[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

JP2015021322A - Tunnel construction method and tunnel structure - Google Patents

Tunnel construction method and tunnel structure Download PDF

Info

Publication number
JP2015021322A
JP2015021322A JP2013151465A JP2013151465A JP2015021322A JP 2015021322 A JP2015021322 A JP 2015021322A JP 2013151465 A JP2013151465 A JP 2013151465A JP 2013151465 A JP2013151465 A JP 2013151465A JP 2015021322 A JP2015021322 A JP 2015021322A
Authority
JP
Japan
Prior art keywords
tunnel
constructed
support
backfilling
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2013151465A
Other languages
Japanese (ja)
Inventor
米三郎 島根
Yonezaburo Shimane
米三郎 島根
敏郎 浅川
Toshiro Asakawa
敏郎 浅川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tekken Corp
Original Assignee
Tekken Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tekken Corp filed Critical Tekken Corp
Priority to JP2013151465A priority Critical patent/JP2015021322A/en
Publication of JP2015021322A publication Critical patent/JP2015021322A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a tunnel construction method capable of reducing rigidity of a tunnel structure required for the amount of loaded earth for backfilling, and a tunnel structure.SOLUTION: On a construction surface GL, an outside lining frame 30 is installed outside a plurality of installed supports 20 that are arranged at predetermined intervals along an axial direction T of a tunnel, and the supports 20 and an upper part of the outside lining frame 30 are constructed by being backfilled with (leanly-mixed) lean-mix concrete 120 with light cement loading.

Description

例えば、トンネル構築箇所に設置したトンネル構造物の上部を埋め戻してトンネルを構築するトンネルの構築方法及びトンネル構造物に関する。   For example, the present invention relates to a tunnel construction method and a tunnel structure in which an upper part of a tunnel structure installed at a tunnel construction site is backfilled to construct a tunnel.

従来から、トンネルは、トンネル構築箇所の環境や諸条件によって、さまざまな施工方法や構造が提案され、安全かつコストパフォーマンスの高い構造や施工方法が採用されている。
特許文献1では、トンネル構造物の天井部分を構築する箇所をあらかじめ掘削し、周辺地山で支持できるように、トンネル構造物の天井部分を構築する方法が、トンネル構築方法の一例として提案されている。例えば、トンネル構造物の底部まで掘削してからトンネル構造物を構築して埋戻し土砂で埋め戻す工法の場合、施工環境によっては周辺地山に対する土留めが必要となり、施工日数や施工費用が嵩むこととなるため、このような施工方法に比べて、安全かつ安価で構築することができるとされている。
Conventionally, various construction methods and structures have been proposed for tunnels according to the environment and conditions of the tunnel construction site, and safe and cost-effective structures and construction methods have been adopted.
In Patent Document 1, a method for constructing a ceiling part of a tunnel structure so as to be excavated in advance and supported by surrounding ground is proposed as an example of a tunnel construction method. Yes. For example, in the case of a construction method in which the tunnel structure is excavated to the bottom of the tunnel structure and then backfilled with backfill earth and sand, depending on the construction environment, earth retaining to the surrounding ground is required, which increases construction days and construction costs. Therefore, it is said that it can be constructed safely and inexpensively compared to such a construction method.

しかしながら、特許文献1におけるトンネル構築方法では、トンネル構造物の天井部分の上部を埋戻し土砂で埋め戻してから、天井部分の下方を掘削してトンネル構造物を構築するため、天井部分に上載される埋戻し土による土圧を天井部分のみで支持する必要があり、そのため天井部分に高い剛性が必要となり、天井部分の厚みが厚くなるといった問題があった。   However, in the tunnel construction method in Patent Document 1, since the upper part of the ceiling part of the tunnel structure is backfilled with backfill earth and sand, the tunnel structure is constructed by excavating the lower part of the ceiling part. It is necessary to support the earth pressure by the backfilled soil only by the ceiling portion, and therefore, the ceiling portion needs to have high rigidity, and there is a problem that the thickness of the ceiling portion is increased.

そもそも、特許文献1に示すようなトンネル構造物を構築してから埋戻し土砂でその上部を埋め戻す施工方法の場合、埋戻し土砂で埋め戻す埋戻し土量、すなわち埋戻し高さ分の全土圧がトンネル構造物に作用するため、施工環境によっては、例えば、山岳トンネルなどの地山を掘削して構築するトンネル構造物(以下において掘削トンネルという)において、埋戻し高さと同程度の土被りを有する掘削トンネルに比べて、例えば、吹付コンクリートの吹付厚や部材厚が厚い高剛性の部材を使用したトンネル構造、つまり高い剛性を要するトンネル構造物となるおそれがあった。   In the first place, in the case of a construction method in which a tunnel structure as shown in Patent Document 1 is constructed and then the upper part is backfilled with backfill earth and sand, the amount of backfill soil to be backfilled with backfill earth and sand, that is, the whole soil for the backfill height. Since the pressure acts on the tunnel structure, depending on the construction environment, for example, in a tunnel structure constructed by excavating a natural mountain such as a mountain tunnel (hereinafter referred to as an excavation tunnel), the earth covering is about the same as the backfill height. Compared to the excavation tunnel having the above, for example, there is a possibility that a tunnel structure using a high-rigidity member having a thick sprayed concrete thickness or member thickness, that is, a tunnel structure requiring high rigidity.

特開平11−323974号公報JP 11-323974 A

そこで、この発明は、上載される埋戻し土量に対して要するトンネル構造物の剛性を低減することができるトンネルの構築方法及びトンネル構造物を提供することを目的とする。   Therefore, an object of the present invention is to provide a tunnel construction method and a tunnel structure that can reduce the rigidity of the tunnel structure required for the amount of backfilled soil to be mounted.

この発明は、トンネル構築箇所に設置したトンネル構造物の上部を埋め戻してトンネルを構築するトンネルの構築方法及びトンネル構造物であって、前記トンネル構造物の少なくとも上半部分を構築してから、該上半部分の上部を、固化材が貧配合で配合された貧配合埋戻し材で埋戻して構築することを特徴とする。   The present invention is a tunnel construction method and a tunnel structure in which an upper part of a tunnel structure installed at a tunnel construction site is backfilled to construct a tunnel, and after constructing at least an upper half part of the tunnel structure, The upper part of the upper half portion is constructed by backfilling with a poorly mixed backfilling material in which a solidifying material is blended with a poor blending.

上述のトンネル構造物は、場所打ちコンクリートなどの覆工材で覆工したトンネル構造物、材質を問わないが、セグメントやコンクリートBOXなどの閉断面構造物を組み付けたトンネル構造物などを含む概念であり、アーチ状(馬蹄形)、円形、楕円形、矩形など様々な断面のトンネル構造物を含み、さらには多連トンネルであってもよい。   The above-mentioned tunnel structure is a concept including a tunnel structure covered with a lining material such as cast-in-place concrete, a tunnel structure in which a closed cross-section structure such as a segment or a concrete BOX is assembled. Yes, including tunnel structures having various cross sections such as arch (horse-shoe), circle, ellipse, and rectangle, and may be a multiple tunnel.

上述の固化材が貧配合で配合された貧配合埋戻し材は、例えば、建設現場で発生した土に、固化材と水を混練し、流動化させた安定処理土である流動化処理土や、固化処理土などとすることができる。なお、上記固化材は、セメント系固化材のみならず、消石灰や生石灰などの石灰系固化材や液状の固化材など、用途や施工条件あるいは対象となる土質等に応じた適宜の固化材とすることができる。
より具体的には、例えば、一般的な強度を有するコンクリートに必要な固化材(セメント)添加量に比べて少ない添加量で構成した、つまり固化材(セメント)が貧配合されたコンクリートで構成した埋戻し材である。
The poor compounding backfill material in which the above-mentioned solidifying material is blended with poor blending is, for example, fluidized treated soil which is a stable treated soil obtained by kneading and fluidizing the solidified material and water to the soil generated at the construction site. , Solidified soil and the like. The solidified material is not only cement-based solidified material but also lime-based solidified material such as slaked lime and quicklime, liquid solidified material, etc., which is an appropriate solidified material according to the application, construction conditions, target soil quality, etc. be able to.
More specifically, for example, it is composed of a small amount of solidification material (cement) necessary for concrete having general strength, that is, composed of concrete in which the solidification material (cement) is poorly mixed. It is a backfill material.

この発明により、上載される埋戻し土量に対して要するトンネル構造物の剛性を低減することができる。
詳しくは、トンネル構造物の上部を、固化材が貧配合で配合された貧配合埋戻し材で埋戻すことによって、貧配合埋戻し材が硬化して自立するため、硬化することのない通常の埋戻し土砂で同じ土量を埋め戻す場合と比較して、トンネル構造物に作用する上載荷重を低減することができる。
According to the present invention, the rigidity of the tunnel structure required for the amount of backfill soil to be mounted can be reduced.
Specifically, the upper portion of the tunnel structure is backfilled with a poorly mixed backfill material in which the solidifying material is blended with a poor blend, so that the poor blended backfill material hardens and becomes self-supporting, so it does not harden normally. Compared with the case where the same amount of soil is backfilled with backfill earth and sand, the overhead load acting on the tunnel structure can be reduced.

したがって、トンネル構造物を構成する構造部材の強度、つまりトンネル構造物の剛性を低減することができる。よって、トンネル構造物を経済的に構築することができる。   Therefore, the strength of the structural member constituting the tunnel structure, that is, the rigidity of the tunnel structure can be reduced. Therefore, a tunnel structure can be constructed economically.

また、トンネル上部を埋戻す埋戻し土として、固化材が貧配合で配合された貧配合埋戻し材を用いることで、十分に締固めせずとも硬化するため、締固めが施工困難な狭隘な施工の場合であっても、施工性が向上するとともに、確実に埋め戻すことができる。さらにまた例えば、硬化後の自立性を得るためにコンクリートを打設する場合に比べて、安価で実現することができる。
このように、この発明によって、トンネル構造物自体及び埋戻しを安価且つ確実に行い、経済的なトンネル構造物を実現することができる。
In addition, as a backfill soil for backfilling the upper part of the tunnel, the use of a poorly mixed backfill material that contains a solidified material with a poor composition hardens without being fully compacted. Even in the case of construction, the workability is improved and it can be reliably backfilled. Furthermore, for example, it can be realized at a lower cost than in the case of placing concrete in order to obtain self-supporting property after curing.
Thus, according to the present invention, the tunnel structure itself and backfilling can be performed inexpensively and reliably, and an economical tunnel structure can be realized.

この発明の態様として、前記トンネル構造物を、上向きに凸なアーチ状の支保工をトンネル軸方向に所定間隔を隔てて設置し、トンネル断面の少なくとも内側上半部分を覆工材で覆工するとともに、前記トンネル断面の下部にインバートを形成して構築する構造とするとともに、前記トンネル構築箇所に、前記支保工を設置する支保工程と、設置した前記支保工の外側に外側覆工枠を設置する外側覆工枠設置工程と、前記支保工の下端部同士の間に、前記支保工を断面閉合するように内梁を設置する内梁設置工程と、前記外側覆工枠の上部を、前記貧配合埋戻し材で埋戻す埋戻し工程と、前記貧配合埋戻し材の硬化後、前記内梁を撤去する内梁撤去工程と、前記トンネル断面の下部にインバートを形成するインバート工程とを、この順で行うことができる。   As an aspect of the present invention, the tunnel structure is provided with arch-shaped supporters protruding upward at a predetermined interval in the tunnel axial direction, and at least the inner upper half portion of the tunnel cross section is covered with a covering material. In addition, the structure is constructed by forming an invert in the lower part of the tunnel cross section, and a supporting process for installing the support work at the tunnel construction location, and an outer lining frame is installed outside the installed support work. The outer lining frame installation step, the inner beam installation step of installing an inner beam so as to close the cross section of the supporting work between the lower ends of the supporting works, and the upper part of the outer lining frame, A backfilling process for backfilling with a poor compounding backfill material, an inner beam removing process for removing the inner beam after the poor compounding backfill material is cured, and an invert process for forming an invert at the lower portion of the tunnel cross section, In this order Door can be.

前記覆工材及び前記インバートは、場所打ちコンクリート、コンクリート加工品、鋼製、あるいは樹脂製など適宜の材質で構成した覆工材とすることができる。
前記外側覆工枠は、適宜の厚みのキーストンプレートや鋼製型枠など所定の強度を有する材料で構成することができる。
The lining material and the invert may be a lining material made of an appropriate material such as cast-in-place concrete, a concrete processed product, steel, or resin.
The outer lining frame can be made of a material having a predetermined strength such as a keystone plate or a steel mold having an appropriate thickness.

この発明により、上載される埋戻し土量に対して要する剛性を低減できるトンネル構造物を効率よく構築することができる。
詳しくは、上向きに凸なアーチ状の支保工をトンネル軸方向に所定間隔を隔てて設置し、トンネル断面の少なくとも内側上半部分を覆工材で覆工するとともに、前記トンネル断面の下部にインバートを形成して構築する構造とするとともに、前記トンネル構築箇所に、前記支保工を設置する支保工程と、設置した前記支保工の外側に外側覆工枠を設置する外側覆工枠設置工程と、前記支保工の下端部同士の間に、前記支保工を断面閉合するように内梁を設置する内梁設置工程と、前記外側覆工枠の上部を、前記貧配合埋戻し材で埋戻す埋戻し工程と、前記貧配合埋戻し材の硬化後、前記内梁を撤去する内梁撤去工程と、前記トンネル断面の下部にインバートを形成するインバート工程とを、この順で行うことにより、上載される埋戻し土量に対して要する剛性を低減できるトンネル構造物を効率よく、経済的に構築することができる。
By this invention, the tunnel structure which can reduce the rigidity required with respect to the amount of the backfill soil to be mounted can be efficiently constructed.
Specifically, upwardly projecting arch-shaped supporters are installed at predetermined intervals in the tunnel axis direction, and at least the inner upper half of the tunnel cross section is covered with a covering material, and the lower part of the tunnel cross section is inverted. In the tunnel construction location, the support process of installing the support work, and the outer cover frame installation process of installing an outer cover frame outside the support work installed, An inner beam installation step of installing an inner beam between the lower ends of the support works so that the cross section of the support work is closed, and an upper portion of the outer lining frame are buried with the poor compounding backfill material. It is mounted by performing a returning step, an inner beam removing step of removing the inner beam after hardening of the poor compounded backfill material, and an invert step of forming an invert at a lower portion of the tunnel cross section in this order. The amount of backfill soil The tunnel structure which can reduce the rigidity required to efficiently can be constructed economically.

なお、上述の支保工程において、あるいは支保工程の後に、トンネル軸方向における支保工同士の間を、モルタル製、あるいは樹脂製など適宜の材質の吹付材で吹き付ける吹付工、もしくは、円形型枠を設置してコンクリートを打設するコンクリート打設工を行ってもよい。   In the above-mentioned support process, or after the support process, a sprayer or a circular formwork is installed between the supporters in the tunnel axis direction with a spray material of an appropriate material such as mortar or resin. Then, a concrete placing work for placing concrete may be performed.

またこの発明の態様として、前記トンネル断面を計測するとともに、前記埋戻し工程、前記内梁撤去工程、及び前記インバート工程における各工程の変位が予め設定した管理基準値内である場合、次工程を行うことができる。   Further, as an aspect of the present invention, when the tunnel cross section is measured and the displacement of each step in the backfilling step, the inner beam removing step, and the inverting step is within a preset management reference value, the next step is performed. It can be carried out.

上述のトンネル断面を計測するは、トンネル構造物に設定した計測点をトランシット計測器で計測する、あるいは自動追尾型のトランシット計測器で自動的に計測、さらには、断面における計測点同士の相対距離を測定器で測定することを含む概念である。   To measure the tunnel cross section mentioned above, measure the measurement points set in the tunnel structure with a transit measuring instrument, or automatically with the automatic tracking type transit measuring instrument, and the relative distance between the measuring points on the section. It is a concept including measuring with a measuring instrument.

上記予め設定した管理基準値は、構築するトンネル構造物をモデル化して、例えば動的解析等の解析によって、各工程における変位量を算出し、算出した変位量をこれまでの工程における変位量に累積させた、つまり初期形状からの変位量に基づいて設定した管理値とすることができる。   The management reference value set in advance is obtained by modeling the tunnel structure to be constructed, calculating the amount of displacement in each process, for example, by analysis such as dynamic analysis, and converting the calculated amount of displacement into the amount of displacement in the previous process. The management value can be set based on the accumulated amount, that is, the displacement amount from the initial shape.

この発明により、より安全にトンネル構造物を構築することができる。
詳述すると、構築中のトンネル構造物に作用する土圧による変位が収束する前に次の工程を行うと、次の工程で施工する部材に意図しない不要な応力が生じる。また、計測結果が予め設定した管理基準値を大きく超える場合、意図しない圧力が構築中のトンネル構造物に作用していることとなる。これに対して、トンネル断面を計測するとともに、前記埋戻し工程、前記内梁撤去工程、及び前記インバート工程における各工程の変位が予め設定した管理基準値内である場合、次工程を行うため、次の工程で施工する部材に意図しない不要な応力が生じることもなく、また、意図しない圧力が構築中のトンネル構造物に作用していないことも確認しながら、トンネル構造物を構築できるため、安全に施工することができる。
According to the present invention, a tunnel structure can be constructed more safely.
More specifically, if the next step is performed before the displacement due to earth pressure acting on the tunnel structure under construction converges, unintended unnecessary stress is generated on the member to be constructed in the next step. Further, when the measurement result greatly exceeds the preset management reference value, an unintended pressure is acting on the tunnel structure being constructed. On the other hand, in addition to measuring the tunnel cross-section, if the displacement of each step in the backfilling step, the inner beam removal step, and the invert step is within a preset management reference value, to perform the next step, Because it is possible to build a tunnel structure while confirming that unintended unnecessary stress does not occur in the members to be constructed in the next process and that unintended pressure is not acting on the tunnel structure being built, It can be constructed safely.

またこの発明の態様として、前記埋戻し工程において、埋め戻した前記貧配合埋戻し材の上部を、埋戻し土砂で埋戻すことができる。
上述の埋め戻した前記貧配合埋戻し材の上部は、上載する埋戻し土砂の圧力がトンネル構造物に作用しないように、埋戻し土砂を支持できる高さ分を埋め戻した前記貧配合埋戻し材の上部とすることができる。
埋戻し土砂とは、山砂、真砂土などの良質土、あるいは掘削土砂を改良した改良土、さらには砕石、アスファルトあるいは路床材などとすることができる。
Moreover, as an aspect of the present invention, in the backfilling step, the upper portion of the poor blend backfilling material backfilled can be backfilled with backfill earth and sand.
The poor blended backfill that has been backfilled at a height capable of supporting the backfilled soil so that the pressure of the backfilled sand that is mounted on the tunnel structure does not act on the upper part of the above-mentioned backfilled poor blended backfill material. It can be the top of the material.
The backfilling earth and sand can be high-quality soil such as mountain sand and true sand, or improved soil obtained by improving excavated earth and sand, as well as crushed stone, asphalt or roadbed material.

この発明により、トンネル構造物より上部をすべて、前記貧配合埋戻し材で埋め戻す場合に比べて、安価で構築することができる。
詳述すると、一般的に、土被りの小さなトンネル構造物には土被り全部の土圧が作用するが、上部の所定高さ分を埋め戻した前記貧配合埋戻し材が硬化したあとは、埋め戻した前記貧配合埋戻し材の上部を埋戻し土砂で埋め戻してもトンネル構造物に埋め戻した埋戻し土砂による土圧は作用しないため、埋戻し土に比べて安価な埋戻し土砂を前記貧配合埋戻し材の上部に埋め戻すことで、上載される埋戻し土量に対して要する剛性を低減できるトンネル構造物を効率よく、さらに経済的に構築できる。
According to the present invention, it is possible to construct the upper part of the tunnel structure at a lower cost as compared with the case of backfilling with the poor blending backfill material.
In detail, in general, the earth pressure of the entire earth covering acts on the tunnel structure with a small earth covering, but after the poor compounding backfill material that has filled up the predetermined height of the upper part is cured, Even if the upper part of the poor compounded backfill material that has been backfilled is backfilled with backfill earth and sand, the earth pressure due to the backfilled sand that has been backfilled in the tunnel structure does not act, so cheap backfill earth and sand can be used. By backfilling the upper portion of the poor blended backfill material, a tunnel structure capable of reducing the rigidity required for the amount of backfilled soil to be mounted can be efficiently and more economically constructed.

またこの発明の態様として、前記トンネル構築箇所を、掘削して構築する掘削トンネルの坑口とするとともに、坑門を構築する坑門工を行うことができる。
通常、いわゆる緩み土圧という所定高さ分の土圧のみが作用するとされている掘削トンネルに対して、坑口部分は明かりで施工され、上載する全土圧が作用するため、掘削トンネルより高剛性なトンネル構造が必要となることが多い坑口部分であっても、上述の構造及び構築方法により、掘削トンネルにおける坑口部分を、剛性を低減できる構造とすることができ、さらに経済的なトンネル構造物を構築することができる。
In addition, as an aspect of the present invention, the tunnel construction site can be used as a pit of an excavation tunnel constructed by excavation, and a gate work for constructing a tunnel can be performed.
Normally, the tunnel head is constructed with light for the excavation tunnel where only a certain height of earth pressure called so-called loose earth pressure acts. Even with a wellhead part that often requires a tunnel structure, the wellhead part in the excavation tunnel can be made a structure that can reduce rigidity by the above-described structure and construction method. Can be built.

またこの発明の態様として、前記トンネル構築箇所を、埋め戻した上部を通行体が通行する通行路が構築される通行路交差部とすることができる。
上記通行体は、自動車や列車などの通行車両や、通行人などとすることができる。
Moreover, as an aspect of the present invention, the tunnel construction location can be a traffic road intersection where a traffic path through which a passing body passes is filled.
The passing body can be a passing vehicle such as an automobile or a train, or a passerby.

この発明により、例えば、すべてを埋戻し土砂で埋め戻す場合に比べて、経年的な圧密によって生じる圧密沈下等の不具合が生じるおそれがなく、安全性の高い通行路を構成することができる。   According to the present invention, for example, compared to a case where everything is backfilled with backfill earth and sand, there is no risk of problems such as consolidation settlement caused by aged consolidation, and a highly safe passage can be configured.

この発明によれば、上載される埋戻し土量に対して要するトンネル構造物の剛性を低減することができるトンネルの構築方法及びトンネル構造物を提供することができる。   ADVANTAGE OF THE INVENTION According to this invention, the construction method and tunnel structure of a tunnel which can reduce the rigidity of the tunnel structure required with respect to the amount of backfill soil to be mounted can be provided.

交差トンネルの概略斜視図。The schematic perspective view of an intersection tunnel. 交差トンネルの坑口部の横断面図。The cross-sectional view of the wellhead part of the crossing tunnel. 交差トンネルの坑口部の縦断面図。The longitudinal cross-sectional view of the wellhead part of an intersection tunnel. 交差トンネルの構築方法のフローチャート。The flowchart of the construction method of an intersection tunnel. 交差トンネルの構築方法の正面図による説明図。Explanatory drawing by the front view of the construction method of an intersection tunnel. 交差トンネルの構築方法の概略斜視図による説明図。Explanatory drawing by the schematic perspective view of the construction method of an intersection tunnel. 交差トンネルの構築方法の概略斜視図による説明図。Explanatory drawing by the schematic perspective view of the construction method of an intersection tunnel. 交差トンネルの構築方法の正面図による説明図。Explanatory drawing by the front view of the construction method of an intersection tunnel. 交差トンネルの構築方法の概略斜視図による説明図。Explanatory drawing by the schematic perspective view of the construction method of an intersection tunnel. 交差トンネルの構築方法の正面図による説明図。Explanatory drawing by the front view of the construction method of an intersection tunnel. 交差トンネルの構築方法の概略斜視図による説明図。Explanatory drawing by the schematic perspective view of the construction method of an intersection tunnel. 交差トンネルの構築方法の正面図による説明図。Explanatory drawing by the front view of the construction method of an intersection tunnel. 交差トンネルの構築方法の概略斜視図による説明図。Explanatory drawing by the schematic perspective view of the construction method of an intersection tunnel. 交差トンネルの構築方法の正面図による説明図。Explanatory drawing by the front view of the construction method of an intersection tunnel. 交差トンネルの構築方法の概略斜視図による説明図。Explanatory drawing by the schematic perspective view of the construction method of an intersection tunnel.

この発明の一実施形態を以下図面とともに説明する。
まず、上部にトンネル軸方向Tと交差する方向の交差通行路300を備えた交差トンネル1について、図1乃至図15とともに説明する。
An embodiment of the present invention will be described below with reference to the drawings.
First, an intersection tunnel 1 having an intersection passage 300 in a direction intersecting the tunnel axis direction T at the top will be described with reference to FIGS.

なお、図1は交差トンネル1の概略斜視図を示し、図2は交差トンネル1の坑口部100の横断面図を示し、図3は交差トンネル1の坑口部100の幅方向中央付近の縦断面図を示し、図4は交差トンネル1の構築方法のフローチャートを示している。   1 shows a schematic perspective view of the crossing tunnel 1, FIG. 2 shows a cross-sectional view of the wellhead part 100 of the crossing tunnel 1, and FIG. 3 shows a longitudinal section near the center in the width direction of the wellhead part 100 of the crossing tunnel 1. FIG. 4 shows a flowchart of a method for constructing the intersection tunnel 1.

また、図5、8、10、12、14は交差トンネル1の構築方法の正面図による説明図を示し、図6、7、9、11、13、15は交差トンネル1の構築方法の概略斜視図による説明図を示している。   5, 8, 10, 12, and 14 are explanatory views of the construction method of the intersection tunnel 1, and FIGS. 6, 7, 9, 11, 13, and 15 are schematic perspective views of the construction method of the intersection tunnel 1. FIG.

詳述すると、図5(a)は切土工についての正面図を示し、図5(b)はコンクリート吹付工完了後の正面図を示し、図6(a)は切土工についての概略斜視図を示し、図6(b)は支保工設置工についての概略斜視図を示し、図7(a)は外側覆工枠設置工についての概略斜視図を示し、図7(b)はコンクリート吹付工についての概略斜視図を示している。   Specifically, FIG. 5 (a) shows a front view of the cut work, FIG. 5 (b) shows a front view after completion of the concrete spraying work, and FIG. 6 (a) shows a schematic perspective view of the cut work. Fig. 6 (b) shows a schematic perspective view of the support construction installation work, Fig. 7 (a) shows a schematic perspective view of the outer lining frame installation work, and Fig. 7 (b) shows a concrete spraying work. The schematic perspective view of is shown.

また、図8(a)は内梁設置工及び計測準備工についての正面図を示し、図8(b)は坑門工についての正面図を示し、図9(a)は内梁設置工及び計測準備工についての概略斜視図を示し、図9(b)は坑門工についての概略斜視図を示している。   8A shows a front view of the inner beam installation work and the measurement preparation work, FIG. 8B shows a front view of the gate work, and FIG. 9A shows an inner beam installation work and A schematic perspective view of the measurement preparation work is shown, and FIG. 9B shows a schematic perspective view of the gate work.

また、図10(a)は貧配合コンクリート埋戻し工についての正面図を示し、図10(b)は路床埋戻し工についての正面図を示し、図11(a)は貧配合コンクリート埋戻し工についての概略斜視図を示し、図11(b)は路床埋戻し工についての概略斜視図を示している。   Moreover, Fig.10 (a) shows the front view about a poor mixing concrete backfill, FIG.10 (b) shows the front view about a roadbed backfilling, FIG.11 (a) is a poor mixing concrete backfill. The schematic perspective view about a construction is shown, and Drawing 11 (b) shows the schematic perspective view about a roadbed backfilling construction.

また、図12(a)は内梁撤去工についての正面図を示し、図12(b)はインバート工についての正面図を示し、図13(a)は内梁撤去工についての概略斜視図を示し、図13(b)はインバート工についての概略斜視図を示している。
また、図14(a)は覆工についての正面図を示し、図14(b)は道路設置工についての正面図を示し、図15(a)は覆工についての概略斜視図を示し、図15(b)は道路設置工についての概略斜視図を示している。
12A shows a front view of the inner beam removal work, FIG. 12B shows a front view of the invert work, and FIG. 13A shows a schematic perspective view of the inner beam removal work. FIG. 13B shows a schematic perspective view of the invert process.
14 (a) shows a front view of the lining, FIG. 14 (b) shows a front view of the road builder, FIG. 15 (a) shows a schematic perspective view of the lining, and FIG. 15 (b) shows a schematic perspective view of the road installation work.

以下で詳細に説明する交差トンネル1は、地山200を掘削する断面アーチ状の山岳トンネルであり、トンネル内部Tには通行路310を形成している。
なお、図1乃至3及び図5乃至図15では、地山200を切土し、交差トンネル1の端部となる坑口部100を中心に図示しているが、交差トンネル1はトンネル軸方向Tに所定の長さを有するトンネル構造物である。
The crossing tunnel 1 described in detail below is a mountain tunnel having an arched cross section for excavating the natural ground 200, and a passage 310 is formed in the tunnel interior T.
In FIGS. 1 to 3 and FIGS. 5 to 15, the natural ground 200 is cut and illustrated with the pit portion 100 serving as the end of the crossing tunnel 1 as a center. The tunnel structure has a predetermined length.

また、交差トンネル1の本体の構築方法については問わないが、例えばNATMなどによって、地山200を掘削し、支保工を設置するとともに、内部吹付けを施したうえで覆工して、所定断面のトンネルを構築すればよい。   Moreover, the construction method of the main body of the crossing tunnel 1 is not limited. For example, the natural ground 200 is excavated by NATM or the like, a supporting work is installed, and the inner spray is applied and then the lining is performed to obtain a predetermined cross section. You just need to build a tunnel.

このようにして構築する交差トンネル1の坑口部100は、交差トンネル1の端部となる箇所の地山200を切土し、交差トンネル1の本体部分と同内空断面のトンネル構造物を構築するとともに埋戻し、上部に、トンネル軸方向Tと交差する方向の交差通行路300を構築している。すなわち、坑口部100は明かり工事で構築している。   The wellhead portion 100 of the crossing tunnel 1 constructed in this way cuts a natural ground 200 that is the end of the crossing tunnel 1, and constructs a tunnel structure having the same internal cross section as the main part of the crossing tunnel 1. At the top, a crossing passage 300 is constructed in the direction intersecting the tunnel axis direction T. That is, the wellhead part 100 is constructed by light work.

詳しくは、交差トンネル1の本体と同じアーチ形状の支保工20の外側に外側覆工枠30を設置し、外側覆工枠30の内側に吹付コンクリート40を吹付け、さらにその内側を覆工材50で覆工して構築している。また、交差トンネル1の断面方向における支保工20の下部同士の間には下向きに略円弧状のインバート60が構築され、インバート60の上部に路体70による通行路310が構築されている。   Specifically, the outer lining frame 30 is installed outside the support arch 20 having the same arch shape as the main body of the crossing tunnel 1, the sprayed concrete 40 is sprayed inside the outer lining frame 30, and the inside is covered with the lining material. 50 is lined and constructed. Further, a substantially arc-shaped invert 60 is constructed downwardly between the lower portions of the support works 20 in the cross-sectional direction of the intersection tunnel 1, and a passage 310 by the road body 70 is constructed above the invert 60.

さらには、坑口部100の端部には、坑門110を構築し、外側覆工枠30の上部における所定高さ分を貧配合コンクリート120で埋め戻すとともに、その上部を路床材130で埋戻し、その上面に交差通行路300を構築している。
支保工20は、H型鋼をアーチ形状に曲げて構成し、外側覆工枠30はキーストンプレートを支保工20の形状に合わせて曲げ加工して構成している。
Furthermore, a pit 110 is constructed at the end of the wellhead portion 100, and a predetermined height at the top of the outer lining frame 30 is backfilled with the poor blended concrete 120, and the top is buried with the roadbed material 130. Returning, the crossing road 300 is constructed on the upper surface.
The support 20 is configured by bending H-shaped steel into an arch shape, and the outer lining frame 30 is configured by bending a keystone plate according to the shape of the support 20.

貧配合コンクリート120は、所定の強度を有する貧配合のコンクリートで構成しているが、所定の強度を有すれば、掘削土などをセメントで処理した流動化処理土で構成してもよい。
より具体的には、通常、強度が1600kN/mの無筋コンクリートに必要なセメント添加量はおよそ160kg/mであるが、貧配合コンクリート120は、必要強度が1000kN/mであり、セメント添加量はおよそ86kg/m程度となる。このように、貧配合コンクリート120は、一般的な強度を有するコンクリートのためのセメント添加量に比べて少ないセメント添加量、つまりセメントが貧配合されたコンクリートである。なお、貧配合コンクリート120の強度は一軸圧縮試験やコーン試験で求めることができ、埋め戻し材として必要な所定の強度を発現するセメント添加量を求めればよい。
路床材130は、山砂、真砂土などの良質土、あるいは掘削土砂を改良した改良土などの埋戻し土砂や、砕石などの路盤材とすることができる。
The poor blended concrete 120 is composed of poor blended concrete having a predetermined strength. However, as long as it has a predetermined strength, the poor blended concrete 120 may be composed of fluidized soil obtained by treating excavated soil with cement.
More specifically, the amount of cement required for unreinforced concrete having a strength of 1600 kN / m 2 is usually about 160 kg / m 3 , but poor blended concrete 120 has a required strength of 1000 kN / m 2 , The amount of cement added is about 86 kg / m 3 . As described above, the poorly-mixed concrete 120 is a cement with a cement addition amount that is small compared to the cement addition amount for concrete having general strength, that is, a cement with poor cement content. The strength of the poor blended concrete 120 can be obtained by a uniaxial compression test or a cone test, and a cement addition amount that expresses a predetermined strength necessary as a backfill material may be obtained.
The roadbed material 130 can be a high-quality soil such as mountain sand or pure sand, or a backfill material such as improved soil obtained by improving excavated soil, or a roadbed material such as crushed stone.

このような構成で構築する交差トンネル1の坑口部100の構築方法について、図4に示すフローチャートとともに説明する。
まず、後述する各工程の管理基準値を設定する(ステップs1)。詳しくは、後述する路床埋戻し工(ステップs10)、内梁撤去工(ステップs12)、及びインバート工(ステップs14)の各工程での坑口部100のモデル化を行うとともに、各工程での変位量を動的解析によって算出し、算出した変位量を累積させて、つまり初期形状に対する当該工程における変位量に基づいて管理基準値を設定する。なお、この管理基準値設定工程(ステップs1)は、後述する路床埋戻し工(ステップs10)の前までに実施すればよく、必ず、最初に行う必要はない。
A method for constructing the wellhead 100 of the crossing tunnel 1 constructed in such a configuration will be described with reference to the flowchart shown in FIG.
First, the management reference value of each process mentioned later is set (step s1). Specifically, the wellhead 100 is modeled in each process of a roadbed backfill (step s10), inner beam removal (step s12), and invert (step s14), which will be described later. The displacement amount is calculated by dynamic analysis, and the calculated displacement amount is accumulated, that is, the management reference value is set based on the displacement amount in the process with respect to the initial shape. The management reference value setting step (step s1) may be performed before the roadbed backfilling step (step s10) described later, and is not necessarily performed first.

交差トンネル1の坑口部100を構築する実施工として、まず、図6(a)に示すように、支保工20が設置できるように地山200を切土して施工面GLを形成し(ステップs2)、図5(b),図6(b)に示すように、H型鋼をアーチ状に形成した支保工20を施工面GLに設置する(ステップs3)。   As an implementation work for constructing the wellhead portion 100 of the crossing tunnel 1, first, as shown in FIG. 6A, the ground 200 is cut so that the support work 20 can be installed, and the construction surface GL is formed (step) As shown in s2), FIG. 5 (b), and FIG. 6 (b), the support 20 in which the H-shaped steel is formed in an arch shape is installed on the construction surface GL (step s3).

このとき、支保工20はトンネル軸方向Tに沿って所定間隔を隔てて複数配置し、支保工20同士の間である支保工間をタイロッド21で連結して一体化している。なお、タイロッド21は、アーチ状に沿って複数配置するとともに、トンネル軸方向Tに隣り合う支保工間では、アーチ状の断面位置がトンネル軸方向Tに連続しないように、互い違いとなるように配置している。   At this time, a plurality of support works 20 are arranged at predetermined intervals along the tunnel axis direction T, and the support works between the support works 20 are connected by a tie rod 21 to be integrated. A plurality of tie rods 21 are arranged along the arch shape, and are arranged so as to be staggered so that the arch-shaped cross-sectional positions do not continue in the tunnel axis direction T between the support works adjacent to each other in the tunnel axis direction T. doing.

続いて、図5(a),図7(a)に示すように。トンネル軸方向Tに沿って所定間隔を隔てて複数配置した支保工20の外側に、キーストンプレートで構成する外側覆工枠30を設置するとともに(ステップs4)、外側覆工枠30の内側における支保工間を吹付コンクリート40で吹き付けて覆工する(ステップs5,図7(b)参照)。   Subsequently, as shown in FIGS. 5 (a) and 7 (a). An outer lining frame 30 composed of a keystone plate is installed outside the supporting structures 20 arranged at predetermined intervals along the tunnel axis direction T (step s4), and the supporting structure inside the outer lining frame 30 is also provided. The work space is sprayed with sprayed concrete 40 to cover the work (see step s5, FIG. 7 (b)).

このようにして、坑口部100の概略断面を構成する支保工20及び吹付コンクリート40に対して、上載荷重が作用していないこの状態で、図8(a),図9(a)に示すように、アーチ状に形成した支保工20の下部の内側同士を突っ張るようにして、内梁22を設置する(ステップs6)。   As shown in FIGS. 8 (a) and 9 (a) in this state in which no overload is acting on the support 20 and the shotcrete 40 constituting the schematic cross section of the wellhead portion 100 in this way. Then, the inner beam 22 is installed so as to stretch the inner sides of the lower part of the support 20 formed in an arch shape (step s6).

このとき、内梁22は、上載荷重が作用して所定の断面形状となるよう、アーチ状の足元を広げるように、アーチ状に形成した支保工20の下部の内側同士を突っ張るようにして設置する。   At this time, the inner beam 22 is installed so as to stretch the inner sides of the lower part of the support 20 formed in an arch shape so as to widen the foot of the arch shape so as to have a predetermined cross-sectional shape due to the applied load. To do.

そして、内梁22が設置された支保工20に対して、計測ポイントとなる計測点23を設置するとともに、初期形状を計測する(ステップs7)。なお、本実施形態においては、支保工20に設定した計測点23を、図示省略するトランシット等の計測装置で計測するが、計測点23同士の相対間隔を計測する計測装置を設置して計測してもよい。また、自動追尾型のトランシット等で計測点23の変位を計測してもよい。   And the measuring point 23 used as a measuring point is installed with respect to the support work 20 in which the inner beam 22 was installed, and an initial shape is measured (step s7). In this embodiment, the measurement point 23 set in the support work 20 is measured by a measurement device such as a transit (not shown). However, a measurement device that measures the relative distance between the measurement points 23 is installed and measured. May be. Further, the displacement of the measurement point 23 may be measured by an automatic tracking type transit or the like.

初期計測完了後に、図8(b),図9(b)に示すように、支保工20の上部を埋め戻す際のトンネル軸方向Tの端部側のつま壁として機能するように、予め、坑口部100のトンネル軸方向Tの端部に坑門110を構築する(ステップs8)。坑門110は、坑口部100のトンネル軸方向Tの端部において、型枠を組付けてコンクリートを打設して構築する。
なお、坑門110の構築後に、支保工20に計測点23を設置して、初期形状を計測してもよい。
After completion of the initial measurement, as shown in FIGS. 8 (b) and 9 (b), in order to function as a toe wall on the end side in the tunnel axial direction T when the upper portion of the support work 20 is backfilled, The tunnel 110 is constructed at the end of the tunnel opening 100 in the tunnel axial direction T (step s8). The pit 110 is constructed by assembling a formwork and placing concrete at the end of the pit portion 100 in the tunnel axial direction T.
In addition, after construction of the pit 110, the measurement point 23 may be installed in the support work 20, and an initial shape may be measured.

坑門110の構築完了後、支保工20及び外側覆工枠30の上方から、図10(a),図11(a)に示すように、貧配合コンクリート120で所定高さまで埋戻し(ステップs9)、貧配合コンクリート120の硬化後に、図10(b),図11(b)に示すように、貧配合コンクリート120の上部を路床材130で埋め戻して(ステップs10)、支保工20上部の埋戻しを完了する。このとき、貧配合コンクリート120の埋戻しによって、上載荷重が作用する支保工20は変形する。   After the completion of the construction of the tunnel 110, as shown in FIGS. 10 (a) and 11 (a), backfilling to a predetermined height from the upper side of the support work 20 and the outer lining frame 30 (step s9). ) After the poor blended concrete 120 is cured, as shown in FIGS. 10B and 11B, the upper portion of the poor blended concrete 120 is backfilled with the roadbed material 130 (step s10), and the upper portion of the support work 20 Complete the backfill. At this time, due to the backfilling of the poor blended concrete 120, the support work 20 on which the loading load acts is deformed.

埋戻し完了後、ステップs7で設置した計測点23を計測し、収束した計測結果が、つまり支保工20の変形量が、ステップs1で設定した管理基準値のうち、埋戻し完了時における管理基準位置以内であれば、後述する次の工程に進む(ステップs11)。なお、本工程や後述する管理基準値の確認工程において、収束した計測結果が各工程における管理基準値を超える場合は、次の工程に進まず、現状の把握及び、以降の工程について、別途対策を検討する。   After completion of the backfilling, the measurement point 23 set in step s7 is measured, and the converged measurement result, that is, the deformation amount of the support 20 is the management reference value when the backfilling is completed among the management reference values set in step s1. If it is within the position, the process proceeds to the next process described later (step s11). If the converged measurement result exceeds the control reference value in each process in this process or the control reference value check process described later, the current process will not proceed to the next process and separate measures will be taken for the subsequent processes. To consider.

ステップs11において、埋戻し完了時の計測結果が管理基準値以内であると確認できた場合、つまり支保工20の変形量が想定した変形量以下である場合、支保工20に作用する上載荷重を、内梁22を設置した支保工20で十分に支持できていると判断できるため、支保工20の下部に設置した内梁22を撤去する(ステップs12)。   In step s11, when it is confirmed that the measurement result at the time of completion of the backfilling is within the control reference value, that is, when the deformation amount of the support 20 is equal to or less than the assumed deformation, the upper load acting on the support 20 is calculated. Since it can be determined that the support beam 20 provided with the inner beam 22 is sufficiently supported, the inner beam 22 installed at the lower portion of the support beam 20 is removed (step s12).

内梁22を撤去することによって、支保工20のアーチアクションのみで上載荷重を支持するため、つまり、内梁22を撤去することで、支保工20のトンネル断面方向の強度は低下するため、支保工20は変形する。   By removing the inner beam 22, the upper load is supported only by the arch action of the support work 20, that is, by removing the inner beam 22, the strength of the support work 20 in the tunnel cross-section direction is reduced. The work 20 is deformed.

内梁22を撤去したことによって変形する支保工20の変形量、つまり、これまでの支保工20の変形量に内梁22を撤去したことによる支保工20の変形量が加算された支保工20の累積変形量を、計測点23を用いて計測し、その収束した計測結果が、ステップs1で設定した管理基準値のうち、内梁撤去完了時における管理基準位置以内であれば、後述する次の工程に進む(ステップs13)。   The amount of deformation of the supporting work 20 that is deformed by removing the inner beam 22, that is, the amount of deformation of the supporting work 20 that is obtained by removing the inner beam 22 to the amount of deformation of the supporting structure 20 so far. Is measured using the measurement point 23, and if the converged measurement result is within the management reference position at the time of completion of the inner beam removal among the management reference values set in step s1, the following will be described later. The process proceeds to step s13.

ステップs13において、内梁撤去時の計測結果が管理基準値以内であると確認できた場合、支保工20に作用する上載荷重を、内梁22を撤去した支保工20で十分に支持できていると判断できるため、支保工20の下部にインバート60を設置する(ステップs14)。   In step s13, when it can be confirmed that the measurement result at the time of removing the inner beam is within the control reference value, the loading load acting on the support beam 20 can be sufficiently supported by the support beam 20 from which the inner beam 22 has been removed. Therefore, the invert 60 is installed in the lower part of the support work 20 (step s14).

詳しくは、図12(a)、図13(a)に示すように、内梁22を撤去した支保工20の下部の施工面GLを所定深さ掘り下げ、掘り下げた箇所に、支保工20の下端同士を跨ぐように、コンクリートを打設してインバート60を設置する。   Specifically, as shown in FIGS. 12 (a) and 13 (a), a lower construction surface GL of the support work 20 from which the inner beam 22 has been removed is dug down to a predetermined depth, and the lower end of the support work 20 is placed at the dug position. The invert 60 is installed by placing concrete so as to straddle each other.

インバート60の設置完了後、すなわちインバート60を構築するコンクリートが硬化後、計測点23を計測して、収束した計測結果が、ステップs1で設定した管理基準値のうち、インバート工完了時における管理基準位置以内であれば、後述する次の工程に進む(ステップs15)。   After the installation of the invert 60 is completed, that is, after the concrete forming the invert 60 is cured, the measurement point 23 is measured, and the converged measurement result is the management standard at the time of completion of the invert work among the management standard values set in step s1. If it is within the position, the process proceeds to the next process described later (step s15).

ステップs15において、インバート工完了時の計測結果が管理基準値以内であると確認できた場合、インバートを設置した支保工20で十分に支持できていると判断できるため、図14(a)、図15(a)に示すように、支保工20及び吹付コンクリート40の内側を覆工材50で覆工する(ステップs16)。さらに、図14(b)、図15(b)に示すように、インバート60の上部に路体70を設置して(ステップs17)、通行路310を構築して、坑口部100の構築を完了する。   In step s15, when it can be confirmed that the measurement result at the completion of the invert work is within the control reference value, it can be determined that the support work 20 in which the invert is installed is sufficiently supported. As shown to 15 (a), the inner side of the support work 20 and the shotcrete 40 is covered with the covering material 50 (step s16). Further, as shown in FIGS. 14 (b) and 15 (b), the road body 70 is installed on the upper part of the invert 60 (step s17), the passage 310 is constructed, and the construction of the wellhead 100 is completed. To do.

なお、交差通行路300は、ステップs10において路床材130で埋め戻した後であれば、坑口部100の構築完了後に構築してもよく、坑口部100の構築と並行して構築してもよい。   Note that the crossing road 300 may be constructed after the completion of the construction of the wellhead part 100 or may be constructed in parallel with the construction of the wellhead part 100 as long as it is backfilled with the roadbed material 130 in step s10. Good.

このような施工方法で構築する坑口部100は、固化材が貧配合で配合された貧配合コンクリート120で上部を埋戻して構築するため、上載される埋戻し土量に対して要する坑口部100の剛性を低減することができる。   The wellhead portion 100 constructed by such a construction method is constructed by backfilling the upper portion with the poor blended concrete 120 in which the solidifying material is blended with poor blending, and therefore the wellhead portion 100 required for the amount of backfilled soil to be mounted. The rigidity of can be reduced.

詳しくは、坑口部100の上部を、固化材が貧配合で配合された貧配合コンクリート120で埋戻すことによって、貧配合コンクリート120が硬化して自立するため、硬化することのない通常の路床材130で同じ土量を埋め戻す場合と比較して、坑口部100に作用する上載荷重を低減することができる。
したがって、坑口部100を構成する構造部材の強度、つまり坑口部100の剛性を低減することができる。よって、坑口部100を経済的に構築することができる。
Specifically, since the poor blended concrete 120 hardens and becomes self-supporting when the upper portion of the wellhead 100 is backfilled with the poor blended concrete 120 in which the solidifying material is blended in the poor blend, a normal roadbed that does not cure. Compared with the case where the same amount of soil is backfilled with the material 130, the overload acting on the wellhead 100 can be reduced.
Therefore, the strength of the structural member constituting the wellhead portion 100, that is, the rigidity of the wellhead portion 100 can be reduced. Therefore, the wellhead 100 can be constructed economically.

また、トンネル上部を埋戻す埋戻し土として、固化材が貧配合で配合された貧配合コンクリート120を用いることで、締固めせずとも硬化するため、締固めが施工困難な狭隘な施工の場合であっても、施工性が向上するとともに、確実に埋め戻すことができる。さらにまた例えば、硬化後の自立性を得るためにコンクリートを打設する場合に比べて、安価で実現することができる。
このように、この発明によって、坑口部100自体及び埋戻しを安価且つ確実に行い、経済的な坑口部100を実現することができる。
In addition, in the case of narrow construction where compaction is difficult to construct because it is hardened without compaction by using the poor blended concrete 120 blended with poor blending material as the backfill soil to refill the upper part of the tunnel Even so, the workability is improved and it can be reliably backfilled. Furthermore, for example, it can be realized at a lower cost than in the case of placing concrete in order to obtain self-supporting property after curing.
As described above, according to the present invention, the wellhead portion 100 itself and backfilling can be performed inexpensively and reliably, and an economical wellhead portion 100 can be realized.

また、上向きに凸なアーチ状の支保工20をトンネル軸方向Tに所定間隔を隔てて設置し、断面内側を覆工材50で覆工するとともに、トンネル断面の下部にインバート60を形成して構築する構造である坑口部100を、施工面GLに支保工20を設置する支保工程(ステップs3)、設置した支保工20の外側に外側覆工枠30を設置する外側覆工枠設置工程(ステップs4)と、支保工20の下端部同士の間に、支保工20を断面閉合するように内梁22を設置する内梁設置工程(ステップs6)と、外側覆工枠30の上部を、貧配合コンクリート120で埋戻す埋戻し工程(ステップs9)と、貧配合コンクリート120の硬化後、内梁22を撤去する内梁撤去工程(ステップs12)と、トンネル断面の下部にインバート60を形成するインバート工程(ステップs14)とを、この順で行うことにより、上載される埋戻し土量に対して要する剛性を低減できる坑口部100を効率よく構築することができる。   Further, an upwardly projecting arch-shaped support 20 is installed at a predetermined interval in the tunnel axis direction T, and the inside of the cross section is covered with a covering material 50, and an invert 60 is formed at the lower part of the tunnel cross section. Supporting step (step s3) of installing the support 20 on the construction surface GL of the wellhead portion 100 to be constructed, and an outer lining frame installation step of installing the outer lining frame 30 on the outside of the installed supporting craft ( Step s4), the inner beam installation step (step s6) for installing the inner beam 22 so as to close the cross section of the support 20 between the lower ends of the support 20, and the upper part of the outer lining frame 30 A backfilling process (step s9) for backfilling with the poor blended concrete 120, an inner beam removing process (step s12) for removing the inner beam 22 after the poor blended concrete 120 is cured, and an invert 60 is formed at the lower portion of the tunnel cross section. And invert process (step s14) which, by performing in that order, it is possible to construct a wellhead portion 100 which can reduce the rigidity required against backfill soil amount of overburden efficiently.

また、計測点23を用いて、トンネル断面を計測するとともに、埋戻し工程(ステップs9)、内梁撤去工程(ステップs12)、及びインバート工程(ステップs14)における各工程の変位が予め設定した管理基準値内である場合、次工程を行うため、より安全に坑口部100を構築することができる。   Moreover, while measuring a tunnel cross section using the measuring point 23, the displacement of each process in a backfill process (step s9), an inner beam removal process (step s12), and an invert process (step s14) was set beforehand. When it is within the reference value, the next step is performed, and thus the wellhead 100 can be constructed more safely.

詳述すると、構築中の坑口部100に作用する土圧による変位が収束する前に次の工程を行うと、次の工程で施工する部材に意図しない不要な応力が生じる。また、計測結果が予め設定した管理基準値を大きく超える場合、意図しない圧力が構築中の坑口部100に作用していることとなる。これに対して、トンネル断面を計測するとともに、埋戻し工程(ステップs9)、内梁撤去工程(ステップs12)、及びインバート工程(ステップs14)における各工程の変位が予め設定した管理基準値内である場合、次工程を行うため、次の工程で施工する部材に意図しない不要な応力が生じることもなく、また、意図しない圧力が構築中の坑口部100に作用していないことも確認しながら、坑口部100を構築できるため、安全に施工することができる。   More specifically, if the next step is performed before the displacement due to earth pressure acting on the wellhead 100 under construction converges, unintended unnecessary stress is generated on the member to be constructed in the next step. Further, when the measurement result greatly exceeds the preset management reference value, an unintended pressure is acting on the wellhead portion 100 being constructed. On the other hand, while measuring the tunnel cross section, the displacement of each step in the backfilling step (step s9), the inner beam removing step (step s12), and the inverting step (step s14) is within a preset management reference value. In some cases, since the next step is performed, unintentional unnecessary stress is not generated in the member to be constructed in the next step, and it is confirmed that unintended pressure is not acting on the wellhead portion 100 being constructed. Since the wellhead 100 can be constructed, it can be constructed safely.

さらにまた、埋戻し工程(ステップs9)において、埋め戻した貧配合コンクリート120の上部を、路床材130で埋戻すため、坑口部100より上部をすべて、貧配合コンクリート120で埋め戻す場合に比べて、安価で構築することができる。   Furthermore, in the backfilling step (step s9), the upper portion of the poor blended concrete 120 that has been backfilled is backfilled with the roadbed material 130, so that all the upper part from the wellhead portion 100 is backfilled with the poor blended concrete 120. And can be constructed at low cost.

詳述すると、一般的に、土被りの小さな坑口部100には土被り全部の土圧が作用するが、上部の所定高さ分を埋め戻した貧配合コンクリート120が硬化したあとは、埋め戻した貧配合コンクリート120の上部を路床材130で埋め戻しても坑口部100に埋め戻した路床材130による土圧は作用しないため、埋戻し土に比べて安価な路床材130を貧配合コンクリート120の上部に埋め戻すことで、上載される埋戻し土量に対して要する剛性を低減できる坑口部100を効率よく、さらに経済的に構築できる。   More specifically, in general, the earth pressure of the entire earth covering acts on the well opening portion 100 with a small earth covering, but after the poor blended concrete 120 that has filled up the predetermined height of the upper part is hardened, it is refilled. Even if the upper portion of the poor blended concrete 120 is backfilled with the roadbed material 130, the earth pressure due to the roadbed material 130 backfilled in the wellhead portion 100 does not act. By backfilling the upper part of the blended concrete 120, the wellhead 100 that can reduce the rigidity required for the amount of backfilled soil can be efficiently and more economically constructed.

また、通常、いわゆる緩み土圧という所定高さ分の土圧のみが作用するとされている掘削トンネルに対して、明かりで施工され、上載する全土圧が作用する坑口部100は、掘削トンネルより高剛性なトンネル構造が必要となることが多いが、上述の施工方法により、剛性を低減できる構造とすることができ、さらに経済的なトンネル構造物を構築することができる。   Moreover, the wellhead portion 100 where the entire earth pressure is applied to the excavation tunnel, which is constructed with light, is usually higher than the excavation tunnel. Although a rigid tunnel structure is often required, the construction method described above can provide a structure that can reduce rigidity, and a more economical tunnel structure can be constructed.

さらにまた、トンネル構築箇所を、埋め戻した上部を通行体が通行する通行路が構築される交差通行路300とするため、例えば、すべてを路床材130で埋め戻す場合に比べて、経年的な圧密によって生じる圧密沈下等の不具合が生じるおそれがなく、安全性の高い通行路を構成することができる。   Furthermore, since the tunnel construction place is the crossing passage 300 in which the passage through which the vehicle passes through is refilled, for example, as compared with the case where everything is backfilled with the roadbed material 130, Therefore, there is no risk of problems such as consolidation settlement caused by compact consolidation, and a highly safe passage can be configured.

この発明の構成と、上述の実施例との対応において、トンネル構造物及び坑口は、坑口部100に対応し、
以下同様に、
トンネル構築箇所は、交差トンネル1の坑口部100に対応し、
貧配合埋戻し材は、貧配合コンクリート120に対応し、
支保工程は、ステップs3及びステップs4に対応し、
内梁設置工程は、ステップs6に対応し、
埋戻し工程は、ステップs9に対応し、
内梁撤去工程は、ステップs12に対応し、
インバート工程は、ステップs14に対応し、
埋戻し土砂は、路床材130に対応し、
掘削トンネルは、交差トンネル1の本体に対応し、
坑門工は、ステップs8に対応し、
通行路交差部は、交差通行路300に対応するも、
この発明は、上述の実施形態の構成のみに限定されるものではなく、多くの実施の形態を得ることができる。
In the correspondence between the configuration of the present invention and the above-described embodiment, the tunnel structure and the wellhead correspond to the wellhead portion 100,
Similarly,
The tunnel construction point corresponds to the wellhead part 100 of the crossing tunnel 1,
The poor blend backfill material corresponds to the poor blend concrete 120,
The support process corresponds to step s3 and step s4,
The inner beam installation process corresponds to step s6,
The backfill process corresponds to step s9,
The inner beam removal process corresponds to step s12,
The invert process corresponds to step s14,
The backfill earth and sand correspond to the roadbed material 130,
The excavation tunnel corresponds to the body of the crossing tunnel 1,
The tunnel worker corresponds to step s8,
The crossing part of the road corresponds to the crossing road 300,
The present invention is not limited only to the configuration of the above-described embodiment, and many embodiments can be obtained.

例えば、上述の坑口部100は、トンネル軸方向Tに所定間隔を隔てて複数支保工20を配置するとともに、断面内側を場所打ちコンクリートなどの覆工材50で覆工したが、セグメントやコンクリートBOXなどの閉断面構造物を組み付けて構成してもよい。また、覆工材50及びインバート60は、場所打ちコンクリートのみならず、コンクリート加工品、鋼製、あるいは樹脂製など適宜の材質で構成してもよい。なお、支保工20もアーチ状(馬蹄形)のみならず、円形、楕円形、矩形など様々な断面であってもよい。さらには多連トンネル構造であってもよい。   For example, the above-described wellhead portion 100 has a plurality of supporters 20 arranged at predetermined intervals in the tunnel axis direction T, and the inside of the cross section is covered with a covering material 50 such as cast-in-place concrete. A closed cross-section structure such as the above may be assembled. Further, the lining material 50 and the invert 60 may be made of an appropriate material such as a cast-in-place concrete, a steel product, a resin, or a resin. The support 20 is not limited to an arch (horse-shoe), but may have various cross sections such as a circle, an ellipse, and a rectangle. Furthermore, a multiple tunnel structure may be used.

なお、貧配合コンクリート120を構成するために配合する固化材は、例えば、セメント系固化材のみならず、消石灰や生石灰などの石灰系固化材や液状の固化材など、用途や施工条件あるいは対象となる土質等に応じた適宜の固化材とすることができる。   In addition, the solidification material mix | blended in order to comprise the poor mixing | blending concrete 120 is not only a cement-type solidification material but lime-type solidification materials, such as slaked lime and quicklime, and a liquid solidification material, use, construction conditions, or object. It can be set as an appropriate solidifying material according to the soil quality.

1…交差トンネル
20…支保工
22…内梁
30…外側覆工枠
50…覆工材
60…インバート
100…坑口部
110…坑門
120…貧配合コンクリート
300…交差通行路
T…トンネル軸方向
DESCRIPTION OF SYMBOLS 1 ... Crossing tunnel 20 ... Supporting work 22 ... Inner beam 30 ... Outer lining frame 50 ... Covering material 60 ... Invert 100 ... Wellhead part 110 ... Tunnel 120 ... Poor compounding concrete 300 ... Crossing road T ... Tunnel axial direction

Claims (12)

トンネル構築箇所に設置したトンネル構造物の上部を埋め戻してトンネルを構築するトンネルの構築方法であって、
前記トンネル構造物の少なくとも上半部分を構築してから、
該上半部分の上部を、貧配合の貧配合埋戻し材で埋戻して構築する
トンネルの構築方法。
A tunnel construction method in which a tunnel is constructed by refilling the upper part of a tunnel structure installed at a tunnel construction site,
After building at least the upper half of the tunnel structure,
A tunnel construction method in which the upper part of the upper half is backfilled with a poorly blended poorly blended backfill material.
前記トンネル構造物を、
上向きに凸なアーチ状の支保工をトンネル軸方向に所定間隔を隔てて設置し、トンネル断面の少なくとも内側上半部分を覆工材で覆工するとともに、前記トンネル断面の下部にインバートを形成して構築する構造とするとともに、
前記トンネル構築箇所に、前記支保工を設置する支保工程と、
設置した前記支保工の外側に外側覆工枠を設置する外側覆工枠設置工程と、
前記支保工の下端部同士の間に、前記支保工を断面閉合するように内梁を設置する内梁設置工程と、
前記外側覆工枠の上部を、前記貧配合埋戻し材で埋戻す埋戻し工程と、
前記貧配合埋戻し材の硬化後、前記内梁を撤去する内梁撤去工程と、
前記トンネル断面の下部にインバートを形成するインバート工程とを、
この順で行う
請求項1に記載のトンネルの構築方法。
The tunnel structure,
An upward arch-shaped support is installed at a predetermined interval in the tunnel axis direction, and at least the inner upper half of the tunnel cross section is covered with a covering material, and an invert is formed at the lower part of the tunnel cross section. And build a structure
A support process for installing the support work at the tunnel construction site;
An outer lining frame installation step of installing an outer lining frame on the outer side of the installed support;
An inner beam installation step of installing an inner beam between the lower ends of the support works so as to close the cross section of the support work;
A backfilling step of backfilling the upper part of the outer lining frame with the poor compounding backfilling material;
After curing the poor compounding backfill material, an inner beam removal step of removing the inner beam,
An inversion step of forming an invert at a lower portion of the tunnel cross section,
The tunnel construction method according to claim 1, which is performed in this order.
前記トンネル断面を計測するとともに、
前記埋戻し工程、前記内梁撤去工程、及び前記インバート工程における各工程の変位が予め設定した管理基準値内である場合、次工程を行う
請求項2に記載のトンネルの構築方法。
While measuring the tunnel cross section,
The tunnel construction method according to claim 2, wherein when the displacement in each step in the backfilling step, the inner beam removing step, and the inverting step is within a preset management reference value, the next step is performed.
前記埋戻し工程において、
埋め戻した前記貧配合埋戻し材の上部を、埋戻し土砂で埋戻す
請求項2または3に記載のトンネルの構築方法。
In the backfilling step,
The tunnel construction method according to claim 2 or 3, wherein the upper portion of the poor-mixed backfill material that has been backfilled is backfilled with backfill earth and sand.
前記トンネル構築箇所を、掘削して構築する掘削トンネルの坑口とするとともに、
坑門を構築する坑門工を行う
請求項2乃至4のうちいずれかに記載のトンネルの構築方法。
While making the tunnel construction site a digging tunnel tunnel to be constructed by excavation,
The tunnel construction method according to any one of claims 2 to 4, wherein a tunnel is constructed to construct a tunnel.
前記トンネル構築箇所を、
埋め戻した上部を通行体が通行する通行路が構築される通行路交差部とした
請求項1乃至4のうちいずれかに記載のトンネルの構築方法。
The tunnel construction point is
The tunnel construction method according to any one of claims 1 to 4, wherein a passage crossing portion is constructed in which a passage through which a passing body passes is refilled.
トンネル構築箇所に設置したトンネル構造物の上部を埋め戻してトンネルを構築するトンネル構造物であって、
前記トンネル構造物の少なくとも上半部分を構築してから、
該上半部分の上部を、貧配合の貧配合埋戻し材で埋戻して構築した
トンネル構造物。
A tunnel structure in which a tunnel is constructed by backfilling the upper part of the tunnel structure installed at the tunnel construction site,
After building at least the upper half of the tunnel structure,
A tunnel structure constructed by backfilling the upper part of the upper half portion with a poorly blended poorly blended backfill material.
前記トンネル構造物を、トンネル軸方向に所定間隔を隔てて設置した、上向きに凸なアーチ状の支保工と、トンネル断面の少なくとも内側上半部分を覆工する覆工材と、前記トンネル断面の下部に形成するインバートとで構成し、
前記トンネル構築箇所に、前記支保工を設置し、設置した前記支保工の外側に外側覆工枠を設置するとともに、前記トンネル軸方向における前記支保工同士の間に前記吹付材を吹き付け、前記支保工の下端部同士の間に、前記支保工を断面閉合するように設置した内梁を、前記外側覆工枠の上部を埋め戻した貧配合の貧配合埋戻し材の硬化後に撤去するとともに、前記トンネル断面の下部にインバートを形成した
請求項7に記載のトンネル構造物。
The tunnel structure is installed at a predetermined interval in the tunnel axial direction, and has an upwardly projecting arch-shaped support, a covering material that covers at least the inner upper half of the tunnel cross section, and the tunnel cross section It consists of inverts formed at the bottom,
The support construction is installed at the tunnel construction site, an outer lining frame is installed outside the installed support construction, and the spray material is sprayed between the support works in the tunnel axial direction. While removing the inner beam installed so as to close the cross section of the support work between the lower ends of the work, after curing the poor compounded poor backfill material that backfilled the upper part of the outer lining frame, The tunnel structure according to claim 7, wherein an invert is formed at a lower portion of the tunnel cross section.
前記トンネル断面を計測するとともに、
前記埋戻し工程、前記内梁撤去工程、及び前記インバート工程における各工程の変位が予め設定した管理基準値内であることを確認してから、次工程を行った
請求項8に記載のトンネル構造物。
While measuring the tunnel cross section,
The tunnel structure according to claim 8, wherein the next step is performed after confirming that the displacement of each step in the backfilling step, the inner beam removing step, and the inverting step is within a preset management reference value. object.
埋め戻した前記貧配合埋戻し材の上部を、埋戻し土砂で埋戻した
請求項8または9に記載のトンネル構造物。
The tunnel structure according to claim 8 or 9, wherein an upper part of the poor-mixed backfill material backfilled is backfilled with backfill earth and sand.
前記トンネル構築箇所を、掘削して構築する掘削トンネルの坑口とするとともに、
前記インバートを覆工した後に、坑門を構築した
請求項8乃至10のうちいずれかに記載のトンネル構造物。
While making the tunnel construction site a digging tunnel tunnel to be constructed by excavation,
The tunnel structure according to any one of claims 8 to 10, wherein a tunnel is constructed after lining the invert.
前記トンネル構築箇所を、
埋め戻した上部を通行体が通行する通行路が構築される通行路交差部とした
請求項7乃至11のうちいずれかに記載のトンネル構造物。
The tunnel construction point is
The tunnel structure according to any one of claims 7 to 11, which is a road crossing portion in which a road through which a passing body passes is refilled.
JP2013151465A 2013-07-22 2013-07-22 Tunnel construction method and tunnel structure Pending JP2015021322A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013151465A JP2015021322A (en) 2013-07-22 2013-07-22 Tunnel construction method and tunnel structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013151465A JP2015021322A (en) 2013-07-22 2013-07-22 Tunnel construction method and tunnel structure

Publications (1)

Publication Number Publication Date
JP2015021322A true JP2015021322A (en) 2015-02-02

Family

ID=52486011

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013151465A Pending JP2015021322A (en) 2013-07-22 2013-07-22 Tunnel construction method and tunnel structure

Country Status (1)

Country Link
JP (1) JP2015021322A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018012962A (en) * 2016-07-20 2018-01-25 ヤマグチ株式会社 Tunnel structure having arch culvert installed therein, and construction method for the same
JP2018053449A (en) * 2016-09-26 2018-04-05 清水建設株式会社 Construction method for spray lining concrete
CN110905547A (en) * 2019-12-17 2020-03-24 中铁二局集团有限公司 Small-spacing three-dimensional tunnel group structure, structure and construction method thereof
CN115306424A (en) * 2022-08-29 2022-11-08 中国建筑第二工程局有限公司 Large-section transverse passage ingate breaking operation platform and construction method
KR102608230B1 (en) * 2022-07-01 2023-11-30 (주)골든엔지니어링 Undergroud structure in embankment and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5952094A (en) * 1982-09-14 1984-03-26 株式会社竹中工務店 Method of measuring and controlling upper section of spray concrete covering work and excavating forward ground propertyin tunnel construction by method of natomu construction
JPS6114399A (en) * 1984-06-28 1986-01-22 三井建設株式会社 Construction of timbering in shield construction method
JPH06137084A (en) * 1990-12-14 1994-05-17 Toyama Pref Gov Contruction method of tunnel opening
JPH07150898A (en) * 1993-12-01 1995-06-13 Ishikawajima Constr Materials Co Ltd Method for constructing tunnel using precast concrete panel
JPH11323974A (en) * 1998-05-19 1999-11-26 Taisei Corp How to build a tunnel
JP2002115495A (en) * 2000-10-10 2002-04-19 Ishikawajima Constr Materials Co Ltd Arch-tunnel bottom slab and its construction method
JP2010121404A (en) * 2008-11-21 2010-06-03 West Nippon Expressway Co Ltd Construction method of multiple tunnel and structure of multiple tunnel

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5952094A (en) * 1982-09-14 1984-03-26 株式会社竹中工務店 Method of measuring and controlling upper section of spray concrete covering work and excavating forward ground propertyin tunnel construction by method of natomu construction
JPS6114399A (en) * 1984-06-28 1986-01-22 三井建設株式会社 Construction of timbering in shield construction method
JPH06137084A (en) * 1990-12-14 1994-05-17 Toyama Pref Gov Contruction method of tunnel opening
JPH07150898A (en) * 1993-12-01 1995-06-13 Ishikawajima Constr Materials Co Ltd Method for constructing tunnel using precast concrete panel
JPH11323974A (en) * 1998-05-19 1999-11-26 Taisei Corp How to build a tunnel
JP2002115495A (en) * 2000-10-10 2002-04-19 Ishikawajima Constr Materials Co Ltd Arch-tunnel bottom slab and its construction method
JP2010121404A (en) * 2008-11-21 2010-06-03 West Nippon Expressway Co Ltd Construction method of multiple tunnel and structure of multiple tunnel

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018012962A (en) * 2016-07-20 2018-01-25 ヤマグチ株式会社 Tunnel structure having arch culvert installed therein, and construction method for the same
JP2018053449A (en) * 2016-09-26 2018-04-05 清水建設株式会社 Construction method for spray lining concrete
CN110905547A (en) * 2019-12-17 2020-03-24 中铁二局集团有限公司 Small-spacing three-dimensional tunnel group structure, structure and construction method thereof
KR102608230B1 (en) * 2022-07-01 2023-11-30 (주)골든엔지니어링 Undergroud structure in embankment and construction method thereof
CN115306424A (en) * 2022-08-29 2022-11-08 中国建筑第二工程局有限公司 Large-section transverse passage ingate breaking operation platform and construction method

Similar Documents

Publication Publication Date Title
CN108412501B (en) Under wear oil pipeline shallow depth loess tunnels construction method
CN102996148A (en) A Supporting Method for High Ground Stress Soft Rock Highway Tunnel
JP2015021322A (en) Tunnel construction method and tunnel structure
CN107130608B (en) Without concrete to the basement construction method for supporting of support
KR101536209B1 (en) Steel Pipe Multi Step Grouting device Open and cut and NATM complex excavation tunnel construction method
JP2014530972A5 (en)
JP2017089104A (en) Construction structure and construction method of tunnel lining body
CN107675704A (en) A kind of artificial digging pile assembled retaining wall and its construction technology
CN102966048B (en) Reinforcing method for increasing bearing force of spandrel-filled arch bridge
KR20120079987A (en) Method of pre-support tunneling reinforced by in-situ soil mixed with cement
Wilmers Restoration of masonry arch bridges
KR101038945B1 (en) Lining with cavity top cavity filling structure
KR101372182B1 (en) Pre-support tunneling reinforced by in-situ soil mixed with cement
KR20190072213A (en) Method Of Ground Half-Openning For Tunnel Excavation
KR102778342B1 (en) Construction method for tunnel of slope
KR102608230B1 (en) Undergroud structure in embankment and construction method thereof
CN114251051B (en) Subway tunnel construction technology
KR100898812B1 (en) Arch tunnel construction method
JP5073960B2 (en) Construction method of underground structure and underground structure
KR101234270B1 (en) Method for non excavated excavating construction using steel pipe and steel pipe with hole
CN108149707A (en) A kind of basement building structure and its construction method
JP2004225453A (en) Construction method of civil engineering structure
CN207891910U (en) A kind of basement building structure
JP2017206882A (en) Method of constructing underground structure
JP2018012962A (en) Tunnel structure having arch culvert installed therein, and construction method for the same

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20160622

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20170425

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20170502

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20171219