DE3242570A1 - Scaffolding - Google Patents

Scaffolding

Info

Publication number
DE3242570A1
DE3242570A1 DE19823242570 DE3242570A DE3242570A1 DE 3242570 A1 DE3242570 A1 DE 3242570A1 DE 19823242570 DE19823242570 DE 19823242570 DE 3242570 A DE3242570 A DE 3242570A DE 3242570 A1 DE3242570 A1 DE 3242570A1
Authority
DE
Germany
Prior art keywords
support
work
working scaffold
scaffolding
scaffold according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
DE19823242570
Other languages
German (de)
Other versions
DE3242570C2 (en
Inventor
Gerhard 6830 Rankweil Hartmann
Günter 6972 Fußach Marte
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Rund Stahl Bau & Co GmbH
Rund Stahl Bau GmbH
Original Assignee
Rund Stahl Bau & Co GmbH
Rund Stahl Bau GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rund Stahl Bau & Co GmbH, Rund Stahl Bau GmbH filed Critical Rund Stahl Bau & Co GmbH
Publication of DE3242570A1 publication Critical patent/DE3242570A1/en
Application granted granted Critical
Publication of DE3242570C2 publication Critical patent/DE3242570C2/de
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/36Scaffolds for particular parts of buildings or buildings of particular shape, e.g. for stairs, cupolas, domes
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/36Scaffolds for particular parts of buildings or buildings of particular shape, e.g. for stairs, cupolas, domes
    • E04G1/362Scaffolds for particular parts of buildings or buildings of particular shape, e.g. for stairs, cupolas, domes specially adapted for tanks, silos or similar vessels

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Movable Scaffolding (AREA)
  • Ladders (AREA)

Abstract

For erecting and removing the inner limitation of conical or dome-shaped structures (3) or structure sections (2), a scaffolding (7) designed as accessible stairs is used. The scaffolding (7) can be adapted to the angle of inclination of the structure or structure section to be erected. This scaffolding (7) can be turned about a vertical axis (9) formed by a supporting or bearing mast (4) arranged centrally in the structure, for this purpose the upper end of the scaffolding (7) being supported displaceably or movably on a bearing ring (8), fastened to the supporting or bearing mast (4), and the lower end being supported displaceably or movably on a working platform (5) or a supporting ramp in the region of the base of the cone or dome. This scaffolding (7) allows all areas on the inside of formwork to be erected or removed to be reached safely and quickly. <IMAGE>

Description

Gegenstand: ArbeitsgerüstSubject: work scaffolding

Die Erfindung betrifft ein Arbeitsgerüst zum Ein- und Ausschalen der Innenbegrenzung kegel- oder kuppelförmiger Bauwerke oder Bauwerksabschnitte, wobei im Zentrum des Bauwerkes ein vertikal verlaufender Stätz- bzw. Tragmast angeordnet und ein Arbeitspodest bzw. eine Abstützrampe zumindest im Bereich des Kegel- oder Kuppelfußes des zu errichtenden Bauwerkes bzw. Bauwerksabschnittes vorgesehen ist, und wobei das Arbeitsgerüst um die vom 8tütz- bzw. Tragmast gebildete vertikale Achse verdrehbar ist.The invention relates to a work scaffold for shuttering and stripping the Inner boundary of conical or dome-shaped buildings or building sections, where In the center of the structure a vertically extending pylon or support mast is arranged and a work platform or a support ramp at least in the area of the cone or Dome base of the structure or structure section to be erected is provided, and wherein the work scaffold around the vertical formed by the 8tütz- or support mast Axis is rotatable.

Bei der Herstellung solcher Bauwerke bzw. Bauwerksabschnitte wird in der Regel knapp unterhalb des kegel- oder kuppelförmigen Bauwerkabschnittes ein Arbeitspodest erstellt, von welchem aus dann die Montage der Schalung für diesen Bauwerksabschnitt erfolgen kann. Gerade im Zentrumsbereich des Kegels oder der Kuppel liegen die Schalungsträger und Schalungsplatten sehr weit oberhalb dieses Arbeitspodestes, so daß es einerseits erforderlich ist, die komplette Innenfläche des Bauwerkes mit einem Arbeitspodest auszubilden und andererseits ist es notwendig, zusätzliche Hilf smittel vorzusehen, wie sum Beispiel Leitern usw., um überhaupt die Montage der Schalung zu ermÆ lichen. Die gleichen Probleme ergeben sich dann selbstverständlich beim Ausschalen des Bauwerkes nach erfolgtem Betonieren.In the manufacture of such structures or structure sections usually just below the conical or dome-shaped building section Work platform is created from which the formwork is then assembled for this Structural section can be done. Especially in the center of the cone or dome are the formwork beams and formwork panels very far above this work platform, so that it is necessary on the one hand to use the entire inner surface of the structure a work platform and on the other hand it is necessary to have additional help Provide means, such as ladders, etc., to allow the assembly of the Formwork to allow. The same problems then naturally arise when stripping the structure after concreting.

Die vorliegende Erfindung hat sich zur Aufgabe gerollt, ein Arbeitsgerüst zu schaffen, mit welchem in einfacher Weise sämtliche Bereiche der Innenbegrensung des zu errichtenden kegel- oder kuppelförmigen Bauwerkes zugänglich sind, so daß das Ein- und Ausschalen ohne Schwierigkeiten und ohne besondere Gefahren für die Bauarbeiter durchgeführt werden kann.The present invention has rolled out to the task, a work scaffold to create, with which all areas of the interior delimitation in a simple manner of the conical or dome-shaped structure to be erected are accessible, so that shuttering and stripping without difficulty and without any particular dangers for the Construction workers can be done.

Erfindun5sgemEß wird hiezu vorgeschlagen, daß das Arbeitsgerüst als begehbare, dem Neigungswinkel des zu errichtenden kegel- oder kuppelförmigen Bauwerkes bzw. Bauwerkabschnittes anpaßbare Treppe ausgebildet ist, an deren oberem Ende zwei mit Abstand voneinander angeordnete Abstützprofile oder -rollen angeordnet sind, welche an einem konzentrisch am Stütz- bzw. Tragmast angeordneten Tragring bzw. einer Tragplatte verschiebbar geführt sind, und an deren unterem, dem Eegel- bzw. Kuppelfuß zugewandten Ende Laufrollen mit horizontal und radial zum Stütz- bzw. Tragmast ausgerichteter Achse vorgesehen sind, welche frei auf dem Arbeitspodest bzw. der Abstützrampe verfahrbar sind.To this end, it is proposed according to the invention that the working scaffold be used as walkable, the angle of inclination of the building to be built conical or dome-shaped Building or building section adaptable staircase is formed, at the top Arranged at the end of two spaced-apart support profiles or rollers are, which are attached to a support ring arranged concentrically on the support or load-bearing mast or a support plate are guided, and at their lower, the Eegel- or dome foot facing end rollers with horizontal and radial to the support or support mast aligned axis are provided, which freely on the work platform or the support ramp are movable.

Durch diese erfindungsgemäßen Maßnahmen wird ein Arbeitsgerüst geschaffen, welches den Ein- und Ausschalvorgang wesentlich vereinfacht, da dieses Arbeitsgerüst über die ganze Höhe des Eegel- oder Kuppelmantels mit gleichem Abstand von diesem angeordnet werden kann, so daß die Schalung an allen Bereichen der Innenbegrenzung des Bauwerkes gleich gut zugänglich ist.By means of these measures according to the invention, a work scaffold is created, which considerably simplifies the shuttering and stripping process, since this work scaffold over the entire height of the leech or dome jacket at the same distance from it can be arranged so that the formwork on all areas of the inner boundary of the structure is equally easily accessible.

Einerseits müssen dadurch nicht zusätzliche Hilfsgeräte aufgestellt werden, wie zum Beispiel Leitern od. dgl., die besondere Gefahrenstellen bilden, und andererseits ist es dadurch nicht mehr erforderlich, ein komplett geschlossenes Arbeitspodest zu bilden, zumal ja der mittlere Beach dieses Bauwerkes von den Arbeitern gar nicht begangen werden muß. Das ansonsten erforderliche Podest wird hier also durch das Arbeitsgerüst ersetzt. Dieses Arbeitsgerüst kann in die erforderliche Stellung entsprechend dem Bortschritt der Einschalungs- bzw. Ausschalungsarbeiten um eine vertikale Achse verdreht werden, so daß eine kontinuierliche, gefahrlose Arbeit möglich ist.On the one hand, this means that additional auxiliary devices do not have to be set up such as ladders or the like that form special danger spots, and on the other hand it is no longer necessary to have a completely closed To form a work platform, especially since the middle beach of this building was used by the workers does not have to be committed at all. The otherwise required pedestal is here replaced by the working scaffold. This work scaffolding can be in the required Position according to the progress of the shuttering or shuttering work can be rotated about a vertical axis, so that a continuous, safe Work is possible.

Da außerdem dieses Arbeitsgerüst dem Neigungswinkel des zu errichtenden kegel- oder kuppelförmigen Bauwerkes bzw. Bauwerksabschnittes anpaßbar ist, können die günstigsten Arbeitsbedingungen geschaffen werden. Dies ist auch deshalb von besonderer Wichtigkeit, zumal ja solche Bauwerke eine recht beträchtliche Höhe aufweisen, und zwar gerade dann, wenn diese kegel- oder kuppelförmigen Bauwerksabschnitte den oberen Abschluß eines Faulbehälters für Kläranlagen bilden.In addition, since this work scaffolding the angle of inclination to be erected conical or dome-shaped structure or structure section is adaptable, can the most favorable working conditions are created. This is also why from of particular importance, especially since such structures are quite considerable in height, and especially when these conical or dome-shaped structural sections the Form the top of a digester for sewage treatment plants.

Weitere erfindungsgemäße Merkmale und besondere Vorteile werden in der nachstehenden Beschreibung anhand der Zeichnungen noch näher erläutert. Es zeigen: Fig. 1 einen Vetikalachnitt durch ein Bauwerk mit einem kegelförmigen Bauwerksabschnitt mit eingesetztem Arbeitsgerüst; Fig. 2 das Arbeitsgerüst gegenüber Big. 1 vergrö{',ert dargestellt in Seitenansicht; Fig. 3 ein Detail des Arbei-tsgerustes, wobei zwei verschiedene Neigungen desselben ersichtlich sind; Fig. 4 eine Aufbaumöglichkeit für das Arbeitsgerüst; die Fig. 5 und 6 eine Ausführungsvariante zum Anhängen des Arbeitsgerüstes an einem Tragring; Fig. 7 ein Ausführungsbeispiel eines Arbeitsgerüstes für einen kuppelförmigen Bauwerksabschnitt und Fig.' 8 eine Konstruktionsvariante zur Ausgestaltung nach Fig. 7.Further features according to the invention and particular advantages are described in the following description with reference to the drawings explained in more detail. Show it: 1 shows a vetical section through a structure with a conical structure section with inserted scaffold; Fig. 2 the work scaffold opposite Big. 1 enlarged shown in side view; 3 shows a detail of the working framework, with two different inclinations of the same can be seen; 4 shows a possible construction for the working scaffold; FIGS. 5 and 6 show an embodiment variant for attaching the Work scaffolding on a support ring; 7 shows an embodiment of a work scaffold for a dome-shaped building section and Fig. ' 8 a construction variant for the configuration according to FIG. 7.

Bei dem in Fig. 1 dargestellten Bauwerk handelt es sich um einen Faulbehälter für Kläranlagen, wobei lediglich der obere Abschnitt desselben gezeigt ist. Am unteren Ende eines solchen Bauwerkes ist in der Regel ein trichterförmiger Bauwerksabschnitt, auf welchen dann ein zylinderförmiger Banwerksabschnitt 1 folgt. Den oberen Abschluß eines solchen Faulbehälters bildet dann ein kegelförmiger Bauwerksabschnitt 2. Der tbersichtlichkeit halber ist hier das fertige Bauwerk dargestellt und es sind daher die Schalungselemente, wie zum Beispiel Schalungsträger, Schalungsplatten usw. nicht dargestellt. Im Zentrum des Bauwerkes 3 ist ein Stützmast 4 angeordnet, welcher vom Boden des Bauwerkes 3 bis zum oberen Ende desselben geführt ist. Dieser Stützmast 4 ist hier als Gitterträger ausgebildet, kann aber selbstverständlich jede andere Konstruktion haben. So wäre es auch denkbar, ein entsprechend dimensioniertes Rohr oder andere konstruktive Mittel vorzusehen. Auch wäre es denkbar, anstelle eines Stützmastes 4 einen Tragmast vorzusehen, welcher gegebenenfalls von oben her durch ein Traggerüst gehalten wird. Auch wäre es möglich, diesen Stützmast 4 über entsprechende Träger im Bereich eines Arbeitspodestes 5 an den Seitenwänden des Bauwerkes 3 abzustützen.The structure shown in Fig. 1 is a digester for sewage treatment plants, only the upper section of which is shown. At the bottom The end of such a structure is usually a funnel-shaped structure section, which is then followed by a cylindrical banwerk section 1. The upper end such a digester then forms a conical structural section 2. The For the sake of clarity, the finished structure is shown here and therefore it is the formwork elements, such as formwork beams, formwork panels, etc. do not shown. In the center of the structure 3, a support mast 4 is arranged, which is guided from the bottom of the structure 3 to the upper end of the same. This support mast 4 is designed here as a lattice girder, but can of course every have other construction. So it would also be conceivable to have a correspondingly dimensioned Provide pipe or other structural means. It would also be conceivable instead a support mast 4 to provide a support mast, which optionally from above is held by a shoring. It would also be possible to use this support mast 4 corresponding carrier in the area of a work platform 5 on the side walls of the Building 3 to support.

Innerhalb dieses Bauwerkes 3, zweckmäßig im Bereich des zylindrischen Bauwerkabschnittes 1 ist ein Arbeitspodest 5 vorgesehen, wobei auch hier der Ubersichtlichkeit halber die horizontalen Träger für dieses Arbeitspodest 5 nicht dargestellt sind. Dieses Arbeitspodest 5 und die entsprechenden Träger sind an vertikal verlaufenden Stützen 6 befestigt. Während des Baufortschrittes wird dieses hrbeitspodest 5 entlang der Stützen 6 nach oben bewegt und in den entsprechenden Stellungen wiederum fixiert.Within this structure 3, expediently in the area of the cylindrical Building section 1, a work platform 5 is provided, here too for the sake of clarity for the sake of the horizontal support for this work platform 5 are not shown. This work platform 5 and the corresponding support are on vertically extending Supports 6 attached. As construction progresses, this work platform 5 is along of the supports 6 moved upwards and again fixed in the corresponding positions.

Gemäß der vorliegenden Erfindung ist nun zusätzlich ein Arbeitsgerüst 7 vorgesehen, welches als begehbare Treppe ausgebildet ist. Dieses Arbeitsgerüst 7 kann den Neigungswinkel des zu errichtenden kogelförmigen Bauwerkabachnittes 2 angepaßt werden, so daß dieses Arbeitsgerüst 7 im wesentlichen parallel zur Neigung des kegelförmigen Bauwerkabschnittes 2 verläuft. Einerseits stützt sich dieses Arbeitsgerüst 7 auf dem Arbeitspodest 5 und andererseits an einem Tragring 8 ab. Der Tragring 8, welcher auch als Tragplatte ausgeführt werden könnte, ist am Stützmast 4 höhenverstellbar befestigt.According to the present invention, there is now also a work scaffold 7 is provided, which is designed as a staircase that can be walked on. This scaffolding 7 can determine the angle of inclination of the spherical building section 2 be adjusted, so that this work frame 7 is substantially parallel to the inclination of the conical building section 2 runs. On the one hand, this work frame is supported 7 on the work platform 5 and on the other hand on a support ring 8. The support ring 8, which could also be designed as a support plate, is height-adjustable on the support mast 4 attached.

Dieses Arbeitsgerüst 7 hat eine den Arbeitsbedingungen angepaßte horizontale Breite, wobei der gesamte Innenbereich des kegelförmigen Bauwerksabschaittes 2 dadurch erreicht werden kann, indem dieses Arbeitsgerüst 7 um die vom Stützmast 4 bzw. vom Tragring 8 gebildete vertikale Achse 9 verdrehbar ist. Es kann so jeder Bereich innerhalb des kegelförmigen Bauwerkabschnittes 2 erreicht werden, wobei die Arbeit dadurch wesentlich erleichtert wird, als über die ganze Länge der Schalungsträger bzw. der anzuordnenden Schalungsplatten die gleichen Arbeitsbedingungen vorliegen, da die zu errichtende Schalung immer tber deren ganze Länge den gleichen Abstand von dem Arbeitsgerüst 7 aufweist.This work scaffold 7 has a horizontal adapted to the working conditions Width, with the entire inner area of the conical building section 2 thereby can be achieved by this work scaffold 7 by the support mast 4 or from Support ring 8 formed vertical axis 9 rotatable is. It can so that every area within the conical building section 2 can be reached, whereby the work is much easier than over the entire length of the Formwork beams or the formwork panels to be arranged have the same working conditions because the formwork to be erected is always the same over its entire length Has a distance from the work scaffold 7.

Es ist zweckmäßig, ein entsprechendes kreisringförmiges Arbeitspodest 5 zumindest im Bereich des Kegelfußes bzw.It is advisable to have a corresponding circular work platform 5 at least in the area of the cone base or

unterhalb desselben vorzusehen, um dadurch eine begehbare Fläche zu schaffen und andererseits um ein einfaches Weiterdrehen durch einfaches Verschieben des unteren Endes des Arbeitsgerüstes 7 zu ermöglichen. Es wäre jedoch durchaus möglich, lediglich eine entsprechende umfangsgeschlossene Abstützrampe am zylinderförmigen Bauwerksabschnitt 1 vorzusehen, auf welchem dann das untere Ende des Arbeitsgerüstes 7 abgestützt wird.to be provided below the same in order to thereby create a walkable area create and on the other hand to a simple further rotation by simply moving the lower end of the work scaffold 7 to enable. However, it would be possible, only a corresponding circumferentially closed support ramp on the cylindrical Provide structural section 1, on which then the lower end of the work scaffolding 7 is supported.

Am oberen, der Kegelspitze zugewandten Ende des Arbeitsgerüstes sind zwei mit Abstand voneinander angeordnete Abstützprofile 10 vorgesehen, welche an dem konzentrisch am Stützmast 4 angeordneten Tragring 8 verschiebbar geführt sind. Anstelle dieser Abstützprofile können selbstverständlich auch entsprechende Abstützrollen vorgesehen werden.At the upper end of the work scaffold facing the cone tip two spaced-apart support profiles 10 are provided, which on the support ring 8 arranged concentrically on the support mast 4 are guided displaceably. Instead of these support profiles, corresponding support rollers can of course also be used are provided.

Auch wäre es möglich, anstelle der zwei mit Abstand voneinander angeordneten Abstützprofile 10 eine Abstützschiene vorzusehen, welche bogenförmig entsprechend dem Verlauf des Tragringes 8 ausgebildet ist.It would also be possible instead of the two spaced apart Support profiles 10 to provide a support rail, which is arcuate accordingly the course of the support ring 8 is formed.

Am unteren, dem Kegelfuß zugewandten Ende desArbeitsgerüstes sind wenigstens zwei mit Abstand voneinander angeordnete Laufrollen 11 vorgesehen, welche um eine horizontale und radial zum Stützmast 4 ausgerichtete Drehachse 12 aufweisen. Diese Laufrollen 11 sind auf dem Arbeitspodest 5 frei verfahrbar. Um dieses Arbeitsgerüst in eine neue Position zu bringen, muß also lediglich das untere Ende desselben entsprechend entlang des Arbeitspodestes 5 verschoben werden, so daß ein Verdrehen um die vertikale Mlttelachse 9 entS ng des Tragringes 8 erfolgt. Es kann so umfangsgeschlossen der gesamte Innenbereich des kegelförmigen Bauwerkabsohnittes 2 erfaßt werden.At the lower end of the working scaffold facing the cone base at least two spaced apart rollers 11 are provided, which have about a horizontal axis of rotation 12 which is aligned radially with respect to the support mast 4. These rollers 11 are on the work platform 5 freely movable. In order to move this work scaffold into a new position, all that has to be done is lower end of the same are moved accordingly along the work platform 5, so that a rotation about the vertical central axis 9 takes place along the support ring 8. The entire inner area of the conical building section can be closed in this way 2 can be detected.

Ein wesentlicher Vorteil des erfindungsgemäßen Arbeitsgerüstes liegt noch darin, daß dieses in einfacher Weise dem Neigelgswinkel des kegelförmigen Bauwerksabschnittes 2 angepaßt werden kann. Es kann also dasselbe Arbeitsgerüst für nterschiedliche Neigungen solcher Bauwerksabsobnitte eingesetzt werden, ohne daß Umkonstruktionen erforderlich wären. Zu diesem Zweck ist vorgesehen, daß die Absitzprofile 10 bzw. die entsprechenden Abstützrollen und die Laufrollen 11 am Tragarmen 13 und 14 gehalten sind, welche um horizontale, quer zur Längserstreckung des Arbeitsgerüstes 7 verlaufende Achsen 15 bzw. 16 mit dem Arbeitsgerüst 7 schwenkbar verbunden sind. In der Neigung des Qrbeitsgerüstes 7 angepaßter Stellung, in welcher diese Tragarme 13 und 14 in annähernd vertikaler Stellung ausgerichtet sind, können diese am Arbeitsgerüst 7 arretiert werden. Zu diesem Zweck sind abstehende Arme 17 und 18 vorgesehen, welche zum Beispiel mehrere mit Abstand voneinander angeordnete Bohrungen 19 aufweisen können. Durch Einsetzen von Sicherungsstiften können dann diese Arme 17 bzw.18 am Arbeitsgerüst 7 fix erst werden.A major advantage of the work scaffolding according to the invention lies still in the fact that this is the inclination angle of the conical building section in a simple manner 2 can be customized. The same working structure can therefore be used for different Slopes of such building sections are used without reconstruction would be required. For this purpose it is provided that the seating profiles 10 or the corresponding support rollers and the rollers 11 are held on the support arms 13 and 14 are, which to horizontal, transverse to the longitudinal extent of the work frame 7 running Axes 15 and 16 are pivotably connected to the work frame 7. In the slope the Qrbeitsgerüstes 7 adapted position in which these support arms 13 and 14 in are aligned approximately vertical position, these can on the work scaffold 7 be locked. For this purpose, protruding arms 17 and 18 are provided which for example, several bores 19 arranged at a distance from one another can. By inserting locking pins, these arms can then 17 or 18 am Working scaffold 7 must first be fixed.

Durch diese Einstellmöglichkeit kann das Arbeitsgerüst 7 aus einer starren Profilkonstruktion gefertigt werden, ohne daß jedesmal eine Anpassung an verschiedene Neigungen erforderlich wäre. Es kann daher auch mit dieser Profilkonstruktion 21 beidseitig der Treppenstufen 20 ein Schutzgeländer 22 angeordnet werden, welches fest mit der Profilkonstruktion 21 verbunden ist. Das gesamte Arbeitsgerüst kann gegebenenfalls zum leichteren Aufbau und zur leichteren Entfernung aus dem Bauwerk 3 zerlegbar ausgebildet werden, wobei auch nur die Schutzgeländer 22 gegebenenfalls entfernt werden können.By this setting option, the work scaffold 7 from a Rigid profile construction can be manufactured without an adjustment to each time different inclinations would be required. It can therefore also be used with this profile construction 21 on both sides of the steps 20 a guardrail 22 are arranged, which firmly with the profile construction 21 is connected. The entire Work scaffolding can be used for easier assembly and removal if necessary be formed from the structure 3 can be dismantled, with only the guardrail 22 can be removed if necessary.

Eine solche zerlegbare Ausgestaltung des Arbeitsgerüstes kann der Fig. 4 entnommen werden. Die Profilkonstruktion ist hier aus mehreren, vorzugsweise gleich langen und in Längsrichtung des Arbeitsgerüstes aufeinanderfolgenden Einzelabschnitten 30 gebildet, welche miteinander verschraubt werden können. Eine solche Zerlegbarkeit ist insbesondere deshalb von Vorteil, weil ja dieses Arbeitsgerüst durch die oben freibleibende Öffnung des kegel- oder eines kuppelförmigen Bauwerksabschnittes wiederum ins Freie befördert werden müssen nach Beendigung der Bauarbeiten.Such a dismountable configuration of the work scaffolding can Fig. 4 can be taken. The profile construction here is made up of several, preferably individual sections of the same length and successive in the longitudinal direction of the work scaffolding 30 formed, which can be screwed together. Such a decomposability is particularly advantageous because yes this work scaffolding by the above remaining free opening of the conical or a dome-shaped building section must be transported outside after completion of the construction work.

Eine konstruktive Variante wäre noch darin gelegen, daß das Arbeitsgerüst aus tragfähigen Seitenteilen besteht, die jeweils aus der unteren Profilkonstruktion 21 und dem Schutzgeländer 22 gebildet werden. Es könnte so ein in sich steifer Träger gebildet werden. Zwischen den Profilkonstruktionen 21 werden dann noch entsprechende Abstandhalter eingesetzt, wobei die Funktion dieser Abstandhalter selbstverständlich auch von den Trittplatten 23 der Tre;)penstuSen 20 übernommen werden könnte.A constructive variant would be that the working scaffold consists of stable side parts, each from the lower profile construction 21 and the guardrail 22 are formed. It could be such a rigid carrier are formed. Between the profile structures 21 are then appropriate Spacers used, the function of these spacers of course could also be taken over by the tread plates 23 of the stairs 20.

Durch die vorliegende Erfindung wird auch ermöglicht, die Treppenstufen 20 den verschiedenen Neigungen des Arbeitsgerüstes 7 anzupassen. Es ist dadurch gewährleistet, daß die Trittplatten 23 der Treppenstufen 20 stets in horizontaler Lage ausgerichtet sind, so daß immer ein R fahrloses Arbeiten gewährleistet ist. Die Trittplatten 23 sind zu diesem Zweck im Bereich ihrer rückwärtigen Längsbegrenzung um eine horizontale Achse 24 verschwenkbar an der Profilkonstruktion 21 gehalten. In konstruktiver Hinsicht kann dies so gelöst werden, daß die Trittplatten 23 an ihren Seitenrändern in U-förmigen Tragteilen 25 gehalten sind, wobei diese Tragteile 25 einen abstehenden Arm 26 aufweisen, welche um die Achse 24 verschwenkbar an der Tragkonstruktion 21 gehalten ist. Anstelle von U-förmigen Tragteilen 25 könnten selbstverständlich auch L-förmige Tragteile vorgesehen werden, wobei dann auf jeden Fall eine gegenseitige Verschraubung der Trittplatten 23 und der Tragteile 25 erforderlich ist.The present invention also enables the stairs 20 to adapt to the various inclinations of the work scaffold 7. It is through it ensures that the tread plates 23 of the stairs 20 are always in a horizontal position Position are aligned so that an R driving-free work is always guaranteed. For this purpose, the step plates 23 are in the region of their rear longitudinal limit pivotable about a horizontal axis 24 on the profile construction 21 held. From a structural point of view, this can be solved in such a way that the step plates 23 are held at their side edges in U-shaped support parts 25, these Support parts 25 have a protruding arm 26 which can be pivoted about the axis 24 is held on the support structure 21. Instead of U-shaped support parts 25 could Of course, L-shaped support parts are also provided, in which case each If a mutual screwing of the tread plates 23 and the support parts 25 is required is.

Die Trittplatten 23 sind also frei um eine horizoxile Achse 24 verschwenkbar. Um diese Trittplatten 23 nun in der erforderlichen Horizontallage zu fixieren, sind die Stufenblenden bildende Stützplatten 27 vorgesehen, welche zwischen die aufenanderfolgenden Trittplatten 23 eingesetzt sind.The step plates 23 are therefore freely pivotable about a horizontal axis 24. In order to fix these step plates 23 in the required horizontal position, are the step panels forming support plates 27 provided, which between the successive Step plates 23 are used.

Wenn nun eine andere Neigung für das Arbeitsgerüst 7 erforderlich ist, dann ist es lediglich notwendig, entsprechend höhere Stützplatten 27' (strichliert in Fig. 3 dargestellt) einzusetzen, um wiederum eine Ausrichtung der Trittplatten 23 in einer horizontalen Ebene zu erreichen. Selbstverständlich ist es möglich, durch entsprechende Verbindungselemente diese Stützplatten 27 bzw. 27' und die Trittplatten 23 gegenseitig zu fixieren. Anstelle von Stützplatten 27 können selbstverständlich auch entsprechende Stüt zpr ofile vorgesehen werden, die nicht unbedingt über die ganze Länge der Trittplatten 23 durchgehend verlaufen müssen.If a different inclination is now required for the working scaffold 7 is, then it is only necessary to use correspondingly higher support plates 27 '(dashed lines shown in Fig. 3) to in turn align the step plates 23 in a horizontal plane. Of course it is possible by means of corresponding connecting elements, these support plates 27 or 27 'and the step plates 23 to fix each other. Instead of support plates 27 can of course also appropriate support zpr ofile are provided, which do not necessarily have the the entire length of the tread plates 23 must run continuously.

Das erfindungsgemäße Arbeitsgerüst ist also individuell einsetzbar für alle Neigungswinkel bei der Errichtung kegelförmiger Bauwerke oder Bauwerksabschnitte. Die einzigen Teile, die für verschiedene Neigungen ausgewechselt werden müssen, sind die Stützplatten 27 bzw. die entsprechenden Stützprofile. Das erfindungsgemäße Arbeitsgerüst ist also nicht nur in Hinblick auf eine universelle Einsetzbarkeit und zur Erzielung einer besseren Arbeitsbedingungbeim Ein-und Ausschalen solcher Bauwerke von Vorteil, sondern auch der konstruktive Aufbau des Arbeitsgerüstes trägt wesentlich dazu bei, die Möglichkeiten gegenüber den bisher erforderlichen flaßnahmen zum Ein- und Ausschalen solcher Bauwerke zu verbessern.The work scaffold according to the invention can therefore be used individually for all angles of inclination when erecting conical structures or building sections. The only parts that need to be changed for different slopes are the support plates 27 or the corresponding support profiles. The inventive So work scaffolding is not just in terms of universal applicability and to achieve better working conditions when shuttering and stripping such structures This is an advantage, but the structural design of the work scaffolding also contributes significantly this contributes to the possibilities of entering into and to improve stripping of such structures.

Aus den Fig. 5 und 6 ist ein Ausführungsbeispiel des Arbeitsgerüstes ersichtlich, bei welchem es insbesondere um eine andere Aufhängung des oberen Endes desselben an dem Tragring 6 geht. Die Abstützung des oberen Endes erfolgt hier zu beiden Seiten des Stützmastes 4, wobei eine durch am Arbeitsgerüst 7 angeordnete Bügel 31, welche den ragring 6 übergreifen, geführte Achse 32 durch die vertikale buchse 9 des Stützmastes 4 geführt ist. Anstelle der Bügel 31 können selbstverständlich auch entsprechende Rollen vorgesehen werden. Bei einer derartigen Ausgestaltung ergibt sich insbesondere der Vorteil, daß auf den Stützmast 4 keine exzentrischen Belastungen einwirken. Die vom Arbeitsgerüst 7 auf den Stützmast 4 einwirkenden Kräfte können keine Biege- oder Knickmomente auf den Stützmast 4 ausüben.From Figs. 5 and 6 is an embodiment of the work scaffold can be seen in which it is in particular a different suspension of the upper end same goes on the support ring 6. The support of the upper end takes place here too both sides of the support mast 4, one being arranged on the work frame 7 Bracket 31, which overlap the ring 6, guided axis 32 through the vertical socket 9 of the support mast 4 is performed. Instead of the bracket 31 can of course appropriate roles are also provided. With such a configuration there is in particular the advantage that there are no eccentric on the support mast 4 Act loads. The ones acting on the support mast 4 from the work scaffold 7 Forces cannot exert any bending or buckling moments on the support mast 4.

Bei einer solchen Ausgestaltung ist es zweckmäßig, wenn die Breite des Arbeitsgerüstes 7 gleich oder größer ist als der Durchmesser des Tragringes 6. Es ist dadurch selbstverständlich auch eine entsprechend große Arbeitsbreite zum Einschalen bzw. Ausschalen des Bauwerkes gegeben. Das Arbeitsgerüst 7 umfaßt daher bei einer derartigen Ausgestaltung den Tragring 6 zumindest auf seinem halben Umfang, da die Bügel 31 ja so angeordnet sind, daß deren gennsame Achse durch den Mittelpunkt des Tragringes führt. Bei einer solchen Ausgestaltung ist es besonders zweckmäßig, wenn die Aufhängung des oberen Endes des Arbeitsgerüstes 7 im Bereich des oberen, einen Handlauf 33 des Schutzgeländers 22 bildenden Abschnitt der Profilkonstruktion vorgesehen ist.In such a configuration, it is useful if the width of the work frame 7 is equal to or greater than the diameter of the support ring 6. It is of course also a correspondingly large working width given for shuttering or stripping the building. The work frame 7 includes therefore, in such a configuration, the support ring 6 at least on its half Scope, since the bracket 31 are so arranged that their gennsame axis through the Center of the support ring leads. It is special with such a configuration useful if the suspension of the upper end of the work scaffold 7 in the area of the upper section of the profile construction which forms a handrail 33 of the guardrail 22 is provided.

Es können dann insbesondere bei Verwendung von aneinander geschraubten Normteilen über die ganze Länge des Arbeitsgerüstes 7 gleiche Teile verwendet werden, zumal äa lediglich an diesem obersten Endteil die Bügel 31 oder auch Laufrollen befestigt werden müssen. Es ist dann lediglich -der unterste Geilabschnitt des Arbeitsgerüstes von einer anderen Konstruktion, da dort ein in der erforderlichen Schräglage des Arbeitsgerüstes annähernd vertikaler Abschluß erforderlich ist, damit das Podest 5 entsprechend erreicht oder begangen werden kann.It can then, especially when using screwed together Standard parts are used over the entire length of the scaffolding 7 identical parts, especially at this uppermost end part only the bracket 31 or rollers need to be attached. It is then only the lowest Geil section of the work scaffolding of a different construction, as there is one in the required inclined position of the Scaffolding approximately vertical completion is required so that the pedestal 5 can be reached or committed accordingly.

Bei der Ausführung nach Fig. 7 handelt es sich um eine Konstruktion, welche insbesondere für kuppelförmige oder in irgendeiner Form gebogene Bauwerksabschnitte eingesetzt werden kann. Das Arbeitsgerüst selbst verläuft dabei annähernd bogenförmig, wobei auch hier eine Anpassung an den entsprechenden Bauwerksabschnitt möglich ist. Bei einer solchen Ausgestaltung werden dann die Einzelabschnitte 30 nicht direkt an ihren Rändern miteinander verschraubt, sondern es kommen Zwischenstücke 34 zwischen diese Einzelabschnitte 30, deren seitliche Begrenzungen oder Begrenzungsabschnitte derselben einen spitzen Winkel zueinander einschließen. Dadurch wird erreicht, daß die aufenanrf olgenden Einzelabschnitte der Profilkonstruktion einen stumpfen Winkel miteinander einschließen, so daß dann ein annähernd bogenförmiger Verlauf des Arbeitsgerüstes erzielbar ist.The embodiment according to FIG. 7 is a construction which are particularly suitable for dome-shaped or curved sections of the building can be used. The working scaffold itself runs approximately in the shape of a curve, Here, too, an adaptation to the corresponding structural section is possible. With such a configuration, the individual sections 30 are then not directly screwed together at their edges, but there are intermediate pieces 34 between these individual sections 30, their lateral boundaries or boundary sections the same include an acute angle to each other. It is thereby achieved that the following individual sections of the profile construction form an obtuse angle include each other, so that then an approximately arcuate course of the work scaffolding is achievable.

Gerade durch die Möglichkeit, die Trittplatten 23 in einer horizontalen Ebene auszurichten und in dieser Lage zu arretieren, kann auch bei einem solcherart aufgebauten Arbeitsgerüst ein einwandfrei begehbarer Treppenlauf erzielt werden.Precisely because of the possibility of the step plates 23 in a horizontal position Aligning the plane and locking it in this position can also be done with one of these A perfectly accessible flight of stairs can be achieved with the work scaffolding built up.

Fig. 8 zeigt eine Ausführungsvariante zur Erreichung des in Fig. 7 aufgezeigten Zieles. Hier wird zwischen aufeinanderfolgende Einzelabschnitte 30 ebenfalls ein Zwischenstück 34 eingesetzt, welches bei dieser Ausführungsvariante aus zwei rechtwinklig miteinander verbundenen Profilen 35 und 36 besteht. Je nach Länge des Profilabschnittes 35 wird dann eine größere oder kleinere Krümmung des Arbeitsgerüstes erreicht. Es wäre in diesem Zusammenhang auch möglich, lediglich ein Profil stück 35 einzusetzen, ohne ein entsprechendes Profil 36, so daß dann die unteren Abschnitte der einander berührenden Einzelabschnitte 30 der Profilkonstruktion direkt miteinander verschraubt werden können, wogegen lediglich beim oberen Abschnitt ein Zwischenstück vorgesehen ist. Um jedoch eine ordnungsgemäße Verschraubung der aufeinanderfolgenden Einzelabschnitte 30 zu gewahrleisten, müßte auch im unteren Bereich dieser Einzelabschnitte 30 ein entsprechend keilförmiges Stück eingesetzt werden.FIG. 8 shows an embodiment variant for achieving the in FIG. 7 indicated goal. Here, between successive individual sections 30 also an intermediate piece 34 used, which in this Design variant of two profiles 35 and 35 connected to one another at right angles 36 exists. Depending on the length of the profile section 35 is then a larger or smaller Curvature of the scaffolding reached. In this context it would also be possible only use a profile piece 35 without a corresponding profile 36, so that then the lower portions of the contacting individual sections 30 of the Profile construction can be screwed together directly, whereas only an intermediate piece is provided in the upper section. However, in order to have a proper To ensure screwing of the successive individual sections 30 would have to also in the lower area of these individual sections 30 a correspondingly wedge-shaped Pieces can be used.

Das erfindungsgemäße Arbeitsgerüst ist also universell einsetzbar, allen Situationen anpaßbar und kann auch in einfacher Weise aufgebaut und demontiert werden, was insbesondere bei der Fertigung von Faulbehältern beim Kläranlagenbau von wesentlichem Vorteil ist. Selbstverständlich können derartige Arbeitsgerüste überall dort, wo kegel-oder kuppelförmige Bauwerke oder Bauwerksabschnitte gefertigt werden müssen, eingesetzt werden.The working scaffold according to the invention can therefore be used universally, Adaptable to all situations and can also be easily assembled and disassembled especially in the manufacture of digesters for sewage treatment plants is of significant advantage. Of course, such work scaffolding wherever conical or dome-shaped buildings or building sections are manufactured must be used.

LeerseiteBlank page

Claims (12)

Patentansprüche: 1. Abeitsgerüst zum Ein- und Ausschalen der Innenbegrenzung kegel- oder kuppelförmiger Bauwerke oder Bauwerksabschnitte, wobei im Zentrum des Bauwerkes ein vertikal verlaufender Stütz- bzw. tragmast angeordnet und ein Arbeitspodest bzw. eine Bbstützrampe zumindest im Bereich des gegel- oder Euppelfußes des zu errichtenden Bauwerkes bzw. Bauwerksabschnittes vorgesehen ist, und wobei das Arbeitsgerüst um die vom Stütz- bzw. Tragmast gebildete vertikale Achse verdrehbar ist, dadurch gekennzeichnet, daß das Arbeitsgerüst (-7) als begehbare, dem Neigungswinkel des zu errichtenden Eegel- oder kuppelförmigen Bauwerkes (3) bzw. Bauwerkabschnittes (2) anpaßbare Treppe ausgebildet ist, an deren oberem Ende zwei mit Abstand voneinander angeordnete Abstützprofile (10) oder -rollen angeordnet sind, welche an einem konzentrisch am Stütz- bzw. Tragmast (4) angeordneten Tragring (8) bzw. einer Tragplatte verschiebbar geführt sind, und an deren unterem, dem Eegel- bzw. Euppelfuß zugewandten Ende Laufrollen (11) mit horizontal und radial zum Stütz- bzw. Tragmast (4) ausgerichteter Achse (12) vorgesehen sind, welche frei auf dem Arbeitspodest (5) bzw. der Abstützrampe verfahrbar sind. Claims: 1. Work scaffolding for shuttering and stripping the inner boundary conical or dome-shaped buildings or building sections, with the center of the Structure a vertically extending support or load-bearing mast and a work platform or a support ramp at least in the area of the gel or Euppelfußes to be built Building or building section is provided, and the work scaffolding around the vertical axis formed by the supporting or supporting mast is rotatable, characterized in that that the working scaffold (-7) as accessible, the angle of inclination of the to be erected Eegel-shaped or dome-shaped building (3) or building section (2) adjustable stairs is formed, at the upper end of two spaced apart support profiles (10) or rollers are arranged, which are arranged on a concentric on the support or load-bearing mast (4) arranged support ring (8) or a support plate are displaceably guided, and at the lower end facing the Eegel or Euppelfuß with rollers (11) provided horizontally and radially to the support or mast (4) aligned axis (12) which can be moved freely on the work platform (5) or the support ramp. 2. Arbeitsgerüst nach Anspruch 1, dadurch gekennzeichnet, daß die Abstützprofile (10) oder -rollen und die Laufrollen (11) an um horizontale, quer zur Längserstreckung des Arbeitsgerüstes (7) verlaufende Achsen (15, 16) verschwenkbaren Tragarmen (13, 14) angeordnet sind, weite in der Neigung des Arbeitsgerüstes (7) angepaßter, annähernd vertikalen Stellung am Arbeitsgerüst (7) arretierbar sind.2. Working scaffold according to claim 1, characterized in that the Support profiles (10) or rollers and the rollers (11) to horizontal, transverse axles (15, 16) extending in the longitudinal direction of the work frame (7) can be pivoted Support arms (13, 14) are arranged, wide in the inclination of the work scaffold (7) adapted, approximately vertical position on the work frame (7) can be locked. 3. Arbeitsgerüst nach Anspruch 1, dadurch gekennzeichnet, daß es aus einer Profilkonstruktion (21, 22) gefertigt ist, welche aus mehreren, vorzugsweise gleich langen, in Langsrichtung des Arbeitsgeriistes (7) aufeinenderfolgenden Einzelabschnitten (30) gebildet ist.3. Working scaffold according to claim 1, characterized in that it consists of a profile structure (21, 22) is made, which consists of several, preferably of the same length, one after the other in the longitudinal direction of the working framework (7) Individual sections (30) is formed. 4. Arbeitsgerüst nach den Ansprüchen 1 und 3, dadurch gekennzeichnet, daß zu beiden Seiten der Treppenstufen (20) ein mit der Profilkonstruktion fest verbundenes und einen Teil desselben bildendes Schutzgeländer (22) angeordnet ist.4. Working scaffold according to Claims 1 and 3, characterized in that that on both sides of the steps (20) a fixed with the profile construction connected and part of the same forming protective railing (22) is arranged. 5. Arbeitsgerüst nach den Ansprüchen 3 und 4, gekennzeichnet durch zwischen die Einzelabschnitte (30) der Profilkonstruktion (21, 22) einsetzbare Zwischenstücke (34) mit spitzwinklig zueinander verlaufenden seitlichen Begrenzungen oder Begrenzungsabschnitten.5. Working scaffold according to claims 3 and 4, characterized by Intermediate pieces that can be inserted between the individual sections (30) of the profile construction (21, 22) (34) with lateral boundaries or boundary sections running at an acute angle to one another. 6. Arbeitsgerüst nach Anspruch 1 und einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, daß das obere Ende desselben zu beiden Seiten des Stütz- oder Tragmastes (4) abgestützt ist, wobei eine durch an einem Tragring (6) abgestützte Bügel (31) oder Rollen gelegte Horizontalachse (32) durch die vertikale Achse (9) des Stütz-bzw. Tragmastes (4) führt.6. Working scaffold according to claim 1 and one of the preceding claims, characterized in that the upper end of the same on both sides of the support or support mast (4) is supported, one supported by on a support ring (6) Brackets (31) or rollers laid horizontal axis (32) through the vertical axis (9) of the support or. Support mast (4) leads. 7. Arbeltsgerüst nach den Ansprüchen 1 und 6, dadurch gekemlzeichnet, daß die Breite desselben gleich oder größer als der Durchmeßser des Tragringes (6) bzw. der Tragplatte ausgeführt ist, wobei der oberste Abschnitt des Arbeitsgerüstes (7) zumindest den halben Umfang des Tragringes (6) bzw. der Tragplatte umfaßt.7. Work frame according to claims 1 and 6, characterized in that that the width of the same is equal to or greater than the diameter of the support ring (6) or the support plate is executed, wherein the uppermost section of the work scaffold (7) comprises at least half the circumference of the support ring (6) or the support plate. 8. Arbeitsgerüst nach den Ansprüchen 6 und 7, dadurch gekennzeichnet, daß die Aufhängung des oberen Endes desselben an dem Tragring (6) bzw. der Tragplatte im Bereich des oberen, einen Handlauf (33) des Schutzgeländers (22) bildenden Abschnittes der Profilkonstruktion (21) vorgesehen ist.8. Working scaffold according to claims 6 and 7, characterized in that that the suspension of the upper end of the same on the support ring (6) or the support plate in the area of the upper section forming a handrail (33) of the guardrail (22) the profile construction (21) is provided. 9. Arbeitsgerüst nach Anspruch 1 und einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, daß die Trittplatten (23) der Treppenstufen (20) an der starren Profilkonstruktion in einer horizontalen Ebene ausrichtbar sind. 9. Working scaffold according to claim 1 and one of the preceding claims, characterized in that the tread plates (23) of the stairs (20) on the rigid profile construction can be aligned in a horizontal plane. 10. Arbeitsgerüst nach Anspruch 9, dadurch gekennzeichnet, daß die Trittplatten (23) der Treppenstufen (20) im Bereich ihrer rückwärtigen Längsbegrenzung in an sich bekannter Weise um eine horizontale Achse (24) verschwenkbar an der Profilkonstruktion (21) gehalten sind.10. Working scaffold according to claim 9, characterized in that the Step plates (23) of the steps (20) in the area of their rear longitudinal boundary in a manner known per se about a horizontal axis (24) pivotable on the profile structure (21) are held. 11. Arbeitsgerüst nach den Ansprüchen 9 und 10, dadurch gekennzeichnet, daß die Trittplatten (23) der Treppenstufen (20) an ihren Seitenrändern in U-oder L-förmigen Tragteilen (25) gehalten sind, wobei diese Tragteile (25) um eine horizontale Achse (24) verschwenkbar an der Profilkonstruktion (21) gehalten sind.11. Working scaffold according to claims 9 and 10, characterized in that that the tread plates (23) of the stairs (20) at their side edges in U or L-shaped support parts (25) are held, these support parts (25) around a horizontal Axis (24) are pivotably held on the profile structure (21). 12. Arbeitsgerüst nach den Ansprüchen 9 bis 11, dadurch gekennzeichnet, daß zwischen den aufeinanderfolgenden Trittplatten (23) der Treppenstufen (20) die Stufenblenden bildende Stützplatten (27, 27') oder -profile in entsprechend dem Neigungswinkel des Arbeitsgerüstes (7) angepaßter Höhe einsetzbar sind.12. Working scaffold according to claims 9 to 11, characterized in that that between the successive tread plates (23) of the stairs (20) the Step panels forming support plates (27, 27 ') or profiles in accordance with the The angle of inclination of the work scaffolding (7) adapted height can be used.
DE19823242570 1981-12-01 1982-11-18 Scaffolding Granted DE3242570A1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
AT0516881A AT374544B (en) 1981-12-01 1981-12-01 WORKING SCAFFOLDING FOR SHELLING AND REMOVING THE INTERNAL LIMITATION OF CONE OR DOME SHAPED CONSTRUCTIONS OR CONSTRUCTION SECTIONS

Publications (2)

Publication Number Publication Date
DE3242570A1 true DE3242570A1 (en) 1983-06-09
DE3242570C2 DE3242570C2 (en) 1993-08-05

Family

ID=3572707

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19823242570 Granted DE3242570A1 (en) 1981-12-01 1982-11-18 Scaffolding

Country Status (3)

Country Link
AT (1) AT374544B (en)
CH (1) CH660616A5 (en)
DE (1) DE3242570A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1996024733A1 (en) * 1995-02-08 1996-08-15 Otto Heinzle Shuttering with scaffolding for use in the construction of an egg-shaped digestion container with a dual-curve wall
WO2018098330A1 (en) * 2016-11-23 2018-05-31 Zavitz Bryant Method and apparatus for constructing a concrete structure in stages
CN111335605A (en) * 2020-03-19 2020-06-26 重庆科技学院 Integral adjustable scaffold for slope construction

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110259171B (en) * 2019-05-30 2021-04-06 郑州工程技术学院 Dome drawing repair system and method
US12098021B2 (en) 2022-01-19 2024-09-24 Dutchland, Llc Concrete tank

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2537830A1 (en) * 1974-08-29 1976-03-11 Holterbosch Engineering B V FRAMEWORK
US3960242A (en) * 1972-12-01 1976-06-01 Whiting Corporation Orbital service bridge
CH585326A5 (en) * 1974-12-06 1977-02-28 Habegger Ag Maschf
DE7829092U1 (en) * 1978-09-29 1979-02-08 Schliephacke, Heinrich, Dipl.-Ing., 4030 Ratingen FRAMEWORK FOR STAIRCASE AND AE. APPLICATION AREAS

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3960242A (en) * 1972-12-01 1976-06-01 Whiting Corporation Orbital service bridge
DE2537830A1 (en) * 1974-08-29 1976-03-11 Holterbosch Engineering B V FRAMEWORK
CH585326A5 (en) * 1974-12-06 1977-02-28 Habegger Ag Maschf
DE7829092U1 (en) * 1978-09-29 1979-02-08 Schliephacke, Heinrich, Dipl.-Ing., 4030 Ratingen FRAMEWORK FOR STAIRCASE AND AE. APPLICATION AREAS

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1996024733A1 (en) * 1995-02-08 1996-08-15 Otto Heinzle Shuttering with scaffolding for use in the construction of an egg-shaped digestion container with a dual-curve wall
WO2018098330A1 (en) * 2016-11-23 2018-05-31 Zavitz Bryant Method and apparatus for constructing a concrete structure in stages
US10435913B2 (en) 2016-11-23 2019-10-08 Tindall Corporation Method and apparatus for constructing a concrete structure in stages
CN111335605A (en) * 2020-03-19 2020-06-26 重庆科技学院 Integral adjustable scaffold for slope construction

Also Published As

Publication number Publication date
AT374544B (en) 1984-05-10
CH660616A5 (en) 1987-05-15
ATA516881A (en) 1983-09-15
DE3242570C2 (en) 1993-08-05

Similar Documents

Publication Publication Date Title
DE2040328C3 (en) Mobile interior formwork for concrete and reinforced concrete structures
WO2008148637A1 (en) Self-climbing system and method for pouring concrete for a girder and/or mounting a prefabricated section using a self-climbing system
EP0270623B1 (en) Shuttering
EP0098962B1 (en) Erecting scaffold for shutterings for circular structures of concrete or the like
DE3036306A1 (en) METHOD FOR ASSEMBLING AND STRETCHING CEILING FORMWORK FOR CONCRETE WORKS AND CEILING FORMING FOR IMPLEMENTING THE METHOD
DE3242570A1 (en) Scaffolding
DE2015940C3 (en) Device for adjusting sliding formwork
DE2759088C2 (en) Climbing scaffold with climbing formwork for the production of a reinforced concrete wall
EP0668953B1 (en) Process and devices for changing the vertical distance between the roof truss and the top ceiling of a building
DE10212305A1 (en) Procedure for erecting of tower for wind power plant from prefabricated elements, involves lifting and mounting elements by assembly unit which is moved by walking support
EP0138196B1 (en) Method of erection of buildings consisting of casting materials in particular of concrete and device for carrying out the method
AT4624U1 (en) ADJUSTABLE WORKSTAGE
AT411079B (en) METHOD FOR THE CONSTRUCTION OF A CONSTRUCTION WITH A CONCRETE WALL CONTAINED IN A CIRCUMFERENCE
DE2402683C3 (en) Climbing formwork
DE2462066A1 (en) Climbing formwork for reinforced concrete - has height adjustable climbing frame and formwork plates swivel mounted around axis
DE2832990C2 (en) Scaffolding and track construction for a people&#39;s amusement facility
EP0320855B1 (en) Wrecking arrangement for chimneys, particularly for convergent chimneys
EP1087077A1 (en) Process and device for lifting and/or renovation of masts
WO1984000189A1 (en) Method for wall concreting and formwork to implement such method
EP0577004A1 (en) Anchoring device
EP4056785B1 (en) Support device, ceiling support, ceiling formwork system and method for stripping a ceiling formwork panel
DE3839261C1 (en) Process and apparatus for pulling down essentially hollow-cylindrical structures, such as chimneys
DE102018104551A1 (en) Method and device for mounting components, in particular facade elements on very tall buildings
DE3048043A1 (en) Ceiling formwork support structure - has folding legs swinging and set at angle round telescopic upright
DE2341402C3 (en) Working platform for erecting a building

Legal Events

Date Code Title Description
8110 Request for examination paragraph 44
D2 Grant after examination
8364 No opposition during term of opposition