JP3236880B2 - Greening seawall and concrete block for seawall - Google Patents
Greening seawall and concrete block for seawallInfo
- Publication number
- JP3236880B2 JP3236880B2 JP05949993A JP5949993A JP3236880B2 JP 3236880 B2 JP3236880 B2 JP 3236880B2 JP 05949993 A JP05949993 A JP 05949993A JP 5949993 A JP5949993 A JP 5949993A JP 3236880 B2 JP3236880 B2 JP 3236880B2
- Authority
- JP
- Japan
- Prior art keywords
- embankment
- block
- concrete
- ribs
- revetment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Revetment (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は、例えば大型河川におけ
る遊水地等のように通常は冠水しない箇所の大型堤防に
用いる緑化護岸及び同護岸用コンクリートブロックに関
する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a greening revetment and a concrete block for revetment used for a large embankment at a place where water is not normally flooded, for example, a basin in a large river.
【0002】[0002]
【従来の技術】従来、大型堤防の護岸は重量式のコンク
リートブロックを法面に沿って積み上げることによりコ
ンクリート護岸壁を堤防の河川側面に貼り付ける構造の
ものが一般的である。2. Description of the Related Art Conventionally, a revetment of a large embankment generally has a structure in which a concrete revetment wall is attached to a river side of a dike by stacking heavy concrete blocks along a slope.
【0003】また通常は流水に洗われることのない遊水
用河川敷の外側に構築された堤防にあっては、盛土の表
面に草類の植生を施したのみのものが一般的であった。[0003] In addition, most embankments constructed outside a riverbed for flooding, which are not usually washed by running water, only have grass vegetation applied to the surface of the embankment.
【0004】[0004]
【発明が解決しようとする課題】上述のような通常は冠
水しない場所の堤防であっても、数年乃至は数十年に一
度といった大雨の際に、その役目を果たす必要がある
が、盛土のみでは流水に洗われた際に崩壊の危険性が高
いため、これを補強しておく必要がある。Even if the embankment is located in a place where water is not normally flooded as described above, it is necessary to fulfill its role during heavy rain, such as once every several years or several decades. It is necessary to reinforce the risk of collapse when washed with running water, because it is very dangerous.
【0005】しかし、従来のコンクリートブロックによ
る護岸の場合にはコンクリート面が露出しているため、
周囲の景観を著しく変化させるという問題があった。[0005] However, in the case of revetment using a conventional concrete block, since the concrete surface is exposed,
There was a problem that the surrounding scenery was significantly changed.
【0006】本発明はこのような問題にかんがみ、通常
は盛土のみの堤防のように草類が表面全域を覆ってお
り、しかも大雨の際の増水によ表面が洗われても堤防の
崩壊には至らない緑化護岸構造及び護岸用ブロックの提
供を目的としてなされたものである。The present invention has been made in view of such a problem, and usually, grasses cover the entire surface of the embankment like a bank with only embankment, and even if the surface is washed away by flooding during heavy rain, the embankment may collapse. The purpose of this project is to provide a greening revetment structure and a revetment block that cannot be reached.
【0007】[0007]
【課題を解決するための手段】上述の如き従来の問題を
解決し、所期の目的を達成するための本発明の緑化護岸
の特徴は、方形状をした厚板のブロック本体の背面に築
堤盛土内に埋め込む定着用アンカー部を一体に有すると
ともに、該ブロック本体の表面側に複数の縦向き突リブ
を設け、該突リブの突出側端部には左右にフランジ状に
張り出した膨出部を一体に設けることにより該縦向き突
リブ間に蟻溝状凹溝が形成される護岸用コンクリートブ
ロックを、前記築堤盛土に前記アンカー部を埋め込むと
ともに突リブを上下に連続させて、前記蟻溝状凹溝が上
下に連続される配置に多数並べてコンクリート護岸壁を
構築し、該コンクリート護岸壁の表面の突リブを埋め込
んで、その表面に一定厚さの表層盛土を敷設し、該盛土
に前記蟻溝状凹溝内に根が張るように植生を施したこと
にある。SUMMARY OF THE INVENTION In order to solve the conventional problems as described above and to achieve the intended purpose, the feature of the greening seawall according to the present invention is that it is built on the back surface of a rectangular block-shaped block body.
An integral anchoring portion embedded in the embankment , and a plurality of vertically projecting ribs are provided on the surface side of the block body, and the projecting side ends of the projecting ribs protrude right and left in a flange shape. The vertical projection
A concrete block for revetment having a dovetail groove formed between ribs is embedded in the embankment embankment and the projecting ribs are vertically connected to each other so that the dovetail groove is raised.
A concrete revetment wall is constructed by arranging a large number of them in a continuous arrangement underneath, a protruding rib on the surface of the concrete revetment wall is buried, a surface embankment having a constant thickness is laid on the surface, and the dove groove recess is formed on the embankment. Vegetation was applied so that the roots could be set up in the grooves .
【0008】また、本発明の護岸用コンクリートブロッ
クの特徴は、方形状をした厚板のブロック本体の背面に
築堤盛土内に埋め込む定着用アンカー部を一体に有する
とともに、該ブロック本体の表面側に複数の縦向き突リ
ブを設け、該突リブの突出側端部には左右にフランジ状
に張り出した膨出部を一体に設けることにより該縦向き
突リブ間に蟻溝状凹溝が形成されるとともに左右に並べ
ることにより隣り合うブロックの縦向き突リブ間に蟻溝
状凹溝が形成されるようにしたことにある。The feature of the concrete block for seawall according to the present invention resides in that
An integral anchoring portion embedded in the embankment embankment , and a plurality of vertically protruding ribs are provided on the surface side of the block main body, and a protruding bulge that protrudes right and left at the protruding end of the protruding rib. The vertical orientation
A dovetail-shaped groove is formed between the protruding ribs and arranged side by side.
Dovetail groove between vertically projecting ribs of adjacent blocks
That is, a concave groove is formed .
【0009】[0009]
【作用】本発明においては、護岸用コンクリートブロッ
クを、その背面のアンカー部を築堤の盛土内に埋め込む
ことにより築堤に安定性良く定着される。また前面側の
突リブを上下に連続させた配置に多数の護岸用コンクリ
ートブロックを並べて設置することにより突リブ間の溝
が上下に連続した配置となり、溝内への表層盛土の充填
が容易となる。In the present invention, a concrete block for revetment is stably fixed to the embankment by embedding the anchor portion on the back surface thereof in the embankment of the embankment. In addition, the grooves between the protruding ribs are arranged vertically continuously by arranging a large number of revetment concrete blocks in an arrangement where the protruding ribs on the front side are vertically connected, making it easy to fill the surface layer embankment into the grooves. Become.
【0010】更に表層盛土に植えた草木類は、その根が
突リブ間の蟻溝状内にはびこることにより内部の土を強
力に保持し、流水によって洗われても容易には洗い流さ
れない。[0010] Furthermore, the plants and plants planted on the surface embankment strongly retain the soil inside by the roots rising into the dovetails between the protruding ribs, and are not easily washed away even when washed with running water.
【0011】[0011]
【実施例】次に本発明の実施例を図面について説明す
る。BRIEF DESCRIPTION OF THE DRAWINGS FIG.
【0012】図1〜図3は本発明に係る護岸用コンクリ
ートブロックAの一例を示している。1 to 3 show an example of a concrete block A for revetment according to the present invention.
【0013】このブロックAは、長方形状の厚板状をし
たブロック本体部10の背面側に互いに平行配置に一対
の定着用アンカー部11,11を一体に有している。こ
のアンカー部11は、縦向きの板状をなしており、突出
側先端部に互いに外側に向けた張出部11aを一体に有
している。The block A has a pair of fixing anchors 11 and 11 integrally arranged in parallel with each other on the back side of a block body 10 having a rectangular thick plate shape. The anchor portion 11 is in the shape of a vertically oriented plate, and integrally has projecting portions 11a outwardly facing each other at the protruding end portions.
【0014】また両アンカー部11には、その上下面に
互いに対称配置の凹部11b,凸部11cが成形されて
おり、ブロック本体10を上下に重ねた際、この凹凸部
11b,11cを互いに整合させることにより、上下の
各ブロック本体10,10……が同一平面配置となるよ
うになっている。The upper and lower surfaces of both anchor portions 11 are formed with concave portions 11b and convex portions 11c which are symmetrically arranged. When the block main body 10 is vertically stacked, the concave and convex portions 11b and 11c are aligned with each other. The upper and lower block bodies 10, 10,... Are arranged in the same plane.
【0015】ブロック本体10の表面側には、一対の縦
向突リブ12,12が一体に突設されている。この突リ
ブ12には、その突出側端部の左右両縁に丸みをおびた
張出部12a,12aがフランジ状に一体成形されてお
り、その突リブ12,12間が奥部が広幅の蟻溝状の凹
溝15となっている。On the front side of the block body 10, a pair of vertically projecting ribs 12, 12 are integrally provided. The protruding ribs 12 are integrally formed with flanges at both left and right edges of the protruding end, and are formed integrally with each other in a flange shape. The dovetail groove 15 is formed.
【0016】またこの両突リブ12,12は、その中心
からブロック本体10の両側縁までの間隔aが両突リブ
12,12の中心間隔bの半分になるように配置されて
いる。The two ribs 12, 12 are arranged such that the distance a from the center thereof to both side edges of the block body 10 is half the center distance b of the two ribs 12, 12.
【0017】ブロック本体10には、その中央部分の肉
厚内に上下に貫通して場所打コンクリート充填孔13が
開口されているとともに、両側面には前記コンクリート
充填孔13を半割した形状の場所打コンクリート充填凹
溝14,14が成形されており、互いに隣り合わせにブ
ロック本体部10を並べた際に凹溝14が互いに向き合
ってコンクリート充填孔13a(図6に示す)となるよ
うにしている。The block body 10 is provided with a cast-in-place concrete filling hole 13 which penetrates vertically in the thickness of the central portion thereof, and has a shape in which the concrete filling hole 13 is divided in half on both sides. Cast-in-place concrete filling grooves 14, 14 are formed so that when the block main bodies 10 are arranged next to each other, the grooves 14 face each other to form concrete filling holes 13a (shown in FIG. 6). .
【0018】このように構成されるブロックAを使用し
て緑化護岸を構築するには、図4に示すように場所打コ
ンクリートをもって基礎20を構築し、その上にブロッ
クAを、そのアンカー部11を築堤盛土Bの法面側に向
け、予め定められた所望の傾斜角度に積み上げる。この
とき上下のブロックAは図5に示すように、その横方向
の長さの1/2ずつ側方にずらせて設置して所謂布積状
となす。これによって、左右のブロックAの突リブ1
2,12間に蟻溝状凹溝15を形成させるとともに、上
下のブロックA間において突リブ12を上下に連続させ
て上下に連続した蟻溝状凹溝15を形成させる。また、
同時に下側のブロック本体10の中央コンクリート充填
孔13上に、上側の両ブロック本体10,10の側面を
突き合わせることによって形成されるコンクリート充填
孔13aを連続させる。[0018] To build the greening revetment using thus constructed blocks A constructs a foundation 20 with a location hitting concrete as shown in FIG. 4, the block A on it, the anchor portion 11 the towards slope side of the embankment fill B, stacked to the desired tilt angle determined in advance. At this time, as shown in FIG. 5, the upper and lower blocks A are laterally shifted by 1/2 of the lateral length thereof, and are so-called laid-up.
And As a result, the projecting ribs 1 of the left and right blocks A
A dovetail-shaped groove 15 is formed between
The protruding ribs 12 are vertically connected between the lower blocks A.
To form a dovetail-shaped concave groove 15 continuous vertically. Also,
At the same time, a concrete filling hole 13a formed by abutting the side surfaces of both upper block bodies 10, 10 on the central concrete filling hole 13 of the lower block body 10 is continued .
【0019】このようにして各ブロックAを順次積み上
げつつその背面に裏込め用の土砂を詰めて築堤盛土Bと
一体化する。そして所定の高さに積み上げる毎に上下に
連通した各コンクリート充填孔13,13a内に連結部
補強用の棒鋼21を挿入し、その中にコンクリート22
を充填し、各ブロックAを一体化し、コンクリート護岸
となす。棒鋼21は、その最下端のものを基礎20内に
埋め込み、カプラージョイント23を使用して順次上方
に延長させる。In this way, while the blocks A are sequentially stacked, the backside is filled with backfill soil and integrated with the embankment embankment B. Each time the pile is stacked at a predetermined height, a steel bar 21 for reinforcing the connecting portion is inserted into each of the concrete filling holes 13 and 13a communicating vertically, and concrete 22 is inserted therein.
And the blocks A are integrated to form a concrete revetment. The lower end of the steel bar 21 is embedded in the foundation 20, and is sequentially extended upward using the coupler joint 23.
【0020】このように築堤盛土Bの川側法面にコンク
リート護岸壁を構築した後、図7に示すようにその表面
側に表層盛土Cを層状に敷設し、突き固める。この表層
盛土Cの敷設には、各突リブ12,12……間の蟻溝状
凹溝15,15……内にも所望の密度となるように充分
に充填する。なおこの充填は法面上部から土砂を投下し
て凹溝15,15……内を滑り落すことにより内部に充
填することができる。After the concrete revetment wall has been constructed on the river side slope of the embankment embankment B in this way, a surface embankment C is laid in layers on the surface side as shown in FIG. When the surface embankment C is laid, the dovetail grooves 15, 15 between the protruding ribs 12, 12,... Are sufficiently filled so as to have a desired density. The filling can be performed by dropping earth and sand from the upper part of the slope and sliding down the inside of the grooves 15, 15,....
【0021】このように敷設された表層盛土に予め草類
の種子と肥料を混入させておくか、又はその表面に芝生
類を貼り、これらを生育させて植生となし(図示せ
ず)、この草類が育つことにより、根が蟻状溝15内の
土砂内に張るように植生を施す。これによって、土砂が
保持されて容易に抜け出ない状態となり、コンクリート
護岸の表面に表層盛土と草類と一体となって強固に定着
される。[0021] either leave is mixed seeds and fertilizer advance grasses in the laid surface embankment Thus, or paste the lawn compound on the surface, they were grown in vegetation and without (not shown), this As the grass grows, the roots
Vegetation is applied to the soil. As a result, the sediment is kept in a state where it is not easily released, and it is firmly fixed on the surface of the concrete revetment with the surface embankment and grass.
Is done .
【0022】[0022]
【発明の効果】上述したように本発明においては、築堤
盛土の法面はコンクリートブロックによる盤状の護岸壁
によって完全に覆われることとなり、大雨によって河川
が増水し、法面が洗われても崩壊することがなく、また
表層盛土は植生と一体となって蟻溝状の凹溝内に嵌まり
込んでいるため、容易に洗い流れることがなく緑化が維
持される。As described above, according to the present invention, the slope of the embankment embankment is completely covered by the board-shaped revetment wall made of concrete blocks, and even if the river is flooded by heavy rain and the slope is washed. Since it does not collapse, and the surface embankment is fitted into the dovetail-shaped groove integrally with the vegetation, it is not easily washed away and the greening is maintained.
【0023】また、強い流水によって長時間洗われ、表
層盛土が流失しても護岸壁の内側には全く影響を及ぼす
ことがなく、出水が元に戻った際に表層盛土のみの盛り
直しによって再度緑化が得られる。Further, even if the surface embankment is washed away by strong running water for a long time, even if the surface embankment is washed away, it has no effect on the inside of the revetment wall. Greening is obtained.
【図1】本発明に係る護岸用コンクリートブロックの平
面図である。FIG. 1 is a plan view of a seawall concrete block according to the present invention.
【図2】同上の正面図である。FIG. 2 is a front view of the same.
【図3】同上の側面図である。FIG. 3 is a side view of the same.
【図4】本発明に係る護岸の構築途中状態を示す縦断面
図である。FIG. 4 is a longitudinal sectional view showing a state in which a seawall according to the present invention is being constructed.
【図5】同上の傾斜を省略した正面図である。FIG. 5 is a front view in which the inclination is not shown.
【図6】図4中のA−A線断面図である。FIG. 6 is a sectional view taken along line AA in FIG. 4;
【図7】本発明に係る護岸の完成状態を示す横断面図で
ある。FIG. 7 is a cross-sectional view showing a completed state of the revetment according to the present invention.
A 護岸用コンクリートブロック B 盛土 C 表層盛土 10 ブロック本体 11 アンカー部 11a 張出部 11b,11c 凹凸部 12 突リブ 12a 膨出部 13,13a コンクリート充填孔 14,15 凹溝 20 基礎 21 棒鋼 22 コンクリート 23 カプラージョイント A Concrete block for revetment B Embankment C Surface embankment 10 Block body 11 Anchor part 11a Overhang part 11b, 11c Uneven part 12 Projection rib 12a Swelling part 13, 13a Concrete filling hole 14, 15 groove 20 Foundation 21 Steel bar 22 Concrete 23 Coupler joint
───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E02B 3/14 E02B 3/12 E02D 17/20 ──────────────────────────────────────────────────続 き Continued on the front page (58) Field surveyed (Int.Cl. 7 , DB name) E02B 3/14 E02B 3/12 E02D 17/20
Claims (2)
に築堤盛土内に埋め込む定着用アンカー部を一体に有す
るとともに、該ブロック本体の表面側に複数の縦向き突
リブを設け、該突リブの突出側端部には左右にフランジ
状に張り出した膨出部を一体に設けることにより該縦向
き突リブ間に蟻溝状凹溝が形成されるとともに左右に並
べることにより隣り合うブロックの縦向き突リブ間に蟻
溝状凹溝が形成される護岸用コンクリートブロックを、
前記築堤盛土に前記アンカー部を埋め込むとともに突リ
ブを上下に連続させて、前記蟻溝状凹溝が上下に連続さ
れる配置に多数並べてコンクリート護岸壁を構築し、該
コンクリート護岸壁の表面の突リブを埋め込んで、その
表面に一定厚さの表層盛土を敷設し、該盛土に前記蟻溝
状凹溝内に根が張るように植生を施してなる緑化護岸。1. A block-shaped block main body having a rectangular shape, an anchor portion for fixing embedded in a bank embankment is integrally provided on a back surface of the block main body, and a plurality of vertically projecting ribs are provided on a surface side of the block main body. The rib is provided with a bulging part that protrudes in the shape of a flange on the left and right sides at the projecting end.
A dovetail groove is formed between the protruding ribs and
Ants between the vertical ribs of adjacent blocks
A concrete block for revetment where a groove-like groove is formed ,
The anchor portion is embedded in the embankment and the projecting ribs are vertically connected so that the dovetail groove is vertically continuous.
Building a large number side by side concrete revetment wall arrangements, embed collision rib surface of the concrete revetment walls, laying surface embankment having a predetermined thickness on the surface thereof, wherein the該盛soil dovetail
A greening seawall with vegetation so that the roots are stretched in the groove .
に築堤盛土内に埋め込む定着用アンカー部を一体に有す
るとともに、該ブロック本体の表面側に複数の縦向き突
リブを設け、該突リブの突出側端部には左右にフランジ
状に張り出した膨出部を一体に設けることにより該縦向
き突リブ間に蟻溝状凹溝が形成されるとともに左右に並
べることにより隣り合うブロックの縦向き突リブ間に蟻
溝状凹溝が形成されるようにしてなる護岸用コンクリー
トブロック2. A block-shaped block main body having a rectangular shape, a fixing anchor portion embedded in a bank embankment is integrally provided on a back surface of the block main body, and a plurality of vertically projecting ribs are provided on a surface side of the block main body. The rib is provided with a bulging part that protrudes in the shape of a flange on the left and right sides at the projecting end.
A dovetail groove is formed between the protruding ribs and
Ants between the vertical ribs of adjacent blocks
Revetment concrete block with grooved grooves formed
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP05949993A JP3236880B2 (en) | 1993-02-24 | 1993-02-24 | Greening seawall and concrete block for seawall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP05949993A JP3236880B2 (en) | 1993-02-24 | 1993-02-24 | Greening seawall and concrete block for seawall |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH06248627A JPH06248627A (en) | 1994-09-06 |
JP3236880B2 true JP3236880B2 (en) | 2001-12-10 |
Family
ID=13115046
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP05949993A Expired - Fee Related JP3236880B2 (en) | 1993-02-24 | 1993-02-24 | Greening seawall and concrete block for seawall |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3236880B2 (en) |
-
1993
- 1993-02-24 JP JP05949993A patent/JP3236880B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH06248627A (en) | 1994-09-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA1043581A (en) | Quay structure | |
US5064313A (en) | Embankment reinforcing structures | |
US10480150B2 (en) | Retaining wall method of precast block to prevent landslide | |
WO1991019057A2 (en) | Improvements in embankment reinforcing structures | |
US20070110522A1 (en) | Retaining wall constructed using sandbags | |
CN210482200U (en) | Ecological bank protection structure of high and steep river course bank slope | |
US5154542A (en) | Earth-retaining module, system and method | |
US5499891A (en) | Earth-retaining module and system | |
KR100515136B1 (en) | Vegetation block, and method for constructing vegetation retaining wall and bank protection using the block | |
JP3236880B2 (en) | Greening seawall and concrete block for seawall | |
KR200345937Y1 (en) | Precast concrete block for retaining wall | |
KR101334749B1 (en) | Vegetation block in tiers for retaining wall and method for construction of retaining wall using the same | |
JP3472708B2 (en) | Slope and seawall retaining wall structures and their construction methods | |
KR200263961Y1 (en) | Sectional block for retaining wall building | |
KR101045019B1 (en) | Installation structure of block type breast wall and its construction method | |
KR20080014176A (en) | Environmental affinity reinforcement soil retaining wall using a earth pressure reduction type environmental affinity block, and the construction method of this | |
KR200300440Y1 (en) | Revetment block | |
KR100514086B1 (en) | Revetment block | |
KR102244753B1 (en) | Eco retaining wall structure using wood | |
JPH0754349Y2 (en) | Concrete block for retaining wall construction | |
RU2034957C1 (en) | Creep resistant construction | |
JP3079381U (en) | Revetment concrete block | |
KR102231712B1 (en) | Retaining wall structure using wood | |
KR200345934Y1 (en) | Anchoring structure of afforestation Retaining-Wall | |
JP3294715B2 (en) | Block structure for retaining wall and method for forming retaining wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |