CN212652950U - Welding fixture - Google Patents

Welding fixture Download PDF

Info

Publication number
CN212652950U
CN212652950U CN202021338934.3U CN202021338934U CN212652950U CN 212652950 U CN212652950 U CN 212652950U CN 202021338934 U CN202021338934 U CN 202021338934U CN 212652950 U CN212652950 U CN 212652950U
Authority
CN
China
Prior art keywords
clamping
lead screw
wall
shaped bracket
chucks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021338934.3U
Other languages
Chinese (zh)
Inventor
张天平
安占法
马红漫
惠刚
高立岗
王峤枫
郭浩
杨志增
刘少华
冉汉卿
李国富
倪士亮
王文利
线登洲
刘金桥
郭群录
崔煦
张佳磊
何健
张力
申展展
常青波
梁文勇
姚正茂
韩建祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Construction Engineering Group Building Decoration Engineering Co., Ltd
Hebei Construction Group Corp Ltd
Original Assignee
Hebei Construction Engineering Group Decoration Engineering Co ltd
Hebei Construction Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Construction Engineering Group Decoration Engineering Co ltd, Hebei Construction Group Corp Ltd filed Critical Hebei Construction Engineering Group Decoration Engineering Co ltd
Priority to CN202021338934.3U priority Critical patent/CN212652950U/en
Application granted granted Critical
Publication of CN212652950U publication Critical patent/CN212652950U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a welding fixture, the structure of which comprises a U-shaped bracket and two chucks arranged on the inner wall of the U-shaped bracket relatively, wherein one chuck is connected with the inner wall of the U-shaped bracket on the corresponding side through a connecting rod, a lead screw is arranged on the wall of the U-shaped bracket on the opposite side, the other chuck is arranged on one end of the lead screw in the U-shaped bracket, the other end of the lead screw passes through the wall of the U-shaped bracket and extends outside, and the clamping distance between the two chucks can be changed by the extending end of the screwed lead screw; the clamping heads are bent steel plates with two mutually vertical sides, the inner side surface of one straight edge of each clamping head is connected with the end part of the corresponding connecting rod or the corresponding screw rod, the outer side surface of the straight edge is a clamping surface, the clamping surfaces of the two clamping heads are mutually parallel, and the two clamping heads can rotate around the axis vertical to the clamping surfaces at the end parts of the connecting rods or the screw rods. The utility model discloses, be convenient for installation and dismantlement can not only improve the construction speed, guarantees construction quality, can also avoid the secondary to rework.

Description

Welding fixture
Technical Field
The utility model relates to a curtain construction appurtenance, specifically speaking are welding jig.
Background
In the installation and construction process of curtain walls, a cross beam is often required to be welded between two vertical beams. When the cross beam is welded, at least three workers are needed to complete the welding, two workers support two ends of the cross beam, and the other worker performs the welding operation between the cross beam and the vertical beam. Therefore, the time and labor are wasted, the positioning accuracy of the cross beam is low, the horizontal elevation is prone to deviation, the welding position of the cross beam is deviated, the construction quality of the whole curtain wall is finally affected, secondary reworking can be carried out, and the construction cost is increased.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a welding jig to in solving the curtain work progress, crossbeam welded position takes place the incline easily, influences the problem of curtain construction quality.
The utility model discloses a realize like this: a welding fixture comprises a U-shaped support and two chucks oppositely arranged on the inner wall of the U-shaped support, wherein one chuck is connected with the inner wall of the U-shaped support on the corresponding side through a connecting rod, a lead screw penetrates through the wall of the U-shaped support on the opposite side, the other chuck is arranged at one end of the lead screw in the U-shaped support, the other end of the lead screw penetrates through the wall of the U-shaped support to extend outside, and the clamping distance between the two chucks can be changed by screwing the extending end of the lead screw;
the clamping heads are bent steel plates with two mutually vertical sides, the inner side surface of one straight edge of each clamping head is connected with the end part of the corresponding connecting rod or the corresponding lead screw, the outer side surface of the straight edge is a clamping surface, the clamping surfaces of the two clamping heads are mutually parallel, and the two clamping heads can rotate around the axis vertical to the clamping surfaces at the end parts of the connecting rods or the lead screws.
The end part of the screw rod extending out of the U-shaped bracket is provided with a straight rod vertical to the screw rod.
The utility model relates to an auxiliary construction tool for in curtain construction process, including U type support and relative two chucks of setting on U type support inner wall, a tip of a connecting rod of one of them chuck setting on U type support inner wall, another chuck setting is at the tip of wearing to establish the lead screw on offside U type support inner wall. The clamping distance between the two chucks can be changed by screwing one end of the screw rod extending out of the U-shaped bracket. The utility model discloses a two chucks are both sides mutually perpendicular's the steel sheet of bending, the medial surface of one of them straight flange of two chucks and the end connection of connecting rod or lead screw, and the lateral surface of this straight flange is the clamping face. The two chucks can rotate around an axis vertical to the clamping surface at the end part of the lead screw or the connecting rod. The utility model discloses in the curtain construction process, generally use in pairs, at first with the both sides of this anchor clamps two clamping faces grasp the perpendicular roof beam to another straight flange face that makes the chuck with wait to splice the bottom surface parallel and level of welding the crossbeam together with perpendicular roof beam, then place the crossbeam on the straight flange of two anchor clamps chucks, thereby carry out the crossbeam and erect the weldment work between the roof beam. The utility model discloses, the installation of being convenient for is dismantled, can effectual roughness and the elevation of guaranteeing the crossbeam, can not only improve the construction speed, guarantees construction quality, can also avoid the secondary to rework.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a schematic view of the usage state of the present invention.
In the figure: 1. a U-shaped bracket; 2. a connecting rod; 3. a chuck; 4. a lead screw; 5. a straight rod; 6. erecting a beam; 7. a cross member.
Detailed Description
As shown in fig. 1 and 2, the present invention includes a U-shaped bracket 1 and two chucks 3 arranged in pairs, wherein the two chucks 3 are respectively arranged on two inner walls of the U-shaped bracket 1, and the two chucks 3 are arranged relatively. A connecting rod 2 is arranged on one of the inner walls of the U-shaped bracket, the connecting rod 2 is vertical to the inner wall of the U-shaped bracket 1, and one clamping head 3 is arranged at the end part of the free end of the connecting rod 2. A lead screw 4 is arranged on the other inner wall of the U-shaped support 1 in a penetrating mode, the other chuck is arranged at the end portion of one end, located in the U-shaped support 1, of the lead screw 4, one end, extending out of the U-shaped support 1, of the lead screw 4 is a screwing end, the screwing end of the lead screw 4 is screwed, the distance between the two chucks 3 can be changed, and therefore clamping work is completed. In order to facilitate the screwing of the screw rod 4, the end of the screw rod 4 is further provided with a straight rod 5 perpendicular to the end, and the straight rod 5 serves as a handle.
The utility model discloses a two chucks 3 are made for the steel sheet of bending by both sides mutually perpendicular, the medial surface of one of them straight flange of chuck 3 and the end connection of connecting rod 2 or lead screw 4 that correspond, and the lateral surface of this straight flange is the clamping face. The clamping surfaces of the two clamping heads 3 are kept parallel, and the outer side surface of the other straight edge of the two clamping heads 3 is a supporting surface for supporting the cross beam 7. The utility model discloses a two chucks 3 can be around rotatory with clamping face vertically axis at connecting rod 2 or lead screw 4's tip to can adjust the holding surface that is used for supporting beam 7, with the accuracy of guaranteeing beam 7's position. As for how the two chucks 3 are rotatably connected at the end of the screw 4 and the connecting rod 2, respectively, the connection structure thereof is a common technical means and will not be described in detail.
When the clamp is used in practice, the clamp is often used in pairs, firstly, the two clamps are respectively clamped between two vertical beams 6 of a cross beam 7 to be welded, as shown in fig. 2, the supporting surface formed by the chucks 3 of the clamp is adjusted in the clamping process, so that the supporting surface formed by the chucks 3 of the two clamps and used for supporting the cross beam 7 is kept flush with the bottom surface of the cross beam 7 to be welded. Finally, the cross beam 7 to be welded is placed on the supporting surface formed by the joints 3 of the two fixtures, so that the welding work between the cross beam 7 and the vertical beam 6 is performed.

Claims (2)

1. A welding fixture is characterized by comprising a U-shaped support and two chucks oppositely arranged on the inner wall of the U-shaped support, wherein one chuck is connected with the inner wall of the U-shaped support on the corresponding side through a connecting rod, a lead screw penetrates through the wall of the U-shaped support on the opposite side, the other chuck is arranged at one end of the lead screw in the U-shaped support, the other end of the lead screw penetrates through the wall of the U-shaped support to extend outside, and the clamping distance between the two chucks can be changed by screwing the extending end of the lead screw;
the clamping heads are bent steel plates with two mutually vertical sides, the inner side surface of one straight edge of each clamping head is connected with the end part of the corresponding connecting rod or the corresponding lead screw, the outer side surface of the straight edge is a clamping surface, the clamping surfaces of the two clamping heads are mutually parallel, and the two clamping heads can rotate around the axis vertical to the clamping surfaces at the end parts of the connecting rods or the lead screws.
2. The welding jig of claim 1 wherein the end of the lead screw extending beyond the U-shaped bracket is provided with a straight bar perpendicular thereto.
CN202021338934.3U 2020-07-09 2020-07-09 Welding fixture Active CN212652950U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021338934.3U CN212652950U (en) 2020-07-09 2020-07-09 Welding fixture

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021338934.3U CN212652950U (en) 2020-07-09 2020-07-09 Welding fixture

Publications (1)

Publication Number Publication Date
CN212652950U true CN212652950U (en) 2021-03-05

Family

ID=74760162

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021338934.3U Active CN212652950U (en) 2020-07-09 2020-07-09 Welding fixture

Country Status (1)

Country Link
CN (1) CN212652950U (en)

Similar Documents

Publication Publication Date Title
CN102182302B (en) Building construction all-steel mold plate and manufacturing and assembling method thereof
CN212652950U (en) Welding fixture
CN109779247A (en) The formwork erection device and construction method of steel column cornerite
JP2008267030A (en) Method and device for supporting anchor bolt for building structure
CN215200320U (en) Simple auxiliary tool for rapid butt joint of multi-angle accurate profiles
CN213979965U (en) A connect auxiliary device for screw-thread steel
CN109235271B (en) Vertical rib positioning tool, positioning clamping seat and working method of combined bridge tower steel shell section
CN210239143U (en) Reserved hole sleeve fixing part for laminated floor slab
CN211958674U (en) Pre-fixing device for distribution box of filler wall
CN111037138B (en) Production method of civil air defense door sealing beam
CN113323143A (en) Building steel tube bundle supporting platform structure
CN214868272U (en) Rectangular pipe welding position frock
CN115430980B (en) Welding process for ultra-long span steel structure beam
CN216283536U (en) Measuring device for building structure engineering
CN214034713U (en) Mounting bracket for mounting scaffold to beam body
CN210649193U (en) Positioning device for welding T-shaped steel stud of bridge
CN220014517U (en) Auxiliary positioning device for installation of building steel girder
CN212926519U (en) Control tool for fixing deformation joint water stop belt device
CN217128969U (en) Building template clamp
CN218341371U (en) Welding positioning device for door leaf and sleeve plate
CN114892973B (en) Deformation joint two-side template reinforcing device and application method thereof
CN218952864U (en) Aligning and adjusting device for segment assembly of overweight steel structural beam
CN212885877U (en) Conjoined base of welding workstation
CN217913655U (en) Welding fixture for crane handrail
CN216713886U (en) Large-scale stand docks supplementary calibration tool

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 050051 No.146 Youyi North Street, Xinhua District, Shijiazhuang City, Hebei Province

Patentee after: HEBEI CONSTRUCTION GROUP Co.,Ltd.

Patentee after: Hebei Construction Engineering Group Building Decoration Engineering Co., Ltd

Address before: 050051 No.146 Youyi North Street, Xinhua District, Shijiazhuang City, Hebei Province

Patentee before: HEBEI CONSTRUCTION GROUP Co.,Ltd.

Patentee before: Hebei Construction Engineering Group Decoration Engineering Co., Ltd