JP2008111240A - Method of constructing underground wall - Google Patents
Method of constructing underground wall Download PDFInfo
- Publication number
- JP2008111240A JP2008111240A JP2006293678A JP2006293678A JP2008111240A JP 2008111240 A JP2008111240 A JP 2008111240A JP 2006293678 A JP2006293678 A JP 2006293678A JP 2006293678 A JP2006293678 A JP 2006293678A JP 2008111240 A JP2008111240 A JP 2008111240A
- Authority
- JP
- Japan
- Prior art keywords
- drilling
- excavation
- underground wall
- hole
- excavator
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
本発明は、ソイルセメント連続壁など止水性能を有する地中壁の施工法に関するものである。 The present invention relates to a method for constructing underground walls having water-stopping performance such as soil cement continuous walls.
ソイルセメント連続地中壁は、アースオーガによる掘削時に、掘削土とセメントミルク等の硬化材とを攪拌してソイルセメントの柱体を地中に製作するが、かかる柱を重ね合わせた柱列壁を施工してなるものである。このような地中壁の施工法に関する技術は、以下の特許文献を含め、種種のものが提案されている。
図3にかかるソイルセメント連続壁を施工するための従来の掘削工法を示すと、図中1はオーガで、これは周知のごとく、油圧モータ等の駆動装置2により回転駆動されるスクリュー掘削軸3の先端を掘削ヘッド4とし、この掘削軸3の内部を通過するセメントミルク等の硬化材を掘削ヘッド4から注入できるようにしている。なお、図示は省略するが、駆動装置2はベースマシンのリーダマストから昇降自在に吊り下げられ、また、掘削軸3は適宜継ぎ足して長尺とすることができる。また、掘削軸3のスクリューは不連続のものでもよい。
A conventional excavation method for constructing a soil cement continuous wall according to FIG. 3 shows an auger 1, which is a
順次行われる工程を説明すると、まず、オーガ1の位置決めを行い(A)、オーガ1の掘削軸3の掘削ヘッド4を正転させ、削孔を開始する。その際、センメントミルク等の硬化材5とエアーを掘削ヘッド4から出して孔内に注入する(B)。
The sequential steps will be described. First, the auger 1 is positioned (A), the
このように正転しながら所定深さまで注入、削孔を継続したならば(C)(D)、引き上げを開始し、その際も硬化材5を注入する。この引き上げは正転と逆転を交互に繰り返す、正転・逆転による(E)。 If the injection and drilling are continued to the predetermined depth while rotating forward in this way (C) (D), the pulling up is started, and the hardening material 5 is also injected at that time. This pulling is by forward / reverse rotation (E) in which forward rotation and reverse rotation are alternately repeated.
ある程度引き上げたならば、再度、正転・逆転で掘削および攪拌を行い(F)、最後に逆転しながら引き上げを行う(G)。 If it is pulled up to a certain extent, excavation and agitation are performed again in the normal rotation and reverse rotation (F), and finally, the rotation is performed while rotating in the reverse rotation (G).
このようにしてソイルセメントによる連続地中壁を施工するには、オーガ1として単軸掘削機を使用する場合は、図4に示すように一本置きの間隔を存して先に掘削を行い、その後にこの掘削孔間を掘削する方法と、図5に示すように一本一本順次端から重ね合わせながらつなげて行く方法とがあり、さらに、図6に示すように多軸掘削機でも同様に一ユニット(多軸の場合はその軸数の連続した孔が形成される)置きの間隔を存して先に掘削を行い、その後にこの掘削孔間を掘削する方法と、図示は省略するが一ユニットずつ順次端から重ね合わせながら掘削孔をつなげて行く方法とがある。 In order to construct a continuous underground wall using soil cement in this way, when a single-axis excavator is used as the auger 1, excavation is performed first at intervals of every other as shown in FIG. Then, there are a method of excavating between the excavation holes and a method of connecting them one by one while sequentially overlapping them as shown in FIG. 5, and further, even with a multi-axis excavator as shown in FIG. Similarly, excavation is performed first with a gap of one unit (in the case of multiple axes, the number of continuous holes are formed), and then the method of drilling between these drill holes and illustration is omitted. However, there is a method of connecting excavation holes one unit at a time from the end.
ところで、図4および図5に示すように、単軸掘削機で削孔する場合、一度に1本の掘削孔しか形成することができず、その分、工期が長引き、作業効率が悪いという問題がある。また、多軸掘削機が複数本の掘削軸を連結して、掘削時に掘削軸相互のずれが起き難く、削孔方向が安定するのに対して、単軸掘削機は掘削時に軸がずれ易いという問題もある。このため、単軸掘削機により地中壁を造成すると、壁面が不揃いとなり、場合によっては掘削孔同士が非連続となり連続した地中壁が得られない可能性もある。 By the way, as shown in FIGS. 4 and 5, when drilling with a single-axis excavator, only one excavation hole can be formed at a time, and the work period is prolonged and work efficiency is poor. There is. In addition, the multi-axis excavator connects multiple excavation shafts so that the excavation shafts do not easily deviate from each other during excavation and the drilling direction is stable, whereas the single-axis excavator tends to deviate during excavation. There is also a problem. For this reason, when the underground wall is created by a single-axis excavator, the wall surfaces become uneven, and in some cases, the excavation holes are discontinuous and a continuous underground wall may not be obtained.
一方、多軸掘削機を使用した場合には、複数本の掘削軸が連結されているため、前記の通り掘削時に掘削軸相互のずれが起き難く、削孔方向が安定して壁面の揃った連続地中壁が造成可能であり、更に、一度に複数の連続削孔が可能となり、作業効率が良く工期を短縮できるという利点がある。 On the other hand, when a multi-axis excavator is used, since a plurality of excavation shafts are connected, it is difficult for the excavation shafts to deviate from each other during excavation, and the drilling direction is stable and the walls are aligned. There is an advantage that a continuous underground wall can be created, and a plurality of continuous drilling holes can be made at a time, so that work efficiency is improved and a construction period can be shortened.
一般的な多軸掘削機の構成を図9および図10に示す。多軸掘削機は、油圧モータおよび減速機からなる駆動機構14に掘削軸3を下方に向けて連結してなり、かつ、この掘削軸3は複数本(図示では5本)並列させ、ロッドを振れ止めのための結束バンド19で結束した。
The structure of a general multi-axis excavator is shown in FIG. 9 and FIG. In the multi-axis excavator, the
掘削軸3は先端に掘削ヘッド4を設け、また、途中に断続するスクリュー羽根による攪拌翼兼用の掘削翼3aを設けたものである。また、図示は省略するが、この掘削軸3は中空軸で内部にセメントミルク等の固結液を流通させ、これを掘削ヘッド4の吐出口より注出できる。
The
前記駆動機構14は、掘削軸3を連結した状態で、クローラ等のベースマシン11に起立するリーダーマスト12のトップシーブ13からワイヤーで吊り支する。さらに、駆動機構14は背面に設けた湾曲ブラケット16をリーダーマスト12に沿設したリーダー17に係合させる。図中18はリーダーマスト12の下端に設けた首かせ状の振れ止めで、掘削軸3が上下に貫通する。
The
なお、各掘削軸3による掘削孔同士を連続させるため、各掘削軸3は、隣接する各掘削軸3の掘削範囲が互いに部分的に重なり合うように並列配置されるが、互いの掘削ヘッド4がぶつからないよう、各掘削軸3は掘削方向の前後互い違いに配置される。
In order to make the excavation holes by the
また、連続地中壁を造成するためには、多軸掘削機の一度の削孔で形成される連続掘削孔の各ユニットの両端を繋げる必要があり、そのためには先に作成された連続掘削孔の端に、並列する掘削軸3の端を合わせてから次の掘削を行わなければならないため、並列する掘削軸3のうち、両サイドに位置する掘削軸3は掘削方向前方に配置され、位置合わせを容易としている。
In addition, in order to create a continuous underground wall, it is necessary to connect both ends of each unit of a continuous drilling hole formed by a single drilling hole of a multi-axis excavator. Since it is necessary to perform the next excavation after aligning the end of the
このように、複数本の掘削軸3を一直線上に並列し、これを結束バンド19により互いに結束固定する構成により、多軸掘削機は一度の掘削で、掘削軸の本数分だけの揃った連続掘削孔を形成することができる。
In this way, by arranging a plurality of
しかし、多軸掘削機は削孔時の削孔方向が比較的安定すると言えども、硬質地盤など、地盤から受ける抵抗があまりにも大きい場合には、削孔位置および削孔方向がずれやすくなってしまう。 However, even though the multi-axis excavator is relatively stable in drilling direction when drilling, if the resistance from the ground such as hard ground is too great, the drilling position and drilling direction are likely to shift. End up.
これを回避するため、例えば図7に示すように、多軸掘削機による削孔(以下、本削孔)に先だって、多軸掘削機の掘削軸と同径の掘削軸を備える単軸掘削機による削孔(以下、先行削孔)を行い、これをガイドとして本削孔を行うとすると、前記の通り単軸掘削機の掘削軸は多軸掘削機の掘削軸に比べて削孔時に軸がぶれ易いため、先行掘削孔6の地下での削孔箇所が地表の削孔箇所からずれ、その結果、地表では本削孔の削孔予定箇所に合わせて削孔したつもりでも、地下ではその範囲からずれてしまうという問題がある。
In order to avoid this, for example, as shown in FIG. 7, a single-axis excavator provided with an excavation shaft having the same diameter as the excavation shaft of the multi-axis excavator prior to the drilling by the multi-axis excavator (hereinafter referred to as main drilling). If drilling is performed by using this as a guide and the main drilling is performed as described above, the drilling shaft of the single-axis excavator is pivoted at the time of drilling compared to the drilling shaft of the multi-axis excavator as described above. Since the drilling site in the basement of the preceding
そして、本削孔による掘削孔内にソイルセメントによる地中壁7を造成しても、本削孔の削孔箇所からはみ出した部分の先行掘削孔6にはソイルセメントが十分に行き渡らず固結が不充分となり、強度不足の緩い削孔体が残留箇所6aとして残ってしまう。そしてその部分が水みちとなり、地中壁7の下側から被圧水が噴出し、遮水効果が期待できない可能性がある。
And even if the
また、地中壁7を土留壁とする場合には、本来土留壁は地山に密着して背面側(主働側、図中下側)の土圧に抵抗するものであるが、土留壁内側(受働側、図中上側)に先行削孔時の緩い削孔体が残置された状態で掘削工事を行った場合には、地中壁7の一部が工事の振動により強度不足の緩い残留箇所6aに向かって移動してしまい、その部分の地中壁7にクラック9が発生して破損し、そこから土留背面側の地下水が噴出することが想定される。
In addition, when the
更に、先行削孔を1本だけ行ったのでは、本削孔において多軸掘削機の掘削軸のうち1本の掘削軸を先行掘削孔6に挿入しても、それを中心として、複数の掘削軸全体が回転方向に位置ずれする可能性もあり、削孔位置を位置決めするガイドしても不充分である。
Further, if only one preceding drilling hole is made, even if one drilling shaft of the drilling shaft of the multi-axis excavator is inserted into the preceding
また、多軸掘削機は同時に複数本の掘削軸を使用して削孔する分、削孔時に地盤から受ける抵抗も大きくなり、特に硬質地盤を削孔する場合には掘削軸に大きな負荷がかかるため、削孔作業が難航する場合がある。 In addition, the multi-axis excavator drills using multiple drilling shafts at the same time, so the resistance received from the ground during drilling increases. Especially when drilling hard ground, a heavy load is applied to the drilling shaft. Therefore, the drilling operation may be difficult.
本発明は前記従来例の不都合を解消し、硬質地盤においても削孔位置および削孔方向を安定させ、多軸掘削機による削孔の負荷を軽減して施工作業全体を順調に進めることができ、且つ、被圧水の噴出や地中壁の破損を招く原因となる強度不足の部分を生じさせることのない地中壁の施工法を提供することを目的とする。 The present invention eliminates the inconveniences of the conventional example, stabilizes the drilling position and drilling direction even on hard ground, reduces the drilling load by the multi-axis excavator, and allows the entire construction work to proceed smoothly. And it aims at providing the construction method of the underground wall which does not produce the part of insufficient intensity | strength causing the ejection of pressurized water and the breakage of an underground wall.
前記目的を達成するため本発明の地中壁の施工法は、第1に、複数の掘削軸を掘削方向の前後互い違いに設けるとともに、両サイドの掘削軸を掘削方向前方に配置する多軸掘削機の削孔径より小さな削孔径の単軸掘削機により、多軸掘削機の掘削軸の隔軸毎の本削孔予定箇所を先行削孔した後、この先行掘削孔に多軸掘削機の両サイドの掘削軸を挿入して本削孔を行い、これを繰り返して全掘削孔を連続させるとともに、掘削孔内にソイルセメント等による地中壁を造成すること、第2に、先行掘削孔に、水にセメントやベントナイトを混合する注入液を注入することを要旨とするものである。 In order to achieve the above object, the underground wall construction method of the present invention is, firstly, a multi-axis excavation in which a plurality of excavation shafts are provided alternately in the front and rear in the excavation direction, and the excavation shafts on both sides are arranged in front of the excavation direction. Using the single-axis drilling machine with a drilling diameter smaller than the drilling diameter of the machine, after pre-drilling the planned drilling site for each separated axis of the drilling shaft of the multi-axis drilling machine, The main drilling hole is inserted by inserting the side drilling shaft, and this is repeated to make all the drilling holes continuous, and the underground wall with soil cement or the like is created in the drilling hole. The gist of the present invention is to inject an injection solution in which cement or bentonite is mixed with water.
請求項1記載の本発明によれば、先行掘削孔に多軸掘削機の両サイドの掘削軸を挿入して掘削するから、本削孔時には、両サイドの掘削軸が挿入される少なくとも2本の先行掘削孔がガイドとなり、並列する掘削軸が回転方向にずれることがなく、本削孔の削孔位置および削孔方向を効果的に安定させることができる。 According to the first aspect of the present invention, since excavation is performed by inserting the excavation shafts on both sides of the multi-axis excavator into the preceding excavation hole, at least two of the excavation shafts on both sides are inserted during the main drilling. The preceding excavation hole serves as a guide, and the excavation shafts arranged in parallel do not shift in the rotation direction, and the drilling position and direction of the main drilling hole can be effectively stabilized.
そして、本削孔時には、掘削方向前方に位置する両サイドの掘削軸を先行掘削孔に挿入することにより、多軸掘削機に比べて削孔時の負荷が少ない単軸掘削機の先行削孔により緩められた地盤を削孔するから、硬質地盤を削孔する場合であっても、本削孔時に多軸掘削機に加わる負荷を効果的に軽減して、削孔作業をスムーズに行うことができる。 And at the time of drilling, by inserting the drilling shafts on both sides located in front of the drilling direction into the preceding drilling hole, the leading drilling of the single-axis drilling machine with less load when drilling compared to the multi-axis drilling machine Since the ground that has been loosened by drilling is drilled, even when drilling hard ground, the load applied to the multi-axis excavator can be effectively reduced during drilling, and the drilling operation can be performed smoothly. Can do.
すなわち、本削孔時において、多軸掘削機の掘削軸のうち、掘削方向前方に配置される掘削軸が削孔する際には、先行削孔により既に緩められた掘削孔の周りを拡大するようにして掘り進むから、掘削軸にかかる負荷を軽減することができる。更に、それに続いて掘削方向後方の掘削軸が削孔する際には、その削孔範囲は掘削方向前方に配置される掘削軸により先に削孔して緩められた削孔範囲と部分的に重なるため、やはり掘削軸にかかる負荷を軽減することができ、本掘削時の負荷全体を効果的に軽減することができる。 In other words, during drilling, when the drilling shaft arranged in front of the drilling direction among the drilling shafts of the multi-axis excavator drills, the area around the drilling hole already loosened by the preceding drilling is expanded. Thus, since the digging proceeds, the load on the excavation shaft can be reduced. Further, when the drilling shaft behind the excavation direction is subsequently drilled, the drilling range is partially the same as the drilling range loosened by drilling first by the drilling shaft arranged in front of the excavation direction. Since they overlap, the load applied to the excavation shaft can be reduced, and the entire load during the main excavation can be effectively reduced.
更に、先行削孔の削孔径を小さくした分、先行削孔時に掘削軸にかかる負荷も軽減でき、先行削孔自体もスムーズに行うことができる。また、多軸掘削機の全掘削軸の削孔予定箇所を先行掘削してしまうと、先行削孔に要する労力が多大となり、作業効率が良くないが、先行削孔の削孔箇所を多軸掘削機の削孔予定箇所の隔軸毎としたから、先行削孔に要する労力を必要最小限として、全体としての作業効率は良好となる。そしてこれらの相乗効果により、施工作業全体を順調に進めることができる。 Furthermore, the load applied to the excavation shaft during the preceding drilling can be reduced by reducing the diameter of the preceding drilling hole, and the preceding drilling itself can be performed smoothly. In addition, if the pre-drilling of all drilling shafts in a multi-axis excavator is performed in advance, the labor required for the previous drilling becomes large and the work efficiency is not good. Since it is set for every separated axis of the planned drilling portion of the excavator, the work efficiency as a whole is improved by minimizing the labor required for the preceding drilling. And by these synergistic effects, the whole construction work can proceed smoothly.
そして、先行削孔の削孔径を本削孔の削孔径より小さくしたので、例え先行削孔時に少し軸がぶれても、先行削孔の範囲が本掘削の削孔範囲からはみ出してしまうことが無く、はみだし部分が強度不足の緩い削孔体として残ることによる被圧水の噴出や地中壁の破損を招くことがない。 And since the drilling diameter of the preceding drilling hole is smaller than the drilling diameter of the main drilling hole, even if the shaft is slightly deviated during the preceding drilling, the range of the preceding drilling may protrude from the drilling range of the main drilling. In addition, the protruding portion remains as a loose drilling body with insufficient strength, so that the blowout of pressurized water and the breakage of the underground wall are not caused.
請求項2記載の本発明によれば、先行削孔による掘削土は注入液と混ざることにより流動性が増し、これにより先行削孔時の負荷を軽減することができるとともに、その後に行われる本削孔およびセメントミルク等の固結材と掘削土との混合によるソイルセメント体の形成をスムーズに行うことができる。 According to the second aspect of the present invention, the excavated soil by the preceding drilling hole is mixed with the injection liquid to increase the fluidity, thereby reducing the load at the time of the preceding drilling, and the book to be performed thereafter. A soil cement body can be formed smoothly by mixing a caking material such as drilling holes and cement milk with excavated soil.
また、本掘削の前に注入液が固まらないよう、注入液に含まれるセメント量を少なく抑えた場合、注入液と掘削土との混合物の固結により得られる部分の強度は、地中壁などの構造物を構成するに足るものではないが、先行削孔の範囲は本掘削の範囲からはみ出ることがないから、強度不足の緩い部分が残ってしまうことがない。 In addition, when the amount of cement contained in the injected solution is kept low so that the injected solution does not solidify before the main excavation, the strength of the part obtained by consolidation of the mixture of the injected solution and the excavated soil is However, since the range of the preceding drilling hole does not protrude from the range of the main excavation, a loose part with insufficient strength does not remain.
なお、先行削孔の削孔径を小さくした分、注入液の使用量を抑えることができるとともに、更に、削孔時に排出される注入液と掘削土との混合攪拌泥土の排出量も抑えることができるから、周辺環境にかかる負荷を抑え、混合攪拌泥土を産業廃棄物として処分するために必要な費用も抑えることもできる。 In addition, the amount of injected liquid used can be reduced by reducing the diameter of the preceding hole, and the amount of mixed agitation mud discharged between the injected liquid and excavated soil discharged during drilling can also be reduced. Therefore, the load on the surrounding environment can be suppressed, and the cost required to dispose of the mixed stirred mud as industrial waste can also be reduced.
以上述べたように本発明の地中壁の施工法は、硬質地盤においても多軸掘削機による削孔の負荷を軽減して施工作業全体を順調に進めることができ、削孔位置および削孔方向を安定させ、且つ、被圧水の噴出や地中壁の破損を招く原因となる強度不足の部分を生じさせることがない。 As described above, the underground wall construction method of the present invention reduces the load of drilling by a multi-axis excavator even on hard ground, and can smoothly proceed with the entire construction work. The direction is stabilized, and there is no occurrence of an insufficiently-strength portion that causes ejection of pressurized water and breakage of the underground wall.
以下、図面について本発明の実施形態を詳細に説明する。図1は本発明の地中壁の施工法の1実施形態を示す第1工程の平面図である。 Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is a plan view of a first step showing an embodiment of the underground wall construction method of the present invention.
図1において多軸掘削機による本削孔の予定箇所を一点鎖線で示すが、第1工程において、多軸掘削機の掘削軸の隔軸毎の本削孔予定箇所8を、セメントとベントナイトと水との混合による注入液を注入しながら単軸掘削機で先行して削孔(以下、先行削孔)し、先行掘削孔6を形成する。単軸掘削機の掘削軸は多軸掘削機の掘削軸よりも小さく設定する。
In FIG. 1, the planned drilling location of the multi-axis excavator is indicated by a one-dot chain line. In the first step, the planned drilling location 8 for each separated axis of the multi-axis drilling machine is changed to cement and bentonite. A
なお、次の本掘削を行うまでの間に先行掘削孔6内が固結してしまわないよう、注入液のセメント配合割合は少なめに設定する。
Note that the cement mixing ratio of the injected liquid is set to be small so that the inside of the preceding
次の第2工程で、多軸掘削機の掘削軸先端からセメントミルクなどの固結材を噴射しながら、本削孔を行う。なお、図示はしないが、多軸掘削機の各掘削軸は互いの削孔範囲を部分的に重ね合わせて掘削穴同士を連結可能としつつ、互いの掘削ヘッドがぶつからないよう、隔軸毎の先端位置を先側と後側にずらして設けられるが、先側に位置する掘削軸を先行削孔の位置に合わせて削孔する。 In the next second step, this drilling is performed while injecting a cemented material such as cement milk from the tip of the multi-axis excavator. Although not shown, each drilling shaft of the multi-axis excavator can be connected to each other by partially overlapping each other's drilling range, so that the drilling heads do not collide with each other. The tip position is provided by shifting the front side and the rear side, but the excavation shaft located on the front side is drilled in accordance with the position of the preceding drilling hole.
これにより、本削孔時には、両サイドの掘削軸3が挿入される少なくとも2本の先行掘削孔6がガイドとなり、並列する掘削軸が回転方向にずれることがなく、本削孔の削孔位置および削孔方向を効果的に安定させることができる。
Thereby, at the time of the main drilling, at least two preceding
また、これにより、先側の掘削軸は既に緩められた先行掘削孔6の周りを拡大するようにして掘り進むから、掘削軸にかかる負荷を軽減することができる。更に、それに続いて削孔する後側の掘削軸の削孔範囲は、先側の掘削軸による削孔で緩められた削孔範囲と部分的に重なるため、後側の掘削軸にかかる負荷も軽減することができ、本削孔時の負荷全体を効果的に軽減することができる。
In addition, this allows the front excavation shaft to dig so as to expand around the previously
なお、本削孔は前記従来例と同様に、削孔と同時に固結材の注入および攪拌を行う。すなわち、掘削軸を正転させて削孔を開始し、その際にセンメントミルク等の固結材とエアーを掘削ヘッドから出して孔内に注入し、所定深さまで削孔したら、なおも固結材を注入しつつ正転と逆転を交互に繰り返しながら掘削軸の引き上げを開始する。そしてある程度引き上げたならば、再度、正転・逆転で掘削および攪拌を行い、最後に逆転しながら引き上げを行う。 In this drilling hole, as in the conventional example, the consolidation material is injected and stirred simultaneously with the drilling. That is, the excavation shaft is rotated forward to start drilling. At that time, a caking material such as sentiment milk and air are extracted from the excavation head and injected into the hole, and after drilling to a predetermined depth, the solidification is still performed. While injecting the binder, the excavation shaft starts to be lifted while repeating forward rotation and reverse rotation alternately. And if it raises to some extent, excavation and agitation are performed again in the normal rotation and reverse rotation, and finally, the pulling is performed while reverse rotation.
このようにして造成された地中壁の地下における横断平面図を図2に示す。図中7は地中壁を示す。単軸掘削機による掘削は軸がぶれるため、先行掘削孔6は一点鎖線で示すように、地表で位置合わせをした箇所からはずれてしまうが、単軸掘削機の削孔径は多軸掘削機の削孔径よりも小さいから、本削孔の削孔範囲からはみ出てしまうことがない。
FIG. 2 shows a cross-sectional plan view of the underground wall constructed in this way. In the figure, 7 indicates the underground wall. As the drilling by the single-axis excavator sways, the preceding
このため、先行掘削孔6が本削孔の削孔範囲からはみ出した部分が強度不足の緩い削孔体として残ることによる、被圧水の噴出や地中壁7の破損を招くことがない。
For this reason, the portion where the preceding
また、先行削孔の削孔径を本削孔の削孔径と同じにした場合と、それよりも小さくした場合との削孔面積の比率を図8に示すが、先行削孔の削孔径を小さくするとその分、先行削孔時に使用する注入液の使用量を抑えることができる。例えば、本削孔の削孔径が1000mmである場合、先行削孔の削孔径を850mmとすると、先行削孔時に使用する注入液の量は、先行削孔の削孔径を本削孔の削孔径と同じとした場合の72.2%で済む。 Moreover, the ratio of the drilling area when the drilling diameter of the preceding drilling hole is the same as that of the main drilling hole and when the drilling hole diameter is smaller than that is shown in FIG. As a result, the amount of the injection solution used during the previous drilling can be reduced. For example, when the drilling diameter of the main drilling hole is 1000 mm and the drilling diameter of the preceding drilling hole is 850 mm, the amount of the injection liquid used at the time of the previous drilling is the same as the drilling diameter of the main drilling hole. 72.2% of the case where it is the same.
さらに、先行削孔の削孔径を小さくすると、先行削孔時に発生する注入液と掘削土との混合攪拌泥土の排出量も削減することができるため、産業廃棄物としての混合攪拌泥土の処分にかかる費用も抑えることができる。 In addition, if the drilling diameter of the preceding drilling hole is reduced, the amount of mixed stirring mud discharged from the injected liquid and excavated soil generated during the previous drilling can be reduced, which makes it possible to dispose of mixed stirring mud as industrial waste. Such costs can be reduced.
その他の実施形態として、先行削孔時の注入液にはセメントを使わず、本削孔時のみセメントを使用するようにしても良い。これにより、先行削孔時に排出される掘削土を、セメントを含む産業廃棄物にせずに済む。 As another embodiment, cement may not be used for the injection liquid at the time of prior drilling, but cement may be used only at the time of final drilling. Thereby, it is not necessary to make the excavated soil discharged at the time of preceding drilling into industrial waste containing cement.
また、掘削土を一端掘削孔から排出して、地中壁の造成に必要な量のソイルセメントを得るだけの量の掘削土をセメントミルクと混ぜてから、掘削孔に充填するようにしても良い。この方法によっても、セメントミルクを混ぜなかった分の掘削土は産業廃棄物にならずに済む。 Also, the excavated soil is discharged from the excavated hole at one end, and the excavated soil is mixed with cement milk in an amount sufficient to obtain the amount of soil cement necessary for the construction of the underground wall, and then filled into the excavated hole. good. Even with this method, the excavated soil that has not been mixed with cement milk does not become industrial waste.
1…オーガ 2…駆動装置
3…掘削軸 3a…掘削翼
4…掘削ヘッド 5…硬化材
6…先行掘削孔 6a…残留箇所
7…地中壁 8…本削孔予定箇所
9…クラック
11…ベースマシン 12…リーダーマスト
13…トップシーブ 14…駆動機構
16…湾曲ブラケット 17…リーダー
18…振れ止め 19…結束バンド
DESCRIPTION OF SYMBOLS 1 ...
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2006293678A JP4550792B2 (en) | 2006-10-30 | 2006-10-30 | Construction method of underground wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2006293678A JP4550792B2 (en) | 2006-10-30 | 2006-10-30 | Construction method of underground wall |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2008111240A true JP2008111240A (en) | 2008-05-15 |
JP4550792B2 JP4550792B2 (en) | 2010-09-22 |
Family
ID=39443904
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2006293678A Expired - Fee Related JP4550792B2 (en) | 2006-10-30 | 2006-10-30 | Construction method of underground wall |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4550792B2 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102561944A (en) * | 2011-12-29 | 2012-07-11 | 北京市三一重机有限公司 | Porous occlusive pile drilling machine and construction technology thereof |
JP2019137971A (en) * | 2018-02-06 | 2019-08-22 | 成幸利根株式会社 | Drilling device and drilling method |
JP2020169455A (en) * | 2019-04-02 | 2020-10-15 | 株式会社丸徳基業 | Construction method of soil cement continuous wall |
JP7408111B1 (en) | 2023-09-01 | 2024-01-05 | 株式会社遠藤工業 | Underground obstacle removal method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0396514A (en) * | 1989-09-11 | 1991-04-22 | Tokyu Constr Co Ltd | Soil cement cut-off wall construction method and device thereof |
JPH05280053A (en) * | 1992-03-30 | 1993-10-26 | Kobe Steel Ltd | Method and device for shaft penetration |
JPH05280052A (en) * | 1992-03-27 | 1993-10-26 | Kobe Steel Ltd | Shaft penetrating method |
JPH07238538A (en) * | 1994-02-28 | 1995-09-12 | R S Japan Reader:Kk | Continuous underground wall construction method |
JPH083980A (en) * | 1994-06-22 | 1996-01-09 | Marutoku Kigyo:Kk | Method for constructing underground wall |
JPH0868046A (en) * | 1994-08-26 | 1996-03-12 | Ask Kenkyusho:Kk | Method for forming underground continuous wall body wherein soil hardened columns are provided in series |
-
2006
- 2006-10-30 JP JP2006293678A patent/JP4550792B2/en not_active Expired - Fee Related
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0396514A (en) * | 1989-09-11 | 1991-04-22 | Tokyu Constr Co Ltd | Soil cement cut-off wall construction method and device thereof |
JPH05280052A (en) * | 1992-03-27 | 1993-10-26 | Kobe Steel Ltd | Shaft penetrating method |
JPH05280053A (en) * | 1992-03-30 | 1993-10-26 | Kobe Steel Ltd | Method and device for shaft penetration |
JPH07238538A (en) * | 1994-02-28 | 1995-09-12 | R S Japan Reader:Kk | Continuous underground wall construction method |
JPH083980A (en) * | 1994-06-22 | 1996-01-09 | Marutoku Kigyo:Kk | Method for constructing underground wall |
JPH0868046A (en) * | 1994-08-26 | 1996-03-12 | Ask Kenkyusho:Kk | Method for forming underground continuous wall body wherein soil hardened columns are provided in series |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102561944A (en) * | 2011-12-29 | 2012-07-11 | 北京市三一重机有限公司 | Porous occlusive pile drilling machine and construction technology thereof |
JP2019137971A (en) * | 2018-02-06 | 2019-08-22 | 成幸利根株式会社 | Drilling device and drilling method |
JP7004975B2 (en) | 2018-02-06 | 2022-01-21 | 成幸利根株式会社 | Drilling equipment and drilling method |
JP2020169455A (en) * | 2019-04-02 | 2020-10-15 | 株式会社丸徳基業 | Construction method of soil cement continuous wall |
JP7408111B1 (en) | 2023-09-01 | 2024-01-05 | 株式会社遠藤工業 | Underground obstacle removal method |
Also Published As
Publication number | Publication date |
---|---|
JP4550792B2 (en) | 2010-09-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5707529B1 (en) | Ground improvement method, excavation rod and ground improvement device used for ground improvement method | |
KR101527723B1 (en) | Complex Ground Improving Devive and Ground Improving Method Using The Same | |
KR101441929B1 (en) | Foundation method for complex pile | |
JP5774618B2 (en) | Foundation pile and foundation pile construction method | |
JP4550792B2 (en) | Construction method of underground wall | |
JP2007308924A (en) | Method of constructing soil improving composite pile structure, and apparatus for constructing the same | |
US6485234B2 (en) | Apparatus and method for making cylindrical columns | |
JP5281213B1 (en) | Core material and soil cement continuous wall method using the same | |
JP2005016295A (en) | Construction method for underground impervious wall | |
JP3158053U (en) | Ground improvement body construction equipment | |
JP4796197B2 (en) | Ground improvement body construction apparatus and ground improvement body construction method | |
JP2007255020A (en) | Construction method of earth retaining wall | |
JP6729902B1 (en) | Construction method of soil cement continuous wall | |
JP2007016507A (en) | Ground improvement method and reinforcing method of existing structural foundation | |
JP2576046B2 (en) | Method of forming cured soil | |
JP2002339345A (en) | Execution method for continuous underground wall | |
KR20160109395A (en) | Agitating road for excavating using soil earth cement mixing method and mixing agitator using the same | |
JPH06341140A (en) | Construction method by which column-wall holes are bored within approximate line by 10-700mm from boundary by intermittent work and continuous wall, connection wall, butt-joint wall, superposed wall, and cut-off wall are erected by use of the hole, and these walls | |
JP2700765B2 (en) | Underground wall construction method | |
JPH0978571A (en) | Execution method for soil cement pile | |
JP2698768B2 (en) | Method of forming underground continuous wall | |
JP2013142256A (en) | Construction method associated with improvement of ground property | |
JPH018587Y2 (en) | ||
JP2009270326A (en) | Construction device and construction method of soil cement column | |
JP3140770U (en) | Auger shaft |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20081008 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20081021 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20081219 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20100105 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20100405 |
|
A911 | Transfer of reconsideration by examiner before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A911 Effective date: 20100412 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20100706 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20100708 |
|
R150 | Certificate of patent (=grant) or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130716 Year of fee payment: 3 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130716 Year of fee payment: 3 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |