[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

JP4030931B2 - Tunnel widening method - Google Patents

Tunnel widening method Download PDF

Info

Publication number
JP4030931B2
JP4030931B2 JP2003209562A JP2003209562A JP4030931B2 JP 4030931 B2 JP4030931 B2 JP 4030931B2 JP 2003209562 A JP2003209562 A JP 2003209562A JP 2003209562 A JP2003209562 A JP 2003209562A JP 4030931 B2 JP4030931 B2 JP 4030931B2
Authority
JP
Japan
Prior art keywords
segment
widening
moving
widened
excavator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2003209562A
Other languages
Japanese (ja)
Other versions
JP2004143917A (en
Inventor
正典 松浦
幸信 佐々木
健一 亀山
博昭 遠藤
寛昌 五十嵐
智 真鍋
雅由 中川
雅彦 杉山
隆史 東
洋樹 染谷
博英 橋本
裕輔 浅野
崇 國藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2003209562A priority Critical patent/JP4030931B2/en
Publication of JP2004143917A publication Critical patent/JP2004143917A/en
Application granted granted Critical
Publication of JP4030931B2 publication Critical patent/JP4030931B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、拡幅坑に設置されるトンネルの拡幅方法、セグメントおよびシールド機に関するものである。
【0002】
【従来の技術】
シールド機を用いて構築する埋設管渠やトンネル等において、構造上、施工上の制約から、途中に通常部以上の断面を有する拡幅部が必要となる場合がある。例えば、道路や鉄道のトンネルの非常駐車帯や引き込み線やランプ部、共同溝等のケーブル接続部や路線分岐部、小口径シールド工法での坑内バッテリーロコのすれ違い用の部分等である。
【0003】
拡幅部を形成するには、以下に述べるような方法がある。(1)必要最大断面、すなわち拡幅部と同等の断面で、全線を掘削する。地上部分を使用できる場合には、拡幅必要区間の前後に構築した立坑の間を拡幅断面で掘削する。(2)通常断面で掘削した後、拡幅部分周辺に地盤改良等により山留めを形成して覆工を解体し、断面を所定の面積に拡幅する。地盤改良は、坑内または地上から行う。(3)拡幅部分を開削により構築する。
【0004】
他に、(4)掘進途中で掘削面積を自由に拡幅できるシールド機を用いて必要部分のみを拡幅断面で掘削する方法(特開2002−89170、特開2001−329781等)が提案されている。
【0005】
【発明が解決しようとする課題】
しかしながら、(1)の方法では、掘削量が多くなり、(2)の方法では、作業工程が複雑となる。地上部分を使用できない場合、(3)の方法は実施できない。(4)の方法では、(1)から(3)の方法の問題点は解消されるが、シールド機本体を拡幅して拡幅坑用のセグメントを設置するため、シールド機テール部のテールシールとセグメントとの間の止水性の確保が困難である。
【0006】
本発明は、このような問題に鑑みてなされたもので、その目的とするところは、シールド機の通過後にセグメント単独で拡幅することで、シールド機テール部とセグメントとの間の止水性を気にすることなくセグメントを拡幅することができるトンネルの拡幅方法およびセグメントを提供することにある。
【0007】
【課題を解決するための手段】
前述した目的を達成するための第1の発明は、掘削機で余掘り部を有する坑を掘削する工程(a)と、前記余掘り部の内側に拡幅用セグメントリングを設置する工程(b)と、
前記掘削機の通過後に、前記拡幅用セグメントリングを構成するセグメントを前記余掘り部内に移動させる工程(c)と、を具備し、前記セグメントは、セグメントリングの外周方向に移動可能な移動部と、移動しない固定部とからなり、前記移動部は内周面側に拡張部材が設けられ、前記移動部は、前記移動部と前記固定部との間に設けられた可動部を中心に回転移動し、前記移動部と前記固定部との境界部の内周面側と外周面側とにそれぞれシール材が設けられてなることを特徴とするトンネルの拡幅方法である。
また第2の発明は、掘削機で余掘り部を有する坑を掘削する工程(a)と、前記余掘り部の内側に拡幅用セグメントリングを設置する工程(b)と、前記掘削機の通過後に、前記拡幅用セグメントリングを構成するセグメントを前記余掘り部内に移動させる工程(c)と、を具備し、前記セグメントは、セグメントリングの外周方向に移動可能な移動部と、移動しない固定部とからなり、前記移動部は内周面側に拡張部材が設けられ、前記拡張部材の内側に止水枠が配置され、隣接する拡幅セグメントの前記止水枠は、隣接する拡幅セグメントの前記拡幅部材の接触部を包み込むように固定されることを特徴とするトンネルの拡幅方法である。
【0008】
掘削機には、例えば、掘削面積を拡縮できるコピーカッタを有するシールド機が用いられる。工程(a)では、コピーカッタを用いて余掘り部を有する坑が掘削される。なお、コピーカッタでは拡幅巾に限界(300mm程度)があるため、必要に応じて、面板スライド方式を併用してもよい。余掘り部内には、必要に応じて充填材が設置される。充填材のみで余掘り部の安定が保たれない場合には、シールド機から山留め用フードをせり出す。山留め用フードを有するシールド機については、第3の発明の部分で説明する。
【0009】
工程(b)で、余掘り部の内側に拡幅用セグメントリングが設置された時点では、拡幅坑用セグメントリングの外径は、通常断面の掘削坑内に設置されたセグメントリングの外径と同じである。拡幅用セグメントリングを構成するセグメントの一部では、セグメントの内周面側に拡幅部材が設けられる。
【0010】
工程(c)では、拡幅用セグメントリング内に、拡幅用セグメントリングの形状を保持する形状保持装置と、セグメントを移動させる押出し装置とが設置される。形状保持装置は、例えば、移動させないセグメントの内周面側に配置される保持治具と、保持治具をセグメントの内周面側に押付けるジャッキとで構成される。押出し装置は、例えば、移動させるセグメント、すなわち、内周面側に拡幅部材が設けられたセグメントの内周面側に配置される押出し治具と、押出し治具をセグメントの内周面側に押付けるジャッキとで構成される。
【0011】
工程(c)では、形状保持装置を用いて、拡幅用セグメントリングを構成するセグメントのうち移動させないセグメントのリング形状を保持しつつ、押出し装置を用いて、内周面側に拡幅部材が設けられたセグメントを余掘り部内に移動させ、拡幅坑の内壁に沿って配置する。このとき、余掘り部内の圧力状況等に基づいて、必要に応じて、充填材を坑内側に抜き取る。工程(c)の後、移動させたセグメントの拡幅部材の所定の部分が撤去される。
【0012】
施工上の制約からトンネル途中に拡幅部を設けた場合、拡幅部の使用が終了した後、工程(c)で余掘り部内に移動させたセグメントを、余掘り部内からトンネル内周方向に移動させてもよい。これにより、拡幅坑用セグメントリングの外径が通常断面の掘削坑内に設置されたセグメントリングの外径と同じとなり、トンネルが通常幅に戻る。なお、セグメントの移動時には、移動と並行して余掘り部内に充填材または裏込め注入材を設置する。
【0013】
第1の発明および第2の発明では、掘削機で余掘り部を有する坑を掘削し、余掘り部の内側に拡幅坑用セグメントリングを設置する。そして、掘削機の通過後に、拡幅坑用セグメントリングを構成するセグメントの一部を余掘り部内に移動させる。
【0014】
余掘り部を有する坑内に設置されるセグメントは、内周面側に拡幅部材が設けられ、外周面方向に移動可能であることを特徴とするセグメントである。
【0015】
拡幅用セグメントにおいて、少なくとも1ヶ所に本発明のセグメントが配置される。
【0016】
本発明に用いるセグメントでは、端部付近に可動部が設けられる。可動部は、例えば、セグメントの一部にあらかじめ設置される。または、セグメントと周方向に隣接する他のセグメントとの境界部に設置される。
【0017】
可動部は、例えば、セグメントの外周面方向への回転移動の中心となるピンと、セグメント外周面側と内周面側との止水のための止水部材とを有する。止水部材には、ゴム、シール材、防水シート等を用いる。
【0018】
さらに、ピンの回転を固定する回転固定手段を設けてもよい。回転固定手段は、例えば、ピンをセグメントに固定する固定用ピン、セグメントの内周面側等に固定される添接板、ピンの回転によって生じる隙間に固定される楔等である。
【0019】
また、セグメント内に溝を形成し、溝内に連結部材を設け、セグメントリングの外周部に止水のためにゴムを設けてもよい。連結部材の一端は溝内の端部に固定され、他端は溝に沿って移動可能である。
【0020】
さらに、セグメントの外周面と内周面との間にゴムを配置し、ゴムを貫通するワイヤを設け、固定手段を用いてワイヤをセグメントに固定してもよい。ワイヤは、トンネルの周方向、または、トンネルの径の方向に、ゴムを貫通して配置される。セグメントの外周面と内周面との間にゴムを配置し、固定手段を用いてゴムをセグメントに固定してもよい。
【0021】
本発明に用いるセグメントでは、軸方向に隣接するセグメントとの間に止水機構を設けてもよい。止水機構とは、軸方向に隣接するセグメントと擦れ合う面に設けられたリップシールや、リング間ボルト締結機構のボルトに設けられたシール材等である。
【0022】
拡幅部材の周囲には、周方向や前後方向に隣接するセグメントとの間の止水のための部材が設けられる場合がある。止水のための部材は、例えば、拡幅部材の内側に設けられた鋼製の部材である。
【0023】
本発明に用いるセグメントでは、外周面方向、すなわち余掘り部内への移動後、拡幅部材の一部、または、拡幅部材と止水のための部材の一部が撤去される。
【0024】
第3の発明は、掘削機本体の周囲に、前記掘削機本体の外周方向に張り出し可能な山留め用フードが設けられることを特徴とするシールド機を用いたトンネルの拡幅方法である。
【0025】
山留め用フードは、掘削機本体の外周の少なくとも1ヶ所に設けられ、第1又は第2の発明の工程(a)においてコピーカッタや面板スライド方式により掘削された余掘り部の壁面に沿うように張り出される。
【0026】
山留め用フードには、必要に応じて、フード本体の後方に設置されるリアフード、前方に設置されるフロントフード等を設けてもよい。山留め用フードは、例えば、通常時にはリアフードやフロントフードをフード本体と重ねて格納し、伸縮時には伸長させることにより、掘削機本体の軸方向に伸縮可能とできる。なお、リアフードやフロントフードを伸縮可能とせず、フード本体と一体化して設けてもよい。
【0027】
【発明の実施の形態】
以下、図面に基づいて、本発明の第1の実施の形態について詳細に説明する。図1は、シールド掘削機1で、拡幅坑12を有するトンネル8を掘削する工程を示す図である。図1に示すように、シールド掘削機1は、掘削機本体3、掘削用カッタ5、コピーカッタ7等で構成される。さらに、必要に応じて、面板スライド機構(図示せず)や山留め用フード101(図16)を有する。
【0028】
掘削用カッタ5は、筒状の掘削機本体3の端面に設けられる。コピーカッタ7は、例えば、掘削用カッタ5の一部として設けられ、必要に応じて、シールド掘削機1の側方に伸長可能である。面板スライド機構(図示せず)は、掘削用カッタ5を掘削機本体3の周方向にスライドさせる機構である。
【0029】
図1(a)は、トンネル8の通常坑10を掘削する工程を示す。通常坑10とは、トンネル8を構築するために掘削される坑道のうち、通常の周方向断面を有する部分である。図1(a)に示すように、シールド掘削機1は、コピーカッタ7を掘削用カッタ5内に格納した状態で地山9を掘削し、トンネル8の通常坑10を形成する。掘削機本体3の後部では、通常坑10の内部にセグメント11が設置される。
【0030】
図1(b)は、トンネル8の拡幅坑12を掘削する工程を示す。図2は、図1(b)のA−A断面図を示す。拡幅坑12とは、トンネル8を構築するために掘削される坑道のうち、通常坑10より周方向断面が拡幅された部分であり、図1(b)、図2に示すように、掘削機本体3の外側に余掘り部17が形成される。
【0031】
図1(b)に示すように、シールド掘削機1は、コピーカッタ7を掘削用カッタ5の周方向に伸長させ、掘削用カッタ5で通常断面を掘削しつつ、コピーカッタ7で余掘り部17を掘削して、トンネル8の拡幅坑12を形成する。なお、掘削する余掘り部17の幅に応じて、コピーカッタ7と面板スライド機構(図示せず)とを併用して余掘り部17を掘削する。
【0032】
掘削機本体3の後部では、通常坑10と拡幅坑12との境界部の通常坑10の内壁に、必要に応じて、調整セグメント13を有する調整用セグメントリング19が設置される。調整セグメント13、調整用セグメントリング19の詳細については、後述する。なお、拡幅坑12の内壁と掘削機本体3の間の余掘り部17には、必要に応じて、充填材を充填する。充填材は、通常の性質のものの他に、凝固が遅いものを用いてもよい。
【0033】
図1(c)は、拡幅用セグメントリング21を設置する工程を示す。図1(c)に示すように、図1(b)に示す状態から地山9をさらに掘削し、掘削機本体3の後部で拡幅セグメント15を有する拡幅用セグメントリング21を設置していく。
【0034】
図3は、拡幅用セグメントリング21の斜視図である。図3に示すように、拡幅用セグメントリング21は、通常坑10に設置されるセグメント11と同様のセグメント23、内周面側に拡幅部材24を有する拡幅セグメント15で構成される。拡幅セグメント15は、拡幅用セグメントリング21の外周方向に移動可能な移動部分28と、移動しない固定部分30とからなる。
【0035】
図4、図5は、可動部22付近の拡大図である。図4は、図5のY−Yによる断面図、図5は、図4のX−Xによる断面図である。拡幅セグメント15の移動部分28と固定部分30との間には、可動部22が設けられる。可動部22は、鋼管46、鋼棒47、芯円固定用ピン20、シール材32、防水シート34等で構成される。
【0036】
図4に示すように、拡幅セグメント15の固定部分30と移動部分28の境界部には、シール材32が設置される。シール材32は、拡幅セグメント15の内周面側に設置されるシール材32aと、外周面側に設置されるシール材32bとからなる。シール材32a、シール材32bは、それぞれ、固定部分30と移動部分28のいずれかに固定される。また、拡幅セグメント15の外周面に沿って、防水シート34が設置される。シール材32、防水シート24は、止水性および弾力性のある材質とする。
【0037】
図5に示すように、鋼管46は、拡幅セグメント15の固定部分30と移動部分28の境界部に配置され、複数の鋼管46aおよび鋼管46bからなる。鋼管46aは拡幅セグメント15の固定部分30に固定され、鋼管46bは移動部分28に固定される。鋼管46aと鋼管46bの管内には、鋼棒47が配置される。
【0038】
図4、図5に示すように、拡幅セグメント15の固定部分30の端部には、芯円固定用ピン20aが設置される。芯円固定用ピン20aは、固定部分30に固定された鋼管46aを貫通し、鋼棒47を拡幅セグメント15の固定部分30の端部に固定する。移動部分28には孔36aが、鋼管46aには孔36bが設けられる。
【0039】
図4、図5に示す状態では、鋼管46bと拡幅セグメント15の移動部分28は、拡幅セグメント15の固定部分30の端部に固定された鋼棒47を中心として、図4に示す矢印E方向に回転可能である。移動部分28は、移動部分28の孔36aと鋼管46aの孔36bとが重なるように、矢印E方向に回転される。孔36aと孔36bからなる孔36には、鋼管46aと鋼棒47とを拡幅セグメント15の移動部分28の端部に固定するための芯円固定用ピン20bが挿入される。
【0040】
移動部分28の移動前、すなわち図4に示す状態では、シール材32aと防水シート34が拡幅セグメント15の外周側から内周側への漏水を防止する。移動部分28を移動し、芯円固定用ピン20bで移動部分28を固定した状態では、シール材32bが固定部分30に接触し、シール材32bと防水シート34が拡幅セグメント15の外周側から内周側への漏水を防止する。
【0041】
図1(c)では、拡幅用セグメントリング21は、余掘り部17の内側に設置される。この時、拡幅用セグメントリング21は図3に示す状態であり、拡幅用セグメントリング21の外径は、通常坑10に設置されたセグメントリングや調整用セグメントリング19の外径と同じである。
【0042】
調整用セグメントリング19の調整セグメント13は、拡幅用セグメントリングの拡幅セグメント15に隣接して設置される。調整セグメント13は、通常坑10のセグメント11と拡幅セグメント15との間を滑らかにつなぐための部材である。図1(c)に示すように、調整セグメント13の内周面16は、通常坑10のセグメント11の内周面14から拡幅セグメント15の内周面26に向けた勾配を有する。
【0043】
図1(c)に示す状態のとき、トンネル8の軸方向に隣接するセグメントリングは、リング間ボルト締結機構で連結される。拡幅用セグメントリング21は、側面に設けられたリング間ボルト締結機構18、18aを用いて、隣接するセグメントリングに連結される。図6は、リング間ボルト締結機構18a付近の断面図を示す。図6は、図1(c)のXに示す部分の拡大図である。
【0044】
図6に示すように、リング間ボルト締結機構18aは、ナット101、ナット103、全ネジボルト105、シール材107、鞘111等で構成される。拡幅セグメント15bに設けられた鞘111bの内部には、ナット101が固定され、隣接する拡幅セグメント15aに設けられた鞘111aの内部には、ナット103が固定される。
【0045】
拡幅セグメント15aと拡幅セグメント15bとを連結するには、六角レンチ109等を用いてナット101とナット103に全ネジボルト105をねじ込む。なお、全ネジボルト105の端部113には、シール材107が設けられる。
【0046】
図7は、拡幅用セグメントリング21内に形状保持装置25を設置した状態を示す図である。図7は、図1(c)のB−Bに示す位置での断面図である。拡幅坑12内に設置された拡幅用セグメントリング21の内部には、図7に示すように、形状保持装置25が設置される。
【0047】
形状保持装置25は、例えば、保持治具29、保持治具31、ジャッキ27等で構成される。保持治具31は、拡幅用セグメントリング21の最下部のセグメント23に沿って配置される。ジャッキ27の両端は、それぞれ、保持治具31と保持治具29に連結される。ジャッキ27は、鉛直方向に伸縮可能で、保持治具29を上下に移動させる。保持治具29は、ジャッキ27によって、拡幅用セグメントリング21の最上部のセグメント23に押付けられる。
【0048】
図1(c)に示す状態で、シールド掘削機1から拡幅セグメント15にトンネル軸方向の力が伝達されないよう、拡幅セグメント15の前方のセグメント11から、シールド掘削機1の推進ジャッキ(図示せず)を離す。それと前後して、図7に示すように、ジャッキ27を矢印Eに示す方向に伸ばす。
【0049】
図8は、拡幅用セグメントリング21内に押出し装置33を設置した状態を示す図である。押出し装置33は、例えば、押出し治具37、ジャッキ35等で構成される。押出し治具37は、拡幅用セグメントリング21の拡幅セグメント15に沿って配置される。ジャッキ35の一端は、ピン41を用いて押出し治具37に連結され、他端は、ピン39を用いてジャッキ27に連結される。
【0050】
押出し治具37は、ジャッキ35の伸縮によって、拡幅セグメント15の内周面26に押付けられる。なお、押出し装置33は、図8の矢印Fに示す方向にジャッキ35を伸ばす際に反力を取れる構造であればよい。ジャッキ35の端部はジャッキ27に連結されなくてもよい。
【0051】
図8では、ジャッキ27を用いて、保持治具29を拡幅用セグメントリング21の最上部のセグメント23に押し付け、拡幅用セグメントリング21のセグメント23の形状を保持した状態で、ジャッキ35を矢印Fに示す方向に伸ばし、押出し治具37を拡幅セグメント15の内周面26に押付ける。
【0052】
図9は、リング間ボルト締結機構18a付近の断面図を示す。図8に示すように形状保持装置25や押出し装置33を設置するのと前後して、図9に示すように、六角レンチ109等を用いて全ネジボルト105をナット101から取り外し、全ネジボルト105を拡幅セグメント105a内に格納して、拡幅セグメント15aと拡幅セグメント15bとの連結を解除する。なお、シール材107を鞘111aに押し付けることで、鞘111aが密閉され、拡幅セグメント15a15bの外周側から拡幅セグメント15a内部への漏水を防ぐことができる。
【0053】
拡幅セグメント15と隣接するセグメントとの連結を解除した後、ジャッキ35を伸ばし、拡幅セグメント15の移動部分28を図8の矢印Gに示す方向に押出す。拡幅セグメント15の移動部分28は、図4、図5を用いて説明したように、可動部22の鋼棒47を中心として回転可能である。
【0054】
図10は、押出し装置33を用いて拡幅セグメント15の移動部分28を押出した状態を示す図である。図8に示す状態から、押出し装置33で拡幅セグメント15の移動部分28を押出し、図10に示す状態にする。そして、前述したように、図4、図5に示す芯円固定用ピン20bを用いて、移動部分28を固定する。図1(d)は、拡幅セグメント15を余掘り部17内に移動させ、拡幅坑12の内壁に沿って配置した状態を示す。図10は、図1(d)のC−C断面図である。
【0055】
形状保持装置25と押出し装置33を用いて、トンネル8の軸方向に配置された全ての拡幅用セグメントリング21の拡幅セグメント15を順次余掘り部17に移動させ、図1(d)に示す状態にする。拡幅セグメント15は、外周面が拡幅坑12の内壁に沿うように配置され、隣接する拡幅セグメント15は、リング間ボルト締結機構18を再度図6に示す状態に戻すことにより、連結される。なお、余掘り部17に充填材を設置した場合には、必要に応じて、充填材をトンネル8の坑内に吸入する。
【0056】
拡幅セグメント15の内周面側に設置された拡幅部材24には、図1(d)、図10に示すように、仮設部43(43a、43b)が設けられる。仮設部43の位置は、拡幅セグメント15の設置位置によって異なる。調整セグメント13に隣接しない拡幅セグメント15bでは、図1(d)や図10に示すように、周方向に隣接するセグメント23に接する面を除く部分が仮設部43bである。
【0057】
調整セグメント13に隣接する拡幅セグメント15aでは、図1(e)に示すように、周方向に隣接するセグメント23に接する面と、調整セグメント13に接する面とを除く部分が仮設部43aである。
【0058】
図11は、仮設部43bを撤去した後の状態を示す図である。図1(e)は、仮設部43を撤去した状態を示す。図11は、図1(e)のD−D断面図である。図1(d)や図10に示す状態から、仮設部43等を撤去し、図1(e)や図11に示す状態にする。
【0059】
図1(e)、図11に示すように、拡幅用セグメントリング21a、拡幅用セグメントリング21bでは、拡幅セグメント15aの仮設部43a、拡幅セグメント15bの仮設部43bをそれぞれ撤去して、拡幅部45aと拡幅部45bを形成する。また、調整用セグメントリング19では、調整セグメント13の内周面16付近を撤去し、トンネル軸方向に隣接するセグメント11の内周面14に面位置を合わせる。そして、図1(e)に示すように、拡幅坑12付近の覆工を完成する。
【0060】
このように、第1の実施の形態では、コピーカッタ7を有するシールド掘削機1を用いて掘削した拡幅坑12の余掘り部17の内側に拡幅用セグメントリング21を組み立て、掘削機本体3が拡幅坑12を通過した後、拡幅セグメント15を余掘り部17内に移動させる。拡幅用セグメントリング21の外径は、設置時には通常坑10に設置されるセグメントリングの外径と等しいため、掘削機本体3のテール部と拡幅用セグメントリング21との止水性を確保できる。
【0061】
次に、第2の実施の形態について説明する。第2の実施の形態では、第1の実施の形態と同様の工程でトンネル8の拡幅坑12付近を覆工するが、拡幅用セグメントリング21aの拡幅セグメント15a、拡幅用セグメントリング21bの拡幅セグメント15bの替わりに、拡幅セグメント51a、拡幅セグメント51bを使用する。
【0062】
図12は、拡幅用セグメントリング21を設置した状態のトンネル軸方向の断面図である。図12は、第1の実施の形態の図1(c)に示す状態に相当する。第2の実施の形態では、図12に示すように、拡幅坑12を掘削した後、余掘り部17の内側に、拡幅セグメント51を有する拡幅用セグメントリング21を設置する。
【0063】
拡幅セグメント51は、本体55、止水枠53等で構成される。本体55は、通常のセグメント11の内周面側に拡幅部材54を設けたものである。本体55は、例えば、外郭の形状が拡幅セグメント15とほぼ同様の箱体であり、可動部22を用いて外周面方向に移動可能である。隣接する拡幅セグメント51は、拡幅部材54が接触するように配置される。
【0064】
止水枠53は、本体55の拡幅部材54の内側に配置される。隣接する拡幅セグメント51の止水枠53は、隣接する拡幅セグメント51の拡幅部材54の接触部を包み込むように、止め具52を用いて固定される。調整セグメント13に隣接して配置される拡幅セグメント51aの止水枠53aは、止め具52を用いて調整セグメント13に固定される。止水枠53は、本体55の移動時に余掘り部17からトンネル坑内への漏水を防止する。
【0065】
図13は、拡幅セグメント51の本体55を移動させる工程を示すトンネル軸方向の断面図である。図13は、第1の実施の形態の図1(c)から図1(d)にへの移行状態に相当する。図12に示すように拡幅用セグメントリング21を設置した後、シールド掘削機1から拡幅セグメント51にトンネル軸方向の力が伝達されないよう、拡幅セグメント51の前方のセグメント11から、シールド掘削機1の推進ジャッキ(図示せず)を離す。但し、図13中に破線で示したように推力伝達材50を設置し、調整セグメント13から止水枠53へ推力を伝達すれば、推進ジャッキを離す必要はない。
【0066】
そして、図13に示すように、拡幅セグメント51aの本体55a、拡幅セグメント51bの本体55bを、順次余掘り部17内に移動させる。本体55aの調整セグメント13に隣接する拡幅部材54の端部は、止め具56を用いて調整セグメント13と止水枠53aに固定される。また、他の拡幅部材54の端部は、止め具56(図14)を用いて隣接する拡幅セグメント51の拡幅部材54に固定される。なお、本体55aや本体55bの移動には、必要に応じて、第1の実施の形態で使用した形状保持装置25や押出し装置33を用いる。
【0067】
図14は、拡幅坑12の覆工が完成した状態でのトンネル軸方向の断面図を示す。全ての拡幅セグメント51の本体55を拡幅坑12の内壁に沿って配置した後、図14に示すように、拡幅セグメント51では、止め具56より内側に位置する止水枠53と拡幅部材54を撤去する。また、調整セグメント13においても、止め具56より内側の部分を撤去する。そして、図14に示すように、拡幅坑12付近の覆工を完成する。
【0068】
このように、第2の実施の形態においても、第1の実施の形態と同様に、拡幅用セグメントリング21を拡幅坑12の余掘り部17の内側に組み立て、掘削機本体3が拡幅坑12を通過した後、拡幅セグメント51の本体55を余掘り部17内に移動させるため、掘削機本体3のテール部と拡幅用セグメントリング21との止水性を確保できる。また、拡幅セグメント51の本体55の内側に止水枠53を設けることで、本体55を余掘り部17内に移動させる際に、隣接する拡幅セグメント55の間の止水性が向上する。
【0069】
なお、第2の実施の形態では、拡幅坑12の断面積を一定としたが、拡幅坑12の断面積を段階的に変化させることもできる。図15は、断面積が一定でない拡幅坑12aのトンネル軸方向の断面図である。
【0070】
図15に示すように、拡幅セグメント51a、拡幅セグメント51bの本体55a、本体55bの外周面の位置をずらして配置し、止め具56で拡幅部材54を固定し、止水枠53や拡幅部材54の一部を撤去することにより、断面積が一定でない拡幅坑12aを覆工できる。図12から図15では、止水枠53と拡幅部材43の接触面や、拡幅部材54と拡幅部材54の接触面にリップシール(図示せず)を設けることで、止水性がさらに向上する。
【0071】
次に、第3の実施の形態について説明する。図16は、第3の実施の形態で使用する掘削機101および掘削機101を用いて設置されたセグメントの斜視図である。図17は、山留めフード103を張り出した掘削機101および掘削機101を用いて設置されたセグメントの斜視図である。第3の実施の形態では、第1の実施の形態の掘削機1の代わりに掘削機101を用いて、拡幅坑を有するトンネルを掘削する。充填材の充填のみで余掘り部17(図1)の壁面の安定が保たれない場合には、掘削機101を使用するのが好ましい。
【0072】
掘削機101は、掘削機本体3、掘削カッタ5、山留めフード103、テール拡幅部107等で構成される。掘削機101は、第1の実施の形態で使用した掘削機1の掘削機本体3の外周からテール拡幅部107を張り出す。テール拡幅部107は、掘削機本体3のテール部付近に設けられる。山留めフード103は、テール拡幅部107の外周面であるフード本体115、フロントフード105、リアフード109からなる。
【0073】
フロントフード105は、例えば、テール拡幅部107のフード本体115と一体であり、テール拡幅部107と同時に掘削機本体3の外周方向に張り出される。テール拡幅部107からは、リアフード109が伸長される。山留めフード103は、図17に示すように、テール拡幅部105を掘削機本体3の外周方向に張り出すことにより、拡幅坑12(図1)の壁面を支持する。なお、図16に示す状態では、リアフード109は、フード本体115の内側に重ねてテール拡幅部107内に格納される。
【0074】
掘削機101は、図1に示す掘削機1と同様に、掘削機5、コピーカッタ7、面板スライド機構(図示せず)等を用いて、通常坑10や、余掘り部17を有する拡幅坑12を地山9内に掘削する。
【0075】
図16に示すように、掘削機101は、通常坑を掘削する際には山留めフード103を張り出さずに掘削しつつ、テール部で通常坑内にセグメント11を設置する。拡幅坑を掘削する際には、山留めフード103を張り出さずに掘削しつつ、テール部で調整用セグメントリング19や拡幅用セグメントリング21を設置する。拡幅坑の余掘り部内には、充填材を充填する。
【0076】
そして、適切な時期に、図17に示すように、拡幅坑(図示せず)の壁面に沿って山留めフード103とフロントフード105を張り出し、さらに、リアフード109をテール拡幅部107から伸長する。このとき、リアフード109の最後尾111が、拡幅予定の拡幅用セグメントリング21の最後尾113と一致するようにする。
【0077】
図17に示す状態で、掘削カッタ5で地山を掘削しつつ、拡幅用セグメントリング21の拡幅セグメント(図示せず)を拡幅用セグメントリング21の外周方向に移動させて、拡幅坑を覆工する。そして、拡幅区間終了時に、リアフード109をテール拡幅部107内に、テール拡幅部107を掘削機本体3内に格納する。
【0078】
このように、第3の実施の形態では、山留めフード103を有する掘削機101を用いることにより、余掘り部の壁面の維持が容易になる。また、山留めフード103を張り出すことで、掘削機101の掘削方向や姿勢制御が可能となる。
【0079】
なお、図16、図17に示す掘削機101では、フロントフード105がフード本体115と一体化されているが、フロントフード105をリアフード109と同様にテール拡幅部107に格納し、伸縮可能にしてもよい。また、フロントフード105やリアフード109を設けない場合もある。
【0080】
次に、第4の実施の形態について説明する。図18は、第4の実施の形態で使用する拡幅用セグメントリング21の一部の斜視図である。第4の実施の形態においても、第1、第2の実施の形態と同様の工程でトンネル8の拡幅坑12付近を覆工するが、拡幅用セグメントリング21の拡幅セグメント15の替わりに、拡幅セグメント57を使用する。
【0081】
図18は、図1(c)に示す工程での拡幅セグメント57の状態を示す。拡幅セグメント57は、内周面に拡幅部材58を有する。拡幅部材58には、適切な部分に仮設部59が設けられる。
【0082】
図18に示す状態の拡幅用セグメントリング21を拡幅坑12の余掘り部17の内側に設置し、掘削機本体3が拡幅坑12を通過した後、シールド掘削機1から拡幅セグメント57にトンネル軸方向の力が伝達されないよう、拡幅セグメント57の前方のセグメントから、シールド掘削機1の推進ジャッキ(図示せず)を離す。
【0083】
そして、複数の拡幅セグメント57をそれぞれ図18の矢印Hに示す方向に押し出して余掘り部17内に移動させ、拡幅坑12の内壁に沿って配置する。拡幅セグメント57の移動には、必要に応じて、第1の実施の形態で使用したような形状保持装置や押出し装置を用いる。
【0084】
図19は、仮設部59を撤去した拡幅用セグメントリング21の一部の斜視図である。拡幅セグメント57を余掘り部17内に押し出した後、拡幅セグメント37の仮設部59を撤去し、拡幅用セグメントリング21内に拡幅部60を形成する。
【0085】
なお、図18、図19に示す拡幅セグメント57は、調整セグメント13に隣接しないものである。調整セグメント13に隣接する拡幅セグメント57では、仮設部は、調整セグメント13に接する面および周方向に隣接するセグメント23に接する面を除く部分に設けられる。
【0086】
拡幅セグメント57のリング間ボルト締結機構18、18a(図18、図199)は、第1の実施の形態の拡幅セグメント15のリング間ボルト締結機構18、18aと同様の構成である。拡幅セグメント57では、拡幅前にリング間ボルト締結機構18aを図6に示す状態から図9に示す状態にして、隣接するセグメントとの連結を解除する。また、拡幅セグメント57を拡幅坑12内に移動した後、リング間ボルト締結機構18aを図6に示す状態に戻して隣接するセグメントと再連結する。
【0087】
第4の実施の形態においても、第1、第2の実施の形態と同様に、拡幅用セグメントリング21を拡幅坑12の余掘り部17の内側に組み立て、掘削機本体3が拡幅坑12を通過した後、拡幅セグメント57を余掘り部17内に移動させるため、掘削機本体3のテール部と拡幅用セグメントリング21との止水性を確保できる。
【0088】
次に、第5の実施の形態について説明する。図20は、拡幅部45a、拡幅部45bが設けられた部分を通常幅に戻す工程を示す図である。図20の(a)は、内部に拡幅部45a、拡幅部45bを設けたトンネル8を示す。図20の(b)は、拡幅セグメント15a、拡幅セグメント15bを移動させて内空の幅を一定としたトンネル8を示す。
【0089】
図20の(a)に示すトンネル8は、例えば、第1の実施の形態で説明した方法で構築される。トンネル8の拡幅部45a、拡幅部45bが、トンネル8の施工時に必要で、完成後は必要でない場合、施工後、図20の(b)に示すように、拡幅部45a、拡幅部45bが設けられた部分のシールド幅を通常幅に戻し、トンネル8の内空の幅を一定とする。図20に示す工程は、例えば、拡幅部45a、拡幅部45bが小口径長距離シールドの資材搬送用台車の坑内離合(すれ違い)に使用される場合に適用される。
【0090】
トンネル8の内空の幅を一定とするには、図20の(a)に示す拡幅用セグメントリング21a、拡幅用セグメントリング21bの外径と通常坑10のセグメントリングとの外径とが同じになるように、拡幅用セグメントリング21aの拡幅セグメント15a、拡幅用セグメントリング21bの拡幅セグメント15bを、トンネル8の内周方向に移動させる。
【0091】
拡幅セグメント15a、拡幅セグメント15bの移動と並行して、図20の(b)に示すように、拡幅セグメント15a、拡幅セグメント15bの外側の余掘り部17(図1)に充填材または裏込め注入材117を注入する。充填材または裏込め注入材117の注入は、拡幅セグメント15a、拡幅セグメント15bに設けた注入孔(図示せず)を介して行う。充填材または裏込め注入材117は、通常の性質のものの他に、凝固が遅いものを用いてもよい。
【0092】
拡幅セグメント15a、拡幅セグメント15bのトンネル内周方向への移動は、第1の実施の形態で述べた、トンネル外周方向(図8の矢印G方向)への移動と逆の手順で行う。拡幅セグメント15a、拡幅セグメント15bをトンネル内周方向に引き寄せるには、図8に示すジャッキ35、ジャッキ27等を用いる。
【0093】
第5の実施の形態では、拡幅坑12を設けた部分のトンネル8のシールド幅を、施工中のみ拡幅した後、通常坑10の部分と同等に戻すので、地下の占有が短期間で済み、地上施設管理者に対する地下占有に関する許可が基本的に不要となる。
【0094】
このように、第1から第5の実施の形態では、掘削機本体3が拡幅坑12を通過した後、拡幅セグメントを余掘り部17内に移動させるので、掘削機本体3のテール部と拡幅用セグメントリング21との止水性を確保できる。なお、使用する拡幅用セグメントは、第1、第2、第4、第5の実施の形態で使用した拡幅セグメント15、拡幅セグメント51、拡幅セグメント57に限らない。拡幅セグメントは、内周面側に拡幅部材が設けられ、余掘り部17の内側に設置された後、余掘り部17内に移動ができるような構造であればよい。
【0095】
図21は、他の拡幅セグメント61を有する拡幅用セグメントリング21の斜視図である。拡幅セグメント61は、本体63、拡幅部材64、拡幅部材65等で構成される。拡幅部材64、拡幅部材65は、いずれも本体63の内周面側に設けられる部材であるが、拡幅部材64は本体63と一体化した部材であり、拡幅部材65は、本体63と一体化されない部材である。
【0096】
本体63は、例えば、可動部22を用いてセグメント23に連結され、可動部22を回転の中心として、矢印Iに示す方向に移動可能である。本体63には、ピン69の位置をガイドするガイド溝67が設けられ、拡幅部材65に固定されたピン69の端部がガイド溝67内に配置される。
【0097】
図22は、拡幅セグメント61を移動させた拡幅用セグメントリング21の斜視図である。図22に示すように、拡幅部材65を本体63と周方向に隣接するセグメント23との間に移動させ、拡幅セグメント61を拡幅坑12の余掘り部17の内部に配置する。このとき、拡幅部材65に固定されたピン69は、本体63のガイド溝67に沿って移動する。
【0098】
拡幅部材64、拡幅部材65には、それぞれ、適切な部分に仮設部66、仮設部68が設けられる。これらの仮設部66、仮設部68を撤去することにより、拡幅用セグメントリング21の内部に拡幅部が形成される。本体63に設けられたリング間ボルト締結機構18aは、拡幅セグメント15、拡幅セグメント57に設けられたリング間ボルト締結機構18aと同様にして用いられる。
【0099】
また、可動部22の構造は、図4に示すものに限らない。可動部22は、拡幅用セグメントリング21の外周側と内周側との止水性を確保しつつ、拡幅セグメントを移動させることができる構造であればよい。図23から図29は、他の構造の可動部22を示す図である。
【0100】
図23に示す可動部22は、拡幅セグメント15の移動部分28と固定部分30との境界部に設けられ、ピン73、ゴム71等で構成される。ピン73は、拡幅セグメント15の移動部分28の端部と固定部分30の端部とをヒンジ結合する。止水用のゴム71は、移動部分28と固定部分30との境界部に設けられる。拡幅セグメント15の移動部分28は、図23の矢印Jに示すように、ピン73を中心として回転可能である。
【0101】
図24に示す可動部22は、拡幅セグメント15の移動部分28と固定部分30との境界部に設けられ、拡幅セグメント15に設けられた溝である主管83と枝管85、金具81、固定ピン77、移動ピン79、ゴム75等で構成される。
【0102】
金具81は、拡幅セグメント15の移動部分28と固定部分30とを連結する。金具81を配置するための主管83は、移動部分28と固定部分30の内部に配置される。移動部分28の内部には、さらに、主管83から枝分かれした枝管85が配置される。移動部分28と固定部分30の接触部の外周面側には、ゴム75が設けられる。
【0103】
金具81の一端は、固定ピン77として固定部分30の主管83の端部に固定される。金具81の他端には、移動ピン79が設けられる。移動ピン79は、移動部分28の移動前には、図24に示すように、移動部分28の主管83の内部に格納されている。移動部分28を矢印Kに示す方向に移動させると、ゴム75が縮み、移動ピン79が移動部分28内の主管83から移動して枝管85に格納される。
【0104】
図25に示す可動部22は、拡幅セグメント15の移動部分28と固定部分30との境界部に設けられ、ワイヤ87、止め具89、ゴム91等で構成される。ゴム91は、拡幅セグメント15の移動部分28と固定部分30との間に設けられる。ゴム91の内部には、トンネル周方向にワイヤ87が配置される。
【0105】
ワイヤ87の両端部には、それぞれネジ山が設けられる。ワイヤ87の両端部は、止め具89を用いて、移動部分28と固定部分30とに固定される。ワイヤ87およびゴム91を変形させることにより、移動部分28を矢印Lに示す方向に移動させることができる。
【0106】
図26に示す可動部22は、拡幅セグメント15の移動部分28と固定部分30との境界部に設けられ、ワイヤ93a、ワイヤ93b、止め具95、ゴム97等で構成される。ゴム97は、拡幅セグメント15の移動部分28と固定部分30との間に設けられる。
【0107】
ゴム97は、固定部分30を外周側から内周側まで貫通するワイヤ93aと、移動部分28を外周側から内周側まで貫通するワイヤ93bとによって、固定部分30と移動部分28に固定される。ワイヤ93a、ワイヤ93bは、それぞれ、止め具95を用いて固定部分30、移動部分28に固定される。ゴム97を変形させることにより、移動部分28を矢印Mに示す方向に移動させることができる。
【0108】
図27に示す可動部22は、拡幅セグメント15の移動部分28と固定部分30との境界部に設けられ、止め具98、ゴム99等で構成される。ゴム99は、拡幅セグメント15の移動部分28と固定部分30との間に設けられる。ゴム99の周方向の端部は、それぞれ、止め具98を用いて固定部分30、移動部分28に固定される。ゴム99を変形させることにより、移動部分28を矢印Nに示す方向に移動させることができる。
【0109】
図28に示す可動部22は、図4に示す可動部22とほぼ同様の構成であるが、図4の矢印Eに示す方向に回転させ、芯円固定用ピン20bを鋼棒47に固定した後、拡幅セグメント15の内周面側に、添接板121が取り付けられる。添接板121は、ボルト123とナット125を用いて移動部分28と固定部分30とに固定される。
【0110】
図29、図30に示す可動部22は、拡幅セグメント15の移動部分28と固定部分30との境界部に設けられ、ピン127、回転板129、防水シート131、楔137等で構成される。ピン127は、拡幅セグメント15の固定部分30と移動部分28の境界部に配置される。防水シート131は、拡幅セグメント15の外周面に沿って設置される。回転板129は、防水シート131の内側に設置される。防水シート131は、止水性および弾力性のある材質、回転板129は変形可能な材質とする。
【0111】
図29に示す状態では、移動部分28と固定部分30とは、ボルト135とナット133を用いて固定されている。ボルト135とナット133を撤去することにより、ピン127を回転の中心として移動部分28を矢印Oに示す方向に移動させることができる。
【0112】
移動部分28を図29の矢印Oに示す方向に回転させた後、図30に示すように、移動部分28と固定部分30との間に楔137を配置する。さらに、移動部分28と楔137と固定部分30とを、テーパーワッシャ143を介してボルト139とナット141とで締付ける。このとき、テーパーワッシャ143に設けるボルト139用の孔を長穴にしておくと、組み立てが容易になる。
【0113】
図4、図5および図21から図27では、拡幅セグメント15(拡幅セグメント55、拡幅セグメント61)を移動部分28と固定部分30に分割し、移動部分28と固定部分30の境界部に可動部22を設けたが、可動部22の設置位置はこれに限らない。拡幅セグメント15(拡幅セグメント55、拡幅セグメント61)を移動部分28と固定部分30に分割せず、拡幅セグメントと、周方向に隣接する他のセグメントとの境界部に可動部22を設けてもよい。この場合、可動部22を用いて拡幅セグメント全体がセグメントリングの周方向に移動する。
【0114】
さらに、形状保持装置、押出し装置の構成は、図7から図10に示すものでなくてもよい。形状保持装置は、拡幅セグメントの移動中に、他のセグメント23の形状を保持できる構造であればよい。また、押出し装置は、拡幅セグメントを拡幅用セグメントリング21の外周方向に押出せる構造であればよい。拡幅セグメントの移動の形態として、拡幅セグメント15や拡幅セグメント61のような回転移動、拡幅セグメント57のような平行移動等が考えられる。押出し装置は、使用される拡幅セグメントの移動形態に応じた構造とする。
【0115】
拡幅セグメント15、拡幅セグメント51等の拡幅セグメントは、鋼製とするのが望ましいが、他の材質で形成してもよい。また、図1では、トンネル8の一方の側面に余掘り部17を設けて拡幅部を形成したが、余掘りを行う位置はこれに限らない。例えば、両側面に余掘り部を掘削して拡幅部を形成してもよい。
【0116】
【発明の効果】
以上、詳細に説明したように、本発明によれば、シールド機の通過後にセグメント単独で拡幅することで、シールド機テール部とセグメントとの間の止水性を気にすることなくセグメントを拡幅することができるトンネルの拡幅方法、セグメントおよびシールド機を提供できる。
【図面の簡単な説明】
【図1】シールド掘削機1で、拡幅坑12を有するトンネル8を掘削する工程を示す図
【図2】図1(b)のA−A断面図
【図3】拡幅用セグメントリング21の斜視図
【図4】可動部22付近の拡大図
【図5】可動部22付近の拡大図
【図6】リング間ボルト締結機構18a付近の断面図
【図7】拡幅用セグメントリング21内に形状保持装置5を設置した状態を示す図
【図8】拡幅用セグメントリング21内に押出し装置33を設置した状態を示す図
【図9】リング間ボルト締結機構18a付近の断面図
【図10】押出し装置33を用いて拡幅セグメント15の移動部分28を押出した状態を示す図
【図11】仮設部43bを撤去した後の状態を示す図
【図12】拡幅用セグメントリング21を設置した状態のトンネル軸方向の断面図
【図13】拡幅セグメント51の本体55を移動させる工程を示すトンネル軸方向の断面図
【図14】拡幅坑12の覆工が完成した状態のトンネル軸方向の断面図
【図15】断面積が一定でない拡幅坑12aのトンネル軸方向の断面図
【図16】第3の実施の形態で使用する掘削機101および掘削機101を用いて設置されたセグメントの斜視図
【図17】山留めフード103を張り出した掘削機101および掘削機101を用いて設置されたセグメントの斜視図
【図18】第4の実施の形態で使用する拡幅用セグメントリング21の一部の斜視図
【図19】仮設部59を撤去した拡幅用セグメントリング21の一部の斜視図
【図20】拡幅部45a、拡幅部45bが設けられた部分を通常幅に戻す工程を示す図
【図21】他の拡幅セグメント61を有する拡幅用セグメントリング21の斜視図
【図22】拡幅セグメント61を移動させた拡幅用セグメントリング21の斜視図
【図23】他の構造の可動部22を示す図
【図24】他の構造の可動部22を示す図
【図25】他の構造の可動部22を示す図
【図26】他の構造の可動部22を示す図
【図27】他の構造の可動部22を示す図
【図28】他の構造の可動部22を示す図
【図29】他の構造の可動部22を示す図
【図30】他の構造の可動部22を示す図
【符号の説明】
1、101………シールド掘削機
3………掘削機本体
7………コピーカッタ
10………通常坑
11、23………セグメント
12………拡幅坑
13………調整セグメント
15、15a、15b、51、51a、51b、57、61………拡幅セグメント
17………余掘り部
20、20a、20b………芯円固定用ピン
21、21a、21b………拡幅用セグメントリング
24、54、58、65………拡幅部材
25………形状保持装置
26………内周面
32、107………シール材
33………押出し装置
34、131………防水シート
43、43a、43b、59、66、68………仮設部
45a、45b、60………拡幅部
46、46a、46b………鋼管
47………鋼棒
53、53a、53b………止水枠
71、75、91、97、99………ゴム
73、127………ピン
81………金具
83………主管
85………枝管
87、93a、93b………ワイヤ
103………山留めフード
105………フロントフード
109………リアフード
115………フード本体
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for widening a tunnel installed in a widening pit, a segment, and a shield machine.
[0002]
[Prior art]
In buried pipes and tunnels constructed using a shield machine, a widened portion having a cross section larger than the normal portion may be required on the way due to structural and construction restrictions. For example, there are emergency parking zones of roads and railway tunnels, cable connection parts such as lead-in lines, ramps, joint grooves, branching parts of routes, and parts for passing through underground battery locores in the small-diameter shield method.
[0003]
In order to form the widened portion, there are methods as described below. (1) Excavate all lines with the necessary maximum cross section, that is, a cross section equivalent to the widened portion. If the ground part can be used, the section between the shafts constructed before and after the section where widening is required is excavated with a widened section. (2) After excavation with a normal cross section, a mountain retaining is formed around the widened portion by ground improvement or the like to dismantle the lining and widen the cross section to a predetermined area. Ground improvement will be carried out from inside the mine or from the ground. (3) The widened part is constructed by excavation.
[0004]
In addition, (4) a method (JP 2002-89170, JP 2001-329781, etc.) for excavating only necessary portions using a shield machine capable of widening the excavation area freely during excavation has been proposed. .
[0005]
[Problems to be solved by the invention]
However, in the method (1), the amount of excavation increases, and in the method (2), the work process becomes complicated. If the ground part cannot be used, method (3) cannot be implemented. In the method of (4), the problems of the methods of (1) to (3) are solved, but since the shield machine main body is widened and the segment for the widening pit is installed, It is difficult to ensure water stoppage between the segments.
[0006]
The present invention has been made in view of such a problem, and the object of the present invention is to widen the segment alone after passing through the shield machine, thereby preventing the water stoppage between the tail part of the shield machine and the segment. It is an object to provide a tunnel widening method and a segment capable of widening the segment without the need to make the segment.
[0007]
[Means for Solving the Problems]
The first invention for achieving the above-described object is a step (a) of excavating a pit having an overexcavation portion with an excavator, and a step (b) of installing a widening segment ring inside the overexcavation portion. When,
And a step (c) of moving a segment constituting the widening segment ring into the extra excavation portion after passing through the excavator, wherein the segment is movable in the outer peripheral direction of the segment ring; The moving part is provided with an expansion member on the inner peripheral surface side, and the moving part is rotationally moved around a movable part provided between the moving part and the fixed part. The tunnel widening method is characterized in that a sealing material is provided on each of the inner peripheral surface side and the outer peripheral surface side of the boundary portion between the moving portion and the fixed portion.
Moreover, 2nd invention is the process (a) which excavates the mine which has an overexcavation part with an excavator, the process (b) which installs the segment ring for widening inside the said overexcavation part, and passage of the said excavator And a step (c) of moving a segment constituting the widening segment ring into the overexcavated portion, wherein the segment is movable in the outer peripheral direction of the segment ring, and a fixed portion that does not move The moving part is provided with an expansion member on the inner peripheral surface side, a water stop frame is disposed inside the expansion member, and the water stop frame of the adjacent widened segment is the widening of the adjacent widened segment. A tunnel widening method characterized by being fixed so as to wrap a contact portion of a member.
[0008]
As the excavator, for example, a shield machine having a copy cutter capable of expanding and reducing the excavation area is used. In the step (a), a mine having an overexcavated portion is excavated using a copy cutter. In addition, since there is a limit (about 300 mm) in the widening width in the copy cutter, a face plate slide method may be used in combination as necessary. In the surplus digging portion, a filler is installed as necessary. If the stability of the overburden cannot be maintained with only the filler, the mountain hood is pushed out from the shield machine. A shield machine having a mountain hood will be described in the third aspect of the invention.
[0009]
In step (b), when the widening segment ring is installed inside the overexcavated portion, the outer diameter of the widening shaft segment ring is the same as the outer diameter of the segment ring installed in the excavation shaft of the normal section. is there. In a part of the segments constituting the widening segment ring, a widening member is provided on the inner peripheral surface side of the segment.
[0010]
In the step (c), a shape holding device for holding the shape of the widening segment ring and an extrusion device for moving the segment are installed in the widening segment ring. The shape holding device includes, for example, a holding jig disposed on the inner peripheral surface side of the segment that is not moved, and a jack that presses the holding jig against the inner peripheral surface side of the segment. The extrusion apparatus, for example, pushes the pushing jig toward the inner peripheral surface side of the segment to be moved, that is, the extrusion jig arranged on the inner peripheral surface side of the segment provided with the widening member on the inner peripheral surface side. Consists of a jack to attach.
[0011]
In the step (c), a widening member is provided on the inner peripheral surface side using the extrusion device while holding the ring shape of the segment that is not moved among the segments constituting the widening segment ring using the shape holding device. The segment is moved into the overexcavated portion and arranged along the inner wall of the widening pit. At this time, based on the pressure situation in the surplus digging part, etc., the filler is extracted to the inside of the pit as necessary. After the step (c), a predetermined portion of the widened member of the moved segment is removed.
[0012]
When the widened part is provided in the tunnel due to construction restrictions, after the use of the widened part is finished, the segment moved in the overexcavated part in the step (c) is moved from the inside of the overexcavated part to the tunnel inner peripheral direction. May be. Thereby, the outer diameter of the segment ring for widening pits becomes the same as the outer diameter of the segment ring installed in the excavation pit of the normal section, and the tunnel returns to the normal width. In addition, at the time of movement of a segment, a filler or a backfilling injection material is installed in the surplus portion in parallel with the movement.
[0013]
In the 1st invention and the 2nd invention, the mine which has a surplus digging part is excavated with an excavator, and the segment ring for widening pits is installed inside a surplus digging part. And after passing an excavator, a part of segment which comprises the segment ring for widening pits is moved in an overexcavation part.
[0014]
The segment installed in the pit having the surplus digging portion is a segment characterized in that a widening member is provided on the inner peripheral surface side and is movable in the outer peripheral surface direction.
[0015]
In the widening segment, at least one segment of the present invention is arranged.
[0016]
In the segment used in the present invention, a movable part is provided near the end. The movable part is installed in advance in a part of the segment, for example. Or it installs in the boundary part of a segment and the other segment adjacent to the circumferential direction.
[0017]
The movable portion includes, for example, a pin that is the center of rotational movement in the direction of the outer peripheral surface of the segment, and a water stop member for water stop on the segment outer peripheral surface side and the inner peripheral surface side. Rubber, a sealing material, a waterproof sheet, etc. are used for a water stop member.
[0018]
Furthermore, you may provide the rotation fixing means which fixes rotation of a pin. The rotation fixing means is, for example, a fixing pin that fixes the pin to the segment, an attachment plate that is fixed to the inner peripheral surface side of the segment, a wedge that is fixed to a gap generated by the rotation of the pin, and the like.
[0019]
Further, a groove may be formed in the segment, a connecting member may be provided in the groove, and rubber may be provided on the outer periphery of the segment ring for water stop. One end of the connecting member is fixed to an end portion in the groove, and the other end is movable along the groove.
[0020]
Further, rubber may be disposed between the outer peripheral surface and the inner peripheral surface of the segment, a wire penetrating the rubber may be provided, and the wire may be fixed to the segment using fixing means. The wire is disposed through the rubber in the circumferential direction of the tunnel or in the direction of the diameter of the tunnel. Rubber may be disposed between the outer peripheral surface and the inner peripheral surface of the segment, and the rubber may be fixed to the segment using a fixing means.
[0021]
In the segment used for this invention, you may provide a water stop mechanism between the segments adjacent to an axial direction. The water stop mechanism is a lip seal provided on a surface that rubs against an axially adjacent segment, a seal material provided on a bolt of an inter-ring bolt fastening mechanism, or the like.
[0022]
Around the widening member, there may be a member for water stoppage between the adjacent segments in the circumferential direction and the front-rear direction. The member for water stop is, for example, a steel member provided inside the widening member.
[0023]
In the segment used in the present invention, a part of the widening member or a part of the widening member and the water stop member is removed after the movement into the outer peripheral surface direction, that is, into the overexcavated portion.
[0024]
According to a third aspect of the present invention, there is provided a tunnel widening method using a shield machine, characterized in that a mountain hood that can project in the outer peripheral direction of the excavator body is provided around the excavator body.
[0025]
The retaining hood is provided at at least one position on the outer periphery of the excavator body so as to follow the wall surface of the overexcavated portion excavated by the copy cutter or the face plate slide method in the step (a) of the first or second invention. Overhang.
[0026]
The mountain hood may be provided with a rear hood installed at the rear of the hood main body, a front hood installed at the front, or the like, if necessary. The mountain hood can be expanded and contracted in the axial direction of the excavator body by, for example, storing a rear hood or a front hood with the hood body in a normal state and extending the hood when extending and contracting. The rear hood and the front hood may not be extendable and may be provided integrally with the hood body.
[0027]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, a first embodiment of the present invention will be described in detail with reference to the drawings. FIG. 1 is a diagram illustrating a process of excavating a tunnel 8 having a widening pit 12 with a shield excavator 1. As shown in FIG. 1, the shield excavator 1 includes an excavator body 3, an excavation cutter 5, a copy cutter 7, and the like. Furthermore, it has a face plate slide mechanism (not shown) and a mountain retaining hood 101 (FIG. 16) as necessary.
[0028]
The excavation cutter 5 is provided on the end surface of the tubular excavator body 3. The copy cutter 7 is provided as a part of the excavation cutter 5, for example, and can be extended to the side of the shield excavator 1 as necessary. The face plate slide mechanism (not shown) is a mechanism that slides the excavation cutter 5 in the circumferential direction of the excavator body 3.
[0029]
FIG. 1A shows a process of excavating the normal mine 10 of the tunnel 8. The normal mine 10 is a portion having a normal circumferential cross section in a mine excavated to construct the tunnel 8. As shown in FIG. 1A, the shield excavator 1 excavates the natural ground 9 in a state where the copy cutter 7 is stored in the excavation cutter 5, and forms the normal pit 10 of the tunnel 8. In the rear part of the excavator main body 3, the segment 11 is installed inside the normal pit 10.
[0030]
FIG. 1B shows a step of excavating the widening pit 12 of the tunnel 8. FIG. 2 is a cross-sectional view taken along the line AA in FIG. The widening pit 12 is a portion of the mine excavated to construct the tunnel 8 and whose circumferential cross section is wider than that of the normal pit 10. As shown in FIGS. 1B and 2, the excavator An extra digging portion 17 is formed outside the main body 3.
[0031]
As shown in FIG. 1 (b), the shield excavator 1 extends the copy cutter 7 in the circumferential direction of the excavation cutter 5, excavates the normal section with the excavation cutter 5, and uses the copy cutter 7 to excavate the excavation portion. 17 is excavated to form the widening pit 12 of the tunnel 8. In addition, according to the width | variety of the excavation part 17 to excavate, the excavation part 17 is excavated using the copy cutter 7 and a face plate slide mechanism (not shown) together.
[0032]
In the rear part of the excavator body 3, an adjustment segment ring 19 having an adjustment segment 13 is installed on the inner wall of the normal pit 10 at the boundary between the normal pit 10 and the widening pit 12 as necessary. Details of the adjustment segment 13 and the adjustment segment ring 19 will be described later. In addition, the surplus digging part 17 between the inner wall of the widening pit 12 and the excavator main body 3 is filled with a filler as necessary. The filler may be one having a slow solidification in addition to a normal one.
[0033]
FIG. 1C shows a step of installing the widening segment ring 21. As shown in FIG. 1C, the natural ground 9 is further excavated from the state shown in FIG. 1B, and the widening segment ring 21 having the widening segment 15 is installed at the rear part of the excavator main body 3.
[0034]
FIG. 3 is a perspective view of the widening segment ring 21. As shown in FIG. 3, the widening segment ring 21 includes a segment 23 similar to the segment 11 installed in the normal well 10 and a widening segment 15 having a widening member 24 on the inner peripheral surface side. The widened segment 15 includes a moving portion 28 that can move in the outer peripheral direction of the widening segment ring 21 and a fixed portion 30 that does not move.
[0035]
4 and 5 are enlarged views of the vicinity of the movable portion 22. 4 is a cross-sectional view taken along line YY in FIG. 5, and FIG. 5 is a cross-sectional view taken along line XX in FIG. A movable portion 22 is provided between the moving portion 28 and the fixed portion 30 of the widened segment 15. The movable portion 22 includes a steel pipe 46, a steel rod 47, a core circle fixing pin 20, a sealing material 32, a waterproof sheet 34, and the like.
[0036]
As shown in FIG. 4, a sealing material 32 is installed at the boundary between the fixed portion 30 and the moving portion 28 of the widened segment 15. The sealing material 32 includes a sealing material 32 a installed on the inner peripheral surface side of the widened segment 15 and a sealing material 32 b installed on the outer peripheral surface side. The sealing material 32a and the sealing material 32b are fixed to either the fixed portion 30 or the moving portion 28, respectively. A waterproof sheet 34 is installed along the outer peripheral surface of the widened segment 15. The sealing material 32 and the waterproof sheet 24 are made of a water-stopping and elastic material.
[0037]
As shown in FIG. 5, the steel pipe 46 is disposed at a boundary portion between the fixed portion 30 and the moving portion 28 of the widened segment 15 and includes a plurality of steel pipes 46a and steel pipes 46b. The steel pipe 46 a is fixed to the fixed part 30 of the widened segment 15, and the steel pipe 46 b is fixed to the moving part 28. A steel rod 47 is disposed in the steel pipe 46a and the steel pipe 46b.
[0038]
As shown in FIGS. 4 and 5, a core circle fixing pin 20 a is installed at the end of the fixing portion 30 of the widened segment 15. The core circle fixing pin 20 a passes through the steel pipe 46 a fixed to the fixing portion 30, and fixes the steel rod 47 to the end portion of the fixing portion 30 of the widened segment 15. The moving part 28 is provided with a hole 36a, and the steel pipe 46a is provided with a hole 36b.
[0039]
4 and 5, the moving portion 28 of the steel pipe 46b and the widened segment 15 is centered on the steel rod 47 fixed to the end of the fixed portion 30 of the widened segment 15, and is in the direction of arrow E shown in FIG. Can be rotated. The moving part 28 is rotated in the direction of arrow E so that the hole 36a of the moving part 28 and the hole 36b of the steel pipe 46a overlap. A core circle fixing pin 20b for fixing the steel pipe 46a and the steel rod 47 to the end of the moving portion 28 of the widened segment 15 is inserted into the hole 36 composed of the hole 36a and the hole 36b.
[0040]
Before the moving portion 28 moves, that is, in the state shown in FIG. 4, the sealing material 32 a and the waterproof sheet 34 prevent water leakage from the outer peripheral side to the inner peripheral side of the widened segment 15. In a state where the moving portion 28 is moved and the moving portion 28 is fixed by the core circle fixing pin 20b, the sealing material 32b contacts the fixing portion 30, and the sealing material 32b and the waterproof sheet 34 are inward from the outer peripheral side of the widened segment 15. Prevent water leakage to the circumferential side.
[0041]
In FIG. 1C, the widening segment ring 21 is installed inside the overexcavation portion 17. At this time, the widening segment ring 21 is in the state shown in FIG. 3, and the outer diameter of the widening segment ring 21 is the same as the outer diameter of the segment ring 19 or the adjusting segment ring 19 installed in the normal well 10.
[0042]
The adjustment segment 13 of the adjustment segment ring 19 is installed adjacent to the widening segment 15 of the widening segment ring. The adjustment segment 13 is a member for smoothly connecting the segment 11 of the normal well 10 and the widened segment 15. As shown in FIG. 1C, the inner peripheral surface 16 of the adjustment segment 13 has a gradient from the inner peripheral surface 14 of the segment 11 of the normal well 10 toward the inner peripheral surface 26 of the widened segment 15.
[0043]
In the state shown in FIG. 1C, the segment rings adjacent in the axial direction of the tunnel 8 are connected by an inter-ring bolt fastening mechanism. The widening segment ring 21 is connected to an adjacent segment ring by using an inter-ring bolt fastening mechanism 18, 18a provided on the side surface. FIG. 6 is a cross-sectional view of the vicinity of the inter-ring bolt fastening mechanism 18a. FIG. 6 is an enlarged view of a portion indicated by X in FIG.
[0044]
As shown in FIG. 6, the inter-ring bolt fastening mechanism 18a includes a nut 101, a nut 103, a full screw bolt 105, a seal material 107, a sheath 111, and the like. The nut 101 is fixed inside the sheath 111b provided in the widened segment 15b, and the nut 103 is fixed inside the sheath 111a provided in the adjacent widened segment 15a.
[0045]
In order to connect the widened segment 15 a and the widened segment 15 b, the entire screw bolt 105 is screwed into the nut 101 and the nut 103 using a hexagon wrench 109 or the like. A sealing material 107 is provided at the end 113 of the entire screw bolt 105.
[0046]
FIG. 7 is a view showing a state in which the shape holding device 25 is installed in the widening segment ring 21. FIG. 7 is a cross-sectional view at the position indicated by BB in FIG. As shown in FIG. 7, a shape holding device 25 is installed inside the widening segment ring 21 installed in the widening pit 12.
[0047]
The shape holding device 25 includes, for example, a holding jig 29, a holding jig 31, a jack 27, and the like. The holding jig 31 is disposed along the lowermost segment 23 of the widening segment ring 21. Both ends of the jack 27 are connected to the holding jig 31 and the holding jig 29, respectively. The jack 27 can extend and contract in the vertical direction, and moves the holding jig 29 up and down. The holding jig 29 is pressed against the uppermost segment 23 of the widening segment ring 21 by the jack 27.
[0048]
In the state shown in FIG. 1C, a propulsion jack (not shown) of the shield excavator 1 is provided from the segment 11 in front of the widened segment 15 so that the force in the tunnel axis direction is not transmitted from the shield excavator 1 to the widened segment 15. ). Before and after that, the jack 27 is extended in the direction indicated by the arrow E as shown in FIG.
[0049]
FIG. 8 is a view showing a state in which the extrusion device 33 is installed in the widening segment ring 21. The extrusion device 33 is composed of, for example, an extrusion jig 37, a jack 35, and the like. The extrusion jig 37 is disposed along the widened segment 15 of the widening segment ring 21. One end of the jack 35 is connected to the extrusion jig 37 using a pin 41, and the other end is connected to the jack 27 using a pin 39.
[0050]
The pushing jig 37 is pressed against the inner peripheral surface 26 of the widened segment 15 by expansion and contraction of the jack 35. In addition, the extrusion apparatus 33 should just be a structure which can take a reaction force, when extending the jack 35 to the direction shown by the arrow F of FIG. The end portion of the jack 35 may not be connected to the jack 27.
[0051]
In FIG. 8, using the jack 27, the holding jig 29 is pressed against the uppermost segment 23 of the widening segment ring 21 and the shape of the segment 23 of the widening segment ring 21 is held. The pushing jig 37 is pressed against the inner peripheral surface 26 of the widened segment 15.
[0052]
FIG. 9 shows a cross-sectional view in the vicinity of the inter-ring bolt fastening mechanism 18a. Before and after installing the shape holding device 25 and the extrusion device 33 as shown in FIG. 8, the entire screw bolt 105 is removed from the nut 101 using a hexagon wrench 109 or the like as shown in FIG. It stores in the widened segment 105a, and the connection between the widened segment 15a and the widened segment 15b is released. In addition, the sheath 111a is sealed by pressing the sealing material 107 against the sheath 111a, and water leakage from the outer peripheral side of the widened segment 15a15b to the inside of the widened segment 15a can be prevented.
[0053]
After releasing the connection between the widened segment 15 and the adjacent segment, the jack 35 is extended and the moving portion 28 of the widened segment 15 is pushed out in the direction indicated by the arrow G in FIG. As described with reference to FIGS. 4 and 5, the moving portion 28 of the widened segment 15 can rotate around the steel rod 47 of the movable portion 22.
[0054]
FIG. 10 is a view showing a state in which the moving portion 28 of the widened segment 15 is extruded using the extrusion device 33. From the state shown in FIG. 8, the moving portion 28 of the widened segment 15 is extruded by the extrusion device 33 to the state shown in FIG. 10. Then, as described above, the moving portion 28 is fixed using the core circle fixing pin 20b shown in FIGS. FIG. 1 (d) shows a state in which the widened segment 15 is moved into the extra excavated portion 17 and arranged along the inner wall of the widened pit 12. FIG. 10 is a cross-sectional view taken along the line CC of FIG.
[0055]
The shape holding device 25 and the extrusion device 33 are used to sequentially move the widening segments 15 of all the widening segment rings 21 arranged in the axial direction of the tunnel 8 to the surplus digging portion 17, as shown in FIG. To. The widening segment 15 is arranged so that the outer peripheral surface is along the inner wall of the widening pit 12, and the adjacent widening segments 15 are connected by returning the inter-ring bolt fastening mechanism 18 to the state shown in FIG. In addition, when a filler is installed in the surplus digging portion 17, the filler is sucked into the tunnel 8 in the tunnel 8 as necessary.
[0056]
The widening member 24 installed on the inner peripheral surface side of the widening segment 15 is provided with temporary portions 43 (43a, 43b) as shown in FIGS. The position of the temporary portion 43 varies depending on the installation position of the widened segment 15. In the widened segment 15b that is not adjacent to the adjustment segment 13, as shown in FIG. 1D and FIG. 10, the portion excluding the surface in contact with the segment 23 adjacent in the circumferential direction is the temporary portion 43b.
[0057]
In the widened segment 15 a adjacent to the adjustment segment 13, as shown in FIG. 1E, the portion excluding the surface in contact with the segment 23 adjacent in the circumferential direction and the surface in contact with the adjustment segment 13 is a temporary portion 43 a.
[0058]
FIG. 11 is a diagram illustrating a state after the temporary portion 43b is removed. FIG.1 (e) shows the state which removed the temporary part 43. FIG. FIG. 11 is a sectional view taken along the line DD in FIG. From the state shown in FIG. 1 (d) or FIG. 10, the temporary portion 43 and the like are removed to obtain the state shown in FIG. 1 (e) and FIG.
[0059]
As shown in FIG. 1 (e) and FIG. 11, in the widening segment ring 21a and the widening segment ring 21b, the temporary portion 43a of the widening segment 15a and the temporary portion 43b of the widening segment 15b are respectively removed, and the widening portion 45a. The widened portion 45b is formed. Further, in the adjusting segment ring 19, the vicinity of the inner peripheral surface 16 of the adjusting segment 13 is removed, and the surface position is aligned with the inner peripheral surface 14 of the segment 11 adjacent in the tunnel axis direction. Then, as shown in FIG. 1E, the lining near the widening pit 12 is completed.
[0060]
Thus, in the first embodiment, the widening segment ring 21 is assembled inside the overexcavation portion 17 of the widening pit 12 excavated using the shield excavator 1 having the copy cutter 7, and the excavator main body 3 is After passing through the widening pit 12, the widening segment 15 is moved into the extra digging portion 17. Since the outer diameter of the widening segment ring 21 is equal to the outer diameter of the segment ring that is normally installed in the pit 10 at the time of installation, it is possible to ensure the water stoppage between the tail portion of the excavator body 3 and the widening segment ring 21.
[0061]
Next, a second embodiment will be described. In the second embodiment, the vicinity of the widening pit 12 of the tunnel 8 is covered by the same process as the first embodiment, but the widening segment 15a of the widening segment ring 21a and the widening segment of the widening segment ring 21b. Instead of 15b, the widened segment 51a and the widened segment 51b are used.
[0062]
FIG. 12 is a cross-sectional view in the tunnel axis direction with the widening segment ring 21 installed. FIG. 12 corresponds to the state shown in FIG. 1C of the first embodiment. In the second embodiment, as shown in FIG. 12, after the widening pit 12 is excavated, the widening segment ring 21 having the widening segment 51 is installed inside the overexcavation portion 17.
[0063]
The widened segment 51 includes a main body 55, a water stop frame 53, and the like. The main body 55 is provided with a widening member 54 on the inner peripheral surface side of the normal segment 11. The main body 55 is, for example, a box whose outer shape is substantially the same as that of the widened segment 15, and can be moved in the direction of the outer peripheral surface using the movable portion 22. Adjacent widening segments 51 are arranged so that widening member 54 contacts.
[0064]
The water stop frame 53 is disposed inside the widening member 54 of the main body 55. The water stop frame 53 of the adjacent widened segment 51 is fixed using the stopper 52 so as to wrap around the contact portion of the widened member 54 of the adjacent widened segment 51. The water stop frame 53 a of the widened segment 51 a arranged adjacent to the adjustment segment 13 is fixed to the adjustment segment 13 using a stopper 52. The water stop frame 53 prevents water leakage from the surplus digging portion 17 into the tunnel mine when the main body 55 moves.
[0065]
FIG. 13 is a cross-sectional view in the tunnel axis direction showing the step of moving the main body 55 of the widened segment 51. FIG. 13 corresponds to the transition state from FIG. 1C to FIG. 1D of the first embodiment. After installing the widening segment ring 21 as shown in FIG. 12, the shield excavator 1 of the shield excavator 1 is moved from the segment 11 in front of the widened segment 51 so that the force in the tunnel axis direction is not transmitted from the shield excavator 1 to the widened segment 51. Release the propulsion jack (not shown). However, if the thrust transmission member 50 is installed as shown by the broken line in FIG. 13 and the thrust is transmitted from the adjustment segment 13 to the water stop frame 53, it is not necessary to release the propulsion jack.
[0066]
Then, as shown in FIG. 13, the main body 55 a of the widened segment 51 a and the main body 55 b of the widened segment 51 b are sequentially moved into the digging portion 17. An end portion of the widening member 54 adjacent to the adjustment segment 13 of the main body 55a is fixed to the adjustment segment 13 and the water stop frame 53a using a stopper 56. Moreover, the edge part of the other widening member 54 is fixed to the widening member 54 of the adjacent widening segment 51 using the stopper 56 (FIG. 14). In addition, for the movement of the main body 55a and the main body 55b, the shape holding device 25 and the extrusion device 33 used in the first embodiment are used as necessary.
[0067]
FIG. 14 is a cross-sectional view in the tunnel axis direction in a state where the lining of the widening pit 12 is completed. After the main bodies 55 of all the widening segments 51 are arranged along the inner wall of the widening pit 12, as shown in FIG. 14, in the widening segment 51, the water stop frame 53 and the widening member 54 positioned inside the stopper 56 are provided. Remove. In the adjustment segment 13, the portion inside the stopper 56 is removed. Then, as shown in FIG. 14, the lining near the widening pit 12 is completed.
[0068]
Thus, also in the second embodiment, as in the first embodiment, the widening segment ring 21 is assembled inside the overexcavation portion 17 of the widening pit 12, and the excavator body 3 is expanded to the widening pit 12. Since the main body 55 of the widening segment 51 is moved into the surplus digging portion 17 after passing through, the water stoppage between the tail portion of the excavator main body 3 and the widening segment ring 21 can be secured. Moreover, when the water stop frame 53 is provided on the inner side of the main body 55 of the widened segment 51, the water stoppage between the adjacent widened segments 55 is improved when the main body 55 is moved into the overburden portion 17.
[0069]
In addition, in 2nd Embodiment, although the cross-sectional area of the widening pit 12 was made constant, the cross-sectional area of the widening pit 12 can also be changed in steps. FIG. 15 is a cross-sectional view in the tunnel axis direction of the widening pit 12a whose cross-sectional area is not constant.
[0070]
As shown in FIG. 15, the widening segment 51 a, the main body 55 a of the widening segment 51 b, and the positions of the outer peripheral surfaces of the main body 55 b are shifted from each other, and the widening member 54 is fixed by a stopper 56, By removing a part of the widening pit 12a, the widening pit 12a whose cross-sectional area is not constant can be lined. In FIGS. 12 to 15, the water stoppage is further improved by providing a lip seal (not shown) on the contact surface between the water stop frame 53 and the widening member 43, or the contact surface between the widening member 54 and the widening member 54.
[0071]
Next, a third embodiment will be described. FIG. 16 is a perspective view of an excavator 101 used in the third embodiment and a segment installed using the excavator 101. FIG. 17 is a perspective view of the excavator 101 overhanging the mountain retaining hood 103 and the segments installed using the excavator 101. In the third embodiment, the excavator 101 is used instead of the excavator 1 of the first embodiment to excavate a tunnel having a widening pit. When the wall surface of the surplus digging portion 17 (FIG. 1) cannot be maintained only by filling with the filler, it is preferable to use the excavator 101.
[0072]
The excavator 101 includes an excavator body 3, an excavation cutter 5, a mountain hood 103, a tail widening portion 107, and the like. The excavator 101 projects the tail widening portion 107 from the outer periphery of the excavator body 3 of the excavator 1 used in the first embodiment. The tail widening portion 107 is provided near the tail portion of the excavator body 3. The mountain retaining hood 103 includes a hood main body 115, a front hood 105, and a rear hood 109 which are outer peripheral surfaces of the tail widening portion 107.
[0073]
For example, the front hood 105 is integrated with the hood main body 115 of the tail widening portion 107 and projects in the outer peripheral direction of the excavator main body 3 simultaneously with the tail widening portion 107. A rear hood 109 is extended from the tail widening portion 107. As shown in FIG. 17, the mountain retaining hood 103 supports the wall surface of the widening pit 12 (FIG. 1) by projecting the tail widening portion 105 in the outer peripheral direction of the excavator body 3. In the state shown in FIG. 16, the rear hood 109 is stored in the tail widening portion 107 so as to overlap the inside of the hood main body 115.
[0074]
As with the excavator 1 shown in FIG. 1, the excavator 101 uses the excavator 5, the copy cutter 7, a face plate slide mechanism (not shown), and the like, and the widening pit having the normal pit 10 and the extra digging portion 17. 12 is excavated in the natural ground 9.
[0075]
As shown in FIG. 16, when excavating a normal mine, the excavator 101 excavates the mountain retaining hood 103 without projecting, and installs the segment 11 in the normal mine at the tail portion. When excavating the widening pit, the adjusting segment ring 19 and the widening segment ring 21 are installed at the tail portion while excavating the mountain retaining hood 103 without overhanging. The surplus portion of the widening pit is filled with a filler.
[0076]
Then, at an appropriate time, as shown in FIG. 17, the mountain retaining hood 103 and the front hood 105 are projected along the wall surface of the widening pit (not shown), and the rear hood 109 is extended from the tail widening portion 107. At this time, the rear end 111 of the rear hood 109 is made to coincide with the rear end 113 of the widening segment ring 21 to be widened.
[0077]
In the state shown in FIG. 17, the widening segment (not shown) of the widening segment ring 21 is moved in the outer peripheral direction of the widening segment ring 21 while excavating the natural ground with the excavation cutter 5 to cover the widening pit. To do. At the end of the widening section, the rear hood 109 is stored in the tail widening portion 107 and the tail widening portion 107 is stored in the excavator body 3.
[0078]
As described above, in the third embodiment, the use of the excavator 101 having the mountain retaining hood 103 makes it easy to maintain the wall surface of the overexcavated portion. Further, by projecting the mountain retaining hood 103, the excavating direction and posture of the excavator 101 can be controlled.
[0079]
In the excavator 101 shown in FIGS. 16 and 17, the front hood 105 is integrated with the hood main body 115. However, the front hood 105 is stored in the tail widening portion 107 like the rear hood 109 so that the front hood 105 can be expanded and contracted. Also good. In some cases, the front hood 105 and the rear hood 109 are not provided.
[0080]
Next, a fourth embodiment will be described. FIG. 18 is a perspective view of a part of the widening segment ring 21 used in the fourth embodiment. Also in the fourth embodiment, the vicinity of the widening pit 12 of the tunnel 8 is covered by the same process as the first and second embodiments, but the widening segment 15 of the widening segment ring 21 is replaced by the widening. Segment 57 is used.
[0081]
FIG. 18 shows the state of the widened segment 57 in the step shown in FIG. The widening segment 57 has a widening member 58 on the inner peripheral surface. The widening member 58 is provided with a temporary portion 59 at an appropriate portion.
[0082]
The widening segment ring 21 in the state shown in FIG. 18 is installed inside the surplus digging portion 17 of the widening pit 12, and after the excavator body 3 passes through the widening pit 12, the tunnel shaft is transferred from the shield excavator 1 to the widening segment 57. The propulsion jack (not shown) of the shield excavator 1 is separated from the segment in front of the widening segment 57 so that no directional force is transmitted.
[0083]
Then, the plurality of widened segments 57 are each extruded in the direction indicated by the arrow H in FIG. 18 and moved into the surplus digging portion 17, and arranged along the inner wall of the widened pit 12. For the movement of the widened segment 57, a shape holding device or an extrusion device as used in the first embodiment is used as necessary.
[0084]
FIG. 19 is a perspective view of a part of the widening segment ring 21 with the temporary portion 59 removed. After the widened segment 57 is pushed into the overburden portion 17, the temporary portion 59 of the widened segment 37 is removed, and the widened portion 60 is formed in the widening segment ring 21.
[0085]
The widened segment 57 shown in FIGS. 18 and 19 is not adjacent to the adjusting segment 13. In the widened segment 57 adjacent to the adjustment segment 13, the temporary part is provided on a portion excluding the surface in contact with the adjustment segment 13 and the surface in contact with the segment 23 adjacent in the circumferential direction.
[0086]
The inter-ring bolt fastening mechanisms 18 and 18a (FIGS. 18 and 199) of the widening segment 57 have the same configuration as the inter-ring bolt fastening mechanisms 18 and 18a of the widening segment 15 of the first embodiment. In the widening segment 57, before the widening, the inter-ring bolt fastening mechanism 18a is changed from the state shown in FIG. 6 to the state shown in FIG. Moreover, after moving the widening segment 57 into the widening pit 12, the inter-ring bolt fastening mechanism 18a is returned to the state shown in FIG. 6 and reconnected to the adjacent segment.
[0087]
Also in the fourth embodiment, as in the first and second embodiments, the widening segment ring 21 is assembled inside the overexcavation portion 17 of the widening pit 12, and the excavator body 3 assembles the widening pit 12. After passing, the widened segment 57 is moved into the extra excavation portion 17, so that the water stoppage between the tail portion of the excavator body 3 and the widening segment ring 21 can be secured.
[0088]
Next, a fifth embodiment will be described. FIG. 20 is a diagram illustrating a process of returning the portion provided with the widened portion 45a and the widened portion 45b to the normal width. FIG. 20A shows the tunnel 8 in which a widened portion 45a and a widened portion 45b are provided. FIG. 20B shows the tunnel 8 in which the widened segment 15a and the widened segment 15b are moved to make the width of the inner space constant.
[0089]
For example, the tunnel 8 shown in FIG. 20A is constructed by the method described in the first embodiment. When the widened portion 45a and the widened portion 45b of the tunnel 8 are necessary at the time of construction of the tunnel 8 and are not necessary after completion, the widened portion 45a and the widened portion 45b are provided after construction as shown in FIG. The shield width of the formed portion is returned to the normal width, and the width of the inner space of the tunnel 8 is made constant. The process shown in FIG. 20 is applied, for example, when the widened portion 45a and the widened portion 45b are used for mine separation (passing) of a material conveying carriage having a small diameter long distance shield.
[0090]
In order to make the width of the inner space of the tunnel 8 constant, the outer diameters of the widening segment ring 21a and the widening segment ring 21b shown in FIG. Thus, the widened segment 15 a of the widening segment ring 21 a and the widened segment 15 b of the widening segment ring 21 b are moved in the inner circumferential direction of the tunnel 8.
[0091]
In parallel with the movement of the widened segment 15a and widened segment 15b, as shown in FIG. 20 (b), filling material or backfilling is injected into the overexcavation portion 17 (FIG. 1) outside the widened segment 15a and widened segment 15b. Material 117 is injected. Injection of the filler or backfilling injection material 117 is performed through injection holes (not shown) provided in the widened segment 15a and the widened segment 15b. The filler or backfilling infusion material 117 may be one having a slow solidification in addition to the normal one.
[0092]
The movement of the widened segment 15a and the widened segment 15b in the tunnel inner circumferential direction is performed in the reverse procedure to the movement in the tunnel outer circumferential direction (arrow G direction in FIG. 8) described in the first embodiment. In order to draw the widened segment 15a and the widened segment 15b in the inner circumferential direction of the tunnel, a jack 35, a jack 27, or the like shown in FIG. 8 is used.
[0093]
In the fifth embodiment, since the shield width of the tunnel 8 in the portion where the widening pit 12 is provided is widened only during construction, and then returned to the same level as the portion of the normal pit 10, the occupation of the basement is short, Permits regarding underground occupation to ground facility managers are basically unnecessary.
[0094]
In this way, in the first to fifth embodiments, after the excavator body 3 passes through the widening pit 12, the widened segment is moved into the overexcavation portion 17, so that the tail portion and the widening of the excavator body 3 are expanded. The water-stopping property with the segment ring 21 can be ensured. The widening segments to be used are not limited to the widening segment 15, the widening segment 51, and the widening segment 57 used in the first, second, fourth, and fifth embodiments. The widened segment may have a structure in which a widening member is provided on the inner peripheral surface side and can be moved into the extra digging portion 17 after being installed inside the extra digging portion 17.
[0095]
FIG. 21 is a perspective view of the widening segment ring 21 having another widening segment 61. The widening segment 61 includes a main body 63, a widening member 64, a widening member 65, and the like. The widening member 64 and the widening member 65 are members provided on the inner peripheral surface side of the main body 63, but the widening member 64 is a member integrated with the main body 63, and the widening member 65 is integrated with the main body 63. It is a member that is not.
[0096]
The main body 63 is connected to the segment 23 using, for example, the movable portion 22 and is movable in the direction indicated by the arrow I with the movable portion 22 as the center of rotation. The main body 63 is provided with a guide groove 67 for guiding the position of the pin 69, and an end portion of the pin 69 fixed to the widening member 65 is disposed in the guide groove 67.
[0097]
FIG. 22 is a perspective view of the widening segment ring 21 in which the widening segment 61 is moved. As shown in FIG. 22, the widening member 65 is moved between the main body 63 and the segment 23 adjacent in the circumferential direction, and the widening segment 61 is disposed inside the overexcavated portion 17 of the widening pit 12. At this time, the pin 69 fixed to the widening member 65 moves along the guide groove 67 of the main body 63.
[0098]
The widening member 64 and the widening member 65 are provided with a temporary portion 66 and a temporary portion 68 at appropriate portions, respectively. By removing the temporary portion 66 and the temporary portion 68, a widened portion is formed inside the widening segment ring 21. The inter-ring bolt fastening mechanism 18 a provided in the main body 63 is used in the same manner as the inter-ring bolt fastening mechanism 18 a provided in the widening segment 15 and the widening segment 57.
[0099]
Further, the structure of the movable portion 22 is not limited to that shown in FIG. The movable part 22 should just be a structure which can move a widening segment, ensuring the water stop of the outer peripheral side and inner peripheral side of the segment ring 21 for widening. 23 to 29 are diagrams showing the movable portion 22 having another structure.
[0100]
A movable portion 22 shown in FIG. 23 is provided at a boundary portion between the moving portion 28 and the fixed portion 30 of the widened segment 15 and includes a pin 73, rubber 71, and the like. The pin 73 hinges the end of the moving portion 28 of the widened segment 15 and the end of the fixed portion 30. The water stopping rubber 71 is provided at the boundary between the moving portion 28 and the fixed portion 30. The moving portion 28 of the widened segment 15 is rotatable around a pin 73 as indicated by an arrow J in FIG.
[0101]
The movable portion 22 shown in FIG. 24 is provided at the boundary between the moving portion 28 and the fixed portion 30 of the widened segment 15, and the main pipe 83 and branch pipe 85 that are grooves provided in the widened segment 15, the fitting 81, and the fixed pin 77, a moving pin 79, rubber 75, and the like.
[0102]
The metal fitting 81 connects the moving portion 28 and the fixed portion 30 of the widened segment 15. The main pipe 83 for arranging the metal fitting 81 is arranged inside the moving part 28 and the fixed part 30. A branch pipe 85 branched from the main pipe 83 is further arranged inside the moving portion 28. A rubber 75 is provided on the outer peripheral surface side of the contact portion between the moving portion 28 and the fixed portion 30.
[0103]
One end of the metal fitting 81 is fixed to the end of the main pipe 83 of the fixing portion 30 as a fixing pin 77. A moving pin 79 is provided at the other end of the metal fitting 81. The moving pin 79 is stored inside the main pipe 83 of the moving part 28 before the moving part 28 moves, as shown in FIG. When the moving part 28 is moved in the direction indicated by the arrow K, the rubber 75 is contracted, and the moving pin 79 is moved from the main pipe 83 in the moving part 28 and stored in the branch pipe 85.
[0104]
The movable portion 22 shown in FIG. 25 is provided at a boundary portion between the moving portion 28 and the fixed portion 30 of the widened segment 15 and includes a wire 87, a stopper 89, rubber 91, and the like. The rubber 91 is provided between the moving portion 28 and the fixed portion 30 of the widened segment 15. Inside the rubber 91, a wire 87 is disposed in the circumferential direction of the tunnel.
[0105]
Both ends of the wire 87 are provided with threads. Both ends of the wire 87 are fixed to the moving part 28 and the fixed part 30 by using a stopper 89. By deforming the wire 87 and the rubber 91, the moving portion 28 can be moved in the direction indicated by the arrow L.
[0106]
The movable portion 22 shown in FIG. 26 is provided at a boundary portion between the moving portion 28 and the fixed portion 30 of the widened segment 15, and includes a wire 93a, a wire 93b, a stopper 95, a rubber 97, and the like. The rubber 97 is provided between the moving portion 28 and the fixed portion 30 of the widened segment 15.
[0107]
The rubber 97 is fixed to the fixed portion 30 and the moving portion 28 by a wire 93a that passes through the fixed portion 30 from the outer peripheral side to the inner peripheral side and a wire 93b that passes through the moving portion 28 from the outer peripheral side to the inner peripheral side. . The wire 93a and the wire 93b are fixed to the fixed portion 30 and the moving portion 28 using a stopper 95, respectively. The moving portion 28 can be moved in the direction indicated by the arrow M by deforming the rubber 97.
[0108]
The movable portion 22 shown in FIG. 27 is provided at the boundary portion between the moving portion 28 and the fixed portion 30 of the widened segment 15 and includes a stopper 98, rubber 99, and the like. The rubber 99 is provided between the moving portion 28 and the fixed portion 30 of the widened segment 15. The end portions in the circumferential direction of the rubber 99 are fixed to the fixed portion 30 and the moving portion 28 using stoppers 98, respectively. By deforming the rubber 99, the moving part 28 can be moved in the direction indicated by the arrow N.
[0109]
The movable part 22 shown in FIG. 28 has substantially the same configuration as the movable part 22 shown in FIG. 4, but is rotated in the direction indicated by the arrow E in FIG. 4 to fix the core circle fixing pin 20 b to the steel rod 47. Thereafter, a contact plate 121 is attached to the inner peripheral surface side of the widened segment 15. The contact plate 121 is fixed to the moving portion 28 and the fixed portion 30 using bolts 123 and nuts 125.
[0110]
29 and 30 is provided at the boundary between the moving portion 28 and the fixed portion 30 of the widened segment 15, and includes a pin 127, a rotating plate 129, a waterproof sheet 131, a wedge 137, and the like. The pin 127 is disposed at the boundary between the fixed portion 30 and the moving portion 28 of the widened segment 15. The waterproof sheet 131 is installed along the outer peripheral surface of the widened segment 15. The rotating plate 129 is installed inside the waterproof sheet 131. The waterproof sheet 131 is made of a water-stopping and elastic material, and the rotating plate 129 is made of a deformable material.
[0111]
In the state shown in FIG. 29, the moving portion 28 and the fixed portion 30 are fixed using bolts 135 and nuts 133. By removing the bolt 135 and the nut 133, the moving portion 28 can be moved in the direction indicated by the arrow O with the pin 127 as the center of rotation.
[0112]
After the moving portion 28 is rotated in the direction indicated by the arrow O in FIG. 29, the wedge 137 is disposed between the moving portion 28 and the fixed portion 30 as shown in FIG. Further, the moving portion 28, the wedge 137, and the fixed portion 30 are tightened with a bolt 139 and a nut 141 via a taper washer 143. At this time, if the hole for the bolt 139 provided in the taper washer 143 is a long hole, assembly is facilitated.
[0113]
In FIGS. 4, 5, and 21 to 27, the widened segment 15 (the widened segment 55, the widened segment 61) is divided into a moving part 28 and a fixed part 30, and a movable part is provided at the boundary between the moving part 28 and the fixed part 30. However, the installation position of the movable portion 22 is not limited to this. The widened segment 15 (the widened segment 55 and the widened segment 61) may not be divided into the moving portion 28 and the fixed portion 30, and the movable portion 22 may be provided at the boundary between the widened segment and other segments adjacent in the circumferential direction. . In this case, the entire widened segment moves in the circumferential direction of the segment ring using the movable portion 22.
[0114]
Furthermore, the configuration of the shape holding device and the extrusion device may not be as shown in FIGS. The shape holding device may be any structure that can hold the shape of the other segment 23 during the movement of the widened segment. Moreover, the extrusion apparatus should just be a structure which can extrude a widening segment to the outer peripheral direction of the segment ring 21 for widening. As a form of movement of the widened segment, rotational movement such as the widened segment 15 and widened segment 61, parallel movement such as the widened segment 57, and the like are conceivable. The extrusion apparatus has a structure corresponding to the movement form of the widening segment used.
[0115]
The widened segments such as the widened segment 15 and the widened segment 51 are preferably made of steel, but may be formed of other materials. Moreover, in FIG. 1, although the overexcavation part 17 was provided in the one side surface of the tunnel 8, and the widening part was formed, the position which performs overexcavation is not restricted to this. For example, the widened portion may be formed by excavating an excessively dug portion on both side surfaces.
[0116]
【The invention's effect】
As described above in detail, according to the present invention, the segment can be widened without worrying about the water stoppage between the tail portion of the shield machine and the segment by widening the segment alone after passing through the shield machine. Tunnel widening method, segment and shield machine can be provided.
[Brief description of the drawings]
FIG. 1 is a diagram showing a process of excavating a tunnel 8 having a widening pit 12 with a shield excavator 1;
FIG. 2 is a cross-sectional view taken along line AA in FIG.
FIG. 3 is a perspective view of a widening segment ring 21. FIG.
FIG. 4 is an enlarged view of the vicinity of the movable part 22
FIG. 5 is an enlarged view of the vicinity of the movable part 22
FIG. 6 is a cross-sectional view of the vicinity of an inter-ring bolt fastening mechanism 18a.
7 is a view showing a state in which the shape holding device 5 is installed in the widening segment ring 21. FIG.
FIG. 8 is a diagram showing a state in which an extrusion device 33 is installed in the widening segment ring 21;
FIG. 9 is a cross-sectional view of the vicinity of an inter-ring bolt fastening mechanism 18a.
FIG. 10 is a view showing a state in which the moving portion 28 of the widened segment 15 is extruded using the extrusion device 33.
FIG. 11 is a view showing a state after the temporary portion 43b is removed.
FIG. 12 is a cross-sectional view in the tunnel axis direction with a widening segment ring 21 installed
13 is a cross-sectional view in the tunnel axis direction showing a step of moving the main body 55 of the widened segment 51. FIG.
FIG. 14 is a cross-sectional view in the tunnel axis direction with the lining of the widening pit 12 completed.
FIG. 15 is a cross-sectional view in the tunnel axis direction of a widening pit 12a whose cross-sectional area is not constant
FIG. 16 is a perspective view of an excavator 101 used in the third embodiment and a segment installed using the excavator 101.
FIG. 17 is a perspective view of an excavator 101 projecting a mountain retaining hood 103 and a segment installed using the excavator 101.
18 is a perspective view of a part of a widening segment ring 21 used in the fourth embodiment. FIG.
FIG. 19 is a perspective view of a part of the widening segment ring 21 from which the temporary portion 59 has been removed.
FIG. 20 is a diagram showing a step of returning the portion provided with the widened portion 45a and the widened portion 45b to the normal width.
21 is a perspective view of a widening segment ring 21 having another widening segment 61. FIG.
FIG. 22 is a perspective view of the widening segment ring 21 with the widening segment 61 moved.
FIG. 23 is a diagram showing a movable portion 22 having another structure.
FIG. 24 is a diagram showing a movable part 22 having another structure.
FIG. 25 is a diagram showing a movable portion 22 having another structure.
FIG. 26 is a diagram showing a movable portion 22 having another structure.
FIG. 27 is a diagram showing a movable portion 22 having another structure.
FIG. 28 is a diagram showing a movable portion 22 having another structure.
FIG. 29 is a diagram showing a movable portion 22 having another structure.
FIG. 30 is a diagram showing a movable portion 22 having another structure.
[Explanation of symbols]
1, 101 ……… Shield excavator
3 ......... Excavator body
7 ... Copy cutter
10 ......... Normal mine
11, 23 ... Segment
12 ......... Wide pit
13 ... Adjustment segment
15, 15a, 15b, 51, 51a, 51b, 57, 61 ......... Widening segment
17 ……… Excavation
20, 20a, 20b ......... Core circle fixing pin
21, 21 a, 21 b ............ widening segment ring
24, 54, 58, 65 ......... Widening member
25 .... Shape retention device
26 ... Inner perimeter
32, 107 ... …… Seal material
33 ... Extruder
34, 131 ……… Waterproof sheet
43, 43a, 43b, 59, 66, 68 ......... Temporary part
45a, 45b, 60 ......... widening part
46, 46a, 46b ……… Steel pipe
47 ……… Steel Bar
53, 53a, 53b ......... Water stop frame
71, 75, 91, 97, 99 ... …… Rubber
73, 127 ......... pin
81 ......... Metal
83 ……… Supervising
85 ……… branch
87, 93a, 93b ......... Wire
103 ... …… Yamazushi Food
105 ……… Front hood
109 ……… Rear food
115 ......... Hood body

Claims (4)

掘削機で余掘り部を有する坑を掘削する工程(a)と、
前記余掘り部の内側に拡幅用セグメントリングを設置する工程(b)と、
前記掘削機の通過後に、前記拡幅用セグメントリングを構成するセグメントを前記余掘り部内に移動させる工程(c)と、
を具備し、
前記セグメントは、セグメントリングの外周方向に移動可能な移動部と、移動しない固定部とからなり、前記移動部は内周面側に拡張部材が設けられ、前記移動部は、前記移動部と前記固定部との間に設けられた可動部を中心に回転移動し、前記移動部と前記固定部との境界部の内周面側と外周面側とにそれぞれシール材が設けられてなることを特徴とするトンネルの拡幅方法。
A step (a) of excavating a mine having an overexcavation portion with an excavator;
A step (b) of installing a widening segment ring inside the overexcavated portion;
A step (c) of moving a segment constituting the widening segment ring into the extra-digging portion after passing through the excavator;
Comprising
The segment includes a moving portion that can move in the outer peripheral direction of the segment ring and a fixed portion that does not move. The moving portion is provided with an expansion member on the inner peripheral surface side, and the moving portion includes the moving portion and the moving portion. It is rotated around a movable part provided between the fixed part and a sealing material is provided on each of the inner peripheral surface side and the outer peripheral surface side of the boundary part between the moving part and the fixed part. A tunnel widening method that is characteristic.
掘削機で余掘り部を有する坑を掘削する工程(a)と、
前記余掘り部の内側に拡幅用セグメントリングを設置する工程(b)と、
前記掘削機の通過後に、前記拡幅用セグメントリングを構成するセグメントを前記余掘り部内に移動させる工程(c)と、
を具備し、
前記セグメントは、セグメントリングの外周方向に移動可能な移動部と、移動しない固定部とからなり、前記移動部は内周面側に拡張部材が設けられ、前記拡張部材の内側に止水枠が配置され、隣接する拡幅セグメントの前記止水枠は、隣接する拡幅セグメントの前記拡幅部材の接触部を包み込むように固定されることを特徴とするトンネルの拡幅方法。
A step (a) of excavating a mine having an overexcavation portion with an excavator;
A step (b) of installing a widening segment ring inside the overexcavated portion;
A step (c) of moving a segment constituting the widening segment ring into the extra-digging portion after passing through the excavator;
Comprising
The segment includes a moving part movable in the outer peripheral direction of the segment ring and a fixed part that does not move. The moving part is provided with an expansion member on the inner peripheral surface side, and a water stop frame is provided inside the expansion member. The tunnel widening method , wherein the water blocking frame of the adjacent widened segment is fixed so as to wrap around the contact portion of the widening member of the adjacent widened segment .
前記掘削機は、前記掘削機本体の外周方向に張り出し可能な山留めフードが設けられ、前記山留めフードは、テール拡幅部の外周面であるフード本体と、前記フード本体と一体であるフロントフードと、前記テール拡幅部から伸長されるリアフードとからなり、拡幅坑の壁面に沿って前記フード本体と前記フロントフードとを張り出し、前記リアフードを前記リアフードの最後尾が、拡幅予定の拡幅用セグメントリングの最後尾と一致するように伸長することを特徴とする請求項1または請求項2記載のトンネルの拡幅方法。The excavator is provided with a mountain hood that can be extended in the outer circumferential direction of the excavator body, the mountain hood includes a hood body that is an outer peripheral surface of a tail widening portion, a front hood that is integral with the hood body, A rear hood extending from the tail widening portion, and extending the hood main body and the front hood along the wall surface of the widening pit, with the rear hood at the rear end of the rear hood and the end of the widening segment ring to be widened The tunnel widening method according to claim 1, wherein the tunnel is extended so as to coincide with the tail . 掘削機で余掘り部を有する坑を掘削する工程(a)と、
前記余掘り部の内側に拡幅用セグメントリングを設置する工程(b)と、
前記掘削機の通過後に、前記拡幅用セグメントリングを構成するセグメントを前記余掘り部内に移動させる工程(c)と、
前記工程(c)において前記余掘り部内に移動させた前記セグメントをトンネル内周方向に移動させ、前記セグメントの外側の余掘り部に充填材または裏込め注入材を注入して、
シールド幅を通常幅に戻す工程(d)と、
を具備し、
前記セグメントは、セグメントリングの外周方向に移動可能な移動部と、移動しない固定部とからなり、前記移動部は内周面側に拡張部材が設けられ、前記移動部は、前記移動部と前記固定部との間に設けられた可動部を中心に回転移動し、前記移動部と前記固定部との境界部の内周面側と外周面側とにそれぞれシール材が設けられてなることを特徴とするトンネルの拡幅方法。
A step (a) of excavating a mine having an overexcavation portion with an excavator;
A step (b) of installing a widening segment ring inside the overexcavated portion;
A step (c) of moving a segment constituting the widening segment ring into the extra-digging portion after passing through the excavator;
In the step (c), the segment moved into the extra digging portion is moved in the inner circumferential direction of the tunnel, and a filler or a backfill injection material is injected into the extra digging portion outside the segment,
Step (d) of returning the shield width to the normal width;
Comprising
The segment includes a moving portion that can move in the outer peripheral direction of the segment ring and a fixed portion that does not move. The moving portion is provided with an expansion member on the inner peripheral surface side, and the moving portion includes the moving portion and the moving portion. It is rotated around a movable part provided between the fixed part and a sealing material is provided on each of the inner peripheral surface side and the outer peripheral surface side of the boundary part between the moving part and the fixed part. A tunnel widening method that is characteristic.
JP2003209562A 2002-08-30 2003-08-29 Tunnel widening method Expired - Fee Related JP4030931B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003209562A JP4030931B2 (en) 2002-08-30 2003-08-29 Tunnel widening method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2002253655 2002-08-30
JP2003209562A JP4030931B2 (en) 2002-08-30 2003-08-29 Tunnel widening method

Publications (2)

Publication Number Publication Date
JP2004143917A JP2004143917A (en) 2004-05-20
JP4030931B2 true JP4030931B2 (en) 2008-01-09

Family

ID=32472849

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003209562A Expired - Fee Related JP4030931B2 (en) 2002-08-30 2003-08-29 Tunnel widening method

Country Status (1)

Country Link
JP (1) JP4030931B2 (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4030866B2 (en) * 2002-12-25 2008-01-09 鹿島建設株式会社 Water stop method and structure for joints between rings in widened segments
JP4184142B2 (en) * 2003-04-24 2008-11-19 鹿島建設株式会社 Water stop structure of widened segment
JP4172020B2 (en) * 2003-12-02 2008-10-29 清水建設株式会社 Shield excavator, shield tunnel expansion construction method and shield tunnel reduction construction method
JP4397797B2 (en) * 2004-11-29 2010-01-13 鹿島建設株式会社 Construction method of underground structure
JP4515352B2 (en) * 2005-08-16 2010-07-28 鹿島建設株式会社 Seal structure between segments and sealing method between segments
JP4854523B2 (en) * 2007-01-12 2012-01-18 鹿島建設株式会社 Tunnel construction method
JP4824653B2 (en) * 2007-09-04 2011-11-30 鹿島建設株式会社 Tunnel junction and method of constructing tunnel junction
JP6906411B2 (en) * 2017-09-22 2021-07-21 鹿島建設株式会社 tunnel
JP6811299B1 (en) * 2019-11-15 2021-01-13 大成建設株式会社 Segment set consisting of B segment and K segment, open tunnel and its construction method

Also Published As

Publication number Publication date
JP2004143917A (en) 2004-05-20

Similar Documents

Publication Publication Date Title
JP4030931B2 (en) Tunnel widening method
JPH0462292A (en) Tunnel diameter expansion and diameter reduction methods
CA1217066A (en) Tunnelling and tunnel relining equipment
JP3863888B2 (en) Two-stage propulsion method and coupler
JP4214082B2 (en) Propulsion method excavation equipment and propulsion method
JP4037436B2 (en) Tunnel excavator for pipe formation
JP4030866B2 (en) Water stop method and structure for joints between rings in widened segments
JP4369627B2 (en) Tunnel construction method and shield excavator used therefor
JP6715164B2 (en) Pipe roof construction method
JP4549247B2 (en) Propulsion pipe start entrance, start entrance structure and start entrance water stop method
JP3733796B2 (en) Shield device and shield method
JP2933278B1 (en) Underground junction type shield machine
JP2693904B2 (en) Underground drilling method
JP2630330B2 (en) Shrinkable segment and shrinkable segment ring
JP2021031943A (en) Section reduction segment, and section reduction system
JP3061586B2 (en) Segment with water stop device and method of assembling the same
JPH0220303Y2 (en)
JP4563331B2 (en) Tunnel variable section construction method and tunnel excavator used in the construction method
JPS60238599A (en) Enlarging shield drilling machine
JP2634633B2 (en) Shield method
JP4376828B2 (en) Tunnel construction method
JPS63138097A (en) Method of re-laying construction of existing culvert
JPH03281898A (en) Joining method and device between shield tunnel and structure or shield tunnel
JPH11117662A (en) Direct underground joining method and shield machine therefor
JPH0649662Y2 (en) Underground joining device for shield machine

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040927

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070529

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20070614

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070730

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20071016

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20071017

R150 Certificate of patent or registration of utility model

Ref document number: 4030931

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101026

Year of fee payment: 3

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101026

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101026

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111026

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121026

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131026

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R370 Written measure of declining of transfer procedure

Free format text: JAPANESE INTERMEDIATE CODE: R370

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees