JP2000045675A - Service pipe laying method and device used in such method - Google Patents
Service pipe laying method and device used in such methodInfo
- Publication number
- JP2000045675A JP2000045675A JP10209502A JP20950298A JP2000045675A JP 2000045675 A JP2000045675 A JP 2000045675A JP 10209502 A JP10209502 A JP 10209502A JP 20950298 A JP20950298 A JP 20950298A JP 2000045675 A JP2000045675 A JP 2000045675A
- Authority
- JP
- Japan
- Prior art keywords
- pit
- casing
- pipe
- circular
- pavement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、ガス管、水道管、
下水管、更には電気、電話などの道路下の地下埋設管か
ら枝管を配管し、道路に沿った建築物にこれらの地下埋
設管を引き込む工事に関する。The present invention relates to a gas pipe, a water pipe,
The present invention relates to a construction in which branch pipes are laid from underground pipes under roads such as sewage pipes and electricity and telephones, and these underground pipes are drawn into a building along a road.
【0002】[0002]
【従来の技術】従来、道路の下に埋設された地下埋設管
から引込管や引込線を分岐させるには、舗装路面を回転
カッターで四角形に切断して徹去し、地下埋設物の上部
周囲の土砂を掘削排土し、土留を施して地下埋設物まで
掘削し、更に、配管のため引き込み個所まで道路を横断
方向に掘削しなければならなかった。2. Description of the Related Art Conventionally, in order to branch a service pipe or a service line from an underground pipe buried under a road, a pavement road surface is cut into a square with a rotary cutter and then exfoliated. The earth had to be excavated, excavated, laid and excavated to an underground burial, and the road had to be excavated transversely to the drop-in point for piping.
【0003】道路を横断方向に開削をせずに、曲線推進
機によってポリエチレン管を推進し、道路の地下埋設管
の埋設位置から目的個所まで推進する工法(特許第19
89217:特公平7−13433)などが提案されて
いる。しかし、この工法においても、推進のために構築
するピットは四角形であり、ピット構築の際に迅速な舗
装路面の切断撤去がおこなわれず、道路を長期間占有し
て道路交通に支障をきたすという問題があった。[0003] A construction method in which a polyethylene pipe is propelled by a curved propulsion machine without digging a road in a transverse direction, and the polyethylene pipe is propelled from a buried position of a buried pipe under a road to a target location (Patent No. 19).
89217: Japanese Patent Publication No. 7-13433). However, even with this method, the pits to be built for propulsion are square, and the pits are not cut and removed quickly during paving, which occupies the road for a long period of time and hinders road traffic. was there.
【0004】[0004]
【発明が解決しようとする課題】従来のピットの掘削工
法では、舗装路面の切断、土砂の掘削排土、さらには土
留を必要とするため工事完了までに2〜3日間を必要と
し、道路交通を制限する期間が比較的長く、円滑な交通
を妨げていた。In the conventional pit excavation method, cutting of the pavement road surface, excavation of earth and sand, and earth retaining are required, so that it takes two to three days to complete the construction. Restrictions on the period was relatively long, preventing smooth traffic.
【0005】そこで、本発明は、この欠点を克服し、舗
装路面の切断と掘削を短時間で完了するようにし、道路
交通を開放するまでの時間を短縮することを目的とす
る。更に、土留と掘削を同時におこないピット構築の時
間を短縮し短時間で掘削を完了し、道路の占有期間を短
縮し、加えて、埋め戻し後も舗装路盤の沈下が起きない
ようにすることを目標とする。Accordingly, an object of the present invention is to overcome this drawback, complete the cutting and digging of a pavement surface in a short time, and shorten the time required for opening road traffic. Furthermore, it is necessary to reduce the time required for pit construction by simultaneously performing earth retaining and excavation, complete excavation in a short time, shorten the occupation period of the road, and also ensure that the subsidence of the pavement will not occur even after backfilling. Target.
【0006】[0006]
【課題を解決するための手段】舗装路面を円形に切断し
て撤去し、円形のピットを構築し、このピットから曲線
推進機で曲線状に管を推進埋設することで、舗装路面の
切断撤去に要する時間を短縮するようにした。舗装路版
の下の土砂を掘削撤去するにあたり、掘削機にローラを
設けて掘削とケーシングの設置を同時におこない、更
に、引込管または引込線を設置完了後、ケーシングを撤
去して埋め戻しと舗装をおこない、道路の復旧を短時間
でおこなえるようにした。舗装路面に形成された円形穴
の縁を保護する保護リングを設置して舗装版の縁を保護
し、舗装路面に悪影響を与えないようにした。埋め戻し
工程においては、掘削土を穴内に戻し、掘削土と固結材
を穴内で混合して転圧することにより復旧後の路面沈下
を防止した。Means for Solving the Problems The pavement road surface is cut in a circular shape and removed, a circular pit is constructed, and a pipe is protruded and buried from the pit in a curved shape by a curved propulsion machine, thereby cutting and removing the pavement road surface. To reduce the time required. When excavating and removing the earth and sand under the pavement slab, the excavator is equipped with rollers to perform excavation and casing installation at the same time.Furthermore, after the installation of the drop pipe or drop line is completed, the casing is removed and backfilling and pavement are performed. The road was restored in a short time. A protection ring for protecting the edge of the circular hole formed on the pavement surface is provided to protect the edge of the pavement plate so that the pavement surface is not adversely affected. In the backfilling process, the excavated soil was returned into the hole, and the excavated soil and the consolidated material were mixed in the hole and rolled to prevent road surface settlement after restoration.
【0007】[0007]
【発明の実施の形態】図1は、本発明の概念図であり、
舗装道路の路面を円形に切断し、路版を撤去して設けた
円形のピット100内に、曲線推進機を設置し、方向を
制御しながらジャッキで曲進管を押し出す。曲進管は、
側溝102や塀103の下を潜り抜けて曲線状に穴10
1を形成し、引込管を設置する場所の地上に出現させ
る。曲線状の穴101が形成されるので、その穴内に必
要な管を引込み、水道、ガス管、または電話線、電力線
に接続できるようにする。FIG. 1 is a conceptual diagram of the present invention.
The road surface of the paved road is cut into a circle, and a curved propulsion device is installed in a circular pit 100 provided by removing the road slab, and a curved pipe is pushed out by a jack while controlling the direction. The curved tube is
Hole 10 in a curved shape passing under gutter 102 and fence 103
Form 1 and make it appear on the ground where the drop pipe is installed. Since the curved hole 101 is formed, necessary pipes are drawn into the hole so that it can be connected to a water supply, a gas pipe, or a telephone line or a power line.
【0008】図2〜図4は本発明に使用する曲線推進機
の一例の正面図、平面図、及び側面図であり、基本的構
造は従来公知のものである。水道管の枝管に、引込管を
家屋に設置する場合を例にして施工手順を説明する。FIGS. 2 to 4 are a front view, a plan view, and a side view of an example of a curved propulsion device used in the present invention. The basic structure is conventionally known. The construction procedure will be described by taking as an example a case where a service pipe is installed in a house as a branch pipe of a water pipe.
【0009】図5に示すように、まず、円形カッター2
で舗装路面1を切断する(A)。円形カッター2で切断
した舗装路版11の中心にドリルで穴をあけ、先端に拡
径部材を有する引き上げ具を舗装路版11に差込み、拡
径部材を拡張させて舗装路版に食い込ませ、クレーンで
引き上げて撤去する(B)。[0009] As shown in FIG.
To cut the pavement road surface 1 (A). Drill a hole in the center of the pavement slab 11 cut by the circular cutter 2, insert a lifting tool having a diameter-enlarging member at the tip into the pavement slab 11, expand the diameter-enlarging member and bite into the pavement slab, Lift up with a crane and remove (B).
【0010】舗装路版11を撤去して形成された穴に図
6に示すリング31の上縁にフランジ32を設けた保護
リング3を設置し、舗装路面1の縁が作業中に欠落する
のを防止する(C)。In the hole formed by removing the pavement road slab 11, a protection ring 3 provided with a flange 32 at the upper edge of the ring 31 shown in FIG. 6 is installed, and the edge of the pavement road surface 1 is cut off during work. (C).
【0011】そして、スクリューオーガ4で初期掘削を
おこなう。初期掘削では、路盤及び路床を掘削排土し、
ケーシング5を設置できる深さまでおこなう(D)。Then, initial excavation is performed by the screw auger 4. In the initial excavation, excavate and excavate the roadbed and subgrade,
This is performed to a depth where the casing 5 can be installed (D).
【0012】ケーシング5は、図7に示すように、下ケ
ーシング51と上ケーシング52からなり、図8に示す
ように突起61と継手穴を有する継手板62で接続し、
必要長さを得ることができる。上ケーシング52の上縁
には、フランジ53が補強リブと共に設けてあり、フラ
ンジ面にはローラが設けてある。スクリューオーガ4
は、加圧リング42がローラを介してケーシングを加圧
しながらケーシング内を掘削し、ケーシング5を沈設す
る。The casing 5 comprises a lower casing 51 and an upper casing 52 as shown in FIG. 7, and is connected by a projection 61 and a joint plate 62 having a joint hole as shown in FIG.
The required length can be obtained. A flange 53 is provided on the upper edge of the upper casing 52 together with a reinforcing rib, and a roller is provided on the flange surface. Screw auger 4
In this case, the inside of the casing is excavated while the pressure ring 42 presses the casing via the roller, and the casing 5 is sunk.
【0013】ある程度の深さになったら下ケーシング5
1に上ケーシング52を接続し、掘削を継続してケーシ
ング5を更に沈設する(E)。埋設されている水道管の
近辺まで掘削したら機械掘りを停止し、人力で水道管を
確認しながら掘削する。When it reaches a certain depth, the lower casing 5
1 and the upper casing 52 is connected, excavation is continued, and the casing 5 is further laid (E). When excavating to the vicinity of the buried water pipe, stop the machine digging and excavate while checking the water pipe manually.
【0014】ケーシングの沈設が終了したら、ケーシン
グ内に断面三日月型の反力板82と曲線推進機81を設
置する(F)。曲線推進機は、公知の推進ヘッド、屈曲
自在な曲進管、及び推進ジャッキとから構成され、推進
ヘッドの位置及び方向がモニタされるようになってお
り、推進ヘッドの方向を推進機本体側で制御して曲線状
に推進ヘッドを進め、目的の個所の地上に推進ヘッドを
向かわせることが可能である。After the sinking of the casing is completed, a reaction force plate 82 having a crescent cross section and a curve propulsion device 81 are installed in the casing (F). The curved propulsion device includes a known propulsion head, a bendable bending pipe, and a propulsion jack. The position and direction of the propulsion head are monitored. It is possible to advance the propulsion head in a curved shape by controlling the propulsion head, and to direct the propulsion head to the ground at a target location.
【0015】ケーシング5の下側、または、ケーシング
5に設けた開口から推進ヘッドを曲進管と共にジャッキ
で押し出し、推進ヘッドの方向を制御して目的位置に推
進する。目的の位置に推進ヘッドが到達して地上に現れ
たところで推進を完了する。推進ヘッドを曲進管から外
し、埋設するパイプを曲進管に接続し、発進ピット10
0側に曲進管を引き戻し、パイプを曲線状の穴101内
に設置する。A propulsion head is pushed out from a lower side of the casing 5 or an opening provided in the casing 5 together with a curved pipe with a jack, and the direction of the propulsion head is controlled to propell the vehicle to a target position. The propulsion is completed when the propulsion head reaches the target position and appears on the ground. The propulsion head is removed from the bend pipe, and the buried pipe is connected to the bend pipe.
The bent pipe is pulled back to the 0 side, and the pipe is set in the curved hole 101.
【0016】パイプは、埋設するものに応じて種々のも
のを用意しておく。水道管など単一の場合は断面が円形
とするが、電気、ガス、水道などを一度の工事で引込を
完了させ、複数のものを配設できるように、図9に示す
ように、パイプの断面が複数に仕切られているものを使
用する。Various pipes are prepared in accordance with the pipes to be buried. In the case of a single pipe such as a water pipe, the cross section is circular. However, as shown in FIG. Use a cross section that is divided into multiple sections.
【0017】引込管工事が終了したところで、曲線推進
機81をピット100から引き上げ、ケーシング5内に
掘削した土砂を埋め戻す。半分ほど埋め戻したら、セメ
ント系の固結材を穴に投入し、撹拌具7で埋め戻し土と
撹拌混合する(G)。撹拌具7は、中心軸から下側に向
かって放射状に複数のアームが取り付けてあり、アーム
の先端には撹拌翼が設けてある。埋め戻し土と固結材が
充分混合されたところで、埋め戻し土を転圧する。埋め
戻しと転圧は掘削深さが1.2メートル程度の場合で3
回程度に分割しておこなう。At the completion of the service pipe work, the curvilinear propulsion device 81 is lifted from the pit 100, and the excavated earth and sand is buried in the casing 5. After backfilling by about half, a cement-based consolidation material is put into the hole, and stirred and mixed with the backfilled soil by the stirring tool 7 (G). The stirrer 7 has a plurality of arms attached radially downward from the central axis, and a stirring blade is provided at the tip of the arm. When the backfill soil and the consolidation material are sufficiently mixed, the backfill soil is compacted. Backfill and compaction are 3 when the excavation depth is about 1.2m.
Divide about once.
【0018】ケーシング5を引き上げて撤去し、保護リ
ング3を取り外し、残りの埋め戻しをおこなう。路盤を
形成したら、急結コンクリートで舗装をおこない、養生
後交通開放する。The casing 5 is pulled up and removed, the protective ring 3 is removed, and the remaining backfill is performed. After the roadbed is formed, paving is performed with quick-setting concrete and traffic is released after curing.
【0019】[0019]
【発明の効果】舗装路面を円形カッターで切断撤去し、
円形のピットを構築することで、効率良く作業をおこな
え、工事期間が短縮され、交通に影響を与えることが少
ない。埋設する引込パイプを複数の断面を有する複合型
とすることにより、工事ごとに掘削を繰り返すことなく
一度で必要な工事を完了することができる。According to the present invention, the pavement is cut and removed with a circular cutter,
By constructing a circular pit, work can be performed efficiently, the construction period is shortened, and traffic is less affected. By using a composite pipe having a plurality of cross-sections, the necessary construction can be completed at once without repeating excavation for each construction.
【図1】 曲線推進の概念図。FIG. 1 is a conceptual diagram of curve propulsion.
【図2】 曲線推進機の正面図。FIG. 2 is a front view of the curved propulsion device.
【図3】 曲線推進機の平面図。FIG. 3 is a plan view of the curved propulsion device.
【図4】 曲線推進機の側面図。FIG. 4 is a side view of the curved propulsion device.
【図5】 円形ピット構築工程図。FIG. 5 is a process chart of a circular pit construction.
【図6】 保護リングの斜視図。FIG. 6 is a perspective view of a protection ring.
【図7】 ケーシングの説明図。FIG. 7 is an explanatory view of a casing.
【図8】 ケーシングの継手部の斜視図。FIG. 8 is a perspective view of a joint portion of a casing.
【図9】 仕切りのあるパイプの断面図。FIG. 9 is a sectional view of a pipe having a partition.
1…舗装路面 11…舗装路版 2…円形カッター 4…スクリューオーガ 5…ケーシング 7…撹拌具 81…曲線推進機 82…反力板 DESCRIPTION OF SYMBOLS 1 ... Pavement road surface 11 ... Pavement road slab 2 ... Circular cutter 4 ... Screw auger 5 ... Casing 7 ... Stirrer 81 ... Curve propulsion machine 82 ... Reaction plate
Claims (9)
ピットを構築し、 このピットから曲線推進機で曲線状
に埋設穴を設ける引込管配設工法。A pavement road is cut and removed in a circular shape, a circular pit is constructed, and a buried pipe is provided from the pit with a curved buried hole by a curved propulsion machine.
設して円形のピットを構築する引込管配設工法。2. A method according to claim 1, wherein a circular casing is sunk to form a circular pit.
らケーシングを設置する引込管配設工法。3. The method according to claim 2, wherein the casing is installed after the ground is initially excavated.
を介して掘削機でケーシングに圧力を加えながらケーシ
ング内を掘削する引込管配設工法。4. A method according to claim 2, wherein the casing is excavated while applying pressure to the casing by an excavator via a roller.
面の円形穴に保護リングを設置して舗装版の縁を保護す
る引込管配設工法。5. A method according to any one of claims 2 to 4, wherein a protection ring is provided in a circular hole on a pavement road surface to protect an edge of the pavement plate.
ングを複数接続する引込管配設工法。6. A drop-in pipe laying method according to claim 2, wherein a plurality of casings are connected.
る引込管が複数に分割された断面を有するものである引
込管配設工法。7. The drop-in pipe laying method according to claim 1, wherein the drop-in pipe to be provided has a cross section divided into a plurality of sections.
をピット内に戻し、掘削土と固結材をピット内で混合す
る引込管配設工法。8. A method according to claim 1, wherein the excavated soil is returned into the pit, and the excavated soil and the consolidated material are mixed in the pit.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP10209502A JP2000045675A (en) | 1998-07-24 | 1998-07-24 | Service pipe laying method and device used in such method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP10209502A JP2000045675A (en) | 1998-07-24 | 1998-07-24 | Service pipe laying method and device used in such method |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2000045675A true JP2000045675A (en) | 2000-02-15 |
Family
ID=16573873
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP10209502A Pending JP2000045675A (en) | 1998-07-24 | 1998-07-24 | Service pipe laying method and device used in such method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2000045675A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2006046324A1 (en) * | 2004-10-26 | 2006-05-04 | Shinnihon-Kogyo, Inc. | Method for laying buried matter |
JP2011026812A (en) * | 2009-07-23 | 2011-02-10 | Mano Kogyo Kk | Method for constructing service pipe |
CN113216985A (en) * | 2021-06-03 | 2021-08-06 | 中建安装集团南京建设有限公司 | Real-time intelligent monitoring system for long-distance curve jacking pipe |
-
1998
- 1998-07-24 JP JP10209502A patent/JP2000045675A/en active Pending
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2006046324A1 (en) * | 2004-10-26 | 2006-05-04 | Shinnihon-Kogyo, Inc. | Method for laying buried matter |
JP2009114852A (en) * | 2004-10-26 | 2009-05-28 | Shin Nihon Kogyo:Kk | Excavating construction method |
JP2011026812A (en) * | 2009-07-23 | 2011-02-10 | Mano Kogyo Kk | Method for constructing service pipe |
CN113216985A (en) * | 2021-06-03 | 2021-08-06 | 中建安装集团南京建设有限公司 | Real-time intelligent monitoring system for long-distance curve jacking pipe |
CN113216985B (en) * | 2021-06-03 | 2022-02-08 | 中建安装集团南京建设有限公司 | Real-time intelligent monitoring system for long-distance curve jacking pipe |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6944882B2 (en) | How to build an invert in an existing tunnel | |
JP2963972B2 (en) | Construction method for underground structures | |
JP2000045675A (en) | Service pipe laying method and device used in such method | |
JP3366580B2 (en) | How to install an invert in the bottom of an existing mountain tunnel | |
JP7566235B1 (en) | Ground improvement methods | |
CN113572082A (en) | Construction method for pre-burying upgraded and reformed cable in old community | |
KR100515684B1 (en) | Propulsion method of construction and the device for pipe piercing | |
JP4863311B2 (en) | Excavation method | |
KR20210002947A (en) | Two-side semicircle arch type leading pipe and structure of non-excavation type tunnel using thereof and method of constructing thereof | |
JP3581332B2 (en) | Earth retaining equipment and open-cutting method using it | |
JP2002138474A (en) | Method and device for cutting and pulling out existing pile | |
JP7323261B2 (en) | Retaining wall construction method using non-cutting method on slope | |
JPH10292410A (en) | Execution method for small-diameter shaft, connecting method for small-diameter shaft and buried pipe, and connecting method for buried pipe utilizing small-diameter shaft | |
KR102243585B1 (en) | Structure of constructing non-excavation type tunnel using steel pipe loof and leading pipe | |
CN107059839A (en) | A kind of construction method of armored concrete waveform sheet pile underground structure | |
JPH11324011A (en) | Method and device for excavating periphery of underground embedded material | |
Drennon | Pipe jacking: state-of-the-art | |
JPH02300584A (en) | Extinction method of useless buried pipe line | |
JP2004353372A (en) | Renewal construction method for old buried pipe | |
CN118441587A (en) | Frame bridge jacking method | |
CN118065430A (en) | Construction method and structure of immersed tube tunnel and shield tunnel | |
JP2003027885A (en) | Construction method for underground tunnel and underground tunnel | |
JP3418126B2 (en) | Excavation method under pavement | |
JPH11247591A (en) | Connection method of underground structure using jacking device | |
JPH06306887A (en) | Chain type ditching machine and pipe embedding method therewith |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
RD02 | Notification of acceptance of power of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7422 Effective date: 20050623 |