JP2001288725A - Pile-type foundation structure and method for constructing the same - Google Patents
Pile-type foundation structure and method for constructing the sameInfo
- Publication number
- JP2001288725A JP2001288725A JP2000101750A JP2000101750A JP2001288725A JP 2001288725 A JP2001288725 A JP 2001288725A JP 2000101750 A JP2000101750 A JP 2000101750A JP 2000101750 A JP2000101750 A JP 2000101750A JP 2001288725 A JP2001288725 A JP 2001288725A
- Authority
- JP
- Japan
- Prior art keywords
- pile
- steel pipe
- steel
- frame structure
- superstructure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A10/00—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
- Y02A10/11—Hard structures, e.g. dams, dykes or breakwaters
Landscapes
- Revetment (AREA)
- Piles And Underground Anchors (AREA)
- Foundations (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、港湾等の水域にお
ける杭式横桟橋や、橋脚基礎などの鋼管杭を使用した杭
式基礎構造物に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pile type foundation structure using a steel pipe pile, such as a pile type horizontal pier or a pier foundation in a water area such as a harbor.
【0002】[0002]
【従来の技術】通常、例えば、港湾等の水域における杭
式桟橋,杭式防波堤あるいは河川等における橋脚基礎な
どに使用する鋼管杭9の頭部は、図29に示すように鉄
筋コンクリート製の梁や頂版コンクリートにより互いに
連結されている杭式基礎構造物40aが知られている。
従来、この杭式基礎構造物40aにおける鉄筋コンクリ
ート製の梁43は、鋼管杭9を水底地盤に打設後、海洋
上の現位置において施工する、いわゆる場所打ちコンク
リート方式により施工されていた。すなわち、杭頭や杭
間への配筋、支保工の設置、型枠の配置、コンクリート
の打設、硬化養生,型枠等の撤去が鋼管杭9の打設後の
海洋上の現位置において行われていた。2. Description of the Related Art Normally, for example, the head of a steel pipe pile 9 used for a pile-type pier, a pile-type breakwater in a water area such as a harbor, or a pier foundation in a river or the like has a reinforced concrete beam as shown in FIG. Pile-type substructures 40a which are connected to each other by top slab concrete are known.
Conventionally, the beam 43 made of reinforced concrete in the pile type foundation structure 40a has been constructed by the so-called cast-in-place concrete method in which the steel pipe pile 9 is cast on the underwater ground and then constructed at the current position on the ocean. In other words, the arrangement of the reinforcing bars between the pile heads and the piles, the installation of the shoring, the arrangement of the formwork, the placement of the concrete, the hardening, the removal of the formwork, etc. are performed at the current position on the sea after the placement of the steel pipe pile 9. It was done.
【0003】[0003]
【発明が解決しようとする課題】しかし、前記の場所打
ちコンクリート方式による杭式基礎構造物の場合には次
の問題があった。 海上作業に長期間を要し、作業途中において波浪の
影響を受け、支保工や型枠が破損し、手戻りが生じる場
合があった。 コンクリートの養生初期に波浪の影響を受けると、
コンクリートの強度発現に問題を生じる場合があった。 上部工が鉄筋コンクリートの充実断面であるため、
上部工が大重量となり、地震時に作用する慣性力が大き
くなり、これに対抗するために大断面の鋼管杭9や多数
本の鋼管杭9の使用を余儀なくされていた。However, in the case of the pile type foundation structure using the cast-in-place concrete method, there are the following problems. The offshore work took a long time, and the work was affected by the waves during the work, and the shoring and the formwork were damaged, and rework was sometimes performed. In the early stages of concrete curing, when affected by waves,
In some cases, there was a problem in the development of concrete strength. Because the superstructure is a solid section of reinforced concrete,
The superstructure was heavy, and the inertial force acting during an earthquake became large. To counter this, a steel pipe pile 9 having a large cross section and a large number of steel pipe piles 9 had to be used.
【0004】本発明は、前記従来の欠点を改良したもの
で、鋼管杭9の打設とその頭部連結構造の施工を全て海
洋上で行うという従来の施工方法に変え、鋼管杭9の頭
部連結構造を予め陸上ヤードなどで製作し、海洋の現場
に搬送して、現場では、簡易に施工できる杭式基礎構造
物およびその施工方法を提供することを目的とする。The present invention is an improvement of the above-mentioned conventional drawbacks. The present invention is changed to a conventional construction method in which the installation of the steel pipe pile 9 and the construction of its head connection structure are all carried out on the sea. It is an object of the present invention to provide a pile-type substructure that can be easily constructed at a site where the partial connection structure is manufactured in advance on a land yard or the like and transported to a marine site.
【0005】[0005]
【課題を解決するための手段】前記の目的を達成するた
め、本発明における請求項1の杭式基礎構造物において
は、複数の鞘管1同士が補強部材2により連結されてフ
レーム構造体19が構成され、前記複数の鞘管1の内部
には鋼管杭9が挿通され、前記鞘管1と前記鋼管杭9の
間にはモルタル等の経時硬化性材料10が充填されてい
ることを特徴とする。In order to achieve the above-mentioned object, in a pile type substructure according to the first aspect of the present invention, a plurality of sheath tubes are connected to each other by a reinforcing member to form a frame structure. A steel pipe pile 9 is inserted into the inside of the plurality of sheath pipes 1, and a time-curable material 10 such as mortar is filled between the sheath pipe 1 and the steel pipe pile 9. And
【0006】また請求項2の発明においては、請求項1
記載の杭式基礎構造物において、補強部材2が、鋼管ま
たは外面突起付き鋼管、あるいはH形鋼またはフランジ
の外面に突起を有するH形鋼等の開断面部材を並設して
中空空間が形成された中空部を有する部材等の中空部材
33であることを特徴とする。[0006] In the invention of claim 2, claim 1 is
In the pile type substructure described above, the hollow space is formed by arranging the reinforcing member 2 in parallel with an open section member such as a steel pipe or a steel pipe with an external projection, or an H-section steel or an H-section steel having a projection on the outer surface of a flange. It is a hollow member 33 such as a member having a hollow portion formed.
【0007】さらに請求項3の発明においては、請求項
1または2のいずれかに記載の杭式基礎構造物におい
て、前記鞘管1の上端部に、上部工係止部材3または吊
り金具4を一体に設けた上部工係止部材3が一体に設け
られていることを特徴とする。According to the third aspect of the present invention, in the pile type substructure according to any one of the first and second aspects, an upper work locking member 3 or a suspension fitting 4 is provided at an upper end of the sheath tube 1. It is characterized in that the upper work locking member 3 provided integrally is provided integrally.
【0008】さらにまた請求項4の発明においては、請
求項1,2または3のいずれかに記載の杭式基礎構造物
において、前記鞘管1に対応する範囲の鋼管杭9の外周
面の所定範囲に突起21が一体に設けられていることを
特徴とする。According to a fourth aspect of the present invention, in the pile type substructure according to any one of the first, second, and third aspects, the outer peripheral surface of the steel pipe pile 9 in a range corresponding to the sheath pipe 1 is defined. It is characterized in that the projection 21 is provided integrally in the range.
【0009】なおまた請求項5の発明においては、請求
項1〜3または4のいずれかに記載の杭式基礎構造物に
おいて、前記鞘管1の内面の所定範囲に突起22が一体
的に設けられていることを特徴とする。According to a fifth aspect of the present invention, in the pile type substructure according to any one of the first to third or fourth aspects, a projection 22 is integrally provided in a predetermined area on the inner surface of the sheath tube 1. It is characterized by having been done.
【0010】また請求項6の発明においては、請求項1
〜3または5のいずれかに記載の杭式基礎構造物におい
て、少なくとも前記鞘管1に対応する範囲の鋼管杭9の
所定範囲が外面突起付き鋼管30であることを特徴とす
る。[0010] In the invention according to claim 6, claim 1 is provided.
The pile-type substructure according to any one of (1) to (3) or (5), wherein at least a predetermined range of the steel pipe pile 9 in a range corresponding to the sheath pipe 1 is a steel pipe 30 with an external projection.
【0011】さらに請求項7の発明においては、請求項
1〜4または6のいずれかに記載の杭式基礎構造物にお
いて、前記鞘管1が内面突起付き鋼管31であることを
特徴とする。Further, according to a seventh aspect of the present invention, in the pile type substructure according to any one of the first to fourth or sixth aspects, the sheath tube 1 is a steel tube 31 having an inner surface projection.
【0012】さらにまた請求項8の発明においては、請
求項1〜6または7のいずれかに記載の杭式基礎構造物
において、前記鞘管1の内面の所定個所にスペーサー3
2が設けられていることを特徴とする。Further, according to the invention of claim 8, in the pile type substructure according to any one of claims 1 to 6, or 7, a spacer 3 is provided at a predetermined position on the inner surface of the sheath tube 1.
2 is provided.
【0013】なおまた請求項9の発明においては、請求
項1〜7または8のいずれかに記載の杭式基礎構造物に
おいて、前記鞘管1の所定個所に揺動防止治具23が設
けられていることを特徴とする。According to a ninth aspect of the present invention, in the pile type substructure according to any one of the first to seventh or eighth aspects, a swing preventing jig 23 is provided at a predetermined position of the sheath tube 1. It is characterized by having.
【0014】また請求項10の発明においては、請求項
1〜8または9のいずれかに記載の杭式基礎構造物にお
いて、前記鞘管1の下部内面に間隔を置いてシール材把
持用突設部材14a,14bが一体に設けられ、前記シ
ール材把持用突設部材14a,14bの間にシール材1
3の基部側が配置されて、これらのシール材係止ボルト
挿通用孔にわたって挿通されたボルト16によりシール
材13がシール材把持用突設部材14に固定され、シー
ル材13が鋼管杭9外表面に密接していることを特徴と
する。According to a tenth aspect of the present invention, in the pile type substructure according to any one of the first to eighth or ninth aspects, a projection for gripping a sealing material is provided at an interval on a lower inner surface of the sheath tube 1. The members 14a and 14b are integrally provided, and the sealing material 1 is provided between the sealing material holding protruding members 14a and 14b.
The seal member 13 is fixed to the seal member gripping projecting member 14 by bolts 16 inserted through the seal member retaining bolt insertion holes, and the seal member 13 is disposed on the outer surface of the steel pipe pile 9. It is characterized by being close to.
【0015】さらにまた請求項11の発明においては、
請求項1〜9または10のいずれかに記載の杭式基礎構
造物において、前記鞘管1の下端部に底型枠11が直接
またはシール用緩衝材12を介して当接されていること
を特徴とする。Furthermore, in the invention of claim 11,
The pile type substructure according to any one of claims 1 to 9 or 10, wherein a bottom form 11 is in contact with a lower end of the sheath tube 1 directly or via a cushioning material 12 for sealing. Features.
【0016】なおまた請求項12の発明においては、請
求項1〜10または11のいずれかに記載の杭式基礎構
造物において、前記底型枠11同士が杭間隔保持部材1
7により連結されていることを特徴とする。According to a twelfth aspect of the present invention, in the pile type substructure according to any one of the first to tenth or eleventh aspects, the bottom forms 11 are connected to each other by the pile spacing member 1.
7 are connected.
【0017】また請求項13の発明においては、請求項
1〜11または12のいずれかに記載の杭式基礎構造物
において、前記鞘管1の所定位置に、鉄筋定着用鋼板6
が固着され、前記鉄筋定着用鋼板6には、鉄筋7が固着
されていることを特徴とする。According to a thirteenth aspect of the present invention, in the pile type substructure according to any one of the first to eleventh or twelfth aspects, the steel plate for fixing a reinforcing steel is provided at a predetermined position of the sheath tube.
And a reinforcing bar 7 is fixed to the reinforcing steel plate 6.
【0018】さらにまた請求項14の発明においては、
請求項1〜12または13のいずれかに記載の杭式基礎
構造物において、前記鞘管1の所定位置に、鉄筋定着用
鋼板6が固着され、前記鉄筋定着用鋼板6には鉄筋7が
固着され、前記鞘管1、鉄筋定着用鋼板6および鉄筋7
を囲むように型枠24が配置されていることを特徴とす
る。Furthermore, in the invention of claim 14,
The pile-type substructure according to any one of claims 1 to 12 or 13, wherein a steel plate 6 for fixing a reinforcing bar is fixed to a predetermined position of the sheath tube 1, and a reinforcing bar 7 is fixed to the steel plate 6 for fixing a reinforcing bar. And the sheath tube 1, the steel plate 6 for fixing the reinforcing bar, and the reinforcing bar 7.
Is characterized in that a mold 24 is arranged so as to surround.
【0019】なおまた請求項15の発明においては、請
求項1〜13または14のいずれかに記載の杭式基礎構
造物において、前記鞘管1の所定位置に、鉄筋定着用鋼
板6が固着され、前記鉄筋定着用鋼板6には鉄筋7が固
着され、前記鞘管1,鉄筋定着用鋼板6,鉄筋7および
補強部材2がコンクリートに埋設されていることを特徴
とする。According to a fifteenth aspect of the present invention, in the pile type substructure according to any one of the first to thirteenth or fourteenth aspects, a steel plate 6 for fixing a reinforcing bar is fixed to a predetermined position of the sheath tube 1. A reinforcing bar 7 is fixed to the reinforcing steel plate 6, and the sheath tube 1, the reinforcing steel plate 6, the reinforcing bar 7 and the reinforcing member 2 are embedded in concrete.
【0020】また請求項16の杭式基礎構造物の施工方
法においては、間隔を置いて配置された複数の鞘管1が
鋼管等の中空部を備えた補強部材2により連結されて予
め製作された上部工用フレーム構造体を搬送して、間隔
をおいて地盤に打設された複数の鋼管杭9の頭部の所定
位置に配置すると共に前記各鋼管杭9に鞘管を嵌合し、
次いで各鞘管と鋼管杭9との間にモルタル等の経時硬化
性材料10を充填・硬化し、前記補強部材2を支保材の
一部として利用しながら上部工鉄筋の配筋および型枠の
配設作業を行い、次いで前記鞘管1,上部工鉄筋および
補強部材2を埋め込むようにコンクリートを打設し、養
生・硬化させることを特徴とする。In the method of constructing a pile type substructure according to a sixteenth aspect, a plurality of sheathed tubes 1 arranged at intervals are connected to each other by a reinforcing member 2 having a hollow portion such as a steel tube and manufactured in advance. Transporting the superstructure frame structure, disposing it at a predetermined position on the head of a plurality of steel pipe piles 9 cast on the ground at intervals, and fitting a sheath pipe to each of the steel pipe piles 9;
Next, a time-hardening material 10 such as mortar is filled and hardened between each sheath pipe and the steel pipe pile 9, and the reinforcing member 2 is used as a part of the supporting material, and the reinforcing steel reinforcement and the formwork are formed. The installation work is performed, and then concrete is poured so as to embed the sheath tube 1, the upper rebar and the reinforcing member 2, and the concrete is cured and hardened.
【0021】さらにまた請求項17の杭式基礎構造物の
施工方法においては、間隔を置いて配置された複数の鞘
管1が鋼管等の中空部を備えた補強部材2により連結し
て上部工用フレーム構造体を構成すると共に、前記上部
工用フレーム構造体に上部工鉄筋を配筋して構成した上
部工鉄筋付き上部工用フレーム構造体を予め製作し、そ
の上部工鉄筋付き上部工用フレーム構造体を搬送して、
間隔をおいて地盤に打設された複数の鋼管杭9の頭部の
所定位置に配置すると共に前記各鋼管杭9に鞘管を嵌合
し、次いで各鞘管と鋼管杭9との間にモルタル等の経時
硬化性材料10を充填・硬化し、前記補強部材2を支保
材の一部として利用しながら型枠の配設作業を行い、次
いで後前記鞘管1,上部工鉄筋および補強部材2を埋め
込むようにコンクリートを打設し、養生・硬化させるこ
とを特徴とする。Further, in the method for constructing a pile-type substructure according to a seventeenth aspect, a plurality of sheathed tubes 1 arranged at intervals are connected by a reinforcing member 2 having a hollow portion such as a steel tube, and a superstructure is constructed. A frame structure for an upper part with an upper rebar is constructed in advance by constructing a frame structure for the upper part, and an upper part rebar is arranged on the frame structure for the upper part. Transport the frame structure,
A plurality of steel pipe piles 9 placed on the ground at intervals are arranged at predetermined positions on the heads, and a sheath pipe is fitted to each of the steel pipe piles 9. A time-setting material 10 such as mortar is filled and hardened, and a formwork is laid while using the reinforcing member 2 as a part of a supporting material. It is characterized by casting concrete to bury 2 and curing and hardening.
【0022】なおまた請求項18の杭式基礎構造物の施
工方法においては、間隔を置いて配置された複数の鞘管
1が鋼管等の中空部を備えた補強部材2により連結して
上部工用フレーム構造体を構成すると共に、前記上部工
用フレーム構造体に上部工鉄筋および型枠ならびに支保
工を一体に配設して構成した型枠支保工付き上部工用フ
レーム構造体を予め製作し、その型枠支保工付き上部工
用フレーム構造体を搬送して、間隔をおいて地盤に打設
された複数の鋼管杭9の頭部の所定位置に配置すると共
に前記各鋼管杭9に鞘管を嵌合し、次いで各鞘管と鋼管
杭9との間にモルタル等の経時硬化性材料10を充填・
硬化し、その後前記鞘管1,上部工鉄筋および補強部材
2を埋め込むようにコンクリートを打設し、養生・硬化
させることを特徴とする。In the construction method for a pile type substructure according to the eighteenth aspect, a plurality of sheathed tubes 1 arranged at intervals are connected by a reinforcing member 2 having a hollow portion such as a steel tube, and a superstructure is constructed. A frame structure for a superstructure with a form supporting structure, in which an upper reinforcing bar, a formwork, and a supporting structure are integrally disposed on the upper structure frame structure, and The frame structure for superstructure with the frame support is transported and arranged at a predetermined position on the head of a plurality of steel pipe piles 9 cast on the ground at intervals, and a sheath is provided on each of the steel pipe piles 9. A pipe is fitted, and then a time-hardening material 10 such as mortar is filled between each sheath pipe and the steel pipe pile 9.
After hardening, concrete is poured into the sheath tube 1, the upper rebar and the reinforcing member 2 so as to be embedded therein, and the concrete is cured and hardened.
【0023】また請求項19の杭式基礎構造物の施工方
法においては、間隔を置いて配置された複数の鞘管1が
鋼管等の中空部を備えた補強部材2により連結して上部
工用フレーム構造体を構成すると共に、前記上部工用フ
レーム構造体に上部工鉄筋を一体に配設し、その後前記
上部工鉄筋および補強部材2を埋め込むようにコンクリ
ートを打設し、養生・硬化させて構成した上部工用フレ
ーム構造体付きプレキャスト鉄筋コンクリート製上部工
を予め製作し、その上部工用フレーム構造体付きプレキ
ャスト鉄筋コンクリート製上部工を搬送して、間隔をお
いて地盤に打設された複数の鋼管杭9の頭部の所定位置
に配置すると共に前記各鋼管杭9に鞘管を嵌合し、次い
で各鞘管と鋼管杭9との間にモルタル等の経時硬化性材
料10を充填・硬化することを特徴とする。In the method for constructing a pile type substructure according to the nineteenth aspect, a plurality of sheathed tubes 1 arranged at intervals are connected by a reinforcing member 2 having a hollow portion such as a steel tube for superstructure. In addition to forming a frame structure, an upper rebar is integrally disposed on the upper frame structure, and then concrete is poured into the upper rebar and the reinforcing member 2 so as to be embedded therein, and then cured and cured. Prefabricated precast reinforced concrete superstructure with superstructure frame structure is constructed in advance, and the precast reinforced concrete superstructure with superstructure frame structure is transported, and a plurality of steel pipes cast on the ground at intervals. It is arranged at a predetermined position on the head of the pile 9 and a sheath tube is fitted to each of the steel tube piles 9. Then, a time-hardening material 10 such as mortar is filled and hardened between each sheath tube and the steel tube pile 9. Characterized in that it.
【0024】[0024]
【発明の実施の形態】次に本発明の実施の形態を、図面
を参照しながら詳細に説明する。図9から図11は、本
発明の杭式基礎構造物において使用される上部工用分割
フレーム構造体18を示すものであって、間隔をおいて
同レベルにおいて縦向きに配置される短筒状鋼管からな
る一対の鞘管1における各上部外面に、前記鞘管1の外
周面と同様な円弧状内周面を備えたそれぞれ4枚の鉄筋
定着用鋼板6がほぼ同レベル(ほぼ鉄筋径差に相当する
板厚分のレベル差があるが)の同一平面上の上側下側に
おいて、周方向に等角度(90度)間隔をおいて配置さ
れて、それらの基端部が鞘管1の外周面に溶接により固
着されて、上部鉄筋定着部6aが構成され、また前記各
鞘管1の下部に、前記鞘管1の外周面と同様な円弧状内
周面を備えたそれぞれ4枚の鉄筋定着用鋼板6が周方向
に等角度(90度)間隔をおいて配置されて、その基端
部が鞘管1の外周面に溶接により固着されて、下部鉄筋
定着部6bが構成されている。また必要に応じ隣り合う
各鉄筋定着用鋼板6は溶接により連結される。なお、杭
頭連結梁用フレーム構造体を分割するのは、トレーラー
等による陸上輸送を容易にするためである。Embodiments of the present invention will now be described in detail with reference to the drawings. FIGS. 9 to 11 show a divided frame structure 18 for superstructure used in the pile type substructure of the present invention. On each upper outer surface of the pair of sheathed tubes 1 made of a steel tube, four steel plates 6 for fixing the reinforcing steels each having an arc-shaped inner peripheral surface similar to the outer peripheral surface of the sheathed tube 1 are substantially at the same level (substantially the difference in the reinforcing steel diameter) Are arranged at equal intervals (90 degrees) in the circumferential direction at the upper and lower sides on the same plane, and the base ends of the sheath tube 1 An upper rebar anchoring portion 6a is formed by being fixed to the outer peripheral surface by welding. In addition, four sheets each having an arc-shaped inner peripheral surface similar to the outer peripheral surface of the sheath tube 1 are provided below the respective sheath tubes 1. Reinforcing steel plates 6 are arranged at equal angular (90 °) intervals in the circumferential direction. End is secured by welding to the outer peripheral surface of the sheath tube 1, the lower reinforcing bar fixing portion 6b is formed. Further, the adjacent reinforcing steel plates 6 are connected by welding if necessary. The reason why the pile head connecting beam frame structure is divided is to facilitate land transportation by a trailer or the like.
【0025】間隔をおいて隣り合う前記各鞘管1は、前
記上部鉄筋定着部6aと下部鉄筋定着部6bの間の下位
側に配置されて端部が溶接等により固定された鋼管から
なる補強部材2により連結され、また前記各鞘管1に
は、前記補強部材2の反対側において、端部が閉塞板に
より閉塞された短尺の鋼管からなる補強部材2の基部側
が溶接により固着され、これにより短尺の端部張り出し
補強部材2aとされている。また前記補強部材2の中心
線と直角方向に、床版端部側に配置される鋼管からなる
端部張り出し補強部材2bの基部側が溶接により前記鞘
管1に溶接により固定されている。前記端部張り出し補
強部材2a,2bは、片持ち式の張り出し梁材を兼用し
た部材とされている。前記鞘管1には端部張り出し補強
部材2bの反対側の同レベルにおいて、継手用短尺鋼管
2cの基部側が溶接により固着されている。この継手用
短尺鋼管2cは、後記するように、これに鋼管からなる
補強部材2を当接して溶接により接合することにより、
一対の分割上部工用フレーム構造体18を一体化した上
部工用フレーム構造体19(図12参照)を構成するた
めに使用される。継手用短尺鋼管2cと補強部材2と
は、これらに溶接により固定された水平リブにより補強
され、また鞘管1と補強部材2(2a,2b)と鉄筋定
着用鋼板6とは、これらに溶接により固着された縦リブ
により補強されている。Each of the sheath tubes 1 adjacent to each other at an interval is disposed on the lower side between the upper reinforcing bar fixing portion 6a and the lower reinforcing bar fixing portion 6b, and is made of a steel pipe whose end is fixed by welding or the like. The reinforcing tube 2 is connected to the sheath tube 1 on the opposite side to the reinforcing member 2 by welding, and the base side of the reinforcing member 2 made of a short steel tube whose end is closed by a closing plate is fixed to the sheath tube 1 by welding. Thus, a short end projecting reinforcing member 2a is formed. Further, in the direction perpendicular to the center line of the reinforcing member 2, the base portion side of the end projecting reinforcing member 2 b made of a steel pipe disposed on the end portion of the floor slab is fixed to the sheath tube 1 by welding. The end overhanging reinforcing members 2a and 2b are members that also serve as cantilever overhanging beam members. The base side of the short steel pipe 2c for a joint is fixed to the sheath pipe 1 by welding at the same level opposite to the end extension reinforcing member 2b. As described below, the short steel pipe 2c for a joint is brought into contact with the reinforcing member 2 made of a steel pipe and joined thereto by welding.
It is used to form a superstructure frame structure 19 (see FIG. 12) in which a pair of divided superstructure frame structures 18 are integrated. The short steel pipe 2c for the joint and the reinforcing member 2 are reinforced by horizontal ribs fixed thereto by welding, and the sheath tube 1, the reinforcing member 2 (2a, 2b), and the steel plate 6 for reinforcing steel are welded to these. Reinforced by vertical ribs fixed by
【0026】前記各鞘管1の上部には、後記の上部工用
フレーム構造体19における対角線方向に配置された縦
鋼板5aの上部に吊り孔5を備えた吊り金具4の下部が
溶接により鞘管1の内周面に固着され、また前記縦鋼板
5aの下部の両面に、直角にかつ間隔を置いて平行に縦
鋼板からなる係止部材5cの基部側が溶接により固着さ
れ、前記各係止部材の先端部が鞘管1の上端部内周面に
当接されて溶接により固着されて、上部工係止部材3が
構成されている。前記上部工係止部材3から上の部分、
すなわち吊り金具4の部分は、上部工用フレームが鋼管
杭9に配設された後において、適宜の時期に溶断により
切断されて、上部工係止部材3のみが残される。この上
部工係止部材3を備えているので、鋼管杭9と鞘管1の
間にモルタル10aが充填され,かつ上部工コンクリー
ト8がこれらを埋め込むように打設されることにより、
前記上部工用分割フレーム構造体18または上部工用フ
レーム構造体19と鋼管杭9とを強固に一体化すことが
でき、また後記するように、上部工用フレーム構造体1
9に梁鉄筋を含む上部工鉄筋Aを備えた上部工鉄筋付き
上部工用フレーム構造体19、さらにこれに支保工およ
び型枠を一体に組み込んだ形態、またその型枠内にコン
クリートを打設し、必要に応じ脱型してプレキャスト化
したプレキャストコンクリート上部工50までのいずれ
かのユニット化された変形形態の上部工用ユニットと鋼
管杭9とを強固に一体化することができる。At the upper part of each of the sheath tubes 1, a lower part of a hanging metal fitting 4 having a hanging hole 5 at an upper part of a vertical steel plate 5a arranged diagonally in an upper frame structure 19 to be described later is sheathed. The base of a locking member 5c made of a vertical steel plate is fixed to the inner peripheral surface of the pipe 1 at right angles and parallel to the lower surface of the vertical steel plate 5a at intervals on both sides by welding. The tip of the member is in contact with the inner peripheral surface of the upper end of the sheath tube 1 and is fixed by welding, so that the superstructure locking member 3 is formed. A portion above the superstructure locking member 3,
That is, the portion of the suspension fitting 4 is cut by fusing at an appropriate time after the superstructure frame is disposed on the steel pipe pile 9, leaving only the superstructure locking member 3. Since the superstructure retaining member 3 is provided, the mortar 10a is filled between the steel pipe pile 9 and the sheath tube 1 and the superstructure concrete 8 is cast so as to embed them.
The divided frame structure for superstructure 18 or the frame structure for superstructure 19 and the steel pipe pile 9 can be firmly integrated, and as described later, the superstructure frame structure 1
9, a superstructure frame structure 19 with an upper rebar having an upper rebar A including a beam rebar, a form in which a supporter and a formwork are integrally incorporated, and concrete is poured into the formwork Then, any of the unitized and modified superstructure units up to the precast concrete superstructure 50, which has been removed from the mold and precast, can be firmly integrated with the steel pipe pile 9.
【0027】前記鞘管1の内周面には、上下方向に間隔
をおいて、円環状の鉄筋が溶接により固定されて突起2
2が設けられ、前記突起22により鞘管1内に充填され
るモルタルの硬化により、鋼管杭9とのずれ止め作用が
図られる。また前記突起22は、図11および図21に
示すように、鋼管杭9の外周面に設けられる突起21と
上下方向のレベル差がつけられて設けられている。鋼管
杭9における前記鞘管1に対応する範囲の外周面には、
上下方向に間隔をおいて、環状に鉄筋が配設されている
と共に溶接により固定されて突起21が形成され、鞘管
1内の突起22と鋼管杭9の外表面の突起21とによ
り、モルタル10aを介して鞘管1と鋼管杭9との一体
化およびずれ止め作用が図られ、また鋼管杭9上部の上
部工に作用する地震時慣性力,上載荷重,波浪等の外力
(水平力および上向きおよび下向きの力)を確実に鋼管
杭9に伝達することができる。An annular reinforcing bar is fixed to the inner peripheral surface of the sheath tube 1 at intervals in the up-down direction by welding.
2 is provided, and the mortar filled in the sheath tube 1 by the projections 22 acts to prevent slippage from the steel pipe pile 9. As shown in FIGS. 11 and 21, the protrusion 22 is provided with a vertical level difference from the protrusion 21 provided on the outer peripheral surface of the steel pipe pile 9. On the outer peripheral surface of the steel pipe pile 9 in a range corresponding to the sheath pipe 1,
Reinforcing bars are disposed annularly at intervals in the vertical direction and are fixed by welding to form projections 21. The projections 22 in the sheath tube 1 and the projections 21 on the outer surface of the steel pipe pile 9 form a mortar. 10a, the sheath tube 1 and the steel pipe pile 9 are integrated and prevented from slipping, and an external force (horizontal force, (Upward and downward forces) can be reliably transmitted to the steel pipe pile 9.
【0028】また図21に示すように、鞘管1の上端面
に、周方向に等角度間隔をおいて複数(3つあるいは4
つ)の揺動防止治具23を設けるようにしてもよい。こ
の揺動防止治具23は、鞘管1の上端面に鋼板からなる
ボルト保持部材23aが溶接により固定され、前記ボル
ト保持部材23aには、鋼管杭9の中心に向かうように
横雌ねじ孔23bが設けられ、前記横雌ねじ孔23bに
は、揺動防止用ボルト23cが螺合されている。前記揺
動防止用ボルト23cの先端部を鋼管杭9の外表面に圧
着することにより、鞘管1の揺動を防止することがで
き、すなわち分割フレーム構造体18あるいはフレーム
構造体19の揺動を防止することができ、鞘管1内に打
設されるモルタル10aの初期養生を確実にすることが
できる。なお、前記揺動防止治具23は鞘管1に直接雌
ねじ孔を設けるようにしてもよく、このようにすると、
鞘管1から鋼管杭9を上方に突出させることなく、図3
に示す実施形態のように鞘管1内に鋼管杭9の上部を納
めることができる。As shown in FIG. 21, a plurality of (three or four) are provided on the upper end surface of the sheath tube 1 at equal angular intervals in the circumferential direction.
) May be provided. The rocking prevention jig 23 has a bolt holding member 23a made of a steel plate fixed to the upper end surface of the sheath tube 1 by welding. The bolt holding member 23a has a lateral female screw hole 23b facing the center of the steel pipe pile 9. The lateral female screw hole 23b is screwed with a swing prevention bolt 23c. By crimping the tip of the rocking prevention bolt 23c to the outer surface of the steel pipe pile 9, rocking of the sheath tube 1 can be prevented, that is, rocking of the divided frame structure 18 or the frame structure 19. Can be prevented, and the initial curing of the mortar 10a cast into the sheath tube 1 can be ensured. Note that the swing prevention jig 23 may be provided with a female screw hole directly in the sheath tube 1.
Without projecting the steel pipe pile 9 upward from the sheath pipe 1, FIG.
The upper part of the steel pipe pile 9 can be accommodated in the sheath tube 1 as in the embodiment shown in FIG.
【0029】また図19に示すように、鞘管1の内周面
の中間部または上部に、周方向に間隔をおいて鋼製等の
半円状のスペーサー32の基端部を溶接等により固定す
るようにして、スペーサー32を設けるようにすると、
鞘管1を備えた分割フレーム構造体18またはフレーム
構造体19あるいはこれを備えたプレキャスト製コンク
リート製上部工50を嵌設するときに、鞘管1内に配置
されたスペーサ−32をガイドにしながら鋼管杭9に高
精度で配設することができ、かつ所定のかぶりを確保す
ることができる。As shown in FIG. 19, the base end of a semicircular spacer 32 made of steel or the like is welded to the middle or upper portion of the inner peripheral surface of the sheath tube 1 at circumferential intervals. By fixing and providing the spacer 32,
When fitting the divided frame structure 18 or the frame structure 19 having the sheath tube 1 or the precast concrete superstructure 50 having the same, the spacer 32 arranged in the sheath tube 1 is used as a guide. It can be arranged on the steel pipe pile 9 with high precision, and a predetermined covering can be secured.
【0030】図12は、上部工用フレーム構造体19を
示したものであって、一対の前記上部工用分割フレーム
構造体18を、同レベルで間隔をおいて平行に、かつ前
記継手用鋼管2cが対向するように配置し、かつ対向す
る継手用鋼管2cの端部に補強用鋼管2dの端部が溶接
により固定されて、ほぼ平面矩形状、または平面井桁状
の上部工用フレーム構造体19が構成されている。FIG. 12 shows a superstructure frame structure 19, in which a pair of the superstructure divided frame structures 18 are arranged in parallel at the same level and spaced apart from each other, and 2c are arranged so as to face each other, and the end of the reinforcing steel pipe 2d is fixed to the opposite end of the joint steel pipe 2c by welding to form a substantially planar rectangular or flat cross-shaped superstructure frame structure. 19 are configured.
【0031】前記平面井桁状の上部工用フレーム構造体
19に、図13から図15に示すように、上部工鉄筋A
の一部を構成する多数の上部主筋6cが、鋼管からなる
補強部材2の上方において、対向する鞘管1間の上部鉄
筋定着部6a間に渡って、前後方向または左右方向に間
隔を置いて平行に配置されて端部が溶接により固着さ
れ、また各鞘管1の外側に端部側上部主筋2dが片持ち
式の端部補強部材2の上方において片持ち式に配置され
て、鞘管1における端部側の上部鉄筋定着部6aに溶接
により固着され、また多数の下部主筋6dが鋼管からな
る補強部材2の下方において、対向する鞘管1間の下部
鉄筋定着部6b間に渡って、前後方向または左右方向に
間隔をおいて平行にかつ前記上部主筋6cに対向するよ
うに配置されて端部が溶接により固着され、また各鞘管
1の外側に端部側下部主筋2eが、片持ち式の端部補強
部材2の下方において片持ち式に端部側上部主筋2dに
対向するように配置されて、鞘管1における端部側の下
部鉄筋定着部6bに溶接により固着されている。また前
記上部主筋6cおよび下部主筋6dを囲むように肋筋2
5が間隔をおいて多数配置されて上部主筋6cまたは下
部主筋6dに溶接または番線等により固定されている。As shown in FIG. 13 to FIG. 15, an upper reinforcing steel A
Are arranged at intervals in the front-rear direction or the left-right direction over the reinforcing member 2 made of a steel pipe, between the upper reinforcing bar fixing portions 6a between the opposing sheath tubes 1. The ends are fixed by welding and arranged in parallel, and an upper end-side main reinforcement 2d is arranged outside the respective sheath tubes 1 in a cantilever manner above the cantilever-type end reinforcing member 2 to form a sheath tube. 1 is fixed to the upper reinforcing bar fixing portion 6a on the end side by welding, and a number of lower main reinforcing bars 6d extend between the lower reinforcing bar fixing portions 6b between the opposing sheath tubes 1 below the reinforcing member 2 made of a steel pipe. An end-side lower main reinforcing bar 2e is arranged parallel to the upper main reinforcing bar 6c at an interval in the front-rear direction or the left-right direction and opposed to the upper main reinforcing bar 6c, and an end is fixed by welding. Below the cantilevered end reinforcing member 2 Are arranged so as to face the end side upper main reinforcement 2d cantilevered, it is fixed by welding on the end side of the lower reinforcing bar fixing portion 6b of the sheath pipe 1. The ribs 2 surround the upper main bar 6c and the lower main bar 6d.
A large number 5 are arranged at intervals and fixed to the upper main reinforcing bar 6c or the lower main reinforcing bar 6d by welding or a number line.
【0032】さらに前記片持ち式の端部側上部主筋2d
の先端部に渡って間隔をおいて平行に端部側上部周縁鉄
筋2fが配置されて番線等により端部側上部主筋2dに
固着され、また端部側下部主筋2eの先端部に渡って間
隔をおいて平行に、かつ前記端部側上部周縁鉄筋2fに
対向するように端部側下部周縁鉄筋2gが配置されて番
線等により端部側下部主筋2eに固着され、前記端部側
上部周縁鉄筋2fおよび端部側下部周縁鉄筋2gを囲む
ように肋筋25が配置されて番線等により端部側上部周
縁鉄筋2fまたは端部側下部周縁鉄筋2gに固着されて
いる。また各周縁鉄筋2f,2gの直交する端部交差部
においては、それぞれ番線等により固着されている。ま
た隅部には適宜ハンチ筋(図示を省略した)が配置され
て、番線等により端部周縁鉄筋2f,2gまたは上部主
筋6c,2dまたは下部主筋6d,2e等に固着されて
いる。Further, the cantilevered end side upper main bar 2d is provided.
The end side upper peripheral reinforcing bar 2f is arranged in parallel at intervals over the distal end of the end side, and is fixed to the end side upper main reinforcing bar 2d by a number line or the like, and is spaced over the distal end of the end side lower main reinforcing bar 2e. An end-side lower peripheral reinforcing bar 2g is arranged in parallel with the end-side upper peripheral reinforcing bar 2f, and is fixed to an end-side lower main reinforcing bar 2e by a number line, etc. A rib 25 is arranged so as to surround the reinforcing bar 2f and the end-side lower peripheral reinforcing bar 2g, and is fixed to the end-side upper peripheral reinforcing bar 2f or the end-side lower peripheral reinforcing bar 2g by a number line or the like. In addition, at the intersections of the end portions of the peripheral reinforcing bars 2f and 2g which are orthogonal to each other, they are fixed to each other with a line or the like. Haunch bars (not shown) are appropriately disposed at the corners, and are fixed to the end peripheral reinforcing bars 2f, 2g, the upper main bars 6c, 2d, or the lower main bars 6d, 2e, etc. by a number line or the like.
【0033】このように構成されて、対向する鞘管1間
において、鋼管からなる補強部材2を囲むように主鉄筋
梁26が中空鋼管からなる補強部材2を囲むように構成
されると共に、鞘管1から片持ち式に張り出すように、
張り出し鉄筋梁27が端部側補強部材2を囲むように構
成され、また張り出し鉄筋梁27の端部に渡って、周縁
鉄筋梁28が形成され、かつ前記周縁鉄筋梁28は上部
工周縁部を補強するように矩形環状に構成されている。
前記主鉄筋梁26と張り出し鉄筋梁27と周縁鉄筋梁2
8とにより上部工鉄筋Aが構成され、必要に応じて、開
口部を有しないフレーム構造体付き鉄筋コンクリート上
部工50にするために、前記主鉄筋梁26と張り出し鉄
筋梁27と周縁鉄筋梁28との上部にわたって床鉄筋
(図示を省略した)が配設される。The main reinforcing bar 26 is configured to surround the reinforcing member 2 made of a hollow steel tube so as to surround the reinforcing member 2 made of a steel tube between the opposing sheath tubes 1. So that it cantilevered from tube 1
An overhanging reinforced beam 27 is configured to surround the end-side reinforcing member 2, and a peripheral reinforced beam 28 is formed over the end of the overhanged reinforced beam 27, and the peripheral reinforced beam 28 extends over the upper peripheral edge. It is configured in a rectangular ring shape to reinforce.
The main reinforcing beam 26, the overhanging reinforcing beam 27, and the peripheral reinforcing beam 2
8 constitutes an upper reinforcing bar A, and if necessary, the main reinforcing beam 26, the overhanging reinforcing beam 27, the peripheral reinforcing beam 28, and the reinforcing steel superstructure 50 with a frame structure having no opening. A floor reinforcing bar (not shown) is disposed over the upper part of the floor.
【0034】前述のような分割フレーム構造体18また
はフレーム構造体19あるいは上部工鉄筋付きフレーム
構造体19を予め工場または陸上ヤード等で製作して、
地盤に打設された鋼管杭9に、適宜陸上または海上輸送
により搬送し、配置するようにしてもよく、あるいは上
部工鉄筋付きフレーム構造体19の周囲に型枠(図示を
省略した)を一体に配設すると共に支保工(図示を省略
した)を一体に配設した状態まで、予め工場または陸上
ヤード等で製作して、これを搬送するようにしてもよ
く、あるいは上部工鉄筋付きフレーム構造体19を埋め
込むようにコンクリートを打設し、養生・硬化したフレ
ーム構造体付きプレキャスト鉄筋コンクリート製上部工
50を予め工場または陸上ヤード等で製作して、これを
地盤に打設された鋼管杭9に、適宜陸上または海上輸送
により搬送し、配置するようにしてもよい。The above-described divided frame structure 18 or frame structure 19 or frame structure 19 with upper rebar is manufactured in advance in a factory or a land yard, and the like.
The steel pipe pile 9 cast on the ground may be conveyed and placed by land or sea transportation as appropriate, or a formwork (not shown) may be integrated around the frame structure 19 with the upper rebar. To a state in which a shoring (not shown) is integrally provided, and may be manufactured in advance in a factory or a land yard, and may be transported. Concrete is cast to bury the body 19, and a precast reinforced concrete superstructure 50 with a cured and hardened frame structure is manufactured in advance in a factory or a land yard or the like, and this is mounted on the steel pipe pile 9 set in the ground. Alternatively, they may be transported and arranged by land or sea transportation as appropriate.
【0035】このフレーム構造体付きプレキャスト鉄筋
コンクリート製上部工50における鞘管1の部分におい
ては、下端は開口している。なお、図13〜図15にお
いては、上部工係止部材3および吊り金具4を省略して
いる。The lower end of the portion of the sheath tube 1 in the precast reinforced concrete superstructure 50 with the frame structure is open. In FIGS. 13 to 15, the upper work locking member 3 and the suspension fitting 4 are omitted.
【0036】図16は本発明において使用される鞘管1
の下端部に配置される底型枠11を示すものであって、
鋼管杭9の上方部の所定位置に、半環状上部支承板11
aおよび半円筒状筒体11b並びにボルト挿通用横孔を
有する連結用フランジ11cを備えた半分割円筒状の一
対の底型枠ユニット11dがそれらの横孔に挿通された
連結用ボルト11eにより連結されて底型枠11が構成
され、前記底型枠11は、その上面がプレキャスト鉄筋
コンクリート製上部工50における鞘管1の下端レベル
になるように鋼管杭9に配設され、かつ前記連結用ボル
ト11eが緊締されて鋼管杭9を締め付けるように、前
記底型枠ユニット11dが鋼管杭9に強固に圧着固定さ
れる(図18参照)。このような底型枠11を使用する
場合には、図22に示すように、底型枠11の上面に、
ゴムや弾性的性質を有する気泡体等の環状のシール用緩
衝材12を載置して、これに鞘管1の下端面を載置する
と、鞘管1を緩衝しながら載置することができると共
に、鞘管1内に充填されるモルタル10a等の経時硬化
性材料10の漏洩を防止することができる。FIG. 16 shows a sheath tube 1 used in the present invention.
Shows a bottom formwork 11 arranged at the lower end of
A semi-circular upper bearing plate 11 is provided at a predetermined position above the steel pipe pile 9.
a, and a pair of half-cylindrical bottom mold units 11d having a semi-cylindrical cylindrical body 11b and a coupling flange 11c having a lateral hole for bolt insertion are coupled by coupling bolts 11e inserted into the lateral holes. The bottom form 11 is disposed on the steel pipe pile 9 such that the upper surface thereof is at the lower end level of the sheath tube 1 in the precast reinforced concrete superstructure 50, and the connection bolts are provided. The bottom form unit 11d is firmly pressed and fixed to the steel pipe pile 9 so that the steel pipe pile 9 is tightened by tightening the steel pipe pile 11e (see FIG. 18). When such a bottom form 11 is used, as shown in FIG.
When the annular sealing buffer material 12 such as rubber or a foam having elastic properties is placed and the lower end surface of the sheath tube 1 is placed thereon, the sheath tube 1 can be placed while buffering. At the same time, it is possible to prevent the time-hardening material 10 such as the mortar 10a filled in the sheath tube 1 from leaking.
【0037】また前記底型枠11に代えて鞘管1にシー
ル材13を設けるようにしてもよい。この場合には、図
21に示すように、鞘管1の下部内周面に、一対の鋼製
環状内向きフランジからなるシール材把持用突設部材1
4(14a,14b)が上下方向に間隔をおいて当接す
るように配置されて、それらの一方または両方の基端部
(外周縁部)が溶接により前記鞘管1に固定され、前記
各シール材把持用突設部材14a,14bの間に、ポリ
エチレン気泡体あるいは独立気泡を有する架橋ポリオレ
フィン気泡体等の弾性的性質を有する気泡体等の環状シ
ール材13の基端部(外周縁部)が当接するように配置
され、前記各シール材把持用突設部材14a,14bと
シール材13とに周方向に間隔をおいて設けられたシー
ル材係止ボルト挿通用縦孔15に渡ってシール材係止用
ボルト16が挿通されると共に、これに螺合されたナッ
トにより緊締されて、前記シール材13はシール材把持
用突設部材14a,14bに固定されている。また前記
シール材13の内径寸法は鋼管杭9の外径寸法よりも小
さく設定され、かつ前記シール材13の内周面は、図2
0に示すように、上縁部に向かって、鋭角になるように
漸次傾斜して、上縁部が薄肉先端部13aになるように
形成されている。したがって、図21に示すように、鞘
管1を鋼管杭9に上側から嵌設するとシール材13が鋼
管杭9の外表面に屈曲した状態で、鋼管杭9の外表面に
密接に圧接することができ、そのためシール材13を鞘
管1の底部のシール装置として利用することができ、鋼
管杭9と鞘管1の間にモルタル10a等の経時硬化性充
填材10を充填しても、これを保持することができる。Further, a sealing material 13 may be provided on the sheath tube 1 instead of the bottom mold 11. In this case, as shown in FIG. 21, on the inner peripheral surface of the lower part of the sheath tube 1, a projecting member 1 for gripping a sealing material comprising a pair of steel annular inward flanges is provided.
4 (14a, 14b) are arranged so as to abut on each other at an interval in the vertical direction, and one or both base ends (outer peripheral edges) thereof are fixed to the sheath tube 1 by welding, and the respective seals are provided. The base end (outer peripheral edge) of the annular sealing material 13 such as a foam having elastic properties such as a polyethylene foam or a cross-linked polyolefin foam having closed cells is provided between the material gripping protruding members 14a and 14b. The sealing material extends over a vertical hole 15 for inserting a sealing material locking bolt, which is disposed so as to be in contact with and is provided at a circumferential interval between the sealing material gripping protruding members 14a and 14b and the sealing material 13. The locking bolt 16 is inserted and tightened by a nut screwed to the locking bolt 16, so that the sealing member 13 is fixed to the sealing member gripping projections 14a, 14b. The inner diameter of the sealing member 13 is set smaller than the outer diameter of the steel pipe pile 9, and the inner peripheral surface of the sealing member 13 is formed as shown in FIG.
As shown in FIG. 0, it is formed so as to be gradually inclined toward the upper edge so as to form an acute angle so that the upper edge becomes the thin end portion 13a. Therefore, as shown in FIG. 21, when the sheath tube 1 is fitted to the steel pipe pile 9 from above, the sealing material 13 is pressed against the outer surface of the steel pipe pile 9 in a state of being bent on the outer surface of the steel pipe pile 9. Therefore, the sealing material 13 can be used as a sealing device at the bottom of the sheath tube 1, and even if the time-hardening filler 10 such as mortar 10 a is filled between the steel pipe pile 9 and the sheath tube 1, Can be held.
【0038】また底型枠11を使用する場合には、これ
に鞘管1を嵌合載置することにより、フレーム構造体1
9等を支持させることができるが、図21に示すモルタ
ル10aを保持するためのシール材13を使用する場合
には、鋼管杭9の上端面に鞘管1の上部に固定した上部
工係止部材3を直接または適宜スペーサーを介在させて
載置するようにしてもよい。また適宜鋼管杭9外周面に
鞘管1を支持するためのブラケット(図示を省略した)
を設けるようにしてもよい。When the bottom form 11 is used, the sheath tube 1 is fitted and mounted on the bottom form 11 to thereby form the frame structure 1.
9 can be supported, but when a sealing material 13 for holding the mortar 10a shown in FIG. The member 3 may be placed directly or with an appropriate spacer interposed. A bracket (not shown) for supporting the sheath tube 1 on the outer peripheral surface of the steel pipe pile 9 as appropriate.
May be provided.
【0039】また、図17および図18に示すように、
各鋼管杭9に装着された底型枠11における半環状上部
支承板11a相互を、前後方向および左右方向ならびに
対角線方向にL型形鋼等の杭間隔保持部材17により溶
接またはボルトにより連結固定すると、前後方向および
左右方向に隣り合う鋼管杭9の間隔を所定の間隔にする
ことができるため、プレキャスト鉄筋コンクリート上部
工50等における鞘管1を正確にかつ確実に鋼管杭9に
嵌合装着することができる。As shown in FIGS. 17 and 18,
The semi-annular upper bearing plates 11a of the bottom formwork 11 attached to the steel pipe piles 9 are connected and fixed to each other by a pile spacing member 17 such as an L-shaped steel in the front-rear direction, the left-right direction, and the diagonal direction by welding or bolts. Since the interval between the steel pipe piles 9 adjacent in the front-rear direction and the left-right direction can be set to a predetermined interval, the sheath pipe 1 in the precast reinforced concrete superstructure 50 or the like can be accurately and reliably fitted and mounted on the steel pipe pile 9. Can be.
【0040】図1から図8は本発明における桟橋等の杭
式基礎構造物40またはこれを直列に多数設けて構成し
た桟橋51を示すものであって、陸側から沖側または陸
側に沿って、前後方向および左右方向に間隔を置いて支
持層20aに支持させるように水底地盤20に複数の鋼
管杭9が4本一組のユニットとして打設され、前記鋼管
杭9の打設間隔は、前記プレキャストコンクリート製上
部工50またはフレーム構造体19あるいは分割型フレ
ーム構造体18における鞘管1間の間隔に設定されてい
る。なお、各鋼管杭9には、飛沫帯に対応する部分に重
防食被覆42が施されている。FIGS. 1 to 8 show a pile type foundation structure 40 such as a pier in the present invention or a pier 51 constructed by arranging many of them in series. The pier 51 extends from land side to offshore side or land side. Then, a plurality of steel pipe piles 9 are driven into the underwater ground 20 as a set of four units so that the steel pipe piles 9 are supported by the support layer 20a at intervals in the front-rear direction and the left-right direction. The distance between the sheath pipes 1 in the precast concrete superstructure 50 or the frame structure 19 or the split type frame structure 18 is set. Each steel pipe pile 9 is provided with a heavy anticorrosion coating 42 at a portion corresponding to the splash zone.
【0041】このような配置間隔に設定された状態で打
設された鋼管杭9に嵌合されたプレキャストコンクリー
ト製上部工50と鋼管杭9とを、鋼管杭9と鞘管1の間
に充填されるモルタル10a等の経時硬化性充填材10
により充填硬化して一体化する。この実施形態の場合に
は、プレキャスト製コンクリート上部工50と鋼管杭9
とを一体化するだけであるので、施工期間を大幅に短縮
することができる。このため、桟橋51の構築費用を大
幅に低減することができるばかりでなく、中空補強部材
を有するフレーム構造体19を使用する場合には、プレ
キャスト製コンクリート上部工の軽量化をはかることが
できる。なお図1の場合は、上部工全面がほぼ閉塞した
状態のプレキャスト鉄筋コンクリート製上部工50が使
用された形態が示されている。The steel pipe pile 9 and the precast concrete superstructure 50 fitted to the steel pipe pile 9 cast in a state where the arrangement interval is set are filled between the steel pipe pile 9 and the sheath pipe 1. Time-curable filler 10 such as mortar 10a
To fill and harden to integrate. In the case of this embodiment, the precast concrete superstructure 50 and the steel pipe pile 9
The construction period can be greatly shortened because the construction is simply integrated. Therefore, not only can the construction cost of the pier 51 be significantly reduced, but also when the frame structure 19 having the hollow reinforcing member is used, the weight of the precast concrete superstructure can be reduced. FIG. 1 shows a form in which a precast reinforced concrete superstructure 50 in which the entire superstructure is substantially closed is used.
【0042】前記プレキャストコンクリート製上部工5
0を予め製作して桟橋51を構築するばかりでなく、本
発明の場合は、下記において説明するように、種々のユ
ニット化された変形形態においても実施可能であるの
で、これらの変形形態について施工する場合について説
明する。例えば、図12に示す上部工用フレーム構造体
19を予め工場または陸上ヤード等に於いて製作して、
これを搬送して鋼管杭9に配置するようにしてもよい。
この場合には、鋼管杭9に対し上部工用フレーム構造体
19における各鞘管1の部分をほぼ同心状に配置し、鞘
管1と鋼管杭9との間にモルタル10a等の経時硬化性
材料10を充填して、鋼管杭9と上部工用フレーム構造
体19とを一体化し、鞘管1間に配置されている芯材を
兼ねる補強部材2を支保材の一部として活用しながら、
上部工鉄筋Aの配筋作業,型枠58,60の配設および
底部型枠保持部材57(図27および図28参照)等の
支保工を設置し、型枠58,60内にコンクリート8を
打設して、養生・硬化させて、一ユニットの鋼管杭式基
礎構造物40を構築する。このような工程を複数個所同
時に施工するかまたは適宜繰り返し施工して、図1に示
すような連続した桟橋51を構築するようにする。この
実施形態の場合には、上部工用フレームが構造体化され
ているので、施工期間を比較的短縮することができ、ま
た桟橋51の構築費用を比較的低減することができるば
かりでなく、上部工50の軽量化をはかることができ
る。特に上部工用フレーム構造体19により鋼管杭9の
杭頭が強固に連結されるので、上部工の施工途中におい
て、波浪の影響を受けずらい。またフレーム構造体1
8,19は予め工場や陸上ヤード等で製作できるため、
従来のように海洋上等の現位置における作業時間が極め
て短くて済む。The precast concrete superstructure 5
In addition to constructing the pier 51 by previously manufacturing the pier 51, the present invention can be implemented in various unitized modifications as described below. Will be described. For example, the superstructure frame structure 19 shown in FIG. 12 is manufactured in advance in a factory or a land yard, and the like.
This may be transported and arranged on the steel pipe pile 9.
In this case, the portions of the respective sheath tubes 1 in the superstructure frame structure 19 are disposed substantially concentrically with respect to the steel tube piles 9, and the aging of the mortar 10 a or the like between the sheath tube 1 and the steel tube piles 9 with time. The material 10 is filled, the steel pipe pile 9 and the superstructure frame structure 19 are integrated, and the reinforcing member 2 serving also as a core disposed between the sheath pipes 1 is used as a part of the supporting material.
Reinforcing work for the upper rebar A, arranging the formwork 58 and 60, and installing a support such as a bottom formwork holding member 57 (see FIGS. 27 and 28), and placing the concrete 8 in the formwork 58 and 60. It is cast, cured and hardened to construct a steel pipe pile type substructure 40 of one unit. Such steps are performed simultaneously at a plurality of locations or are repeated as appropriate to construct a continuous pier 51 as shown in FIG. In this embodiment, since the superstructure frame is structured, the construction period can be relatively shortened, and the construction cost of the pier 51 can be relatively reduced, The weight of the superstructure 50 can be reduced. In particular, since the pile head of the steel pipe pile 9 is firmly connected by the frame structure 19 for the superstructure, it is hard to be affected by waves during the construction of the superstructure. Frame structure 1
Since 8, 19 can be manufactured in advance in a factory or land yard,
The working time at the current position on the sea or the like as in the related art can be extremely short.
【0043】また、上部工用フレーム構造体19とこれ
に梁鉄筋を含む上部工鉄筋Aを予め溶接等により固着し
た上部工鉄筋付き上部工用フレーム構造体19を予め工
場または陸上ヤード等に於いて製作して、これを搬送し
て鋼管杭9に配置するようにしてもよい。この場合に
は、上部工鉄筋付き上部工用フレーム構造体19におけ
る各鞘管1部分を同心状に配置し、鞘管1と鋼管杭9と
の間にモルタル10a等の経時硬化性材料10を充填し
て、鋼管杭9と上部工鉄筋付き上部工用フレーム構造体
19とを一体化し、各鞘管1間に配置されている芯材を
兼ねる補強部材2を支保材の一部として活用しながら、
型枠58,60および底部型枠保持部材55(図27お
よび図28参照)等の支保工を設置し、型枠58,60
内にコンクリート8を打設して、養生・硬化させ、一ユ
ニットの杭式基礎構造物40を構築する。このような工
程を複数同時に施工するかまたは適宜繰り返し施工し
て、図1に示すような連続した桟橋51を構築するよう
にする。Also, an upper frame structure 19 with an upper reinforcing bar to which an upper frame bar 19 including a beam reinforcing bar is fixed in advance by welding or the like is attached to the upper frame structure 19 at a factory or a land yard. It may be manufactured and transported and arranged on the steel pipe pile 9. In this case, the respective sheath pipes 1 in the superstructure frame structure 19 with the upper steel rebar are arranged concentrically, and the time-hardening material 10 such as mortar 10 a is placed between the sheath pipe 1 and the steel pipe pile 9. After filling, the steel pipe pile 9 and the upper frame structure 19 with the upper steel bar are integrated, and the reinforcing member 2 serving also as a core disposed between the respective sheath pipes 1 is used as a part of the supporting material. While
Supports such as the molds 58 and 60 and the bottom mold holding member 55 (see FIGS. 27 and 28) are installed, and the molds 58 and 60 are installed.
Concrete 8 is poured into the inside, cured and hardened, and a pile type substructure 40 of one unit is constructed. A plurality of such steps are performed at the same time or are repeated as appropriate, so that a continuous pier 51 as shown in FIG. 1 is constructed.
【0044】また、図27および図28に示すように、
上部工用フレーム構造体19とこれに梁鉄筋を含む上部
工鉄筋Aを予め溶接等により固着した上部工鉄筋付き上
部工用フレーム構造体19に底部型枠保持部材55等の
支保工および型枠58,60を組み立てた状態のものを
予め工場または陸上ヤード等に於いて製作し、これを搬
送して鋼管杭9に配置するようにしてもよい。なお、型
枠は通常脱型するが、埋め殺し型枠とする場合には、繊
維補強コンクリート(GRC)からなる繊維補強コンク
リート版を使用する場合が多い。この形態について、さ
らに詳細に説明すると、鋼管等の中空部材からなる補強
部材2(2a,2b)に、その長手方向に間隔をおい
て、ほぼ逆U字状あるいは逆凹字状等の鋼棒からなる多
数の底部型枠保持部材55が配置されると共に、その各
底部型枠保持部材55における半円状上部56が嵌合載
置されると共に溶接により固定されて、各補強部材2
(2a,2b)に底部型枠保持部材55が補強部材2
(2a,2b)に支持され、また前記底部型枠保持部材
55の螺杆からなる各脚部57が分割型等の底部型枠5
8の透孔に挿通されて、前記各脚部57に螺合されると
共に前記底部型枠58の下面に係合されたナット等の係
止部材59により、底部型枠58は支持されている。ま
た底部型枠58は、底型枠11の外周側面に当接される
ように配設されるか、または鞘管1の下端円形外周面に
当接されるように配置され、鞘管1に当接される場合に
は、鞘管1との当接部が円弧状側面(図示を省略)を備
えている。また補強部材2(2a,2b)の両側あるい
は端部側周縁鉄筋2f,2gの両側に間隔をおいて対向
するように配置されている分割型等の側部型枠60は前
記底部型枠58に載置されると共に、型枠相互の連結金
具(図示を省略した)により、底部型枠58に側部型枠
60が着脱自在に取り付けられると共に、対向するよう
に配置された前記各側部型枠60は、両端部に型枠固定
用ナットおよび型枠支承部材およびセパレータ等の型枠
間隔保持具61により所定の間隔を保持されて配設され
ている。なお、小梁側すなわち端部側周縁鉄筋2f,2
gの下方に配置される底部型枠58の中間部を支持する
必要のある場合には、図28aに2点鎖線で示すよう
に、前記補強部材2に固定されている底部型枠保持部材
55の下端部に、前後方向または左右方向に延長するよ
うに、水平に溝形鋼またはH形鋼等の底部型枠支持部材
62の上端部を支持させ、その底部型枠支持部材に載置
するように端部側周縁の底部型枠58を載置するように
してもよい。また、端部側に張り出すように設けられて
いる補強部材2に取り付けられている複数の底部型枠保
持部材57により、端部側の底部型枠58は支持されて
いる。この実施形態の場合には、上部工鉄筋付き上部工
用フレーム構造体19に、支保部材を兼ねる補強部材2
および底部型枠保持部材55等の型枠を保持する支保工
および型枠58,60を組み立てた状態における各鞘管
1部分を鋼管杭9にほぼ同心状に配置し、鞘管1と鋼管
杭9との間にモルタル10a等の経時硬化性材料10を
充填して、鋼管杭9と上部工鉄筋付き上部工用フレーム
構造体19とを一体化し、各鞘管1間に配置されている
芯材を兼ねる補強部材2を支保材の一部として活用しな
がら、型枠58,60および支保工を設置し、型枠5
8,60内にコンクリート8を打設して、養生・硬化さ
せて、一ユニットの杭式基礎構造物40を構築する。こ
のような工程を複数同時に施工するかまたは適宜繰り返
し施工して、図1に示すような連続した桟橋51を構築
するようにする。As shown in FIGS. 27 and 28,
Supporting and formwork of the bottom formwork holding member 55 and the like on the superstructure frame structure 19 with upper rebars, in which the superstructure frame structure 19 and the upper rebar A including the beam rebar are fixed in advance by welding or the like. The assembled state of 58 and 60 may be manufactured in advance in a factory or a land yard or the like, and may be transported and placed on the steel pipe pile 9. The mold is usually removed from the mold. However, when the mold is used as a buried mold, a fiber reinforced concrete plate made of fiber reinforced concrete (GRC) is often used. This form will be described in more detail. A steel bar having a substantially inverted U-shape or an inverted concave shape is provided on a reinforcing member 2 (2a, 2b) formed of a hollow member such as a steel pipe at intervals in the longitudinal direction. Are formed, and the semicircular upper portions 56 of the respective bottom mold holding members 55 are fitted and mounted, and are fixed by welding.
In (2a, 2b), the bottom mold holding member 55 is
(2a, 2b), and each leg 57 made of a screw of the bottom mold holding member 55 is connected to the bottom mold 5 such as a split mold.
The bottom mold 58 is supported by a locking member 59 such as a nut that is inserted into the through hole 8 and is screwed to each of the legs 57 and engaged with the lower surface of the bottom mold 58. . The bottom mold 58 is disposed so as to be in contact with the outer peripheral side surface of the bottom mold 11 or is arranged so as to be in contact with the lower circular outer peripheral surface of the sheath tube 1. In the case of contact, the contact portion with the sheath tube 1 has an arc-shaped side surface (not shown). Further, a side mold 60 such as a split mold, which is arranged so as to face at both sides of the reinforcing member 2 (2a, 2b) or both sides of the end side peripheral reinforcing bars 2f, 2g with a space therebetween, is the bottom mold 58. The side mold 60 is removably mounted on the bottom mold 58 by a metal fitting (not shown) for interconnecting the molds, and the respective side parts arranged to face each other. The formwork 60 is disposed at both ends thereof at predetermined intervals by formwork fixing nuts, formwork support members, and formwork space holding members 61 such as separators. In addition, the small beam side, that is, the end side peripheral reinforcing bar 2f, 2
When it is necessary to support the intermediate portion of the bottom formwork 58 disposed below the bottom form g, the bottom formwork holding member 55 fixed to the reinforcing member 2 as shown by a two-dot chain line in FIG. The upper end of a bottom form support member 62 such as a channel steel or an H-section steel is horizontally supported at the lower end of the base form so as to extend in the front-rear direction or the left-right direction, and is placed on the bottom form support member. The bottom mold 58 on the end side peripheral edge may be placed as described above. The bottom formwork 58 on the end side is supported by a plurality of bottom formwork holding members 57 attached to the reinforcing member 2 provided to protrude to the end side. In the case of this embodiment, the reinforcing member 2 also serving as a support member is provided on the upper frame structure 19 with an upper reinforcing bar.
In addition, the sheath pipe 1 in a state in which the supporting structure for holding the formwork such as the bottom formwork holding member 55 and the formwork 58, 60 is assembled is disposed substantially concentrically on the steel pipe pile 9, and the sheath pipe 1 and the steel pipe pile are arranged. 9 is filled with a time-hardening material 10 such as a mortar 10 a to integrate the steel pipe pile 9 and the upper frame structure 19 with an upper reinforcing bar, and a core disposed between the sheath pipes 1. While utilizing the reinforcing member 2 also serving as a material as a part of the support material, the formwork 58, 60 and the support work are installed, and the formwork 5
The concrete 8 is poured into the insides 8 and 60, and the concrete 8 is cured and hardened to construct the pile-type substructure 40 of one unit. A plurality of such steps are performed at the same time or are repeated as appropriate, so that a continuous pier 51 as shown in FIG. 1 is constructed.
【0045】また、前記実施形態のように、上部工用フ
レーム構造体19とこれに梁鉄筋を含む上部工鉄筋Aを
予め溶接等により固着した上部工鉄筋付き上部工用フレ
ーム構造体19に支保工および型枠58,60を組み立
てコンクリート8を打設し、脱型して上部工用フレーム
構造体19を内臓したプレキャスト製鉄筋コンクリート
上部工50としたものを予め工場または陸上ヤード等に
於いて製作して、これを搬送して鋼管杭9に配置するよ
うにしてもよい。この場合には、プレキャスト製鉄筋コ
ンクリート上部工50における各鞘管1部分を鋼管杭9
にほぼ同心状に配置し、鞘管1と鋼管杭9との間にモル
タル10a等の経時硬化性材料10を充填して、鋼管杭
9とプレキャスト製鉄筋コンクリート上部工50とを一
体化し、一ユニットの杭式基礎構造物40を構築する。
このような工程を複数同時に施工するかまたは適宜繰り
返し施工して、図1に示すような連続した桟橋51を構
築するようにする。Further, as in the above-described embodiment, the superstructure frame structure 19 and the superstructure steel bar A including the beam reinforcement are supported by the superstructure frame structure 19 with the upper steel bar which is previously fixed by welding or the like. The prefabricated reinforced concrete superstructure 50 with the superstructure frame structure 19 built therein is manufactured in advance in a factory or a land yard or the like. Then, this may be transported and arranged on the steel pipe pile 9. In this case, a part of each sheath pipe in the precast reinforced concrete superstructure 50 is connected to the steel pipe pile 9.
And a time-hardening material 10 such as mortar 10a is filled between the sheath pipe 1 and the steel pipe pile 9 to integrate the steel pipe pile 9 and the precast reinforced concrete superstructure 50 into one unit. Is constructed.
A plurality of such steps are performed at the same time or are repeated as appropriate, so that a continuous pier 51 as shown in FIG. 1 is constructed.
【00046】本発明を実施する場合に、鞘管1と鋼管
杭9との一体化を高めるために、図23に示すような、
帯状鋼板の表面に間隔をおいて断面台形の線状突起を長
手方向に連続して設けた帯状鋼板をコイル状に構成した
線状突起付きコイル37から、これをスパイラル製管機
により製作し、図25に示すような内面に突起21が一
体に設けられた内面突起付き鋼管31を所要の寸法に切
断して鞘管1の本体を構成することもできる。このよう
にすると、鞘管1内に鉄筋を溶接により固定する工程を
省略することができる。When the present invention is carried out, in order to enhance the integration between the sheath tube 1 and the steel pipe pile 9, as shown in FIG.
From a coil 37 with a linear projection formed in a coil shape from a strip-shaped steel sheet having a trapezoidal linear projection continuously provided in the longitudinal direction at intervals on the surface of the strip-shaped steel sheet, this is manufactured by a spiral tube machine, As shown in FIG. 25, the main body of the sheath tube 1 can be formed by cutting a steel pipe 31 with an inner surface projection having the projections 21 integrally provided on the inner surface to a required size. This makes it possible to omit the step of fixing the reinforcing steel in the sheath tube 1 by welding.
【0047】また本発明を実施する場合に、補強部材2
としては、通常の鋼管に代えて、図23に示すような線
状突起付きコイル37からスパイラル製管機により製作
した図24に示すような外面突起付き鋼管30からなる
中空部材34(33)としてもよく、また図26(A)
に示すように、鋼製H型鋼あるいは溝形鋼等の側方が開
口した開断面部材38を並設して、(必要に応じ、隣り
合うフランジ41相互を長手方向に間隔を置いた部分溶
接または連続溶接により固着し、)これにより長手方向
に中空部分を備えた中空部材35(33)からなる中空
の補強部材2を構成してもよく、その長手方向の端部を
鞘管1に溶接により固定するようにして、分割フレーム
構造体18あるいはフレーム構造体19を構成するよう
にしてもよく、またこの場合に上部工コンクリート8と
の一体化を高めるために、図26(B)、(C)に示す
ように、各フランジ外表面に長手方向に間隔をおいて、
多数の突起39を設けるようにするとよい。このように
中空部材33を使用するとコンクリート8の打設量を減
らすことができ、上部工部分の軽量化を図ることができ
るばかりでなく、上部工50を強固に補強することがで
き、地震時等に隣り合う鋼管杭9相互を離反させるよう
な力が作用しても、それに対する抵抗力を高めることが
できる。In practicing the present invention, the reinforcing member 2
Instead of a normal steel pipe, a hollow member 34 (33) made of a steel pipe 30 with an external projection as shown in FIG. 24 manufactured by a spiral tube machine from a coil 37 with a linear projection as shown in FIG. FIG. 26 (A)
As shown in FIG. 5, side-opening members 38 such as steel H-section steel or channel steel are provided side by side, and (if necessary, the adjacent flanges 41 are partially welded to each other at intervals in the longitudinal direction. Alternatively, the hollow reinforcing member 2 may be constituted by a hollow member 35 (33) having a hollow portion in the longitudinal direction, and the longitudinal end portion may be welded to the sheath tube 1. 26, the divided frame structure 18 or the frame structure 19 may be configured. In this case, in order to enhance the integration with the superstructure concrete 8, FIGS. As shown in C), the outer surface of each flange is longitudinally spaced,
A large number of projections 39 may be provided. By using the hollow member 33 in this manner, the amount of concrete 8 to be poured can be reduced, and not only the weight of the superstructure can be reduced, but also the superstructure 50 can be strongly reinforced. Even when a force acting to separate the adjacent steel pipe piles 9 from each other acts, the resistance to the force can be increased.
【0048】前記実施形態においては、工場から建設地
点までの輸送の制約を考慮して、半分割フレーム構造体
18により分割フレーム構造体19を構成するようにし
たが、本発明を実施する場合、半分割フレーム構造体1
8の継手用短尺鋼管2cを端部張り出し補強部材2b程
度若干長くすると共にその端部を閉塞して構成した、半
分割フレーム構造体18をフレーム構造体19として、
間隔をおいて直列に打設された鋼管杭9に装着して、杭
式基礎構造物40を構成するようにしてもよい。In the above-described embodiment, the divided frame structure 19 is constituted by the half-divided frame structure 18 in consideration of the restriction of transportation from the factory to the construction point. Half-divided frame structure 1
The half-segment frame structure 18 is formed as a frame structure 19 in which the short steel pipe 2c for joint 8 of FIG.
The pile type substructure 40 may be configured by being mounted on the steel pipe piles 9 that are cast in series at intervals.
【0049】前記実施形態においては、鞘管1以外の上
部工部分に開口部を備えたプレキャスト製鉄筋コンクリ
ート製上部工50あるいは全面が閉塞したプレキャスト
製鉄筋コンクリート製上部工50を使用する形態を示し
たが、いずれの形態を使用するかは、適宜設計に応じて
選択すればよい。In the above embodiment, the precast reinforced concrete superstructure 50 having an opening at the superstructure other than the sheath tube 1 or the precast reinforced concrete superstructure 50 whose entire surface is closed is used. Which form to use may be appropriately selected according to the design.
【0050】[0050]
【発明の効果】本発明によれば、下記のような効果を奏
することができる。 (1)フレーム構造体により杭頭が強固に連結されるの
で、上部工の施工途中において、波浪の影響を受けずら
い。 (2)分割フレーム構造体またはフレーム構造体あるい
は上部工鉄筋付きフレーム構造体さらにはフレーム構造
体を内臓したプレキャスト鉄筋コンクリート製上部工を
予め工場や陸上ヤード等で製作するため、従来のように
海洋上等の現位置における作業時間が極めて短くて済
む。 (3)上部工係止部材3は鋼管杭9に作用する押し込み
力を鞘管を介して上部工に確実に伝達する役割も果たす
ため構造安定性が向上する。 (4)補強部材2に中空部材を使用すると上部工が軽く
なり、地震時に上部工に作用する貫性力が小さくなるた
め、鋼管杭9の断面積の軽減や本数の低減が可能となり
経済的な杭式基礎構造物の構築が可能となる。According to the present invention, the following effects can be obtained. (1) Since the pile head is firmly connected by the frame structure, it is unlikely to be affected by waves during the construction of the superstructure. (2) Since a divided frame structure or a frame structure or a frame structure with an upper rebar and a superstructure made of precast reinforced concrete incorporating the frame structure are manufactured in advance in a factory or a land yard, it is necessary to use a conventional marine method. Work time at the current position can be extremely short. (3) Since the superstructure locking member 3 also plays a role of reliably transmitting the pushing force acting on the steel pipe pile 9 to the superstructure via the sheath tube, the structural stability is improved. (4) When a hollow member is used as the reinforcing member 2, the superstructure is lightened, and the penetrating force acting on the superstructure during an earthquake is reduced, so that the cross-sectional area and the number of the steel pipe piles 9 can be reduced and economical. It is possible to construct a simple pile type foundation structure.
【図1】(A)は本発明の杭式基礎構造物を多数設置し
て杭式桟橋を築造した状態を示す概略平面図であり、
(B)はその平面図である。FIG. 1A is a schematic plan view showing a state in which a pile type pier is built by installing a number of pile type foundation structures of the present invention,
(B) is a plan view thereof.
【図2】図1の拡大した側面図である。FIG. 2 is an enlarged side view of FIG. 1;
【図3】(A)は本発明において使用される一実施形態
のプレキャストコンクリート上部工と杭とを結合した状
態を示す平面図であり、(B)は(A)のI−I線断面
図であり、(C)は(A)のII−II線断面図であ
る。FIG. 3A is a plan view showing a state in which a precast concrete superstructure and a pile of one embodiment used in the present invention are connected, and FIG. 3B is a cross-sectional view taken along line II of FIG. (C) is a sectional view taken along line II-II of (A).
【図4】(A)は図3(A)におけるIII−III線
断面図であり、(B)は図3(A)におけるIV−IV
線断面図である。4A is a sectional view taken along line III-III in FIG. 3A, and FIG. 4B is a sectional view taken along IV-IV in FIG.
It is a line sectional view.
【図5】(A)は図3(A)における右側面図であり、
(B)は図3(A)における背面図であり、(C)は図
3(A)における正面図である。FIG. 5 (A) is a right side view in FIG. 3 (A),
FIG. 3B is a rear view in FIG. 3A, and FIG. 3C is a front view in FIG. 3A.
【図6】上部工鉄筋を省略した状態のプレキャストコン
クリート上部工と鋼管杭との結合部を示す縦断正面図で
ある。FIG. 6 is a longitudinal sectional front view showing a joint portion between a precast concrete superstructure and a steel pipe pile in a state in which an upper rebar is omitted.
【図7】図6のV―V線断面図である。FIG. 7 is a sectional view taken along line VV of FIG. 6;
【図8】図6のVI−VI線断面図である。FIG. 8 is a sectional view taken along line VI-VI of FIG. 6;
【図9】(A)は本発明において使用される分割フレー
ム構造体を示す平面図であり、(B)は(A)の正面図
である。9A is a plan view showing a divided frame structure used in the present invention, and FIG. 9B is a front view of FIG. 9A.
【図10】図9(A)の側面図である。FIG. 10 is a side view of FIG. 9 (A).
【図11】図9(A)の一部縦断側面図である。FIG. 11 is a partial longitudinal side view of FIG. 9 (A).
【図12】分割フレーム構造体相互を連結用補強部材を
溶接により連結して井桁状のフレーム構造体を構成した
状態を示す平面図である。FIG. 12 is a plan view showing a state in which the divided frame structures are connected to each other by welding a connecting reinforcing member to form a double-girder frame structure.
【図13】上部工鉄筋を配置した状態を示す一部横断平
面図である。FIG. 13 is a partial cross-sectional plan view showing a state where an upper rebar is arranged.
【図14】(A)は図13のVII−VII線断面図で
あり、(B)は図13のVIII−VIII線断面図で
あり、(C)は図13のIX−IX線断面図であり、
(D)は図13のX−X線断面図である。14A is a sectional view taken along line VII-VII of FIG. 13, FIG. 14B is a sectional view taken along line VIII-VIII of FIG. 13, and FIG. 14C is a sectional view taken along line IX-IX of FIG. Yes,
FIG. 14D is a sectional view taken along line XX of FIG. 13.
【図15】(A)は図13のXI−XI線断面図であ
り、(B)は図13のXII−XII線断面図であり、
(C)は図13のXIII−XIII線断面図であり、
(D)は図13のXIV−XIV線断面図である。15A is a sectional view taken along the line XI-XI in FIG. 13, FIG. 15B is a sectional view taken along the line XII-XII in FIG.
(C) is a sectional view taken along line XIII-XIII in FIG. 13,
(D) is a sectional view taken along line XIV-XIV in FIG. 13.
【図16】(A)は底型枠の正面図であり、(B)はそ
の平面図である。FIG. 16A is a front view of a bottom formwork, and FIG. 16B is a plan view thereof.
【図17】隣り合う鋼管杭を底型枠に取り付けた杭間隔
保持部材により連結した状態を示す平面図である。FIG. 17 is a plan view showing a state where adjacent steel pipe piles are connected by a pile spacing member attached to a bottom formwork.
【図18】図17の一部を拡大して示す一部縦断正面図
である。18 is a partially longitudinal sectional front view showing a part of FIG. 17 in an enlarged manner.
【図19】鞘管にスペーサーを取り付けた状態および鋼
管杭との関係を示す一部縦断正面図である。FIG. 19 is a partially longitudinal front view showing a state in which a spacer is attached to a sheath pipe and a relationship with a steel pipe pile.
【図20】鞘管にシール材を取り付けた状態の鞘管の下
部を示す縦断正面図である。FIG. 20 is a longitudinal sectional front view showing a lower portion of the sheath tube in a state where a sealing material is attached to the sheath tube.
【図21】鞘管内に鋼管杭を挿入位置し、鞘管と鋼管杭
との間にモルタル等の経時硬化性充填材を充填した状態
を示す縦断正面図である。FIG. 21 is a vertical sectional front view showing a state where a steel pipe pile is inserted into a sheath pipe and a time-curable filler such as mortar is filled between the sheath pipe and the steel pipe pile.
【図22】底型枠と鞘管との間にシール用緩衝材を配設
した状態を示す縦断正面図である。FIG. 22 is a longitudinal sectional front view showing a state in which a cushioning material for sealing is provided between a bottom mold and a sheath tube.
【図23】線状突起付き帯状鋼板をコイル状に巻き取っ
た状態を示す斜視図である。FIG. 23 is a perspective view showing a state in which a strip-shaped steel sheet with linear projections is wound into a coil shape.
【図24】外面突起付き鋼管の一形態を示す概略斜視図
である。FIG. 24 is a schematic perspective view showing one embodiment of a steel pipe with external projections.
【図25】内面突起付き鋼管の一形態を示す斜視図であ
る。FIG. 25 is a perspective view showing one embodiment of a steel pipe having an inner surface projection.
【図26】(A)は側方に開口する開断面部材(H形
鋼)を並設して、中空部材からなる補強部材を構成する
形態を示す斜視図であり、(B)は開断面部材(H形
鋼)におけるフランジに突起を設けた形態の一形態を示
す正面図であり、(C)はその側面図である。FIG. 26A is a perspective view showing a configuration in which an open-section member (H-section steel) that opens laterally is arranged side by side to form a reinforcing member composed of a hollow member, and FIG. 26B is an open section. It is a front view which shows one form which provided the protrusion in the flange in a member (H-shaped steel), and (C) is the side view.
【図27】上部工用鉄筋付きフレーム構造体の周囲に支
保工および型枠を配設した状態を示す概略平面図であ
る。FIG. 27 is a schematic plan view showing a state in which a shoring and a formwork are arranged around a frame structure with a reinforcing steel bar for superstructure.
【図28】(a)は図27のXV−XV線断面図であ
り、(b)は(a)の一部を拡大して示す断面図であ
る。28A is a cross-sectional view taken along line XV-XV in FIG. 27, and FIG. 28B is a cross-sectional view showing a part of FIG.
【図29】従来の杭式基礎構造物を示す一部縦断正面図
である。FIG. 29 is a partially longitudinal front view showing a conventional pile type substructure.
1 鞘管 2 補強部材 2a 端部張り出し補強部材 2b 端部張り出し補強部材 2c 継手用短尺鋼管 2d 端部側上部主筋 2e 端部側下部主筋 2f 端部側上部周縁鉄筋 2g 端部側下部周縁鉄筋 3 上部工係止部材 4 吊り金具 5 吊り孔 5a 縦鋼板 5c 係止部材 6 鉄筋定着用鋼板 6a 上部鉄筋定着部 6b 下部鉄筋定着部 6c 上部主筋 6d 下部主筋 7 鉄筋 8 コンクリート 9 鋼管杭 10 経時硬化性材料 10a モルタル 11 底型枠 11a 半環状上部支承板 11b 半円筒状筒体 11c 連結用フランジ 11d 底型枠ユニット 11e 連結用ボルト 12 シール用緩衝材 13 シール材 13a 薄肉先端部 14 シール材把持用突設部材 14a シール材把持用突設部材 14b シール材把持用突設部材 15 シール材係止ボルト挿通用孔 16 シール材係止ボルト 17 杭間隔保持部材 18 分割フレーム構造体 19 フレーム構造体 20 水底地盤 20a 岩盤 21 突起 21a 線状突起 22 突起 23 揺動防止治具 23a ボルト保持部材 23b 横雌ねじ孔 23c 揺動防止用ボルト 24 型枠 25 肋筋 26 主鉄筋梁 27 張り出し鉄筋梁 28 周縁鉄筋梁 29 突起 30 外面突起付き鋼管 31 内面突起付き鋼管 32 スペーサー 33 中空部材 34 外面突起付き鋼管等の中空部材 35 H型鋼等の開断面部材を並設して中空空間を形成
せしめた中空部材 36 フランジの外面に突起を有するH形鋼等の開断面
部材を並設して中空空間を形成せしめた中空部材 37 線状突起付きコイル 38 開断面部材 39 突起 40 杭式基礎構造物 40a 従来の杭式基礎構造物 41 フランジ 42 重防食被覆 43 鉄筋コンクリート製の梁 50 プレキャストコンクリート製上部工 51 桟橋 55 底部型枠保持部材 56 半円状上部 57 底部型枠保持部材 58 型枠 59 係止部材 60 型枠 61 型枠間隔保持具 62 底部型枠支持部材 A 上部工鉄筋DESCRIPTION OF SYMBOLS 1 Sheath tube 2 Reinforcement member 2a End overhang reinforcement member 2b End overhang reinforcement member 2c Short steel pipe for joint 2d End side upper main reinforcement 2e End lower lower reinforcement 2f End side upper peripheral reinforcement 2g End side lower peripheral reinforcement 3 Superstructure retaining member 4 Suspension metal fitting 5 Hanging hole 5a Vertical steel plate 5c Locking member 6 Reinforcing steel plate 6a Upper reinforcing bar fixing portion 6b Lower reinforcing bar fixing portion 6c Upper main reinforcing bar 6d Lower main reinforcing bar 7 Reinforcing steel 8 Concrete 9 Steel pipe pile 10 Temporary hardening Material 10a Mortar 11 Bottom form 11a Semi-annular upper support plate 11b Semi-cylindrical cylindrical body 11c Connection flange 11d Bottom form unit 11e Connection bolt 12 Seal buffer 13 Seal 13a Thin tip 14 Seal protrusion Installation member 14a Projection member for gripping sealing material 14b Projection member for gripping sealing material 15 For insertion of sealing material locking bolt Hole 16 Seal material locking bolt 17 Pile spacing holding member 18 Split frame structure 19 Frame structure 20 Underground ground 20a Rock 21 Projection 21a Linear projection 22 Projection 23 Swing prevention jig 23a Bolt holding member 23b Horizontal female screw hole 23c Swing Movement prevention bolt 24 Formwork 25 Rib 26 Main reinforced beam 27 Overhanging reinforced beam 28 Peripheral reinforced beam 29 Projection 30 Steel tube with external projection 31 Steel tube with internal projection 32 Spacer 33 Hollow member 34 Hollow member such as steel tube with external projection 35 H A hollow member having a hollow space formed by juxtaposing open section members such as a mold steel, etc. 36 A hollow member having an open cross section member such as H-section steel having a protrusion on the outer surface of a flange juxtaposed to form a hollow space 37 Coil with projection 38 Open-section member 39 Projection 40 Pile-type foundation 40a Conventional pile-type foundation 41 F Lange 42 Heavy Corrosion Protection 43 Reinforced Concrete Beam 50 Precast Concrete Superstructure 51 Pier 55 Bottom Form Holder 56 Semicircular Top 57 Bottom Form Holder 58 Form 59 Locking Member 60 Form 61 Space Hold Tool 62 Bottom formwork support member A Upper rebar
Claims (19)
れてフレーム構造体が構成され、前記複数の鞘管の内部
には鋼管杭が挿通され、前記鞘管と前記鋼管杭の間には
モルタル等の経時硬化性材料が充填されていることを特
徴とする杭式基礎構造物。A frame structure is formed by connecting a plurality of sheath tubes with a reinforcing member, a steel pipe pile is inserted into the plurality of sheath tubes, and a gap between the sheath tube and the steel pipe pile is provided. A pile-type substructure characterized by being filled with a time-curable material such as mortar.
管、あるいはH形鋼またはフランジの外面に突起を有す
るH形鋼等の開断面部材を並設して中空空間が形成され
た中空部を有する部材等の中空部材であることを特徴と
する請求項1記載の杭式基礎構造物。2. A hollow member in which a hollow space is formed by juxtaposing an open-section member such as a steel pipe or a steel pipe with an external projection, or an H-section steel or an H-section steel having a projection on the outer surface of a flange is used as a reinforcing member. The pile type substructure according to claim 1, wherein the substructure is a hollow member such as a member having the same.
たは吊り金具を一体に設けた上部工係止部材が一体に設
けられていることを特徴とする請求項1または2のいず
れかに記載の杭式基礎構造物。3. An upper work locking member integrally provided with an upper work locking member or a suspension metal fitting at an upper end portion of the sheath tube. The pile type foundation structure described in Crab.
周面の所定範囲に突起が一体に設けられていることを特
徴とする請求項1,2または3のいずれかに記載の杭式
基礎構造物。4. The pile according to claim 1, wherein a projection is integrally provided in a predetermined range on an outer peripheral surface of the steel pipe pile in a range corresponding to the sheath tube 1. Formula foundation structure.
体的に設けられていることを特徴とする請求項1〜3ま
たは4のいずれかに記載の杭式基礎構造物。5. The pile-type substructure according to claim 1, wherein a projection is integrally provided in a predetermined range on an inner surface of the sheath tube 1.
管杭の所定範囲が外面突起付き鋼管であることを特徴と
する請求項1〜3または5のいずれかに記載の杭式基礎
構造物。6. The pile-type substructure according to claim 1, wherein at least a predetermined range of the steel pipe pile in a range corresponding to the sheath pipe is a steel pipe with an external projection.
を特徴とする請求項1〜4または6のいずれかに記載の
杭式基礎構造物。7. The pile-type substructure according to claim 1, wherein the sheath tube is a steel tube with an inner surface projection.
ー32が設けられていることを特徴とする請求項1〜6
または7のいずれかに記載の杭式基礎構造物。8. A spacer (32) is provided at a predetermined position on the inner surface of the sheath tube (1).
Or a pile-type substructure according to any of 7.
けられていることを特徴とする請求項1〜7または8の
いずれかに記載の杭式基礎構造物。9. The pile-type substructure according to claim 1, wherein a swing preventing jig is provided at a predetermined position of the sheath tube.
ール材把持用突設部材が一体に設けられ、前記シール材
把持用突設部材の間にシール材の基部側が配置されて、
これらのシール係止ボルト挿通用孔にわたって挿通され
たボルトにより、シール材がシール材把持用突設部材に
固定され、シール材が鋼管杭外表面に密接していること
を特徴とする請求項1〜8または9のいずれかに記載の
杭式基礎構造物。10. A sealing member-holding protruding member is integrally provided at a lower inner surface of the sheath tube with a space therebetween, and a base side of the sealing material is disposed between the sealing member-holding protruding members.
2. The sealing material is fixed to the sealing material holding protruding member by the bolt inserted through the seal locking bolt insertion hole, and the sealing material is in close contact with the outer surface of the steel pipe pile. The pile-type foundation structure according to any one of to 8 to 9, wherein
たはシール用緩衝材を介して当接されていることを特徴
とする請求項1〜9または10のいずれかに記載の杭式
基礎構造物。11. The pile according to claim 1, wherein a bottom form is abutted on the lower end of the sheath tube 1 directly or via a cushioning material for sealing. Formula foundation structure.
り連結されていることを特徴とする請求項1〜10また
は11のいずれかに記載の杭式基礎構造物。12. The pile type substructure according to claim 1, wherein the bottom forms are connected to each other by a pile spacing member.
板が固着され、前記鉄筋定着用鋼板には、鉄筋が固着さ
れていることを特徴とする請求項1〜11または12の
いずれかに記載の杭式基礎構造物。13. The steel plate for fixing a reinforcing bar is fixed at a predetermined position of the sheath tube, and a reinforcing bar is fixed to the steel plate for fixing a reinforcing bar. The pile type substructure described in 1.
が固着され、前記鉄筋定着用鋼板には鉄筋が固着され、
前記鞘管,鉄筋定着用鋼板および鉄筋を囲むように型枠
が配置されていることを特徴とする請求項1〜12また
は13のいずれかに記載の杭式基礎構造物。14. A steel plate for fixing a reinforcing bar is fixed to a predetermined position of the sheath tube, and a reinforcing bar is fixed to the steel plate for fixing a reinforcing bar.
The pile type substructure according to any one of claims 1 to 12, wherein a formwork is arranged so as to surround the sheath tube, the steel plate for fixing the reinforcing bar, and the reinforcing bar.
板が固着され、前記鉄筋定着用鋼板には鉄筋が固着さ
れ、前記鞘管,鉄筋定着用鋼板,鉄筋および補強部材が
コンクリートに埋設されていることを特徴とする請求項
1〜13または14のいずれかに記載の杭式基礎構造
物。15. A steel plate for fixing a reinforcing bar is fixed to a predetermined position of the sheath tube, a reinforcing bar is fixed to the steel plate for fixing a reinforcing bar, and the sheath tube, the steel plate for fixing a reinforcing bar, a reinforcing bar, and a reinforcing member are embedded in concrete. The pile type substructure according to any one of claims 1 to 13, wherein the pile type substructure is provided.
鋼管等の中空部を備えた補強部材により連結されて予め
製作された上部工用フレーム構造体を搬送して、間隔を
おいて地盤に打設された複数の鋼管杭の頭部の所定位置
に配置すると共に前記各鋼管杭に鞘管を嵌合し、次いで
各鞘管と鋼管杭との間にモルタル等の経時硬化性材料を
充填・硬化し、前記補強部材を支保材の一部として利用
しながら上部工鉄筋の配筋および型枠の配設作業を行
い、次いで前記鞘管および上部工鉄筋および補強部材を
埋め込むようにコンクリートを打設し、養生・硬化させ
ることを特徴とする杭式基礎構造物の施工方法。16. A plurality of sheathed tubes arranged at intervals are connected by a reinforcing member having a hollow portion such as a steel tube, and convey a prefabricated frame structure for superstructure, and are spaced apart from each other. A plurality of steel pipe piles placed on the ground are arranged at predetermined positions on the heads, and a sheath pipe is fitted to each of the steel pipe piles. Then, a time-curable material such as mortar is placed between each sheath pipe and the steel pipe pile. Filling and hardening, performing the work of arranging the reinforcing steel bar and arranging the formwork while using the reinforcing member as a part of the support material, and then embedding the sheath tube and the upper reinforcing steel bar and the reinforcing member. A method of constructing a pile-type foundation structure characterized by placing concrete, curing and hardening.
鋼管等の中空部を備えた補強部材により連結されて上部
工用フレーム構造体を構成すると共に、前記上部工用フ
レーム構造体に上部工鉄筋を配筋して構成した上部工鉄
筋付き上部工用フレーム構造体を予め製作し、その上部
工鉄筋付き上部工用フレーム構造体を搬送して、間隔を
おいて地盤に打設された複数の鋼管杭の頭部の所定位置
に配置すると共に前記各鋼管杭に鞘管を嵌合し、次いで
各鞘管と鋼管杭との間にモルタル等の経時硬化性材料を
充填・硬化し、前記補強部材を支保材の一部として利用
しながら型枠の配設作業を行い、次いで後前記上部工鉄
筋および補強部材を埋め込むようにコンクリートを打設
し、養生・硬化させることを特徴とする杭式基礎構造物
の施工方法。17. A plurality of sheathed tubes arranged at intervals are connected by a reinforcing member having a hollow portion such as a steel tube to form a frame structure for superstructure, and the frame structure for superstructure is connected to the frame structure for superstructure. An upper frame structure with upper rebar is constructed in advance by arranging upper rebars, and the upper frame structure with upper rebar is transported and placed on the ground at intervals. A plurality of steel pipe piles are placed at predetermined positions on the heads, and a sheath pipe is fitted to each of the steel pipe piles, and then a time-curable material such as mortar is filled and cured between each of the sheath pipes and the steel pipe piles. Performing the work of arranging the formwork while using the reinforcing member as a part of the supporting material, and then placing concrete so as to embed the upper rebar and the reinforcing member, curing and curing. Construction method of pile type foundation structure.
鋼管等の中空部を備えた補強部材により連結されて上部
工用フレーム構造体を構成すると共に、前記上部工用フ
レーム構造体に上部工鉄筋および型枠ならびに支保工を
一体に配設して構成した型枠支保工付き上部工用フレー
ム構造体を予め製作し、その型枠支保工付き上部工用フ
レーム構造体を搬送して、間隔をおいて地盤に打設され
た複数の鋼管杭の頭部の所定位置に配置すると共に前記
各鋼管杭に鞘管を嵌合し、次いで各鞘管と鋼管杭との間
にモルタル等の経時硬化性材料を充填・硬化し、その後
前記上部工鉄筋および補強部材を埋め込むようにコンク
リートを打設し、養生・硬化させることを特徴とする杭
式基礎構造物の施工方法。18. A plurality of sheathed tubes arranged at intervals are connected by a reinforcing member having a hollow portion such as a steel tube to form a frame structure for superstructure, and the frame structure for superstructure is connected to the frame structure for superstructure. An upper frame structure with a form support is constructed in advance by integrally arranging a reinforcing steel bar, a formwork and a support, and the frame structure for the upper work with the form support is transported. A plurality of steel pipe piles placed on the ground at intervals are arranged at predetermined positions on the heads, and a sheath pipe is fitted to each of the steel pipe piles. Then, a mortar or the like is provided between each sheath pipe and the steel pipe piles. A method of constructing a pile-type substructure, characterized by filling and curing the time-hardenable material of the above, and then placing concrete so as to embed the upper rebar and the reinforcing member, and curing and curing.
鋼管等の中空部を備えた補強部材により連結して上部工
用フレーム構造体を構成すると共に、前記上部工用フレ
ーム構造体に上部工鉄筋を一体に配設し、その後前記上
部工鉄筋および補強部材2を埋め込むようにコンクリー
トを打設し、養生・硬化させて構成した上部工用フレー
ム構造体付きプレキャスト鉄筋コンクリート製上部工を
予め製作し、その上部工用フレーム構造体付きプレキャ
スト鉄筋コンクリート製上部工を搬送して、間隔をおい
て地盤に打設された複数の鋼管杭の頭部の所定位置に配
置すると共に前記各鋼管杭に鞘管を嵌合し、次いで各鞘
管と鋼管杭との間にモルタル等の経時硬化性材料を充填
・硬化することを特徴とする杭式基礎構造物の施工方
法。19. A superstructure frame structure is formed by connecting a plurality of sheathed tubes arranged at intervals by a reinforcing member having a hollow portion such as a steel tube to form a superstructure frame structure. An upper rebar is integrally disposed, and then concrete is poured into the upper rebar and the reinforcing member 2 so as to be embedded therein, and then a precast reinforced concrete superstructure with a frame structure for an upper is constructed by curing and curing. Manufacture and transport the precast reinforced concrete superstructure with its superstructure frame structure, place it at a predetermined position on the head of a plurality of steel pipe piles that have been cast into the ground at intervals, and apply to each of the steel pipe piles A method for constructing a pile-type substructure, comprising fitting a sheath tube, and then filling and hardening a time-curable material such as mortar between each sheath tube and a steel tube pile.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000101750A JP3848518B2 (en) | 2000-04-04 | 2000-04-04 | Pile-type foundation structure and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000101750A JP3848518B2 (en) | 2000-04-04 | 2000-04-04 | Pile-type foundation structure and its construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2001288725A true JP2001288725A (en) | 2001-10-19 |
JP3848518B2 JP3848518B2 (en) | 2006-11-22 |
Family
ID=18615739
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000101750A Expired - Lifetime JP3848518B2 (en) | 2000-04-04 | 2000-04-04 | Pile-type foundation structure and its construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3848518B2 (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005105720A (en) * | 2003-09-30 | 2005-04-21 | Chugoku Electric Power Co Inc:The | Suspended curtain wall sealing plate assembly |
CN100410448C (en) * | 2006-05-17 | 2008-08-13 | 大连理工大学土木建筑设计研究院有限公司 | Integrated casing board type long piled wharf |
JP2012144951A (en) * | 2011-01-14 | 2012-08-02 | Jfe Steel Corp | Steel pipe pile type landing pier |
JP2015155645A (en) * | 2015-04-23 | 2015-08-27 | Jfeスチール株式会社 | Steel pipe pile type pier and steel pipe pile |
JP2017095955A (en) * | 2015-11-24 | 2017-06-01 | 新日鐵住金株式会社 | Pile foundation structure and construction method thereof |
CN108867547A (en) * | 2018-08-19 | 2018-11-23 | 天津大学 | The construction method of semi-circular caisson and pile foundation combined type breakwater |
JP2019100070A (en) * | 2017-12-01 | 2019-06-24 | 五洋建設株式会社 | Foundation structure of offshore wind power generation facility, and construction method of the same |
JP2021059962A (en) * | 2019-10-09 | 2021-04-15 | 東亜建設工業株式会社 | Construction method of superstructure on water and structure of superstructure |
JP2022532121A (en) * | 2019-05-07 | 2022-07-13 | カーリー オーシャン システムズ リミテッド | Mechanical connection methods and equipment between marine structures and submarine piles |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105297698B (en) * | 2015-09-28 | 2017-04-19 | 中海油能源发展股份有限公司 | Pile foundation type reinforced concrete structure offshore oil platform |
-
2000
- 2000-04-04 JP JP2000101750A patent/JP3848518B2/en not_active Expired - Lifetime
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005105720A (en) * | 2003-09-30 | 2005-04-21 | Chugoku Electric Power Co Inc:The | Suspended curtain wall sealing plate assembly |
CN100410448C (en) * | 2006-05-17 | 2008-08-13 | 大连理工大学土木建筑设计研究院有限公司 | Integrated casing board type long piled wharf |
JP2012144951A (en) * | 2011-01-14 | 2012-08-02 | Jfe Steel Corp | Steel pipe pile type landing pier |
JP2015155645A (en) * | 2015-04-23 | 2015-08-27 | Jfeスチール株式会社 | Steel pipe pile type pier and steel pipe pile |
JP2017095955A (en) * | 2015-11-24 | 2017-06-01 | 新日鐵住金株式会社 | Pile foundation structure and construction method thereof |
JP2019100070A (en) * | 2017-12-01 | 2019-06-24 | 五洋建設株式会社 | Foundation structure of offshore wind power generation facility, and construction method of the same |
CN108867547A (en) * | 2018-08-19 | 2018-11-23 | 天津大学 | The construction method of semi-circular caisson and pile foundation combined type breakwater |
JP2022532121A (en) * | 2019-05-07 | 2022-07-13 | カーリー オーシャン システムズ リミテッド | Mechanical connection methods and equipment between marine structures and submarine piles |
JP7539068B2 (en) | 2019-05-07 | 2024-08-23 | カーリー オーシャン システムズ リミテッド | Method and device for mechanical connection between an offshore structure and a subsea pile |
JP2021059962A (en) * | 2019-10-09 | 2021-04-15 | 東亜建設工業株式会社 | Construction method of superstructure on water and structure of superstructure |
Also Published As
Publication number | Publication date |
---|---|
JP3848518B2 (en) | 2006-11-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4793634B2 (en) | Temporary deadline construction method | |
JP6427045B2 (en) | Reinforcement structure and reinforcement method of existing concrete structure | |
JP2023164649A (en) | Jacket type structure and construction method thereof | |
JP2001288725A (en) | Pile-type foundation structure and method for constructing the same | |
KR101167511B1 (en) | Underpass using precast concrete pile and method for constructing the same | |
JP2024149814A (en) | Water-impermeable structure of seawall at marine disposal site | |
JP4440497B2 (en) | Construction method of underground continuous wall and construction method of underground structure | |
JP3245126B2 (en) | Casting method of steel pipe sheet pile | |
JP6971874B2 (en) | Connection structure between steel structure and precast concrete member, structural wall having the connection structure, and connection method between steel structure and precast concrete member | |
JP5280150B2 (en) | Yamadome retaining wall and method of forming Yamadome retaining wall | |
JP4798203B2 (en) | Reinforcement structure and reinforcement method for existing foundation | |
JPH1077644A (en) | Earthquake resisting pile foundation construction method | |
JP2548634B2 (en) | Underwater structure using underwater ground driving member | |
JPH09296427A (en) | Structure in water area and construction method thereof | |
JP7519945B2 (en) | Reinforcement method for concrete structures and reinforced structures | |
KR102656370B1 (en) | Underground structure capable of forming a supporting point of a molded beam and its construction method | |
JPH1082055A (en) | Method of earthquake-resisting pile foundation construction | |
JP3849234B2 (en) | Reinforced concrete underground outer wall construction method | |
JP7308491B2 (en) | Double sheet pile type water structure and its construction method | |
JP2001214412A (en) | Substructure of bridge | |
JP3030622B2 (en) | How to build a tunnel | |
JP2947706B2 (en) | Bridge pier construction method | |
JPH0477764B2 (en) | ||
KR101650312B1 (en) | Concrete retaining wall and method for manufacturing the same | |
JP2005180018A (en) | Method of reinforcing pier |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040901 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060613 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060728 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20060822 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20060825 |
|
R151 | Written notification of patent or utility model registration |
Ref document number: 3848518 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R151 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100901 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100901 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110901 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120901 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120901 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130901 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130901 Year of fee payment: 7 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130901 Year of fee payment: 7 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130901 Year of fee payment: 7 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
EXPY | Cancellation because of completion of term |