ES2297999A1 - Loading bay for industrial installations, has structure carrying mechanical or hydraulic units for lifting ramp, and flap support is provided on surface of vehicle, and hydraulic, mechanical or pneumatic units lifts flap support - Google Patents

Loading bay for industrial installations, has structure carrying mechanical or hydraulic units for lifting ramp, and flap support is provided on surface of vehicle, and hydraulic, mechanical or pneumatic units lifts flap support Download PDF

Info

Publication number
ES2297999A1
ES2297999A1 ES200502637A ES200502637A ES2297999A1 ES 2297999 A1 ES2297999 A1 ES 2297999A1 ES 200502637 A ES200502637 A ES 200502637A ES 200502637 A ES200502637 A ES 200502637A ES 2297999 A1 ES2297999 A1 ES 2297999A1
Authority
ES
Spain
Prior art keywords
flap
hydraulic
mechanical
industrial installations
vehicle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
ES200502637A
Other languages
Spanish (es)
Other versions
ES2297999B1 (en
Inventor
Jose Labrador Blasco
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to ES200502637A priority Critical patent/ES2297999B1/en
Publication of ES2297999A1 publication Critical patent/ES2297999A1/en
Application granted granted Critical
Publication of ES2297999B1 publication Critical patent/ES2297999B1/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G69/00Auxiliary measures taken, or devices used, in connection with loading or unloading
    • B65G69/28Loading ramps; Loading docks
    • B65G69/2805Loading ramps; Loading docks permanently installed on the dock
    • B65G69/2811Loading ramps; Loading docks permanently installed on the dock pivoting ramps
    • B65G69/2817Loading ramps; Loading docks permanently installed on the dock pivoting ramps with fluid-operated means
    • B65G69/2823Loading ramps; Loading docks permanently installed on the dock pivoting ramps with fluid-operated means extensible by pivoting parts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Auxiliary Methods And Devices For Loading And Unloading (AREA)

Abstract

The loading bay has a structure carrying mechanical or hydraulic units for lifting a ramp. A flap support is provided on the surface of a vehicle. The hydraulic, mechanical or pneumatic units lift the flap support. An articulation unit is provided between the ramp and the base. The flap includes a base that forms a stuffing wall and shuttering, which forms the floor of an industrial plant.

Description

Muelle de carga para instalaciones industriales.Loading dock for facilities Industrial

La presente invención consiste en un muelle de carga para instalaciones industriales que posee una estructura que permite una adecuada integración con la obra civil en la fase de construcción, y medios de ajuste adecuados para el correcto ajuste y posicionamiento en el proceso de carga descarga de camiones y furgonetas.The present invention consists of a spring of load for industrial facilities that has a structure that allows an adequate integration with the civil works in the phase of construction, and appropriate adjustment means for correct adjustment and positioning in the process of loading truck unloading and Vans

Antecedentes Background

Las naves industriales tienen en muchos casos en la zona de entrada y salida de mercancías muelles de carga integrados en la obra civil.Industrial warehouses have in many cases in the area of entry and exit of goods loading docks integrated into civil works.

Antiguamente el muelle de carga era simplemente una base de hormigón, sobre la cual se adosaba el vehículo que debía ser cargado o descargado, de modo que en el caso de producirse desniveles había que poner piezas añadidas, con riesgo para las personas y las mercancías en el caso de un desplazamiento, con el tiempo y esfuerzo de colocar la pieza o plataforma añadida y con el agravante de que la pieza supletoria comportaba un desnivel a superar en cada tránsito.Formerly the loading dock was simply a concrete base, on which the vehicle that it had to be loaded or unloaded, so that in the case of occur unevenly had to put added pieces, with risk for people and goods in the case of displacement, with the time and effort of placing the added part or platform and with the aggravating fact that the extra piece involved an unevenness to overcome in each transit.

Existen también muelles de carga, tal como el descrito por ES 1 050 679, en el que se define un muelle articulado que comprende una solapa de apoyo sobre la base de la caja de un camión, y que permite generar una rampa que se ajusta a la altura del vehículo.There are also loading docks, such as the described by ES 1 050 679, in which an articulated spring is defined comprising a support flap on the basis of the box of a truck, and that allows to generate a ramp that adjusts to the height vehicle.

Sin embargo, este muelle de carga debe ser instalado sobre un hueco previsto a tal efecto en la zona de carga, y no es útil para todos los vehículos ya que éstos tienen distintas anchuras.However, this loading dock must be installed on a space provided for this purpose in the loading area, and it is not useful for all vehicles since they have different widths

Es deseable, por tanto, un muelle de carga que permita adaptarse a la altura y anchura de cualquier vehículo de carga, tal como un camión o una furgoneta.It is desirable, therefore, a loading dock that allow to adapt to the height and width of any vehicle of cargo, such as a truck or van.

Resumen de la invenciónSummary of the Invention

Consiste la presente invención en un muelle de carga para ser instalado en obra en instalaciones industriales, comandado hidráulicamente, y provisto de pestaña de apoyo sobre la plataforma de carga de anchura múltiple selectiva en función de la anchura del vehículo.The present invention consists of a spring of load to be installed on site in industrial facilities, hydraulically commanded, and provided with a support tab on the selective multiple width loading platform depending on the vehicle width

Breve descripción de los dibujosBrief description of the drawings

Con objeto de ilustrar la explicación que va a seguir, adjuntamos a la presente memoria descriptiva cinco hojas de dibujos, que en seis figuras representan la esencia de la presente invención, y en las que:In order to illustrate the explanation that will follow, herewith five sheets of drawings, which in six figures represent the essence of the present invention, and in which:

La figura 1 muestra una vista en sección frontal del muelle de carga de la invención instalado sobre la obra civil;Figure 1 shows a front section view of the loading dock of the invention installed on site civil;

La figura 2 muestra una vista esquemática del muelle de carga de la invención, en la que se observa ha adquirido una posición inclinada;Figure 2 shows a schematic view of the loading dock of the invention, in which it is observed has acquired an inclined position;

La figura 3 muestra una vista esquemática de una sección del muelle de carga de la invención, con su extremo articulado a la altura del suelo de la nave, y cuyo extremo libre se sitúa sobre la plataforma de un vehículo de carga;Figure 3 shows a schematic view of a section of the loading dock of the invention, with its end articulated at the height of the floor of the ship, and whose free end is placed on the platform of a cargo vehicle;

La figura 4 muestra una vista esquemática en perspectiva del muelle de carga de la invención, en que se aprecia que dispone una solapa extrema articulada de apoyo sobre la superficie de carga, que está dividida en distintas secciones;Figure 4 shows a schematic view in perspective of the loading dock of the invention, in which it is appreciated which has an articulated extreme flap of support on the loading surface, which is divided into different sections;

La figura 5 muestra un detalle en la figura anterior en que se aprecia el modo de fijación de las secciones extremas sobre la sección central; yFigure 5 shows a detail in the figure previous in which the way of fixing the sections is appreciated extremes on the central section; Y

La figura 6 muestra un detalle visto desde la parte inferior del muelle, de la solapa extrema articulada sobre la plataforma que constituye la superficie principal articulada del muelle de carga, y el modo de fijación de las secciones extremas.Figure 6 shows a detail seen from the bottom of the spring, of the end flap articulated on the platform that constitutes the articulated main surface of the loading dock, and the way of fixing the sections extreme

Descripción detallada de la invenciónDetailed description of the invention

Conforme puede observarse en los dibujos, se describe un muelle de carga para instalaciones industriales donde se ubican zonas de carga y descarga con el exterior, que es susceptible de integrarse en obra durante la realización de la obra civil, y particularmente permite formar el borde o límite de la zona de encofrado. De acuerdo con la figura 1, puede observarse como el muelle 1 se dispone sobre el suelo de zona de carga de la nave industrial, se ajusta a la altura que debe tener el suelo mediante las patas de la estructura portante 9, y se rellena la base de un material de relleno 2, tal como escombros, piedras, u otras tierras, que servirá de base para la colocación de un encofrado que formará el suelo 3 de la zona de carga, con el muelle de carga integrado. Mediante la disposición de este muelle de carga se evita el realizar el ajuste del encofrado en dicha zona para una posterior colocación de un muelle añadido, evitando, por una parte costes de encofrado, y por otra costes de instalación del muelle.As can be seen in the drawings, it describes a loading dock for industrial facilities where loading and unloading areas are located outside, which is liable to integrate into work during the completion of the work civil, and particularly allows to form the edge or boundary of the area Formwork According to figure 1, it can be seen as the Pier 1 is arranged on the ground of the ship's cargo area industrial, adjusts to the height that the floor must have by the legs of the supporting structure 9, and the base of a filler material 2, such as debris, stones, or other land, which will serve as the basis for the placement of a formwork that will form the floor 3 of the loading area, with the integrated loading dock. By arranging this loading dock, it is avoided to perform formwork adjustment in said area for subsequent placement of an added spring, avoiding, on the one hand formwork costs, and  for other installation costs of the dock.

Visto de frente, el muelle 1 presenta dos cuerpos 4 y 5 cuya sección según un plano transversal frontal presenta la forma de dos rectángulos superpuestos, el inferior 5 de mayor anchura que el superior 4, quedando por tanto a ambos lados, sendas alas 6 formando oquedades interiores.Seen from the front, Pier 1 presents two bodies 4 and 5 whose section according to a frontal transverse plane it has the shape of two superimposed rectangles, the bottom 5 of wider than the upper 4, being therefore on both sides, 6 wing paths forming interior cavities.

La estructura portante se fija a las paredes externas del muelle mediante unas bridas de unión 10, repartidas adecuadamente. La disposición de la estructura portante 9 y las bridas 10 permite dar al muelle una solidez suficiente para ser cogida, por ejemplo, por un puente grúa, o mediante la pluma de un camión, ya que en ausencia de dicha estructura el muelle podría sufrir deterioros durante su transporte.The supporting structure is fixed to the walls external of the dock by means of connecting flanges 10, distributed adequately. The arrangement of the bearing structure 9 and the flanges 10 allows the spring to be solid enough to be caught, for example, by a crane bridge, or by the boom of a truck, since in the absence of said structure the pier could suffer damage during transport.

Las alas laterales 6 están rematadas en sendas paredes exteriores 13 y recubrimientos superiores 7. El cuerpo que forma el rectángulo superior comprende una cubierta o rampa 8, que está articulada en uno de sus extremos junto al suelo 3 de la nave por medio de una articulación 16.Side wings 6 are topped on paths outer walls 13 and top coatings 7. The body that form the upper rectangle comprises a deck or ramp 8, which It is articulated at one of its ends next to the floor 3 of the ship by means of a joint 16.

Para evitar todo posible acceso a la zona articulada y consecuentemente posibles daños personales o a las cosas, se disponen lateralmente en el cuerpo superior unas paredes 11 solidarias a la parte fija del muelle 1, y otras paredes 12 solidarias al cuerpo articulado que comprende la superficie de tránsito 8, y con ella una solapa de apoyo 15. Puesto que en altos grados de elevación persiste un hueco entre las paredes móvil 12 y fija 11, se dispone una pared adicional 14 que empezará a elevarse solamente cuando el extremo inferior anterior (la zona libre) de la pared móvil 12 vaya a comenzar a separarse del ángulo anterior inferior de la pared 11.To avoid all possible access to the area articulated and consequently possible personal injury or damage to things, some walls are arranged laterally in the upper body 11 in solidarity with the fixed part of pier 1, and other walls 12 solidarity with the articulated body that includes the surface of transit 8, and with it a support flap 15. Since in high degrees of elevation a gap persists between the movable walls 12 and fixed 11, there is an additional wall 14 that will begin to rise only when the lower front end (the free zone) of the moving wall 12 will start to separate from the previous angle bottom of the wall 11.

La estructura del muelle comprende unos medios de accionamiento hidráulico 19, que pudieran también ser neumáticos o mecánicos, que en su extensión empujan hacia arriba el extremo anterior de la superficie 8 de tránsito, siendo este extremo anterior el que soporta una solapa 15 articulada mediante una articulación 28 a la plataforma elevable, siendo dicho extremo anterior el que ha de apoyar sobre la plataforma de carga 27 del vehículo. La articulación tiene lugar por la parte inferior de ambas piezas, mediante uniones a la solapa 25 y a la plataforma 25.The structure of the spring comprises means hydraulic drive 19, which could also be pneumatic or mechanics, which in their extension push up the end front of the traffic surface 8, this end being anterior which supports a flap 15 articulated by a joint 28 to the lifting platform, said end being previous the one that has to support on the loading platform 27 of the vehicle. The articulation takes place at the bottom of both pieces, by means of connections to the flap 25 and the platform 25.

Cuando la plataforma del muelle se eleva, se produce simultáneamente una elevación del extremo colgante de la solapa 15, mediante el pistón 17, de modo que dicha plataforma queda sobreelevada respecto al vehículo, para liberar posteriormente la presión del pistón de elevación 19 de la plataforma mientras que el de la solapa 17 la mantiene, y así bajar y ajustar perfectamente sobre la superficie de carga 27 del vehículo. La articulación de la solapa 15 se realiza mediante el empuje y retracción del pistón 17 sobre una prolongación 29 que emerge por debajo de dicha solapa, y la cual se mantiene extendida durante el descenso de la plataforma para ajustarse al vehículo.When the dock platform rises, it simultaneously produces an elevation of the hanging end of the flap 15, by means of piston 17, so that said platform it is raised above the vehicle, to release subsequently the pressure of the lifting piston 19 of the platform while the flap 17 keeps it, and thus lower and fit perfectly on the loading surface 27 of the vehicle. The flap 15 is articulated by means of the thrust and retraction of piston 17 over an extension 29 which emerges below said flap, and which remains extended during the descent of the platform to fit the vehicle.

La solapa de apoyo 15, presenta preferentemente unas divisiones laterales 20, que permiten mediante una fijación temporal 21 quedar unidas a dicha porción central 15 en su movimiento de elevación o descenso, o separarse de ella mediante un empuje o pequeño golpe manual, de modo que queden colgando retraídas sometidas a la acción de la gravedad. Ello permite que cuando la plataforma de un cierto vehículo sea de menor anchura que la totalidad, sean retirados uno o dos de los lados y poder apoyar la plataforma sin más inconvenientes.The support flap 15, preferably presents lateral divisions 20, which allow by fixing temporary 21 being attached to said central portion 15 in its lifting or lowering movement, or be separated from it by a push or small manual punch, so that they are hanging back  subjected to the action of gravity. This allows when the platform of a certain vehicle is smaller than the all, be removed one or two of the sides and be able to support the platform without further inconvenience.

Como una solución particular del medio de fijación, se dispone un cuerpo 22 que aloja un medio elástico tal como un muelle, provisto en su extremo de una bola o taco deslizante 23. La acción elástica de la bola se realiza contra una pieza 26 dispuesta en el extremo liberable 20 (o viceversa) de la solapa 15, que mediante el empuje de dicho extremo supera la acción elástica de la bola 23 y muelle o similar, no quedando sujetado por el pistón neumático 17.As a particular solution of the means of fixing, a body 22 is provided that houses an elastic means such like a spring, provided at its end with a ball or block slide 23. The elastic action of the ball is performed against a piece 26 arranged at the releasable end 20 (or vice versa) of the flap 15, which by pushing said end overcomes the action elastic of the ball 23 and spring or the like, not being held by the pneumatic piston 17.

Es de aplicación en la fabricación de muelles de carga naves industriales.It is applicable in the manufacture of springs of Load industrial buildings.

Claims (6)

1. Muelle de carga para instalaciones industriales, que comprende una estructura portadora de medios hidráulicos (19), mecánicos o neumáticos para la elevación de una rampa (8), una solapa de apoyo (15) sobre la superficie de un vehículo (27), medios hidráulicos (17), mecánicos o neumáticos para la elevación de la solapa de apoyo (15), y medios de articulación (16) entre la base y la rampa (8) y (28) entre la rampa (8) y la solapa (15), caracterizado por comprender una base que conforma la pared de relleno (2) y encofrado (3) que conforma el suelo de la instalación
industrial.
1. Loading dock for industrial installations, comprising a structure that carries hydraulic (19), mechanical or pneumatic means for lifting a ramp (8), a support flap (15) on the surface of a vehicle (27) , hydraulic (17), mechanical or pneumatic means for lifting the support flap (15), and articulation means (16) between the base and the ramp (8) and (28) between the ramp (8) and the flap (15), characterized by comprising a base that forms the filling wall (2) and formwork (3) that forms the floor of the installation
industrial.
2. Muelle de carga para instalaciones industriales, según la reivindicación 1, caracterizado porque según un plano de corte transversal comprende dos zonas rectangulares, una superior (4) y una inferior (5) siendo la inferior (5) de mayor anchura que la superior (4), y definiendo sendos huecos (6) a cada uno de los lados de dicha zona rectangular inferior (5).2. Loading dock for industrial installations according to claim 1, characterized in that according to a cross-sectional plane it comprises two rectangular areas, one upper (4) and one lower (5) being the lower (5) wider than the upper (4), and defining two holes (6) on each side of said lower rectangular area (5). 3. Muelle de carga para instalaciones industriales, según cualquiera de las reivindicaciones 1 y 2, caracterizado porque está soportado sobre una estructura portante (9), provista de bridas de unión (10) con las paredes (7, 13) que forman dicho muelle.3. Loading dock for industrial installations, according to any of claims 1 and 2, characterized in that it is supported on a supporting structure (9), provided with connecting flanges (10) with the walls (7, 13) forming said spring . 4. Muelle de carga para instalaciones industriales, según cualquiera de las reivindicaciones 1 a 3, caracterizado porque la solapa (15) de apoyo sobre la superficie del vehículo (27) está dividida en secciones, al menos una de ellas (15) vinculada a los medios hidráulicos (17), mecánicos o neumáticos de accionamiento de dicha solapa (15), y las secciones accesorias (20) vinculadas a la solapa principal (15) o a otra solapa accesoria (20) por medios elásticos susceptibles de liberación.4. Loading dock for industrial installations according to any one of claims 1 to 3, characterized in that the support flap (15) on the surface of the vehicle (27) is divided into sections, at least one of them (15) linked to the hydraulic (17), mechanical or pneumatic actuating means of said flap (15), and the accessory sections (20) linked to the main flap (15) or another accessory flap (20) by elastic means capable of releasing. 5. Muelle de carga para instalaciones industriales, según la reivindicación 4, caracterizado porque las secciones accesorias (20) de la solapa (15) son dos y están situadas a ambos lados de dicha solapa central (15).5. Loading dock for industrial installations according to claim 4, characterized in that the accessory sections (20) of the flap (15) are two and are located on both sides of said central flap (15). 6. Muelle de carga para instalaciones industriales, según cualquiera de las reivindicaciones 4 o 5, caracterizado porque los medios elásticos comprenden al menos una pieza retráctil tal como una bola (23) contra la acción de un muelle dispuesto en un alojamiento (22), y al menos una pieza de retención (26) en la posición de fijación.6. Loading dock for industrial installations according to any of claims 4 or 5, characterized in that the elastic means comprise at least one retractable piece such as a ball (23) against the action of a spring disposed in a housing (22), and at least one retaining part (26) in the fixing position.
ES200502637A 2005-10-28 2005-10-28 LOAD SPRING FOR INDUSTRIAL FACILITIES. Withdrawn - After Issue ES2297999B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
ES200502637A ES2297999B1 (en) 2005-10-28 2005-10-28 LOAD SPRING FOR INDUSTRIAL FACILITIES.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
ES200502637A ES2297999B1 (en) 2005-10-28 2005-10-28 LOAD SPRING FOR INDUSTRIAL FACILITIES.

Publications (2)

Publication Number Publication Date
ES2297999A1 true ES2297999A1 (en) 2008-05-01
ES2297999B1 ES2297999B1 (en) 2009-03-16

Family

ID=39316080

Family Applications (1)

Application Number Title Priority Date Filing Date
ES200502637A Withdrawn - After Issue ES2297999B1 (en) 2005-10-28 2005-10-28 LOAD SPRING FOR INDUSTRIAL FACILITIES.

Country Status (1)

Country Link
ES (1) ES2297999B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL2022895B1 (en) * 2019-04-08 2020-10-15 Stertil Bv Dock leveler with adjustable side-elements, docking station and distribution center provided therewith and method there for

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4364137A (en) * 1980-10-31 1982-12-21 Rite-Hite Corporation Releasable locking device
WO1998046506A1 (en) * 1997-04-15 1998-10-22 Rite-Hite Holding Corporation Safety leg system for dock leveler
US6405397B1 (en) * 2001-05-21 2002-06-18 United Dominion Industries Loading dock with segmented wide lip
EP1231171A1 (en) * 2001-02-13 2002-08-14 Benno Drössler GmbH & Co, Bauunternehmung KG Loading bridge
WO2002098773A1 (en) * 2001-06-05 2002-12-12 Campisa S.R.L. Integral formwork system for the construction of pits for loading ramps

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4364137A (en) * 1980-10-31 1982-12-21 Rite-Hite Corporation Releasable locking device
WO1998046506A1 (en) * 1997-04-15 1998-10-22 Rite-Hite Holding Corporation Safety leg system for dock leveler
EP1231171A1 (en) * 2001-02-13 2002-08-14 Benno Drössler GmbH & Co, Bauunternehmung KG Loading bridge
US6405397B1 (en) * 2001-05-21 2002-06-18 United Dominion Industries Loading dock with segmented wide lip
WO2002098773A1 (en) * 2001-06-05 2002-12-12 Campisa S.R.L. Integral formwork system for the construction of pits for loading ramps

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL2022895B1 (en) * 2019-04-08 2020-10-15 Stertil Bv Dock leveler with adjustable side-elements, docking station and distribution center provided therewith and method there for

Also Published As

Publication number Publication date
ES2297999B1 (en) 2009-03-16

Similar Documents

Publication Publication Date Title
ES2392717T3 (en) Vehicles and trailers that incorporate mobile platforms for cargo transport
US9950881B2 (en) Robotic trailer loading device with telescoping robot
ES2352410T3 (en) INSTALLATION TO TRANSPORT LOAD TO AND / OR FROM A VESSEL.
ES2713511T3 (en) Transport wagon with height compensation interface with respect to the ground and this mainly depending on the weight of the load to be transported
ES2646554T3 (en) Multi-level cargo container
CN104875659B (en) Breech lock locking system for the cargo compartment of truck lift installation
ES2938211T3 (en) transport platform
KR20150102097A (en) Method and device in lifting a car/truck carrying deck panel aboard a multi deck pure car/truck carrier (pctc)
US20120141241A1 (en) Mechanical Handling Apparatus
CN104875660A (en) Truck Body With Rapid Load/unload Cargo Pods
ES2380998T3 (en) Modular heavy-duty motor vehicle for lifting and transporting in an erect way a foundation of a wind power installation
ES2654685T3 (en) A pit cover for vehicle inspection
ES2297999B1 (en) LOAD SPRING FOR INDUSTRIAL FACILITIES.
ES2885973T3 (en) Convertible vehicle for the transport of goods
ES2629618T3 (en) Lifting device for loading / unloading products
WO2011123965A1 (en) Apparatus for moving loads on slip sheets
PT2377801E (en) Method of serving a complex including two and more mobile wharf boom cranes
ES2477841B1 (en) Cargo platform for vehicles
ES2235496T3 (en) DEVICE FOR HANDLING OF BOARDS AND SUPPORT PLATFORM FOR USE IN A SIZE DEVICE.
CN207498010U (en) A kind of mobile hoistable platform
US20190047804A1 (en) Truck well barrier system
ES2289864B1 (en) CONVERTIBLE CONTAINER IN CAMPAIGN HOSPITAL.
ES2372101B1 (en) LOAD AND UNLOAD SYSTEM FOR CONTAINERS AND TRUCKS.
ES2775519A1 (en) Track system with intercom nodes arranged vertically and vehicles with a double support system running through them (Machine-translation by Google Translate, not legally binding)
ES2378968B1 (en) CONTAINER PLATFORM.

Legal Events

Date Code Title Description
EC2A Search report published

Date of ref document: 20080501

Kind code of ref document: A1

FG2A Definitive protection

Ref document number: 2297999B1

Country of ref document: ES

FA2A Application withdrawn

Effective date: 20091019