JP2506398B2 - Construction method of cast-in-place concrete pile - Google Patents
Construction method of cast-in-place concrete pileInfo
- Publication number
- JP2506398B2 JP2506398B2 JP430088A JP430088A JP2506398B2 JP 2506398 B2 JP2506398 B2 JP 2506398B2 JP 430088 A JP430088 A JP 430088A JP 430088 A JP430088 A JP 430088A JP 2506398 B2 JP2506398 B2 JP 2506398B2
- Authority
- JP
- Japan
- Prior art keywords
- pipe
- concrete
- pile
- pile hole
- cast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Piles And Underground Anchors (AREA)
Description
【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、地盤に杭孔を、その中に安定液を注入しな
がら掘削形成し、前記杭孔の内部に鉄筋カゴを入れ、前
記杭孔内にコンクリートを打設する場所打ちコンクリー
ト杭の構築方法に関する。DETAILED DESCRIPTION OF THE INVENTION [Industrial field of application] The present invention is to form a pile hole in the ground by excavation while pouring a stabilizing solution into the pile hole, and put a reinforcing bar basket inside the pile hole to form the pile. The present invention relates to a method for constructing a cast-in-place concrete pile in which concrete is placed in a hole.
従来、第3図(イ)に示すように、地盤(2)に杭孔
(3)を掘削形成すると共に、孔壁安定化のためにベン
トナイトスラリー等の安定液(4)を入れ、安定液
(4)に浸漬させた状態で鉄筋カゴ(5)を杭孔(3)
の内部に入れ、その後で杭孔(3)の全体にコンクリー
ト(11)を打設し、第3図(ロ)の全体に示すように、
円柱状の場所打ちコンクリート杭を構築していた。Conventionally, as shown in FIG. 3 (a), a pile hole (3) is excavated and formed in the ground (2), and a stabilizing solution (4) such as bentonite slurry is added to stabilize the hole wall. Reinforcing bar basket (5) is immersed in (4) and pile hole (3)
Then, concrete (11) is poured into the whole pile hole (3), as shown in the whole Fig. 3 (b).
It was building a columnar cast-in-place concrete pile.
しかし、杭の支持力を強大にするために周面及び底面
の面積を大きくすると、杭孔(3)の容積が極めて大き
くなり、コンクリート(11)の打設量が膨大になってコ
スト高になる欠点があった。However, if the area of the peripheral surface and the bottom surface is increased in order to increase the bearing capacity of the pile, the volume of the pile hole (3) becomes extremely large, and the amount of concrete (11) to be placed becomes enormous, resulting in high cost. There was a drawback.
本考案の目的は、周面及び底面の面積を大きくして強
大な支持力が得られる割には、コンクリートの必要量を
大巾に減少できるようにし、しかも、そのことによって
工事が面倒になったり、杭強度が大巾に低下するという
不都合な事態を派生しないように工夫する点にある。The purpose of the present invention is to make it possible to greatly reduce the required amount of concrete in spite of enlarging the area of the peripheral surface and the bottom surface to obtain a strong supporting force, and moreover, the construction becomes troublesome. In addition, there is a point to devise so as not to cause an inconvenient situation in which the strength of the pile is significantly reduced.
本発明の特徴手段は、両端が開口したパイプを安定液
内蔵の杭孔内に、鉄筋カゴの内部に位置する状態で設置
し、前記杭孔内に前記パイプの下端よりも上方までコン
クリートを打設して、そのコンクリートにより前記パイ
プの下端を閉塞し、その後、前記パイプの外側にコンク
リートを打設すると共に、前記パイプの内部に充填物を
投入することにあり、その作用効果は次の通りである。The characteristic means of the present invention is to install a pipe with both ends open in a pile hole containing a stable liquid in a state of being positioned inside a reinforced basket, and to pour concrete into the pile hole above the lower end of the pipe. It is to block the lower end of the pipe with the concrete, and then to pour the concrete on the outside of the pipe and to put the filler inside the pipe, and the effect is as follows. Is.
つまり、パイプを杭孔内に設置して、パイプの外側で
鉄筋カゴを設置した杭孔部分だけにコンクリートを打設
するから、杭孔を大径にして杭の周面と底面を大面積に
しても、パイプの径を杭の必要強度に見合って適当に設
定することで、コンクリートの必要量を大巾に減少で
き、コストダウンを十分に達成できる。In other words, the pipe is installed inside the pile hole, and the concrete is placed only on the outside of the pipe where the cage is installed.Therefore, the diameter of the pile hole should be large and the circumference and bottom of the pile should be large. However, by appropriately setting the diameter of the pipe in accordance with the required strength of the pile, the required amount of concrete can be greatly reduced and the cost can be sufficiently reduced.
ちなみに、コンクリート打設時にパイプ内に下端側か
らコンクリートが流入しないようにすると、例えばパイ
プの下端を蓋することも考えられるが、安定液内蔵の杭
孔内に浮力に抗してパイプを沈降させる工事に多大の経
費、労力、工期を必要とする問題が派生して、実質的に
はコストダウンを十分に達成できなくなる。By the way, if concrete is prevented from flowing into the pipe from the lower end when pouring the concrete, it is possible to cover the lower end of the pipe, for example, but the pipe will settle against the buoyancy in the pile holes containing the stabilizing liquid. The problem that a large amount of expense, labor, and construction period are required for construction is generated, and it is practically impossible to achieve sufficient cost reduction.
しかし、本発明によれば、両端が開口したパイプを安
定液内蔵の杭孔内に設置した後、杭孔内にパイプの下端
より上方までコンクリートを打設し、そのコンクリート
の高粘性でパイプの下端を閉じ、その後でパイプの外側
にコンクリートを打設して、パイプ内に大量のコンクリ
ートが流入しないようにするから、安定液による浮力の
悪影響を受けずに、パイプ設置を容易迅速に実行でき
る。However, according to the present invention, after installing a pipe with both ends open in a pile hole containing a stable liquid, concrete is poured into the pile hole to a position above the lower end of the pipe, and the high viscosity of the concrete causes the pipe to Closing the lower end and then placing concrete on the outside of the pipe to prevent a large amount of concrete from flowing into the pipe, so the pipe can be installed easily and quickly without being adversely affected by the buoyancy of the stabilizing liquid. .
さらに、パイプの内部を空にしたままで杭に十分な強
度を備えさせようとすると、パイプを肉厚の大きい強度
大なるものにするか又は小径のものにしなければなら
ず、コストダウン達成に障害があり、逆に、コストダウ
ン達成を重視すると強度面での信頼性に悪影響を及ぼ
す。Furthermore, if the pile is to be provided with sufficient strength while the inside of the pipe is emptied, the pipe must have a large wall thickness and strength or a small diameter to achieve cost reduction. There are obstacles, and conversely, if importance is placed on achieving cost reduction, reliability in terms of strength will be adversely affected.
しかし、本発明によれば、例えば残土、砂、砕石など
の充填物をパイプ内に投入するから、パイプを比較的低
強度で大径にしてコストダウンを十分に達成すると共
に、十分な杭強度を信頼性の高い状態で得られる。However, according to the present invention, for example, a filling material such as residual soil, sand, and crushed stone is put into the pipe, so that the pipe has a relatively low strength and a large diameter to sufficiently achieve cost reduction, and sufficient pile strength. Can be obtained in a reliable condition.
その結果、杭の支持力と強度を十分に大きくしなが
ら、かつ、工事が面倒にならないようにしながら、杭構
築に要する経費を大巾に低減でき、経済性において一段
と有利な場所打ちコンクリート杭の構築方法を完成でき
た。As a result, the cost required for constructing the pile can be greatly reduced while the bearing capacity and strength of the pile are sufficiently increased, and the construction work is not troublesome, and the cast-in-place concrete pile is more economically advantageous. The construction method was completed.
次に実施例を示す。 Next, examples will be shown.
第1図(イ)に示すように、アースドリル(1)によ
り地盤(2)に杭孔(3)を全長にわたってほぼ等径に
なる状態でかつ断面がほぼ円形になる状態で掘削形成す
ると共に、杭孔(3)内にベントナイトスラリーなどの
安定液(4)を注入して、孔壁の崩壊を防止する。As shown in FIG. 1 (a), a pile hole (3) is excavated and formed in the ground (2) with a ground drill (1) in a state where the pile hole (3) has a substantially equal diameter over a whole length and a cross section has a substantially circular shape. A stabilizing solution (4) such as bentonite slurry is injected into the pile hole (3) to prevent the hole wall from collapsing.
第1図(ロ)に示すように、ほぼ円筒形の鉄筋カゴ
(5)を杭孔(3)内に設置すると共に、両端が開口し
たスパイラル鋼製、樹脂製などのパイプ(6)を杭孔
(3)内に、鉄筋カゴ(5)の内部にほぼ同芯状に位置
する状態で設置する。As shown in Fig. 1 (b), a substantially cylindrical reinforcing bar basket (5) is installed in the pile hole (3), and a pipe (6) made of spiral steel or resin with both ends opened is piled. It is installed in the hole (3) so as to be located substantially concentrically inside the reinforcing bar basket (5).
鉄筋カゴ(5)とパイプ(6)を杭孔(3)内に入れ
るタイミングは同時でも別々でもよい。The reinforcing bar basket (5) and the pipe (6) may be inserted into the pile hole (3) at the same time or separately.
第1図(ハ)に示すように、鉄筋カゴ(5)とパイプ
(6)の間にトレミー管(7)を挿入し、杭孔(3)内
にパイプ(6)の下端より上方までトレミー管(7)で
コンクリート(8)を打設し、そのコンクリート(8)
の固化でパイプ(6)の下端を閉塞する。As shown in FIG. 1 (c), the tremie pipe (7) is inserted between the reinforcing bar basket (5) and the pipe (6), and the tremie is inserted into the pile hole (3) above the lower end of the pipe (6). Placing concrete (8) with pipe (7), and then concrete (8)
The lower end of the pipe (6) is closed by solidification of.
第1図(ニ)に示すように、トレミー管(7)でパイ
プ(6)の外側にコンクリート(9)を打設すると共
に、残土、砂、砕石などの充填物(10)をパイプ(6)
の内部に投入し、杭孔(3)から排出される安定液
(4)を回収し、そして、第1図(ホ)に示すように、
杭孔(3)の上端までコンクリート(9)を打設すると
共に、パイプ(6)の上端まで充填物(10)を投入し、
その後、コンクリート(9)を固化させて、第2図に断
面構造を示す場所打ちコンクリート杭を構築する。As shown in FIG. 1D, concrete (9) is placed on the outside of the pipe (6) with the tremie pipe (7), and the filler (10) such as residual soil, sand and crushed stone is piped (6). )
The stabilizing liquid (4) discharged from the pile hole (3) is collected inside the pile, and as shown in FIG. 1 (e),
Concrete (9) is poured to the upper end of the pile hole (3), and the filler (10) is charged to the upper end of the pipe (6),
Then, the concrete (9) is solidified to construct a cast-in-place concrete pile whose sectional structure is shown in FIG.
コンクリート(9)の打設と充填物(10)の投入のタ
イミングは同時でも別々でもよい。The timing of pouring concrete (9) and the injection of filler (10) may be the same or different.
次に別実施例を示す。 Next, another embodiment will be described.
杭孔(3)の形状は適宜変更自在であり、また、その掘
削工法は適当に選定できる。The shape of the pile hole (3) can be changed as appropriate, and the excavation method can be appropriately selected.
安定液(4)の種類、注入タイミングは適当に選定で
きる。The kind of the stabilizing solution (4) and the injection timing can be appropriately selected.
鉄筋カゴ(5)の構造、形状、寸法、設置数は選択自
在であり、複数個を同芯状に設けてもよい。The structure, shape, size, and number of the reinforcing bar baskets (5) can be freely selected, and a plurality of reinforcing bar baskets (5) may be concentrically provided.
パイプ(6)の材質、形状、寸法、設置数は選択自在
であり、複数本を並設してもよい。The material, shape, size, and number of pipes (6) can be freely selected, and a plurality of pipes (6) may be arranged in parallel.
コンクリート(8),(9)の打設法は適当に変更で
き、トレミー管(7)を鉄筋カゴ(5)の外側に挿入し
たり、パイプ(6)の下端閉塞のためのコンクリート
(8)打設に際してはトレミー管(7)をパイプ(6)
内に挿入してもよい。The method of placing concrete (8) and (9) can be changed as appropriate, and the tremie pipe (7) is inserted into the outside of the reinforcing steel basket (5) or the concrete (8) is placed to close the lower end of the pipe (6). When installing the tremie pipe (7) pipe (6)
It may be inserted in.
パイプ(6)の下端を閉塞するコンクリート(8)の
上に載せる仕切板をパイプ(6)内に入れ、その仕切板
の上に充填物(10)を投入してもよい。A partition plate to be placed on the concrete (8) that closes the lower end of the pipe (6) may be put in the pipe (6), and the filler (10) may be put on the partition plate.
第1図及び第2図は本発明の実施例を示し、第1図
(イ)ないし(ホ)は施工手順の説明図、第2図は杭の
横断面図である。第3図(イ)ないし(ロ)は従来法の
施工手順説明図である。 (2)……地盤、(3)……杭孔、(4)……安定液、
(5)……鉄筋カゴ、(6)……パイプ、(8),
(9)……コンクリート、(10)……充填物。FIGS. 1 and 2 show an embodiment of the present invention, FIGS. 1 (a) to (e) are explanatory views of the construction procedure, and FIG. 2 is a transverse sectional view of a pile. FIGS. 3 (a) to 3 (b) are explanatory views of the construction procedure of the conventional method. (2) …… Soil, (3) …… Pile holes, (4) …… Stabilizer,
(5) …… Reinforcing bar basket, (6) …… Pipe, (8),
(9) …… Concrete, (10) …… Filler.
Claims (1)
液(4)を注入しながら掘削形成し、前記杭孔(3)の
内部に鉄筋カゴ(5)を入れ、前記杭孔(3)内にコン
クリートを打設する場所打ちコンクリート杭の構築方法
であって、両端が開口したパイプ(6)を前記安定液
(4)内蔵の杭孔(3)内に、前記鉄筋カゴ(5)の内
部に位置する状態で設置し、前記杭孔(3)内に前記パ
イプ(6)の下端よりも上方までコンクリート(8)を
打設して、そのコンクリート(8)により前記パイプ
(6)の下端を閉塞し、その後、前記パイプ(6)の外
側にコンクリート(9)を打設すると共に、前記パイプ
(6)の内部に充填物(10)を投入する場所打ちコンク
リート杭の構築方法。1. A pile hole (3) is formed in the ground (2) by pouring a stabilizing liquid (4) into the pile hole (3), and a reinforcing bar basket (5) is put inside the pile hole (3). A method for constructing a cast-in-place concrete pile in which concrete is placed in the pile hole (3), wherein a pipe (6) having open ends is provided in the pile hole (3) containing the stabilizing solution (4). It is installed in a state where it is located inside the reinforced steel basket (5), and concrete (8) is placed in the pile hole (3) above the lower end of the pipe (6) and the concrete (8) is used. A cast-in-place concrete in which the lower end of the pipe (6) is closed, then concrete (9) is placed on the outside of the pipe (6), and a filler (10) is put inside the pipe (6). How to build a pile.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP430088A JP2506398B2 (en) | 1988-01-11 | 1988-01-11 | Construction method of cast-in-place concrete pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP430088A JP2506398B2 (en) | 1988-01-11 | 1988-01-11 | Construction method of cast-in-place concrete pile |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH01182410A JPH01182410A (en) | 1989-07-20 |
JP2506398B2 true JP2506398B2 (en) | 1996-06-12 |
Family
ID=11580663
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP430088A Expired - Lifetime JP2506398B2 (en) | 1988-01-11 | 1988-01-11 | Construction method of cast-in-place concrete pile |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2506398B2 (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0751776B2 (en) * | 1990-05-21 | 1995-06-05 | 大亜ソイル株式会社 | How to build a pile |
JPH073782A (en) * | 1993-06-18 | 1995-01-06 | Kajima Corp | Method for constructing cast-in-place hollow concrete pile, and cast-in-place concrete pile |
JP4530391B2 (en) * | 2000-12-26 | 2010-08-25 | 株式会社クボタ | Method of treating construction mud soil and retaining wall filled with construction mud soil |
JP5503823B2 (en) * | 2009-08-07 | 2014-05-28 | 大成建設株式会社 | Cast-in-place pile construction method and cast-in-place pile |
CN113685190B (en) * | 2021-08-28 | 2024-02-09 | 华东交通大学 | Reinforcing system for shield to penetrate shallow soft clay and construction method |
-
1988
- 1988-01-11 JP JP430088A patent/JP2506398B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH01182410A (en) | 1989-07-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4571124A (en) | Method of forming cast-in-place concrete pile | |
US20080019779A1 (en) | Steel-Cased Concrete Piers | |
JP2506398B2 (en) | Construction method of cast-in-place concrete pile | |
JPS5854210B2 (en) | Chichiyurenzokuhekisekouhou | |
JPH0598636A (en) | Cylindrical shell foundation and construction method thereof | |
JP3131688B2 (en) | Construction method of shaft | |
KR0148168B1 (en) | Woorking method of underground foundation wall | |
JP2001295270A (en) | Pile and burying method thereof | |
JP2002054137A (en) | Method for constructing cast-in-plate concrete pile | |
JP2001090060A (en) | Driving method for pile and constructing method for cut- off wall using the method | |
JPS58127822A (en) | Liquefaction preventive structure of foundation ground | |
JP3935259B2 (en) | On-site concrete pile construction method | |
JPS6042114Y2 (en) | embedded steel pipe pile | |
JPS6149452B2 (en) | ||
JPH01102125A (en) | Placement of concrete pile at site | |
JPH03122317A (en) | Concrete pile for hollow place and driving method thereof | |
JPH073781A (en) | Method for constructing foundation footing on cast-in-place concrete pile head | |
JPH042134B2 (en) | ||
JP3103286B2 (en) | Construction method of cast-in-place concrete pile | |
JP4521848B2 (en) | Earth removal backfill hole forming device | |
JP2564609B2 (en) | Reinforcing cage for cast-in-place concrete pile and construction method using it | |
JP2006138091A (en) | Construction method for burying tank and the like | |
KR100408132B1 (en) | Method of construction for the lower part reinforcement of well open cassion in hard ground. | |
KR200167828Y1 (en) | An installation for pre-venting material spereration in case of forming a concrete strut | |
JP2002097647A (en) | Pile head recessed part formation method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
EXPY | Cancellation because of completion of term |