JP3996993B2 - Construction scaffolding board - Google Patents
Construction scaffolding board Download PDFInfo
- Publication number
- JP3996993B2 JP3996993B2 JP03912398A JP3912398A JP3996993B2 JP 3996993 B2 JP3996993 B2 JP 3996993B2 JP 03912398 A JP03912398 A JP 03912398A JP 3912398 A JP3912398 A JP 3912398A JP 3996993 B2 JP3996993 B2 JP 3996993B2
- Authority
- JP
- Japan
- Prior art keywords
- fitting
- horizontal member
- clamp
- lock
- building frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Mutual Connection Of Rods And Tubes (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、建設現場の仮設足場に使用される建設用足場板に関する。
【0002】
【従来の技術】
建設用足場板は建築物の周囲に組み上げられた建枠間に掛け渡されて作業用足場を形成するもので、足場板本体の両端部には実開昭60−1840号公報に記載のように、足場板を建枠の管体より成る横架材に係止する略逆U字形状のクランプ金具を備えている。そして足場板を掛け渡したときには、クランプ金具の基部に取り付けたロック金具を回動して挟持用突起を突出させて横架材を挟持させ、足場板が風圧によって簡単に吹き上がらないようにしている。
【0003】
そして、建築工事が終了して作業足場を解体するときには、足場板の四隅のクランプ金具のロック金具を手で回動して横架材の挟持状態を解除し、足場板を建枠から取り外している。
【0004】
【発明が解決しようとする課題】
しかしながら、上記従来の足場板のロック金具は、挟持状態を解除する位置に一時的に保持できる構造となっているものの、少しの振動でロック金具が回動して元の挟持状態に戻ることがあり、一人で足場板を取り外そうとする時、足場板の片方の端を持ち上げると他方の端のロック金具が回動して挟持状態となることがある。また、従来の足場板のクランプ金具2の凹部は、図7に示すように、建枠の組み立て時の寸法精度を見込んで建枠横架材Pよりやや大きめにはしているものの、足場板本体1を傾斜させると凹部の下部開口は建枠横架材Pを垂直方向には抜け出せる寸法となっておらず、四隅のロック金具を解除した後、足場板本体をほぼ水平に保ちながら垂直方向に持ち上げないと取り外しができない構造となっている。
【0005】
そのため、一人作業では取り外し作業がはかどらないこともあり、二人一組で取り外し作業を行うことが多く、解体作業の能率は決して良いとは言えないものであった。
【0006】
本発明は上記の点に鑑み、一人作業でも簡単に取り外せて解体作業の能率を向上できる建設用足場板を提供することを課題とする。
【0007】
【課題を解決するための手段】
本発明は上記の課題を達成するために、足場板本体の両端部に下向きに開口した略逆U字形状のクランプ金具を備え、該クランプ金具の基部に二つのガイド孔を形成したロック金具を二本の支持ピンを介して取り付け、該ロック金具の下端部には建枠横架材を挟持する時に建枠横架材の下面に当接させる挟持用突起を形成し、ロック金具をガイド孔に沿って回動させながら前記挟持用突起をクランプ金具の凹部の下部開口に向けて出没させて建枠横架材を挟持・解除するようにした建設用足場板において、足場板本体の少なくとも一方側のクランプ金具の凹部の下部開口は足場板本体を傾斜させた状態で建枠横架材から抜き出し可能な広さとすると共に、足場板本体を傾斜させた状態でクランプ金具の凹部の下部開口に突出するクランプ金具の基部のロック金具を建枠横架材に押し当てると、前記ロック金具がガイド孔に案内されながらクランプ金具の凹部の下部開口より退避没入して建枠横架材の下面より離間し、クランプ金具の凹部の下部開口を開放状態とするように前記支持ピンとガイド孔を配置形成したことを特徴としている。
【0008】
【発明の実施の形態】
本発明に係る建設用足場板にあっては、組み上げた建枠の横架材の間に掛け渡した足場板を解体しようとするときには、足場板本体の一端側のクランプ金具のロック金具を操作して挟持状態を解除し、足場板の一端側を上方に持ち上げる。この足場板の一端側を持ち上げた状態で足場板を傾斜方向に沿って斜め下方向に押し下げると、他端側に配設したクランプ金具のロック金具の凹部側に面する縁部が建枠横架材に押し当たり、その押圧力によってロック金具が凹部より退避没入する。次に、足場板を傾斜させた状態で上方向に持ち上げると、クランプ金具の凹部の下部開口を足場板の傾斜状態で建枠横架材から抜き出し可能な広さにしているために支障なく横架材より取り外すことができる。
【0009】
このように、足場板一端側のクランプ金具のロック金具を手で操作して挟持状態を解除した後、この足場板を持ち上げた状態で、他端側のクランプ金具のロック金具に手を触れずに挟持状態を解除して足場板を取り外すことができ、一人で取り外し作業が容易に行えて解体作業の能率を向上させることができる。
【0010】
【実施例】
以下、本発明の実施例を図面に基づいて説明する。
【0011】
図1は本発明に係る建設用足場板を示すもので、足場板本体1の両端の四隅には、略逆U字形状のクランプ金具2を備えており、該クランプ金具2には図2に示すように建枠横架材Pを嵌め入れる凹部3を備えており、該凹部3は凹部3の中心部を挟んで水平方向に略6.5mmの距離L2を隔てた二つの中心から略22mmの半径rによって描かれる円弧により形成されている。
【0012】
これは、図7に示す従来のクランプ金具の凹部の二つの中心O、O´間の距離L1の3mmより更に3.5mm広くしたもので、図5に示すように、足場板本体1を傾斜させた状態で持ち上げれば、建枠横架材Pから抜き出すことができる広さを確保するものである。
【0013】
また、クランプ金具2の基部には建枠横架材Pの側面を挟持するロック金具4を配設している。ロック金具4は、図2に示すように、その凹部3側に位置する縁部5を建枠横架材Pの外周に沿うように湾曲させると共に、ロック金具4の下端部には建枠横架材Pを挟持する時に建枠横架材Pの下面に当接させる挟持用突起6を形成しており、該挟持用突起6の先端は建枠横架材Pを挟持したときに建枠横架材Pの断面中心の真下付近まで突出するように形成されている。
【0014】
また、ロック金具4の挟持用突起6をクランプ金具2の凹部3に対して出没自在とするために、ロック金具4に穿設した二つのガイド孔7、8に二本の支持ピン9、10を介してロック金具4をクランプ金具2に取り付け、ガイド孔7、8に案内されながらロック金具4の挟持用突起6をクランプ金具2の凹部3に対し出没自在とし、建枠横架材Pの挟持・解除をできるようにしている。
【0015】
前記支持ピン9、10の配置及びガイド孔7、8の孔形状は、足場板本体1を傾斜させた状態で傾斜方向に沿って斜め下方向に押し下げると、クランプ金具2の凹部3に突出するロック金具4の縁部5が建枠横架材Pに押し当たり、図5に示すように、その押圧力によってロック金具4が凹部3より退避没入するような配置と孔形状とする。図2に示すクランプ金具2では、支持ピン10を支持ピン9位置より若干右側上方としクランプ金具2が退避しやすいような配置とし、またガイド孔7、8も傾斜時にロック金具4の縁部5側を押すとスムーズに退避没入できる形状に工夫している。
【0016】
また、ガイド孔8は略L字形状として係止部11を形成し、図5に示すように、ロック金具4がクランプ金具2の凹部3より退避没入時に係止部11に支持ピン10を嵌め入れてロック金具4を係止してずり落ちないようにしている。
【0017】
次に、本発明に係る足場板の取り外し方法について説明する。
【0018】
足場板は、図3に示すように、対向させた建枠の建枠横架材Pに足場板本体1両端のクランプ金具2を嵌め入れて係止されている。そして、工事が完了して足場板を取り外すときには、先ず、図4に示すように、足場板本体1の一端側のクランプ金具2のロック金具4を操作して挟持状態を解除し、そのまま足場板本体1を上方に持ち上げて足場板の一端部を建枠横架材Pから外す。
【0019】
足場板の一端側を外すと足場板本体1は傾斜状態となる。そこで、図4に示すように、傾斜状態になった足場板本体1をその状態で斜め下方に押し下げると、図5に示すように、下方のクランプ金具2のロック金具4の縁部5が横架材Pに押し当てられることになり、その作用でロック金具4が凹部3より退避没入するように回動する。そして所定位置まで回動するとロック金具4のガイド孔8の係止部11に支持ピン10が嵌り込んでロック金具4を係止してずり落ちないようにする。
【0020】
この状態になると、図6に示すように、傾斜状態の足場板本体1を垂直方向に持ち上げると、クランプ金具2の凹部3の下部開口を建枠横架材Pから抜き出しできる広さとしているので、建枠横架材Pより簡単に取り外すことができる。
【0021】
このように、足場板の一端のクランプ金具2の挟持を解除して持ち上げ、この状態で足場板の傾斜方向に沿って斜め下方向に押し下げると、他端側のクランプ金具2のロック金具4の挟持を手を触れずに解除できて足場板を簡単に取り外せるので、作業員一人で簡単に取り外し作業が行えて解体作業の能率を向上できる。
【0022】
なお、この足場板を取り付けるときには、ロック金具4のガイド孔8の係止部11を支持ピン10に嵌め込んでロック金具4を係止し、この状態で建枠横架材Pに掛け渡してからロック金具4を挟持状態とする。ロック金具4が挟持状態となっていると、風圧による足場板の吹き上げが起こっても、クランプ金具2に備えたロック金具4の挟持用突起6が横架材Pの下面に当接して挟持状態を維持し、足場板が外れることはない。
【0023】
なお、本実施例のクランプ金具2を足場板の両端に取り付けると、ロック金具の解除側をいちいち選択せずに取り外すことができて好都合であるが、足場板の一端側のみを本実施例のクランプ金具2とすることもできる。
【0024】
【発明の効果】
以上説明したように、本発明に係る建設用足場板によれば、足場板本体の少なくとも一方側のクランプ金具の凹部の下部開口は足場板本体を傾斜させた状態で建枠横架材から抜き出し可能な広さとすると共に、足場板本体を傾斜させた状態でクランプ金具の凹部の下部開口に突出するクランプ金具の基部のロック金具を建枠横架材に押し当てると、前記ロック金具がガイド孔に案内されながらクランプ金具の凹部の下部開口より退避没入して建枠横架材の下面より離間し、クランプ金具の凹部の下部開口を開放状態とするように前記支持ピンとガイド孔を配置形成したので、足場板取り外し時に、足場板の一端側のクランプ金具を手作業により外して持ち上げ、この傾斜状態で傾斜方向に押し下げれば他端側のロック金具を手を触れずに外すことができ、一人作業でも簡単に足場板の取り外し作業を行え、解体作業の能率を向上できる。
【図面の簡単な説明】
【図1】本発明に係る建設用足場板の正面図である。
【図2】図1のクランプ金具を示す説明図である。
【図3】本発明に係る建設用足場板の使用状況を説明する説明図である。
【図4】本発明に係る建設用足場板の使用状況を説明する説明図である。
【図5】本発明に係る建設用足場板の使用状況を説明する説明図である。
【図6】本発明に係る建設用足場板の使用状況を説明する説明図である。
【図7】従来の建設用足場板の図2に相当する説明図である。
【符合の説明】
1…足場板本体 2…クランプ金具
3…凹部 4…ロック金具
5…縁部 6…挟持用突起
7、8…ガイド孔 9、10…支持ピン
11…係止部 P…建枠横架材[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction scaffold plate used for a temporary scaffold at a construction site.
[0002]
[Prior art]
Construction scaffolding boards are spanned between building frames assembled around the building to form working scaffolds. As described in Japanese Utility Model Publication No. 60-1840 at both ends of the scaffolding board main body. In addition, a substantially inverted U-shaped clamp fitting for locking the scaffolding plate to a horizontal member made of a tubular body of a building frame is provided. When the scaffolding plate is passed over, the locking bracket attached to the base of the clamp bracket is rotated to project the clamping projection to clamp the horizontal member so that the scaffolding plate does not easily blow up due to wind pressure. Yes.
[0003]
And when the construction work is finished and the work scaffold is dismantled, the clamp brackets at the four corners of the scaffold plate are manually rotated to release the holding state of the horizontal member, and the scaffold plate is removed from the building frame. Yes.
[0004]
[Problems to be solved by the invention]
However, although the above-mentioned conventional lock plate of the scaffolding plate has a structure that can be temporarily held at the position where the clamped state is released, the lock metal plate can rotate and return to the original clamped state with a slight vibration. Yes, when one person tries to remove the scaffolding plate, if one end of the scaffolding plate is lifted, the lock metal fitting on the other end may rotate and be in a clamping state. Moreover, although the recessed part of the
[0005]
For this reason, removal work may not be achieved by one person's work, and removal work is often carried out by a group of two people, and the efficiency of the dismantling work is never good.
[0006]
In view of the above points, an object of the present invention is to provide a construction scaffold plate that can be easily removed even by one person and can improve the efficiency of the dismantling work.
[0007]
[Means for Solving the Problems]
In order to achieve the above object, the present invention is provided with a lock metal fitting provided with a substantially inverted U-shaped clamp fitting opened downward at both ends of a scaffold plate body, and two guide holes formed at the base of the clamp fitting. Attach via two support pins. At the lower end of the lock fitting, a pinching protrusion is formed to contact the lower surface of the building frame horizontal member when holding the building frame horizontal member. in the above construction scaffolding plate as the holding projection is retractable toward the lower opening of the recess of the clamping bracket for clamping and releasing the Kenwaku lateral bridging material, at least one of the scaffold plate body while rotating along the The lower opening of the concave part of the clamp bracket on the side is wide enough to be extracted from the building frame horizontal member with the scaffold plate body tilted, and the lower opening of the concave part of the clamp bracket with the scaffold plate body tilted clamp bracket that projects When pressing the lock fitting of the base to Kenwaku horizontal member, apart from the lower surface of Kenwaku horizontal member the locking fitting while being guided by the guide hole and retracted retracted from the lower opening of the recess of the clamping bracket, the clamping bracket The support pin and the guide hole are arranged and formed so that the lower opening of the concave portion is opened .
[0008]
DETAILED DESCRIPTION OF THE INVENTION
In the construction scaffold plate according to the present invention, when trying to disassemble the scaffold plate spanned between the horizontal members of the assembled building frame, the lock fitting of the clamp fitting on one end side of the scaffold plate body is operated. Then, the sandwiched state is released, and one end side of the scaffold plate is lifted upward. When one side of this scaffolding plate is lifted and the scaffolding plate is pushed down diagonally downward along the tilt direction, the edge facing the concave side of the lock fitting of the clamp fitting arranged on the other end side is the side of the building frame. The lock fitting comes into contact with the base material and the lock fitting is retracted and retracted from the recess by the pressing force. Next, when the scaffolding plate is tilted upward, the lower opening of the concave part of the clamp fitting is wide enough to be pulled out from the building frame horizontal member with the scaffolding plate tilted. It can be removed from the frame.
[0009]
In this way, after releasing the clamping state by manually operating the clamp metal fitting on one end of the scaffolding plate, lift the scaffolding plate and do not touch the lock metal fitting on the other clamp. The scaffolding plate can be removed by releasing the sandwiched state, and the removal work can be easily performed by one person to improve the efficiency of the dismantling work.
[0010]
【Example】
Embodiments of the present invention will be described below with reference to the drawings.
[0011]
FIG. 1 shows a construction scaffolding plate according to the present invention. At the four corners of both ends of the scaffolding plate
[0012]
This is made wider by 3 mm than the distance L1 between the two centers O and O ′ of the recesses of the conventional clamp fitting shown in FIG. 7, and as shown in FIG. If it lifts in the state made to do, the area which can be extracted from the building frame horizontal member P is ensured.
[0013]
In addition, a lock fitting 4 that clamps the side surface of the building frame horizontal member P is disposed at the base of the
[0014]
In addition, in order to allow the
[0015]
The arrangement of the
[0016]
Further, the
[0017]
Next, a method for removing the scaffold plate according to the present invention will be described.
[0018]
As shown in FIG. 3, the scaffolding plate is locked by fitting
[0019]
When one end side of the scaffolding plate is removed, the
[0020]
In this state, as shown in FIG. 6, when the
[0021]
In this way, when the
[0022]
When attaching this scaffolding plate, the locking
[0023]
Note that it is convenient to attach the clamp fitting 2 of the present embodiment to both ends of the scaffold plate, so that it is possible to remove the lock bracket without selecting the release side one by one, but only one end side of the scaffold plate of the present embodiment is used. The clamp fitting 2 can also be used.
[0024]
【The invention's effect】
As described above, according to the construction scaffolding plate according to the present invention, the lower opening of the concave portion of the clamp fitting on at least one side of the scaffolding plate body is extracted from the building frame horizontal member with the scaffolding plate body inclined. When the lock bracket at the base of the clamp fitting that protrudes into the lower opening of the concave portion of the clamp fitting is pressed against the building frame horizontal member while the scaffold plate body is inclined , the lock fitting is moved into the guide hole. The support pin and the guide hole are arranged and formed so as to retract and sink from the lower opening of the recess of the clamp fitting while being guided by the guide, and are separated from the lower surface of the building frame horizontal member to open the lower opening of the recess of the clamp fitting . So, when removing the scaffolding plate, remove the clamp bracket on one end of the scaffolding plate by hand, lift it up and push it down in the tilted direction, and remove the lock bracket on the other end without touching it. Door can be, perform the removal work of easily scaffolding plate also one work, it is possible to improve the efficiency of the demolition work.
[Brief description of the drawings]
FIG. 1 is a front view of a construction scaffold plate according to the present invention.
FIG. 2 is an explanatory view showing the clamp fitting of FIG. 1;
FIG. 3 is an explanatory diagram for explaining a use situation of a construction scaffold board according to the present invention.
FIG. 4 is an explanatory diagram for explaining a use situation of a construction scaffold board according to the present invention.
FIG. 5 is an explanatory diagram for explaining a use situation of a construction scaffold board according to the present invention.
FIG. 6 is an explanatory diagram for explaining a use situation of the construction scaffold board according to the present invention.
FIG. 7 is an explanatory view corresponding to FIG. 2 of a conventional construction scaffold board.
[Explanation of sign]
DESCRIPTION OF
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP03912398A JP3996993B2 (en) | 1998-02-20 | 1998-02-20 | Construction scaffolding board |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP03912398A JP3996993B2 (en) | 1998-02-20 | 1998-02-20 | Construction scaffolding board |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH11236762A JPH11236762A (en) | 1999-08-31 |
JP3996993B2 true JP3996993B2 (en) | 2007-10-24 |
Family
ID=12544333
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP03912398A Expired - Fee Related JP3996993B2 (en) | 1998-02-20 | 1998-02-20 | Construction scaffolding board |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3996993B2 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
TW201439411A (en) * | 2013-04-11 | 2014-10-16 | Sucoot Ind Co Ltd | Fastening member of scaffolding deck |
GB2543933B (en) * | 2016-09-20 | 2017-11-15 | Ischebeck Titan Ltd | Bracket |
-
1998
- 1998-02-20 JP JP03912398A patent/JP3996993B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH11236762A (en) | 1999-08-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3996993B2 (en) | Construction scaffolding board | |
JP7278071B2 (en) | Fittings hanger and fitting method | |
JP3860864B2 (en) | Hook devices such as scaffolding boards | |
JP4683595B2 (en) | Mounting method of handrail on frame scaffold | |
US20020014371A1 (en) | Tube element | |
JPH1037455A (en) | Scaffolding bracing | |
JP3009373B2 (en) | Scaffold board | |
JP2578580Y2 (en) | Scaffold board | |
JP2000064601A (en) | Construction scaffold board | |
CN214495428U (en) | Pre-buried hoisting point structure of prefabricated panel | |
JP2968700B2 (en) | Gripping connection fittings for structures | |
JPH11241502A (en) | Scaffolding board for construction | |
JPH11166316A (en) | Continuous frame with floor for temporary scaffold | |
JPH08231200A (en) | Vehicle for high lift work | |
KR20060000012U (en) | Pin needless and install no-impact lug for hand-rail | |
JP3019857U (en) | Suspension bracket for overhanging scaffold | |
JP3029468U (en) | Handrail device for temporary scaffolding | |
JP3043918U (en) | Handrail for temporary scaffolding | |
JPH0510640U (en) | Frame scaffold railing frame | |
JPH074284Y2 (en) | Auxiliary tool for mounting form panel | |
JPH0721908U (en) | PC board erection jig | |
JP2555101Y2 (en) | Jack for adjusting panel height | |
JP4373975B2 (en) | Opening and closing body device and hanging device used in the opening and closing body device | |
JP2004316157A (en) | Handrail for prefabricated scaffolding | |
JP2829827B2 (en) | Column lifting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050214 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070510 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070514 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070705 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070730 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070806 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100810 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100810 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100810 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110810 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120810 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120810 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130810 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |