JP3167203B2 - Main column replacement equipment for steel pipe steel tower - Google Patents
Main column replacement equipment for steel pipe steel towerInfo
- Publication number
- JP3167203B2 JP3167203B2 JP33718092A JP33718092A JP3167203B2 JP 3167203 B2 JP3167203 B2 JP 3167203B2 JP 33718092 A JP33718092 A JP 33718092A JP 33718092 A JP33718092 A JP 33718092A JP 3167203 B2 JP3167203 B2 JP 3167203B2
- Authority
- JP
- Japan
- Prior art keywords
- replacement
- main
- main column
- slide
- tower
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Electric Cable Installation (AREA)
Description
【0001】[0001]
【産業上の利用分野】この発明は、鋼管を用いた鉄塔の
最下腕金より下部の主柱材を取替えるための装置に関す
る。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an apparatus for replacing a main pillar below a lower arm of a steel tower using a steel pipe.
【0002】[0002]
【従来の技術】例えば、架空送電線用鋼管鉄塔におい
て、最下腕金より下部の主柱材が損傷するなどして取替
えが必要になった場合、従来は、鉄塔に架設されている
電線を取外し、その後、図4に示すように、取替主柱材
1の両隣りの主柱に支線5、6をかけてこの線を緊張す
る方法や取替主柱材1の上部の健全な主柱材2をトラッ
ククレーンで吊り上げる方法等で取替主柱材に掛ってい
る応力を除去し、鉄塔上部を傾かないように支えながら
新主柱材と交換する方法を採っている。2. Description of the Related Art For example, in a steel tube tower for overhead power transmission lines, when a main pillar material below a lower arm is damaged and needs to be replaced, conventionally, an electric wire installed on the steel tower is replaced with a new one. After that, as shown in FIG. 4, as shown in FIG. 4, a method of tensioning this line by applying branch lines 5 and 6 to the main columns adjacent to the main column The method removes the stress applied to the replacement main column by lifting the column 2 with a truck crane or the like, and replaces the column with the new main column while supporting the upper part of the tower so as not to tilt.
【0003】架空電線を事前に外すのは、最下腕金より
下部の場合、鉄塔重量だけでなく、電線、碍子類の重
量、鉄塔、電線が受ける風圧荷重、線路の角度荷重等、
全ての応力が主柱材に働いているため、支線やトラック
クレーンによる支持では不測の事態に対応するのが難し
く、従って、鉄塔を身軽にして取替作業を進める方が安
全上からも好ましいことによる。[0003] In the case where the overhead electric wire is removed in advance below the lower arm, not only the weight of the steel tower but also the weight of the electric wire and insulators, the wind pressure load applied to the steel tower and the electric wire, the angular load of the line, and the like.
Since all stress is acting on the main pillar, it is difficult to respond to unexpected situations by supporting with a branch line or a truck crane. Therefore, it is preferable from the viewpoint of safety to make the tower light and proceed with replacement work by.
【0004】なお、送電線建設技術研究会発行の「鉄塔
工事基準解説書」(TLS−2 1991年)P16
1、P178〜183に示されている嵩上げ工法用の装
置を用いて取替位置より上部の鉄塔全体を一旦持ち上げ
る方法でも主柱材の取替えは可能である。[0004] In addition, "Tower construction standard commentary book" (TLS-2 1991) P16 issued by the Transmission Line Construction Technology Research Group.
1. It is also possible to replace the main pillar by a method in which the entire tower above the replacement position is once lifted by using the apparatus for raising method shown on pages 178 to 183.
【0005】[0005]
【発明が解決しようとする課題】上述した在来の取替工
法では、架空送電鉄塔の場合、電線を外すので作業中の
停電が避けられず、作業に要する工具、人員、時間も非
常に多くなる。In the conventional replacement method described above, in the case of an overhead power transmission tower, electric wires are removed, so that a power outage during work is unavoidable, and the tools, personnel, and time required for the work are extremely large. Become.
【0006】また、鋼管鉄塔の場合、主柱材をつなぐフ
ランジ継手間に20mm程度の隙間がないと主柱材の入替
えが難しいので、その隙間を作るために上部の鉄塔の持
ち上げを大きくしており、そのため、周囲の主柱材や腹
材が持ち上げに抵抗して持ち上げに過大な力が必要にな
り、周囲の部材にも余分な応力が発生する。In the case of a steel pipe tower, if there is no gap of about 20 mm between the flange joints connecting the main pillars, it is difficult to replace the main pillars. As a result, the surrounding main pillars and abdominal material resist lifting, and an excessive force is required for lifting, and extra stress is generated in the surrounding members.
【0007】一方、嵩上げ装置を用いる工法では、電線
を架線したままで作業できる利点はあるが、線路に角度
がなくて安定支持ができる鉄塔であること、平地で装置
の搬入運搬路を整備できる場所に鉄塔があること、装置
の設計が困難にならない中、小型の山形鋼を用いた鉄塔
や比較的小型の鋼管鉄塔であること、更には、装置の取
付位置、工事中の装置及び鉄塔の強度、基礎補強などの
特殊設計を各鉄塔毎に行わなければならないなどの多く
の条件がつくため、利用範囲が狭く、汎用性にも欠け
る。[0007] On the other hand, the construction method using the raising device has an advantage that the work can be carried out with the electric wire being wired, but it is a steel tower capable of stably supporting the track without an angle, and the carrying path of the device can be maintained on flat ground. While there is a steel tower in the place and the design of the equipment does not become difficult, it should be a steel tower using small angle iron or a relatively small steel pipe steel tower.In addition, the installation position of the equipment, the equipment under construction and the steel tower There are many conditions, such as the need to perform special designs such as strength and foundation reinforcement for each steel tower, so the range of use is narrow and lacks versatility.
【0008】また、工事期間中は停電を必要とし、さら
に、工法特有の管理項目が多いため、施工も大変難し
い。加えて、装置が大型かつ高価で現場への運搬も大変
な上に、作業人員も多くなり、施工コストが高くつく。[0008] Further, during the construction period, a power outage is required, and since there are many management items specific to the construction method, the construction is very difficult. In addition, the equipment is large and expensive, and it is difficult to transport it to the site. In addition, the number of workers increases, and the construction cost is high.
【0009】在来の取替工法や嵩上げ装置を用いての工
法には、上述した如き数多くの問題がある。そこで、こ
の発明は、作業の省人、省力化、時間短縮、コスト削
減、実施規制の緩和を可能ならしめることを課題として
いる。The conventional replacement method and the method using a raising device have a number of problems as described above. Therefore, an object of the present invention is to enable labor saving, labor saving, time reduction, cost reduction, and relaxation of implementation regulations.
【0010】[0010]
【課題を解決するための手段】上記の課題を解決するこ
の発明の主柱材取替装置は、取替主柱材の上下に位置す
る健全な主柱材に固定する対向一対のベース金具と、こ
の対のベース金具間に取付けるジャッキアップ支柱及び
この支柱を長手方向に押し引きするシリンダと、上下の
健全な主柱材に固定して取替主柱材の上下の各接続部に
取付ける対向一対のスライド交換装置を具備し、この対
のスライド交換装置のスライド面間に新主柱材を取替主
柱材と並列にセットし、前記シリンダを押出して取替主
柱材に掛っている応力を除いた後、新主柱材をスライド
交換装置で横滑りさせて取替主柱材と入れ替えるように
したものである。According to a first aspect of the present invention, there is provided a main column replacement device which comprises a pair of opposed base fittings fixed to sound main columns located above and below the replacement main column. A jack-up strut to be mounted between the pair of base brackets, a cylinder for pushing and pulling the strut in the longitudinal direction, and a facing to be fixed to upper and lower sound main pillars and to be attached to upper and lower connection portions of the replacement main pillar. A pair of slide exchange devices are provided, and the new main column is set in parallel with the replacement main column between the slide surfaces of the pair of slide exchange devices, and the cylinder is pushed out to hang on the replacement main column. After removing the stress, the new main pillar is slid by the slide exchanging device and replaced with the replacement main pillar.
【0011】なお、スライド交換装置は、新主柱材を押
込んでスライドさせるもの、引込んでスライドさせるも
ののどちらであってもよい。The slide exchanging device may be either a device that pushes in the new main pillar and slides it, or a device that pulls in and slides it.
【0012】[0012]
【作用】本装置は、鉄塔の4脚中の1脚のみにセットす
る。その1脚について、取替主柱材の上下の健全な主柱
材を本装置で連結し、ジャッキアップ支柱で取替主柱材
に掛っている応力を肩代わりして受けるので、鉄塔は4
脚支持と差のない状態になり、作業中と云えども常に安
定する。This device is set on only one of the four legs of the tower. For this one leg, healthy main pillars above and below the replacement main pillar are connected by this device, and the stress applied to the replacement main pillar by the jack-up support is shouldered and the steel tower is replaced by four.
There is no difference with the leg support, and it is always stable even when working.
【0013】また、取替主柱材と新主柱材をスライド交
換装置を用いて入れ替えるので、フランジ継手間の隙間
は主柱材のスライドを妨げないだけの微々たる量でよ
く、周囲の部材に余分な応力を発生させずに済む。しか
も、交換中の主柱材の少なくとも一方が作業中常に上下
の健全な主柱材間にあって鉄塔の上部を支え得る態勢に
なっているので、急激な荷重増加、シリンダの故障など
の不測の事態が生じても安全である。Further, since the replacement main column material and the new main column material are exchanged by using the slide exchanging device, the gap between the flange joints may be only a small amount that does not hinder the sliding of the main column material. No extra stress is generated. In addition, since at least one of the main pillars being replaced is always located between the upper and lower healthy main pillars and is able to support the upper part of the tower, unexpected situations such as a sudden increase in load, cylinder failure, etc. It is safe even if it occurs.
【0014】従って、架空送電鉄塔の場合、電線を外さ
なくても、また、取替場所によっては送電を止めなくて
も作業を進めることができる。Therefore, in the case of an overhead power transmission tower, the work can be carried out without disconnecting the electric wires and without stopping the power transmission depending on the replacement place.
【0015】このほか、装置そのものも1脚に掛ってい
る応力に対応するだけの設備となるので、さほど大きく
ならず、複雑にもならない。嵩上げ工法用の装置に比べ
ると極端に小さく、かつ簡素である。従って、地形等に
よる搬入規制を受け難く、500KV級の大型鋼管鉄塔
用のものも困難なく製作できる。また、鉄塔や基礎の補
強等も必要としない。[0015] In addition, since the device itself is a facility only to cope with the stress applied to one leg, it is not so large or complicated. It is extremely small and simple as compared with the device for the raising method. Therefore, it is hard to be restricted by the loading due to the topography and the like, and it can be manufactured without difficulty for a large steel pipe tower of 500 KV class. Also, there is no need to reinforce the tower or foundation.
【0016】[0016]
【実施例】図1に、この発明の一実施例を示す。図に示
すように、主柱材取替装置10は、対向一対のベース金
具11、11と、これ等のベース金具を連結する左右一
対のジャッキアップ支柱12、12と、この支柱の各々
を長手方向に押し引きする油圧シリンダ13、13と、
上下一対のスライド交換装置14、14から成る。FIG. 1 shows an embodiment of the present invention. As shown in the figure, the main column replacement device 10 includes a pair of opposed base fittings 11, 11, a pair of left and right jack-up supports 12, 12 for connecting these base fittings, and each of the supports is longitudinally extended. Hydraulic cylinders 13, 13 for pushing and pulling in the directions;
It consists of a pair of upper and lower slide exchanging devices 14, 14.
【0017】ベース金具11は、図2に示すように、ベ
ース板11aと一体の半割りリング11b、11cをヒ
ンジ部11dを支点に開閉して取替主柱材1の上下の健
全な主柱材2、3の外周に嵌め、ヒンジ部11dと18
0°反対側のクランプボルト11eで半割りリングを締
付けて主柱材に抱きつかせる構造にしている。各半割り
リング11b、11cと主柱材2(又は3)との間に
は、周方向に分割したくさび17を圧入し、さらに、半
割りリングの上下にこれも半割りの押え金具18とスト
ッパ19を取付けてベース金具11の定置安定性を高め
ているが、これ等の要素は必要に応じて設ければよい。As shown in FIG. 2, the base metal fitting 11 is opened and closed with half rings 11b and 11c integral with the base plate 11a with the hinge portion 11d as a fulcrum. Hinged portions 11d and 18
The half ring is tightened with the clamp bolt 11e on the opposite side of 0 ° to hold the main pillar. A wedge 17 divided in the circumferential direction is press-fitted between each half ring 11b, 11c and the main pillar 2 (or 3). Although the stopper 19 is attached to increase the stationary stability of the base fitting 11, these elements may be provided as needed.
【0018】ジャッキアップ支柱12と油圧シリンダ1
3は、図2(b)に示すベース板11a上の鎖線領域に
ボルト止めされる。ジャッキアップ支柱12は、数本の
鋼管をフランジ継手で接続したものであり、適当な位置
の鋼管を長さの異なるものと差し替えることによって取
替主柱材1の長さ変化に対応することができる。なお、
油圧シリンダ13は、ジャッキアップ支柱12の長手方
向途中に組込むこともある。Jack-up support 12 and hydraulic cylinder 1
3 is bolted to a chain line region on the base plate 11a shown in FIG. The jack-up support 12 is formed by connecting several steel pipes with a flange joint, and can cope with a change in the length of the replacement main pillar 1 by replacing a steel pipe at an appropriate position with a steel pipe having a different length. it can. In addition,
The hydraulic cylinder 13 may be incorporated in the jack-up support 12 in the longitudinal direction.
【0019】スライド交換装置14は、ベース金具11
と同様に2者を対向させて上部の主柱材2と下部の主柱
材3に各々固定する。その固定は、図3に示すように、
交換装置の本体部を14aと14bの2者に分割し、ボ
ルトで締結するこれ等の分割部材14a、14bの突き
合わせ部に半割りリング14c、14dを設けてこのリ
ングを健全な主柱材2(又は3)に抱きつかせる方法で
行っている。このスライド交換装置14は、各々が油圧
シリンダ15と、主柱材端のフランジ継手を受けるスラ
イド面14eを有している。一部のスライド面14e
は、新主柱材4の主柱材3上への乗り移りを円滑化する
ために可動板14fに形成してこの板を上下動させるレ
ベル調整器16によりその高さの微調整を可能ならしめ
ている。The slide changing device 14 includes the base fitting 11
Similarly, the two members are fixed to the upper main column member 2 and the lower main column member 3 with facing each other. The fixing is performed as shown in FIG.
The main body of the exchange device is divided into two parts, 14a and 14b, and half-split rings 14c, 14d are provided at the butting portions of these divided members 14a, 14b which are fastened with bolts, and these rings are attached to the sound main column 2 (Or 3) in a way to hug you. The slide changing device 14 has a hydraulic cylinder 15 and a slide surface 14e for receiving a flange joint at the end of the main pillar. Some sliding surfaces 14e
Is formed on a movable plate 14f to facilitate the transfer of the new main column member 4 onto the main column member 3, and the height thereof can be finely adjusted by a level adjuster 16 which moves the plate up and down. I have.
【0020】次に、図示の取替装置の使用法について述
べる。Next, how to use the illustrated replacement device will be described.
【0021】図1に示すように、作業の支障になる位置
の腹材(一点鎖線にて表示)等を外して取替主柱材1の
上下の健全な主柱材2、3間を、ベース金具11、ジャ
ッキアップ支柱12及び油圧シリンダ13で連結し、さ
らに、上下のスライド交換装置14も所定位置に取付け
てこの装置のスライド面14e間に新主柱材4を取替主
柱材1に対して並列に、かつ、下部のフランジ継手の面
位置が揃うようにセットする。このとき、新主柱材4と
取替主柱材1は、双方の主柱材にUボルト等を用いて取
付ける並列押え金具20で相互に連結しておくのが望ま
しい。As shown in FIG. 1, abdominal material (indicated by a dashed line) at a position where the work is obstructed is removed, and the space between the healthy main pillars 2 and 3 above and below the replacement main pillar 1 is removed. The base metal fitting 11, the jack-up support 12 and the hydraulic cylinder 13 are connected, and the upper and lower slide exchanging device 14 is also mounted at a predetermined position, and the new main column 4 is replaced between the sliding surfaces 14e of this device. Are set in parallel with each other and so that the surface positions of the lower flange joint are aligned. At this time, it is desirable that the new main column member 4 and the replacement main column member 1 be connected to each other by a parallel press fitting 20 that is attached to both main column members using a U-bolt or the like.
【0022】以上の下準備を終えたら、取替主柱材1の
上部フランジ継手のボルトによる締結を解く。この後、
左右の油圧シリンダ13、13を同時に操作して押出す
と対のベース金具11、11間に押し開き力が働き、上
部の健全な主柱材2が持ち上げられて取替主柱材1の上
部のフランジ継手間に隙間が生じる。これにより、取替
主柱材に掛っていた応力が無くなるのでこの取替主柱材
1の下部のフランジ継手による締結を解いて(これは応
力を抜く前でも可)上下のスライド交換装置の油圧シリ
ンダ15、15を操作し、交換装置間にセットされてい
る新主柱材4をスライド面14e上を滑らせながらシリ
ンダ15、15で横から取替主柱材1の位置に押込む。
このとき、取替主柱材1も新主柱材4に押されて部材1
4b側のスライド面14e上をスライドし、新主柱材4
と取替主柱材1が入れ替わる。このように、主柱材1、
4を並列にして同時に横スライドさせながら入れ替える
と、フランジ継手間の隙間を大きくせずに済む。また、
作業中は主柱材2、3間に1と4のどちらかの主柱材が
常にあることになり、これ等が、急激な荷重変動等でジ
ャッキアップ支柱12による支持が不充分になったとき
には代わりに荷重を受け止めるため、鉄塔上部の安定支
持も保証される。When the above preparations are completed, the fastening of the upper flange joint of the replacement main pillar 1 by bolts is released. After this,
When the left and right hydraulic cylinders 13, 13 are simultaneously operated and pushed out, a push-open force acts between the pair of base fittings 11, 11, and the upper sound main pillar 2 is lifted, and the upper part of the replacement main pillar 1 is lifted. A gap is created between the flange joints. As a result, the stress applied to the replacement main column member is eliminated, so that the fastening by the lower flange joint of the replacement main column member 1 is released (this is possible even before the stress is released). By operating the cylinders 15, 15, the new main pillar 4 set between the replacement devices is pushed into the position of the replacement main pillar 1 from the side by the cylinders 15, 15 while sliding on the slide surface 14 e.
At this time, the replacement main pillar 1 is also pushed by the new main pillar 4 and
4b, slides on the slide surface 14e to form the new main pillar 4
And the replacement main pillar 1 is replaced. Thus, the main pillar 1,
If the four joints 4 are arranged side by side and replaced while simultaneously sliding horizontally, the gap between the flange joints does not need to be increased. Also,
During the operation, there was always one of the main pillars 1 and 4 between the main pillars 2 and 3, which were insufficiently supported by the jack-up support 12 due to a sudden load change or the like. Occasionally, a load is received instead, so that a stable support at the top of the tower is also guaranteed.
【0023】なお、主柱材1、4を金具20で連結し、
取替主柱材1を油圧シリンダで引抜く装置構成にしても
同様の入れ替えを行うことができるが、交換装置14の
簡素化、小型化面からは図示の押込み方式の方が好まし
い。この押込み方式であれば、シリンダ15のロッドを
新主柱材4に単に押し当てるだけでよいし、シリンダ1
5も、主柱材1、4の中心間距離よりストロークの短い
もので間に合う。一旦押出したロッドを引込んでロッド
先端と新主柱材4との間の隙間をスペーサで埋め再度押
出す作業を繰り返えせば短ストロークのシリンダでスト
ローク以上の押込みを行うことができる。In addition, the main pillars 1 and 4 are connected by the metal fitting 20,
The same replacement can be performed even when the replacement main pillar 1 is pulled out by a hydraulic cylinder, but from the viewpoint of simplification and miniaturization of the replacement device 14, the push-in method shown is more preferable. With this pushing method, the rod of the cylinder 15 may be simply pressed against the new main pillar 4 and the cylinder 1
5 also has a shorter stroke than the center-to-center distance between the main pillars 1 and 4 and can be used in time. Once the extruded rod is pulled in, the gap between the rod tip and the new main pillar 4 is filled with a spacer, and the operation of extruding again is repeated, so that the cylinder can be pushed more than the stroke by a short stroke cylinder.
【0024】このほか、図示の装置は、力のバランスと
取扱い性を考慮してジャッキアップ支柱12を2本とし
たが、強度のある支柱であれば、その数は1本でもよ
い。In addition, the illustrated apparatus has two jack-up struts 12 in consideration of the balance of force and handleability, but the number of the struts may be one as long as the strut is strong.
【0025】[0025]
【発明の効果】以上述べたように、この発明の主柱材取
替装置は、上下の健全な主柱材間を連結するジャッキア
ップ支柱で荷重を肩代わりして受け、この状態でスライ
ド交換装置により新主柱材と取替主柱材を横スライドさ
せて両者を入れ替えるようにしたので、主柱材端のフラ
ンジ継手間に生じさせる取替用の隙間が極く僅かで済
み、周囲の部材に無用の応力を生じさせないため作業時
の応力予測が容易になる。また、取替中の主柱材による
鉄塔上部の支持のバックアップ効果も得られ、従って、
送電鉄塔の場合、架設されている電線を取外さなくて
も、また、取替場所によっては停電なしでも、さらに、
線路に角度のある鉄塔でも取替作業を安全に実施するこ
とが可能である。As described above, the main column replacement device of the present invention receives the load by shouldering the jack-up support connecting the upper and lower sound main columns, and in this state, the slide replacement device. As a result, the new main column material and the replacement main column material are slid laterally so that they are exchanged, so the replacement gap created between the flange joints at the ends of the main column material is extremely small, and the surrounding members Since unnecessary stress is not generated, stress prediction during work is facilitated. In addition, the backing effect of the support of the upper part of the tower by the main pillar material being replaced can be obtained,
In the case of power transmission towers, even if the installed electric wires are not removed, and depending on the replacement place, there is no power outage,
It is possible to safely perform the replacement work even on a tower with an angled track.
【0026】また、鉄塔や基礎の補強も不要である。Further, it is not necessary to reinforce the tower and the foundation.
【0027】さらに、装置自体が鉄塔の1脚にのみ対応
する構造であり、簡素、小型、軽量のもので間に合うた
め、設計上の規制や現場への搬入規制なども取除かれ、
取扱いに要する労力や製造コストも少なくて済む。Further, since the apparatus itself has a structure corresponding to only one leg of a steel tower, and is simple, small, and light in time, restrictions on design and restrictions on loading into the site are removed.
The labor required for handling and the manufacturing cost are reduced.
【0028】従って、この発明の装置を用いれば作業の
省人、省力化、時間短縮、コスト削減が図れ、実施規制
も殆どなくなる。Therefore, if the apparatus of the present invention is used, labor and labor of the work can be saved, time can be reduced, cost can be reduced, and the enforcement regulations can be almost eliminated.
【0029】なお、作業に要する人員は、電線を外す在
来工法の場合、16〜20人/日、嵩上げ装置を用いた
工法の場合12〜16人/日程度になるが、この発明の
装置を用いた工法では6人/日で対応できる。これから
判るように、この発明の装置を用いての主柱材の取替え
は、送電鉄塔に限定されるものではないが、送電鉄塔を
対象とした場合に特に、作業の省人、省力化、コスト削
減の効果が顕著になる。The number of personnel required for the work is 16 to 20 persons / day in the case of the conventional method of removing the electric wire, and about 12 to 16 persons / day in the case of the method using the raising device. Can be handled by 6 people / day. As can be seen, the replacement of the main pillars using the apparatus of the present invention is not limited to the transmission tower, but particularly when the transmission tower is targeted, labor saving, labor saving, and cost reduction are required. The effect of reduction becomes remarkable.
【図1】この発明の取替装置の一例を簡略化し、使用状
態にして示す斜視図FIG. 1 is a perspective view showing an example of a replacement device of the present invention in a simplified and used state.
【図2】(a)はベース金具の正面図 (b)はベース金具の平面図2A is a front view of a base metal fitting, and FIG. 2B is a plan view of the base metal fitting.
【図3】(a)はスライド交換装置の正面図 (b)はスライド交換装置の平面図 (c)は(b)図のX−X線部の拡大断面図 (d)は(a)図のY−Y線部の拡大断面図3A is a front view of the slide exchanging device, FIG. 3B is a plan view of the slide exchanging device, FIG. 3C is an enlarged cross-sectional view taken along line XX of FIG. Enlarged sectional view of the YY line portion of FIG.
【図4】(a)は在来の取替工法の一例を示す側面視線
図 (b)は同上の平面視線図4A is a side view showing an example of a conventional replacement method, and FIG. 4B is a plan view showing the same.
1 取替主柱材 2 上部の健全な主柱材 3 下部の健全な主柱材 4 新主柱材 5、6 支線 10 主柱材取替装置 11 ベース金具 12 ジャッキアップ支柱 13、15 油圧シリンダ 14 スライド交換装置 16 レベル調整器 17 くさび 18 押え金具 19 ストッパ 20 並列押え金具 DESCRIPTION OF SYMBOLS 1 Replacement main pillar material 2 Upper healthy main pillar material 3 Lower healthy main pillar material 4 New main pillar material 5 and 6 Branch lines 10 Main pillar material replacement device 11 Base fitting 12 Jack up pillar 13 and 15 Hydraulic cylinder 14 Slide exchange device 16 Level adjuster 17 Wedge 18 Presser bracket 19 Stopper 20 Parallel presser bracket
───────────────────────────────────────────────────── フロントページの続き (72)発明者 長谷川 徹 大阪市北区中之島3丁目3番22号 関西 電力株式会社内 (72)発明者 浅野 順一 尼崎市若王寺3丁目11番20号 関西電力 株式会社総合技術研究所内 (56)参考文献 特開 平8−163729(JP,A) 実開 昭53−38698(JP,U) (58)調査した分野(Int.Cl.7,DB名) H02G 1/02 E04H 12/10 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Toru Hasegawa 3-3-22 Nakanoshima, Kita-ku, Osaka-shi Inside Kansai Electric Power Co., Inc. (72) Inventor Junichi Asano 3-11-20 Wakaoji, Amagasaki-shi Kansai Electric Power Stock (56) References JP-A-8-163729 (JP, A) JP-A-53-38698 (JP, U) (58) Fields investigated (Int. Cl. 7 , DB name) H02G 1 / 02 E04H 12/10
Claims (1)
材に固定する対向一対のベース金具と、この対のベース
金具間に取付けるジャッキアップ支柱及びこの支柱を長
手方向に押し引きするシリンダと、上下の健全な主柱材
に固定して取替主柱材の上下の各接続部に取付ける対向
一対のスライド交換装置を具備し、この対のスライド交
換装置のスライド面間に新主柱材を取替主柱材と並列に
セットし、前記シリンダを押出して取替主柱材に掛って
いる応力を除いた後、新主柱材をスライド交換装置で横
滑りさせて取替主柱材と入れ替える鋼管鉄塔の主柱材取
替装置。1. A pair of opposed base fittings fixed to sound main pillars located above and below a replacement main pillar, a jack-up support attached between the pair of base fittings, and the support pushed and pulled in the longitudinal direction. And a pair of opposed slide changers fixed to the upper and lower sound main pillars and attached to the upper and lower connections of the replacement main pillar, and a new slide changer is provided between the slide surfaces of the pair of slide changers. After setting the main column material in parallel with the replacement main column material, extruding the cylinder to remove the stress on the replacement main column material, slide the new main column material with the slide exchange device Main column replacement equipment for steel pipe towers to be replaced with pillars.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP33718092A JP3167203B2 (en) | 1992-12-17 | 1992-12-17 | Main column replacement equipment for steel pipe steel tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP33718092A JP3167203B2 (en) | 1992-12-17 | 1992-12-17 | Main column replacement equipment for steel pipe steel tower |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH06189421A JPH06189421A (en) | 1994-07-08 |
JP3167203B2 true JP3167203B2 (en) | 2001-05-21 |
Family
ID=18306205
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP33718092A Expired - Fee Related JP3167203B2 (en) | 1992-12-17 | 1992-12-17 | Main column replacement equipment for steel pipe steel tower |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3167203B2 (en) |
Families Citing this family (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6143859A (en) * | 1999-08-09 | 2000-11-07 | General Electric Company | Copolycarbonate preparation by solid state polymerization |
US6333394B1 (en) | 1999-08-09 | 2001-12-25 | General Electric Company | Copolycarbonate preparation by solid state polymerization |
JP4588542B2 (en) * | 2005-06-03 | 2010-12-01 | 東京電力株式会社 | Member replacement method for truss structure |
JP4746023B2 (en) * | 2007-11-12 | 2011-08-10 | 三菱重工業株式会社 | Seismic retrofit method for steel structures and seismic steel structures |
JP5064247B2 (en) * | 2008-01-17 | 2012-10-31 | 株式会社Ihiインフラシステム | Method and structure for reinforcing bridge |
JP6004373B2 (en) * | 2012-12-07 | 2016-10-05 | 株式会社デンロコーポレーション | Auxiliary device for investigation of inner surface of main pillar material and investigation method using auxiliary device |
CN103362344B (en) * | 2013-07-18 | 2015-04-22 | 国家电网公司 | Device for correcting angle irons of iron towers in electric transmission lines |
CN106958380B (en) * | 2016-01-12 | 2020-12-11 | 浙江宁远塔桅制造有限公司 | Method for replacing main material of non-single-tube communication iron tower |
JP6632157B2 (en) * | 2017-09-21 | 2020-01-22 | 株式会社Ihiインフラシステム | Replacement method of truss structure members |
CN107769074A (en) * | 2017-11-01 | 2018-03-06 | 云南电网有限责任公司曲靖供电局 | Livewire work segmentation brace type roofbolt insulated platform |
JP7240959B2 (en) * | 2019-06-06 | 2023-03-16 | 大成建設株式会社 | Hanging jig and steel tower dismantling method |
-
1992
- 1992-12-17 JP JP33718092A patent/JP3167203B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH06189421A (en) | 1994-07-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3167203B2 (en) | Main column replacement equipment for steel pipe steel tower | |
US20220259014A1 (en) | Tank car lifting apparatus | |
CA2354292C (en) | Method and apparatus for providing lateral support to a post | |
US7114690B2 (en) | Universal mast support frame and method for mounting masts | |
JP5056659B2 (en) | Utility pole rebuilding tool and utility pole rebuilding method | |
CN211088924U (en) | High-voltage isolating switch overhauling operation platform | |
CN109610800A (en) | A kind of architectural engineering movable altitude faces side safety work device and application method | |
JPH08163729A (en) | Main pillar member replacement device for steel pipe tower | |
JP3630536B2 (en) | Device for temporarily increasing the load capacity of a crane girder | |
CN108821127A (en) | The devices and methods therefor of disassembly lifting open type TBM in a kind of hole | |
CN110565535B (en) | Suspension bridge space main cable linear adjusting device and adjusting method | |
CN209652976U (en) | Fashioned iron Force transmission parts | |
JP3764951B2 (en) | Pier suspension system | |
CN207513137U (en) | Building engineering construction builder's jack | |
CN218147821U (en) | Telescopic general operating platform in cable-stayed bridge cable tower | |
JP7533956B2 (en) | Temporary reinforcement member for replacing steel tower web members and web member replacement method | |
RU2114046C1 (en) | Rail support | |
CN220058769U (en) | Unit type hanging construction operation platform | |
CN220013409U (en) | Synchronous protection platform for temporary stay bars and tower beams of cable-stayed bridge tower | |
CN219009661U (en) | Hoisting tool with adjustable be used for high-voltage motor | |
CN110984172B (en) | Horizontal steel supporting mechanism for foundation pit supporting and use method thereof | |
CN218508245U (en) | Auxiliary device for mounting railway box girder support | |
JP2850300B2 (en) | Link type frame for push-up method | |
CN211897873U (en) | Operating platform device for bridge pipeline installation | |
US20240309670A1 (en) | Utility pole lifting apparatus and method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090309 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090309 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100309 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100309 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110309 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110309 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120309 Year of fee payment: 11 |
|
LAPS | Cancellation because of no payment of annual fees |