Concrete temporary storage box with partition plate structure Download PDFInfo
- Publication number
- CN220578002U CN220578002U CN202322231707.0U CN202322231707U CN220578002U CN 220578002 U CN220578002 U CN 220578002U CN 202322231707 U CN202322231707 U CN 202322231707U CN 220578002 U CN220578002 U CN 220578002U
- Authority
- CN
- China
- Prior art keywords
- temporary storage
- concrete
- main
- storage box
- partition
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000004567 concrete Substances 0.000 title claims abstract description 81
- 238000005192 partition Methods 0.000 title claims abstract description 32
- 238000004140 cleaning Methods 0.000 claims abstract description 17
- 230000007246 mechanism Effects 0.000 claims abstract description 14
- 238000002955 isolation Methods 0.000 claims abstract description 5
- 238000003756 stirring Methods 0.000 claims description 7
- 238000009434 installation Methods 0.000 claims 4
- 238000007599 discharging Methods 0.000 abstract description 15
- 238000007790 scraping Methods 0.000 description 4
- 125000006850 spacer group Chemical group 0.000 description 4
- 230000015271 coagulation Effects 0.000 description 3
- 238000005345 coagulation Methods 0.000 description 3
- 238000010276 construction Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000008676 import Effects 0.000 description 2
- 239000011378 shotcrete Substances 0.000 description 2
- 239000012615 aggregate Substances 0.000 description 1
- 230000004075 alteration Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000005507 spraying Methods 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model discloses a concrete temporary storage box with a partition plate structure, which comprises a temporary storage box main body, wherein the temporary storage box main body comprises a main box body, a motor, a rotating shaft and a discharging opening, the motor is fixedly arranged at the top end of the main box body through bolts, the rotating shaft is arranged in the main box body and is positioned at the end part of the motor, and the discharging opening is arranged at the bottom end of the main box body; through the design isolation except that the thing mechanism, can be when the case of keeping in after keeping in concrete and discharge the back, keep in the concrete treatment by baffle to the inside bottom drainage of main tank when discharging and to the corner, be difficult for piling up, when driving the pivot through the motor simultaneously, the pivot rotates through dead lever one and dead lever two drive connecting plate and scraper blade contact in the internal surface rotation of main tank and baffle, consequently be convenient for after keeping in concrete to the internal surface cleaning of main tank and baffle, be difficult for influencing the space of keeping in, improve the case of keeping in to the volume of concrete temporary, stable the keeping in.
Description
Technical Field
The utility model belongs to the technical field of temporary storage boxes, and particularly relates to a concrete temporary storage box with a partition plate structure.
Background
The concrete is a composite material which is formed by configuring gel materials, aggregates and water according to a proper proportion and hardening for a certain time, the sprayed concrete is sprayed on a building through spraying equipment during construction of the building, temporary storage treatment is needed for the sprayed concrete, the temporary storage box is used for temporary storage of the concrete usually, the existing temporary storage box is applied to equipment for temporary storage of the concrete during construction of the building, the temporary storage box is provided with a partition plate structure during use, and is used for rapidly guiding blanking treatment, meanwhile, the temporary storage box is cleaner to treat after temporary storage of the concrete, and the temporary storage amount of the temporary storage box to the concrete is improved;
the existing temporary storage box is used for temporarily storing concrete, the concrete is directly stored temporarily in the temporary storage box, the internal concrete is continuously stirred by the stirring mechanism during temporary storage, the concrete is temporarily stored and is not easy to coagulate, and the concrete is directly discharged from the outlet during use, so that after the temporary storage box is used for storing the concrete, the inner surface is inconvenient to clean, the residual concrete is attached to the inner surface of the box body to coagulate, and the temporary storage box is inconvenient to clean and causes excessive coagulation in the temporary storage box after long-time use, and the temporary storage amount of the temporary storage box to the concrete is influenced.
Disclosure of Invention
The utility model aims to provide a concrete temporary storage box with a partition plate structure, so as to solve the problems that after the temporary storage box is put forward in the background technology and concrete is stored, the inner surface is inconvenient to clean, the concrete is easy to discharge from the interior of the temporary storage box, residual concrete is attached to the inner surface of a box body to be coagulated, and excessive coagulation in the interior of the temporary storage box is caused by inconvenient cleaning after long-time use, so that the temporary storage quantity of the temporary storage box to the concrete is affected.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a concrete case of keeping in with baffle structure, includes the case main part of keeping in, the case main part of keeping in includes main tank body, motor, pivot and feed opening, the top at the main tank body is passed through bolt fixed mounting to the motor, the inside at the main tank body is located the tip of motor is installed to the pivot, the feed opening sets up the inside bottom at the main tank body, still be provided with in the case main part of keeping in:
the isolation and removal mechanism comprises a partition component, a fixed mounting component and a removal and cleaning component, wherein the partition component is arranged at the end part of the inner bottom end of the main box body, which is positioned at the feed opening, the fixed mounting component is arranged at the two ends of the rotating shaft, and the removal and cleaning component is arranged at the end part of the fixed mounting component;
the feeding mechanism is accelerated, and comprises a feeding component and a conveying component, wherein the feeding component is arranged at the end part of the feeding port and positioned on the lower surface of the main box body, and the conveying component is arranged inside the feeding component.
Preferably, an inlet is formed in one side, located at the top end of the main box body, of the motor, a stirring shaft is fixedly mounted on the outer surface of the rotating shaft through bolts, and a supporting frame is fixedly welded to the lower surface of the main box body.
Preferably, the partition assembly comprises a partition body fixedly mounted inside the main box body and located at the top end of the feed opening, and the inner surface of the partition body is of an arc-shaped structure.
Preferably, the fixed mounting assembly comprises a first fixing rod and a second fixing rod which are respectively and fixedly mounted at two ends of the rotating shaft through bolts, and the rotating shaft penetrates through the ends of the first fixing rod and the second fixing rod.
Preferably, the article removing and cleaning assembly comprises a connecting plate fixedly arranged at the first end part and the second end part of the fixed rod through bolts, and a scraping plate is fixedly arranged on the inner surface of the connecting plate through bolts.
Preferably, the bottom of the scraping plate is of an arc-shaped structure, one end of the connecting plate is in contact with the inner surface of the partition plate body, and the other end of the connecting plate is in contact with the inner surface of the main box body.
Preferably, the blanking assembly comprises a conveying pipeline fixedly arranged at the bottom end of the blanking opening through bolts, and a discharge outlet is formed in the end part of the conveying pipeline.
Preferably, the conveying assembly comprises a conveyor rotatably connected inside a conveying pipe, and a motor is mounted on the surface of the conveying pipe at the end of the conveyor.
Compared with the prior art, the utility model has the beneficial effects that:
through the design isolation except that the thing mechanism, can be when the case of keeping in after keeping in concrete and discharge the back, keep in the interior bottom drainage of box to the main tank by the baffle body and to the isolated concrete processing of corner, be difficult for piling up, when driving the pivot through the motor simultaneously, the pivot rotates through dead lever one and dead lever two drive connecting plate and scraper blade contact in the internal surface rotation of main tank and baffle body, consequently be convenient for behind keeping in concrete to the internal surface cleaning treatment of main tank and baffle body, be difficult for causing the case of keeping in to keep in behind the concrete internal surface adhesion concrete, be difficult for influencing the space of keeping in, improve the case of keeping in to the volume of concrete temporary, stabilize the temporary.
Drawings
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a schematic cross-sectional view of a main body of a temporary storage box according to the present utility model;
FIG. 3 is a schematic view of a connection plate and a scraper according to the present utility model;
FIG. 4 is a schematic diagram of the structure of the conveying pipeline, motor and conveyor of the present utility model;
in the figure: 100. a temporary storage box main body; 101. a main case; 1011. a first fixed rod; 1012. a connecting plate; 1013. a scraper; 1014. a second fixing rod; 1015. a separator body; 102. an inlet; 103. a motor; 104. a support frame; 105. a feed opening; 1051. a delivery conduit; 1052. a discharge port; 1053. a motor; 1054. a conveyor; 106. a rotating shaft; 107. a stirring shaft.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1 to 4, the present utility model provides a technical solution: the utility model provides a concrete temporary storage box with baffle structure, including temporary storage box main part 100, temporary storage box main part 100 includes main tank body 101, a motor 103, pivot 106 and feed opening 105, the lower surface welded fastening of main tank body 101 has support frame 104, place temporary storage box main part 100 stable in the position department of using through support frame 104, motor 103 passes through bolt fixed mounting at the top of main tank body 101, the tip that the inside of main tank body 101 is located motor 103 is installed to pivot 106, the top of main tank body 101 is located one side of motor 103 and is provided with import 102, the surface of pivot 106 has (mixing) shaft 107 through bolt fixed mounting, the feed opening 105 sets up in the inside bottom of main tank body 101, get into concrete by import 102 to the inside of main tank body 101, and when getting into concrete, it rotates the concrete of holding to inside temporary storage by motor 103 drive pivot 106 and (mixing) shaft 107, prevent to condense, and when using, outwards the bound by feed opening 105, and be convenient for discharge concrete use fast, consequently, be convenient for keep temporary storage to handle the main part 100, still set up on the temporary storage box main part 100:
keep apart except that the thing mechanism, and this keep apart except that the thing mechanism includes the thing subassembly, fixed mounting subassembly and except that thing clearance subassembly, the setting of thing subassembly is located the tip fixed mounting subassembly of feed opening 105 in the inside bottom of main tank body 101 and is set up the both ends at pivot 106, except that the thing clearance subassembly sets up the tip at fixed mounting subassembly, when can keeping in the concrete through keeping in tank main part 100, remove the inside bottom edge drainage concrete discharge of main tank body 101 by the thing mechanism apart, to the internal surface cleaning treatment of main tank body 101 and baffle 1015 after the discharge simultaneously, be difficult for influencing the space of keeping in, improve the volume of keeping in tank main part 100 to the concrete temporarily, it is stable to keep in.
In order to facilitate drainage of concrete at the bottom edge of the main casing 101 and isolation of the concrete by the spacer assembly, in this embodiment, preferably, the spacer assembly includes a spacer 1015 fixedly installed inside the main casing 101 at the top end of the feed opening 105 by bolts, and the inner surface of the spacer 1015 is of an arc structure, and in order to facilitate the fixing and using of the connection plate 1012 by the fixing and installing assembly, the fixing and installing assembly includes a fixing rod one 1011 and a fixing rod two 1014 fixedly installed at both ends of the rotation shaft 106 by bolts, and the rotation shaft 106 penetrates through the ends of the fixing rod one 1011 and the fixing rod two 1014, so that the connection plate 1012 is conveniently installed on the inner surface of the main casing 101 by the fixing rod one 1011 and the fixing rod two 1014.
In order to facilitate the cleaning treatment of the residual concrete inside the main tank 101 and the partition plate 1015 through the removal cleaning assembly, in this embodiment, preferably, the removal cleaning assembly includes a connection plate 1012 fixedly installed at the ends of the first fixing rod 1011 and the second fixing rod 1014 through bolts, the scraper 1013 is fixedly installed on the inner surface of the connection plate 1012 through bolts, the connection plate 1012 drives the scraper 1013 to rotate for cleaning treatment, in order to facilitate the cleaning treatment of the partition plate 1015 and the inner surface of the main tank 101 when the connection plate 1012 rotates with the scraper 1013, and facilitate the rotating cleaning treatment, the bottom end of the scraper 1013 is in an arc structure, one end of the connection plate 1012 contacts with the inner surface of the partition plate 1015, and the other end of the connection plate 1012 contacts with the inner surface of the main tank 101, so that the rotating cleaning treatment is facilitated, and the concrete is not easy to adhere.
The conveying mechanism is quickened, and the conveying mechanism comprises a blanking component and a conveying component, the blanking component is arranged on the lower surface of the main box body 101 at the end part of the blanking opening 105, the conveying component is arranged inside the blanking component, concrete can be temporarily stored in the temporary storage box main body 100 and discharged from the blanking opening 105, the conveying mechanism is quickened to convey the concrete to the outside for discharging, the discharging treatment is quickened conveniently, and the blanking is more convenient.
In order to be convenient for side discharge concrete through unloading subassembly, and discharge concrete is more convenient, in this embodiment, preferably, unloading subassembly includes the pipeline 1051 through bolt fixed mounting in the feed opening 105 bottom, the tip of pipeline 1051 is provided with discharge port 1052, be convenient for discharge by discharge port 1052 when getting into the concrete to the inside of pipeline 1051, be convenient for discharge the external world when carrying concrete through the conveying subassembly, be difficult for stifled, be convenient for carry handling, the conveying subassembly is including rotating the conveyer 1054 of connecting in pipeline 1051 inside, the tip of conveyer 1054 is located pipeline 1051's surface mounting and has motor 1053, carry the discharge with concrete when driving conveyer 1054 by motor 1053 operation.
The motor 1053 in the present utility model is model XD-3420.
The working principle and the using flow of the utility model are as follows: the concrete temporary storage box with the partition plate structure has the advantages that when the concrete temporary storage box is used, the temporary storage box main body 100 is directly and stably placed at a using position through the support frame 104, and when concrete is temporarily stored, the concrete directly enters the main box body 101 from the inlet 102, and when the concrete enters, the motor 103 moves to drive the rotating shaft 106 and the stirring shaft 107 to rotate so as to continuously stir the concrete temporarily stored in the inside, so that coagulation is prevented, and when the concrete temporary storage box is used, the concrete is discharged to the outside through the discharging hole 105, and the concrete is conveniently and rapidly discharged for use, so that temporary storage treatment of the concrete is facilitated through the temporary storage box main body 100;
then when the temporary storage box main body 100 is discharged through the discharging opening 105 after concrete is temporarily stored, at the moment, the internal inclined surface of the partition plate 1015 slides to the inside of the discharging opening 105 and slides to the inside of the conveying pipeline 1051 through the discharging opening 105, the motor 1053 is electrified to operate so as to drive the conveyor 1054 to rotate, and the conveyor 1054 continuously conveys the concrete in the conveying pipeline 1051 to the end part of the conveying pipeline 1051 and is discharged through the discharging opening 1052 when the inside of the conveying pipeline 1051 rotates, so that the temporary storage box main body 100 is convenient for conveying the outside after concrete is temporarily stored, the discharging treatment is more convenient and difficult to block during discharging, the discharging speed of the temporary storage box main body 100 during concrete temporarily storing is improved, and the discharging is more convenient;
finally, when the temporary storage box main body 100 is used for temporarily storing concrete, and the concrete is poured in the main box body 101, the partition plate 1015 is used for draining and discharging the bottom end of the main box body 101 and isolating the concrete at the corners, so that the temporary storage box main body 101 is not easy to accumulate, a small amount of concrete is easy to remain on the inner surface of the main box body 101, the motor 103 is used for driving the rotating shaft 106 and the stirring shaft 107 to rotate, the connecting plate 1012 and the scraping plate 1013 are driven by the first fixing rod 1011 and the second fixing rod 1014 to contact the connecting plate 1012 and the scraping plate 1013 when the rotating shaft 106 rotates, the inner surfaces of the main box body 101 and the partition plate 1015 are conveniently cleaned after the temporary storage of the concrete, the inner surface of the temporary storage box main body 100 is not easy to adhere to the concrete, the temporary storage space is not easy to influence, the temporary storage box main body 100 is improved, and the temporary storage amount of the concrete is stable.
Although embodiments of the present utility model have been shown and described in detail with reference to the foregoing detailed description, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations may be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.
Claims (8)
1. The utility model provides a concrete temporary storage case with baffle structure, includes temporary storage case main part (100), temporary storage case main part (100) include main tank body (101), motor (103), pivot (106) and feed opening (105), motor (103) pass through the top of bolt fixed mounting at main tank body (101), pivot (106) are installed in the inside of main tank body (101) and are located the tip of motor (103), feed opening (105) set up in the inside bottom of main tank body (101), its characterized in that: the temporary storage box main body (100) is also provided with:
the isolation and removal mechanism comprises a partition component, a fixed installation component and a removal and cleaning component, wherein the partition component is arranged at the end part of the inner bottom end of the main box body (101) which is positioned at the blanking opening (105), the fixed installation component is arranged at the two ends of the rotating shaft (106), and the removal and cleaning component is arranged at the end part of the fixed installation component;
the feeding mechanism is accelerated, the feeding mechanism comprises a feeding component and a conveying component, the feeding component is arranged at the end part of the feeding port (105) and located on the lower surface of the main box body (101), and the conveying component is arranged inside the feeding component.
2. A concrete temporary storage box with a partition structure according to claim 1, wherein: an inlet (102) is formed in one side, located at the top end of the main box body (101), of the motor (103), a stirring shaft (107) is fixedly mounted on the outer surface of the rotating shaft (106) through bolts, and a supporting frame (104) is fixedly welded to the lower surface of the main box body (101).
3. A concrete temporary storage box with a partition structure according to claim 1, wherein: the partition assembly comprises a partition body (1015) fixedly installed inside the main box body (101) and located at the top end of the feed opening (105), and the inner surface of the partition body (1015) is of an arc-shaped structure.
4. A concrete temporary storage box with a partition structure according to claim 1, wherein: the fixed installation component comprises a first fixed rod (1011) and a second fixed rod (1014) which are respectively and fixedly installed at two ends of the rotating shaft (106) through bolts, and the rotating shaft (106) penetrates through the ends of the first fixed rod (1011) and the second fixed rod (1014).
5. The concrete temporary storage box with a partition plate structure according to claim 4, wherein: the article removing and cleaning assembly comprises a connecting plate (1012) fixedly arranged at the end parts of a first fixed rod (1011) and a second fixed rod (1014) through bolts, and a scraper (1013) is fixedly arranged on the inner surface of the connecting plate (1012) through bolts.
6. The concrete temporary storage box with a partition plate structure according to claim 5, wherein: the bottom end of the scraper (1013) is of an arc-shaped structure, one end of the connecting plate (1012) is in contact with the inner surface of the partition plate (1015), and the other end of the connecting plate (1012) is in contact with the inner surface of the main box body (101).
7. A concrete temporary storage box with a partition structure according to claim 1, wherein: the blanking assembly comprises a conveying pipeline (1051) fixedly installed at the bottom end of the blanking opening (105) through bolts, and an exhaust port (1052) is formed in the end portion of the conveying pipeline (1051).
8. The concrete temporary storage box with a partition plate structure according to claim 7, wherein: the conveying assembly comprises a conveyor (1054) rotatably connected inside a conveying pipeline (1051), and a motor (1053) is arranged on the surface of the conveying pipeline (1051) at the end of the conveyor (1054).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322231707.0U CN220578002U (en) | 2023-08-18 | 2023-08-18 | Concrete temporary storage box with partition plate structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322231707.0U CN220578002U (en) | 2023-08-18 | 2023-08-18 | Concrete temporary storage box with partition plate structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN220578002U true CN220578002U (en) | 2024-03-12 |
Family
ID=90113619
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202322231707.0U Active CN220578002U (en) | 2023-08-18 | 2023-08-18 | Concrete temporary storage box with partition plate structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN220578002U (en) |
-
2023
- 2023-08-18 CN CN202322231707.0U patent/CN220578002U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN220578002U (en) | Concrete temporary storage box with partition plate structure | |
CN111112285B (en) | Fermentation cylinder for organic solid waste recovery processing | |
CN213532214U (en) | Through type wet sand blasting cleaning machine | |
CN214917027U (en) | Thick liquids deironing device convenient to it is clean | |
CN211548810U (en) | Concrete injection apparatus with prevent stifled injector head effect | |
CN210905093U (en) | Soil pick-up car with flocculation and precipitation mechanism | |
CN112025999A (en) | Agitating unit for building cement | |
CN219705655U (en) | Cement pouring equipment | |
CN220936664U (en) | Radish pre-soaking device with sand and stone removing function | |
CN211030646U (en) | Reinforced concrete agitated vessel | |
CN220450488U (en) | Fabric smooth finishing agent adding device with residual material scraping plate | |
CN221244735U (en) | Paint diluting device for paint production | |
CN217628308U (en) | Oligo nucleic acid purification device of easy clearance | |
CN220257785U (en) | Fodder stirring device | |
CN221800113U (en) | Shield mortar continuous conveying device | |
CN221774898U (en) | Concrete discharging equipment for concrete production | |
CN218025703U (en) | PP material sewage treatment tank | |
CN220657291U (en) | Sewage treatment agent sowing device for sewage treatment | |
CN220840902U (en) | Vertical mortar agitated vessel is used in construction convenient to guide | |
CN218892967U (en) | Powder conveyer pipe is used in concrete production | |
CN218089317U (en) | Hydraulic engineering sediment removal device | |
CN215313433U (en) | Environment-friendly spraying device is used in laboratory | |
CN220011101U (en) | Food packaging equipment with cleaning function | |
CN213408325U (en) | Stirrer convenient for discharging | |
CN221908697U (en) | Mechanism grit aggregate dust collector |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |