GB2296904A - Mooring ang Flowline System - Google Patents
Mooring ang Flowline System Download PDFInfo
- Publication number
- GB2296904A GB2296904A GB9504276A GB9504276A GB2296904A GB 2296904 A GB2296904 A GB 2296904A GB 9504276 A GB9504276 A GB 9504276A GB 9504276 A GB9504276 A GB 9504276A GB 2296904 A GB2296904 A GB 2296904A
- Authority
- GB
- United Kingdom
- Prior art keywords
- mooring
- flowline
- vessel
- tanker
- riser
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B22/00—Buoys
- B63B22/02—Buoys specially adapted for mooring a vessel
- B63B22/021—Buoys specially adapted for mooring a vessel and for transferring fluids, e.g. liquids
Landscapes
- Chemical & Material Sciences (AREA)
- Engineering & Computer Science (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Loading And Unloading Of Fuel Tanks Or Ships (AREA)
- Laying Of Electric Cables Or Lines Outside (AREA)
Description
1 1 "Moorincr and Flowline System11 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
17 18 19 20 21 22 23 24 25 2296904 This invention relates to a mooring and flowline system for use in floating petroleum production facilities. The system is particularly, but not exclusively, applicable to the mooring and loading of floating export storage in production wells or wells undergoing extended well testing.
Production from offshore wells was originally exported ashore by subsea pipeline, which requires a very large capital expenditure. More recently there has been a move to exploiting more marginal fields by the use of a floating production platform in conjunction with a floating storage facility from which oil is exported periodically by tanker. Commonly, the floating production facility has been provided by conversion of an existing tanker. Such arrangements have worked well, but there is a continuing need for a substantial reduction in installation costs in order to improve the economics of marginal field production, and in order to make extended well testing more economically feasible.
Tanker conversions used hitherto have required extensive conversion. In some cases a turret mooring 2 1 2 3 4 5 6 7 8 9 11 12 13 14 is 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 is used which includes a rotary oil flowline joint, and this requires major structural work on the tanker in addition to the complex mooring turret. In other cases, a flexible riser to the tanker has been used but has required large quick connect-disconnect (QCDC) valves with a physical size and weight requiring installation outboard of the tanker bow on a specially installed and relatively large structure.
An object of the present invention is to provide an improved mooring and flowline system which is simple and economical to install. It is also an object of the invention to provide a system which enables conventional tankers to be.used as floating storage with a minimum of structural alteration.
Accordingly, the present invention provides a mooring and flowline system for use in floating petroleum production facilities; the system comprising means for mooring a floating storage and/or production vessel to the seabed, and a flowline for connection to a producing well or facility; the mooring means comprising at least two anchors in the sea bed, a respective anchor riser extending from each of the anchors, each of the anchor risers having one end secured to its anchor and the other end secured to a common mooring node member, and mooring pendant means extending from the node member for connection, in use, to the vessel; the flowline comprising a seabed flowline extending from the direction of the well or facility into the vicinity of the mooring means, and a flexible riser flowline extending from the seabed flowline to the vessel; and in which the flexible riser flowline is a 3 2 3 4 6 7 8 9 11 12 13 14 is 16 17 18 19 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 1 continuous conduit without rotational couplings and has part of its length secured alongside at least part of the mooring pendant means.
Preferably, there are at least three anchors in an angular array, three anchors at mutual 120 spacings being particularly preferred.
The flowline riser is suitably held clear of the anchor risers and node member by providing a portion of the flowline riser with flotation and by tethering the same portion to restrict sideways movement.
Preferably also, there is no swivel between the anchors and the vessel; the node member may be a plain ring, shackle or plate.
The mooring pendant may comprise two parallel chains, one passing over each bow of the vessel.
Preferably, the vessel is a tanker.
In a particularly preferred form the invention, which allows a conventional tanker to be utilised as the storage vessel with a minimal amount of conversion, the parallel chains are brought inboard of the tanker to standard chain stoppers or to remotely controlled release stoppers, the flexible riser flowline is brought inboard of the tanker over a chute to have its inboard end lying along the tanker deck, and quick connect/disconnect valve means are located on the tanker deck between said flowline riser inboard end and a tank manifold of the tanker.
An embodiment of the invention will now be described, by way of example, with reference to the drawings, in 4 1 which:
2 3 4 6 7 8 9 11 12 13 14 16 17 18 19 20 21 Fig. 1 is a schematic side view of one embodiment of the invention in use with a storage tanker; Fig. 2 is a plan view corresponding to Fig. 1; Fig. 3 is a view similar to Fig. 1 but showing the system out of use with the storage tanker removed; Fig. 4 is a schematic side view of a tanker bow illustrating a suitable arrangement for use in present invention; Fig. 5 is a plan view corresponding to Fig. 4; Fig. 6 is a side view of a chute seen in Fig. 5; and Fig. 7 illustrates in more detail part of the oil line seen in Fig. 5.
Referring particularly to Figs. 1 and 2, a floating storage tanker 10 is anchored to the sea bed 12 by means of a three-leg anchor system comprising anchors 14a, 14b, 14c connected by risers 16a, 16b, 16c to a node 18, from which a mooring pendant 20 is secured to the tanker 10. The mooring is in the vicinity of a 22 floating production platform (FPF) (not seen in the 23 drawings) from which oil is transferred via a flowline.
24 26 27 28 29 30 31 32 33 34 35 36 The flowline comprises a seabed portion 22 and a flexible riser 24. The riser 24 has a mid portion which is provided with flotation collars 26 and is restrained by a tether 28 secured to a clump weight 30. As seen in Fig. 2, the mooring is set such that a 1200 angle may be presented towards the FPF with the flowline approaching along the bisector of this angle. This geometry, together with the flotation of the collars 26 and the restraint by the tether 28 maintains the riser 24 clear of conflict with the mooring node 18.
2 3 4 5 6 7 8 9 10 11 12 13 14 is 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 The upper part of the riser 24 is secured along the mooring pendant 20 by spaced double collars 32 and then taken aboard the tanker 10 via a chute assembly indicated at 34.
The anchors 14 may be any suitable form of conventional mooring anchor. Each of the anchor risers 16 has at least its on-bottom length constituted by chain. For water depths up to about 75 metres, the chain can be continuous to the node 18.
In greater water depths up to about 150 metres, it is preferred to have the on-bottom section of chain but the catenary section of wire. The use of wire has several advantages. Principally, it reduces the weight which has to be lifted when the tanker is connecting to the system, as is discussed more fully below. It also makes the departure angle of the riser 16 from the node 18 nearer the horizontal, which increases the horizontal stability of the system, and simplifies stowage on the vessel used to deploy the system. Where wire is used for the catenary section, it is desirable to have the final 30 metres or so nearest the node 18 of chain, to reduce the risk of kinking of the wire.
The node 18 may take any suitable form which connects together the three risers 16 and the pendant 20 with adequate mechanical strength. A suitably sized master ring may be used, or a triangular plate arrangement, together with conventional shackles. No swivel is incorporated in the node 18.
In some circumstances there may be an advantage in reducing the weight of the node and the catenary sections, and to this end buoyancy (not shown) may be incorporated in the.node 18 or in the anchor risers 16 1 2 3 4 6 7 8 9 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 6 adjacent the node 18.
In a typical installation, the tanker 10 is a segregated ballast tanker of 600,000 to 700,000 bbl capacity and the mooring is designed to hold the node 18 at a depth of 20 to 30 metres, and thus up to about 15 metres beneath the tanker hull. In these circumstances, the mooring pendant 22 will require to be of the order of 40 to 50 metres in length.
The preferred form for the mooring pendant 22 comprises a single largesize chain 36 extending from the node 18 and connected to a pair of chafe chains 38. For the same order of size of the tanker 10, it is suitable to use have the chains 38 of 76 mm size, which will fit the standard OCIMF recommended tongue-type bow stoppers fitted to most tankers of this size. This arrangement simplifies the node design and minimises modification to the tanker.
Referring to Figs 4 and 5, there is shown a suitable tanker bow installation which requires a minimum of modification from standard shipping practice. Each of the chains 38 is held by a tongue-type bow stopper 40 raised above the focIsle deck 42 on a seating 44. The incoming chain 38 passes through a fairlead 46 in the bow bulwark 48 aligned with the bow stopper 44, and the inboard end of the chain is passed to a winch windlass via a pedestal fairlead 50.
As will be seen from Figs 5 and 6 the chute 34 is simple structure providing an accurate guide on two axes for the flexible riser 24. It is not necessary to have any guidance for the riser 24 below bulwark level, since the riser will be spaced away from the remainder of the vessel's hull.by the considerable flare of the 7 1 2 3 4 5 6 7 8 9 10 11 12 13 14 is 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 focIsle bulwarks in relation to the lower part of the hull.
Fig. 5 also indicates the position on the focIsle deck of valve gear generally designated at 52. The valve gear 52 is shown in more detail in Fig. 7, in which it will be seen that the flexible riser 25 is connected to a deck line 54 via a spool piece 56, a manually operated ball valve 58, a breakaway coupling 60, first and second hydraulically operated ball valves 62 and 64 between which is located a hydraulically operated emergency release collar 66, and an emergency shutdown valve 68. The breakaway coupling 60 is suitably a Gall-Thomson coupling which has bolts which shear at a predetermined axial load, the chute 34 ensuring that the load on the coupling is always axial. The Gall-Thomson coupling also includes a double-acting disc valve which seals both sides of the coupling as the unit breaks apart. The manually operated ball valve 58 would be used to close the connection in normal disconnection routines. The hydraulically activated release system comprising the components 62, 64, 66 can be operated remotely, for example, from the bridge of the vessel, where it is decided to make an emergency disconnection of the tanker. The emergency shutdown valve 68 is included to provide shutdown of flow without disconnection and would normally be part of the tanker's equipment even if not located close to the release system.
The deck line 54 is most conveniently connected with the vessel tankage via the normal midships tank manifold, and thus the deck line 54 must extend from the bow area to the midships of the vessel. The line 54 can be provided in the form of steel tubing fixed to the conventional tube racking, or as a further length 8 1 2 3 4 5 6 7 8 9 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 of hose of the same nature as the riser 24.
The riser 24 must be a flexible hose with sufficient dynamic properties to accept movement of the ship's bow and movement of the touchdown point at the bottom of the catenary. A suitable hose is a fully bonded rubber hose, preferably Manuli hose of C or 8" size.
It will be appreciated from the foregoing description that the mooring arrangement of the present invention does not include a fluid swivel. There will therefore be a restriction on the number of turns the vessel can make, since turning full circle will effectively twist the fluid riser and the chafe chains round each other. Contrary to previous practice, the present inventors believe that this is not a real restriction in a floating production situation. It is believed that the weather patterns actually found in practice may make a vessel do complete turns, but there would be more than sufficient lighter weather periods when the vessel could be pulled back around to take a turn out.
It is currently accepted practice to have a tug on permanent standby in these situations. This is for three main reasons: emergency towing if the tanker suffers a power blackout, support for the tanker when connecting and disconnecting, and as a guard vessel to stop passing fishing and other craft from going between the rig and the tanker.
The mooring system of the present invention allows a large tug to be dispensed with as the standby vessel since the mooring system provides a redundant system in the event of a blackout, and the other roles could be filled by a much smaller vessel such as an AHTS (Anchor Handling/Tug/Supply) vessel.
9 1 2 3 4 5 6 7 8 9 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Because it uses standard anchors and anchor cable, a normal anchor handling tug vessel can install the system. Initially each anchor would be laid using DGPS to a 10 metre tolerance. This has been achieved in depths in excess of 500 metres so is not anticipated a problem in any depth of less than 150 metres, even without European DGPS accuracy.
Each anchor is laid in turn, the cables run back to a common point; each cable as it is laid is buoyed off on a pendant wire. Insurance tensioning of the system can be done using the bollard pull of the tug. When all three have been laid the anchor handler recovers all three cables over the stern roller. This requires a fairly large anchor handler with a winch of at least 250 tonne pull, and a bollard pull of about 150 tons. These are readily available in most areas of the world on the spot market. The node point is assembled and deployed over the side, lowering the node point to the seabed using the chafe chains, then their pendant wires, and finally polyprop rope. The main polyprop would then be buoyed off, a messenger attached and a marker buoy at the end of that.
When the tanker is coming on to location, the support vessel recovers the messenger, and passes it across to the tanker using a compressed air rocket gun. The tanker pulls in on the messengers, then the polyprop ropes, then the pendant wires, and starts to heave in the chafe chains, securing them in the bow stoppers. The windlasses to be used for this will require to be in good condition, and both to be operating at once. But the typical 40 tonne pull of ships windlasses should be more than sufficient for this application, as the node point is only being brought to about 25 or 30 metres below the surface, and hence 10 to 15 metres 1 2 3 4 5 6 7 8 9 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 below the ships hull.
In the event of disconnection, it is no different from a tanker disconnecting from a buoy: release the chafe chains from the bow stoppers, and lower them over the bow as the vessel moves away. The assistance of a support tug on site would make this operation feasible even in bad weather, by providing control of the bow and using the ship's main engines to keep slack on the chafe chains for releasing from the tongues.
Recovery of the system would be by chasing each of the anchor legs back to the anchor and lifting from that point; or alternatively to disconnect at the node point and heave in on the AHTS, working back to the anchor and lifting it up on deck.
It will be seen that the present invention provides a mooring and flowline system which is of a surprisingly simplified nature in comparison with conventional systems for similar purposes and which uses simple, conventional, and readily available components in the novel manner.
Although described with particular reference to the transfer of oil from a producing well to a storage vessel, the application is equally applicable to other situations involving a mooring and a flowline, for example for mooring a floating production vessel and exporting its production via the flowline to some other facility.
Other modifications may be made to the foregoing within the scope of the present invention.
1 A 1 2 3 4 5 6 7 8 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Claims (14)
1. A mooring and flowline system comprising:
means for mooring a floating storage and/or production vessel to the seabed, and a flowline for connection to a producing well or facility; the mooring means comprising at least two anchors in the sea bed, a respective anchor riser extending from each of the anchors, each of the anchor risers having one end secured to its anchor and the other end secured to a common mooring node member, and mooring pendant means extending from the node member for connection, in use, to the vessel; the flowline comprising a seabed flowline extending from the direction of the well or facility into the vicinity of the mooring means, and a flexible riser flowline extending from the seabed flowline to the vessel; and in which the flexible riser flowline is a continuous conduit without rotational couplings and has part of its length secured alongside at least part of the mooring pendant means.
2. A system according to claim 1, in which there are at least three anchors in an angular array.
3. A system according to claim 2, in which there are three anchors at mutual 1201 spacings.
4. A system according to any preceding claim, in which the riser flowline is of fully bonded reinforced rubber construction.
5. A system according to any preceding claim, in which a portion of the flowline riser is provided with 12, 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 flotation means, and in which a tether connects said portion to the seabed.
6. A system according to any preceding claim, in which there is no swivel between the anchors and the vessel.
7. A system according to claim 6, in which the node member comprises a plate or one or more plain rings or shackles.
8. A system according to any preceding claim, in which the mooring pendant comprises two parallel chains, one passing over each bow of the vessel.
9. A system according to claim 8, in which the vessel is a tanker.
10. A system according to claim 9, in which the parallel chains are brought inboard of the tanker to standard chain stoppers or to remotely controlled release stoppers.
11. A system according to claim 10, in which the flexible riser flowline is brought inboard of the tanker over a chute to have its inboard end lying along the tanker deck, and quick connect/disconnect valve means are located on the tanker deck between said flowline riser inboard end and a tank manifold of the tanker.
12. A system according to claim 11, in which said valve means includes a self-sealing breakaway coupling.
13. A vessel for use in the system of claim 1, the vessel including stopper means for releasably securing a mooring pendant, fairlead means for receiving the 1,5 mooring pendant from outboard and guiding it to said stopper means, a petroleum conduit terminating in quick connect/disconnect valve means, and a chute for receiving and guiding a flexible riser hose disposed, in use, between said valve means and a mooring pendant outboard of said fairlead means.
2 3 4 5 6 7 8 9 10 11 12 13 14 15
14. A vessel according to claim 13, said vessel being a tanker ship with said chute and valve means positioned on the focIsle of the ship, and in which the fairlead means comprises port and starboard fairleads for a twin chain pendant and said stopper means comprises a pair of tongue-type stoppers.
Priority Applications (6)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB9504276A GB2296904B (en) | 1995-03-03 | 1995-03-03 | Mooring and Flowline System |
DK96301381T DK0729882T3 (en) | 1995-03-03 | 1996-03-01 | Mooring and mains system |
DE69605696T DE69605696D1 (en) | 1995-03-03 | 1996-03-01 | Definition and transfer system |
NO19960847A NO313453B1 (en) | 1995-03-03 | 1996-03-01 | Mooring and connecting system |
EP19960301381 EP0729882B1 (en) | 1995-03-03 | 1996-03-01 | Mooring and flowline system |
GR20000400729T GR3033043T3 (en) | 1995-03-03 | 2000-03-23 | Mooring and flowline system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB9504276A GB2296904B (en) | 1995-03-03 | 1995-03-03 | Mooring and Flowline System |
Publications (5)
Publication Number | Publication Date |
---|---|
GB9504276D0 GB9504276D0 (en) | 1995-04-19 |
GB2296904A true GB2296904A (en) | 1996-07-17 |
GB2296904A8 GB2296904A8 (en) | 1996-07-21 |
GB2296904A9 GB2296904A9 (en) | 1996-07-21 |
GB2296904B GB2296904B (en) | 1996-12-18 |
Family
ID=10770576
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
GB9504276A Expired - Fee Related GB2296904B (en) | 1995-03-03 | 1995-03-03 | Mooring and Flowline System |
Country Status (6)
Country | Link |
---|---|
EP (1) | EP0729882B1 (en) |
DE (1) | DE69605696D1 (en) |
DK (1) | DK0729882T3 (en) |
GB (1) | GB2296904B (en) |
GR (1) | GR3033043T3 (en) |
NO (1) | NO313453B1 (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2311503A (en) * | 1996-03-28 | 1997-10-01 | Alcatel Kabel Norge As | Anchoring a cable or riser pipe |
GB2330157A (en) * | 1997-10-07 | 1999-04-14 | Bluewater Terminal Systems Nv | Riser system for connecting a seabed installation with a floating vessel |
GB2336143A (en) * | 1998-03-04 | 1999-10-13 | Victoria Oilfield Dev | Mooring system |
US6200180B1 (en) | 1998-09-01 | 2001-03-13 | Nortrans Offshore (S) Pte Ltd | Mooring system for tanker vessels |
GB2359054A (en) * | 2000-02-08 | 2001-08-15 | Brovig Rds Ltd | Mooring and flowline system |
US7690434B2 (en) | 2004-10-01 | 2010-04-06 | Stanwell Consulting Limited | Offshore vessel mooring and riser inboarding system |
WO2013027036A1 (en) | 2011-08-19 | 2013-02-28 | Axis Limited | Mooring system and connector assembly |
CN103738477A (en) * | 2014-01-26 | 2014-04-23 | 中国海洋石油总公司 | Method for replacing upper anchor cable of mooring anchor legs |
CN106089108A (en) * | 2016-06-30 | 2016-11-09 | 西南石油大学 | A kind of drain injection destroys the vortex-induced vibration suppression device around laminar boundary layer and method |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2387188B (en) * | 2002-04-04 | 2005-06-01 | Bluewater Terminal Systems Nv | Apparatus for attaching a fluid conduit to a structure |
US7793723B2 (en) | 2006-01-19 | 2010-09-14 | Single Buoy Moorings, Inc. | Submerged loading system |
NO341536B1 (en) * | 2016-02-23 | 2017-12-04 | Can Systems As | A marine riser and method for installation |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1492111A (en) * | 1974-01-14 | 1977-11-16 | Imodco | Automatic mooring system |
GB2173160A (en) * | 1985-04-05 | 1986-10-08 | Amtel Inc | Vessel mooring and hydrocarbon transfer system |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3466680A (en) * | 1967-07-14 | 1969-09-16 | Air Logistics Corp | Apparatus for loading and unloading offshore vessels |
GB1404775A (en) * | 1971-10-06 | 1975-09-03 | Exxon Production Research Co | Articulated riser |
NL7206986A (en) * | 1972-05-24 | 1973-11-27 | ||
FR2219053B3 (en) * | 1973-02-23 | 1976-02-20 | Cg Doris Fr | |
FR2534545A1 (en) * | 1982-10-18 | 1984-04-20 | Loire Rene | SIMPLIFIED SIMPLIFYING DEVICE FOR MOORING AND LOADING OR UNLOADING TANK VESSELS FROM AN UNDERWATER SUPPLY OR FLUID EXHAUST DUCT AND METHOD FOR ESTABLISHING UNDERWATER DRIVING AND UNDERWATER DRIVING SIMPLIFIED MOORING DEVICE |
EP0407662B2 (en) * | 1989-07-14 | 1999-06-23 | Single Buoy Moorings Inc. | Device for positioning of a buoy body |
-
1995
- 1995-03-03 GB GB9504276A patent/GB2296904B/en not_active Expired - Fee Related
-
1996
- 1996-03-01 DK DK96301381T patent/DK0729882T3/en active
- 1996-03-01 DE DE69605696T patent/DE69605696D1/en not_active Expired - Lifetime
- 1996-03-01 EP EP19960301381 patent/EP0729882B1/en not_active Expired - Lifetime
- 1996-03-01 NO NO19960847A patent/NO313453B1/en not_active IP Right Cessation
-
2000
- 2000-03-23 GR GR20000400729T patent/GR3033043T3/en not_active IP Right Cessation
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1492111A (en) * | 1974-01-14 | 1977-11-16 | Imodco | Automatic mooring system |
GB2173160A (en) * | 1985-04-05 | 1986-10-08 | Amtel Inc | Vessel mooring and hydrocarbon transfer system |
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2311503A (en) * | 1996-03-28 | 1997-10-01 | Alcatel Kabel Norge As | Anchoring a cable or riser pipe |
GB2311503B (en) * | 1996-03-28 | 2000-06-14 | Alcatel Kabel Norge As | Cable anchoring method and device |
GB2330157B (en) * | 1997-10-07 | 2001-11-07 | Bluewater Terminal Systems Nv | Riser system for connecting a seabed installation with a floating vessel |
GB2330157A (en) * | 1997-10-07 | 1999-04-14 | Bluewater Terminal Systems Nv | Riser system for connecting a seabed installation with a floating vessel |
US6109830A (en) * | 1997-10-07 | 2000-08-29 | Bluewater Terminal Systems N.V. | Riser system for connecting a seabed installation with a floating vessel |
GB2336143B (en) * | 1998-03-04 | 2002-03-13 | Victoria Oilfield Dev | Mooring system |
GB2336143A (en) * | 1998-03-04 | 1999-10-13 | Victoria Oilfield Dev | Mooring system |
US6200180B1 (en) | 1998-09-01 | 2001-03-13 | Nortrans Offshore (S) Pte Ltd | Mooring system for tanker vessels |
GB2359054A (en) * | 2000-02-08 | 2001-08-15 | Brovig Rds Ltd | Mooring and flowline system |
US6435124B1 (en) | 2000-02-08 | 2002-08-20 | Brovig Rds Limited | Mooring and flowline system |
GB2359054B (en) * | 2000-02-08 | 2003-04-02 | Brovig Rds Ltd | Mooring and flowline system |
US7690434B2 (en) | 2004-10-01 | 2010-04-06 | Stanwell Consulting Limited | Offshore vessel mooring and riser inboarding system |
WO2013027036A1 (en) | 2011-08-19 | 2013-02-28 | Axis Limited | Mooring system and connector assembly |
US9032892B2 (en) | 2011-08-19 | 2015-05-19 | Axis Energy Products Ltd. | Mooring system and connector assembly |
CN103738477A (en) * | 2014-01-26 | 2014-04-23 | 中国海洋石油总公司 | Method for replacing upper anchor cable of mooring anchor legs |
CN106089108A (en) * | 2016-06-30 | 2016-11-09 | 西南石油大学 | A kind of drain injection destroys the vortex-induced vibration suppression device around laminar boundary layer and method |
CN106089108B (en) * | 2016-06-30 | 2018-01-09 | 西南石油大学 | A kind of vortex-induced vibration suppression device and method for draining injection destruction around laminar boundary layer |
Also Published As
Publication number | Publication date |
---|---|
GB2296904B (en) | 1996-12-18 |
GB9504276D0 (en) | 1995-04-19 |
NO960847L (en) | 1996-09-04 |
EP0729882B1 (en) | 1999-12-22 |
EP0729882A1 (en) | 1996-09-04 |
NO960847D0 (en) | 1996-03-01 |
NO313453B1 (en) | 2002-10-07 |
GR3033043T3 (en) | 2000-08-31 |
GB2296904A8 (en) | 1996-07-21 |
DE69605696D1 (en) | 2000-01-27 |
GB2296904A9 (en) | 1996-07-21 |
DK0729882T3 (en) | 2000-06-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5944448A (en) | Oil field installation with mooring and flowline system | |
US6435124B1 (en) | Mooring and flowline system | |
EP1796958B1 (en) | Offshore vessel mooring and riser inboarding system | |
AU670236B2 (en) | A system for offshore loading/unloading of a flowable medium, especially oil | |
EP2744703B1 (en) | Mooring system and connector assembly | |
US6415828B1 (en) | Dual buoy single point mooring and fluid transfer system | |
JP2011520698A (en) | Separable turret mooring system with rotatable turntable | |
EP0729882B1 (en) | Mooring and flowline system | |
AU686328B2 (en) | A vessel for production and/or loading/unloading and transport of hydrocarbons from offshore fields, and/or for carrying out well operations | |
Rutkowski | A comparison between conventional buoy mooring CBM, single point mooring SPM and single anchor loading sal systems considering the hydro-meteorological condition limits for safe ship’s operation offshore | |
AU2010252013A1 (en) | Offshore structure and mooring arrangement | |
EP2398695B1 (en) | Deep water and ultra deep water mooring system | |
CN117622381A (en) | Oilfield development facility with mooring and streamline system | |
GB2459739A (en) | A counterbalanced cantilever connector assembly for a vessel | |
GB2123775A (en) | Mooring ships | |
Poranski et al. | The First Yoke Mooring For Avlcc In The Open Ocean | |
Bensimon et al. | Deepwater Installation of a Large Capacity FPSO with Large Number of Risers in the Marlim Field | |
GB2273694A (en) | Offshore loading system. | |
GB1564755A (en) | Marine riser mooring apparatus | |
IE44501B1 (en) | Marine riser mooring apparatus | |
AU2005203655A1 (en) | System for managing offshore drilled products |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
732E | Amendments to the register in respect of changes of name or changes affecting rights (sect. 32/1977) | ||
732E | Amendments to the register in respect of changes of name or changes affecting rights (sect. 32/1977) | ||
732E | Amendments to the register in respect of changes of name or changes affecting rights (sect. 32/1977) | ||
732E | Amendments to the register in respect of changes of name or changes affecting rights (sect. 32/1977) | ||
732E | Amendments to the register in respect of changes of name or changes affecting rights (sect. 32/1977) | ||
PCNP | Patent ceased through non-payment of renewal fee |
Effective date: 20140303 |