JP2007321452A - Construction method for bridge and bridge structure thereof - Google Patents
Construction method for bridge and bridge structure thereof Download PDFInfo
- Publication number
- JP2007321452A JP2007321452A JP2006153219A JP2006153219A JP2007321452A JP 2007321452 A JP2007321452 A JP 2007321452A JP 2006153219 A JP2006153219 A JP 2006153219A JP 2006153219 A JP2006153219 A JP 2006153219A JP 2007321452 A JP2007321452 A JP 2007321452A
- Authority
- JP
- Japan
- Prior art keywords
- bridge
- embankment
- reinforced
- ramen
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
本発明は、河川や道路横断部等における橋梁の構築方法およびその橋梁構造物に関するものである。 The present invention relates to a method for constructing a bridge in a river, a road crossing portion, and the like and a bridge structure thereof.
従来、河川部や道路交差部に橋梁を構築する場合には、初めに、図6(a)に示すように支持地盤101に基礎杭102(支持地盤101が強固な場合には基礎杭102は不要な場合もある)を打ち、その上に橋台103を構築する。その後、図6(b)に示すように、橋台103の背面に盛土104を盛り立て、橋台103上に固定支承105と自由支承106とを設置し、橋桁107を橋台103間に構築するという手順で施工されてきた。ここで橋台103は、盛土104による土圧に抵抗するとともに、橋桁107の桁座として、桁自重や桁に上載する列車などを支持する役割がある。
Conventionally, when a bridge is constructed in a river part or a road intersection, first, as shown in FIG. 6 (a), the foundation pile 102 (if the
また、本願の発明者らは、(1)既に、土嚢を積み、コントリートを食いつかせることによる盛土の構築に伴う安定化工法及びその構造物(補強土壁工法)を既に提案している(下記特許文献1参照)。(2)切土直後の地盤、あるいは一般の地盤を補強するための引張り補強体について提案している(下記特許文献2参照)。(3)橋梁改築に伴う橋台の構築工法およびその橋台構造物について提案している(下記特許文献3参照)。
しかしながら、上記した橋梁の構築工法およびその橋梁構造物では、橋台基礎部には大きな水平力と鉛直力、モーメントが作用するため、大きなフーチングと多数の基礎杭が必要となる。また、従来の施工法では、杭基礎を施工した後に、橋台背面の盛土を盛り立てることになるため、盛土の盛り立て時に橋台構造物に過大な土圧を与える可能性があるだけでなく、地盤が過大に沈下したり側方に変位して杭基礎を押す場合がある。これを抑制しようとすると、さらに大掛かりな基礎が必要となる。 However, in the bridge construction method and the bridge structure described above, a large horizontal force, vertical force, and moment act on the abutment foundation, so a large footing and a large number of foundation piles are required. In addition, in the conventional construction method, after the pile foundation is constructed, the embankment on the back of the abutment is raised, so there is a possibility that excessive earth pressure is applied to the abutment structure when embankment is raised, The ground may sink excessively or may be displaced laterally and push the pile foundation. In order to suppress this, a larger foundation is required.
構築後においても、橋台とその背面の盛土は弱点となりやすい。特に、図7に示すように、背面盛土が沈下した場合には、橋台との間に段差が生じて列車や自動車の走行安全性に支障を与える。しかも、地震時(特にレベル2地震動)において橋台構造物に過大な土圧を与える可能性があるだけでなく、橋台背後の盛土の沈下を抑制することは難しい。また、従来の橋梁では、橋桁支承の維持管理も問題になる。さらに、多数の工種から構成されるため、従来の構造形式の橋台は、一般に建設費が高く建設期間が長い。
Even after construction, the abutment and the embankment on the back of the abutment tend to be weak points. In particular, as shown in FIG. 7, when the back embankment sinks, a step is generated between the abutment and the travel safety of trains and automobiles is hindered. Moreover, not only may there be an excessive earth pressure on the abutment structure during an earthquake (particularly
本発明は、上記状況に鑑みて、強度が堅牢で、地震に強い橋梁の構築工法およびその橋梁構造物を提供することを目的とする。 In view of the above circumstances, an object of the present invention is to provide a bridge construction method and a bridge structure that are strong in strength and strong against earthquakes.
本発明は、上記目的を達成するために、
〔1〕橋梁の構築工法において、ジオテキスタイルと土嚢などの柔軟性(変形追随性)の高い壁面部材を用いて、補強盛土を構築し、支持地盤が軟弱な場合には、補強盛土の盛り立てによる地盤沈下などが収束した段階で基礎杭などの基礎を施工し、対面する側にも、同時にジオテキスタイルと土嚢などの柔軟性(変形追随性)の高い壁面部材を用いて、補強盛土を構築し、支持地盤が軟弱な場合には、補強盛土の盛り立てによる地盤沈下などが収束した段階で基礎杭などの基礎を施工し、上記した対面する補強盛土の壁面工と、橋桁の梁部分を一体化して、ラーメン橋梁部の鉄筋コンクリートを打設することを特徴とする。
In order to achieve the above object, the present invention provides
[1] In the construction method of the bridge, reinforced embankment is constructed using wall materials with high flexibility (deformability following) such as geotextiles and sandbags. When foundation subsidence has converged, foundations such as foundation piles are constructed, and reinforced embankments are constructed on the facing side using a highly flexible wall member such as geotextile and sandbags at the same time, If the supporting ground is soft, foundations such as foundation piles are constructed when the ground subsidence due to the embankment of the reinforced embankment has converged, and the wall work of the reinforced embankment facing above and the beam part of the bridge girder are integrated. It is characterized by placing reinforced concrete in the ramen bridge.
〔2〕橋梁の構築工法において、両側の既設盛土に土留め壁を打設し、その後、小段の掘削を行い、掘削面に対して、引張り補強材を打設し、これらの工程を繰り返し、所定の深さまで掘削し、前記土留め壁の前面の空いたスペースに、必要に応じて基礎杭を設置し、前記引張り補強材、前記土留め壁と連結し一体化して、ラーメン橋梁部の鉄筋コンクリートを打設することを特徴とする。 [2] In the construction method of the bridge, a retaining wall is placed on the existing embankment on both sides, and then a small excavation is performed, a tensile reinforcement is placed on the excavation surface, and these steps are repeated. Excavate to a predetermined depth, install foundation piles in the empty space in front of the retaining wall, if necessary, connect with the tensile reinforcement and the retaining wall, and integrate them, reinforced concrete of the ramen bridge part It is characterized by placing.
〔3〕上記〔1〕又は〔2〕記載の橋梁の構築工法において、ラーメン橋梁部の桁長が長い場合には、ラーメン橋梁部の中間部においてローラ支承による橋脚を設け、ラーメン橋梁部の鉛直力だけを支持することを特徴とする。 [3] In the bridge construction method described in [1] or [2] above, when the girder length of the ramen bridge portion is long, a bridge pier with roller support is provided in the middle portion of the ramen bridge portion, It is characterized by supporting only force.
〔4〕橋梁構造物において、ジオテキスタイルと土嚢などの柔軟性(変形追随性)の高い壁面部材を用いて、補強盛土を構築し、支持地盤が軟弱な場合には、補強盛土の盛り立てによる地盤沈下などが収束した段階で基礎杭などの基礎を施工し、対面する側にも、同時に補強盛土と、支持地盤が軟弱な場合には、補強盛土の盛り立てによる地盤沈下などが収束した段階で基礎杭などの基礎を施工し、対面する補強盛土の壁面工と、橋桁の梁部分を一体化するように鉄筋コンクリートを打設したラーメン橋梁部とを具備することを特徴とする。 [4] In bridge structures, reinforced embankments are constructed using highly flexible wall surfaces such as geotextiles and sandbags, and if the supporting ground is soft, the ground by raising the reinforced embankment When subsidence has converged, foundations such as foundation piles are constructed, and on the facing side, if the reinforced embankment and the supporting ground are soft, the subsidence due to the embankment of the reinforced embankment has converged. It is characterized by comprising a foundation such as a foundation pile, and a wall work of reinforcing embankments facing each other, and a ramen bridge part in which reinforced concrete is cast so that the beam part of the bridge girder is integrated.
〔5〕橋梁構造物において、両側の既設盛土の両側に打設される土留め壁と、掘削面に対して、打設される引張り補強材と、前記土留め壁の前面の空いたスペースに、必要に応じて設置される基礎杭と、前記引張り補強材、前記土留め壁と連結し一体化するように鉄筋コンクリートを打設したラーメン橋梁部とを具備することを特徴とする。 [5] In a bridge structure, a retaining wall that is placed on both sides of the existing embankment on both sides, a tensile reinforcement member that is placed against the excavation surface, and an empty space in front of the retaining wall Further, the present invention is characterized by comprising a foundation pile installed as necessary, a ramen bridge portion in which reinforced concrete is cast so as to be connected to and integrated with the tensile reinforcement member and the retaining wall.
〔6〕上記〔4〕又は〔5〕記載の橋梁構造物において、ラーメン橋梁部の桁長が長い場合には、ラーメン橋梁部の中間部にラーメン橋梁部の鉛直力だけを支持するローラ支承による橋脚を具備することを特徴とする。 [6] In the bridge structure described in [4] or [5] above, when the girder length of the ramen bridge portion is long, a roller bearing that supports only the vertical force of the ramen bridge portion at the middle portion of the ramen bridge portion A pier is provided.
本発明によれば、次のような効果を奏することができる。 According to the present invention, the following effects can be achieved.
本発明の橋梁の構築工法は、補強土壁工法の手順で、ジオテキスタイルと土嚢などの柔軟性(変形追随性)の高い壁面部材を用いて、補強盛土を構築し、支持地盤が軟弱な場合には、補強盛土の盛り立てによる地盤沈下などが収束した段階で基礎を施工し、対面する側にも、同時に補強盛土を構築し、支持地盤が軟弱な場合には、補強盛土の盛り立てによる地盤沈下などが収束した段階で基礎杭などの基礎を施工し、上記した対面する補強盛土の壁面工と、橋桁の梁部分を一体化して、ラーメン橋梁部の鉄筋コンクリートを打設する。 The bridge construction method of the present invention is a procedure of the reinforced earth wall construction method, when a reinforced embankment is constructed using a highly flexible wall member such as geotextile and sandbag, and the supporting ground is soft. The foundation is constructed when the ground subsidence due to the embankment of the reinforced embankment has converged, and the reinforced embankment is also constructed on the facing side at the same time. If the supporting ground is soft, the ground by the embankment of the reinforced embankment When subsidence has converged, foundations such as foundation piles are constructed, and the reinforced concrete wall of the facing reinforcement embankment and the beam part of the bridge girder are integrated into the reinforced concrete of the ramen bridge part.
以下、本発明の実施の形態について詳細に説明する。 Hereinafter, embodiments of the present invention will be described in detail.
まず、本発明の第1実施例を示す橋梁の構築工法について説明する。 First, a bridge construction method according to the first embodiment of the present invention will be described.
図1は本発明の第1実施例を示す橋梁の構築工法を示す模式図である。 FIG. 1 is a schematic view showing a bridge construction method according to a first embodiment of the present invention.
この実施例では、河川や道路横断部などにおける橋梁の構築方法に関する。 This embodiment relates to a method for constructing a bridge in a river or a road crossing section.
(1)図1(a)に示すように、初めに補強土壁工法の手順で、ジオテキスタイル2と土嚢3などを用いて、補強盛土4を構築する。
(1) As shown to Fig.1 (a), the
(2)次に、図1(a)に示すように、支持地盤1が軟弱な場合には、補強盛土4の盛り立てによる地盤沈下などが収束した段階で基礎杭5などの基礎を施工する。ただし、支持地盤1が堅固な場合には、基礎杭5は不要となる。
(2) Next, as shown in FIG. 1A, when the supporting
(3)次に、図1(b)に示すように、壁面工6を施工する際に、その壁面工6の上部を所定の厚み(後述する橋桁の厚み)残しておく。
(3) Next, as shown in FIG. 1 (b), when the
(4)次に、図1(c)に示すように、対面する側にも、同時に補強盛土4と、必要に応じて基礎杭5などを施工する。
(4) Next, as shown in FIG.1 (c), the
(5)次に、図1(c)に示すように、対面する補強盛土4の壁面工6と、橋桁7の梁部分を一体化して、鉄筋コンクリートを打設し、ラーメン橋梁部8とする。つまり、橋桁7の梁部分に打設される鉄筋コンクリートは、土嚢3とジオテキスタイル2に十分に食いつくことになり、橋桁7と補強盛土4とが強固に構築される。したがって、橋桁7上を、例えば、列車9が走行しても、橋桁7と補強盛土4とは強固に一体化されているので、橋桁7と補強盛土4の間が陥没することはない。
(5) Next, as shown in FIG.1 (c), the
このように、初めに補強盛土構造で盛土部を構築することにより、施工中ならびに構築初期に生じる盛土や地盤の変形に対する高い追随性を確保することができる。この工法は補強土壁工法と呼ばれ、擁壁の代替として多くの実績を有する。この補強土壁工法と、更に、その補強土壁工法の壁面部(壁面工)と橋桁とを一体化した鉄筋コンクリートの打設によるラーメン橋梁部を打設する前に盛土が建設されるので、盛土の盛り立てに伴う地盤の変形を抑制するための基礎杭や地盤改良は不要である。 Thus, by constructing the embankment part with a reinforced embankment structure first, it is possible to ensure high followability to the embankment and ground deformation that occurs during construction and at the initial stage of construction. This method is called a reinforced earth wall method and has many achievements as an alternative to retaining walls. Since the embankment is constructed before the ramen bridge part is placed by placing reinforced concrete with the reinforcement earth wall method and the wall part (wall work) of the reinforcement earth wall method and the bridge girder integrated, There is no need for foundation piles or ground improvement to suppress the deformation of the ground due to the uplifting of the ground.
しかしながら、完成後にはラーメン橋梁部8の自重や交通荷重によるラーメン橋梁部8(壁面工6+橋桁7)の長期残留沈下を防ぐ必要がある場合には、杭基礎5が必要となる。また、壁面工6は補強盛土4と一体となっていて活荷重は補強盛土4内にも分散される。また、地震時などにおいて、ラーメン橋梁部8に水平慣性力が作用した場合でも、盛土背面のジオテキスタイル2が抵抗するため、基礎杭5に作用する水平力やモーメントは格段に小さくなる。したがって、基礎杭5の本数は大幅に少なくすることができる。
However, the
また、支承を有しない橋台・橋桁の一体構造であり、支承の製作、設置費、維持管理費が不要となる。 In addition, it has an abutment / bridge girder integrated structure that does not have a support, so there is no need to produce, install and maintain the support.
ここで、背面盛土を補強盛土構造としないラーメン橋梁も考えられ、実際にヨーロッパなどにおいては多用されている(図5)。しかし、この場合には橋桁の温度変化に伴う熱膨張収縮に伴う壁面工の強制繰返し水平変位(年周期)によって、壁面工背後の盛土が沈下し、最大土圧が増加する場合がある。したがって、補強盛土を併用しないラーメン橋梁では、この増加した土圧に対して壁面工は構造的に対抗する必要がある。一方、本発明の工法は、背面盛土にジオテキスタイルを配置し、ラーメン橋梁と一体化を図ることを特徴とする。つまり、図2に示すように、ジオテキスタイル2で補強されているため拘束圧が高くなり背面盛土4の剛性が増加し、温度変化による壁面工6の強制繰返し水平変位も減少する。また、壁面工6の背面に結合されているジオテキスタイル2によって盛土の累積的な沈下が防止できる。さらに、壁面工6とジオテキスタイル2が結合されている箇所は壁面工6に対する支点として機能するので、作用土圧が増加しても壁面工6は多支点で支持された連続梁として機能するので、壁面工6には高い構造的強度が必要にはならない。
Here, a ramen bridge where the back embankment does not have a reinforced embankment structure is also conceivable, and is actually used frequently in Europe and the like (FIG. 5). However, in this case, due to forced repeated horizontal displacement (annual cycle) of the wall work accompanying the thermal expansion and contraction accompanying the temperature change of the bridge girder, the embankment behind the wall work may sink and the maximum earth pressure may increase. Therefore, in the case of a ramen bridge that does not use reinforced embankment, the wall work must be structurally countered against this increased earth pressure. On the other hand, the construction method of the present invention is characterized in that a geotextile is arranged on the back embankment and integrated with the ramen bridge. That is, as shown in FIG. 2, since it is reinforced by the
さらに、構造的な特徴として、両側の橋台としての壁面工6と橋桁7が一体化されることによって耐震性が向上する。これらの相乗効果で、温度変化による壁面工6の背後での盛土沈下や、地震荷重による壁面工6の背後での盛土沈下がさらに防止できる。
Furthermore, as a structural feature, the seismic resistance is improved by integrating the
なお、上記した図1(b)に示すように、壁面工6を施工する際に、その壁面工6の上部を所定の厚み(後述する橋桁の厚み)残すのではなく、当初から門型の鉄筋をくみ上げておき、同時に壁面工と橋桁とのラーメン橋梁部の鉄筋コンクリートを打設するようにしてもよい。この場合にも、補強盛土とラーメン橋梁部との強固な一体化を図ることができる。
As shown in FIG. 1 (b), when the
図3は本発明の第2実施例を示す橋梁の構築工法を示す模式図である。 FIG. 3 is a schematic view showing a bridge construction method according to the second embodiment of the present invention.
上記実施例は、専ら橋梁を新築する場合の施工手順であったが、既設橋梁の架け替え時においても、本発明は応用できる。つまり、補強盛土の部分を地山補強土工法で構築し、ラーメン橋梁と一体化すれば、上記と同じ構造となる。具体的な施工手順は以下の通りである。
(1)既設盛土11に土留め壁(H鋼や鋼矢板、ソイルセメント壁など)12を打設し、その後、小段の掘削を行う。
(2)掘削面に対して、ネイリング、マイクロパイリング、ダウアリングなどの引張り補強材13を打設し、これらの工程を繰り返し、所定の深さまで掘削する。
(3)土留め壁12の前面の空いたスペースに、必要に応じて基礎杭14を設置する。
(4)最終的には、引張り補強材13、土留め壁12と連結し一体化するように、ラーメン橋梁部15の鉄筋コンクリートを打設する。
Although the above-mentioned embodiment was a construction procedure when a new bridge was newly constructed, the present invention can be applied even when an existing bridge is replaced. In other words, if the reinforced embankment part is constructed by the natural ground reinforced earth method and integrated with the ramen bridge, the same structure as above is obtained. The specific construction procedure is as follows.
(1) An earth retaining wall (H steel, steel sheet pile, soil cement wall, etc.) 12 is placed on the existing
(2)
(3) A
(4) Finally, the reinforced concrete of the
このように、補強盛土の部分を地山補強土工法と引張り補強材、土留め壁と連結し一体化するように、ラーメン橋梁部の鉄筋コンクリートを打設することにより、第1実施例と同様の盛土の累積的な沈下が防止でき、両側の橋台が一体化されることによって耐震性が向上する。これらの相乗効果で、温度変化による壁面工背後での盛土沈下や、地震荷重による壁面工背後での盛土沈下がさらに防止できる。 In this way, the reinforced concrete of the ramen bridge part is placed so that the reinforced embankment part is connected and integrated with the natural ground reinforced earth method, the tensile reinforcement, and the retaining wall, and the same as in the first embodiment. Cumulative settlement of the embankment can be prevented, and earthquake resistance is improved by integrating the abutments on both sides. These synergistic effects can further prevent embankment sinking behind the wall work due to temperature changes and embankment sinking behind the wall work due to seismic load.
図4は本発明の第3実施例を示す橋梁の構築工法を示す模式図である。 FIG. 4 is a schematic view showing a bridge construction method according to the third embodiment of the present invention.
この図において、22は橋梁において桁長が長い場合に設けられる橋脚であり、この橋脚22は桁の中間部の基礎杭21上において、ローラ支承23により鉛直力だけを支持する構造である。
In this figure,
このように、本発明のラーメン橋梁部において桁長が長い場合には、中間部において、ローラ支承により鉛直力だけを支持する構造とした橋脚を設けることにより、ラーメン橋梁部の支持力を高めることができる。 As described above, when the girder length is long in the rigid frame bridge portion of the present invention, the support force of the rigid frame bridge portion is increased by providing a bridge pier having a structure that supports only the vertical force by the roller support in the intermediate portion. Can do.
なお、本発明は上記実施例に限定されるものではなく、本発明の趣旨に基づいて種々の変形が可能であり、これらを本発明の範囲から排除するものではない。 In addition, this invention is not limited to the said Example, A various deformation | transformation is possible based on the meaning of this invention, and these are not excluded from the scope of the present invention.
本発明の橋梁の構築工法及びその橋梁構造物は、強度が堅牢であり、地震にも強い鉄道や道路の橋梁の構築工法及びその橋梁構造物として利用可能である。 The bridge construction method and the bridge structure according to the present invention are strong in strength and can be used as a construction method of a bridge for a railway or road and a bridge structure that are resistant to earthquakes.
1 支持地盤
2 ジオテキスタイル
3 土嚢
4 補強盛土
5,14,21 基礎杭
6 壁面工
7 橋桁
8,15 ラーメン橋梁部
9 列車
11 既設盛土
12 土留め壁
13 引張り補強材
22 橋脚
23 ローラ支承
DESCRIPTION OF
Claims (6)
(b)支持地盤が軟弱な場合には、補強盛土の盛り立てによる地盤沈下などが収束した段階で基礎杭などの基礎を施工し、
(c)対面する側にも、同時にジオテキスタイルと土嚢などの柔軟性の高い壁面部材を用いて、補強盛土を構築し、
(d)支持地盤が軟弱な場合には、補強盛土の盛り立てによる地盤沈下などが収束した段階で基礎杭などの基礎を施工し、
(e)上記した対面する補強盛土の壁面工と、橋桁の梁部分を一体化して、ラーメン橋梁部の鉄筋コンクリートを打設することを特徴とする橋梁の構築工法。 (A) Using a highly flexible wall surface member such as geotextile and sandbag, construct a reinforced embankment,
(B) If the supporting ground is soft, construct foundations such as foundation piles at the stage where ground subsidence due to the embankment of the reinforced embankment has converged,
(C) Construct a reinforced embankment on the facing side using a highly flexible wall member such as geotextile and sandbag at the same time,
(D) If the supporting ground is soft, construct foundations such as foundation piles at the stage when the ground subsidence due to the embankment of the reinforced embankment has converged,
(E) A construction method of a bridge characterized in that the above-mentioned wall construction of the reinforcing embankment facing and the beam portion of the bridge girder are integrated and reinforced concrete of the ramen bridge portion is cast.
(b)掘削面に対して、引張り補強材を打設し、これらの工程を繰り返し、所定の深さまで掘削し、
(c)前記土留め壁の前面の空いたスペースに、必要に応じて基礎杭を設置し、
(d)前記引張り補強材、前記土留め壁と連結し一体化して、ラーメン橋梁部の鉄筋コンクリートを打設することを特徴とする橋梁の構築工法。 (A) Placing a retaining wall on the existing embankment on both sides, then excavating a small step,
(B) Placing a tensile reinforcement on the excavation surface, repeating these steps, excavating to a predetermined depth,
(C) If necessary, install foundation piles in the vacant space in front of the retaining wall,
(D) A method for constructing a bridge, comprising connecting and integrating the tensile reinforcement member and the retaining wall, and placing reinforced concrete in a ramen bridge portion.
(b)支持地盤が軟弱な場合には、補強盛土の盛り立てによる地盤沈下などが収束した段階で基礎杭などの基礎を施工し、
(c)対面する側にも、同時に補強盛土と、支持地盤が軟弱な場合には、補強盛土の盛り立てによる地盤沈下などが収束した段階で基礎杭などの基礎を施工し、
(d)対面する補強盛土の壁面工と、橋桁の梁部分を一体化するように鉄筋コンクリートを打設したラーメン橋梁部とを具備することを特徴とする橋梁構造物。 (A) Using a highly flexible wall surface member such as geotextile and sandbag, construct a reinforced embankment,
(B) If the supporting ground is soft, construct foundations such as foundation piles at the stage where ground subsidence due to the embankment of the reinforced embankment has converged,
(C) If the reinforced embankment and the supporting ground are soft at the same time, construct foundations such as foundation piles at the stage where ground subsidence due to the embankment of the reinforced embankment has converged,
(D) A bridge structure characterized by comprising a wall construction of a reinforced embankment facing each other and a ramen bridge portion in which reinforced concrete is cast so that the beam portion of the bridge girder is integrated.
(b)掘削面に対して、打設される引張り補強材と、
(c)前記土留め壁の前面の空いたスペースに、必要に応じて設置される基礎杭と、
(d)前記引張り補強材、前記土留め壁と連結し一体化するように鉄筋コンクリートを打設したラーメン橋梁部とを具備することを特徴とする橋梁構造物。 (A) earth retaining walls placed on both sides of the existing embankment on both sides;
(B) a tensile reinforcement member to be placed against the excavation surface;
(C) a foundation pile installed as needed in a vacant space in front of the retaining wall;
(D) A bridge structure comprising: a reinforcing frame and a ramen bridge portion in which reinforced concrete is cast so as to be connected to and integrated with the retaining wall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2006153219A JP4863268B2 (en) | 2006-06-01 | 2006-06-01 | Bridge construction method and its bridge structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2006153219A JP4863268B2 (en) | 2006-06-01 | 2006-06-01 | Bridge construction method and its bridge structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2007321452A true JP2007321452A (en) | 2007-12-13 |
JP4863268B2 JP4863268B2 (en) | 2012-01-25 |
Family
ID=38854509
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2006153219A Active JP4863268B2 (en) | 2006-06-01 | 2006-06-01 | Bridge construction method and its bridge structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4863268B2 (en) |
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011058168A (en) * | 2009-09-07 | 2011-03-24 | Railway Technical Res Inst | Method for repairing bridge |
JP2012207432A (en) * | 2011-03-29 | 2012-10-25 | National Agriculture & Food Research Organization | Method for laying reinforcement material and structure constructed by the method |
JP2012237127A (en) * | 2011-05-11 | 2012-12-06 | Ohbayashi Corp | Portal rigid-frame bridge with improved dispersibility of vertical load |
CN103225267A (en) * | 2013-03-29 | 2013-07-31 | 天津二十冶建设有限公司 | Construction method of deep and thick soft soil foundation bed bridge abutment |
JP2013253389A (en) * | 2012-06-05 | 2013-12-19 | National Agriculture & Food Research Organization | Construction method of banking structure and banking structure constructed by the same |
JP2014020168A (en) * | 2012-07-23 | 2014-02-03 | Railway Technical Research Institute | Consecutive reinforcing-soil integrated bridge |
JP2014125761A (en) * | 2012-12-26 | 2014-07-07 | Fumio Tatsuoka | Structure and construction method for the same |
JP2016089525A (en) * | 2014-11-07 | 2016-05-23 | 公益財団法人鉄道総合技術研究所 | Bridge structure having self-weight support mechanism |
CN106021736A (en) * | 2016-05-23 | 2016-10-12 | 长安大学 | Truss structure robust design size optimization method based on Info-Gap decision |
JP2017057701A (en) * | 2015-09-18 | 2017-03-23 | 公益財団法人鉄道総合技術研究所 | Concrete wall structure for reinforcing fill-integrated bridge, and construction method |
CN110424404A (en) * | 2019-07-30 | 2019-11-08 | 中铁建设集团有限公司 | A kind of deep basal pit part inner support system |
CN111705678A (en) * | 2020-07-13 | 2020-09-25 | 中国五冶集团有限公司 | Isolation structure for continuous beam grouting layer and grouting method |
KR20210114296A (en) * | 2020-03-10 | 2021-09-23 | 한국철도기술연구원 | Transitional zone available deformation absorption and subsidence reduction and constructing method therefor |
CN114808735A (en) * | 2022-05-20 | 2022-07-29 | 中铁建大桥工程局集团第四工程有限公司 | Jacking construction control method for frame-structure bridge |
CN115418985A (en) * | 2022-10-10 | 2022-12-02 | 中铁九局集团第一建设有限公司 | High-speed railway expanded soil culvert transition section reinforcing structure and construction method thereof |
CN115450118A (en) * | 2022-08-14 | 2022-12-09 | 中铁十局集团第八工程有限公司 | Jacking construction device and construction method for cross frame bridge of underpass high-speed motor car test line |
KR20230058255A (en) * | 2021-10-22 | 2023-05-03 | 한국철도기술연구원 | Protrusive transitional zone available deformation absorption and subsidence reduction and constructing method therefor |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103469789B (en) * | 2013-09-30 | 2015-07-01 | 中铁二十局集团有限公司 | Karst-area underwater bridge pier drilled pile construction method |
JP6333207B2 (en) * | 2015-03-31 | 2018-05-30 | 公益財団法人鉄道総合技術研究所 | Bridge construction method and bridge structure |
CN109680733A (en) * | 2019-01-27 | 2019-04-26 | 浙江大学 | The displacement of foundation pit rigid retaining walls induces the model test apparatus and operating method for cheating outer ground surface soil body sedimentation |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5737724B2 (en) * | 1979-01-18 | 1982-08-11 | ||
JP2002004224A (en) * | 2000-06-08 | 2002-01-09 | Min Se Koo | Construction method of single span and multi span composite girder bridge |
JP2005068816A (en) * | 2003-08-25 | 2005-03-17 | Railway Technical Res Inst | Construction method for abutment with reconstruction for bridge and its abutment structure |
JP2005113467A (en) * | 2003-10-07 | 2005-04-28 | Railway Technical Res Inst | Method of constructing reinforced soil abutment and pier, and structures of the same |
-
2006
- 2006-06-01 JP JP2006153219A patent/JP4863268B2/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5737724B2 (en) * | 1979-01-18 | 1982-08-11 | ||
JP2002004224A (en) * | 2000-06-08 | 2002-01-09 | Min Se Koo | Construction method of single span and multi span composite girder bridge |
JP2005068816A (en) * | 2003-08-25 | 2005-03-17 | Railway Technical Res Inst | Construction method for abutment with reconstruction for bridge and its abutment structure |
JP2005113467A (en) * | 2003-10-07 | 2005-04-28 | Railway Technical Res Inst | Method of constructing reinforced soil abutment and pier, and structures of the same |
Cited By (23)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011058168A (en) * | 2009-09-07 | 2011-03-24 | Railway Technical Res Inst | Method for repairing bridge |
JP2012207432A (en) * | 2011-03-29 | 2012-10-25 | National Agriculture & Food Research Organization | Method for laying reinforcement material and structure constructed by the method |
JP2012237127A (en) * | 2011-05-11 | 2012-12-06 | Ohbayashi Corp | Portal rigid-frame bridge with improved dispersibility of vertical load |
JP2013253389A (en) * | 2012-06-05 | 2013-12-19 | National Agriculture & Food Research Organization | Construction method of banking structure and banking structure constructed by the same |
JP2014020168A (en) * | 2012-07-23 | 2014-02-03 | Railway Technical Research Institute | Consecutive reinforcing-soil integrated bridge |
JP2014125761A (en) * | 2012-12-26 | 2014-07-07 | Fumio Tatsuoka | Structure and construction method for the same |
CN103225267A (en) * | 2013-03-29 | 2013-07-31 | 天津二十冶建设有限公司 | Construction method of deep and thick soft soil foundation bed bridge abutment |
CN103225267B (en) * | 2013-03-29 | 2015-07-15 | 天津二十冶建设有限公司 | Construction method of deep and thick soft soil foundation bed bridge abutment |
JP2016089525A (en) * | 2014-11-07 | 2016-05-23 | 公益財団法人鉄道総合技術研究所 | Bridge structure having self-weight support mechanism |
JP2017057701A (en) * | 2015-09-18 | 2017-03-23 | 公益財団法人鉄道総合技術研究所 | Concrete wall structure for reinforcing fill-integrated bridge, and construction method |
CN106021736A (en) * | 2016-05-23 | 2016-10-12 | 长安大学 | Truss structure robust design size optimization method based on Info-Gap decision |
CN110424404A (en) * | 2019-07-30 | 2019-11-08 | 中铁建设集团有限公司 | A kind of deep basal pit part inner support system |
CN110424404B (en) * | 2019-07-30 | 2024-06-07 | 中铁建设集团有限公司 | Deep foundation pit local inner support system |
KR20210114296A (en) * | 2020-03-10 | 2021-09-23 | 한국철도기술연구원 | Transitional zone available deformation absorption and subsidence reduction and constructing method therefor |
KR102369701B1 (en) * | 2020-03-10 | 2022-03-04 | 한국철도기술연구원 | Transitional zone available deformation absorption and subsidence reduction and constructing method therefor |
CN111705678A (en) * | 2020-07-13 | 2020-09-25 | 中国五冶集团有限公司 | Isolation structure for continuous beam grouting layer and grouting method |
KR102562385B1 (en) | 2021-10-22 | 2023-08-02 | 한국철도기술연구원 | Protrusive transitional zone available deformation absorption and subsidence reduction and constructing method therefor |
KR20230058255A (en) * | 2021-10-22 | 2023-05-03 | 한국철도기술연구원 | Protrusive transitional zone available deformation absorption and subsidence reduction and constructing method therefor |
CN114808735B (en) * | 2022-05-20 | 2023-09-12 | 中铁建大桥工程局集团第四工程有限公司 | Frame bridge jacking construction control method |
CN114808735A (en) * | 2022-05-20 | 2022-07-29 | 中铁建大桥工程局集团第四工程有限公司 | Jacking construction control method for frame-structure bridge |
CN115450118A (en) * | 2022-08-14 | 2022-12-09 | 中铁十局集团第八工程有限公司 | Jacking construction device and construction method for cross frame bridge of underpass high-speed motor car test line |
CN115418985A (en) * | 2022-10-10 | 2022-12-02 | 中铁九局集团第一建设有限公司 | High-speed railway expanded soil culvert transition section reinforcing structure and construction method thereof |
CN115418985B (en) * | 2022-10-10 | 2024-05-28 | 中铁九局集团第一建设有限公司 | Reinforced structure of transition section of expansive soil road culvert of high-speed railway and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
JP4863268B2 (en) | 2012-01-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4863268B2 (en) | Bridge construction method and its bridge structure | |
CN103958780B (en) | method of forming a cementitious retaining wall | |
KR100971004B1 (en) | Retaining Wall with Panels | |
JP4281567B2 (en) | Reinforcement structure of existing pier foundation and reinforcement method of existing pier foundation | |
KR20090130637A (en) | Fill-up structure for back-area of rigid structure and construction method of the same | |
JP2020204151A (en) | Improvement structure and improvement method of existing sheet pile type quay | |
JP7149919B2 (en) | Improvement structure and improvement method of existing wharf | |
JP4569525B2 (en) | Steel wall for composite structure | |
JP5208904B2 (en) | Wall construction method using bags | |
JP4765965B2 (en) | Revetment integrated ramen bridge and its construction method | |
JP6387996B2 (en) | Reinforcing structure and reinforcing method of existing steel sheet pile wall | |
JP6477565B2 (en) | Reinforcing structure and reinforcing method of existing steel sheet pile wall | |
KR100496735B1 (en) | Abutment and pier using composite pile and sheet pile of a bridge, and it's construction method | |
Eskandari et al. | Basic Types of Sheet Pile Walls and Their Application in the Construction Industry--a Review | |
JP2017057701A (en) | Concrete wall structure for reinforcing fill-integrated bridge, and construction method | |
JP3832845B2 (en) | Steel sheet pile combined direct foundation and construction method of steel sheet pile combined direct foundation | |
Tatsuoka et al. | Seismic design, construction and performance of geosynthetic-reinforced soil retaining walls and bridge abutments for railways in Japan | |
JPH0913343A (en) | Revetment structure and its construction method | |
JP6846585B2 (en) | Reinforced soil wall type structure Reinforced laying member connection structure and reinforced laying member laying method | |
JP4283194B2 (en) | Wave-absorbing structure, method for constructing wave-absorbing structure | |
JP2008081960A (en) | Ocean wave protection structure | |
JP2003321826A (en) | Earthquake resisting property reinforced structure of levee body such as earth filling dam or the like | |
KR102443020B1 (en) | Construction method of bridge using overlapped piles and bridge using overlspped piles | |
KR101089729B1 (en) | The wall for the bridge post foundation construction | |
KR200344087Y1 (en) | abutment and pier using composite pile and sheet pile of a bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20080711 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20100514 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20100608 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20100706 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20100810 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20100922 |
|
A911 | Transfer of reconsideration by examiner before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A911 Effective date: 20101018 |
|
A912 | Removal of reconsideration by examiner before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A912 Effective date: 20101112 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20110909 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20111102 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20141118 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4863268 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |