交差部径間の手前側に隣接する径間において予備的に架設した後、この交差部構成部分を交差部径間に移動させるようになっているので、次のような作用効果を得ることができる。
【0012】
すなわち、従来のように交差部径間において主桁の架設作業を行うようにした場合には、交差する道路の交通規制を長期にわたって行う必要があるが、交差部径間の手前側に隣接する径間において予備的架設を行うようにすれば、交差部構成部分の架設作業自体に起因する交通規制を不要とすることができる。
【0013】
したがって本願発明によれば、交差点に立体交差高架橋を架設する際、交差する道路の交通規制の必要性を緩和することができる。
【0014】
しかも本願発明においては、材料運搬に架設済みの主桁橋面を利用することができるので、架設ヤードの小規模化を図ることができる。
【0015】
上記構成において、交差部構成部分を予備的に架設する際、これをガーダに吊下げ固定しておき、このガーダを移動させることにより交差部構成部分の移動を行うようにすれば、ガーダの移動作業等の際にのみ、交差する道路の交通規制を行えば足りるようにすることができる。
【0016】
このようにする代わりに、交差部構成部分を予備的に架設する際、これを走行装置を介してガーダに吊り下げておき、この走行装置を移動させることにより交差部構成部分の移動を行うようにすれば、交差部構成部分を移動させる際にのみ、交差する道路の交通規制を行えば足りるようにすることができる。また、このようにした場合には、交差部構成部分の架設のためにガーダを移動させる必要がなくなるので、その分だけ架設作業の簡略化を図ることができる。
【0017】
また上記構成において、交差部構成部分を予備的に架設する際、この予備的架設と同時に、上記ガーダを用いて、交差部径間の前端部に位置する基礎工および橋脚の施工を行うようにすれば、架設作業の作業効率を高めることができる。
【0018】
【発明の実施の形態】
以下、図面を用いて、本願発明の実施の形態について説明する。
【0019】
図1〜3は、本願発明の一実施形態に係る立体交差高架橋の架設方法の工程を示す側面図である。
【0020】
図1(a)に示すように、本実施形態に係る架設方法の架設対象となる立体交差高架橋は、図中左右方向に延びる道路102に沿って架設され、そして、この道路102と直交する道路との交差点104において該道路を跨ぐようにして架設されるようになっている。
【0021】
この立体交差高架橋は、道路102の中央分離帯に沿って所定間隔をおいて設置された複数の橋脚12と、これら複数の橋脚12の上端部に設置された主桁14とを備えてなっている。そして、この主桁14は、複数のプレキャストセグメント22が橋軸方向に連結配置されてなっている。
【0022】
本実施形態においては、架設途中の主桁14上に左右1対のガーダ50を設置し、これらガーダ50を用いて、各径間S1、S2、・・・における主桁14の延長架設と、その前方側に隣接する先行径間S2、S3、・・・の前端部に位置する基礎工16および橋脚12の施工とを同時に行うようになっている。なお、この立体交差高架橋においては、その端部から4番目の径間S4が交差点104に位置する交差部径間を構成している。
【0023】
両ガーダ50は、1番目の径間S1の途中位置から交差部径間S4の途中位置まで延びるようにして設置されるようになっている。
【0024】
これを実現するため、主桁14を構成する複数のプレキャストセグメント22のうち、2番目の径間S2の前後両側に位置する橋脚12A、12Bの橋座に設置されるべき脚頭部セグメント22A、22Bについては、これらを両橋脚12A、12Bの橋座に予め設置しておき、これら脚頭部セグメント22A、22Bの上面に支保工52A、52Bを設置して、これら支保工52A、52Bによりガーダ50を支持するようになっている。また、交差部径間S4の後端部近傍位置にも支柱54を設置しておき、この支柱54の上端面に支保工52Cを設置して、この支保工52Cによりガーダ50の前端部を支持するようになっている。その際、これら各支保工52A、52B、52Cの上端部には各々ローラが設けられており、これによりガーダ50を前後方向に移動可能な状態で支持するようになっている。
【0025】
両ガーダ50の前端近傍部位には、掘削機58および門型クレーン60が前後方向に移動可能に設置されている。
【0026】
各橋脚12の下方に位置する基礎工16は、フーチング32と前後1対の場所打ち鋼管コンクリート杭34とからなっている。そして、この基礎工16の施工を行う際、掘削機58を用いた杭孔の掘削を行うとともに、門型クレーン60を用いて鋼管等の搬送や埋込みを行うようになっている。また、各橋脚12の施工を行う際にも、門型クレーン60を用いて必要資材の搬送を行うようになっている。
【0027】
各径間S1、S2、・・・における主桁14の架設は、複数のプレキャストセグメント22を橋軸方向に連結配置することにより行われるようになっている。その際、各プレキャストセグメント22は、架設済みの主桁14の橋面上においてセグメント移動装置(図示せず)に吊り下げられ、この状態で架設対象となる径間に搬入されるようになっている。
【0028】
ただし、交差部径間S4に位置する主桁14の交差部構成部分14Aに関しては、この交差部構成部分14Aを、その橋軸方向両側に位置する脚頭部セグメント22C、22Dと共に、交差部径間S4の手前側に隣接する3番目の径間S3において予備的に架設した後、交差部径間S4に移動させることによって、その架設が行われるようになっている。
【0029】
以下、この交差部構成部分14Aの架設工程について具体的に説明する。
【0030】
まず、図1(a)に示すように、交差部径間S4の後端部に位置する橋脚12Cの上端面に押し出し装置56および鉛直ジャッキ(図示せず)を設置した後、脚頭部セグメント22Dと交差部構成部分14Aを構成する一部のプレキャストセグメント22とを押し出し装置56の上に配置する。
【0031】
次に、同図(b)に示すように、ガーダ50を前方へ向けて延長形成し、掘削機58および門型クレーン60をガーダ50の前端部寄りに移動させる。
【0032】
次に、同図(c)に示すように、交差部構成部分14Aを構成する残りのプレキャストセグメント22および脚頭部セグメント22Cを連結配置する。そして、これら連結配置された複数のプレキャストセグメント22および脚頭部セグメント22C、22Dに対して、その相互間の目地工を行うとともにPC鋼材の挿入および緊張を行い、交差部構成部分14Aの予備的架設を完了させる。
【0033】
次に、図2(d)に示すように、連結配置された交差部構成部分14Aおよび脚頭部セグメント22C、22Dを、複数のPC鋼棒62によりガーダ50に吊り下げ固定する。またこのとき、交差部径間S4の前端部においては、その基礎工16Dの施工として、掘削機58による杭孔の掘削を行う。
【0034】
次に、同図(e)に示すように、3番目の径間S3の略中央位置に、上端部にローラが設けられた仮支柱64を設置し、交差部構成部分14Aを前後方向に移動可能な状態で支持させる。またこのとき、交差部径間S4の前端部においては、その基礎工16Dの施工として、杭孔への鋼管杭の挿入、鉄筋配置およびコンクリートの打設を行う。
【0035】
次に、同図(f)に示すように、押し出し装置56により、交差部構成部分14Aおよび脚頭部セグメント22C、22Dを、ガーダ50と共に前方へ移動させる。またこのとき、交差部径間S4の前端部においては、橋脚12Dの施工を行うとともにその橋座にローラ66を設置する。
【0036】
そして、図3(g)に示すように、脚頭部セグメント22Dが橋脚12Dのローラ66に到達する位置まで、ガーダ50を移動させた後、この移動を停止させる。
【0037】
最後に、同図(h)に示すように、橋脚12C、12Dの橋座から押し出し装置56およびローラ66を撤去するとともに、PC鋼棒62による吊り下げ固定を解放した後、鉛直ジャッキをジャッキダウンさせて、脚頭部セグメント22C、22Dを橋脚12C、12Dの橋座の支承工38にセットすることにより、交差部構成部分14Aの架設を完了させる。そして、その後、3番目の径間S3における主桁14の延長架設を行う。
【0038】
以上詳述したように、本実施形態に係る立体交差高架橋の架設方法は、交差点104に立体交差高架橋を架設する際、架設途中の主桁14上に左右1対のガーダ50を設置し、これらガーダ50を用いて、主桁14の交差部構成部分14Aをその橋軸方向両側に位置する脚頭部セグメント22C、22Dと共に、交差部径間S4の手前側に隣接する径間S3において予備的に架設した後、この交差部構成部分14Aを交差部径間S4に移動させるようになっているので、交差部構成部分14Aの架設作業自体に起因する交通規制を不要とすることができる。そしてこれにより、交差点に立体交差高架橋を架設する際、交差する道路の交通規制の必要性を緩和することができる。
【0039】
具体的には、交差部構成部分14Aを予備的に架設する際、該交差部構成部分14Aをガーダ50に吊下げ固定しておき、このガーダ50を移動させることにより交差部構成部分14Aの移動を行うようになっているので、ガーダ50の延長作業時および移動作業時にのみ、交差する道路の交通規制を行えば足りるようにすることができる。
【0040】
しかも本実施形態においては、後方の径間S1、S2に架設された主桁14の橋面を、材料運搬に利用することができるので、架設ヤードの小規模化を図ることができる。
【0041】
また本実施形態においては、交差部構成部分14Aを予備的に架設する際、この予備的架設と同時に、両ガーダ50を用いて、交差部径間S4の前端部に位置する基礎工16Dおよび橋脚12Dの施工を行うようになっているので、架設作業の作業効率を高めることができる。
【0042】
図4は、上記実施形態の変形例に係る架設方法を示す工程図である。
【0043】
本変形例においては、交差部構成部分14Aを予備的に架設する際、同図(a)に示すように、この交差部構成部分14Aをその橋軸方向両側に位置する脚頭部セグメント22C、22Dと共に、前後1対の走行装置68を介してガーダ50に吊り下げておき、同図(b)、(c)に示すように、これら走行装置68をガーダ50に沿って前方へ移動させることにより、交差部構成部分14Aの移動を行うようになっている。その際、橋脚12Cの位置において、交差部構成部分14Aと両ガーダ50との間にローラ70を介装しておき、これにより交差部構成部分14Aの移動が円滑に行われるようにする。なお、これ以外の架設工程については上記実施形態の架設方法と同様である。
【0044】
本変形例の架設方法を採用することにより、交差部構成部分14Aを移動させる際にのみ、交差する道路の交通規制を行えば足りるようにすることができる。
【0045】
しかも本変形例の架設方法を採用した場合には、交差部構成部分14Aの架設のためにガーダ50を移動させる必要がなくなるので、その分だけ架設作業の簡略化を図ることができる。また、ガーダ50が移動しないので、ガーダ50を延長形成しなくても該ガーダ50を常に3点支持の状態に維持しておくことが可能となり、これにより架設作業の一層の簡略化を図ることができる。
【図面の簡単な説明】
【図1】本願発明の一実施形態に係る立体交差高架橋の架設方法を示す工程図(その1)
【図2】上記実施形態の架設方法を示す工程図(その2)
【図3】上記実施形態の架設方法を示す工程図(その3)
【図4】上記実施形態の変形例に係る架設方法を示す工程図
【符号の説明】
10 立体交差高架橋
12、12A、12B、12C、12D 橋脚
14 主桁
14A 交差部構成部分
16、16D 基礎工
22 プレキャストセグメント
22A、22B、22C、22D 脚頭部セグメント
32 フーチング
34 場所打ち鋼管コンクリート杭
38 支承工
50 ガーダ
52A、52B、52C 支保工
54 支柱
56 押し出し装置
58 掘削機
60 門型クレーン
62 PC鋼棒
64 仮支柱
66、70 ローラ
68 走行装置
102 道路
104 交差点
S1 1番目の径間
S2 2番目の径間
S3 3番目の径間
S4 4番目の径間(交差部径間)
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for constructing a three-dimensional intersection viaduct at an intersection.
[0002]
[Prior art]
Conventionally, when a viaduct is installed, a girder is installed on a main girder in the middle of the construction, and the girder is used to extend the main girder for each span.
[0003]
In this erection method, for example, as described in Patent Document 1, the girder is moved forward by one span each time the extension erection between each diameter is completed.
[0004]
[Patent Document 1]
JP, 2000-230206, A [Problems to be solved by the invention]
However, in the above conventional construction method, when constructing the intersection part of the main girder located between the intersections spanning the intersection, the traffic on the intersecting road during the girder moving work and the main girder construction work Regulations need to be made.
[0005]
At that time, the girder movement work can be done in a relatively short time, but the construction work of the main girder takes a relatively long time, so it is necessary to regulate the traffic on the intersecting road for a long time There's a problem.
[0006]
The present invention has been made in view of such circumstances, and when a three-dimensional intersection viaduct is constructed at an intersection, a method for constructing a three-dimensional intersection viaduct that can alleviate the need for traffic regulation of intersecting roads. It is intended to provide.
[0007]
[Means for Solving the Problems]
In the present invention, the above-described object is achieved by devising a construction method of the crossing portion constituting the main girder.
[0008]
That is, the construction method of the three-dimensional intersection viaduct according to the present invention is:
In a method of constructing a three-dimensional intersection viaduct at an intersection,
Install girder on the main girder in the middle of erection,
Using this girder, the intersection portion of the main girder located between the intersection diameters across the intersection, together with the leg head segments located on both sides in the bridge axis direction of the intersection portion, the intersection diameter In a state where the plurality of precast segments and the both leg head segments constituting the intersection portion are connected and arranged in a span adjacent to the front side between the plurality of precast segments and the both leg head segments connected to each other. After preliminarily erection by performing joint work between each segment and inserting and tensioning PC steel ,
This intersection part is moved between the intersection diameters ,
Thereafter, the main girder is extended between the adjacent diameters on the near side between the intersection diameters .
[0009]
The specific configuration such as the length of the “girder” and the number of installations is not particularly limited.
[0010]
The specific configuration of the above “intersection portion” is not particularly limited, and the specific method for “moving the intersection portion between the intersection diameters” is also particularly limited. It is not something.
[0011]
[Effects of the invention]
As shown in the above configuration, the method of installing the three-dimensional crossover viaduct according to the present invention is to install a girder on the main girder in the middle of the construction when installing the three-dimensional crossover viaduct at the intersection, and using this girder, After the cross-section component is preliminarily installed with the leg head segments located on both sides in the bridge axis direction and adjacent to the front side of the cross-section diameter, the cross-section configuration section is moved between the cross-section diameters. Thus, the following operational effects can be obtained.
[0012]
That is, when the main girder construction work is performed between the intersections as in the past, it is necessary to carry out traffic regulation of the intersecting road over a long period of time. If preliminary erection is performed at, traffic regulation due to the erection work of the intersection portion itself can be eliminated.
[0013]
Therefore, according to this invention, when constructing a three-dimensional intersection viaduct at an intersection, the necessity of traffic regulation of the intersecting road can be eased.
[0014]
Moreover, in the present invention, since the main girder bridge surface that has been installed can be used for material transportation, the installation yard can be reduced in size.
[0015]
In the above configuration, when the intersection part is preliminarily installed, it is suspended and fixed to the girder, and the girder is moved to move the intersection part. It is possible to restrict traffic on the intersecting roads only when working.
[0016]
Instead of doing this, when the intersection part is preliminarily installed, it is suspended on the girder via the traveling device, and the intersection part is moved by moving the traveling device. In this case, it is only necessary to restrict the traffic on the intersecting road only when moving the intersection portion. Further, in this case, it is not necessary to move the girder for the construction of the intersection portion constituting portion, so that the construction work can be simplified correspondingly.
[0017]
Also, in the above configuration, when preliminarily constructing the intersection portion, the foundation work and the pier located at the front end between the intersection diameters are constructed simultaneously with the preliminary construction using the girder. Then, the work efficiency of the erection work can be improved.
[0018]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
[0019]
1-3 is a side view which shows the process of the construction method of the three-dimensional intersection viaduct concerning one Embodiment of this invention.
[0020]
As shown in FIG. 1 (a), a three-dimensional intersection viaduct to be installed in the installation method according to the present embodiment is installed along a road 102 extending in the left-right direction in the drawing, and is a road orthogonal to the road 102. It is constructed so as to straddle the road at the intersection 104.
[0021]
This three-dimensional crossover viaduct includes a plurality of piers 12 installed at predetermined intervals along the central separation zone of the road 102, and a main girder 14 installed at the upper ends of the plurality of piers 12. Yes. The main girder 14 has a plurality of precast segments 22 connected and arranged in the bridge axis direction.
[0022]
In the present embodiment, a pair of left and right girders 50 are installed on the main girder 14 in the middle of the erection, and the girder 50 is used to extend the main girder 14 in the spans S1, S2,. Construction of the foundation work 16 and the pier 12 located at the front end of the preceding spans S2, S3,... Adjacent to the front side is performed simultaneously. In this three-dimensional crossover viaduct, the fourth span S4 from the end constitutes the intersection span located at the intersection 104.
[0023]
Both girders 50 are installed so as to extend from the midway position of the first span S1 to the midway position of the intersection span S4.
[0024]
In order to realize this, the leg head segments 22A to be installed on the bridge piers of the piers 12A and 12B located on both front and rear sides of the second span S2 among the plurality of precast segments 22 constituting the main girder 14, For 22B, these are installed in advance on the bridge piers of both piers 12A and 12B, and supporters 52A and 52B are installed on the upper surfaces of these leg head segments 22A and 22B. 50 is supported. Further, a support post 54 is also installed in the vicinity of the rear end portion of the cross section span S4, a support work 52C is installed on the upper end surface of the support post 54, and the front end part of the girder 50 is supported by the support work 52C. It is supposed to be. At that time, rollers are provided at the upper ends of the respective supporting works 52A, 52B, 52C, thereby supporting the girder 50 in a state of being movable in the front-rear direction.
[0025]
An excavator 58 and a portal crane 60 are installed in the vicinity of the front ends of both girders 50 so as to be movable in the front-rear direction.
[0026]
The foundation work 16 located below each pier 12 is composed of a footing 32 and a pair of cast-in-place steel pipe concrete piles 34 in the front and rear. And when performing this foundation work 16, while excavating a pile hole using the excavator 58, the portal crane 60 is used to convey and embed steel pipes. In addition, when constructing each pier 12, necessary materials are transported using the portal crane 60.
[0027]
The main girder 14 in each span S1, S2,... Is constructed by connecting and arranging a plurality of precast segments 22 in the bridge axis direction. At that time, each precast segment 22 is suspended by a segment moving device (not shown) on the bridge surface of the main girder 14 that has been installed, and in this state, it is carried into the span to be installed. Yes.
[0028]
However, with regard to the intersection portion 14A of the main girder 14 located in the intersection span S4, the intersection portion 14A is used together with the leg head segments 22C and 22D located on both sides in the bridge axis direction. After preliminarily erection in the third span S3 adjacent to the front side of the interval S4, the erection is performed by moving to the intersection span S4.
[0029]
Hereinafter, the construction process of the intersecting portion constituting portion 14A will be specifically described.
[0030]
First, as shown in FIG. 1 (a), after an extrusion device 56 and a vertical jack (not shown) are installed on the upper end surface of the pier 12C located at the rear end of the intersection span S4, the leg head segment 22D and a part of the precast segment 22 constituting the intersection component 14A are arranged on the extrusion device 56.
[0031]
Next, as shown in FIG. 4B, the girder 50 is formed to extend forward, and the excavator 58 and the portal crane 60 are moved closer to the front end of the girder 50.
[0032]
Next, as shown in FIG. 5C, the remaining precast segment 22 and leg head segment 22C constituting the intersection portion 14A are connected and arranged. Then, jointing between the plurality of precast segments 22 and leg head segments 22C and 22D arranged in connection with each other and insertion and tension of the PC steel material are performed, so that the preliminary construction of the intersection portion 14A is performed. Complete the erection.
[0033]
Next, as shown in FIG. 2 (d), the crossing component 14 </ b> A and the leg head segments 22 </ b> C and 22 </ b> D that are connected and arranged are suspended and fixed to the girder 50 by a plurality of PC steel bars 62. At this time, the excavator 58 excavates the pile hole at the front end portion of the intersection span S4 as the foundation work 16D.
[0034]
Next, as shown in FIG. 5E, a temporary support column 64 having a roller provided at the upper end portion is installed at a substantially central position of the third span S3, and the intersecting portion constituting portion 14A is moved in the front-rear direction. Support as possible. At this time, at the front end portion of the intersection span S4, as the foundation work 16D, steel pipe piles are inserted into the pile holes, reinforcing bars are placed, and concrete is placed.
[0035]
Next, as shown in FIG. 5F, the crossing component 14A and the leg head segments 22C and 22D are moved forward together with the girder 50 by the pushing device 56. At this time, at the front end of the intersection span S4, the pier 12D is constructed and the roller 66 is installed on the bridge seat.
[0036]
Then, as shown in FIG. 3G, after the girder 50 is moved to a position where the leg head segment 22D reaches the roller 66 of the pier 12D, this movement is stopped.
[0037]
Finally, as shown in FIG. 6 (h), the push-out device 56 and the roller 66 are removed from the bridge seats of the piers 12C and 12D, the suspension by the PC steel rod 62 is released, and then the vertical jack is jacked down. Then, by setting the leg head segments 22C and 22D to the bridge support 38 of the bridge piers 12C and 12D, the construction of the intersection portion 14A is completed. After that, the extension of the main girder 14 in the third span S3 is performed.
[0038]
As described above in detail, the method of installing the three-dimensional crossover viaduct according to the present embodiment sets a pair of left and right girders 50 on the main girder 14 in the middle of the installation when installing the three-dimensional crossover viaduct at the intersection 104. Using the girder 50, the intersection portion 14A of the main girder 14 is preliminary in the span S3 adjacent to the front side of the intersection span S4 together with the leg head segments 22C and 22D located on both sides in the bridge axis direction. Since the intersection portion 14A is moved to the intersection span S4 after the installation, the traffic regulation due to the installation work itself of the intersection portion 14A can be made unnecessary. And when this constructs a three-dimensional intersection viaduct at an intersection, the necessity of the traffic regulation of the road which crosses can be eased.
[0039]
Specifically, when the intersection portion 14A is preliminarily installed, the intersection portion 14A is suspended and fixed to the girder 50, and the girder 50 is moved to move the intersection portion 14A. Therefore, it is only necessary to restrict the traffic on the intersecting road only when the girder 50 is extended or moved.
[0040]
In addition, in the present embodiment, the bridge surface of the main girder 14 installed between the rear spans S1 and S2 can be used for material transportation, so the installation yard can be reduced in size.
[0041]
Further, in the present embodiment, when the intersection portion 14A is preliminarily installed, the foundation work 16D and the pier located at the front end of the intersection span S4 are used simultaneously with the preliminary installation, using both girders 50. Since the construction of 12D is performed, the work efficiency of the erection work can be increased.
[0042]
FIG. 4 is a process diagram showing a construction method according to a modification of the embodiment.
[0043]
In this modified example, when the intersection portion 14A is preliminarily installed, as shown in FIG. 5A, the intersection portion 14A is located on both sides in the bridge axis direction, as shown in FIG. 22D and suspended on the girder 50 via a pair of front and rear traveling devices 68, and the traveling devices 68 are moved forward along the girder 50 as shown in FIGS. Thus, the intersection portion 14A is moved. At that time, at the position of the bridge pier 12C, a roller 70 is interposed between the intersection portion constituting portion 14A and the two girders 50, so that the movement of the intersection portion constituting portion 14A is performed smoothly. In addition, about the installation process other than this, it is the same as that of the installation method of the said embodiment.
[0044]
By adopting the erection method of this modification, it is only necessary to regulate the traffic on the intersecting road only when moving the intersection portion 14A.
[0045]
In addition, when the erection method of this modification is adopted, it is not necessary to move the girder 50 for erection of the intersection portion constituting portion 14A, so that the erection operation can be simplified correspondingly. Further, since the girder 50 does not move, it is possible to always keep the girder 50 in a three-point support state without extending the girder 50, thereby further simplifying the construction work. Can do.
[Brief description of the drawings]
FIG. 1 is a process diagram (No. 1) showing a construction method of a three-dimensional crossover viaduct according to an embodiment of the present invention.
FIG. 2 is a process diagram (part 2) showing the erection method of the embodiment.
FIG. 3 is a process diagram (part 3) showing the erection method of the embodiment.
FIG. 4 is a process diagram illustrating a construction method according to a modification of the embodiment.
DESCRIPTION OF SYMBOLS 10 Three-dimensional crossover viaduct 12,12A, 12B, 12C, 12D Pier 14 Main girder 14A Crossing part 16,16D Foundation 22 Precast segment 22A, 22B, 22C, 22D Leg head segment 32 Footing 34 Cast-in-place steel pipe concrete pile 38 Bearing work 50 Girder 52A, 52B, 52C Support work 54 Strut 56 Extruding device 58 Excavator 60 Portal crane 62 PC steel rod 64 Temporary strut 66, 70 Roller 68 Traveling device 102 Road 104 Intersection S1 First span S2 Second Span S3 3rd span S4 4th span (between intersections)

Claims (4)

交差点に立体交差高架橋を架設する方法において、
架設途中の主桁上にガーダを設置し、
このガーダを用いて、上記交差点を跨ぐ交差部径間に位置する上記主桁の交差部構成部分を、該交差部構成部分の橋軸方向両側に位置する脚頭部セグメントと共に、上記交差部径間の手前側に隣接する径間において、上記交差部構成部分を構成する複数のプレキャストセグメントおよび上記両脚頭部セグメントを連結配置した状態で、これら連結配置された複数のプレキャストセグメントおよび両脚頭部セグメントに対して、各セグメント相互間の目地工を行うとともにPC鋼材の挿入および緊張を行うことにより、予備的に架設した後、
この交差部構成部分を上記交差部径間に移動させ
その後、上記交差部径間の手前側に隣接する径間における上記主桁の延長架設を行う、ことを特徴とする立体交差高架橋の架設方法。
In a method of constructing a three-dimensional intersection viaduct at an intersection,
Install girder on the main girder in the middle of erection,
Using this girder, the intersection portion of the main girder located between the intersection diameters across the intersection, together with the leg head segments located on both sides in the bridge axis direction of the intersection portion, the intersection diameter In a state where the plurality of precast segments and the both leg head segments constituting the intersection portion are connected and arranged in a span adjacent to the front side between the plurality of precast segments and the both leg head segments connected to each other. After preliminarily erection by performing joint work between each segment and inserting and tensioning PC steel ,
This intersection part is moved between the intersection diameters ,
Then, the installation method of the three-dimensional crossover viaduct characterized by performing the extension installation of the said main girder between the diameters adjacent to the near side between the said diameters of said cross | intersection part .
上記交差部構成部分を予備的に架設する際、該交差部構成部分を上記ガーダに吊下げ固定しておき、
上記交差部構成部分の移動を、上記ガーダを移動させることにより行う、ことを特徴とする請求項1記載の立体交差高架橋の架設方法。
When preliminarily laying the intersection part, the intersection part is suspended and fixed to the girder,
The construction method for a three-dimensional crossover viaduct according to claim 1, wherein the crossing portion is moved by moving the girder.
上記交差部構成部分を予備的に架設する際、該交差部構成部分を所定の走行装置を介して上記ガーダに吊り下げておき、
上記交差部構成部分の移動を、上記走行装置を移動させることにより行う、ことを特徴とする請求項1記載の立体交差高架橋の架設方法。
When preliminarily laying the intersection part, the intersection part is suspended from the girder via a predetermined traveling device,
The construction method for a three-dimensional intersection viaduct according to claim 1, wherein the crossing portion is moved by moving the traveling device.
上記交差部構成部分を予備的に架設する際、この予備的架設と同時に、上記ガーダを用いて、上記交差部径間の前端部に位置する基礎工および橋脚の施工を行う、ことを特徴とする請求項1〜3いずれか記載の立体交差高架橋の架設方法。  When preliminarily constructing the intersection part, the foundation work and the pier located at the front end between the intersection diameters are constructed simultaneously with the preliminary construction using the girder. The construction method of the three-dimensional intersection viaduct according to any one of claims 1 to 3.
JP2003042265A 2003-02-20 2003-02-20 How to install a three-dimensional crossover viaduct Expired - Lifetime JP4128887B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003042265A JP4128887B2 (en) 2003-02-20 2003-02-20 How to install a three-dimensional crossover viaduct

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003042265A JP4128887B2 (en) 2003-02-20 2003-02-20 How to install a three-dimensional crossover viaduct

Publications (2)

Publication Number Publication Date
JP2004250986A JP2004250986A (en) 2004-09-09
JP4128887B2 true JP4128887B2 (en) 2008-07-30

Family

ID=33025591

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003042265A Expired - Lifetime JP4128887B2 (en) 2003-02-20 2003-02-20 How to install a three-dimensional crossover viaduct

Country Status (1)

Country Link
JP (1) JP4128887B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4937838B2 (en) * 2007-05-30 2012-05-23 三井住友建設株式会社 How to build a bridge
JP4860595B2 (en) * 2007-11-30 2012-01-25 株式会社Ihiインフラシステム Viaduct construction method
CN110093864B (en) * 2019-06-17 2021-04-27 秦皇岛天业通联重工科技有限公司 Bridge girder erection machine simple to operate

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0860620A (en) * 1994-08-16 1996-03-05 Mitsui Eng & Shipbuild Co Ltd Installation method of main girder
JP4264470B2 (en) * 1997-02-19 2009-05-20 株式会社横河ブリッジ Bridge girder member erection method and erection device
JP3356048B2 (en) * 1998-02-10 2002-12-09 鹿島建設株式会社 Construction method of elevated structure using building girder
JP2001146716A (en) * 1999-11-22 2001-05-29 Shimizu Corp Bridge girder erection method

Also Published As

Publication number Publication date
JP2004250986A (en) 2004-09-09

Similar Documents

Publication Publication Date Title
JP5477898B2 (en) Construction equipment and construction method for foundation work of directly elevated viaduct
JP2010059748A (en) Apparatus and method for constructing bridge girder
JP4777319B2 (en) Bridge erection method
JP3844743B2 (en) Box girder bridge structure and its construction method
JP2008115628A (en) Construction method for elevated structure
JP2003253621A (en) Continuous beam structure for continuing existing simple beam bridge
JP2004270235A (en) Erection method of bridge
JP4057953B2 (en) Bridge and its construction method
KR100806867B1 (en) Steel pipe roof structure and tunnel structure construction method using the steel pipe loop structure
JP4128887B2 (en) How to install a three-dimensional crossover viaduct
JP3851539B2 (en) Block-type traffic roads, split-bridge-type traffic roads, and bridge traffic roads
JP2005016106A (en) Method for preventing settlement of viaduct
JP4406577B2 (en) Digging road
KR101788581B1 (en) Constructing Method of Bridge with Reinforced Corner Portion and Bridge with the Same
JP3954905B2 (en) Three-dimensional crossing method of plane intersection and viaduct
JP4263935B2 (en) Construction method and elevated detour
JP2005220526A (en) Overhead crossing and its construction method
CN110396946B (en) Method for replacing bridge expansion device
JP4033871B2 (en) How to build a bridge girder
JP7003376B2 (en) Construction method of structure
JP2004278230A (en) Road grade crossing construction method and pier connection structure
JP3380301B2 (en) Viaduct construction method
JP2004250985A (en) Erection method for grade separation viaduct
KR20070088114A (en) Steel pipe roof structure and tunnel structure construction method using the steel pipe loop structure
JP2005060959A (en) Grade separation construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20051027

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070828

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070911

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20071102

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080513

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080515

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110523

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4128887

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110523

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140523

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term