[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

JP2005307544A - Laying method and removal method for covering plate for open shield method - Google Patents

Laying method and removal method for covering plate for open shield method Download PDF

Info

Publication number
JP2005307544A
JP2005307544A JP2004125253A JP2004125253A JP2005307544A JP 2005307544 A JP2005307544 A JP 2005307544A JP 2004125253 A JP2004125253 A JP 2004125253A JP 2004125253 A JP2004125253 A JP 2004125253A JP 2005307544 A JP2005307544 A JP 2005307544A
Authority
JP
Japan
Prior art keywords
open shield
lining
laying
girder
board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2004125253A
Other languages
Japanese (ja)
Other versions
JP3917146B2 (en
Inventor
Makoto Uemura
誠 植村
Kenjiro Uemura
賢治郎 植村
Hiroaki Takegawa
廣明 竹川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP2004125253A priority Critical patent/JP3917146B2/en
Publication of JP2005307544A publication Critical patent/JP2005307544A/en
Application granted granted Critical
Publication of JP3917146B2 publication Critical patent/JP3917146B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Road Paving Structures (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To obtain a laying method and a removal method for a covering plate, which can reduce a traffic hindrance and shorten a construction period, when a concrete box is laid by an open shield method. <P>SOLUTION: In this open shield method, bearing girder guide steel materials 21 are installed on both the sides of a place subject to excavation, before the start of the step of excavating/removing sediment ahead of the open shield machine; main-push-cum-retracting equipment 14 is installed in a starting shaft 13; the covering plate 12, wherein the bearing girder 22 is fixed to a lower part, is extruded by the equipment 14 along the steel material 21; and the covering plate 12 is installed in the upper part of the place subject to the excavation. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は、上下水道、共同溝、電信・電話などの付設地下道等の地下構造物をオープンシールド工法で市街地などに施工する場合の覆工板の布設方法および撤去方法に関するものである。   TECHNICAL FIELD The present invention relates to a method for laying and removing a lining board when an underground structure such as an attached underground passage such as a water and sewage system, a common ditch, a telegraph and a telephone is constructed in an urban area or the like by an open shield method.

オープンシールド工法は開削工法(オープンカット工法)とシールド工法の長所を活かした合理性に富む工法である。図14にその概略を示すと、図中1はオープンシールド機1で、これは左右の側壁板1aと、これら側壁板1aに連結する底板1bとからなる前面、後面および上面を開口したシールド機である。   The open shield method is a highly rational method that utilizes the advantages of the open cut method (open cut method) and the shield method. FIG. 14 schematically shows an open shield machine 1 in the figure, which is a shield machine having left, right and left side wall plates 1a and bottom plates 1b connected to the side wall plates 1a, with front, rear and top surfaces opened. It is.

このオープンシールド機1は、前記側壁板1aと底板1bの先端を刃口11として形成し、また側壁板1aの中央または後端近くに推進ジャッキ2を後方に向け上下に並べて配設する。図中3は隔壁を示す。   In this open shield machine 1, the front ends of the side wall plate 1a and the bottom plate 1b are formed as blade edges 11, and the propulsion jacks 2 are arranged in the vertical direction in the center or near the rear end of the side wall plate 1a. In the figure, 3 indicates a partition wall.

かかるオープンシールド機1を使用して施工するオープンシールド工法は、図示は省略するが、発進坑内にこのオープンシールド機1を設置して、オープンシールド機1の推進ジャッキ2を伸長して発進坑内の反力壁に反力をとってオープンシールド機1を前進させ、地下構造物を形成する第1番目のコンクリート函体4を上方から吊り降ろし、オープンシールド機1のテール部1c内で縮めた推進ジャッキ2の後方にセットする。推進ジャッキ2と反力壁との間にはストラットを配設して適宜間隔調整をする。   The open shield method to be constructed using such an open shield machine 1 is not shown in the figure, but this open shield machine 1 is installed in the start pit, and the propulsion jack 2 of the open shield machine 1 is extended so that the The open shield machine 1 is moved forward with the reaction force against the reaction wall, the first concrete box 4 forming the underground structure is suspended from above, and the propulsion is shrunk in the tail portion 1c of the open shield machine 1 Set behind jack 2. A strut is disposed between the propulsion jack 2 and the reaction wall to adjust the distance appropriately.

また、発進坑は土留壁で構成し、オープンシールド機1を発進させるにはこの土留壁を一部鏡切りするが、必要に応じて薬液注入などで発進坑の前方部分に地盤改良を施しておくこともある。   In addition, the start pit is made up of a retaining wall, and in order to start the open shield machine 1, a part of this retaining wall is mirror-cut. If necessary, the ground is improved at the front part of the starting pit by chemical injection or the like. Sometimes it is left.

ショベル等の掘削機9でオープンシールド機1の前面または上面から土砂を掘削しかつ排土する。この排土工程と同時またはその後に推進ジャッキ2を伸長してオープンシールド機1を前進させる。この前進工程の場合、コンクリート函体4の前にはボックス鋼材または型鋼を用いた枠体よりなる押角8を配設し、オープンシールド機1は後方にセットされたコンクリート函体4から反力をとる。   Excavator 9 such as an excavator excavates and removes soil from the front or top surface of open shield machine 1. At the same time as or after this earth removal step, the propulsion jack 2 is extended to advance the open shield machine 1. In the case of this forward process, a pushing angle 8 made of a frame made of box steel or mold steel is arranged in front of the concrete box 4, and the open shield machine 1 receives a reaction force from the concrete box 4 set rearward. Take.

そして第1番目のコンクリート函体4の前に第2番目のコンクリート函体4をオープンシールド機1のテール部1内で吊り降ろす。以下、同様の排土工程、前進工程、コンクリート函体4のセット工程を適宜繰り返して、順次コンクリート函体4をオープンシールド機1の前進に伴い縦列に地中に残置し、さらにこのコンクリート函体4の上面に埋戻土5を入れる。   Then, the second concrete box 4 is suspended in the tail portion 1 of the open shield machine 1 in front of the first concrete box 4. Thereafter, the same soil removal process, advance process, and setting process of the concrete box 4 are repeated as appropriate, and the concrete boxes 4 are sequentially left in the ground as the open shield machine 1 moves forward. Put backfill 5 on the upper surface of 4.

なお、コンクリート函体4をオープンシールド機1のテール部1c内に吊り降ろす際には、コンクリートブロック等による高さ調整材7をコンクリート函体4下に配設し、このテール部1c内でコンクリート函体4の左右および下部の空隙にグラウト材6を充填する。   When the concrete box 4 is suspended in the tail part 1c of the open shield machine 1, a height adjusting material 7 such as a concrete block is disposed under the concrete box 4, and the concrete part 4 is placed in the tail part 1c. The grout material 6 is filled in the left and right and lower spaces of the box 4.

このようにして、オープンシールド機1が到達坑まで達したならばこれを撤去して工事を完了する。   In this way, if the open shield machine 1 reaches the reaching mine, it is removed and the construction is completed.

このようなオープンシールド工法では、前記のごとくコンクリート函体4をオープンシールド機1の前進に伴い縦列に地中に残置し、コンクリート函体4は、オープンシールド機1のテール部1c内に吊り降ろされ、オープンシールド機1の前進とともに該テール部1cから出て地中に残されていくものであり、オープンシールド機1はこのように地中に残置したコンクリート函体4に反力をとって前進する。   In such an open shield construction method, as described above, the concrete box 4 is left in the ground in a column as the open shield machine 1 advances, and the concrete box 4 is suspended in the tail portion 1c of the open shield machine 1. As the open shield machine 1 moves forward, it leaves the tail portion 1c and remains in the ground. The open shield machine 1 takes a reaction force on the concrete box 4 left in the ground in this way. Advance.

コンクリート函体4は鉄筋コンクリート製で、図15に示すように左側板4a、右側板4bと上床板4cと下床板4dとからなる一体のもので、前後面が開口10として開放されている。   The concrete box 4 is made of reinforced concrete, and as shown in FIG. 15, is a unitary body including a left side plate 4 a, a right side plate 4 b, an upper floor plate 4 c and a lower floor plate 4 d, and the front and rear surfaces are opened as openings 10.

ところでこのようなオープンシールド工法によるコンクリート函体4の埋設は市街地の道路下で施工されることが多く、施工中は通行止めとなるが、一日のうちの一定の時間は道路を開放して通行可能とすることが義務付けられている。このため、オープンシールド機が発進坑から到達坑にまで到達するまでの間に、掘進を適宜中止し、オープンシールド機の上部開口すなわち道路の開削した部分に覆工板を布設して開口を一時的に閉塞し、この覆工板の上を自動車が走行し、また、人が歩行できるようにしている。   By the way, the burying of the concrete box 4 by such an open shield method is often carried out under the road in the city area, and the road is closed during the construction, but the road is opened for a certain time of day. It is obliged to make it possible. Therefore, until the open shield machine reaches from the start pit to the arrival mine, the excavation is appropriately stopped, and a lining plate is laid on the upper opening of the open shield machine, i.e., the cut part of the road, to temporarily open the opening. The vehicle is closed and the car runs on the lining board, and a person can walk.

この覆工板の布設は、従来、例えば、受桁を開口の側部に設置し、この上にクレーンなどで吊り上げた覆工板を一枚ずつ架け渡すようにして順次載せている。また、覆工板の撤去も布設の場合と反対の作業で行っている。   For laying the lining plate, conventionally, for example, a girder is installed on the side of the opening, and the lining plates lifted by a crane or the like are placed on the lining plate one by one. In addition, the removal of the lining plate is performed in the opposite operation to the case of laying.

前記先行技術は当業者間で一般的に行なわれているものであり、文献公知発明にかかるものではない。   The prior art is generally performed by those skilled in the art, and is not related to a known invention.

前記のような覆工板の設置方法では、手間を要してその分だけ工期が長引くだけでなく、規制される交通時間も長くなって交通に及ぼす影響が大きい。   The above-described method of installing the lining board not only requires time and labor, but also increases the restricted traffic time and has a great influence on traffic.

本発明の目的は前記従来例の不都合を解消し、オープンシールド工法でコンクリート函体を敷設する場合に、交通障害を少なくでき、工期の短縮も図ることができる覆工板の敷設および撤去方法を提供することにある。   An object of the present invention is to eliminate the disadvantages of the conventional example, and to lay and remove a lining plate that can reduce traffic obstacles and shorten the construction period when laying a concrete box by an open shield method. It is to provide.

本発明は前記目的を達成するため、請求項1記載の発明は、オープンシールド機の前面または上面開口より前方の土砂を掘削・排土する工程と、推進ジャッキを伸長してコンクリート函体を反力にしてシールド機を前進させる工程と、シールド機のテール部内で縮めた推進ジャッキの後方に新たなコンクリート函体をセットする工程とを適宜繰り返して順次コンクリート函体を縦列に埋設するオープンシールド工法において、前記オープンシールド機の前方の土砂を掘削・排土する工程の開始前に、掘削予定場所の両側に受桁ガイド鋼材を設置するとともに発進坑に元押し兼引戻し設備を設置し、下部に受桁材を固定した覆工板を前記受桁ガイド鋼材にそって前記元押し設備で押し出し、掘削予定場所の上部に覆工板を設置することを要旨とするものである。   In order to achieve the above object, the invention according to claim 1 includes a step of excavating and discharging soil in front of an open shield machine or a front opening of the open shield machine, and extending a propulsion jack to depress the concrete box. Open shield construction method in which concrete boxes are sequentially embedded in columns by repeating the process of moving the shield machine forward with force and the process of setting a new concrete box behind the propulsion jack shrunk in the tail of the shield machine. Before the start of the process of excavating and discharging the earth and sand in front of the open shield machine, install girder guide steel materials on both sides of the planned excavation site and install push-and-pull-back equipment on the starting pit, The gist is to push out the lining plate to which the girder material is fixed along the girder guide steel material by the main pushing equipment, and to install the lining plate at the upper part of the planned excavation place. Is shall.

請求項1記載の本発明によれば、土砂の掘削・排土、コンクリート函体の敷設に先行して覆工板を敷設して路面覆工し、土砂の掘削やコンクリート函体の敷設などの施工は、必要箇所の覆工板のみを外して施工することにより、日々の仮復旧工事を削減できる。これにより、規制される交通時間を短くでき、工期の短縮も図れる。また、覆工板は受桁とともに一体のものとして布設するから、設置が容易で、交通障害が少なく、布設に要する時間も短時間ですみ交通時間規制も少しですむ。   According to the first aspect of the present invention, prior to the excavation and earthing of earth and sand and the laying of the concrete box, the lining plate is laid and the road surface is covered, and the excavation of earth and sand and the laying of the concrete box, etc. The construction can be reduced by removing only the lining plates at the necessary locations for daily temporary restoration work. As a result, the restricted traffic time can be shortened and the construction period can be shortened. In addition, since the lining board is laid together with the girder, it is easy to install, has few traffic obstacles, requires less time for laying, and requires little traffic time regulation.

請求項2記載の発明は、発進坑に設置した元押し設備としてのピンジャッキを伸縮させて発進坑側から一方向に複数の覆工板を順次縦列に押し出して設置することを要旨とするものである。   The gist of the invention described in claim 2 is that the pin jack as the main pushing equipment installed in the start pit is expanded and contracted, and a plurality of lining plates are sequentially pushed out from the start pit side in one direction and installed. It is.

請求項2記載の本発明によれば、発進坑側から一方向に向けて複数の覆工板を同時に押し出せるから、交通障害を少なくでき、交通時間規制も少なくてすみ、また、覆工板敷設に必要な大型のクレーンなどが設置できない場所でも押し出しによって覆工板の敷設が可能となる。   According to the second aspect of the present invention, since a plurality of lining plates can be pushed out simultaneously in one direction from the starting pit side, traffic obstacles can be reduced and traffic time regulations can be reduced. Even in places where large cranes necessary for laying cannot be installed, lining plates can be laid by extrusion.

請求項3記載の発明は、前記受桁材は元押し設備にピン結合されることを要旨とするものである。   The gist of the invention described in claim 3 is that the girder material is pin-coupled to the main pushing equipment.

請求項3記載の本発明によれば、受桁材を元押し設備にピン結合することで、元押し設備による引戻しも容易に行うことが可能となる。   According to the third aspect of the present invention, it is possible to easily perform pulling back by the main pushing equipment by pin-connecting the girder material to the main pushing equipment.

請求項4記載の発明は、発進坑に反力材とベースコンクリートとを配設し、この反力材とベースコンクリートとで反力をとって引戻し設備としてのピンジャッキを縮めて受桁材およびその上に固定された覆工板を引戻すことを要旨とするものである。   In the invention according to claim 4, the reaction material and the base concrete are arranged in the starting pit, and the reaction force and the base concrete are used to reduce the pin jack as the pull-back equipment and The gist is to pull back the lining plate fixed thereon.

請求項4記載の本発明によれば、覆工板の撤去も発進坑側でピンジャッキを縮めるだけで一方向に覆工板をスライドさせて引戻すことにより行えるから、交通障害を少なくでき、また、交通時間規制も少なくできて、工期を短縮できる。また、ピンジャッキは、覆工板を布設する際に押し出すために使用したものを、縮めることで引戻し用のものとして使用できるから、引戻しのための設備を別途配設する必要はない。   According to the present invention of claim 4, the removal of the lining plate can also be performed by sliding the lining plate in one direction and pulling it back just by shrinking the pin jack on the start pit side, so that traffic obstacles can be reduced, In addition, traffic time restrictions can be reduced and the construction period can be shortened. In addition, since the pin jack can be used for pulling back the one used for laying out the lining board, it is not necessary to separately provide equipment for pulling back.

本発明のオープンシールド工法における覆工板の布設方法および撤去方法は、オープンシールド工法でコンクリート函体を敷設する場合に、オープンシールド工法による施工に先行して覆工板を布設して路面覆工を行うことにより、規制される交通時間を少なくでき、また、覆工板は発進坑から一方向に順次押し出すことにより交通障害を少なくでき、工期の短縮も図ることができる。覆工板の撤去も布設の場合と反対の作業で行えるから、さらに工期の短縮を図れるものである。   The laying method and removal method of the lining plate in the open shield method of the present invention are the road surface lining by laying the lining plate prior to the construction by the open shield method when laying the concrete box by the open shield method. As a result, the restricted traffic time can be reduced, and the obstacles can be reduced by sequentially pushing the lining board in one direction from the starting pit, and the construction period can be shortened. The removal of the lining plate can be done in the opposite operation to the case of laying, so that the construction period can be further shortened.

以下、図面について本発明の実施形態を詳細に説明する。図1は本発明のオープンシールド工法における覆工板の設置方法の実施形態を示す平面図、図2は同上縦断側面図で、本発明の覆工板の設置方法は、図14に示すようにオープンシールド機1を使用するオープンシールド工法でシールド機前方の土砂を掘削・排土して、ここに縦列にコンクリート函体4を埋設する工程に先行して施工予定場所の路面に、発進坑13側から到達坑の方向に向けて元押し兼引戻し設備14で覆工板12を押し出して布設し、路面覆工を行うものである。   Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is a plan view showing an embodiment of a method of installing a lining plate in the open shield method of the present invention, FIG. 2 is a longitudinal side view of the same as above, and the method of installing a lining plate of the present invention is as shown in FIG. The excavation and excavation of the soil in front of the shield machine using the open shield machine 1 and the process of burying the concrete box 4 in tandem here, on the road surface where the construction is planned, The lining plate 12 is pushed out and laid by the original pushing / retracting equipment 14 from the side toward the reaching pit, and road surface lining is performed.

元押し兼引戻し設備14は、図3、図4にも示すように発進坑13の周囲に打設した土留壁15の内側に設置するもので、土留壁15の内側に反力材16を設置し、この反力材16の前面に水平垂直方向に回動自在にピンジャッキ17を設置する。図中18は発進坑13に打設したベースコンクリートを示す。   As shown in FIG. 3 and FIG. 4, the former pushing and pulling equipment 14 is installed inside the retaining wall 15 placed around the start pit 13, and the reaction material 16 is installed inside the retaining wall 15. A pin jack 17 is installed on the front surface of the reaction force member 16 so as to be rotatable in the horizontal and vertical directions. In the figure, 18 indicates the base concrete placed in the start pit 13.

前記反力材16は、H鋼の組み合わせによるもので、土留壁15に接してベースコンクリート18上に水平に設置した反力材16aと、これと離間させて平行に設置した反力材16bと、これら反力材16a,16bの間に垂直に配設されてベースコンクリート18を貫通して打設した杭として機能する反力材16cとで構成し、反力材16a、16bと、反力材16cとはボルトで結合される。   The reaction material 16 is a combination of H steel, and a reaction material 16a installed horizontally on the base concrete 18 in contact with the retaining wall 15; and a reaction material 16b installed parallel to and spaced from the reaction material 16b. The reaction force members 16a and 16b are arranged vertically between the reaction force members 16a and 16b, and function as a pile driven through the base concrete 18. The reaction force members 16a and 16b and the reaction force The material 16c is coupled with bolts.

図中20はピンジャッキ17の前方に配設されるストラット、19はストラット20とベースコンクリート18との間に設けた調整材を示す。   In the figure, 20 is a strut disposed in front of the pin jack 17, and 19 is an adjusting material provided between the strut 20 and the base concrete 18.

次に、覆工板12を設置する方法を、図1、図2、図5〜図7について説明する。土留壁15で山留めして発進坑13を構築し、ここからコンクリート函体4の敷設予定場所の両側に、覆工板12を押し出すための覆工板12の受桁ガイド鋼材設置用の溝をバックホーなどの掘削機27で掘削し、この溝に受桁ガイド鋼材21を設置する。   Next, a method of installing the lining plate 12 will be described with reference to FIGS. 1, 2, and 5 to 7. A starting pit 13 is constructed by retaining the retaining wall 15 and a groove for installing a girder guide steel material for the lining plate 12 for pushing out the lining plate 12 on both sides of the place where the concrete box 4 is to be laid. The excavator 27 such as a backhoe is excavated, and the girder guide steel material 21 is installed in this groove.

この受桁ガイド鋼材21は、図5、図16(b)に示すように断面L字形のアングル材として、H形鋼による受台21aの上に設置するタイプの他に、図16(a)に示すように断面ロ字形の鋼材を受台21aとしてこの上にアングル材による受桁ガイド鋼材21を配設するタイプ、図16(c)に示すように受台21aもアングル材で構成し、同じ形状のアングル材を平板21bで結合して組み合わせて全体をクランク形状とするタイプ、図16(d)に示すように外向きに配置したアングル材による受桁ガイド鋼材21をH形鋼の受台21aに設置するタイプ、図16(e)に示すようにH形鋼による受桁ガイド鋼材21を2個上下にボルト結合して受桁ガイド鋼材21とし、3個のH形鋼を平板21bで横方向に結合した受台21aの上にボルトで結合するタイプなどが考えられ、いずれにしても後述の受桁を支持する段部を備える形状のものであればよく、受桁22の高さなどによって適宜選択する。   As shown in FIGS. 5 and 16 (b), this girder guide steel material 21 is an angle material having an L-shaped cross section, and in addition to the type installed on a pedestal 21a made of H-shaped steel, FIG. 16 (a). As shown in FIG. 16 (c), the pedestal 21a is also made of an angle material. An angle member of the same shape is joined by a flat plate 21b and combined to form a crank shape as a whole. As shown in FIG. As shown in FIG. 16 (e), two types of girder guide steel materials 21 made of H-shaped steel are bolted up and down to form a girder guide steel material 21 as shown in FIG. Of the cradle 21a coupled laterally at Etc. type of bolted is considered, as long as a shape with a stepped portion for supporting the 受桁 later in any event, selected as appropriate depending on the height of 受桁 22.

受桁ガイド鋼材21を設置した後、溝を埋め戻し、受桁ガイド鋼材21の設置を完了する。さらに発進坑13を掘削し、元押し兼引戻し設備14を設置し、前記したとおりの発進坑13を構築する(図3、図4参照)。   After installing the girder guide steel material 21, the groove is backfilled to complete the installation of the girder guide steel material 21. Further, the start pit 13 is excavated, the original push / retract facility 14 is installed, and the start pit 13 is constructed as described above (see FIGS. 3 and 4).

覆工板12を設置する予定場所をバックホーなどの掘削機27で掘削し、埋め戻した受桁ガイド鋼材21を露出させ、発進坑13内でベースコンクリート18上に覆工板12と受桁22とをセットする。   The place where the lining plate 12 is to be installed is excavated by an excavator 27 such as a backhoe, the back-filled girder guide steel material 21 is exposed, and the lining plate 12 and the girder 22 are placed on the base concrete 18 in the start pit 13. And set.

受桁22は図5〜図6にも示すように桁材としてH鋼を使用するもので、複数のH鋼を縦横に配置してボルト23で結合し、この上に複数の覆工板12を横列に配置してボルトで一体に接合する。そして、上部に覆工板12が一体に固定された受桁22をベースコンクリート18からピンジャッキ17で押し出して受桁ガイド鋼材21の上にスライド自在に設置する。   As shown in FIGS. 5 to 6, the receiving girder 22 uses H steel as a girder, and a plurality of H steels are arranged vertically and horizontally and connected by bolts 23. Are arranged in rows and joined together with bolts. Then, the receiving girder 22 with the cover plate 12 fixed integrally therewith is pushed out from the base concrete 18 by the pin jack 17 and is slidably installed on the girder guide steel material 21.

覆工板12が上部に固定された受桁22を受桁ガイド鋼材21の上に設置したならば、覆工板12の前方を掘削機9でさらに掘削した後、図1、図2に示すようにピンジャッキ17を受桁22に結合してピンジャッキ17を伸長するとともにストラット20を使用して覆工板12を受桁22とともに受桁ガイド鋼材21上をスライドさせるようにして前方に押し出す。この場合、覆工板12は複数枚を横列に結合し、ピンジャッキ17も複数(図示の例では3本)を配設して、複数の覆工板12を同時に推進する。押出しの反力は後方の地山から得る。   If the girder 22 with the lining plate 12 fixed to the upper part is installed on the girder guide steel material 21, the front of the lining plate 12 is further excavated by the excavator 9 and then shown in FIGS. 1 and 2. The pin jack 17 is coupled to the receiving girder 22 to extend the pin jack 17 and the strut 20 is used to push the lining plate 12 forward together with the receiving girder 22 so as to slide on the girder guide steel 21. . In this case, a plurality of the lining plates 12 are coupled in a row, and a plurality of pin jacks 17 (three in the illustrated example) are disposed to simultaneously propel the lining plates 12. The reaction force of extrusion is obtained from the back ground.

ピンジャッキ17と受桁22との結合構造は、図7に示すようにストラット20の先端に突設した水平片によるブラケット24と、受桁22に突設した水平片によるブラケット25とを相互に噛み合わせ、両ブラケット24,25を連結ピン26で結合するもので、ストラット20と受桁22とはピン結合により回動自在に結合される。   As shown in FIG. 7, the connecting structure of the pin jack 17 and the receiving girder 22 includes a bracket 24 made of a horizontal piece protruding from the end of the strut 20 and a bracket 25 made of a horizontal piece protruding from the receiving girder 22. The brackets 24 and 25 are engaged with each other by a connecting pin 26, and the strut 20 and the receiving girder 22 are rotatably connected by pin connection.

覆工板12を発進坑13から押し出したならば、次ぎにピンジャッキ17を収縮させて、発進坑13内のベースコンクリート18上に次の覆工板12および受桁22をセットする。そして、押し出されている最前列の覆工板12の前方をさらにバックホーなどの掘削機27で掘削した後、前回と同様にして横列に結合してある複数の覆工板12をピンジャッキ17で同時に前方に押し出し、これを繰り返して縦列に複数の覆工板12を順次押し出して、コンクリート函体の敷設予定場所の上部の路面に覆工板12を布設する。   When the lining plate 12 is pushed out from the start pit 13, the pin jack 17 is then contracted, and the next lining plate 12 and the receiving girder 22 are set on the base concrete 18 in the start pit 13. And after excavating the front of the lining board 12 of the front row | line | column pushed out further with excavators 27, such as a backhoe, the several lining board 12 couple | bonded with the row | line | column is carried out with the pin jack 17 like the last time. At the same time, it is pushed forward, and this is repeated to sequentially extrude a plurality of lining boards 12 in a column, and the lining board 12 is laid on the road surface above the place where the concrete box is to be laid.

かかる覆工板12の布設は、図1、図2からもわかるように布設方向に対して一方向から全ての作業が行え、予め施工した受桁ガイド鋼材21の上を滑らすようにして覆工板12と受桁22とを同時に押し出すから交通障害が少なく、交通時間規制も少なくてすむ。   As shown in FIGS. 1 and 2, the laying of the lining plate 12 can be carried out from one direction with respect to the laying direction, and the lining is carried out by sliding on the pre-constructed girder guide steel material 21. Since the board 12 and the girder 22 are pushed out at the same time, there are few traffic obstacles and less traffic time restrictions.

そして、図11、図12に示すように昼間の施工時には、全面交通止めにすることなく、片側交通とすることができ、図12、図13に示すように夜間は、道路全面に覆工板12を布設することで両側交通とすることができるが、かかる場合に交通に及ぼす影響を最小限にとどめることができる。   As shown in FIGS. 11 and 12, during construction in the daytime, it is possible to make one-sided traffic without stopping the entire traffic, and as shown in FIGS. By laying 12, the traffic can be made on both sides, but in such a case, the influence on the traffic can be minimized.

以上のようにして覆工板12を敷設した後、コンクリート函体4を設置するために必要な箇所のみ、覆工板12を取り除いて施工する。   After laying the lining plate 12 as described above, the lining plate 12 is removed and applied only to the portions necessary for installing the concrete box 4.

また、前記のように発進坑13側から一方向に向けて覆工板12を押し出すから、例えば施工場所の上方に高架橋が存在して覆工板12を吊り下ろすラフテレーンクレーンなどの重機を設置できない場合でも、施工予定場所への覆工板12の設置が可能となる。   Moreover, since the lining board 12 is pushed out in one direction from the start pit 13 side as described above, a heavy machine such as a rough terrain crane that hangs the lining board 12 with a viaduct present above the construction site is installed. Even when it is not possible, the lining plate 12 can be installed at the planned construction site.

以上のようにして覆工板12を敷設して路面覆工し、下部に地下構造物を構築しこれが完了したならば、今度は図8、図9に示すようにピンジャッキ17を収縮させ覆工板12を発進坑13側に引き戻し、覆工板12が敷設されていた場所をブルドーザ28で即時埋め戻す。これより、直ちに路面開放できる。これにより、施工が完了する。   As described above, the lining board 12 is laid and the road surface is covered. When the underground structure is constructed in the lower part and this is completed, the pin jack 17 is contracted and covered as shown in FIGS. The work board 12 is pulled back to the start pit 13 side, and the place where the lining board 12 is laid is immediately backfilled by the bulldozer 28. As a result, the road surface can be opened immediately. Thereby, construction is completed.

覆工板12の引戻しは、受桁22とピンジャッキ17がピン結合されているから容易に行える。引戻しの反力は反力材16、特に反力杭とし作用する反力材16cとベースコンクリート18のフリクションで得る。   The lining plate 12 can be pulled back easily because the receiving girder 22 and the pin jack 17 are pin-coupled. The reaction force for pulling back is obtained by the friction between the reaction material 16, particularly the reaction material 16 c acting as a reaction force pile and the base concrete 18.

本発明のオープンシールド工法における覆工板の布設方法の実施形態を示す平面図である。It is a top view which shows embodiment of the laying method of the lining board in the open shield method of this invention. 本発明のオープンシールド工法における覆工板の布設方法の実施形態を示す側面図である。It is a side view which shows embodiment of the laying method of the lining board in the open shield method of this invention. 本発明のオープンシールド工法における覆工板の布設方法および撤去方法が実施される発進坑の平面図である。It is a top view of the starting pit in which the laying method and the removal method of the lining board in the open shield method of this invention are implemented. 本発明のオープンシールド工法における覆工板の布設方法および撤去方法が実施される発進坑の縦断側面図である。It is a vertical side view of the starting pit in which the laying board laying method and the removal method in the open shield method of the present invention are implemented. 本発明のオープンシールド工法における覆工板の布設方法および撤去方法が実施される覆工板の正面図である。It is a front view of the lining board in which the laying method and the removal method of the lining board in the open shield method of this invention are implemented. 本発明のオープンシールド工法における覆工板の布設方法および撤去方法が実施される受桁の結合部の正面図である。It is a front view of the coupling | bond part of the receiving girder in which the laying board laying method and removal method in the open shield method of this invention are implemented. 本発明のオープンシールド工法における覆工板の布設方法および撤去方法が実施される覆工板とストラットの結合部の説明図である。It is explanatory drawing of the connection part of the lining board and strut in which the laying method and the removal method of the lining board in the open shield method of this invention are implemented. 本発明のオープンシールド工法における覆工板の撤去方法の実施形態を示す平面図である。It is a top view which shows embodiment of the removal method of the lining board in the open shield method of this invention. 本発明のオープンシールド工法における覆工板の撤去方法の実施形態を示す縦断側面図である。It is a vertical side view which shows embodiment of the removal method of the lining board in the open shield method of this invention. 本発明のオープンシールド工法における覆工板の布設方法が実施された昼間の施工例を示す平面図である。It is a top view which shows the construction example of the daytime in which the laying method of the lining board in the open shield method of this invention was implemented. 本発明のオープンシールド工法における覆工板の布設方法が実施された昼間の施工例を示す縦断側面図である。It is a vertical side view which shows the construction example of the daytime in which the laying method of the lining board in the open shield method of this invention was implemented. 本発明のオープンシールド工法における覆工板の布設方法が実施された夜間の施工例を示す平面図である。It is a top view which shows the construction example of the night in which the laying method of the lining board in the open shield method of this invention was implemented. 本発明のオープンシールド工法における覆工板の布設方法が実施された夜間の施工例を示す縦断側面図である。It is a vertical side view which shows the example of construction at night in which the laying method of the lining board in the open shield method of this invention was implemented. オープンシールド工法の概略を示す縦断側面図である。It is a vertical side view which shows the outline of an open shield construction method. コンクリート函体の斜視図である。It is a perspective view of a concrete box. 本発明のオープンシールド工法における覆工板の布設方法で使用される受桁ガイド鋼材および受台の縦断正面図である。It is a longitudinal front view of the girder guide steel material and cradle used in the laying method of the lining board in the open shield method of the present invention.

符号の説明Explanation of symbols

1 オープンシールド機 1a 側壁板
1b 底板 1c テール部
2 推進ジャッキ 3 隔壁
4 コンクリート函体
4a 左側板 4b 右側板
4c 上床板 4d 下床板
5 埋戻土 6 グラウト材
7 高さ調整材 8 押角
9 掘削機 10 開口
11 刃口 12 覆工板
13 発進坑 14 元押し兼引戻し設備
15 土留壁 16,16a,16b,16c 反力材
17 ピンジャッキ 18 ベースコンクリート
19 調整材 20 ストラット
21 受桁ガイド鋼材 21a 受台
21b 平板 22 受桁
23 ボルト 24 ブラケット
25 ブラケット 26 連結ピン
27 掘削機 28 ブルドーザ
DESCRIPTION OF SYMBOLS 1 Open shield machine 1a Side wall board 1b Bottom board 1c Tail part 2 Propulsion jack 3 Bulkhead 4 Concrete box 4a Left side board 4b Right side board 4c Upper floor board 4d Lower floor board 5 Backfill soil 6 Grout material 7 Height adjustment material 8 Pushing angle 9 Excavator DESCRIPTION OF SYMBOLS 10 Opening 11 Cutting edge 12 Covering board 13 Starting pit 14 Former push-and-pull-back equipment 15 Retaining wall 16, 16a, 16b, 16c Reaction material 17 Pin jack 18 Base concrete 19 Adjustment material 20 Strut 21 Girder guide steel material 21a Receiving base 21b Flat plate 22 Girder 23 Bolt 24 Bracket 25 Bracket 26 Connecting pin 27 Excavator 28 Bulldozer

Claims (4)

オープンシールド機の前面または上面開口より前方の土砂を掘削・排土する工程と、推進ジャッキを伸長してコンクリート函体を反力にしてシールド機を前進させる工程と、シールド機のテール部内で縮めた推進ジャッキの後方に新たなコンクリート函体をセットする工程とを適宜繰り返して順次コンクリート函体を縦列に埋設するオープンシールド工法において、前記オープンシールド機の前方の土砂を掘削・排土する工程の開始前に、掘削予定場所の両側に受桁ガイド鋼材を設置するとともに発進坑に元押し兼引戻し設備を設置し、下部に受桁材を固定した覆工板を前記受桁ガイド鋼材にそって前記元押し設備で押し出し、掘削予定場所の上部に覆工板を設置することを特徴とするオープンシールド工法における覆工板の布設方法。   The process of excavating and discharging soil in front of the front or top opening of the open shield machine, the process of extending the propulsion jack and advancing the shield machine with the concrete box as a reaction force, and shrinking in the tail part of the shield machine In the open shield construction method, in which the concrete box is sequentially embedded in series by repeating the process of setting a new concrete box behind the propulsion jack, the step of excavating and discharging soil in front of the open shield machine Before the start, install the girder guide steel on both sides of the planned excavation site, install the pushing and pulling equipment on the starting pit, and install the lining plate with the girder material fixed at the bottom along the girder guide steel A method for laying a lining plate in an open shield method, wherein the lining plate is pushed out by the main pushing equipment and a lining plate is installed at an upper portion of a planned excavation site. 発進坑に設置した元押し設備としてのピンジャッキを伸縮させて発進坑側から一方向に複数の覆工板を順次縦列に押し出して設置することを特徴とする請求項1記載のオープンシールド工法における覆工板の設置方法。   The open shield method according to claim 1, wherein a pin jack as a main pusher installed at the start pit is expanded and contracted, and a plurality of lining plates are sequentially pushed out from the start pit side in one direction and installed. How to install the lining board. 前記受桁材は元押し設備にピン結合されることを特徴とする請求項1または請求項2に記載の覆工板の布設方法。   The laying board laying method according to claim 1 or 2, wherein the girder material is pin-coupled to a main pushing facility. 発進坑に反力材とベースコンクリートとを配設し、この反力材とベースコンクリートとで反力をとって引戻し設備としてのピンジャッキを縮めて受桁材およびその上に固定された覆工板を引戻すことを特徴とする覆工板の撤去方法。   A reaction force material and base concrete are arranged in the starting pit, and the reaction force is taken by this reaction force material and the base concrete to shrink the pin jack as a pull-back equipment, and the girder material and the lining fixed on it. A method for removing a lining board, wherein the board is pulled back.
JP2004125253A 2004-04-21 2004-04-21 Laying method and removing method of lining plate in open shield method Expired - Lifetime JP3917146B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004125253A JP3917146B2 (en) 2004-04-21 2004-04-21 Laying method and removing method of lining plate in open shield method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004125253A JP3917146B2 (en) 2004-04-21 2004-04-21 Laying method and removing method of lining plate in open shield method

Publications (2)

Publication Number Publication Date
JP2005307544A true JP2005307544A (en) 2005-11-04
JP3917146B2 JP3917146B2 (en) 2007-05-23

Family

ID=35436623

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004125253A Expired - Lifetime JP3917146B2 (en) 2004-04-21 2004-04-21 Laying method and removing method of lining plate in open shield method

Country Status (1)

Country Link
JP (1) JP3917146B2 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010242373A (en) * 2009-04-06 2010-10-28 Makoto Uemura Installation method for covering plate in open shield method
JP2013204362A (en) * 2012-03-29 2013-10-07 Nippon Expressway Research Institute Co Ltd Abutment section breast wall improvement method
JP2016121523A (en) * 2014-12-25 2016-07-07 植村 誠 Road face lining method in propulsion-type open shield method
JP2017078304A (en) * 2015-10-21 2017-04-27 植村 誠 Road surface lining method
CN108071402A (en) * 2017-12-05 2018-05-25 北京交通大学 The micro- step construction method of loess tunnel
CN111720127A (en) * 2020-06-28 2020-09-29 中铁二局集团有限公司 Jacking platform for shield station crossing, shield station crossing system and construction method
JP7405912B1 (en) 2022-07-01 2023-12-26 誠 植村 Bottom widening repair method of existing fenced channel

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010242373A (en) * 2009-04-06 2010-10-28 Makoto Uemura Installation method for covering plate in open shield method
JP2013204362A (en) * 2012-03-29 2013-10-07 Nippon Expressway Research Institute Co Ltd Abutment section breast wall improvement method
JP2016121523A (en) * 2014-12-25 2016-07-07 植村 誠 Road face lining method in propulsion-type open shield method
JP2017053219A (en) * 2014-12-25 2017-03-16 植村 誠 Road surface lining method through jacking-type open shield technique
JP2017078304A (en) * 2015-10-21 2017-04-27 植村 誠 Road surface lining method
CN108071402A (en) * 2017-12-05 2018-05-25 北京交通大学 The micro- step construction method of loess tunnel
CN111720127A (en) * 2020-06-28 2020-09-29 中铁二局集团有限公司 Jacking platform for shield station crossing, shield station crossing system and construction method
JP7405912B1 (en) 2022-07-01 2023-12-26 誠 植村 Bottom widening repair method of existing fenced channel
JP2024006256A (en) * 2022-07-01 2024-01-17 誠 植村 Bottom widening repair method for existing fence conduit channel

Also Published As

Publication number Publication date
JP3917146B2 (en) 2007-05-23

Similar Documents

Publication Publication Date Title
JP6251375B2 (en) Road surface lining method in propulsion type open shield method
JP3917146B2 (en) Laying method and removing method of lining plate in open shield method
JP6629825B2 (en) Road lining method in open shield method
JP6194388B1 (en) Open shield method
JP5155236B2 (en) Installation method of lining board in open shield method
JPH0462230A (en) Setting construction for underground structure
JP4295272B2 (en) Friction cut plate used in open shield method and its fixing method
JP5639213B2 (en) Open shield method
JP4402640B2 (en) Open shield method
JP6276300B2 (en) Open shield method
JP4148047B2 (en) Open shield machine
JP4436401B2 (en) Open shield method and open shield machine
JP2668648B2 (en) Construction method of underground structure and starting pit used for it
JP3581332B2 (en) Earth retaining equipment and open-cutting method using it
JP3302661B2 (en) Open shield machine and construction method of underground structure using it
JP3333770B2 (en) Construction method for underground structures
JP4349570B2 (en) Construction method of division box and underground level crossing
JP3926818B2 (en) Installation method of concrete box
JP6871344B1 (en) Tunnel repair method and repair equipment for existing tunnels
JP3868959B2 (en) Waterway construction method
JP2024092472A (en) Method for open shield machine to enter arrival shaft in open shield construction method, and arrival shaft of open shield machine
JP6375334B2 (en) Road lining method
JP4060836B2 (en) Open shield method
JP2879429B2 (en) Open shield method and concrete box used for it
JP6121504B1 (en) Road lining method

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060726

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060926

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20061122

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20061122

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070206

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070207

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 3917146

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100216

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110216

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110216

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120216

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130216

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130216

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140216

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250