EP0731863B1 - Procede et dispositif servant a renover des voies ferrees de chemin de fer - Google Patents
Procede et dispositif servant a renover des voies ferrees de chemin de fer Download PDFInfo
- Publication number
- EP0731863B1 EP0731863B1 EP95900633A EP95900633A EP0731863B1 EP 0731863 B1 EP0731863 B1 EP 0731863B1 EP 95900633 A EP95900633 A EP 95900633A EP 95900633 A EP95900633 A EP 95900633A EP 0731863 B1 EP0731863 B1 EP 0731863B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- gaugers
- trench
- frame
- follower
- knife
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000000034 method Methods 0.000 title claims description 13
- 238000009434 installation Methods 0.000 title claims description 6
- 210000000078 claw Anatomy 0.000 claims description 23
- 238000010276 construction Methods 0.000 claims description 11
- 239000000463 material Substances 0.000 claims description 9
- 239000004576 sand Substances 0.000 claims description 6
- 239000013590 bulk material Substances 0.000 claims description 4
- 239000004927 clay Substances 0.000 claims description 3
- 238000006073 displacement reaction Methods 0.000 claims description 3
- 230000006835 compression Effects 0.000 claims 5
- 238000007906 compression Methods 0.000 claims 5
- 238000000605 extraction Methods 0.000 claims 2
- 230000000284 resting effect Effects 0.000 abstract description 3
- 238000009418 renovation Methods 0.000 description 11
- 238000009412 basement excavation Methods 0.000 description 5
- 238000012937 correction Methods 0.000 description 4
- 238000009415 formwork Methods 0.000 description 4
- 238000003801 milling Methods 0.000 description 4
- 239000002689 soil Substances 0.000 description 3
- 239000004566 building material Substances 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 238000005065 mining Methods 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 230000001154 acute effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 230000000052 comparative effect Effects 0.000 description 1
- 238000000280 densification Methods 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 238000009499 grossing Methods 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000000750 progressive effect Effects 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 238000009419 refurbishment Methods 0.000 description 1
- 238000005067 remediation Methods 0.000 description 1
- 238000012958 reprocessing Methods 0.000 description 1
- 230000005641 tunneling Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
- E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
- E02D17/086—Travelling trench shores
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B27/00—Placing, renewing, working, cleaning, or taking-up the ballast, with or without concurrent work on the track; Devices therefor; Packing sleepers
- E01B27/06—Renewing or cleaning the ballast in situ, with or without concurrent work on the track
- E01B27/08—Renewing or cleaning the ballast in situ, with or without concurrent work on the track the track having been taken-up
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F5/00—Dredgers or soil-shifting machines for special purposes
Definitions
- the invention relates to a method for the rehabilitation of railway track systems, in particular multi-track track systems, whereby clearing the track substructure of the old track an in its progressive trench with trench side wall protection in which the material for the creation is created of the track bed of the new track. Furthermore, the Invention on a useful device for implementation of the procedure.
- the knife can be installed consist of a leading knife shield, its jacking knife provided with articulated trailing knives are who are supported and guided on a trailing frame and secure the trench in the pipe laying area.
- the trailer frame can also be connected to the support frame of the flow knife shield Pull cylinder in the direction of advance of the trench be moved forward.
- the trenching can be done by means of a boring device arranged in the leading blade shield (DE-A 34 43 282, DE-A 26 58 349, DE-B 28 10 386, DE-A 26 22 671).
- DE-U-9211801 describes a device for exchanging soil material especially known alongside traffic routes and buildings, the one formwork arrangement with two parallel, at a distance held vertical formwork walls that after Type of knife installation by ramming and / or in a previous one excavated excavation pit can be brought into the ground. Between the formwork walls is in this known device plate-shaped abutment arranged over adjustment cylinders is coupled to the formwork walls and thus their propulsion allowed in the ground.
- This known device can in particular next to traffic routes, for example next to train tracks to find a soil exchange there.
- Knife shields whose main area of application is tunneling, are due to their frictional engagement between the jacking knives and the principle of work based so far on the trench walls only used as a knife shoring for trenching if, as with pipe laying work, trenches of proportionate great depth must be created.
- the primary object of the invention is a method and a To create facility with which the aforementioned Track repair work technically flawless and reliable with have high rates of progress.
- the method according to the invention is used for the renovation of Track systems of the sliding knife shoring, for this purpose has not been considered so far and due to the comparative given in this application shallow trench depths for this application also not without offers more.
- high rates of progress can be achieved when refurbishing track systems to reach.
- the sliding knife shoring enables the excavated trench to be reliably secured on a sufficiently large working distance and also enables one Curving in line with the course of the track. in the The trench excavation work can protect the knife shoring the work for the creation of the new track bed is reliable and be carried out quickly.
- the support of the support frame of the knife shoring on the bottom of the trench via the floor knife leads to a desirable smoothing and densification of the trench bottom and favors the operation of the knife shoring in Prepressing the jacking knife and also when catching up on the support frame.
- With the help of the attached pressure or equalization bar can the trench bottom before inserting the new bedding be equalized.
- its support frame forms a lead frame to which by means of hydraulic Pulling cylinder a trailing frame is coupled to which the side knives with articulated, preferably universal joints Support and guide the trailing knives connected to them.
- the trailing frame is placed on floor knives or on hinged to the bottom knives of the lead frame Trailing floor knives supported and smoothly retightened.
- the trench in the head area of the knife shoring can be excavated with With the help of a wheel excavator or with the help of one on the support frame the dismantling device.
- the renovation work while maintaining rail traffic on the neighboring track reliably and quickly with high progress speeds perform, being a reliable Support of the track bed of the neighboring track serving the rail traffic remains preserved and with the slope of the bottom of the trench good drainage of the new track bed is ensured.
- the side knives show the knife shoring expediently has a considerably greater length than the floor knife, such that both the front and the floor knives protrude from the back of the support frame and thus the trench side walls both in the area of the trench excavation as well as in the area of installing the new track bed to back up.
- the ground knives are conveniently spaced apart arranged to each other so that they are essentially the trench bottom cover the entire surface, making it suitable for the Operation of the knife shoring result in favorable friction conditions and on the other hand the bottom of the trench through which thereon supporting floor knife is largely leveled.
- the support frame of the knife shoring provided according to the invention is expediently carried out so that it is not or only insignificantly protrudes upwards from the trench. Can on the support frame the necessary pump units for the supply of the hydraulic consumers and other devices stored will. Otherwise, as mentioned, the knife shoring is preferred designed so that its support frame is a lead frame forms a trailing frame with the hydraulic pulling cylinder is coupled so that this after moving the support frame one step with the help of the pulling cylinder can be made up.
- the knife shoring is preferred designed so that its support frame is a lead frame forms a trailing frame with the hydraulic pulling cylinder is coupled so that this after moving the support frame one step with the help of the pulling cylinder can be made up.
- Side knives connected in joints that are supported and guided laterally on the trailing frame.
- the Joints are preferably designed as universal joints, so that the trailing knife both around a vertical swivel axis also around one running in the direction of the transverse axis of the trench Axis are pivotally connected to the feed knives.
- Trailing frame can have a significantly shorter overall length than the support or lead frame placed in front of him. It recommends itself, on the outer floor knives trailing floor knives in joints connect, on which the trailing frame slides, whereby also catching up on the trailer frame when the trailer frame is stationary is facilitated.
- the trailing knives of the side knives are Conveniently designed so that they are on the back of the trailing frame protrude into the open trench and thus the Secure the trench space for the introduction of the new track bed.
- Support frame of the knife shoring against the trench bottom preferably hydraulic, adjustable claws or the like arranged, expediently on the back of the support or lead frame and both sides of the frame axis.
- the claws exist preferably made of claw plates on the bottom Spikes or the like wear and the height adjustable on the support frame be arranged, the height adjustment and their contact pressure expediently against the trench bottom by means of hydraulic adjusting cylinders he follows. With the help of this claw claws the support or lead frame is anchored to the bottom of the trench, so that the proper pre-pressing of the jacking knife With the help of the knife cylinder even at low trench heights and accordingly low height of the sliding knife shoring reliably is guaranteed.
- the claw claws can also be used for side control of the knife shoring.
- the one with the support frame or with the trailing frame via a shift cylinder coupled leveling bar is used for leveling or leveling the bottom of the trench before building the building materials of the new track bed can be placed in the trench.
- the pressure and leveling bar is appropriately designed so that it leads on the side knives or the trailing knives.
- Knife shoring while maintaining a reliable support of the Trench wall to the neighboring track on which the rail traffic is maintained during the renovation work take different measures.
- This can be done as in Knife shields known per se, by appropriate control the feed movements of the side knives reach such that when pre-pressing the outer side knife of the support frame slight canting in the trench and therefore on the side inner side knives (or the inner Side knife) due to its guidance on the support frame assumes a certain inclination towards the trench wall.
- the control can also be done by one-sided clawing of the support or lead frame with the help of the claw claw concerned or claw plate can be reached.
- the support frame slightly conical such that it tapers conically towards its back so that it is a certain inclination to the trench axis towards the inner one Trench wall can occupy.
- the end of the inner knife or knives with Wedge cutting or wedge shoes to be equipped in such a way are that with the pre-pressing or the side knives under Exploiting the play in the knife guides an adjusting movement towards the inner trench wall.
- the support frame can also be supported over the pressure and equalization bar in its position are stabilized, this bar e.g. on the material that has already been introduced and compacted in the trench can support the new track bed.
- the advance can also of the support frame in the working direction through the Thrust piston gear associated with pressure and equalization bars get supported.
- FIG. 1 a double track to be renovated Track 1 with track 2 recognize which of the maintenance of rail transport during the implementation of the renovation work on the neighboring track running parallel to it serves, which with its track superstructure already in the area of Implementation of the renovation work is removed.
- the one from the Rails 3 and the sleepers 4 of the track 2 existing track superstructure rests in the usual way on the track substructure by a compacted rock bed 5 is formed, which in turn can rest on a compacted sand bed.
- Out Fig. 1 can be seen that the track bed 5 on the sole below is inclined outwards (to the left) at a small angle so that the track bed is drained to this side.
- the entire track substructure is used if necessary cleared up into the grown soil, whereby a trench 6 is dug out with the help of an excavator can happen, of which in Fig. 3 only on the excavator boom arranged excavator bucket 7 is shown.
- a trench 6 is dug out with the help of an excavator can happen, of which in Fig. 3 only on the excavator boom arranged excavator bucket 7 is shown.
- the trench 6 excavated so that its trench bottom 8 to the Track 2 facing away from you, i.e. towards the outside for the Drainage of the newly built track bed is inclined.
- the inner side wall of the trench 6 is in the upper area through the compacted ballast bed 5 of the neighboring track 2 educated.
- the direction of work when carrying out the renovation work or the direction in which the trench 6 in the course of Remediation work is excavated in Fig. 2 by the Arrow A indicated.
- the trench 6 is secured in the respective renovation area with the help of a sliding knife sheath 9.
- the parallel bottom knife 13 form between the two Trench walls a substantially full coverage of the Trench sole 8.
- the flat frame part 11 of the support frame 10 has upstanding fixed side parts 14 on both sides, which form the two U-legs of the U-shaped support frame and on which in each case a side knife 15 in a knife guide 12 is led.
- the knife guides 12 exist, as with knife shields known from T-slot guides.
- Each bottom knife 13 and side knife 15 is in each case at least one knife cylinder 16 in the shown Embodiment (Fig. 1) assigned a pair of knife cylinders.
- the knife cylinders 16 consist of double-acting hydraulic Cylinders. 3, they are in Joints 17 on the one hand on the support frame 10 and on the other hand on the associated Knife 13 or 15 connected.
- the knife cylinder 16 can therefore the bottom knife and the side knife 15 individually independently or in groups opposite the standing support frame 10 in the working direction acc.
- the support frame 10 of the sliding knife shoring forms one Lead frame, with the 18 hydraulic pull cylinder Trailing frame 19 is coupled, which in Fig. 2 only on the one side of the trench axis X is shown, but to the trench axis X is symmetrical.
- the trailing frame 19 is accordingly on both sides of the trench axis X, which is aligned with the longitudinal axis of the Knife shoring coincides, each via a hydraulic Pull cylinder 18 connected to the support and lead frame 10.
- the two pulling cylinders 18 also suitably exist made of double-acting hydraulic cylinders. It is recognizable that the trailing frame 19 has a shorter overall length as the support or lead frame 10. Also shows in particular Fig.
- FIG. 2 that at the rear ends of the side knife 15 knife extensions in the form of so-called trailing knives 20 are connected in joints 21, preferably after Kind of universal joints are designed such that joint movements between the knives 15 and the trailing knives 20 both in the vertical direction and in the lateral direction are possible.
- the Trailing knife 20 lead in knife guides 12 of the trailing frame 19. Accordingly, the side knives 15 and their articulated connected trailing knife 20 both on the support or Leading frame 10 and laterally supported on the trailing frame 19 and can be moved with play in the direction of advance (arrow A) guided. From Fig. 2 it can be seen that the side knife 15th protrude from the front of the support or lead frame 10 and consequently the trench walls in the front work space 22 where the trench 6 is excavated, supported. In addition, Fig.
- FIG. 2 shows that the trailing knife connected to the side knives 15 20 on the rear (against the direction of arrow A) over the trailing frame 19 protrude and thus the trench walls in one Secure the rear work area 23 in which the new track bed is established. Furthermore, Fig. 2 shows that the side knife 15 under Including their trailing knife 20 a much larger one Have length than the bottom knife 13, their length essentially the overall length of the support or lead frame plus the Stroke of the knife cylinder 16 corresponds. Only on the two outer floor knives on the side of the two trench walls 13 is in each case a trailing ground knife in a joint 24 25 connected swiveling, which is also on supports the trench bottom 8.
- the two parallel trailing ground knives 25 form a sliding support for the trailing frame 19, which is thus slidably supported on the caster blades 25 is.
- the trailing floor knife 25 ends in front of the rear work area 23, so that here the trench bottom 8 over the entire trench width is exposed.
- the two claw claws or claw plates 26 are each vertically movable on the support or lead frame 10 stored so that they can with the help of a hydraulic Setting cylinder 28 pressed against the trench bottom 8 for clawing or be lifted from this working position in which they have no contact with the bottom of the trench.
- the claw claws or claw plates 26 each height-adjustable in a vertical guide on the support or Lead frame 10 stored and using the jack 28 actuatable. In the claw position, the support or Lead frame 10 by the claws 26 in position stabilized so that the jacking knives 13, 15 with the help allow the knife cylinder to advance in working direction A without that the support or lead frame 20 is undesirable in the Trench 6 pushes back.
- FIG. 2 and 3 show, is behind the trailing frame 19th of the knife shoring in the trench a pressure and leveling bar 29 arranged, with the help of which the trench bottom 8 is smoothed or can be equalized before the new track bed in the work room 23 is introduced.
- the pressure and leveling bar 29 forms in Dig the frontal boundary of the work area 23. He points towards the support or lead frame 10 pointing lugs 30 on which he each have a double-acting hydraulic shift cylinder 31 on the support and lead frame 10 is connected so that it is with the support and lead frame standing 10 using the shift cylinder 31 in both Directions can be moved over the bottom of the trench to the Equalize trench bottom.
- Fig. 2 shows that the Pressure and leveling bar 29 on its two opposite Pages at 32 leads laterally on the trailing knives 20 and that the trailing knife 20 is also supported here Can find pressure and equalization bars.
- the side knives 15 together or individually one after the other in the pre-pressing direction A by the stroke of the Knife cylinder 16 pre-pressed, whereupon the bottom knife 13 with Using the knife cylinder 16 assigned to them individually or are also pre-pressed in groups in the pre-pressing direction A.
- the bottom knives 13 and the side knives move 15 with their trailing knives 20 on the lead frame or support frame 10 and on the trailing frame 19.
- the leading or supporting frame 10 is here by lowering the claws 26 against the trench sole 8 stabilized in its position.
- the new track substructure or the new track bed introduced while securing the trench walls in the work room 23.
- a thin one can first be placed on the smooth bottom 8 of the trench Cover, e.g. a fleece, a layer of clay or the like.
- 33 (Fig. 3) be applied as a waterproof layer on which then a sand bed 34 is applied, e.g. by means of a Vibrating plate, a roller or the like. is compressed.
- a gravel bed can then be applied to the sand bed are, which is also compressed in the usual way and to which the track superstructure of the new track is then applied.
- the sliding knife shoring can be from a control station 35 on Control support or lead frame 10 forth. Are on this frame there are also pump units 36 and 37 for the supply of the various hydraulic thrust piston transmissions of the sliding knife shoring. Also located on the frame 10 a tank 38 which holds the hydraulic fluid for tracking the Pump units and the thrust piston gearbox.
- the knife shoring shown in FIGS. 4 and 5 differs of that according to FIGS. 1 to 3 essentially only because that the trench excavation in the front work space 22 with With the help of a mining device mounted on the support or lead frame 10 39 takes place, two in the exemplary embodiment shown Has coaxial driven milling drums 30 which on one common pivot arm 41 are mounted vertically, which in turn in a pivot bearing 42 on the support or lead frame 10 is mounted with a horizontal pivot axis, the height pivoting by means of at least one hydraulic swivel cylinder 43 takes place.
- the drive of the milling drums 40 is 44 designated, the one on their roller shell with milling tools equipped transport spiral 45 have the dissolved material feed a center conveyor 46 that it from the work area of the trench, e.g.
- the shipment of the bulk material released from the rotating milling drums 40 on the overburden conveyor 46 can be driven by means of driven loading arms 47 take place on both sides of the receiving end of the overburden conveyor 46 rotatable behind a mining device 39 on a loading ramp are stored,
- brackets 26 for example such that only one of the two brackets 26 is in the bracing so that the support frame 10th influence with the help of the different working cylinders in its position leaves.
- front End of the side knife 5 'supporting the side slope 15 to arrange a wedge shoe 15 '(Fig. 2) during the pre-pressing this or this side knife as part of the knife guides given game a slight inclination of the knife in In the sense of a course correction of the knife shoring.
- the support frame 10 slightly conical, such that it tapers conically towards the rear so that the frame in the trench 6 is slightly opposite the trench axis X. can be inclined to carry out the aforementioned control movement.
- the side knives in their knife guides with a play in the transverse direction of the trench to shift, so that e.g. with the help of small hydraulic Control cylinder the position of the side knives opposite the support frame can be changed to perform tax corrections.
- the pressure and Equalization bar 29 is supported as an abutment in the trench 6 be so that its shift cylinder 31 to the ancestor of the Support or lead frame 10 can be used or the Support frame or lead frame 10 when pressing the jacking knives via the shift cylinder 31 and the pressure and leveling bar 29 can be supported to the rear.
- the support the pressure and equalization bar 29 can also be on one Implement, e.g.
- Another design feature of the invention is the printing and equalization bar 29 or the like via locking elements.
- on the two trailing floor knives 25 can be set so that it Ancesting the support or lead sign 10 in the working direction A can form the mentioned abutment.
- the floor knife 13 and / or the trailing floor knife 25 can on their underside with claw elements, e.g. Spikes, so that them by the support weight of the trailing frame 19 in the Trench sole 8 are pressed and thus the feed movement of the Favor support or lead frame 10 in working direction A.
- claw elements e.g. Spikes
- These spikes are expediently designed as helical teeth so that the feed movement of the floor knife in the working direction A not significantly hamper, but their return movement prevent when moving up the support or lead frame 10.
- trailing frame 19 trains so that he braced or set in the trench 6 leaves.
- This can be arranged with the help of a trailing frame 19 Claw device, e.g. according to the claw claws 26.
- On the arranged on the support or lead frame Claw claws 26 can in this case under certain circumstances also be dispensed with.
- Clamping devices e.g. hydraulic clamping cylinder units provided with the help of the trailing knife 20 against the Have the trench walls pressed on. With the help of these clamping devices the trailing frame 19 also has an abutment function when driving of the lead label.
- his pull cylinder 18 for advancing the support or lead frame 10 in Working direction A can be used.
- Fig. 1 shows that on both sides of the support or lead frame 10 only a single side knife 15 is provided is. The width (height) of these side knives 15 corresponds approximately the depth of the trench 6.
- Fig. 1 shows that the entire Support or lead frame with the knives arranged on it 13, 15 inclined according to the inclination of the trench bottom 8 is and that the side knife 15 against the vertical under mounted at an acute angle on the support or lead frame 10 and are led.
Landscapes
- Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Architecture (AREA)
- Paleontology (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Mechanical Engineering (AREA)
- Machines For Laying And Maintaining Railways (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
- Blast Furnaces (AREA)
- Train Traffic Observation, Control, And Security (AREA)
- Harvester Elements (AREA)
- Sewage (AREA)
- Near-Field Transmission Systems (AREA)
- Soil Working Implements (AREA)
Claims (19)
- Procédé de réfection des installations de voies ferrées, en particulier des installations à plusieurs voies, selon lequel, en procédant à l'évacuation de l'infrastructure de l'ancienne voie, on creuse une tranchée (6) progressant en suivant son parcours, dans lequel est déposé le matériau pour la mise en place du lit de la nouvelle voie, dans lequel pour assurer la tranchée (6), est utilisé un dispositif porte-lames (9) glissant, ayant des lames de sol (13) reposant sur le fond (8) de la tranchée et ayant des lames latérales servant à la sécurité des parois latérales (15), et les lames de sol et les lames latérales (13, 15), guidées sur un cadre d'appui (10) du dispositif porte-lames (9) glissant, étant précomprimées au moyen de vérins porte-lames (16) disposés entre-elles et le cadre d'appui, avant que le cadre d'appui (10) soit déplacé à la suite, et, dans lequel en outre, derrière le dispositif porte-lames (9) glissant, au moyen d'une poutre de pressage et d'égalisation (19) couplée à celui-ci de façon mobile, on procède à l'égalisation du fond (8) de la tranchée, avec une inclinaison par rapport au côté arrière de la tranchée, et, à l'abri du dispositif porte-lames (9) dans la zone des extrémités arrières des lames latérales, sont déposés les matériaux destinés à constituer le nouveau lit de voie de manière que, dans l'espace de travail arrière (23) du dispositif porte-lames (9) glissant, à titre de nouveau lit de voie, sur le fond de tranchée soient déposés, un revêtement (33) constitué par exemple d'une couverture, d'une couche d'argile ou analogue et, sur celui-ci, une couche compactée de sable (34) et, enfin, sur celle-ci une couche compactée de ballast.
- Procédé selon la revendication 1, caractérisé en ce qu'est utilisé un dispositif porte-lames en plusieurs parties, susceptible d'être commandé en direction, dont le cadre d'appui (10) constitue un cadre avant, auquel est rattaché, par l'intermédiaire de vérins hydrauliques de rappel par traction (18), un cadre arrière (19), destiné au guidage de lames suiveuses (20) raccordées de façon articulée aux lames latérales (15), le cadre arrière (19) étant tracté à l'arrière, en glissant sur les lames de sol, respectivement les lames suiveuses de sol (25) y étant raccordées de façon articulée.
- Procédé selon la revendication 1 ou 2, caractérisé en ce que l'avancement de la tranchée est effectué au moyen d'un appareil de creusement (39) disposé sur le cadre d'appui (10).
- Dispositif pour la réfection des installations de voies ferrées, en particulier des installations à plusieurs voies, avec un dispositif porte-lames (9) glissant, suivant le parcours de l'ancienne voie, qui assure la tranchée (6) creusée de façon progressive sur son parcours par évacuation de l'infrastructure de l'ancienne voie, et qui est pourvu de lames de sol et de lames latérales (13, 15) guidées sur son cadre d'appui (10) et de vérins porte-lames (16) associés, prenant appui sur le cadre d'appui, de sorte que le cadre d'appui (10) présente une section transversale sensiblement en forme de U, dont la partie cadre (11) plate, constituant la barre du U, présente en face inférieure des guidages (12) de lames destinés aux lames de sol (13) et dont les parties latérales (14), constituant les branches du U, dépassant de la partie cadre plate (11), présentent des guidages (12) destinés aux lames latérales (15), et que, en outre, dans un espace de travail arrière (23), se trouvant derrière le cadre d'appui (10) ou bien derrière un cadre arrière (19), est disposée, pour la mise en place du nouveau lit de voie, une poutre de pressage et d'égalisation (29), déplaçable sur le fond (8) de la tranchée et couplée au cadre d'appui par l'intermédiaire de vérins de déplacement (31) hydrauliques.
- Dispositif selon la revendication 4, caractérisé en ce que le cadre d'appui (10) du dispositif porte-lames (9) glissant constitue un cadre avant, à l'aide duquel, par l'intermédiaire de vérins hydrauliques de rappel par traction (18) est couplé un cadre arrière (19), et en ce qu'aux lames latérales (15), guidées sur le cadre avant, sont raccordées dans des articulations (21), de préférence des articulations à la cardan des lames suiveuses (20) qui se guident sur le cadre arrière (19).
- Dispositif selon la revendication 5, caractérisé en ce qu'aux lames de sol (13) extérieures sont raccordées dans des articulations (24) des lames suiveuses de sol (25), sur lesquelles prend appui le cadre arrière (19).
- Dispositif selon l'une des revendications 4 à 6, caractérisé en ce que les lames latérales (15) ont une longueur supérieure à celles des lames de fond (13), de sorte qu'elles dépassent à l'avant et à l'arrière du cadre d'appui (10) et des lames de sol.
- Dispositif selon l'une des revendications 4 à 7, caractérisé en ce que sur le cadre d'appui (10) est disposé un appareil de creusement (39), de préférence pouvant pivoter en hauteur, pour creuser la tranchée conjointement avec un transporteur d'évacuation (46).
- Dispositif selon l'une des revendications 4 à 8, caractérisé en ce que des griffes de cramponnement (26), pouvant être calées contre le fond (8) de la tranchée, sont disposées sur le cadre d'appui (10) et/ou sur le cadre arrière (19).
- Dispositif selon l'une des revendications 4 à 9, caractérisé en ce que la poutre de pressage et d'égalisation (29) peut prendre appui, pour constituer un contre-appui dans la tranchée (6), par exemple contre le matériau en vrac compacté déposé dans l'espace de travail (23) arrière, ou bien contre un appareil de travail, par exemple contre une plaque vibrante ou analogue, pour le compactage du matériau en vrac.
- Dispositif selon l'une des revendications 4 à 10, caractérisé en ce que la poutre de pressage et d'égalisation (29) est pourvue de moyens de serrage, par exemple d'ensembles de vérins de serrage, pour produire un serrage contre les lames suiveuses (20), respectivement pour presser les lames suiveuses (20) contre les parois de la tranchée.
- Dispositif selon l'une des revendications 4 à 11, caractérisé en ce que les lames latérales (15) ont une largeur correspondant à peu près à la profondeur de la tranchée.
- Dispositif selon l'une des revendications 5 à 12, caractérisé en ce que les lames suiveuses (20) des lames latérales (15) ressortent à l'arrière du cadre arrière (19) et assurent à cet endroit l'espace de travail (23), pour le dépôt du nouveau lit de voie.
- Dispositif selon l'une des revendications 4 à 13, caractérisé en ce qu'au moins une partie des lames latérales (15) présente, à l'extrémité la plus avant de la lame un tranchant (15'), en forme de coin.
- Dispositif selon l'une des revendications 4 à 14, caractérisé en ce que la poutre de pressage et d'égalisation (29) se guide sur les lames latérales, respectivement sur leurs lames suiveuses (20).
- Dispositif selon l'une des revendications 4 à 15, caractérisé en ce que le cadre d'appui (10) va en s'effilant de façon conique vers sa face arrière.
- Dispositif selon l'une des revendications 4 à 16, caractérisé en ce que les lames latérales (15), respectivement leurs lames suiveuses (20), peuvent être calées angulairement avec intervention de force contre la paroi latérale de la tranchée.
- Dispositif selon l'une des revendications 5 à 17, caractérisé en ce que le cadre arrière (19) est équipé de moyens de serrage agissant contre les lames suiveuses (20), par exemple des ensembles à cylindre de serrage, dans le but d'effectuer un serrage dans la tranchée, respectivement pour assurer le pressage des lames suiveuses (20) contre la paroi de la tranchée.
- Dispositif selon l'une des revendications 4 à 18, caractérisé en ce que les lames de sol (13) et/ou les lames suiveuses de sol (25) peuvent être mis en cramponnement sur le fond (8) de la tranchée au moyen d'éléments de cramponnement tels que, surtout, des crampons antidérapants.
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE4341418A DE4341418A1 (de) | 1993-12-04 | 1993-12-04 | Verfahren und Einrichtung zur Sanierung von Eisenbahn-Gleisanlagen |
DE4341418 | 1993-12-04 | ||
PCT/DE1994/001353 WO1995015418A1 (fr) | 1993-12-04 | 1994-11-11 | Procede et dispositif servant a renover des voies ferrees de chemin de fer |
Publications (2)
Publication Number | Publication Date |
---|---|
EP0731863A1 EP0731863A1 (fr) | 1996-09-18 |
EP0731863B1 true EP0731863B1 (fr) | 1998-09-23 |
Family
ID=6504215
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP95900633A Expired - Lifetime EP0731863B1 (fr) | 1993-12-04 | 1994-11-11 | Procede et dispositif servant a renover des voies ferrees de chemin de fer |
Country Status (9)
Country | Link |
---|---|
US (1) | US5802744A (fr) |
EP (1) | EP0731863B1 (fr) |
AT (1) | ATE171496T1 (fr) |
CZ (1) | CZ160596A3 (fr) |
DE (1) | DE4341418A1 (fr) |
HU (1) | HU214851B (fr) |
PL (1) | PL175743B1 (fr) |
SK (1) | SK70996A3 (fr) |
WO (1) | WO1995015418A1 (fr) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE19547511A1 (de) * | 1995-12-19 | 1997-06-26 | Weiss Gmbh & Co Leonhard | Verfahren und Einrichtung zur Aufbereitung des Unterbaus eines Eisenbahngleises |
EP0786558A1 (fr) | 1996-01-25 | 1997-07-30 | LEONHARD WEISS GmbH & Co. NIEDERLASSUNG CRAILSHEIM | Appareillage mobile le reconditionnement de déblais d'une voie ferrée |
DE19650443A1 (de) * | 1996-01-25 | 1997-07-31 | Weiss Gmbh & Co Leonhard | Mobile Aufbereitungseinrichtung für Bodenaushub bei einem Bahngleis |
DE19718733A1 (de) * | 1997-05-02 | 1998-11-05 | Gepro Ing Gmbh | Mittelkernverbau für Bahnanlagen |
DE19833522A1 (de) * | 1998-07-25 | 2000-01-27 | Weiss Gmbh & Co Leonhard | Verfahren zur Sanierung und/oder Strukturverbesserung eines Bodenbereiches |
DE102007038461B4 (de) * | 2007-08-14 | 2013-06-13 | Rail.One Gmbh | Verfahren zur Sanierung einer Schienenfahrbahn und zugehörige Schienenfahrbahn |
AT513824B1 (de) * | 2013-02-25 | 2014-08-15 | Plasser Bahnbaumasch Franz | Maschine zur Reinigung von Schotter eines Gleises |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE9211801U1 (de) * | 1992-09-02 | 1992-11-05 | Josef Möbius Bau-Gesellschaft (GmbH & Co), 2000 Hamburg | Vorrichtung zum Austausch von Bodenmaterial, insbesondere neben Verkehrswegen und Bauwerken |
Family Cites Families (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3750409A (en) * | 1972-08-08 | 1973-08-07 | L Orfei | Self-propelled trench-shoring apparatus |
US3967396A (en) * | 1974-09-23 | 1976-07-06 | Canron, Inc. | Undercutter with rotary trencher |
FR2316379A1 (fr) * | 1975-07-02 | 1977-01-28 | Secmafer Sa | Degarnisseuse pour voies ferrees |
AT340985B (de) * | 1976-02-02 | 1978-01-10 | Plasser Bahnbaumasch Franz | Einrichtung zum verlegen oder abschnittsweisen auswechseln eines gleises |
DE2622671C2 (de) * | 1976-05-21 | 1985-03-14 | Gewerkschaft Eisenhütte Westfalia, 4670 Lünen | Einrichtungen zum Vortrieb eines Grabens im offenen Verbau für die Rohrverlegung |
DE2658349A1 (de) * | 1976-12-23 | 1978-06-29 | Gewerk Eisenhuette Westfalia | Verfahren und einrichtung zum vortrieb eines offenen grabens, insbesondere fuer die rohrverlegung im erdboden |
DE2810386C2 (de) * | 1978-03-10 | 1979-11-15 | Friedrich Wilhelm 4230 Wesel Paurat | Vorrichtung zum Vortrieb von Gräben |
DE3117898A1 (de) * | 1980-07-24 | 1982-03-04 | Franz Plasser Bahnbaumaschinen-Industriegesellschaft mbH, 1010 Wien | Fahrbare anlage und verfahren zur gleisunterbau-sanierung |
DE3443282A1 (de) * | 1984-11-28 | 1986-05-28 | Gewerkschaft Eisenhütte Westfalia, 4670 Lünen | Gleitender messerverbau fuer den leitungsgrabenbau |
US5109775A (en) * | 1990-09-28 | 1992-05-05 | Knox Kershaw, Inc. | Ballast reconditioning apparatus with multiple excavating wheels and independent cleaning stations for increased operating speed |
-
1993
- 1993-12-04 DE DE4341418A patent/DE4341418A1/de not_active Withdrawn
-
1994
- 1994-11-11 EP EP95900633A patent/EP0731863B1/fr not_active Expired - Lifetime
- 1994-11-11 CZ CZ961605A patent/CZ160596A3/cs unknown
- 1994-11-11 WO PCT/DE1994/001353 patent/WO1995015418A1/fr not_active Application Discontinuation
- 1994-11-11 PL PL94314836A patent/PL175743B1/pl unknown
- 1994-11-11 AT AT95900633T patent/ATE171496T1/de active
- 1994-11-11 SK SK709-96A patent/SK70996A3/sk unknown
- 1994-11-11 HU HU9601510A patent/HU214851B/hu not_active IP Right Cessation
- 1994-11-11 US US08/649,607 patent/US5802744A/en not_active Expired - Fee Related
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE9211801U1 (de) * | 1992-09-02 | 1992-11-05 | Josef Möbius Bau-Gesellschaft (GmbH & Co), 2000 Hamburg | Vorrichtung zum Austausch von Bodenmaterial, insbesondere neben Verkehrswegen und Bauwerken |
Also Published As
Publication number | Publication date |
---|---|
PL314836A1 (en) | 1996-09-30 |
SK70996A3 (en) | 1998-04-08 |
ATE171496T1 (de) | 1998-10-15 |
WO1995015418A1 (fr) | 1995-06-08 |
US5802744A (en) | 1998-09-08 |
PL175743B1 (pl) | 1999-02-26 |
EP0731863A1 (fr) | 1996-09-18 |
DE4341418A1 (de) | 1995-06-08 |
HUT75282A (en) | 1997-05-28 |
CZ160596A3 (en) | 1996-12-11 |
HU214851B (hu) | 1998-06-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE68912167T2 (de) | Verfahren und Gerät zum Erweitern von Tunneln. | |
EP0771909B1 (fr) | Machine pour le démontage d'une ancienne voie ferrée et l'installation d'une nouvelle voie | |
EP0731863B1 (fr) | Procede et dispositif servant a renover des voies ferrees de chemin de fer | |
EP0585657B1 (fr) | Procédé et dispositif pour le remplacement du sol, particulièrement à proximité de routes et de bâtiments | |
DE2519210A1 (de) | Verfahren und einrichtung zum rohrverlegen in einem mittels eines verbauschildes vorgetriebenen offenen graben | |
EP0206371B1 (fr) | Tête de coupe pour le percement de conduits en béton préfabriqués pour la construction de galeries ou tunnels | |
DE2135577A1 (de) | Kanalgrabenverbau- und bodeneinbaugeraet | |
AT511199B1 (de) | Schildvortriebsvorrichtung | |
EP0103706A1 (fr) | Dispositif de soutènement pour l'étayage de tranchées | |
DE2250635A1 (de) | Verfahren zum bau eines tunnels | |
EP0230667B1 (fr) | Procédé d'enlèvement par bandes de couches de terrain souterraines, en particulier en terrain meuble | |
DE3009923A1 (de) | Verfahren und einrichtung zum abbau der pfeiler beim kammer-pfeilerbau | |
DE2533904C3 (de) | Schildvortriebseinrichtung zum Vortrieb eines Grabens und zum Verlegen eines Rohrstranges im Graben | |
DE19756418C2 (de) | Senkmaschine mit Vertikal-Schwenkwalzen | |
DE3134071A1 (de) | Gleitender messerverbau fuer den grabenvortrieb zur durchfuehrung von rohrverlegearbeiten im erdreich | |
DE3442871C2 (fr) | ||
DE2826580A1 (de) | Einrichtung zum errichten eines roehrenfoermigen bauwerks o.dgl. im offenen grabenverbau | |
DE4317553C2 (de) | Vorrichtung zum Bodenaustausch neben einem Verkehrsweg | |
DE19623454C2 (de) | Verfahren zum Herstellen und Verbauen von Gräben | |
DE2651474C3 (de) | Verwendung einer Teilschnitt-Streckenvortriebsmaschine zum Durchbauen (Nachreißen) von deformierten Strecken im untertagigen Bergbau | |
DE8516946U1 (de) | Schneidkopf für den Vortrieb vorgefertigter Betonrohre zur Herstellung von Stollen oder Tunneln | |
DE19532690A1 (de) | Einrichtung und Verfahren zum Bodenaustausch bei Gleisanlagen | |
DE3234440A1 (de) | Verbaukorb zum verbau eines kanalgrabens | |
DE3536990A1 (de) | Ausbau unterhalb von deponien | |
DE2161392C2 (de) | Verfahren und Vorrichtung zum Herstellen von Tunneln in offener Baugrube |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
17P | Request for examination filed |
Effective date: 19960420 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE CH ES FR IT LI |
|
17Q | First examination report despatched |
Effective date: 19961121 |
|
GRAG | Despatch of communication of intention to grant |
Free format text: ORIGINAL CODE: EPIDOS AGRA |
|
GRAG | Despatch of communication of intention to grant |
Free format text: ORIGINAL CODE: EPIDOS AGRA |
|
GRAH | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOS IGRA |
|
GRAH | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOS IGRA |
|
ITF | It: translation for a ep patent filed | ||
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
RAP1 | Party data changed (applicant data changed or rights of an application transferred) |
Owner name: TAMROCK VOEST-ALPINE BERGTECHNIK GESELLSCHAFT M.B. |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE CH ES FR IT LI |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: THE PATENT HAS BEEN ANNULLED BY A DECISION OF A NATIONAL AUTHORITY Effective date: 19980923 |
|
REF | Corresponds to: |
Ref document number: 171496 Country of ref document: AT Date of ref document: 19981015 Kind code of ref document: T |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 19981012 Year of fee payment: 5 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: AT Payment date: 19981020 Year of fee payment: 5 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: CH Payment date: 19981023 Year of fee payment: 5 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19981130 |
|
ET | Fr: translation filed | ||
REG | Reference to a national code |
Ref country code: CH Ref legal event code: NV Representative=s name: ZIMMERLI, WAGNER & PARTNER AG |
|
BERE | Be: lapsed |
Owner name: TAMROCK VOEST-ALPINE BERGTECHNIK G.M.B.H. Effective date: 19981130 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed | ||
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19991111 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19991130 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19991130 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20000731 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES;WARNING: LAPSES OF ITALIAN PATENTS WITH EFFECTIVE DATE BEFORE 2007 MAY HAVE OCCURRED AT ANY TIME BEFORE 2007. THE CORRECT EFFECTIVE DATE MAY BE DIFFERENT FROM THE ONE RECORDED. Effective date: 20051111 |