[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

JP2002194892A - Construction method of building - Google Patents

Construction method of building

Info

Publication number
JP2002194892A
JP2002194892A JP2000393517A JP2000393517A JP2002194892A JP 2002194892 A JP2002194892 A JP 2002194892A JP 2000393517 A JP2000393517 A JP 2000393517A JP 2000393517 A JP2000393517 A JP 2000393517A JP 2002194892 A JP2002194892 A JP 2002194892A
Authority
JP
Japan
Prior art keywords
floor slab
walls
constructing
building
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2000393517A
Other languages
Japanese (ja)
Inventor
Kenji Yoshimatsu
賢二 吉松
Hidehiko Watanabe
英彦 渡辺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP2000393517A priority Critical patent/JP2002194892A/en
Publication of JP2002194892A publication Critical patent/JP2002194892A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To shorten a construction period by efficiently constructing a horizontal part such as a floor slab in constructing a building such as a multiple dwelling house. SOLUTION: In this construction method of the building wherein columns 1 or walls 2 are vertically erected at specified spaces and a floor slab or the like is horizontally arranged between the columns 1 or walls 2, after the preceding construction of the columns 1 or walls 2 formed with a form 6 of the same plane cross section by a jump form construction method, the form 6 is jumped up, and then the horizontal part such as the floor slab is constructed.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は建物の構築方法に関
するものであり、特に、柱又は壁をジャンプフォーム工
法で先行して構築した後、該柱又は壁間に床スラブ等を
効率よく構築することができる建物の構築方法に関する
ものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a building, and more particularly to a method of constructing a floor or a slab between the pillars or walls efficiently after the columns or walls are previously constructed by a jump form method. It relates to a method of building a building that can do it.

【0002】[0002]

【従来の技術及び発明が解決しようとする課題】従来、
鉄筋コンクリート造の集合住宅等を構築する場合、1層
(1階分)ずつ躯体を構築する方法が一般的に行われて
いる。
2. Description of the Related Art
When building a reinforced concrete apartment house or the like, a method of building a frame by one layer (one floor) is generally used.

【0003】この施工方法は、コストが掛かり過ぎると
共に工期を短縮することが難しい。工期を短縮する方法
としては柱、梁及び床スラブをプレキャスト部材化する
ことも考えられるが、コストアップは避けられない。
又、壁(戸境壁)が何重にも連立する建築物の場合には
工期短縮効果は小さい。
[0003] This construction method is too costly and it is difficult to shorten the construction period. As a method of shortening the construction period, it is conceivable to convert columns, beams and floor slabs into precast members, but an increase in cost is inevitable.
Also, in the case of a building having multiple layers of walls (door border walls), the effect of shortening the construction period is small.

【0004】尚、壁(戸境壁)を効率的に施工する方法
としては、プレキャスト化するか、大型システム型枠を
用いて型枠の建て込み、脱型及び盛り替えを効率的に行
う方法も行われているが、プレキャスト化はコストアッ
プするし、大型システム型枠での施工はかなり大規模な
建築物でないと転用効果が現われてこない等の問題があ
る。
[0004] As a method of efficiently constructing a wall (door boundary wall), a method of precasting or a method of efficiently constructing, removing and replacing a form using a large system form is used. However, there are problems in that precasting increases the cost, and construction with a large system formwork does not produce a diversion effect unless it is a fairly large building.

【0005】一方、構築しようとする構造体の周囲に型
枠を配置すると共に、該型枠内にコンクリートを打設
し、コンクリート硬化後、予め、コンクリート内に埋設
したアンカー等により反力を取りながら電動油圧装置等
により前記型枠を上昇させ、尺取り虫のような動きで型
枠を盛り替える工程を繰り返すジャンプフォーム工法
は、専ら大煙突やサイロ、橋脚等の中間階に床のない建
築物で施工されているのみで、集合住宅等の一般建物で
は実施されていない。
On the other hand, a formwork is placed around the structure to be constructed, concrete is poured into the formwork, and after the concrete is hardened, the reaction force is removed by an anchor or the like buried in the concrete in advance. The jump form method that repeats the process of raising and lowering the formwork with an electric hydraulic device and reshaping the formwork with a movement like a measuring insect is exclusively used for buildings with no floor on the middle floor such as large chimneys, silos, piers, etc. It has only been constructed and has not been implemented in general buildings such as apartment houses.

【0006】そこで、集合住宅等の建物を構築する際、
ジャンプフォーム工法を応用して工事費の大幅低減化及
び大幅な工期短縮を可能にすることができる建物の構築
方法を得るために解決すべき技術的課題が生じてくるの
であり、本発明は該課題を解決することを目的とする。
Therefore, when constructing a building such as an apartment house,
The technical problem to be solved arises in order to obtain a building construction method that can greatly reduce the construction cost and significantly shorten the construction period by applying the jump form method, and the present invention The purpose is to solve the problem.

【0007】[0007]

【課題を解決するための手段】本発明は上記目的を達成
するために提案されたものであり、柱又は壁を所定間隔
で垂直に立設し、且つ、該柱又は壁間に水平に床スラブ
等を配設する建物の構築方法に於て、同一平面断面の型
枠で形成される該柱又は壁をジャンプフォーム工法によ
り先行して構築した後、該型枠をジャンプアップし、そ
の後、該床スラブ等の水平部分を構築する建物の構築方
法、及び柱又は壁を所定間隔で垂直に立設し、且つ、該
柱又は壁間に水平に床スラブ等を配設する建物の構築方
法に於て、該柱又は壁をジャンプフォーム工法で構築す
るとき、該柱又は壁に対する該床スラブの設置予定位置
に予め埋込み金具を該柱又は壁の外面に合せて設置し、
コンクリートを打設して該柱又は壁を構築した後、該埋
込み金具の下部近傍に該床スラブとなる床スラブ板を支
持する受具を固着し、更に、該受具間に該床スラブ板を
架設する建物の構築方法、及び、柱又は壁を所定間隔で
垂直に立設し、且つ、該柱又は壁間に水平に床スラブ等
を配設する建物の構築方法に於て、該柱又は壁をジャン
プフォーム工法で構築するとき、該柱又は壁に対する該
床スラブの設置予定位置に予め凹部形成用型枠を設置
し、コンクリートを打設して該柱又は壁を構築した後、
該凹部形成用型枠を撤去し、該柱又は壁に凹部を形成
し、該凹部内に該床スラブとなる床スラブ板を架設する
建物構築方法、及び、前記床スラブ板は、前記柱又は壁
間の中央部近傍で分割された長さのものを用い、該床ス
ラブ板を前記受具又は前記凹部と中央部近傍に設置する
支持台間に複数架設して前記床スラブを形成する建物の
構築方法、並びに、前記受具又は前記凹部内に前記床ス
ラブ板を設置する際、該床スラブ板の両端近傍に玉掛け
ワイヤを掛け渡すと共に、該玉掛けワイヤの一方には吊
り治具を取り付け、前記柱又は壁間に吊下げ時には該吊
り治具で該玉掛けワイヤの一方を巻き上げて該床スラブ
板を傾斜させ、更に、該柱又は壁間に架設時には該吊り
治具で該玉掛けワイヤの一方を伸ばしながら該床スラブ
板を水平にする建物の構築方法を提供するものである。
SUMMARY OF THE INVENTION The present invention has been proposed to achieve the above-mentioned object, in which columns or walls are vertically erected at predetermined intervals, and floors are horizontally placed between the columns or walls. In the method of constructing a building in which slabs and the like are arranged, after the pillars or walls formed by the formwork having the same plane cross section are constructed in advance by the jump form method, the formwork is jumped up, and thereafter, A method for constructing a building for constructing a horizontal portion such as the floor slab, and a method for constructing a building wherein pillars or walls are vertically erected at predetermined intervals and a floor slab or the like is horizontally arranged between the pillars or walls. In constructing the pillar or wall by the jump form method, an embedding metal fitting is installed in advance at an installation position of the floor slab with respect to the pillar or wall in accordance with the outer surface of the pillar or wall,
After casting the concrete to construct the pillar or wall, a support for supporting the floor slab plate serving as the floor slab is fixed near the lower part of the embedding metal fitting, and further, the floor slab plate is interposed between the support members. And a method of constructing a building in which pillars or walls are vertically erected at predetermined intervals and a floor slab or the like is horizontally arranged between the pillars or walls. Or, when constructing the wall by the jump form method, after setting the recess forming form in advance at the installation position of the floor slab with respect to the column or wall, and after casting the concrete to construct the column or wall,
Removing the formwork for forming the concave portion, forming a concave portion in the column or the wall, constructing a floor slab plate serving as the floor slab in the concave portion, and the floor slab plate is the column or the A building in which the floor slab is formed by using a plurality of floor slab plates which are divided in the vicinity of the center between the walls and which are erected between the receiving member or the concave portion and the support base installed near the center. Construction method, and, when installing the floor slab plate in the receiver or the recess, while hanging a sling wire near both ends of the floor slab plate, and attaching a hanging jig to one of the sling wires When suspending between the columns or walls, one of the sling wires is wound up by the suspending jig to incline the floor slab plate, and when suspended between the pillars or walls, the hanging jig is used to suspend the sling wires. A building where the floor slab is leveled while extending one side There is provided a construction method.

【0008】[0008]

【発明の実施の形態】以下、本発明の実施の形態を図1
乃至図9に従って詳述する。図1はRC構造で構築され
る集合住宅の平面図を示し、外周には所定間隔で垂直に
柱1,1…を立設し、該柱1,1…の図の左右方向には
梁3,3…を掛け渡し、且つ、該柱1,1…の図の上下
方向には壁(戸境壁)2,2…を配設し、更に、該壁
2,2…と該梁3,3…とで囲まれた空間には床スラブ
4,4…を構築する。従って、平面形状がハーモニカタ
イプ構造躯体の中高層集合住宅を構築することになる。
FIG. 1 is a block diagram showing an embodiment of the present invention.
This will be described in detail with reference to FIG. FIG. 1 is a plan view of an apartment house constructed by the RC structure, in which columns 1, 1... , 3 ..., and walls (door boundary walls) 2, 2, ... in the vertical direction in the figure of the pillars 1, 1, ..., and furthermore, the walls 2, 2, ... and the beams 3, Floor slabs 4, 4 ... are constructed in the space surrounded by 3 ... Accordingly, a mid- to high-rise apartment house having a harmonica-type structure skeleton in plan view will be constructed.

【0009】尚、図示は省略するが、該柱1,1…の両
方の外側には夫々所定幅の廊下及びバルコニーを構築す
る。
Although not shown, corridors and balconies having a predetermined width are respectively constructed outside both of the pillars 1, 1,....

【0010】構造躯体の施工方法としてジャンプフォー
ム工法を採用し、図2に示すようにジャンプフォーム装
置5,5…を利用して同一平面断面の型枠6(図3参
照)で形成される前記柱1,1…及び前記壁2,2…を
先行して構築し、その後、該型枠6をジャンプアップ
し、2層(2階分)程度遅れて水平に配設される前記梁
3,3…を構築し、更に、前記床スラブ4,4…を水平
に構築することとする。
As shown in FIG. 2, a jump form method is employed as a method of constructing the structural frame, and the form 6 is formed with a form frame 6 (see FIG. 3) having the same plane cross section by using jump form devices 5, 5,. .. And the walls 2, 2... Are built in advance, and then the formwork 6 is jumped up and the beams 3, which are horizontally arranged with a delay of about two layers (two floors). 3 are constructed, and the floor slabs 4, 4 are constructed horizontally.

【0011】尚、前記構造躯体の垂直部分を壁だけで構
成する場合もあるが、この場合に於ても前記と同様の施
工方法を用いる。又、該柱1又は該壁2を構築すると
き、後述するように該床スラブ4を設置するための受部
を形成するようにする。
In some cases, the vertical portion of the structural body may be constituted only by walls. In this case, the same construction method as described above is used. When the pillar 1 or the wall 2 is constructed, a receiving portion for installing the floor slab 4 is formed as described later.

【0012】次に、図3によりジャンプフォーム工法を
説明する。図3(a)は該柱1及び該壁2の外周に囲繞
して設置されるジャンプフォーム装置5の断面図であ
る。該ジャンプフォーム装置5の下部両側には該柱1に
沿ってクライミングするクライミング機構8を設け、ク
ライミングレール(図示せず)を上昇させると共に該ク
ライミングレールに沿って該ジャンプフォーム装置5を
上昇させる。
Next, the jump form method will be described with reference to FIG. FIG. 3A is a cross-sectional view of a jump form device 5 installed around the outer circumference of the pillar 1 and the wall 2. A climbing mechanism 8 for climbing along the column 1 is provided on both lower sides of the jump form device 5 to raise a climbing rail (not shown) and raise the jump form device 5 along the climbing rail.

【0013】又、該ジャンプフォーム装置5の上部両側
には、該柱1及び該壁2の幅厚間隔を保持する伸縮機構
7,7を介して所定長さの型枠6,6を配設する。今、
1,2階の柱1及び壁2を構築した後、3階の柱を構築
する。先ず、3階の柱鉄筋9を組み終った位置に、該伸
縮機構7,7を調整して該型枠6,6をセットし、該型
枠6,6間にコンクリートを打設し1階分の柱構築を完
了する。
On both sides of the upper part of the jump form device 5, form frames 6, 6 of a predetermined length are provided via expansion mechanisms 7, 7 for maintaining the width and thickness intervals of the column 1 and the wall 2. I do. now,
After the first and second floor pillars 1 and the wall 2 are constructed, the third floor pillars are constructed. First, the telescopic mechanisms 7, 7 are adjusted to set the formwork 6, 6 at the position where the column reinforcing bar 9 on the third floor has been assembled, and concrete is poured between the formwork 6, 6 to make the first floor. Complete construction of the minutes pillar.

【0014】次に、図3(b)に示すように該ジャンプ
フォーム装置5をジャンプアップして4階分の柱構築に
移る。その後、2階の梁3,3及び床スラブ4の水平部
分の構築を行う。このようにジャンプフォーム工法は、
従来のスリップフォーム工法のように小さい幅のコンク
リートを徐々に打ち上げて行く方法と違い、例えば3m
位のスパンのコンクリートを一度に打設していくので該
ジャンプフォーム工法を活用すれば、同じ断面である柱
及び壁を先行して構築でき、大幅な工期短縮が図れる。
Next, as shown in FIG. 3 (b), the jump form device 5 jumps up to move to the construction of pillars for four floors. Thereafter, the horizontal portions of the beams 3 and 3 and the floor slab 4 on the second floor are constructed. In this way, the jump form method is
Unlike the method of gradually launching concrete with a small width like the conventional slip form method, for example, 3m
Since concrete of the same span is cast at a time, if the jump form method is used, columns and walls having the same cross section can be constructed in advance, and the construction period can be significantly reduced.

【0015】更に、床スラブが設置できる高さの柱又は
壁を同時に複数構築することにより、尚一層大幅な工期
短縮が図れる。
Further, by simultaneously constructing a plurality of columns or walls having a height at which a floor slab can be installed, the construction period can be further greatly reduced.

【0016】次に、図4に従い前記柱1,1…及び前記
壁2,2…の構築後、略2階分遅れて該壁2,2間に床
スラブ4を効率よく構築する方法を説明する。先ず、前
記ジャンプフォーム装置5で該壁2を構築する際、該壁
2の両側の該床スラブ4の設置予定位置に予め、該床ス
ラブ4の垂直高さより大きい幅の埋込み金具13を設置
しておく。
Next, a method of efficiently constructing the floor slab 4 between the walls 2, 2 after the construction of the columns 1, 1,... And the walls 2, 2,. I do. First, when constructing the wall 2 with the jump form device 5, an embedding metal fitting 13 having a width larger than the vertical height of the floor slab 4 is set in advance at the installation position of the floor slab 4 on both sides of the wall 2. Keep it.

【0017】該埋込み金具13は鋼板で構成され、該壁
2の外面と面一になるように設置し、内側の両端部近傍
には所定長さのスタッドボルト14,14を固着しコン
クリートCを打設したとき該壁2と一体化するようにす
る。又、該埋込み金具13の下部近傍には前記床スラブ
4となる床スラブ板10の下部を支持するアングル材か
らなる受具16を固着する。該受具16の固着方法は、
予め該埋込み金具13に螺子部(図示せず)を設けてボ
ルトで固着してもよく、又、溶着してもよい。
The embedding metal fitting 13 is made of a steel plate, and is installed so as to be flush with the outer surface of the wall 2. Stud bolts 14, 14 having a predetermined length are fixed near both inner end portions, and concrete C is formed. When it is cast, it is integrated with the wall 2. A receiving member 16 made of an angle material for supporting a lower portion of the floor slab plate 10 serving as the floor slab 4 is fixed near the lower portion of the embedding metal fitting 13. The fixing method of the receiver 16 is as follows.
A screw portion (not shown) may be provided in advance on the embedded metal fitting 13 and fixed with a bolt or welded.

【0018】更に、該受具16上に該床スラブ板10を
水平に架設する。該床スラブ板10はハーフプレキャス
ト板で上部に上スラブ筋11を配設し、下部のプレキャ
スト部とトラス筋12で結合されている。該上スラブ筋
11の上部近傍には、該上スラブ筋11と平行に該埋込
み金具13に所定長さのスタッド差し筋15を固着し、
前記床スラブ板10上にコンクリートを該スタッド差し
筋15の上方まで打設して該床スラブ板10と前記壁2
とをピン結合して一体化を図る。
Further, the floor slab plate 10 is horizontally laid on the receiving member 16. The floor slab plate 10 is a half precast plate with an upper slab bar 11 disposed at the upper part, and is connected to a lower precast part by a truss bar 12. In the vicinity of the upper part of the upper slab streaks 11, a stud insertion bar 15 having a predetermined length is fixed to the embedding fitting 13 in parallel with the upper slab streaks 11,
Concrete is cast on the floor slab plate 10 to a position above the stud bar 15 and the floor slab plate 10 and the wall 2
And are integrated with each other by pins.

【0019】従って、該床スラブ板10と該壁2とは該
埋込み金具13を介して確実に、且つ、強力に一体化す
ることができる。
Therefore, the floor slab plate 10 and the wall 2 can be surely and strongly integrated with each other through the embedding fitting 13.

【0020】尚、該床スラブ板10の据え付けはクレー
ン(図示せず)によって行うが、図5に示すように該壁
2の上部に前記ジャンプフォーム装置5,5があり、該
壁2,2間一杯の幅の床スラブ板10を用いた場合、上
部からの据え付けは該ジャンプフォーム装置5,5が邪
魔になり、且つ、横方向からの据え付けもかなり困難と
なる。そこで、該床スラブ板10を該壁2,2間の中央
部近傍で分割された長さのものを用いて据え付けし易い
ようにする。この場合、該壁2,2間の中央部近傍に下
階の床スラブ4上からスタンド型の支持台17を立設
し、前記受具16又は後述する凹部25との間に該床ス
ラブ板10を複数架設して前記床スラブ4を形成する。
The floor slab plate 10 is installed by a crane (not shown). As shown in FIG. When the floor slab 10 having a full width is used, the installation from the upper side hinders the jump-form devices 5 and 5 and the installation from the lateral direction becomes considerably difficult. Therefore, the floor slab plate 10 has a length divided near the center between the walls 2 and 2 to facilitate installation. In this case, a stand-type support base 17 is erected from the floor slab 4 on the lower floor near the center between the walls 2 and 2, and the floor slab plate is placed between the support 16 and a recess 25 described later. The floor slab 4 is formed by erection of a plurality of 10s.

【0021】次に図6及び図7に従い他の実施の形態を
説明する。図6は前記ジャンプフォーム装置5に設けら
れている型枠6の側面であって、該型枠6の前記壁2側
に凹部形成用型枠18を取り付けた側断面図である。該
凹部形成用型枠18は、図7に示すように前記床スラブ
板10を該壁2内に据え付けるための凹部25を形成す
るためのものであり、予め該壁2の両側の該床スラブ板
10の設置予定位置に設置して置く。該凹部形成用型枠
18の下部は該床スラブ板10の設置を水平にするため
に該壁2に対し水平に形成し、上部は該床スラブ板10
と該壁2との結合をし易くするために該壁2の内側に向
けて傾斜を付ける。
Next, another embodiment will be described with reference to FIGS. FIG. 6 is a side sectional view of a side surface of the mold 6 provided in the jump form device 5, in which a mold 18 for forming a concave portion is attached to the wall 2 of the mold 6. The recess forming mold 18 is for forming a recess 25 for installing the floor slab plate 10 in the wall 2 as shown in FIG. 7, and the floor slabs on both sides of the wall 2 are previously formed. The plate 10 is set and placed at the planned position. The lower part of the recess forming form 18 is formed horizontally with respect to the wall 2 in order to make the installation of the floor slab board 10 horizontal, and the upper part is formed of the floor slab board 10.
The wall 2 is inclined toward the inside to facilitate the connection with the wall 2.

【0022】又、該凹部形成用型枠18の該壁2内の幅
や深さは該床スラブ板10の支持荷重等により決定し、
且つ、高さは該床スラブ板10の厚さ等により決定し、
その全体形状は外周をプレートで内空状に形成し、その
材料は鋼材、木材、プラスチック材等で形成する。更
に、該凹部形成用型枠18の下部近傍の前記型枠6側に
は、該型枠6よりボルト19を挿入し、該凹部形成用型
枠18の内空側に設けた螺子部20に螺合させて該凹部
形成用型枠18を該型枠6に固着する。
The width and depth of the recess forming mold 18 in the wall 2 are determined by the supporting load of the floor slab plate 10, and the like.
And the height is determined by the thickness of the floor slab plate 10 and the like,
The whole shape is formed by a plate having an inner periphery formed in an inner space, and its material is formed of steel, wood, plastic or the like. Further, a bolt 19 is inserted from the mold frame 6 into the mold frame 6 near the lower portion of the recess-forming mold frame 18, and a screw portion 20 provided on the inner space side of the recess-forming mold frame 18 is inserted. The concave portion forming mold 18 is fixed to the mold 6 by screwing.

【0023】又、該壁2内の上部には、図7に示すよう
に前記床スラブ板10の上スラブ筋11の下部近傍に平
行に配設する差筋26を取り付けるための差筋アンカ2
2を該凹部形成用型枠18の内側のプレートの外側に接
して配設する。該差筋アンカ22は円柱状に形成すると
共に、前記差筋26を螺着させるための螺子部24を中
心部に設ける。該凹部形成用型枠18の設置時には、該
螺子部24にボルト23を螺着して該凹部形成用型枠1
8と該差筋アンカ22とを固着して置く。その後、コン
クリートを打設して該壁2を構築し、該凹部形成用型枠
18を脱型するときは、先ず、前記ボルト19を取り外
し、更に、該凹部形成用型枠18の上部の前記型枠6側
に設けられる開口部21より前記ボルト23を取り外す
ことにより行う。
On the upper part of the wall 2, as shown in FIG. 7, a reinforcing bar anchor 2 for attaching a reinforcing bar 26 arranged in parallel with the floor slab plate 10 in the vicinity of the lower portion of the upper slab bar 11 is provided.
2 is disposed in contact with the outside of the plate inside the concave forming mold 18. The streak anchor 22 is formed in a cylindrical shape, and a screw portion 24 for screwing the streak 26 is provided at the center. At the time of installation of the recess forming mold 18, a bolt 23 is screwed into the screw portion 24 so that the recess forming mold 1
8 and the streak anchor 22 are fixedly placed. Thereafter, when the wall 2 is constructed by casting concrete, and the mold 18 for forming the concave portion is removed from the mold, first, the bolt 19 is removed, and further, the upper portion of the mold 18 for forming the concave portion is removed. This is performed by removing the bolt 23 from the opening 21 provided on the mold frame 6 side.

【0024】該凹部形成用型枠18を撤去した該壁2に
は、図7に示すように凹部25が形成されると共に所定
の箇所に前記差筋アンカ22が埋設される。その後、図
7に示すように、該凹部25内に前記ハーフプレキャス
ト板からなる床スラブ板10を水平に架設する。該差筋
アンカ22に前記差筋26を螺合した後、該床スラブ板
10上にコンクリートCを該差筋26及び前記上スラブ
筋11の上方まで打設して該床スラブ板10と前記壁2
とを剛結合して一体化する。
As shown in FIG. 7, a recess 25 is formed in the wall 2 from which the recess forming mold 18 has been removed, and the difference anchor 22 is embedded at a predetermined position. Thereafter, as shown in FIG. 7, the floor slab plate 10 made of the half precast plate is horizontally installed in the concave portion 25. After screwing the reinforcing bar 26 to the reinforcing bar anchor 22, concrete C is poured onto the floor slab plate 10 above the reinforcing bar 26 and the upper slab bar 11, and the floor slab plate 10 and the Wall 2
And are rigidly connected to be integrated.

【0025】従って、該床スラブ板10と該壁2とは該
差筋26を介して確実に、且つ、強力に一体化すること
ができる。尚、図中の27は梁筋を、28は壁筋を示
す。
Accordingly, the floor slab plate 10 and the wall 2 can be surely and strongly integrated with each other through the reinforcing bars 26. In addition, 27 in a figure shows a beam reinforcement and 28 shows a wall reinforcement.

【0026】次に、図8により該床スラブ板10の据え
付け方法を説明する。前述の据え付け方法は該床スラブ
板10を分割して据え付け易くしたが、該床スラブ板1
0を小割りにすることにより施工工数は増加し、工期は
延長されることになる。そこで、大版の床スラブ板10
を一気に据え付けるため、図8(a)に示すようにクレ
ーン(図示せず)のワイヤ32が掛け渡されたフック3
1に該床スラブ板10を水平に吊り下げる玉掛けワイヤ
30の一方に吊り治具29を取り付ける。該吊り治具2
9は無線によりリモートコントロール可能にした電動チ
ェーンブロックで、その構成はチェーンブロック本体と
レシーバ付きドライバと発信機付きコントローラからな
っている。
Next, a method of installing the floor slab plate 10 will be described with reference to FIG. Although the above-described installation method splits the floor slab board 10 to facilitate installation, the floor slab board 1
By subdividing 0, the number of construction steps increases, and the construction period is extended. Therefore, the large-sized floor slab board 10
8A, the hook 3 around which the wire 32 of the crane (not shown) is stretched as shown in FIG.
A hanging jig 29 is attached to one of the slinging wires 30 for suspending the floor slab board 10 horizontally. The hanging jig 2
Reference numeral 9 denotes an electric chain block that can be remotely controlled by radio, and has a structure including a chain block main body, a driver with a receiver, and a controller with a transmitter.

【0027】図8(b)に示すように、前記ジャンプフ
ォーム装置5,5間に前記床スラブ板10を吊下げる時
には、該吊り治具29の操作で前記玉掛けワイヤ30の
一方を巻き上げて該床スラブ板10を傾斜させ、更に、
前記フック31の下降と共に該吊り治具29の操作で該
玉掛けワイヤ30の一方を伸ばして徐々に水平になるよ
うにする。その後、該床スラブ板10の一方の端部を予
め構築した凹部25に挿入し、該吊り治具29を調整し
ながら該床スラブ板10の姿勢制御を行いながら一方の
端部を対峙する凹部に挿入して、水平に前記壁2,2間
に据え付ける。このように、予め構築した凹部25,2
5と該吊り治具29の操作により該床スラブ板10を容
易に、且つ、確実に該壁2,2間に据え付けられるた
め、工期の短縮が更に進む。
As shown in FIG. 8 (b), when suspending the floor slab plate 10 between the jump form devices 5, 5, one of the slinging wires 30 is wound up by operating the suspending jig 29. The floor slab board 10 is inclined,
As the hook 31 is lowered, one of the slinging wires 30 is extended by operating the suspending jig 29 so as to gradually become horizontal. Thereafter, one end of the floor slab plate 10 is inserted into the recess 25 constructed in advance, and the posture of the floor slab plate 10 is controlled while the posture of the floor slab plate 10 is controlled while adjusting the suspending jig 29. And installed horizontally between the walls 2,2. As described above, the recesses 25 and 2 constructed in advance are used.
The floor slab plate 10 can be easily and reliably installed between the walls 2 and 2 by operating the hanging jig 29 and the hanging jig 29, so that the construction period is further reduced.

【0028】尚、該壁2と該床スラブ板10との接合は
施工現場の状況によっては、図9に示すように該壁2に
設ける差筋アンカ33に直接前記差筋26を打ち込み、
更に、該床スラブ板10の端部を支持具34上の受台3
5に支持させて床スラブを構築する。この方法は、該支
持具34を設置する下階の床スラブのコンクリートの強
度が十分に発現されていることが条件となるので、前記
方法に比べて工期の短縮に於ては幾分劣る。
The joining of the wall 2 and the floor slab plate 10 is performed by directly driving the reinforcing bar 26 into the reinforcing bar anchor 33 provided on the wall 2 as shown in FIG.
Further, the end of the floor slab plate 10 is
5 to build a floor slab. This method requires that the concrete of the floor slab on the lower floor where the support member 34 is installed has sufficient strength, so that the method is somewhat inferior in shortening the construction period as compared with the above method.

【0029】次に、本発明を用いた集合住宅構築に於け
るサイクル工程を説明する。今、図1に示す集合住宅の
平面図に於て、壁2,2間の幅を6m、上部の柱1と下
部の柱1との間の幅を10m、左右の壁2,2で区画さ
れた戸数を6戸とし、更に、該柱1,1…の外側に夫々
所定幅のバルコニー及び廊下を設けた場合を検討する。
Next, the cycle steps in the construction of an apartment house using the present invention will be described. Now, in the plan view of the apartment house shown in FIG. 1, the width between the walls 2 and 6 is 6 m, the width between the upper pillar 1 and the lower pillar 1 is 10 m, and the left and right walls 2 and 2 are partitioned. Consider the case where the number of houses is set to six, and furthermore, balconies and corridors of a predetermined width are provided outside the pillars 1, 1,..., Respectively.

【0030】先ず、区画された1戸(1単位当り)の施
工時間を検討する。初めに、柱1,1…及び壁2の垂直
部分を施工するに当り、ジャンプフォーム装置の上昇
準備及び上昇に1時間、柱筋組立(ユニット)に30
分、壁筋組立に2時間、型枠建込みに2時間、コ
ンクリート打設に2時間掛かり、朝8時に作業開始した
場合、午前中に壁筋組立までを、午後から型枠建込み及
びコンクリート打設を行い、17時に作業を完了させる
ことができる。
First, the construction time of one partitioned unit (per unit) will be examined. Firstly, in constructing the vertical portions of the columns 1, 1 ... and the wall 2, it is necessary to prepare for the ascent of the jump form device and to ascend for 1 hour, and to assemble the column reinforcements (units) 30 hours.
Minutes, 2 hours for wall reinforcement, 2 hours for formwork construction, 2 hours for concrete placement, if work starts at 8:00 in the morning, until wall reinforcement in the morning, formwork and concrete in the afternoon. Casting can be performed and the work can be completed at 17:00.

【0031】次に、柱及び壁の構築より2階分遅れて施
工する水平部分の梁及び床スラブ等の1単位当りの施工
時間は、図1の左右方向へのプレキャスト梁(2本)
のセットに1時間、梁接合、接合部の配筋及び型枠セ
ットに2時間、ハーフプレキャスト板(4枚)のセッ
トに1時間、バルコニー及び廊下のプレキャスト板の
セットに1時間、床スラブ筋の配筋等に4時間、コ
ンクリート打設に2時間掛り、朝8時に作業開始した場
合、午前中に梁関係の作業を終了させ、午後から次の日
の午前中にかけてハーフプレキャスト板のセットからコ
ンクリート打設までの作業を完了させることができる。
Next, the construction time per unit of horizontal beams and floor slabs to be constructed two floors later than the construction of columns and walls is the precast beam in the horizontal direction in FIG. 1 (two).
1 hour for set, 2 hours for beam joint, joint arrangement and formwork set, 1 hour for set of half precast boards (four pieces), 1 hour for set of precast boards on balconies and corridors, floor slab streaks If it takes 4 hours for reinforcement and 2 hours for concrete placement and starts work at 8 am, finish the work related to beams in the morning, and from the afternoon to the morning of the next day from the set of half precast plates Work up to concrete placement can be completed.

【0032】このようにして1階分の作業を完了させる
のに遅くとも5日位掛かるが、早ければ3〜4日で完了
させることも可能となる。通常の従来工法では、11日
〜14日掛かりプレキャスト工法を用いても6〜7日の
サイクル工程に比べれば超短工期施工となる。
In this way, it takes about five days at the latest to complete the work for one floor, but it can be completed in three to four days at the earliest. In the usual conventional construction method, even if the precast construction method which takes 11 to 14 days is used, the construction becomes an extremely short construction period compared to the cycle process of 6 to 7 days.

【0033】尚、本発明は柱及び壁の構築のためにジャ
ンプフォーム装置を使用するが、該ジャンプフォーム装
置自体は高価である。
It should be noted that the present invention uses a jump-form device for building columns and walls, but the jump-form device itself is expensive.

【0034】しかし、該ジャンプフォーム装置はリース
品を使用でき、且つ、転用回数も大変多くできるのでコ
ストアップの要因は小さい。従って、該ジャンプフォー
ム装置を使用することにより工数が少なくなり、且つ、
必要人工数も少なくなるのでコストを大幅に削減するこ
とができる。
However, the jump-form device can use leased products and can be diverted a great number of times, so that the factor of cost increase is small. Therefore, the man-hour is reduced by using the jump form device, and
Since the required number of man-hours is reduced, the cost can be significantly reduced.

【0035】尚、本発明は、本発明の精神を逸脱しない
限り種々の改変を為すことができ、そして、本発明が該
改変されたものに及ぶことは当然である。
The present invention can be variously modified without departing from the spirit of the present invention, and it goes without saying that the present invention extends to the modified ones.

【0036】[0036]

【発明の効果】以上説明したように、請求項1記載の発
明は同一平面断面の型枠で形成される柱又は壁をジャン
プフォーム工法により先行して構築した後、該型枠をジ
ャンプアップし、その後、床スラブ等の水平部分を構築
するので、サイクル工程が短縮され、超短工期施工が可
能となる。又、ジャンプフォーム工法により、柱又は壁
の垂直部分を一気に構築し、その後、床スラブ等の水平
部分を構築するのでコンクリート打設区画が完全に分か
れていて従来のようなコンクリートの打ち重ねによるコ
ールドジョイントやジャンカ等のコンクリート品質不良
を起こすこともない。
As described above, according to the first aspect of the present invention, after a column or a wall formed of a form having the same plane cross section is constructed in advance by a jump form method, the form is jumped up. After that, since a horizontal portion such as a floor slab is constructed, a cycle process is shortened, and an ultra-short construction period can be performed. In addition, the vertical part of the pillar or wall is constructed at a stretch by the jump form method, and then the horizontal part such as the floor slab is constructed. It does not cause concrete quality defects such as joints and junkers.

【0037】請求項2記載の発明は、柱又は壁をジャン
プフォーム工法で構築するとき、予め、床スラブの施工
のための埋込み金具の設置及び該埋込み金具に受具を固
着しておくので、床スラブ板の据え付けが容易に、且
つ、確実に行うことができ、工期の短縮を図ることがで
きる。更に、柱又は壁と床スラブ板とをコンクリート打
設により埋込み金具を介して確実に、且つ、強力に一体
化することができる。
According to the second aspect of the present invention, when the pillar or the wall is constructed by the jump form method, the embedding metal fitting for the construction of the floor slab and the receiving tool are fixed to the embedding metal fitting in advance. The floor slab can be easily and reliably installed, and the construction period can be shortened. Further, the column or wall and the floor slab plate can be reliably and strongly integrated through the embedding metal fitting by concrete casting.

【0038】請求項3記載の発明は、柱又は壁をジャン
プフォーム工法で構築するとき、予め、柱又は壁に対す
る床スラブの設置予定位置に凹部形成用型枠を用いて凹
部を形成するので、ジャンプフォーム工法の施工と同時
に、且つ、容易に床スラブ板の支持部を形成することが
できる。又、該凹部内に床スラブを架設するので、据え
付けを容易に、且つ、確実に行うことができ、工期の短
縮を図ることができる。更に、柱又は壁と床スラブ板と
を剛結合により強力に一体化することができる。
According to the third aspect of the present invention, when the pillar or the wall is constructed by the jump form method, the concave portion is formed in advance at the position where the floor slab is to be installed relative to the column or the wall by using the concave portion forming form. At the same time as the execution of the jump form method, the support portion of the floor slab plate can be easily formed. In addition, since the floor slab is erected in the recess, the installation can be performed easily and reliably, and the construction period can be shortened. Further, the column or wall and the floor slab plate can be strongly integrated by rigid connection.

【0039】請求項4記載の発明は、前記請求項2又は
3記載の発明の効果に加えて床スラブ板を分割した長さ
のものを用いるので、柱又は壁の上部に設置されるジャ
ンプフォーム装置の邪魔にならずに該柱又は壁間に該床
スラブ板をスムーズに据え付けることができる。
According to a fourth aspect of the present invention, in addition to the effects of the second or third aspect of the present invention, since a floor slab having a divided length is used, a jump form installed above a pillar or a wall is used. The floor slab can be smoothly installed between the pillars or walls without disturbing the apparatus.

【0040】請求項5記載の発明は、前記請求項2又は
3記載の発明の効果に加えて床スラブ板を設置する際、
玉掛けワイヤの一方に吊り治具を取り付けるので、該吊
り治具の操作により該玉掛けワイヤを巻き上げることに
より床スラブ板を傾斜させて該柱又は壁間に容易に吊下
げることができ、且つ、伸ばすことにより水平に据え付
けることができる。
According to a fifth aspect of the present invention, in addition to the effect of the second or third aspect of the present invention, when installing a floor slab,
Since the hanging jig is attached to one of the sling wires, the floor jig can be easily hung between the pillars or the walls by tilting the floor slab plate by winding up the sling wire by operating the hanging jig, and extending it. By doing so, it can be installed horizontally.

【0041】斯くして、ジャンプフォーム工法を利用し
て柱又は壁を構築した後、床スラブ等の水平部分を構築
するので工期が短縮されて工事費を大幅に節減すること
ができる等、正に諸種の著大なる効果を奏する発明であ
る。
In this way, after the columns or walls are constructed by using the jump form method, the horizontal parts such as floor slabs are constructed, so that the construction period is shortened and the construction cost can be greatly reduced. It is an invention which has various significant effects.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施の形態を示し、集合住宅の平面
図。
FIG. 1 shows an embodiment of the present invention and is a plan view of an apartment house.

【図2】柱及び壁構築のためのジャンプフォーム装置の
平面図。
FIG. 2 is a plan view of a jump form device for constructing columns and walls.

【図3】(a)ジャンプフォーム装置の側断面図。 (b)ジャンプフォーム装置がジャンプアップした状態
を示す側断面図。
FIG. 3A is a side sectional view of a jump form device. (B) Side sectional drawing which shows the state which the jump form apparatus jumped up.

【図4】壁内に埋込み金具を設置した状態を示す側断面
図。
FIG. 4 is a side sectional view showing a state where an embedded metal fitting is installed in a wall.

【図5】分割した床スラブ板を設置した状態を示す集合
住宅の側面図。
FIG. 5 is a side view of an apartment house showing a state where divided floor slabs are installed.

【図6】他の実施の形態を示し、ジャンプフォーム装置
の型枠に凹部形成用型枠を取り付けた状態を示す側断面
図。
FIG. 6 is a side cross-sectional view showing another embodiment, in which a concave forming mold is attached to a mold of a jump foam device.

【図7】壁の側断面図であって、上部は凹部形成用型枠
の設置状態を示し、下部は床スラブ板との接合状態を示
す。
FIG. 7 is a side sectional view of a wall, in which an upper part shows an installed state of a recess forming mold and a lower part shows a joint state with a floor slab plate.

【図8】(a)床スラブ板の吊下げ状態を示す側面図。 (b)壁間に床スラブ板を据え付ける状態を示す集合住
宅の側面図。
FIG. 8A is a side view showing a suspended state of a floor slab plate. (B) The side view of the apartment house which shows the state which installs a floor slab board between walls.

【図9】更に他の実施の形態を示し、壁と床スラブ板と
の接合状態を示す側断面図。
FIG. 9 is a side cross-sectional view showing a still further embodiment and showing a joint state between a wall and a floor slab plate.

【符号の説明】[Explanation of symbols]

1 柱 2 壁(戸境壁) 4 床スラブ 6 型枠 10 床スラブ板 13 埋込み金具 16 受具 17 支持台 18 凹部形成用型枠 25 凹部 29 吊り治具 30 玉掛けワイヤ C コンクリート DESCRIPTION OF SYMBOLS 1 pillar 2 wall (door boundary wall) 4 floor slab 6 formwork 10 floor slab board 13 embedding metal fittings 16 receiving device 17 support base 18 concave form forming form 25 concave section 29 hanging jig 30 slinging wire C concrete

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 柱又は壁を所定間隔で垂直に立設し、且
つ、該柱又は壁間に水平に床スラブ等を配設する建物の
構築方法に於て、同一平面断面の型枠で形成される該柱
又は壁をジャンプフォーム工法により先行して構築した
後、該型枠をジャンプアップし、その後、該床スラブ等
の水平部分を構築することを特徴とする建物の構築方
法。
1. A method of constructing a building in which pillars or walls are vertically erected at predetermined intervals and floor slabs or the like are horizontally arranged between the pillars or walls. A method for constructing a building, comprising: constructing a pillar or wall to be formed in advance by a jump form method, jumping up the formwork, and then constructing a horizontal portion such as the floor slab.
【請求項2】 柱又は壁を所定間隔で垂直に立設し、且
つ、該柱又は壁間に水平に床スラブ等を配設する建物の
構築方法に於て、該柱又は壁をジャンプフォーム工法で
構築するとき、該柱又は壁に対する該床スラブの設置予
定位置に予め埋込み金具を該柱又は壁の外面に合せて設
置し、コンクリートを打設して該柱又は壁を構築した
後、該埋込み金具の下部近傍に該床スラブとなる床スラ
ブ板を支持する受具を固着し、更に、該受具間に該床ス
ラブ板を架設することを特徴とする建物の構築方法。
2. A method for constructing a building in which pillars or walls are erected vertically at predetermined intervals and a floor slab or the like is horizontally arranged between the pillars or walls. When constructing by the construction method, the embedding metal fittings are installed in advance at the installation positions of the floor slab with respect to the columns or walls in accordance with the outer surfaces of the columns or walls, and concrete is cast to construct the columns or walls. A method for constructing a building, comprising: fixing a support for supporting a floor slab plate serving as the floor slab in the vicinity of a lower portion of the embedding metal fitting; and laying the floor slab plate between the mounts.
【請求項3】 柱又は壁を所定間隔で垂直に立設し、且
つ、該柱又は壁間に水平に床スラブ等を配設する建物の
構築方法に於て、該柱又は壁をジャンプフォーム工法で
構築するとき、該柱又は壁に対する該床スラブの設置予
定位置に予め凹部形成用型枠を設置し、コンクリートを
打設して該柱又は壁を構築した後、該凹部形成用型枠を
撤去し、該柱又は壁に凹部を形成し、該凹部内に該床ス
ラブとなる床スラブ板を架設することを特徴とする建物
構築方法。
3. A method of constructing a building in which pillars or walls are vertically erected at predetermined intervals and a floor slab or the like is horizontally arranged between the pillars or walls. When constructing by the construction method, a recess forming mold is installed in advance at the installation position of the floor slab with respect to the pillar or wall, and concrete is cast to construct the pillar or wall, and then the recess forming mold is formed. Removing the slab, forming a recess in the pillar or wall, and laying a floor slab plate serving as the floor slab in the recess.
【請求項4】 前記床スラブ板は、前記柱又は壁間の中
央部近傍で分割された長さのものを用い、該床スラブ板
を前記受具又は前記凹部と中央部近傍に設置する支持台
間に複数架設して前記床スラブを形成する請求項2又は
請求項3記載の建物の構築方法。
4. A support for installing the floor slab plate in the vicinity of the central portion of the receiving slab or the recessed portion using a floor slab plate having a length divided near the center between the columns or walls. The building construction method according to claim 2 or 3, wherein the floor slab is formed by erection between a plurality of stands.
【請求項5】 前記受具又は前記凹部内に前記床スラブ
板を設置する際、該床スラブ板の両端近傍に玉掛けワイ
ヤを掛け渡すと共に、該玉掛けワイヤの一方には吊り治
具を取り付け、前記柱又は壁間に吊下げ時には該吊り治
具で該玉掛けワイヤの一方を巻き上げて該床スラブ板を
傾斜させ、更に、該柱又は壁間に架設時には該吊り治具
で該玉掛けワイヤの一方を伸ばしながら該床スラブ板を
水平にすることを特徴とする請求項2又は請求項3記載
の建物の構築方法。
5. When the floor slab plate is installed in the receiving member or the recess, a sling wire is wound around both ends of the floor slab plate, and a hanging jig is attached to one of the sling wires. At the time of hanging between the columns or walls, one of the sling wires is wound up by the hanging jig to incline the floor slab plate. The building construction method according to claim 2 or 3, wherein the floor slab is leveled while extending.
JP2000393517A 2000-12-25 2000-12-25 Construction method of building Withdrawn JP2002194892A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000393517A JP2002194892A (en) 2000-12-25 2000-12-25 Construction method of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000393517A JP2002194892A (en) 2000-12-25 2000-12-25 Construction method of building

Publications (1)

Publication Number Publication Date
JP2002194892A true JP2002194892A (en) 2002-07-10

Family

ID=18859306

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000393517A Withdrawn JP2002194892A (en) 2000-12-25 2000-12-25 Construction method of building

Country Status (1)

Country Link
JP (1) JP2002194892A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009097275A (en) * 2007-10-18 2009-05-07 Ohbayashi Corp Construction method for skeleton, and form unit
KR100968068B1 (en) 2007-07-30 2010-07-08 (주)바로건설기술 Multi-Horizontal Structure Member Forming Method
JP2014020120A (en) * 2012-07-19 2014-02-03 Maeda Corp Anchor bar, and slab joining structure employing the same
CN108756038A (en) * 2018-07-11 2018-11-06 上海应用技术大学 Assembly concrete shear wall and floor support plate rigid connection node and construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100968068B1 (en) 2007-07-30 2010-07-08 (주)바로건설기술 Multi-Horizontal Structure Member Forming Method
JP2009097275A (en) * 2007-10-18 2009-05-07 Ohbayashi Corp Construction method for skeleton, and form unit
JP2014020120A (en) * 2012-07-19 2014-02-03 Maeda Corp Anchor bar, and slab joining structure employing the same
CN108756038A (en) * 2018-07-11 2018-11-06 上海应用技术大学 Assembly concrete shear wall and floor support plate rigid connection node and construction method

Similar Documents

Publication Publication Date Title
WO2019133406A1 (en) Precast concrete system with rapid assembly formwork
US4023315A (en) Prefabricated buildings
AU2017282720B2 (en) Method for constructing a concrete floor in a multistorey building
KR101614842B1 (en) frame system of buildings using the pc-column with overhanging beam applicable various span without increase of story-height
KR20210038684A (en) Precast building construction system
US20040098934A1 (en) Load bearing building panel
JP2002194892A (en) Construction method of building
JP2003328320A (en) Construction method of precast capital part and bridge pier capital part
RU2032047C1 (en) Building skeleton erection method
JP7572413B2 (en) How to build a structure
JP2928002B2 (en) Column formwork structure
JP2759361B2 (en) Pillar support members for building reinforced concrete buildings
JPH084196A (en) Panel for building
AU2022204051B2 (en) Method for constructing a concrete floor in a multistorey building
JP4520830B2 (en) Exterior wall panel construction method and exterior wall panel mounting structure
JP2759360B2 (en) Construction method of reinforced concrete building
JP3045839B2 (en) Method and apparatus for installing floor slab in unit building
JP2990216B2 (en) Construction method of reinforced concrete building
JP3207276B2 (en) How to build a unit building
JP2724891B2 (en) Construction method of pillar half PCa formwork
JP2722121B2 (en) Construction method of reinforced concrete building
JPH0874381A (en) Reinforcement unit and construction method of reinforced concrete-made building using the same
JP2002194895A (en) Arrangement method of horizontal reinforcement
AU2002234421B2 (en) A load bearing building panel
JPH0715177B2 (en) How to build a reinforced concrete structure

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20080304