JP2000154538A - Plumb bob type device for driving steel pipe in inner moat and plumb bob type construction method of driving steel pipe in inner moat - Google Patents
Plumb bob type device for driving steel pipe in inner moat and plumb bob type construction method of driving steel pipe in inner moatInfo
- Publication number
- JP2000154538A JP2000154538A JP10330824A JP33082498A JP2000154538A JP 2000154538 A JP2000154538 A JP 2000154538A JP 10330824 A JP10330824 A JP 10330824A JP 33082498 A JP33082498 A JP 33082498A JP 2000154538 A JP2000154538 A JP 2000154538A
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- pile
- weight
- digging
- frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Piles And Underground Anchors (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、砂層、シルト、粘
土層などの地層と転石層、巨礫層、岩盤層などの地層と
からなる複合地盤を対象として、打込みと中掘りとを併
用しながら前記複合地盤に対して鋼管杭を連続的に貫入
させるようにした重錘式鋼管中掘打込み装置およびこれ
を用いた重錘式鋼管中掘打込み工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a composite ground comprising a formation such as a sand layer, a silt, and a clay layer and a formation layer such as a boulder layer, a boulder layer and a bedrock layer. The present invention relates to a weight-type steel-pipe digging apparatus for continuously penetrating steel pipe piles into the composite ground, and a weight-type steel-pipe digging method using the same.
【0002】[0002]
【従来の技術】従来より、鋼管杭を岩盤または礫層など
の支持層まで貫入させるためには、まず上層側のシル
ト、粘性土などの沖積層に対してバイブロハンマーやデ
ィーゼルパイルハンマーなどによって杭頭に振動や衝撃
を与えながら岩盤または礫層からなる支持地盤の直前ま
で貫入し、その後ロータリー式削孔機によって所定の根
入れ深さまで掘削した後、再びバイブロハンマーまたは
ディーゼルパイルハンマーによって鋼管杭を貫入させる
手順によって鋼管杭の打設を行っていた。2. Description of the Related Art Conventionally, in order to penetrate a steel pipe pile to a supporting layer such as a bedrock or a gravel layer, first, a pile of piles such as a silt and a cohesive soil on the upper layer side is piled with a vibro hammer or a diesel pile hammer. While penetrating to the head just before the supporting ground consisting of rock or gravel layer while applying vibration or impact to the head, and then excavating to the specified depth of penetration with a rotary drilling machine, the steel pipe pile is again pierced with a vibro hammer or diesel pile hammer. The steel pipe pile was driven according to the procedure for penetration.
【0003】しかし、この方法では杭貫入工程が実質的
に3工程になるとともに、各工程毎に異なる施工機械を
必要とするため、施工機械の取替えに手間が掛かり作業
が効率化しない、施工設備が多岐に亘るため施工費が嵩
むとともに、工期も長期化するなどの問題があった。[0003] However, in this method, the pile intrusion step is substantially three steps, and different construction machines are required for each step. However, there is a problem that the construction cost is increased due to the wide variety, and the construction period is prolonged.
【0004】このような問題を一挙に解決するものとし
て提案されたのが重錘式鋼管中掘打込み工法である。こ
の工法に係るものとしては、たとえば特公昭60−39
809号公報、特公平2−15694号公報などを挙げ
ることができる。[0004] It has been proposed to solve this problem at once by using a weight-type steel pipe excavation method. Examples of this method include, for example, Japanese Patent Publication No. 60-39.
809 and JP-B-2-15694.
【0005】この工法の開発当初は、専ら陸上部におけ
る鋼管杭貫入を対象として施工が行われており、三点式
杭打ち機のリーダーに、中掘り用重錘、掘削ズリ排出用
ズリ排出管および鋼管杭打撃用油圧ハンマーを装備し、
中掘りと打込みとを併行して行いながら大口径鋼管杭を
岩盤に直接貫入させるようにしていた。[0005] At the beginning of the development of this method, construction was carried out exclusively for the penetration of steel pipe piles on the land. The leader of a three-point pile driver was provided with a weight for medium digging, a chip discharge pipe for excavating waste, and a steel pipe. Equipped with hydraulic hammer for pile hitting,
The large-diameter steel pipe pile was made to penetrate directly into the bedrock while performing the inside digging and driving in parallel.
【0006】その後、海上施工に対する要求のために開
発されたのが重錘式鋼管中掘併用吊打ち工法である。具
体的には、大型基礎構造物を海峡部に築造するためのジ
ャケット式桟台を周囲に構築するために採用されたもの
で、図13に示されるように、三点式杭打ち機のリーダ
ーに代わるフレーム枠体状の架構50(以下、フライン
グリーダーという。)内に中空型油圧ハンマー51を組
込むとともに、ズリ排出管52を中央に縦方向に長手通
しで固定配置し、このズリ排出管52の下端部に対して
このズリ排出管52を貫通させた状態で中掘り用重錘5
3を設け、この中掘り用重錘53を引き上げ/落下する
ためにワイヤー54によって吊持した装置である。After that, a method of hanging with a heavy-duty steel pipe was also developed to meet the demand for offshore construction. More specifically, as shown in FIG. 13, it is adopted to build a jacket-type pier for building a large-scale foundation structure in the strait, and replaces a leader of a three-point pile driver. A hollow hydraulic hammer 51 is incorporated into a frame 50 (hereinafter, referred to as a flying leader) in the form of a frame, and a slip discharge pipe 52 is fixedly disposed at the center of the frame 50 in a longitudinal direction in a longitudinal direction. In the state where the slip discharge pipe 52 penetrates the portion,
3 is a device which is suspended by a wire 54 in order to pull up / drop the weight 53 for digging.
【0007】鋼管杭Pの打込みに当たっては、前記重錘
式中掘吊打ち装置49を起重機船56によって吊り上げ
るとともに、前記中掘り用重錘53の引き上げを行うた
め起重機船56上に艤装された重錘用油圧ウインチに対
して前記ワイヤー54を巻き掛けした後(図示せず)、
油圧ハンマー51の下端側に連結された雇い杭(ヤット
コ)55を地盤上に直立支持された鋼管杭Pの頭部に貫
入し、かつ前記起重機船56によって重錘式中掘吊打ち
装置49を吊り状態で保持したまま、鋼管杭Pの内部で
前記中掘り用重錘53を引き上げては自由落下を繰り返
すことによって鋼管杭先端の岩盤を打撃破砕するととも
に、油圧ハンマー51によって鋼管杭頭部に打撃を与え
ることにより最終深さまで鋼管杭Pを貫入させるように
する。なお、中掘り用重錘53によって破砕されたズリ
は、ズリ排出管52を通じて系外に排出される。When driving the steel pipe pile P, the weight-type digging and hanging device 49 is lifted by the hoisting ship 56 and the weight mounted on the hoisting ship 56 for raising the digging weight 53. After winding the wire 54 around the hydraulic winch for weight (not shown),
A hiring pile (yatco) 55 connected to the lower end side of the hydraulic hammer 51 penetrates into the head of the steel pipe pile P supported upright on the ground, and the weight-lifting boring device 49 is driven by the hoisting ship 56. While holding in a suspended state, the weight of the middle digging weight 53 is pulled up inside the steel pipe pile P, and the rock rock at the tip of the steel pipe pile is hit and crushed by repeating free fall. The steel pipe pile P is made to penetrate to the final depth by giving an impact. Note that the debris crushed by the digging weight 53 is discharged out of the system through the debris discharge pipe 52.
【0008】[0008]
【発明が解決しようとする課題】しかしながら、前記重
錘式鋼管中掘併用吊打ち工法の場合には、鋼管杭Pの打
込み開始から終了までの間、起重機船56によってフラ
イングリーダー50を吊り続けていなければならず、1
台の重錘式中掘吊打ち装置49に対して1台の起重機船
56を張り付けて配置しなければならないなどの問題が
あった。すなわち、一般的に杭打ち作業は、作業の効率
化を図るため、複数台の重錘式中掘吊打ち装置49によ
って併行的に行われるため、重錘式中掘吊打ち装置49
の数だけ大型の起重機船56を用意しなければならず、
起重機船56の損料が嵩み、施工費が膨大となるなどの
問題が生じていた。However, in the case of the above-mentioned suspension method using the weight-type steel pipe digging, the flying leader 50 is continuously suspended by the hoist ship 56 from the start to the end of the driving of the steel pipe pile P. Must be 1
There is a problem that one hoist ship 56 has to be attached to and disposed on one of the weight-type underground suspension devices 49. That is, in general, a pile driving operation is performed in parallel by a plurality of weight type digging and hanging devices 49 in order to improve the efficiency of the operation.
The number of large hoist ships 56 must be prepared,
There have been problems such as an increase in the penalty fee of the hoist ship 56 and an enormous construction cost.
【0009】また、中掘り用重錘53の引き上げ・落下
を行うためのワイヤ操作は、起重機船56に設置された
重錘用油圧ウインチによって行うようにしていたため、
ワイヤの延長が長くなり、中掘り用重錘53を吊り上げ
ている2本のワイヤ54,54を均等に同調させて操作
することが困難となり、片方のワイヤ54に過度の張力
が作用したり、ワイヤ54に捻れが発生するなどしてワ
イヤ寿命が非常に短くなってしまうなどの問題も生じて
いた。Further, since the wire operation for lifting and dropping the digging weight 53 is performed by the hydraulic winch for the weight installed on the hoist ship 56,
The extension of the wire becomes long, and it becomes difficult to operate the two wires 54, 54 that lift the weight for boring 53 evenly in synchronization, and excessive tension acts on one of the wires 54, There has also been a problem that the wire life is extremely shortened due to the twist of the wire 54 or the like.
【0010】そこで本発明の主たる課題は、起重機船の
拘束を最小限にし、1台の起重機船によって複数台の重
錘式中掘杭打ち装置による施工を可能として作業の効率
化並びに工費削減を図るようにするとともに、中掘り用
重錘操作用ワイヤの操作延長を短くすることによりワイ
ヤ張力の均一化を図り、従来頻繁に発生していたワイヤ
交換の手間を省力化することにある。Therefore, a main object of the present invention is to minimize the restraint of a hoist ship, and to make it possible to perform construction by a plurality of weight-type digging pile driving devices with one hoist ship, thereby improving work efficiency and reducing construction costs. Another object of the present invention is to shorten the operation extension of the wire for operating the weight for boring, to make the wire tension uniform, and to reduce the labor of wire replacement which has conventionally occurred frequently.
【0011】[0011]
【課題を解決するための手段】前記課題を解決し得る第
1の重錘式鋼管中掘打込み装置は、打込みされる鋼管杭
の頭部に対して直接的または他部材を介在させて間接的
に搭載され、鋼管杭に対して打撃を加えることによって
前記鋼管杭を地盤中に貫入させる杭用打撃装置と、この
杭用打撃装置からの衝撃を吸収可能な状態で杭用打撃装
置の周りに一体的に取り付けられたフレーム枠体状の架
構と、このフレーム枠体状の架構より垂下され、鋼管杭
の内部に挿入されるズリ排出管と、中央に軸貫通孔部を
有し前記ズリ排出管が貫通された状態で前記ズリ排出管
の下端部に配置された中掘り用重錘と、前記フレーム枠
体状の架構に対して一体的に設けられた機器設置架台
と、この機器設置架台上に配置されたパワーユニット、
ウインチ類、各種シーブ類等の少なくとも前記杭用打撃
装置および中掘り用重錘を稼働できる設備機器一式とか
ら構成されたことを特徴とするものである。A first weight-type steel pipe digging and driving apparatus capable of solving the above-mentioned problems is provided directly or indirectly by interposing another member on the head of a steel pipe pile to be driven. A pile hitting device that is mounted on the steel pipe pile to penetrate the ground by applying a hit to the steel pipe pile, and around the pile hitting device in a state where the impact from the pile hitting device can be absorbed. A frame-like frame integrally attached thereto, a shear discharge pipe that is suspended from the frame-like frame and inserted into the inside of the steel pipe pile; A digging weight disposed at a lower end of the shear discharge pipe in a state where the pipe is penetrated, an equipment installation base integrally provided with the frame-shaped frame, and an equipment installation base Power unit placed above,
It is characterized by comprising at least a set of equipment that can operate the hitting device for piles such as winches and various sheaves and a weight for digging.
【0012】また、第2の重錘式鋼管中掘打込み装置
は、打込みされる鋼管杭の頭部に対して直接的または他
部材を介在させて間接的に搭載され、鋼管杭に対して打
撃を加えることによって前記鋼管杭を地盤中に貫入させ
る杭用打撃装置と、この杭用打撃装置からの衝撃を吸収
可能な状態で杭用打撃装置の周りに一体的に取り付けら
れたフレーム枠体状の架構と、このフレーム枠体状の架
構より垂下され、鋼管杭の内部に挿入されると共に管長
手方向に伸縮自在に構成されたズリ排出管と、中央に軸
貫通孔部を有し前記ズリ排出管が貫通された状態で前記
ズリ排出管の下端部に配置された中掘り用重錘と、前記
フレーム枠体状の架構に対して一体的に設けられた機器
設置架台と、この機器設置架台上に配置されたパワーユ
ニット、ウインチ類、各種シーブ類等の少なくとも前記
杭用打撃装置および中掘り用重錘を稼働するとともに、
前記ズリ排出管の伸縮操作を行うための設備機器一式と
から構成されたことを特徴とするものである。前記伸縮
自在のズリ排出管は、たとえば内管および外管からなる
伸縮管路部を1または複数段に亘って備えており、伸縮
操作ワイヤの下端部を最下段伸縮管路部の下端部に連結
固定し、前記伸縮操作ワイヤの巻き上げ/繰り出し操作
によってズリ排出管長が制御される構造とすることがで
きる。The second weight-type steel pipe digging and driving apparatus is mounted directly or indirectly on the head of the steel pipe pile to be driven by interposing other members. A pile hitting device for allowing the steel pipe pile to penetrate into the ground by adding the same, and a frame frame integrally attached around the pile hitting device in a state capable of absorbing the impact from the pile hitting device. And a slip discharge pipe that is suspended from the frame-shaped frame, inserted into the steel pipe pile, and is configured to be extendable and contractible in the pipe longitudinal direction. A digging weight disposed at a lower end of the slip discharge pipe in a state where the discharge pipe is penetrated, an equipment installation base integrally provided with the frame-shaped frame, and an equipment installation Power units and winches placed on the gantry With running at least the pile for percussion device and medium weight for digging of various sieves include,
And a set of equipment for performing the expansion / contraction operation of the shear discharge pipe. The telescopic shed discharge pipe includes, for example, one or a plurality of telescopic pipe sections including an inner pipe and an outer pipe, and a lower end of the telescopic operation wire is provided at a lower end of the lowermost telescopic pipe section. It is possible to adopt a structure in which the length of the slip discharge pipe is controlled by connecting and fixing, and winding / unwinding the telescopic operation wire.
【0013】これらの場合において、前記フレーム枠体
状の架構下部に各種鋼管杭径に適合させるためのアジャ
スタブルガイド装置を設けてあることが望ましい。In these cases, it is desirable that an adjustable guide device for adjusting to various steel pipe pile diameters is provided below the frame-shaped frame.
【0014】本発明装置と従来装置との大きな相違点
は、本発明装置の場合には基本的に起重機船によって吊
り保持されていなくても、及びウインチやパワーユニッ
トなどの機器類が配置された起重機船や台船などが傍に
居なくても装置単独で杭打撃装置および中掘り用重錘を
稼働でき、杭打ちが出来るようにした点にある。具体的
には、フレーム枠体状の架構に対して一体的に機器設置
架台を設け、この機器設置架台上に装置の稼働に必要な
設備一式を配置するようにしている。また、従来装置の
場合には常に装置全体を吊り上げた状態で前記油圧ハン
マーを稼働させるという前提の下、フレーム枠体状架構
と油圧ハンマーとはボルト等によって堅固に一体化さ
れ、フレーム枠体状架構に伝播される振動や衝撃に対す
る配慮は一切成されていないが、本発明装置の場合に
は、フレーム枠体状架構に機器設置架台が設けられ、施
工に必要な機器類が装備されているため、極力、油圧ハ
ンマーからの振動や衝撃がフレーム枠体状の架構に伝わ
らないように、フレーム枠体状架構と油圧ハンマーとは
衝撃を吸収できるような構造により一体化されている。
たとえば、後述のように、フレーム枠体状の架構内部に
油圧ハンマーを上吊りワイヤと下吊りワイヤとによって
中空位置に保持することによって振動や衝撃が伝わらな
いようになっている。この場合、フレーム枠体状の架構
を起重機船で吊り上げた状態では、上吊りワイヤによっ
て油圧ハンマーが吊持され、油圧ハンマーが鋼管杭頭部
に搭載された状態では、下吊りワイヤによってフレーム
枠体状の架構が吊持される。A major difference between the apparatus of the present invention and the conventional apparatus is that in the case of the apparatus of the present invention, the hoist basically does not have to be hung and held by a hoist ship, and has a device such as a winch or a power unit. The point is that the pile hitting device and the weight for digging can be operated by itself without using a ship or a barge, and the pile driving can be performed. Specifically, an equipment installation frame is provided integrally with the frame-like frame, and a set of equipment necessary for operating the apparatus is arranged on the equipment installation frame. Further, in the case of the conventional device, on the premise that the hydraulic hammer is always operated while the entire device is lifted, the frame frame-shaped frame and the hydraulic hammer are firmly integrated with bolts or the like, and the frame frame-shaped frame is formed. No consideration is given to vibrations and shocks transmitted to the frame, but in the case of the device of the present invention, an equipment installation frame is provided on the frame-like frame, and equipment necessary for construction is provided. Therefore, the frame frame-shaped frame and the hydraulic hammer are integrated by a structure capable of absorbing the impact so that vibration and impact from the hydraulic hammer are not transmitted to the frame-shaped frame as much as possible.
For example, as will be described later, vibration and impact are prevented from being transmitted by holding a hydraulic hammer in a hollow position inside a frame-shaped frame by an upper suspension wire and a lower suspension wire. In this case, the hydraulic hammer is suspended by the upper suspending wire in a state where the frame-shaped frame is lifted by the hoisting ship, and in a state in which the hydraulic hammer is mounted on the steel pipe pile head, the frame suspender is suspended by the lower suspending wire. Frame is suspended.
【0015】第2の重錘式鋼管中掘打込み装置では、特
にズリ排出管を長手方向に伸縮自在としたものであり、
後述のように、ズリ排出管を収縮させた状態で油圧ハン
マーによって鋼管杭の貫入を行い、鋼管杭を自立させた
後、ズリ排出管を伸ばしながら中掘り用重錘を鋼管杭の
下端近傍まで下降させることができるようになってい
る。[0015] In the second weight-type steel pipe digging and driving apparatus, the slip discharge pipe is made particularly expandable and contractible in the longitudinal direction.
As will be described later, the steel pipe pile is penetrated by a hydraulic hammer with the shear discharge pipe contracted, and after the steel pipe pile is made to stand by itself, the middle digging weight is extended to the vicinity of the lower end of the steel pipe pile while extending the shear discharge pipe. It can be lowered.
【0016】また本発明では、フレーム枠体状の機器設
置架台上に置かれたウインチから繰り出されるワイヤに
よって中掘り用重錘が昇降制御されるようになるため、
中掘り用重錘用ワイヤの操作延長が短くなり、ワイヤ張
力の均一化が図れると共に、捻れなどが防止されるよう
になるため、従来頻繁に発生していたワイヤ交換の手間
が省力化されるようになる。Further, in the present invention, since the weight for digging is controlled to be lifted and lowered by a wire fed from a winch placed on a frame-shaped equipment installation base.
The lengthening of the operation of the wire for the boring weight is shortened, the wire tension is made uniform, and twisting is prevented, so that the time and effort of replacing the wire, which has frequently occurred in the past, can be saved. Become like
【0017】他方、前記第1の重錘式鋼管中掘打込み装
置を用いた施工方法は、杭下端部を地盤に当接させた状
態で打込み対象の鋼管杭を直立的に保持し、前記重錘式
鋼管中掘打込み装置を起重機船によって吊持して前記鋼
管杭の頭部に搭載するとともに、前記起重機船によって
重錘式鋼管中掘打込み装置を吊り状態で保持したまま、
前記杭用打撃装置および/または中掘り用重錘を稼働す
ることによって前記鋼管杭を所定の深さ位置まで貫入さ
せたならば、前記起重機船による吊り保持を解放し、そ
の後、頂部に重錘式鋼管中掘打込み装置を搭載した自立
状態のままで鋼管杭の打込みを継続して行うことを特徴
とするものである。On the other hand, in the construction method using the first weight type steel pipe digging and driving apparatus, the steel pipe pile to be driven is held upright while the lower end of the pile is in contact with the ground, While the weight type steel pipe digging and driving device is hung by a hoist ship and mounted on the head of the steel pipe pile, while the weight type steel pipe digging and driving device is held by the hoisting ship in a suspended state,
If the steel pipe pile is penetrated to a predetermined depth position by operating the pile hitting device and / or the digging weight, the suspension holding by the hoist ship is released, and then the weight is placed on the top. The present invention is characterized in that the driving of the steel pipe pile is continuously performed while the steel pipe pile is driven in a self-supporting state equipped with a steel pipe excavation driving device.
【0018】また、第2の重錘式鋼管中掘打込み装置を
用いた施工方法は、杭下端部を地盤に当接させた状態で
打込み対象の鋼管杭を直立的に保持し、前記重錘式鋼管
中掘打込み装置を起重機船によって吊持して前記鋼管杭
の頭部に搭載するとともに、前記起重機船によって重錘
式鋼管中掘打込み装置を吊り状態で保持したまま、前記
ズリ排出管を収縮させた状態として前記杭用打撃装置を
稼働することによって前記鋼管杭を所定の深さ位置まで
貫入させたならば、前記起重機船による吊り保持を解放
し、次いで鋼管貫入深さを現位置に留めた状態で、中掘
り用重錘の引き上げと落下とを繰り返し前記ズリ排出管
を伸長させながら中掘り用重錘を鋼管杭の下端近傍位置
まで下降させ、その後、頂部に重錘式鋼管中掘打込み装
置を搭載した自立状態のままで鋼管杭の打込みを継続し
て行うことを特徴とするものである。Further, in the construction method using the second weight-type steel pipe digging and driving apparatus, the steel pipe pile to be driven is held upright while the lower end of the pile is in contact with the ground. While holding the type steel pipe digging and driving device by a hoisting ship and mounting it on the head of the steel pipe pile, while holding the weight type steel pipe digging and driving device in a suspended state by the hoisting ship, the slip discharge pipe is removed. If the steel pipe pile is penetrated to a predetermined depth position by operating the pile hitting device in a contracted state, the suspension holding by the hoist ship is released, and then the steel pipe penetration depth is set to the current position. In the fixed state, while repeatedly pulling up and dropping the weight for boring, the boring weight is lowered to a position near the lower end of the steel pipe pile while extending the shear discharge pipe. Independence equipped with excavation equipment It is characterized in that the continuously performed implantation of the steel pipe piles remain state.
【0019】[0019]
【発明の実施の形態】以下、本発明の実施の形態につい
て図面を参照しながら詳述する。図1は本発明に係る重
錘式中掘併用杭打ち装置1の上部側側面図、図2はその
下部側縦断面図であり、図3はその全体図である。Embodiments of the present invention will be described below in detail with reference to the drawings. FIG. 1 is a side view of an upper side of a pile-type pile driving device 1 according to the present invention, FIG. 2 is a vertical sectional view of a lower side thereof, and FIG. 3 is an overall view thereof.
【0020】前記重錘式中掘併用杭打ち装置1は、主
に、フレーム枠体状の架構たるフライングリーダー2
と、このフライングリーダー2の上部および下部に一体
的に設けられた機器設置架台3,4と、これら機器設置
架台3,4上に設置されたパワーユニット、ウインチ
類、エアホース用リール、各種シーブ類等の設備機器一
式と、前記フライングリーダー2内に宙吊り状態で配置
された中空油圧ハンマー5と、この中空油圧ハンマー5
の中空を通して縦通しで配置された伸縮可能なズリ排出
管6と、ズリ排出管6を貫通させた状態でズリ排出管6
の下部位置に配設された中掘り用重錘7とから構成され
ている。[0020] The weight-type co-digging pile driving device 1 mainly comprises a flying leader 2 which is a frame-shaped frame.
And equipment installation bases 3 and 4 integrally provided on the upper and lower parts of the flying leader 2, and power units, winches, air hose reels, various sheaves and the like installed on the equipment installation bases 3 and 4. And a hollow hydraulic hammer 5 arranged in a suspended state in the flying leader 2 and a hollow hydraulic hammer 5
A telescopic shed discharge pipe 6 vertically arranged through a hollow of the shed, and a shed discharge pipe 6 with the shed discharge pipe 6 penetrated therethrough.
And a weight 7 for digging, which is disposed at a lower position of the center.
【0021】以下、具体的に詳述すると、前記フライン
グリーダー2は、フレーム枠よりなるリーダー本体10
の下部側に鋼管杭P頭部の挿入孔11を有し、かつこの
挿入孔11の周囲には鋼管杭Pの外面に当接する複数の
アジャスタブルガイド装置12,12…を備えている。
このアジャスタブルガイド装置12は、押圧板12a
と、この押圧板12aを前後進させるためのジャッキ1
2bとからなり、貫入される鋼管杭Pの外径に応じて前
記押圧板12aの位置を調整することによって径が異な
っても鋼管杭Pに外面に対して前記押圧板12aをきっ
ちりと押圧接触させることが出来るようにしたものであ
る。後述するように、自立した鋼管杭Pの頭部に対して
中空油圧ハンマー5を搭載させる際に、前記押圧板12
a、12a…が鋼管杭Pの外面に対して押圧させること
によってフライングリーダー2が堅固に支持されるよう
になっている。なお、中空油圧ハンマー5の直下部には
複数径の鋼管杭Pに対応できるように接合用ブロック金
物16が固定されており、この接合用ブロック金物16
の下面に鋼管径毎に設けられた所定の係合溝に対して鋼
管杭Pの頭部縁が係合するようになっている。Hereinafter, the flying leader 2 will be described in detail.
Has an insertion hole 11 at the bottom of the steel pipe pile P, and a plurality of adjustable guide devices 12, 12,... Which come into contact with the outer surface of the steel pipe pile P around the insertion hole 11.
The adjustable guide device 12 includes a pressing plate 12a.
And a jack 1 for moving the pressing plate 12a forward and backward.
2b, and by adjusting the position of the pressing plate 12a according to the outer diameter of the steel pipe pile P to be penetrated, the pressing plate 12a is brought into tight contact with the outer surface of the steel pipe pile P even if the diameter is different. It is made to be able to be. As described later, when the hollow hydraulic hammer 5 is mounted on the head of the self-standing steel pipe pile P, the pressing plate 12
are pressed against the outer surface of the steel pipe pile P so that the flying leader 2 is firmly supported. It should be noted that a joining block hardware 16 is fixed directly below the hollow hydraulic hammer 5 so as to correspond to the steel pipe piles P having a plurality of diameters.
The head edge of the steel pipe pile P is engaged with a predetermined engagement groove provided for each steel pipe diameter on the lower surface of the steel pipe pile.
【0022】一方、フライングリーダー2の頂部4カ所
には、それぞれ吊りピース13,13…が設けられてお
り、起重機船によって吊持できるようになっている。On the other hand, hanging pieces 13, 13... Are provided at four tops of the flying leader 2, respectively, so that they can be hung by a hoist ship.
【0023】このフライングリーダー2の内部に配置さ
れる中空油圧ハンマー5は、フライングリーダ2の上部
と中空油圧ハンマー5の上部との間に掛け渡されたワイ
ヤーロープ14,14と、中空油圧ハンマー5の上部と
フライングリーダー2の下部との間に掛け渡されたワイ
ヤーロープ15,15…によってフライングリーダー2
の内部に宙吊り状態で支持されている。すなわち、起重
機船でフライングリーダー2を吊持した際には中空油圧
ハンマー5が吊り支持され、鋼管杭Pの頭部に中空油圧
ハンマー5を搭載させた際には逆にフライングリーダー
2が中空油圧ハンマー5によって吊り状態で支持される
ようになっている。The hollow hydraulic hammer 5 disposed inside the flying leader 2 includes wire ropes 14, 14 laid between the upper portion of the flying leader 2 and the upper portion of the hollow hydraulic hammer 5, and the hollow hydraulic hammer 5. Of the flying leader 2 by means of wire ropes 15, 15.
It is supported in a suspended state inside. That is, when the flying leader 2 is hung on the hoist ship, the hollow hydraulic hammer 5 is suspended and supported, and when the hollow hydraulic hammer 5 is mounted on the head of the steel pipe pile P, the flying hydraulic It is supported by the hammer 5 in a suspended state.
【0024】他方、前記フライングリーダー2の上部お
よび下部にはそれぞれ機器設置架台3,4が一体的に設
けられている。この機器設置架台3,4には、杭打ち作
業に必要なパワーユニット、ウインチ類、エアホース用
リール、各種シーブ類等の機器が設置される。具体的に
は、上部機器設置架台3には、ズリ排出管6に供給され
るリフト用エアを供給するためのエアホースリール1
7,17と、中掘り重錘操作ワイヤー用シーブ18と、
伸縮自在のズリ排出管6のズリ管長を調整するためのズ
リ排出管操作ワイヤー用シーブ19などが設置されてい
る。また、下部機器設置架台4には中掘り重錘用ウイン
チ21と、ズリ排出管用ウインチ22と、ウインチ用パ
ワープラント23と、油圧ハンマー用パワープラントな
どの機器が設置されている。これらの機器設置架台3,
4には、作業員が機器操作や点検保守などのために昇る
ことがあるため、落下防止のために周囲にはすべて柵が
設けられている。On the other hand, on the upper part and the lower part of the flying leader 2, equipment installation stands 3 and 4 are provided integrally. Equipment such as power units, winches, reels for air hoses, and various sheaves necessary for pile driving work are installed on the equipment installation frames 3 and 4. Specifically, an air hose reel 1 for supplying the lift air supplied to the shear discharge pipe 6 is provided on the upper device installation base 3.
7, 17 and a sheave 18 for a boring weight operating wire,
A shear discharge pipe operation wire sheave 19 for adjusting the length of the telescopic discharge pipe 6 is installed. Further, on the lower device installation stand 4, devices such as a winch 21 for a boring weight, a winch 22 for a shear discharge pipe, a power plant 23 for a winch, and a power plant for a hydraulic hammer are installed. These equipment installation stands 3,
4 is provided with a fence all around in order to prevent a worker from climbing up for equipment operation or inspection and maintenance.
【0025】他方、ズリ排出管6は中空油圧ハンマー5
およびフライングリーダー2を上下方向に貫通する上部
固定管路部16Aと、伸縮管路部16Bと、下部上段固
定管路部16Cと、下部下段固定管路部16Dとから構
成されている。図3(A)がズリ搬出管6を全伸長した
状態の全体図であり、図3(B)はズリ排出管6を全収
縮した状態の全体図である。On the other hand, the slip discharge pipe 6 is a hollow hydraulic hammer 5
And an upper fixed pipe section 16A vertically penetrating the flying leader 2, a telescopic pipe section 16B, a lower upper fixed pipe section 16C, and a lower lower fixed pipe section 16D. FIG. 3A is an overall view of the state in which the shear discharge pipe 6 is fully extended, and FIG. 3B is an overall view of the state in which the shear discharge pipe 6 is fully contracted.
【0026】前記伸縮管路部16Bは、詳細には図4に
示されるように、上部側から上部接続管25,第1伸縮
管26、中間接続管27,第2伸縮管28,中間接続管
29、第3伸縮管30、下部接続管31の順に構成され
ており、前記第1〜第3伸縮管26,28,30が管長
手方向に伸縮できるようになっている。代表的に第1伸
縮管26について説明すると、第1伸縮管26は内管3
2と外管33とから構成されており、前記内管32は上
部側に位置する上部接続管25の下面側にボルトによっ
て連結され、一方外管33は内径をほぼ内管32と同じ
くし、内面側にシールのためにOリングが配設された第
1外管部33Aとその下側に連設された内管外径よりも
若干内径の大きい第2外管部33Bと、さらにこの第2
外管部33Bの下端側に連設された第3外管部34とか
ら構成され、前記第1及び第2外管部33A、33Bに
対して内管32が挿入されることによって管長手方向に
伸縮可能となっている。As shown in detail in FIG. 4, the telescopic pipe section 16B includes an upper connecting pipe 25, a first telescopic pipe 26, an intermediate connecting pipe 27, a second telescopic pipe 28, and an intermediate connecting pipe from the upper side. 29, a third telescopic pipe 30, and a lower connecting pipe 31 in this order, so that the first to third telescopic pipes 26, 28, 30 can expand and contract in the pipe longitudinal direction. Representatively, the first telescopic tube 26 will be described.
2 and an outer tube 33. The inner tube 32 is connected to the lower surface side of the upper connection tube 25 located on the upper side by bolts, while the outer tube 33 has an inner diameter substantially the same as the inner tube 32, A first outer tube portion 33A having an O-ring provided on the inner surface for sealing, a second outer tube portion 33B having a slightly larger inner diameter than the inner tube outer diameter continuously provided below the first outer tube portion 33A; 2
A third outer tube portion 34 continuously provided at the lower end of the outer tube portion 33B, and the inner tube 32 is inserted into the first and second outer tube portions 33A and 33B, so that the longitudinal direction of the tube is increased. It can be expanded and contracted.
【0027】前記伸縮管路部16Bの伸縮制御は、前記
機器設置架台4に設置されたズリ排出管用ウインチ22
から繰り出された2条の伸縮管操作ワイヤ35A、35
Bを前記第3伸縮管30の下端部に連結固定し、伸縮管
操作ワイヤ35A、35Bの巻き上げ/繰り出し操作に
よって前記伸縮管路部16Bの長さが制御されるように
なっている。The expansion and contraction control of the expansion and contraction pipe section 16B is performed by a shear discharge pipe winch 22 installed on the equipment installation base 4.
Telescopic tube operation wires 35A, 35
B is connected and fixed to the lower end of the third telescopic tube 30, and the length of the telescopic tube passage 16B is controlled by the winding / unwinding operation of the telescopic tube operation wires 35A and 35B.
【0028】一方、前記ズリ排出管6には、その長手方
向に沿って2本のエア供給ホース36A、36Bが配設
され、これらのエア供給ホース36A、36Bは、下部
上段固定管路部16Cの下端部に接続され、破砕したズ
リをエアリフト方式によって循環水と共に前記ズリ排出
管6を通じて系外に排出するようになっている。排出さ
れたズリと循環水とは、スクリーンによって循環水とズ
リとに大別され、一方のズリは残土タンクに排出され、
他方の循環水(砂分含む。)はサンドポンプによりサイ
クロンに送られ、ここで循環水と砂分とに分離される。
そして、サイクロンオーバーした低比重循環水が再びズ
リ排出管6の上部に送られるようになっている。On the other hand, two air supply hoses 36A, 36B are provided along the longitudinal direction of the shear discharge pipe 6, and these air supply hoses 36A, 36B are connected to the lower upper fixed pipe section 16C. The crushed waste is discharged to the outside of the system through the waste discharge pipe 6 together with the circulating water by an air lift method. The discharged waste and circulating water are roughly divided into circulating water and waste by the screen, and one of the waste is discharged to the residual soil tank,
The other circulating water (including sand) is sent to the cyclone by a sand pump, where it is separated into circulating water and sand.
Then, the low-specific-gravity circulating water that has passed over the cyclone is sent to the upper portion of the waste discharge pipe 6 again.
【0029】なお、前記エア供給ホース36A、36B
は、伸縮管路部16Bの外管33に対して固定金具37
によって固定され、伸縮管路部16Bの伸縮に同調する
ようになっており、前記固定金具37の上部側では、図
5および図6に示されるように、前記伸縮管操作ワイヤ
35A、35Bとエア供給ホース36A、36Bとは保
護管38の内部に収容されているとともに、この保護管
38の上下端部に配設されたガイドガイドローラ39が
配設され、伸縮管操作ワイヤ35A、35Bとエア供給
ホース36A、36Bとの伸縮が円滑に行われるように
なっている。The air supply hoses 36A, 36B
Are fixed to the outer pipe 33 of the telescopic pipe section 16B.
5 and 6, the upper part of the fixing bracket 37 is connected to the telescopic pipe operation wires 35A, 35B and the air, as shown in FIGS. The supply hoses 36A and 36B are housed inside the protection tube 38, and guide guide rollers 39 provided at the upper and lower ends of the protection tube 38 are provided. Expansion and contraction with the supply hoses 36A and 36B are performed smoothly.
【0030】他方、ズリ排出管6の最下部となる下部下
段固定管路部16Dに対して設けられた中掘り用重錘7
は、図7に示されるように、下端部にビット42aを備
えた摺動管42の周囲に対して、同じく下端縁にビット
41,41…を固設した重錘板40、40…を平面視で
放射状に多数固設したものであり、この中掘り用重錘7
の上部側には下部下段固定管路部16Dに外嵌するイコ
ライザ43が設けられ、2条のチェーン44,44に連
結されている。前記イコライザ43には、中掘り重錘用
ウインチ21から中掘り重錘操作ワイヤー用シーブ18
を介して繰り出された2条の重錘用操作ワイヤ45A、
45Bの下端が連結固定されており、前記中掘り重錘用
ウインチ21における巻きドラムの回転制御によって下
部下段固定管路部16Dをガイド管として中掘り用重錘
7が上方に引き上げられた後、一気に張力が解放される
ことにより自由落下し、岩盤を衝撃によって破砕する。
破砕されたズリは、下部下段固定管路部16Dの下端に
設けられたズリ取り込み口16dより管の内部に取り込
まれ、ズリ排出管6を通して外部に排出される。On the other hand, the digging weight 7 provided for the lower lower fixed pipeline 16D, which is the lowermost portion of the shear discharge pipe 6, is provided.
As shown in FIG. 7, the weight plates 40, 40... On which the bits 41, 41. Many of them are fixed radially by visual inspection.
An equalizer 43 is provided on the upper side of the lower end of the lower fixed pipe section 16D, and is connected to the two chains 44, 44. The equalizer 43 includes the boring weight winch 21 to the boring weight operating wire sheave 18.
Weight operation wire 45A fed out through
The lower end of 45B is connected and fixed, and after the lower digging weight 7 is pulled up with the lower lower fixed conduit 16D as a guide tube by the rotation control of the winding drum in the inner digging weight winch 21, When the tension is released at once, it falls freely and breaks the rock by impact.
The crushed waste is taken into the inside of the pipe through a waste intake port 16d provided at the lower end of the lower fixed pipe section 16D, and is discharged through the waste discharge pipe 6 to the outside.
【0031】以下、前述した重錘式中掘併用杭打ち装置
1を用いて海底に鋼管杭Pを打ち込む方法について、図
8〜図12に基づいて詳述することとする。Hereinafter, a method of driving the steel pipe pile P into the seabed by using the above-described weight type excavator 1 with piles will be described in detail with reference to FIGS.
【0032】先ず、鋼管杭Pが傾斜した状態で地盤中に
打ち込まれるのを防止するため、準備工として海面近傍
に鋼管杭ガイド枠50を設置する。鋼管杭ガイド枠50
は、図11に示されるように、鋼管杭Pの列方向に沿っ
てかつ中心列線Sを挟んでその両側に導杭52,52…
を打設するとともに、この導杭52,52…の内側に鋼
管杭P方向に沿って縦導枠51、51を配設し、かつ鋼
管杭P分の空間を空けて縦導枠51,51の間に横導枠
53,53…を掛け渡すことによって構成されている。First, in order to prevent the steel pipe pile P from being driven into the ground in an inclined state, a steel pipe pile guide frame 50 is installed near the sea surface as a preparatory work. Steel pipe pile guide frame 50
11, the guide piles 52, 52,... Along the column direction of the steel pipe piles P and on both sides of the central column line S, as shown in FIG.
, And vertical guide frames 51, 51 are disposed along the steel pipe piles P inside the guide piles 52, 52,... Are arranged between the horizontal guide frames 53, 53.
【0033】なお、前記鋼管杭ガイド枠としては、前記
例に限らずたとえば図12に示されるように、起重機船
または台船60の端縁部より外がわに突出して、縦導枠
61A、61Bおよび横導枠62A、62Bとから構成
された鋼管杭ガイド枠59を設け、貫入させる鋼管杭P
毎に保持するようにしてもよい。The steel pipe pile guide frame is not limited to the above example, and as shown in FIG. 12, for example, as shown in FIG. A steel pipe pile guide frame 59 composed of a steel pipe pile 61 composed of a steel pipe pile 61B and horizontal guide frames 62A and 62B is provided.
It may be held every time.
【0034】前記鋼管杭ガイド枠50の中に鋼管杭Pを
挿入して下端部を海底に当接させたならば、鋼管杭Pの
頭部に起重機船によって吊り上げた重錘式中掘併用杭打
ち装置1を設置する。When the steel pipe pile P is inserted into the steel pipe pile guide frame 50 and the lower end thereof is brought into contact with the seabed, the pile with the heavy weight type excavation suspended on the head of the steel pipe pile P by the crane ship. The driving device 1 is installed.
【0035】前記起重機船によって重錘式中掘併用杭打
ち装置1を吊り状態で保持したまま、図8に示されるよ
うに、中空油圧ハンマー5を稼働し、鋼管杭Pに打撃を
与えながら鋼管杭Pを海底地盤中に貫入させる。この状
態では、ズリ排出管6は収縮させておき、少なくとも鋼
管杭Pが地盤に貫入される際に海底に接触したり、鋼管
杭Pの貫入を阻害しないようにしておく。As shown in FIG. 8, the hollow hydraulic hammer 5 is operated and the steel pipe piles P are hit while the steel pipe piles are struck, while the weight-driven drilling and pile driving device 1 is suspended by the hoist ship. The pile P is made to penetrate into the seabed ground. In this state, the shear discharge pipe 6 is contracted so that at least when the steel pipe pile P penetrates into the ground, it does not contact the sea bottom or hinder the penetration of the steel pipe pile P.
【0036】前記鋼管杭Pが任意の所定深さL、本例で
は自立貫入深さLまで達したならば、起重機船によるフ
ライングリーダー2の吊り保持を解放する。この時点
で、起重機船は自由となり別の鋼管杭Pの打設作業に入
ることができるようになる。鋼管杭Pを起重機船によっ
て自立貫入深さLまで貫入させることによって、起重機
船による吊り支持が無くなっても鋼管杭Pは倒れること
なく自立し、その後も鉛直状態を維持したまま安全に杭
打ちが行えるようになる。When the steel pipe pile P reaches an arbitrary predetermined depth L, in this example, a self-supporting penetration depth L, the suspension of the flying leader 2 by the hoist ship is released. At this point, the hoist ship is free and can start the work of placing another steel pipe pile P. By penetrating the steel pipe pile P to the self-supporting penetration depth L by the hoist ship, the steel pipe pile P can stand up without falling down even if the lifting support by the hoist ship is lost, and thereafter the pile can be safely driven while maintaining the vertical state. Will be able to do it.
【0037】次いで、図9に示されるように、鋼管貫入
深さLを現位置に留めた状態で、中掘り用重錘7の引き
上げと落下とを繰り返し、かつズリ排出管6を伸長させ
ながら中掘り重錘7を鋼管杭Pの下端近傍位置まで下降
させる。Next, as shown in FIG. 9, while the steel pipe penetration depth L is kept at the current position, the lifting and dropping of the weight 7 for digging is repeated, and the slip discharge pipe 6 is extended. The digging weight 7 is lowered to a position near the lower end of the steel pipe pile P.
【0038】その後は、図10に示されるように、油圧
ハンマー5によって鋼管杭Pに対する打撃打込みと、中
掘り重錘7の引き上げと落下とを繰り返すことによる中
掘り掘削とを併用しながら鋼管杭Pを予定深さ位置まで
貫入させる。この中掘り・打込み工程においては、地盤
種別に応じて、中掘りおよび打込みの内の一方を先行さ
せながら杭の貫入を行ったり、鋼管杭Pの先端部で中掘
りと打込みとを同時に行うことができる。すなわち、硬
質地盤の場合には中掘りを打込みに先行させることによ
って、鋼管杭Pの先端地盤にクラックを誘発することが
でき、小さな打撃力で鋼管杭Pを打ち込むことができる
ようになり、また軟質地盤の場合には打込みを先行させ
ることにより鋼管杭Pの貫入効率を向上させ得るように
なる。また、中間程度の硬さの地盤の場合には、中掘り
と打込みとを同時に行うことにより貫入効率が向上す
る。Thereafter, as shown in FIG. 10, the hydraulic hammer 5 strikes and hits the steel pipe pile P, and the hollow pipe excavation by repeating the lifting and dropping of the boring weight 7, while simultaneously excavating the steel pipe pile. P is penetrated to the planned depth position. In this middle digging and driving process, depending on the type of ground, the piercing of the pile is performed while one of the digging and driving is performed first, and the digging and driving are simultaneously performed at the tip of the steel pipe pile P. Can be. In other words, in the case of hard ground, cracking can be induced in the ground at the tip of the steel pipe pile P by digging the medium digging prior to driving, and the steel pipe pile P can be driven with a small impact force. In the case of soft ground, the penetration efficiency of the steel pipe pile P can be improved by preceding the driving. Further, in the case of the ground having an intermediate hardness, the penetration efficiency is improved by simultaneously performing the excavation and the driving.
【0039】鋼管杭Pの貫入を前述要領によって継続し
て行い、鋼管杭Pの先端が支持岩盤に達したならば、中
掘りを先行して行った後、油圧ハンマー5による打込み
を行い所定の根入れ深さKまで鋼管杭Pを貫入させたな
らば本鋼管杭の貫入作業を終了し、次の鋼管杭の貫入作
業に入る。The penetration of the steel pipe pile P is continued as described above, and when the tip of the steel pipe pile P reaches the supporting rock, the digging is performed in advance, and the hydraulic hammers 5 are used to drive the steel pipe pile P into a predetermined position. When the steel pipe pile P has been penetrated to the penetration depth K, the penetration work of the steel pipe pile is completed, and the penetration work of the next steel pipe pile is started.
【0040】なお、本例では、鋼管杭Pの貫入鉛直精度
を確保するため、海面付近に鋼管杭ガイド枠50を用い
たが、鋼管杭Pの設置精度が要求されないような場合に
は、前記鋼管杭ガイド枠50を省略し、鋼管杭Pを起重
機船などにより一時的に鉛直保持するようにしてもよ
い。もちろん、この場合には他の支持がなくても鋼管杭
Pが自立できる程度に初期貫入深さLを十分に取る必要
がある。In this embodiment, the steel pipe pile guide frame 50 is used near the sea surface in order to secure the penetration vertical accuracy of the steel pipe pile P. However, when the installation precision of the steel pipe pile P is not required, The steel pipe pile guide frame 50 may be omitted, and the steel pipe pile P may be temporarily held vertically by a hoist ship or the like. Of course, in this case, the initial penetration depth L needs to be sufficiently large so that the steel pipe pile P can stand alone without any other support.
【0041】以上、ズリ排出管を伸縮自在とした重錘式
鋼管中掘打込み装置1について、その装置構成および施
工方法について説明したが、ズリ排出管を固定長とした
ままとすることもできる。この場合には、初期の油圧ハ
ンマー5による鋼管杭Pの貫入時にズリ排出管が海底に
当接することになるため、前記起重機船によって重錘式
鋼管中掘打込み装置1を吊り状態で保持したまま、中空
油圧ハンマー5による打撃打込みと、中掘り用重錘7に
よる中掘り掘削とを併用しながら鋼管杭Pを所定の深さ
位置まで貫入させた後に、前記起重機船による吊り保持
を解放するようにすればよい。As described above, the apparatus structure and the method of construction of the weight type steel pipe digging and driving apparatus 1 in which the slip discharge pipe is extendable and contractible have been described. However, the slip discharge pipe may be kept at a fixed length. In this case, when the steel pipe pile P is penetrated by the initial hydraulic hammer 5, the shear discharge pipe comes into contact with the seabed. Therefore, the weight type steel pipe digging and driving device 1 is suspended by the hoist ship. After the steel pipe pile P is penetrated to a predetermined depth position while using both the hammering in by the hollow hydraulic hammer 5 and the digging and digging by the digging weight 7, the suspension holding by the hoist ship is released. What should I do?
【0042】[0042]
【発明の効果】以上詳説のとおり本発明によれば、起重
機船の拘束を最小限にし、1台の起重機船によって複数
台の重錘式中掘杭打ち装置による施工が可能となるた
め、作業の効率化が図れるようになるとともに、起重機
船の損料軽減により工費削減が図るようになる。また、
中掘り用重錘用ワイヤの操作延長を短くすることがで
き、ワイヤ張力の均一化や捻れ防止により、従来頻繁に
発生していたワイヤ交換の手間を省力化することができ
るようになる。As described above in detail, according to the present invention, the restraint of the hoist ship can be minimized, and the construction can be performed by a plurality of weight type underground pile driving devices by one hoist ship. And the cost of construction can be reduced by reducing the loss on hoist ships. Also,
It is possible to shorten the operation extension of the wire for the boring weight, and to equalize the wire tension and prevent torsion, so that it is possible to save labor for wire replacement which has conventionally frequently occurred.
【図1】本発明に係る重錘式中掘併用杭打ち装置1の上
部側側面図である。FIG. 1 is a side view of an upper side of a pile-type pile driving device 1 with a weight-type underground digging according to the present invention.
【図2】その下部縦断面図である。FIG. 2 is a lower longitudinal sectional view thereof.
【図3】その全体図であり、(A)はズリ排出管6の全
伸時、(B)はズリ排出管6の全縮時である。3A and 3B are overall views, in which FIG. 3A shows a state in which the shear discharge pipe 6 is fully extended, and FIG.
【図4】ズリ排出管6の伸縮管路部16Bの縦断面図で
ある。FIG. 4 is a longitudinal sectional view of a telescopic pipe section 16B of the tip discharge pipe 6.
【図5】図4のV−V線矢視図である。FIG. 5 is a view taken along line VV of FIG. 4;
【図6】図4のVI−VI線矢視図である。FIG. 6 is a view taken along line VI-VI of FIG. 4;
【図7】中掘り用重錘7部の拡大側面図である。FIG. 7 is an enlarged side view of a weight 7 for digging.
【図8】鋼管杭の杭打ち手順図(その1)である。FIG. 8 is a pile driving procedure diagram (part 1) of a steel pipe pile.
【図9】鋼管杭の杭打ち手順図(その2)である。FIG. 9 is a pile driving procedure diagram (part 2) of a steel pipe pile.
【図10】鋼管杭の杭打ち手順図(その3)である。FIG. 10 is a pile driving procedure diagram (part 3) of a steel pipe pile.
【図11】鋼管杭ガイド枠の平面図である。FIG. 11 is a plan view of a steel pipe pile guide frame.
【図12】他の方法による鋼管杭ガイド枠の設置要領図
であり、(A)は側面図、(B)は平面図である。12A and 12B are installation guide diagrams of a steel pipe pile guide frame by another method, in which FIG. 12A is a side view and FIG. 12B is a plan view.
【図13】重錘式鋼管中掘併用吊打ち装置49の側面図
である。FIG. 13 is a side view of a weight-type steel-pipe digging and hanging device 49.
【図14】従来の重錘式鋼管中掘併用吊打ち工法による
施工要領図である。FIG. 14 is a construction view of a conventional weight-type steel pipe digging combined with hanging method.
1…重錘式中掘併用杭打ち装置、2…フライングリーダ
ー、3…上部機器設置架台、4…下部機器設置架台、5
…中空油圧ハンマー、6…ズリ排出管、7…中掘り用重
錘、10…リーダー本体、12…アジャスタブルガイド
装置、17…エアホースリール、18…中掘り重錘操作
ワイヤー用シーブ、19…ズリ排出管操作ワイヤー用シ
ーブ、21…中掘り重錘用ウインチ、22…ズリ排出管
用ウインチ、16A…上部固定管路部、16B…伸縮管
路部、16C…下部上段固定管路部、16D…下部下段
固定管路部、32…内管、33…外管、35A・35B
…伸縮管操作ワイヤ、36A・36B…エア供給ホー
ス、50…鋼管杭ガイド枠、52…導杭、51…縦導
枠、53…横導枠、L…自立貫入深さDESCRIPTION OF SYMBOLS 1 ... Pile driving device combined with weight-type inner digging, 2 ... Flying leader, 3 ... Mounting base for upper equipment, 4 ... Mounting base for lower equipment, 5
... Hollow hydraulic hammer, 6 ... Slip discharge pipe, 7 ... Pit weight for digging, 10 ... Leader body, 12 ... Adjustable guide device, 17 ... Air hose reel, 18 ... Sheave for digging weight weight operation wire, 19 ... Dip discharge Sheave for pipe operation wire, 21: winch for middle digging weight, 22: winch for shear discharge pipe, 16A: upper fixed pipe section, 16B: telescopic pipe section, 16C: lower upper fixed pipe section, 16D: lower lower section Fixed pipe section, 32 ... inner pipe, 33 ... outer pipe, 35A / 35B
... Expansion pipe operation wire, 36A / 36B ... Air supply hose, 50 ... Steel pipe guide frame, 52 ... Pile guide, 51 ... Vertical guide frame, 53 ... Horizontal guide frame, L ... Self-supporting penetration depth
───────────────────────────────────────────────────── フロントページの続き (72)発明者 坂本 和己 東京都大田区南蒲田2丁目16番2号 利根 地下技術株式会社内 Fターム(参考) 2D041 AA02 BA33 CA01 CB06 DB02 FA03 2D050 AA06 CA02 CB13 EE08 EE10 EE15 ────────────────────────────────────────────────── ─── Continuing on the front page (72) Inventor Kazumi Sakamoto 2-16-2 Minami Kamata, Ota-ku, Tokyo Tone Underground Engineering Co., Ltd. F-term (reference) 2D041 AA02 BA33 CA01 CB06 DB02 FA03 2D050 AA06 CA02 CB13 EE08 EE10 EE15
Claims (7)
または他部材を介在させて間接的に搭載され、鋼管杭に
対して打撃を加えることによって前記鋼管杭を地盤中に
貫入させる杭用打撃装置と、この杭用打撃装置からの衝
撃を吸収可能な状態で杭用打撃装置の周りに一体的に取
り付けられたフレーム枠体状の架構と、このフレーム枠
体状の架構より垂下され、鋼管杭の内部に挿入されるズ
リ排出管と、中央に軸貫通孔部を有し前記ズリ排出管が
貫通された状態で前記ズリ排出管の下端部に配置された
中掘り用重錘と、前記フレーム枠体状の架構に対して一
体的に設けられた機器設置架台と、この機器設置架台上
に配置されたパワーユニット、ウインチ類、各種シーブ
類等の少なくとも前記杭用打撃装置および中掘り用重錘
を稼働できる設備機器一式とから構成されたことを特徴
とする重錘式鋼管中掘打込み装置。1. A steel pipe pile to be driven is directly or indirectly mounted with another member interposed therebetween, and the steel pipe pile is penetrated into the ground by hitting the steel pipe pile. A pile hitting device, a frame-like frame integrally attached around the pile hitting device in a state capable of absorbing the impact from the pile hitting device, and a droop from the frame-like frame A shear discharge pipe inserted into the inside of the steel pipe pile, and a middle digging weight disposed at the lower end of the shear discharge pipe having a shaft through hole at the center and penetrating the shear discharge pipe And an equipment installation base provided integrally with the frame-like frame, and at least the pile hitting device such as a power unit, a winch, and various sheaves disposed on the equipment installation base, and Equipment that can operate a digging weight Weight type steel pipe during drilling implantation apparatus characterized by being composed of a vessel set.
または他部材を介在させて間接的に搭載され、鋼管杭に
対して打撃を加えることによって前記鋼管杭を地盤中に
貫入させる杭用打撃装置と、この杭用打撃装置からの衝
撃を吸収可能な状態で杭用打撃装置の周りに一体的に取
り付けられたフレーム枠体状の架構と、このフレーム枠
体状の架構より垂下され、鋼管杭の内部に挿入されると
共に管長手方向に伸縮自在に構成されたズリ排出管と、
中央に軸貫通孔部を有し前記ズリ排出管が貫通された状
態で前記ズリ排出管の下端部に配置された中掘り用重錘
と、前記フレーム枠体状の架構に対して一体的に設けら
れた機器設置架台と、この機器設置架台上に配置された
パワーユニット、ウインチ類、各種シーブ類等の少なく
とも前記杭用打撃装置および中掘り用重錘を稼働すると
ともに、前記ズリ排出管の伸縮操作を行うための設備機
器一式とから構成されたことを特徴とする重錘式鋼管中
掘打込み装置。2. A steel pipe pile to be driven is directly or indirectly mounted with another member interposed therebetween, and the steel pipe pile is penetrated into the ground by applying a blow to the steel pipe pile. A pile hitting device, a frame-like frame integrally attached around the pile hitting device in a state capable of absorbing the impact from the pile hitting device, and a droop from the frame-like frame And a slip discharge pipe that is inserted into the inside of the steel pipe pile and configured to be extendable and contractible in the pipe longitudinal direction,
A center digging weight which has a shaft through hole in the center and is disposed at a lower end of the waste discharge pipe while the waste discharge pipe is penetrated, and is integrally formed with the frame-shaped frame. The installed equipment installation base and the power unit, winch, various sheaves, etc., at least the pile hitting device and the digging weight, such as sheaves, arranged on the equipment installation base are operated, and the expansion and contraction of the shear discharge pipe is performed. A weight-type steel pipe digging and driving device, comprising a set of equipment for performing an operation.
杭径に適合させるためのアジャスタブルガイド装置を設
けてある請求項1,2いずれかに記載の重錘式鋼管中掘
打込み装置。3. An apparatus according to claim 1, further comprising an adjustable guide device provided at a lower portion of said frame-shaped frame to adjust to various steel pipe pile diameters.
外管からなる伸縮管路部を1または複数段に亘って備え
ており、伸縮操作ワイヤの下端部を最下段伸縮管路部の
下端部に連結固定し、前記伸縮操作ワイヤの巻き上げ/
繰り出し操作によってズリ排出管長が制御されるように
してある請求項2記載の重錘式鋼管中掘打込み装置。4. The telescopic shed discharge pipe is provided with one or more telescopic pipe sections comprising an inner pipe and an outer pipe, and a lower end of a telescopic operation wire is provided at a lowermost telescopic pipe section. Connected to the lower end of the telescopic operation wire,
3. A weight type steel pipe excavating apparatus according to claim 2, wherein the length of the shear discharge pipe is controlled by the feeding operation.
中掘打込み装置を用いた鋼管杭の打込み方法であって、 杭下端部を地盤に当接させた状態で打込み対象の鋼管杭
を直立的に保持し、前記重錘式鋼管中掘打込み装置を起
重機船によって吊持して前記鋼管杭の頭部に搭載すると
ともに、前記起重機船によって重錘式鋼管中掘打込み装
置を吊り状態で保持したまま、前記杭用打撃装置および
/または中掘り用重錘を稼働することによって前記鋼管
杭を所定の深さ位置まで貫入させたならば、前記起重機
船による吊り保持を解放し、 その後、頂部に重錘式鋼管中掘打込み装置を搭載した自
立状態のままで鋼管杭の打込みを継続して行うことを特
徴とする重錘式鋼管中掘打込み工法。5. A method of driving a steel pipe pile using the weight type steel pipe digging and driving device according to claim 1, wherein the pile target is driven in a state where the lower end of the pile is in contact with the ground. While holding the steel pipe pile upright, the weight type steel pipe digging and driving device is suspended by a hoist ship and mounted on the head of the steel pipe pile, and the weight type steel pipe digging and driving device is mounted by the hoist ship. If the steel pipe pile is penetrated to a predetermined depth position by operating the hitting device for piles and / or the weight for digging while holding in a suspended state, the suspension holding by the hoist ship is released. After that, the pile type pile driving method is characterized in that the pile pile is continuously driven while the steel pipe pile is driven in a self-supporting state with the weight type pipe drilling device installed on the top.
中掘打込み装置を用いた鋼管杭の打込み方法であって、 杭下端部を地盤に当接させた状態で打込み対象の鋼管杭
を直立的に保持し、前記重錘式鋼管中掘打込み装置を起
重機船によって吊持して前記鋼管杭の頭部に搭載すると
ともに、前記起重機船によって重錘式鋼管中掘打込み装
置を吊り状態で保持したまま、前記ズリ排出管を収縮さ
せた状態として前記杭用打撃装置を稼働することによっ
て前記鋼管杭を所定の深さ位置まで貫入させたならば、
前記起重機船による吊り保持を解放し、 次いで鋼管貫入深さを現位置に留めた状態で、中掘り用
重錘の引き上げと落下とを繰り返し前記ズリ排出管を伸
長させながら中掘り用重錘を鋼管杭の下端近傍位置まで
下降させ、その後、頂部に重錘式鋼管中掘打込み装置を
搭載した自立状態のままで鋼管杭の打込みを継続して行
うことを特徴とする重錘式鋼管中掘打込み工法。6. A method for driving a steel pipe pile using the weight-type steel pipe digging and driving device according to claim 2, wherein the lower end of the pile is brought into contact with the ground to be driven. While holding the steel pipe pile upright, the weight type steel pipe digging and driving device is suspended by a hoist ship and mounted on the head of the steel pipe pile, and the weight type steel pipe digging and driving device is mounted by the hoist ship. While holding in a suspended state, if the steel pipe pile was penetrated to a predetermined depth position by operating the pile hitting device with the shear discharge pipe contracted,
Release the suspension holding by the hoist ship, then, while keeping the steel pipe penetration depth at the current position, repeatedly pulling up and dropping the digging weight, while extending the shear discharge pipe, pulling the digging weight Lowering the steel pipe pile to a position near the lower end of the steel pipe pile, and then continuously driving the steel pipe pile in a self-standing state with the weight type steel pipe drilling device installed at the top Driving method.
面近傍に鋼管杭ガイド枠を予め設置するようにする請求
項5,6いずれかに記載の重錘式鋼管中掘打込み工法。7. The method according to claim 5, wherein a steel pipe pile guide frame is previously installed near the sea surface to hold the steel pipe pile upright.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP33082498A JP3169911B2 (en) | 1998-11-20 | 1998-11-20 | Heavy weight type steel pipe digging and driving method using the same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP33082498A JP3169911B2 (en) | 1998-11-20 | 1998-11-20 | Heavy weight type steel pipe digging and driving method using the same |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2000154538A true JP2000154538A (en) | 2000-06-06 |
JP3169911B2 JP3169911B2 (en) | 2001-05-28 |
Family
ID=18236962
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP33082498A Expired - Fee Related JP3169911B2 (en) | 1998-11-20 | 1998-11-20 | Heavy weight type steel pipe digging and driving method using the same |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3169911B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2016032401A (en) * | 2014-07-30 | 2016-03-07 | 奥地建産株式会社 | Construction method of pile member for frame for planar article |
JP2019060227A (en) * | 2018-10-29 | 2019-04-18 | 深田サルベージ建設株式会社 | Construction method of jacket structure |
WO2020233145A1 (en) * | 2019-05-23 | 2020-11-26 | 上海长凯岩土工程有限公司 | Construction method using inclined steel pipe combined structure to form force bearing body |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102312442A (en) * | 2011-07-01 | 2012-01-11 | 中铁大桥局股份有限公司 | Construction method of trestle steel pipe pile foundation |
CN102383436B (en) * | 2011-09-05 | 2014-03-19 | 中铁大桥局股份有限公司 | Accurate positioning construction method of double-wall steel cofferdam |
CN103981867B (en) * | 2014-05-26 | 2016-02-24 | 天津港航工程有限公司 | The piling position-limited rack of intertidal zone offshore wind power foundation pile sinking and construction method thereof |
-
1998
- 1998-11-20 JP JP33082498A patent/JP3169911B2/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2016032401A (en) * | 2014-07-30 | 2016-03-07 | 奥地建産株式会社 | Construction method of pile member for frame for planar article |
JP2019060227A (en) * | 2018-10-29 | 2019-04-18 | 深田サルベージ建設株式会社 | Construction method of jacket structure |
WO2020233145A1 (en) * | 2019-05-23 | 2020-11-26 | 上海长凯岩土工程有限公司 | Construction method using inclined steel pipe combined structure to form force bearing body |
Also Published As
Publication number | Publication date |
---|---|
JP3169911B2 (en) | 2001-05-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
RU2240418C2 (en) | Drilling device and drilling method | |
US6540443B2 (en) | Apparatus for and a method of boring the ground | |
CN107700479A (en) | A kind of construction method of large diameter drill hole pile | |
CN108978661B (en) | Construction method for removing cast-in-situ bored pile | |
WO2023207250A1 (en) | Construction method for rapidly driving trestle steel pipe pile into sloped bare rock | |
JP3169911B2 (en) | Heavy weight type steel pipe digging and driving method using the same | |
CN211623325U (en) | High efficiency drilling equipment | |
CN110080775A (en) | Complex environment digs a well basic microvariations excavation method | |
CN111155513B (en) | Full-slewing drilling machine and hydraulic vibration hammer cooperative well drilling method | |
JP2515888B2 (en) | Construction method of steel pipe pile for building offshore structure and its equipment | |
JP4478348B2 (en) | Steel pipe pile driving method and apparatus | |
CN115874613B (en) | Advanced inclined thread enlarged composite pile, construction equipment and construction process thereof | |
CN106869125A (en) | A kind of steel pipe pile construction method | |
CN214196393U (en) | Adjustable anti-blocking dredging device controlled by rock slag block degree of deep large ventilation shaft | |
JP3451275B2 (en) | Deep foundation excavator | |
CN211623326U (en) | Drilling equipment with spliced protective cylinder | |
CN113089654A (en) | Construction process of hole digging pile in complex soil layer and steel casing for construction | |
CN215475627U (en) | Reef explosion ship equipment for dredging engineering | |
CN116201161A (en) | Construction method of steel trestle foundation under complex geological conditions | |
CN114687356B (en) | Construction method for deep foundation pit excavation of building | |
CN109440801A (en) | A kind of reinforcement for pile foundation | |
JPS6133930B2 (en) | ||
CN118668644A (en) | Method for drilling and piling inclined rock face piles in sea-filled area | |
CN111101865A (en) | High efficiency drilling equipment | |
CN115627760A (en) | Underground pile body type barrier pulling-out construction method and system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20010305 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |