[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

EP0788572B1 - Procede de reprise en sous-oeuvre de batiments - Google Patents

Procede de reprise en sous-oeuvre de batiments Download PDF

Info

Publication number
EP0788572B1
EP0788572B1 EP96938908A EP96938908A EP0788572B1 EP 0788572 B1 EP0788572 B1 EP 0788572B1 EP 96938908 A EP96938908 A EP 96938908A EP 96938908 A EP96938908 A EP 96938908A EP 0788572 B1 EP0788572 B1 EP 0788572B1
Authority
EP
European Patent Office
Prior art keywords
bore
process according
concrete
building
reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
EP96938908A
Other languages
German (de)
English (en)
Other versions
EP0788572A1 (fr
Inventor
Roland Beck
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from DE19547763A external-priority patent/DE19547763A1/de
Application filed by Individual filed Critical Individual
Publication of EP0788572A1 publication Critical patent/EP0788572A1/fr
Application granted granted Critical
Publication of EP0788572B1 publication Critical patent/EP0788572B1/fr
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/48Foundations inserted underneath existing buildings or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations

Definitions

  • the invention relates to a method for undertaking of buildings, according to the preamble of claim 1, and a method for forming reinforced concrete support elements, according to the preamble of claim 16.
  • GB-A-2 254 631 teaches parts of the masonry in the immediate vicinity To be removed near the ground or in the foundation area and stiffened with a reinforced concrete skeleton. With dilapidated or dilapidated structures or buildings this represents one considerable interference with the existing building fabric significant risks.
  • US-A-3,345,824 teaches the sealing of under-rinsed Buildings to be filled with concrete, if necessary iron armored sacks.
  • a cloth tube inside a cylinder made of wire mesh or the like arranged, being inside the fabric hose another wire mesh cylinder can be arranged.
  • the Fabric hose is together with the outer wire mesh cylinder squeezed under a foundation washed in by water and then pressed out through a pipe with a concrete mixture, until it goes through the outer wire mesh cylinder dimensionally stabilized, concrete filled hose between the Underside of the washed-out foundation and the opposite Bottom pressed, the inner wire mesh cylinder forms a kind of reinforcement.
  • WO-A-86/03532 teaches approximately according to the figures there 1 to 5 on the side next to the building to be underpinned to drill a horizontal shaft or tunnel. That tunnel runs between a start and a target shaft and must have a diameter that the insertion of the high-pressure injector, as shown in FIG. 3. Furthermore, this tunnel needs the considerable Must have a diameter so that a human being can at least get involved in it bent over or crawling, in regular motion Distances lateral breakthroughs through which an injection lance from inside the tunnel to the neighboring one Soil can be pushed. It is therefore about a "work tunnel" to the side of the building from which partially penetrated from under the building becomes.
  • FR-A-2 686 356 suggests going out from a starting shaft under the building a horizontal one To advance the shaft or tunnel towards a target shaft. The shaft is then filled with concrete, with one or more tie rods embedded become. The tunnel is driven in such a way that the or the foundations of the building pierced or be pierced. Given that to be underpinned Buildings in the vast majority already one have more or less damaged building structure appears drilling or puncturing the foundations is extremely questionable because risky. For example, when renovating Jordan would apply the procedure under FR-A-2 686 356 mean that the individual column foundations are pierced or need to be pierced. This poses a risk represents which probably no renovation company undertake would like to.
  • a first aspect of the present invention accordingly becomes a process for undertaking buildings created in which at least one support element under the structure is formed, and characterized in that is that the at least one support element is elongated / rod-shaped is trained; and that at least a support element substantially parallel to and below from a foundation of the structure in one previously trained there Hole is arranged.
  • a method of forming reinforced concrete support elements which in particular for the undertaking of Structures are used in which by means of a drilling device a hole below the element to be supported is formed by the drilling device from a Start area is moved to a target area, and at then a reinforced concrete support element in the hole is formed according to another aspect of the present Invention characterized in that according to the Production of the hole Steel wires inserted into the hole be used during the installation with additional reinforcement elements to be connected to a reinforcement.
  • the invention makes it particularly advantageous Way that an entire foundation section of a Structure can be supported.
  • the support element becomes the subsurface not so badly affected under the foundation that there are settlements.
  • Another major advantage is that the Risk of accident for the people working there is essential can be reduced as this is not immediately below the wall to be underpinned, but laterally spaced from the building.
  • Another advantage of the method is that common means in construction engineering and sewer construction can be applied.
  • the one required for implementation Technology is therefore available and relatively inexpensive.
  • support elements in the form of a grid or Grid can be arranged, in particular at larger buildings, such as churches or the like. an effective undertaking of the entire structure become. Buildings of this type are usually constructed in such a way that the load of the structure on a grid of load-bearing Supports columns. These pillars are partly in the side walls and partly inside the building. By the grid-shaped The arrangement of the support elements becomes a targeted support of the respective load-bearing element possible. On gentle undertaking of the entire static support points of the building is therefore possible.
  • the individual Training support elements in that the bore with Steel mesh and grouted concrete is filled.
  • the concrete ring with the tension and compression strands essential.
  • the simpler or more complex one can be used here Method can be applied.
  • Such a bore with pressed tubes is advantageously by means of pipe pressing or Shield tunneling created. This can turn on common procedures from sewer construction can be used.
  • the upright holes are made with concrete and preferably steel reinforced concrete filled, the particular is introduced by high pressure injection. So that becomes a certain displacement of the unstable subsurface under the Foundation reached and the room filled with concrete. Provided if the subsurface cannot be ousted, it will be so far condenses that it is now stable.
  • the area between the at least a support element and the supporting element after insertion the upright holes and the ones made in them Support excavated and covered with concrete, which is preferred steel reinforced, to be filled. Even with that stable undertaking of the supporting element can be achieved.
  • reinforced concrete support elements can be therefore significantly simplify by after the manufacturing process of the hole, steel strands are individually inserted into the hole and during the installation with additional reinforcement elements to be connected to a reinforcement.
  • the reinforcement is connected to the tension element and pulled through this into the hole.
  • the advantage here is that the reinforcement is inserted in the bore is guided, and further that an insertion means Traction is much easier to manage than insertion by means of pressure forces. The danger of getting caught the reinforcement with the hole wall and thus one Blockage is significantly less.
  • the reinforcement is on the end connected to the traction element is not yet full is trained and e.g. forms a cone shape that is relative simply slides through the hole.
  • the steel cable with the attached Reinforcement using a preferably arranged in the target area Winch is pulled through the hole, can apply the forces required to insert the reinforcement be reliably applied. Furthermore, the progression of the introduction are controlled continuously, whereby a jerky slip or the like, e.g. when pulling in by hand due to a hooking of the Reinforcement with the bore wall can be prevented can be.
  • the reinforcement during withdrawing the drilling device or the drive to the drilling device in the start area in the hole is drawn in. It can be used to introduce a Tension element are dispensed with, since the retraction movement of the Drilling device as a drive for inserting the reinforcement Application. Arranging the reinforcement in the This further simplifies drilling.
  • the steel strands are rolled up, so the roles can be arranged in the start area and the Unroll the strands when pulling them into the hole. The bringing in this simplifies the steel strands in the bore essential.
  • the length of the steel strands on the Role predetermined, so the space required in the start area be kept low.
  • FIG. 1 and 2 represent a first embodiment to undertake buildings.
  • This is a building 1 with a foundation 2 of its front wall.
  • a first shaft 3 and a second shaft 4 created laterally spaced from the front wall.
  • Means a device, not shown, with an earth rocket is a bore 9 between the first shaft 3 and second shaft 4 spaced below the foundation 2 of the Building 1 generated.
  • a support element 5 in the form of a concrete ring with tension or compression strands 6 by a concreting process and by means of a suitable Formwork created (see Fig. 8).
  • the support element 5 also as a concrete bar with appropriate reinforcement be formed.
  • the support element 5 thus extends spaced below of the foundation 2.
  • the diameter of the support element 5 is chosen such that the introduction of the hole 9 the underground under the foundation 2 is not additionally unnecessary destabilized.
  • the support elements 5 are coupled together and form a foundation, which is like a "raft" on the Foundation 2 works.
  • the stabilizing effect of this multitude of support elements 5 on the foundation 2 of the front wall of the building 1 may already be sufficient to build the structure to protect.
  • An undertaking of the building 1 according to the one described Way can with an existing building on one side and - if necessary - on all sides or can be created under the partition walls in the building.
  • Fig. 3 is a schematic representation of a three-aisled Church 10 shown in plan view.
  • the statics the church 10 is essentially based on structural elements or pillars 11.
  • the upright bores 13 can alternatively also through pressing concrete into the horizontal bores 9 for the support elements 5 are filled from below. In order to there is a good connection between the horizontal ones and upright holes.
  • the column 11 is thus underpinned by a concrete foundation and safely supported. A corresponding procedure is also on the other pillars 11 of the church 10 made, as well as if necessary on the foundations of the outer walls.
  • By adding more wedge-shaped Support element groups is also used in such a In case a safe support of the building is possible, because wedge the support element groups against each other.
  • This arrangement the support elements 5 can also on any transfer other use cases for the undertaking of buildings become. There are also other arrangements the support elements 5 in any way and the respective Requirements possible.
  • Fig. 7 it is possible to Upright support elements 5 and one Coupling them to form a wall in the ground that the formation of a basement under an existing building enables.
  • the underpinning as a wall of sufficient height on three sides of the building trained and sufficient on the fourth page Underpinning created in the sense of a static beam his. If the base plate of the existing building is the absorb static forces through the internal bearing walls can or with an underpinning again in Is provided in the sense of a beam, the soil of on the fourth side of the building.
  • the support elements can be arranged in a single row or multiple rows be, so that a kind of horizontal bar wall or bored pile wall.
  • a basement with the help of the support elements 5 can also be formed in a different way, wherein only care must be taken that the existing Building is adequately supported on the ground.
  • FIG. 8 shows how a support element according to a first embodiment is constructed. This points a concrete ring, which is provided with tension or compression strands 6 is. These tension or pressure strands 6 take the occurring Tensile or compressive loads.
  • the concrete ring is through Filling in the space between an outer and an inner Steel pipe 7 and 8 generated and finally with if necessary provided with reinforcement and poured with concrete.
  • pre-made pipes can also be pressed in and these are in turn arranged with steel mesh or suitably Tension or compression strands and pressed-in concrete fill out.
  • the hole 9 itself can be done using an anchor drill or an earth rocket be created, and if pipes are pressed in should, this can be done with the help of a pipe pressure or Shield driving can be achieved.
  • Pressing in prefabricated pipes is recommended especially on very loose ground, such as Sand or gravel, as it is very difficult here, a stable shape To produce a hole.
  • This method of stabilizing a hole or a cavity in the floor can also be used for other applications, e.g. be transferred in tunnel construction.
  • boring 9 can also be created by a milling process.
  • each The plane here has a plurality of juxtaposed Support elements 5. They are each rectified planes offset from each other, see above the effect of surface foundation increases.
  • the air in the cavity in a support element according to FIG. 8 can e.g. also used in this way on a damp surface that a buoyancy is generated.
  • the hollow Support element 5 therefore has a tendency to be on the groundwater table to "swim", which may even raise buildings can be.
  • additional ones can also be used Buoyancy body e.g. in the area of the side Manholes are arranged. It creates a "floating Foundation ", which stabilizes the building.
  • the building 1 is only through here three supports 22, 23 and 24 indicated for the foundations of the building.
  • first Pressure element 25 horizontally in the area of the supports 22, 23 and 24 arranged.
  • a first tension element 26 is below the supports 22, 23 and 24 passed through and on one side anchored in the stable rock layer 21.
  • the other side of the first tension element 26 is replaced by an upright Support element in the form of a pillar 27 on the stable Supported rock layer 21.
  • the tension and compression elements can be used with a single Steel strand, or with an arrangement of several steel strands or a reinforcement formed in concrete is embedded.
  • tension elements 28 and 29 are under the supports 22, 23 and 24 passed through.
  • a tension element 28 as shown in FIG. 10 is a single one Reach under support 22, or as with the traction element 29 indicated, several supports 23 and 24. In the latter Fall can pull the element by controlling the drilling device between the supports returned to the earth's surface become.
  • the other tension elements 28 and 29 are thereby additional printing elements 30-34 on the stable base layer 21 or supported on the first tension element 26.
  • the tension elements 26, 28 and 29 are tensioned and the supports 22, 23 and 24 of building 1 are supported.
  • the upright pressure elements 31-34 are e.g. placed directly on the first tension element 26 or on a Plurality of first tension members 26 to form a stable base to obtain.
  • Fig. 11 it is shown how the horizontal and Upright support elements can be coupled together to avoid moving or folding.
  • Here embrace e.g. two each arranged essentially horizontally Support elements from two directions an upright Support element in one area. This embrace can be at a location spaced from the first wrap done again so that the freedom of movement of the Upright support element is limited.
  • the upright support element is thus firmly encompassed and between the horizontal support elements clamped.
  • Fig. 12 shows how the support elements according to the invention 5 with different soil layers for stabilization of the underground e.g. under a base plate 37 Concrete can be used.
  • a gravel layer 38 and a clay layer 39 due to washes on it Stabilization can be achieved.
  • an earth rocket created.
  • the not shown in the figures Earth rocket is launched into launch area 3 and moved towards the target area 4 by means of a drive, that by displacing the soil a stable Bore 9 forms.
  • the head of the Earth rocket removed and the propulsion device finally withdrawn to start area 3.
  • a steel cable 16 is attached to it, whereby this in turn pulled through the bore 9 becomes.
  • the steel cable 16 is from a not shown Cable winch rolled off in target area 4. After this the steel cable 16 has reached the start area 3, the Earth rocket propulsion device from launch area 3 taken.
  • the steel strands 6 a concrete delivery hose 17 is also drawn into the bore 9 and is now at the end of the bore 9 in the area of target area 4.
  • the opening of hole 9 at the target area 4 can now, if necessary, by formwork be closed and then concreting begins the hole 9.
  • concrete is fed through the concrete delivery hose 17 introduced into the bore 9.
  • the concrete delivery hose 17 is continuously coordinated Way with the flow rate of concrete towards the start area 3 withdrawn. A full fill of hole 9 in each area below the foundation 2 of the structure 1 is thus achieved.
  • a repressing hose can also be used with inserted into the bore 9 to a concrete pressure to allow the complete filling of the bore 9th ensures.
  • reinforced concrete support element 5 After hardening, there is now a reinforced concrete support element before that as an underpinning for a building 1 with ailing building substance is suitable.
  • the reinforced concrete support element 5 is shown in FIG. 15 trained. This shape with arranged in a ring Steel strands allow e.g. the good reception of train and Compression forces perpendicular to the main direction of the reinforced concrete support element 5.
  • the procedure shown can always then be applied as soon as any reinforced concrete element between a start and a finish point should.
  • This is not just limited to drilling, but can e.g. can also be used for open formwork.
  • tubular reinforced concrete support elements be trained, provided another Formwork for the core is used.
  • the number of steel strands used during training the reinforcement can vary arbitrarily, with certain Cases a single steel strand could be sufficient.
  • the type of additional reinforcement elements is limited not on the spiral 14 shown here, but also others Elements such as steel baskets e.g. with steel mats or similar can be used.
  • the spiral 14 be in practice partly also ring elements applied in some use cases are usually cheaper but then not the high bending stiffness and the high Load resistance achieved when using the spiral.
  • the spiral 14 can also on both outside and inside the steel strands are arranged.
  • the application of the method according to the invention is limited also not trained on horizontally Reinforced concrete elements, but can also be used for example Formation of vertical support columns in old walls or when stabilizing soil or rock formations Find use.
  • the steel strands wound on the strand rolls can be of any length or can be pre-selected Length can be set. Furthermore, it is of course possible to do without the heald rolls and the healds fed individually from the top edge of the shaft.
  • the steel strands 6 are with the other reinforcement elements assembled in a known manner to form a reinforcement 15. This can be done by connecting using wires, the so-called structural steel braiding, happen, or e.g. also by welding of the reinforcement elements with each other.
  • the static calculation of the underpinning according to the invention can be based on a combination of the known static Calculation method for the bored pile wall or the surface foundation respectively.
  • the arrangement of the support elements, e.g. 7, can be in the sense of a lying Bored pile wall are treated, making a calculation with minor modifications is possible. Let the results themselves in connection with results from a calculation process similar to the foundation of the area makes sense to the invention apply. The undertaking of buildings can thus based on a reliable static calculation.
  • the invention thus shows a method for undertaking of structures on, below the to be underpinned Building 1 at least one elongated / rod-shaped support element 5 essentially parallel to the foundation 2 of the building 1 is arranged.
  • This can be an underpinning in one go reached an entire side wall of the building 1 become unnecessary without the existing subsurface is weakened.
  • the elongated support elements 5 can be a kind of foundation and also created a secure foundation for building 1 become. This also allows the structure of preserve very old buildings in a gentle way. About that in addition, the process is very fast and with relatively little Effort feasible. It can also be done in this way increase the seismic safety of buildings. This can by means of water-filled cavities in the solid underground Attenuation of shock waves can be achieved.
  • voids in the floor can be stabilized. This is achieved in that in the course of cavity production a binder in the periphery of the cavity is introduced.
  • Funds are used. Examples include concrete, Resins, silicates or other suitable mineral Fabrics or plastics.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)
  • Working Measures On Existing Buildindgs (AREA)
  • Foundations (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)
  • Investigating Or Analyzing Materials Using Thermal Means (AREA)
  • Branch Pipes, Bends, And The Like (AREA)
  • Controlling Rewinding, Feeding, Winding, Or Abnormalities Of Webs (AREA)

Claims (23)

  1. Procédé de reprise en sous-oeuvre de bâtiments (1), selon lequel au moins un élément d'appui (5) est formé au-dessous du bâtiment (1), caractérisé en ce
    qu'on réalise au moins un élément d'appui (5) sous une forme allongée / une forme de poutre; et
    qu'on dispose de au moins un élément d'appui (5) essentiellement parallèlement à et au-dessous d'une fondation (2) du bâtiment (1) dans un forage (9) effectué en cet endroit au préalable.
  2. Procédé selon la revendication 1, caractérisé en ce qu'on dispose une multiplicité de segments allongés d'appui (5) au-dessous de la fondation (2) et qu'on les accouple au moins partiellement entre eux.
  3. Procédé selon la revendication 2, caractérisé en ce qu'on dispose les éléments d'appui (5) sous la forme d'un réseau ou d'une grille.
  4. Procédé selon la revendication 3, caractérisé en ce qu'on disposer les points d'intersection du réseau d'éléments d'appui (5) au-dessous d'éléments porteurs ou de colonnes porteuses (11).
  5. Procédé selon l'une des revendications 1 à 4, caractérisé en ce qu'on forme au-dessous du bâtiment (1) devant être repris en sous-oeuvre, un système d'éléments d'appui (5) disposés essentiellement horizontalement et verticalement et qui sont accouplés entre eux.
  6. Procédé selon l'une des revendications 1 à 5, caractérisé en ce qu'on forme les différents éléments d'appui (5) en réalisant, dans le forage (9), un anneau en béton ou une poutre en béton, qui comporte des torons (6) travaillant en traction et en compression.
  7. Procédé selon l'une des revendications 1 à 5, caractérisé en ce qu'on forme les différents éléments d'appui (5) en remplissant le forage (9) avec un treillis d'acier et du béton injecté.
  8. Procédé selon la revendication 6 ou 7, caractérisé en ce qu'on réalise le forage (9) à l'aide d'une foreuse à ancre ou d'un engin guidé de forage du sol.
  9. Procédé selon l'une des revendications 1 à 5, caractérisé en ce qu'on forme les différents éléments d'appui (5) en enfonçant des tubes dans le forage (9) au-dessous de la fondation (2) et en remplissant ces tubes avec un treillis d'acier et du béton injecté.
  10. Procédé selon la revendication 9, caractérisé en ce qu'on réalise le forage (9) moyennant l'application d'une pression aux tubes ou à l'aide d'un creusement à l'aide d'un bouclier.
  11. Procédé selon l'une des revendications 1 à 10, caractérisé en ce qu'on aménage, entre la partie marginale d'un élément porteur (11) et le au moins un élément d'appui (5), des forages verticaux (13) dans lesquels sont disposés des appuis.
  12. Procédé selon la revendication 11, caractérisé en ce qu'on forme les appuis dans les forages verticaux (13) en utilisant du béton, de préférence du béton armé, que l'on introduit notamment par injection à haute pression.
  13. Procédé selon la revendication 11, caractérisé en ce qu'on excave la zone située entre le au moins un élément d'appui (5) et l'élément porteur (11) et qu'on la remplit par du béton, qui contient de préférence un armaturage en acier.
  14. Procédé selon l'une des revendications 1 à 13, caractérisé en ce qu'on dispose plusieurs éléments d'appui (5) verticalement les uns au-dessus des autres.
  15. Procédé selon l'une des revendications 1 à 14, caractérisé en ce qu'on forme des cavités, dans les éléments d'appui, les cavités formées dans les éléments d'appui (5) pouvant être remplies.
  16. Procédé pour former des éléments d'appui en béton armé (5), qui sont utilisés notamment pour la reprise en sous-oeuvre de bâtiments (1) selon l'une des revendications 1 à 15, selon lequel à l'aide d'un dispositif de forage, on aménage un forage (9) au-dessous de l'élément devant être soutenu, en déplaçant le dispositif de forage d'une zone de départ (3) jusqu'à une zone de destination (4), et selon lequel on forme ensuite, dans le forage (9). un élément d'appui en béton armé (5), caractérisé en ce qu'après la fabrication du forage (9), on insère dans le forage (9) des torons d'acier (6), qu'on relie, pendant leur introduction, à d'autres éléments d'armature (14) pour former une armature (15).
  17. Procédé selon la revendication 16, caractérisé en ce que lors du retrait du dispositif de forage, on tire dans la zone de départ (3), une fois le forage (9) terminé, un élément travaillant en traction, notamment un câble d'acier (16), à travers le forage (9), élément travaillant en traction à l'aide duquel on tire ensuite à travers le forage l'armature (15) disposée de préférence dans la zone de départ (3).
  18. Procédé selon la revendication 17, caractérisé en ce qu'on tire le câble d'acier (16), auquel est fixée l'armature (15), à l'aide d'un treuil à câble disposé de préférence dans la zone de destination (4), à travers le forage (9).
  19. Procédé selon la revendication 16, caractérisé en ce qu'on tire l'armature (15) pendant le retrait du dispositif de forage ou du dispositif d'entraínement du dispositif de forage dans la zone de départ (3), dans le forage (9).
  20. Procédé selon l'une des revendications 16 à 19, caractérisé en ce qu'on relie les torons d'acier (6), pendant l'introduction par tirage dans le forage (9), à une hélice pour former l'armature (15).
  21. Procédé selon l'une des revendications 16 à 20, caractérisé en ce que les torons d'acier (6) sont présents sous forme enroulée, de préférence avec une longueur prédéterminée, et qu'on les déroule lors de l'introduction par tirage à l'intérieur du forage (9).
  22. Procédé selon l'une des revendications 16 à 21, caractérisé en ce qu'on introduit par tirage dans le forage (9), conjointement avec l'armature (15), également au moins un tuyau (17) de transport du béton et qu'on rétracte continûment ce dernier pendant le bétonnage.
  23. Procédé selon la revendication 1, caractérisé en ce qu'on dispose des éléments d'appui allongés (figure 7) au-dessous de la fondation et qu'on soulève le bâtiment lors de la mise en pression avec un liant et qu'on élimine d'une manière réglée les différences entre bâtiments moyennant l'utilisation d'éléments d'ancrage.
EP96938908A 1995-08-17 1996-08-16 Procede de reprise en sous-oeuvre de batiments Expired - Lifetime EP0788572B1 (fr)

Applications Claiming Priority (5)

Application Number Priority Date Filing Date Title
DE19530304 1995-08-17
DE19530304 1995-08-17
DE19547763 1995-12-20
DE19547763A DE19547763A1 (de) 1995-08-17 1995-12-20 Verfahren zum Unterfangen von Bauwerken
PCT/DE1996/001526 WO1997007295A1 (fr) 1995-08-17 1996-08-16 Procede de reprise en sous-oeuvre de batiments

Publications (2)

Publication Number Publication Date
EP0788572A1 EP0788572A1 (fr) 1997-08-13
EP0788572B1 true EP0788572B1 (fr) 2001-07-11

Family

ID=26017796

Family Applications (1)

Application Number Title Priority Date Filing Date
EP96938908A Expired - Lifetime EP0788572B1 (fr) 1995-08-17 1996-08-16 Procede de reprise en sous-oeuvre de batiments

Country Status (9)

Country Link
US (1) US6062770A (fr)
EP (1) EP0788572B1 (fr)
AT (1) ATE203075T1 (fr)
CZ (1) CZ292795B6 (fr)
DK (1) DK0788572T3 (fr)
ES (1) ES2158362T3 (fr)
GR (1) GR3036352T3 (fr)
PT (1) PT788572E (fr)
WO (1) WO1997007295A1 (fr)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102795554A (zh) * 2012-08-10 2012-11-28 中油吉林化建工程有限公司 固定式塔吊整体迁移机构及迁移方法

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030233798A1 (en) * 2002-06-21 2003-12-25 Berkey John William Post-tensioned, below-grade concrete foundation system
US7618216B1 (en) * 2006-11-17 2009-11-17 Lucas Tong Faultline fearless nanotube homes
US20080163567A1 (en) * 2007-01-05 2008-07-10 Jordan Alfred A S&T Jordan PowerStructure System
KR101026731B1 (ko) * 2010-12-16 2011-04-08 주식회사고려이엔시 준공된 건축물의 지하실 시공방법
CN106150118A (zh) * 2015-04-24 2016-11-23 贵州中建建筑科研设计院有限公司 一种旧墙体托换施工方法及其梁板改造承重结构
JP6675173B2 (ja) * 2015-11-10 2020-04-01 株式会社竹中工務店 基礎構築方法
CA3015706A1 (fr) * 2016-02-04 2017-08-10 Ivan TEOBALDELLI Fondation
CN107642252B (zh) * 2017-09-21 2019-09-10 青岛静力工程股份有限公司 老旧建筑免拆除双增改造施工工艺
CN113323011B (zh) * 2021-06-30 2022-12-27 武汉武建机械施工有限公司 既有建筑地基基础下钢管新型托换施工方法

Family Cites Families (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1085600A (en) * 1912-08-26 1914-02-03 John B Goldsborough Method of underpinning buildings and other structures.
US1093262A (en) * 1913-06-17 1914-04-14 John B Goldsborough Method of underpinning buildings.
US2561676A (en) * 1950-01-12 1951-07-24 V C Patterson & Associates Inc Method of lowering ice-buckled cold room floors
US3091938A (en) * 1960-07-27 1963-06-04 Jr Harry Schnabel Method and structure for underpinning
US3224203A (en) * 1961-02-28 1965-12-21 Skanska Cementgjuteriet Ab Method of driving tunnels in rock
US3345824A (en) * 1964-05-06 1967-10-10 Lee A Turzillo Method and means for bracing or bolstering subaqueous structures
US3429126A (en) * 1966-01-21 1969-02-25 Gino Wey Method of producing a continuous bore pile wall
DE2217459A1 (de) * 1972-04-12 1973-10-31 Lysson Joachim Friedrich Verfahren und einrichtung zum unterfangen von bauwerken und verkehrswegen
US3854294A (en) * 1972-12-29 1974-12-17 A Frank Method for producing a pile support arrangement
US4119764A (en) * 1976-11-23 1978-10-10 Neturen Company Ltd. Helical reinforcing bar for steel cage in concrete structure
DE2752605C2 (de) * 1977-11-25 1986-05-15 Friedrich Wilh. Schwing Gmbh, 4690 Herne Auf einem fahr- oder umsetzbaren Unterbau montierte Vorrichtung zum Einbringen von Beton in Schalungen, insbesondere beim Streckenausbau im Berg- und Tunnelbau
GB2067623A (en) * 1980-01-23 1981-07-30 Bullivant R A Method for supporting buildings
SE439793B (sv) * 1983-10-21 1985-07-01 Bjorn Magnus Ringesten Med Fir Forfarande att genom kompensationsgrundleggning astadkomma grundleggning och/eller grundforsterkning
GB2188351B (en) * 1984-12-07 1988-08-03 Gkn Keller Gmbh Grout stabilisation
GB2186310B (en) * 1986-01-16 1990-09-26 Roxbury Ltd Methods for underpinning unstable structures
US4906140A (en) * 1987-01-29 1990-03-06 Clark Howard E Method and apparatus for raising and supporting a foundation
GB8712591D0 (en) * 1987-05-28 1987-07-01 Roxbury Ltd Supporting building structures
SE459189B (sv) * 1987-09-09 1989-06-12 Pieux Armes Int Foerfarande och anordning foer att paaverka samverkan mellan ett jordlager och en i anslutning till jordlagret befintlig konstruktion
GB2254631A (en) * 1991-03-05 1992-10-14 Guardian Foundations Plc Underpinning
FR2686356B1 (fr) * 1992-01-22 1998-11-06 Freyssinet Int & Co Perfectionnements aux procedes et dispositifs de reprise des fondations en sous-óoeuvre et aux fondations ainsi obtenues.
DE4210196A1 (de) * 1992-03-28 1993-09-30 Gerd Prof Dr Ing Gudehus Verfahren zum Verformungsausgleich im Untergrund durch Einpressen bodenschonender Pasten
US5314267A (en) * 1992-08-27 1994-05-24 Mark Osadchuk Horizontal pipeline boring apparatus and method
US5433557A (en) * 1993-12-27 1995-07-18 Spencer, White & Prentis Foundation Corporation Method for underpinning an existing footing
DE4415399C2 (de) * 1994-05-03 2003-10-30 Putzmeister Ag Anordnung zum Vortrieb eines Tunnel- oder Abwasserrohrs
IL112441A (en) * 1995-01-25 1998-02-08 Lipsker Yitshaq Method for underground excavation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102795554A (zh) * 2012-08-10 2012-11-28 中油吉林化建工程有限公司 固定式塔吊整体迁移机构及迁移方法

Also Published As

Publication number Publication date
CZ151097A3 (cs) 1998-02-18
DK0788572T3 (da) 2001-09-24
ES2158362T3 (es) 2001-09-01
EP0788572A1 (fr) 1997-08-13
US6062770A (en) 2000-05-16
WO1997007295A1 (fr) 1997-02-27
GR3036352T3 (en) 2001-11-30
ATE203075T1 (de) 2001-07-15
PT788572E (pt) 2001-10-31
CZ292795B6 (cs) 2003-12-17

Similar Documents

Publication Publication Date Title
EP0788572B1 (fr) Procede de reprise en sous-oeuvre de batiments
DE3215153C2 (de) Stützbauwerk und Verfahren zur Herstellung eines Stützbauwerks
DE2545572A1 (de) Bauverankerung
EP2108744B1 (fr) Procédé de sécurisation de mur de soutènement
AT391506B (de) Vorrichtung zur abfuehrung von waerme in den erdboden bzw. zur aufnahme der waerme aus dem erdboden
DE4224042A1 (de) Verfahren und Vorrichtung zur Pfahlgründung
DE7021646U (de) Bewehrungskorb fuer eine unterirdische sperrwand aus stahlbeton fuer tiefbauwerke.
DE3516044C2 (de) Verfahren zur Abschirmung von Objekten gegen über den Boden fortgepflanzte Erschütterungen
CH676015A5 (fr)
EP0109397B1 (fr) Element de fondation creux et procede pour sa fabrication
DE3318050C2 (fr)
DE69938438T2 (de) Ein in beton eingebetteter rundpfahl und pfahlrammmethode
DE3443040A1 (de) Verfahren zur herstellung unterirdischer bauwerke mittels tuerstock-deckelbauweise
DE3534655A1 (de) Verfahren zur herstellung einer gegen auftrieb gesicherten betonsohle
DE4312231C2 (de) Verfahren und Vorrichtung zur Herstellung von flächigen Bauelementen im Boden
DE102016107899A1 (de) Verfahren zum Herstellen einer Rohrspundwand und Tragrohr
DE19547763A1 (de) Verfahren zum Unterfangen von Bauwerken
DE1910556A1 (de) Verfahren zur Herstellung von Gruendungspfaehlen aus Ortbeton mit Erweiterungen des Pfahlschaftes und des Pfahlfusses,sowie Innenschalung zur Durchfuehrung des Verfahrens
DE102021116487B3 (de) Geotextilummantelte Flüssigbodensäulen
AT16710U1 (de) Stützmauerelement und Stützmauer aus Stützmauerelementen
EP0048959A2 (fr) Elément de fondation, pouvant supporter des charges, particulièrement en béton armé
DE2105432C3 (de) Verfahren zur Herstellung eines in Längsrichtung vorgespannten Verbundpfahles
DE102020131395A1 (de) Verfahren zum Sichern eines Bauwerks und Anordnung eines Bauwerks in einem Gelände
EP2728070B1 (fr) Procédé d'enfoncement et d'ancrage d'un pilot dans la terre ainsi que pilot
AT256916B (de) Verfahren zur Herstellung von Stützwänden, insbesondere für offene Baugruben od. dgl.

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 19970509

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE CH DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE

17Q First examination report despatched

Effective date: 19980420

GRAG Despatch of communication of intention to grant

Free format text: ORIGINAL CODE: EPIDOS AGRA

GRAG Despatch of communication of intention to grant

Free format text: ORIGINAL CODE: EPIDOS AGRA

GRAH Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOS IGRA

GRAH Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOS IGRA

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE CH DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE

REF Corresponds to:

Ref document number: 203075

Country of ref document: AT

Date of ref document: 20010715

Kind code of ref document: T

REG Reference to a national code

Ref country code: CH

Ref legal event code: NV

Representative=s name: ISLER & PEDRAZZINI AG

Ref country code: CH

Ref legal event code: EP

GBT Gb: translation of ep patent filed (gb section 77(6)(a)/1977)

Effective date: 20010712

REF Corresponds to:

Ref document number: 59607272

Country of ref document: DE

Date of ref document: 20010816

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

Free format text: GERMAN

ITF It: translation for a ep patent filed
REG Reference to a national code

Ref country code: ES

Ref legal event code: FG2A

Ref document number: 2158362

Country of ref document: ES

Kind code of ref document: T3

REG Reference to a national code

Ref country code: DK

Ref legal event code: T3

REG Reference to a national code

Ref country code: PT

Ref legal event code: SC4A

Free format text: AVAILABILITY OF NATIONAL TRANSLATION

Effective date: 20010713

ET Fr: translation filed
REG Reference to a national code

Ref country code: GB

Ref legal event code: IF02

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed
REG Reference to a national code

Ref country code: IE

Ref legal event code: FD4D

Ref document number: Errata: In Journal N

Country of ref document: IE

REG Reference to a national code

Ref country code: CH

Ref legal event code: PCAR

Free format text: ISLER & PEDRAZZINI AG;POSTFACH 1772;8027 ZUERICH (CH)

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: PT

Payment date: 20080811

Year of fee payment: 13

Ref country code: NL

Payment date: 20080820

Year of fee payment: 13

Ref country code: LU

Payment date: 20080826

Year of fee payment: 13

Ref country code: ES

Payment date: 20080828

Year of fee payment: 13

Ref country code: DK

Payment date: 20080822

Year of fee payment: 13

Ref country code: CH

Payment date: 20080825

Year of fee payment: 13

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: MC

Payment date: 20080820

Year of fee payment: 13

Ref country code: IT

Payment date: 20080826

Year of fee payment: 13

Ref country code: IE

Payment date: 20080819

Year of fee payment: 13

Ref country code: FR

Payment date: 20080818

Year of fee payment: 13

Ref country code: FI

Payment date: 20080825

Year of fee payment: 13

Ref country code: AT

Payment date: 20080821

Year of fee payment: 13

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20080822

Year of fee payment: 13

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20081007

Year of fee payment: 13

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: SE

Payment date: 20080825

Year of fee payment: 13

Ref country code: BE

Payment date: 20080822

Year of fee payment: 13

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GR

Payment date: 20080826

Year of fee payment: 13

REG Reference to a national code

Ref country code: PT

Ref legal event code: MM4A

Free format text: LAPSE DUE TO NON-PAYMENT OF FEES

Effective date: 20100217

BERE Be: lapsed

Owner name: *BECK ROLAND

Effective date: 20090831

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090831

REG Reference to a national code

Ref country code: NL

Ref legal event code: V1

Effective date: 20100301

Ref country code: CH

Ref legal event code: PL

REG Reference to a national code

Ref country code: DK

Ref legal event code: EBP

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20090816

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20100217

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090831

Ref country code: FI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090816

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090831

REG Reference to a national code

Ref country code: FR

Ref legal event code: ST

Effective date: 20100430

REG Reference to a national code

Ref country code: IE

Ref legal event code: MM4A

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090831

Ref country code: AT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090816

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20100301

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090817

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090831

Ref country code: DK

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090831

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20100302

REG Reference to a national code

Ref country code: ES

Ref legal event code: FD2A

Effective date: 20090817

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20100303

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090816

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090816

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090816

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090817

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: ES

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090817