[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN217921146U - Switch replacing device and system - Google Patents

Switch replacing device and system Download PDF

Info

Publication number
CN217921146U
CN217921146U CN202221087897.2U CN202221087897U CN217921146U CN 217921146 U CN217921146 U CN 217921146U CN 202221087897 U CN202221087897 U CN 202221087897U CN 217921146 U CN217921146 U CN 217921146U
Authority
CN
China
Prior art keywords
lifting
turnout
switch
gantry crane
sliding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221087897.2U
Other languages
Chinese (zh)
Inventor
李石平
晏红文
陈亮陪
卢云波
朱利君
吴青考
罗前星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuzhou CRRC Times Electric Co Ltd
Original Assignee
Zhuzhou CSR Times Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuzhou CSR Times Electric Co Ltd filed Critical Zhuzhou CSR Times Electric Co Ltd
Priority to CN202221087897.2U priority Critical patent/CN217921146U/en
Application granted granted Critical
Publication of CN217921146U publication Critical patent/CN217921146U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)

Abstract

The utility model discloses a switch replacement device and system, the device includes the portal crane, and the portal crane further includes: a cross beam; the sliding frames are respectively movably arranged at the left end and the right end of the cross beam and can transversely move along the cross beam; the hoisting mechanism is arranged on the cross beam, is positioned between the two sliding frames and can move transversely along the cross beam; set up respectively in two frame belows that slide, can follow the landing leg that vertically stretches out and draws back. In an operating state, a plurality of gantry cranes are arranged at intervals along the direction of a railway line and are arranged on the roadbed at two sides of the steel rail in a spanning mode. The utility model discloses can solve current switch and change equipment operation security low, can't lift by crane the technical problem of jumbo size switch part.

Description

Switch replacing device and system
Technical Field
The utility model relates to a railway engineering machine tool technical field especially relates to a device and system are changed to switch for high-speed railway ballastless track.
Background
The ballastless track turnout of the high-speed rail is an important part of a passenger special line, is an object of line key maintenance and is one of wearing parts, and needs to be maintained and repaired frequently or replaced regularly. The switch mainly comprises a switch rail, a curve transition section, a switch core and a guard rail. The turnout center, the switch rail and the like are main components of the turnout, and the turnout center, the switch rail and the like are mainly characterized by long size, heavy weight and difficult manual replacement. The turnout of the passenger dedicated line in China mainly comprises 18 turnout types and 42 turnout types, wherein the length of the 42 turnout is nearly twice of that of the 18 turnout. At present, the turnout replacement equipment applied in China mainly adopts the following two modes:
the first mode is to use a flat car as a transportation tool, use a 25T hoisting rail car to hoist from an adjacent line, and replace the rail by manually pulling and pulling the rail. This approach has a number of disadvantages: if the crane boom is easy to scrape and touch a contact network, hidden damage to a new rail part is easy to cause, the adjacent line space is occupied, the construction efficiency is low, the skylight occupation time is long, and the large-size turnout part is difficult to lift.
The second mode is to adopt special replacement equipment for turnout parts, namely two platforms are modified and respectively provided with movable cantilever cranes. However, the two cantilever cranes are used for independently hoisting new and old turnout parts respectively, and the turnout parts have large external dimensions, so the main disadvantages of the mode are that: high cost, low safety and incapability of hoisting large-size turnout parts.
In the prior art, the following technical scheme is mainly related to the utility model:
the prior art 1 is applied to the engineering machinery limited company of the time of baby chicken middle turning in 2018, 02/01, and is published in 2019, 03/01, and the publication number CN109403161a, which is the chinese invention application of the construction process for replacing turnout of large-tonnage lifting rail car. The invention discloses a construction process for replacing turnouts of a large-tonnage lifting rail car, which comprises the following specific steps of: 1. before a new turnout is installed on a track bed, a pre-paving and moving method is adopted to carry out sectional and integral assembly on the new turnout; 2. before installing a new turnout, a hoisting rail car is used as main turnout dismantling equipment to dismantle an old turnout and clean a track bed; 3. after the assembly of the new turnout is finished, a hoisting rail car is used as main turnout transfer equipment to transfer the new turnout to the position near the position to be installed; 4. after the new turnout is transported to a position near the installation position, the lifting rail car is adopted as main turnout installation equipment to be accurately installed to the corresponding position of the track bed. The method is used for integrally replacing the grouped turnouts, the weight and the size of the grouped turnouts are large, a hoisting rail car is adopted for operation, a large safety risk exists, a contact net is easy to touch, in addition, the turnouts are unstable in the hoisting process, and the rail car has the possibility of overturning. Meanwhile, the method requires more personnel, and has high labor intensity and low efficiency.
The prior art 2 is applied for 15/08/2016 and announced 06/2017 by the china company of capital construction and high-tech equipment limited for railway switch, and the publication number is CN 206219916U. The utility model discloses a railway switch major-part quick replacement equipment, it includes at least a set of load-bearing platform, and this load-bearing platform below is equipped with and walks capable mechanism, and load-bearing frame is equipped with to this load-bearing platform top, and this load-bearing frame connects flexible quick-witted roof beam, and this flexible quick-witted roof beam is connected and is slided hoisting machine structure, and actuating mechanism still is equipped with to flexible quick-witted roof beam, the one end linking frame hinge roof beam of flexible quick-witted roof beam to can be based on this frame hinge roof beam rotation or lateral shifting, load-bearing platform still connects one set at least stable strutting arrangement, and one set at least front end strutting arrangement is connected to flexible quick-witted roof beam front end. However, the equipment has a large and complex structure and high cost, only small turnout parts with small sizes can be replaced, and large turnout parts with the lengths of tens of meters cannot be replaced due to size limitation.
The prior art 3 is a method for changing and laying railway switches and a railway switch laying machine set thereof applied by medium-iron heavy industry limited companies and medium-iron science group limited companies in 2013, 05.01.2013, and published in 2013, 05.01.20163, with publication number CN103074829 a. The invention discloses a railway track laying unit, which comprises a main machine, an auxiliary machine and a hydraulic reloading frame, wherein the main machine comprises a main machine flat car, a machine arm, a front upright column gantry structure, a rear upright column gantry structure, a crane trolley, a hoisting mechanism and a traveling mechanism, and the auxiliary machine at least comprises an auxiliary machine flat car; the hydraulic reloading frame comprises a first reloading frame, a second reloading frame and a reloading lifting appliance. However, the unit is large and complex in structure and high in cost; the transportation of the whole set of equipment is difficult, the required equipment is more, and the construction management is difficult; only small turnout parts with small size can be replaced, and longer large turnout parts cannot be replaced due to size limitation.
SUMMERY OF THE UTILITY MODEL
In view of this, the utility model aims at providing a switch changes device and system to it is low to solve current switch and change equipment operation security, can't lift by crane the technical problem of jumbo size switch part.
In order to realize the above utility model, the utility model particularly provides a technical implementation scheme that device was changed to switch, the device is changed to switch, including the portal crane, the portal crane further includes:
a cross beam;
the sliding frames are respectively movably arranged at the left end and the right end of the cross beam and can transversely move along the cross beam;
the lifting mechanism is arranged on the cross beam, is positioned between the two sliding frames and can move transversely along the cross beam;
set up respectively in two frame belows that slide, can follow the landing leg that vertically stretches out and draws back.
Furthermore, the lower parts of the supporting legs are provided with adjustable supporting feet, and the supporting legs and the gantry crane can be leveled through the adjustable supporting feet.
Furthermore, the gantry crane further comprises a sliding driving mechanism, the sliding frame is sleeved on the cross beam, one end of the sliding driving mechanism is arranged on the cross beam, and the other end of the sliding driving mechanism is connected with the sliding frame.
Furthermore, a transverse moving support with internal threads is arranged on the sliding frame, and a mounting seat is arranged on the cross beam. The sliding driving mechanism adopts a power driving screw rod mechanism, a power driving end of the sliding driving mechanism is fixed on the mounting seat, and a screw rod end is connected to the transverse moving support.
Furthermore, a wedge-shaped locking mechanism is arranged in the sliding frame, is positioned between the cross beam and the sliding frame and comprises two wedge-shaped sliding blocks which are in mutual contact. After the locking mechanism penetrates through the sliding frame, the two wedge-shaped sliding blocks are compressed to lock the position of the sliding frame.
Further, the landing leg comprises a threaded cylinder, a screw, a support and a landing leg sleeve. The threaded cylinder is connected below the sliding frame, the lower part of the threaded cylinder is sleeved with the supporting leg sleeve, and the support is arranged below the supporting leg sleeve. The screw rod is arranged in the supporting leg sleeve, the upper end of the screw rod is connected with the thread cylinder through threads, and the lower end of the screw rod is connected with the lifting driving mechanism. And a lifting driving mechanism is arranged in the support, and drives a screw rod to rotate through the lifting driving mechanism so as to enable the threaded cylinder to move up and down.
Further, a bearing is arranged between the screw and the support.
Further, the device still includes the handling frock, the handling frock includes carrier bar, mounting bracket, rings and lifting claw. The lifting mechanism comprises a lifting hook capable of vertically lifting, the lifting ring is arranged on the upper portion of the bearing beam, and the lifting hook is connected with the lifting ring. The mounting bracket is movably arranged at the lower part of the bearing beam, and the lifting claws are arranged at the left side and the right side of the mounting bracket along the line direction. And when the gantry crane carries out hoisting operation, hoisting the turnout by the hoisting claw. After the turnout is hoisted, the turnout is hoisted to a specified longitudinal position by moving the turnout back and forth on the bearing beam along the line direction through the mounting frame.
Further, the mounting bracket is movably connected with the carrier bar, chain wheels are arranged at two ends of the carrier bar along the line direction, and the two chain wheels are connected through a chain. The chain is connected with the mounting rack, one of the chain wheels is driven to rotate through the longitudinal movement mechanism, and the chain wheel rotates to drive the chain to move along the line direction.
The utility model discloses still specifically provide a switch replacement system's technical implementation scheme based on above-mentioned device in addition, switch replacement system, include:
the system comprises a rail car, a first transport flat car and a second transport flat car;
the gantry crane is arranged on the first transport flat car in a transport state;
the rotary mounting seat is arranged on the first transport flat car in a transport state and used for fixing the gantry crane;
and the lifting tool and the turnout are arranged on the second transport flat car in a transport state.
Furthermore, under the operation state, a plurality of portal cranes are arranged at intervals along the railway line direction and are arranged on the roadbed on two sides of the steel rail in a spanning mode. The upper portion of handling frock links to each other with the lifting hook of a plurality of portal cranes through rings, the lower part of handling frock links to each other with the switch through a plurality of lifting claws.
Furthermore, after the turnout is lifted, the longitudinal moving mechanism drives the mounting frame to move back and forth along the line direction relative to the bearing beam so as to realize accurate longitudinal positioning of the turnout.
Through implementing the aforesaid the utility model provides a technical scheme of device and system is changed to switch has following beneficial effect:
(1) The utility model discloses switch changes device and system, portal crane landing leg stride locate the both sides of railway circuit, need not to occupy the adjacent line operation, do not have the safe risk that the super limit of operation, and device simple structure, reliability are high simultaneously, be convenient for maintain and repair, the operating efficiency is high, can realize that jumbo size switch part lifts by crane;
(2) The turnout replacing device and the turnout replacing system are suitable for replacing the whole set of turnout and also suitable for replacing a single switch rail, a turnout center and the like, and can realize the carrying, the placing, the position adjustment and the replacement of various circuit parts with different lengths through the combination of a plurality of gantry cranes, and especially can realize the lifting of large-size turnout parts;
(3) The utility model discloses switch replacement device and system, portal crane possess landing leg sideslip, go up and down, leveling function, landing leg transverse span interval, apart from ground height all adjustable, can satisfy the function of different circuit ground operating mode demands, and portal crane device height-adjustable, do not have the risk of touching the contact net in the lifting process;
(4) The utility model discloses device and system are changed to switch, portal crane low in manufacturing cost, operating personnel are few, change swift, efficient, and longitudinal installation does not surpass the vehicle boundary limit on the flatcar during portal crane transportation, and handling frock hanging point can realize that longitudinal movement makes the location of switch more accurate.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below. It is obvious that the drawings in the following description are only some embodiments of the invention, from which other embodiments can be derived by a person skilled in the art without inventive effort.
Fig. 1 is a schematic three-dimensional structure diagram of a gantry crane in one embodiment of the turnout replacing device of the utility model;
fig. 2 is a schematic front structural view of a gantry crane in one embodiment of the turnout replacement device of the present invention;
fig. 3 is a schematic side structure view of a gantry crane in one embodiment of the turnout replacement device of the present invention;
fig. 4 is a perspective view of a side structure of a gantry crane in one embodiment of the turnout replacement device;
fig. 5 is a schematic plan view of a gantry crane in one embodiment of the switch replacing device of the present invention;
fig. 6 is a schematic diagram of a hoisting tool in one embodiment of the turnout replacing device of the present invention;
fig. 7 is a schematic side structure view of a hoisting tool in one embodiment of the turnout replacing device of the present invention;
fig. 8 is a schematic perspective view of a lifting tool in another embodiment of the turnout replacing device of the present invention;
FIG. 9 is a schematic view of the installation structure of a gantry crane in one embodiment of the turnout replacement system of the present invention;
figure 10 is a schematic diagram of the structure of the swivel mount in one embodiment of the switch changing system of the present invention;
fig. 11 is a schematic perspective view of a rotary mounting seat in one embodiment of the turnout replacement system of the present invention;
figure 12 is a bottom view of the rotary mounting base of one embodiment of the switch replacement system of the present invention;
figure 13 is a schematic side view of a swivel mount in one embodiment of the switch replacement system of the present invention;
figure 14 is a schematic side view of a swivel mount of an embodiment of the switch replacement system of the present invention at another viewing angle;
fig. 15 is a schematic structural view of an embodiment of the turnout replacement system of the present invention from a side view;
fig. 16 is a schematic structural view of an embodiment of the switch replacement system of the present invention from a top view;
fig. 17 is a schematic view of a transporting step of a gantry crane in a side view in one embodiment of the turnout replacement system operating method of the present invention;
fig. 18 is a schematic view of a gantry crane transportation step in a top view in one embodiment of the turnout replacement system operation method of the present invention;
fig. 19 is a schematic view of a step of rotating the gantry crane to the transverse direction in a side view in one embodiment of the operation method of the turnout replacement system of the present invention;
figure 20 is a schematic view of the step of gantry crane rotation to traverse in the top view in one embodiment of the switch replacement system operating method of the present invention;
FIG. 21 is a schematic view of the step of getting off the gantry crane in a side view in a telescopic manner in one embodiment of the turnout replacement system operation method of the present invention;
FIG. 22 is a schematic view of the step of getting off the gantry crane in the top view in the embodiment of the method for operating a switch changing system of the present invention;
fig. 23 is a schematic view of a new turnout hoisting step in a side view in one embodiment of the turnout replacement system operation method of the present invention;
fig. 24 is a schematic view of a new turnout hoisting step at a top view in an embodiment of the turnout replacement system operating method of the present invention;
fig. 25 is a schematic view of a new turnout placement step at a side view in an embodiment of the turnout replacement system operating method of the present invention;
fig. 26 is a schematic view of a new switch placement step at a top view in an embodiment of the switch changing system operating method of the present invention;
fig. 27 is a schematic view of an old turnout removal step at a top view in one embodiment of the turnout replacement system operating method of the present invention;
fig. 28 is a schematic view of the old switch crane placement step in a top view in one embodiment of the switch replacement system operating method of the present invention;
fig. 29 is a schematic view of a new turnout installation step at a top view in one embodiment of the turnout replacement system operating method of the present invention;
fig. 30 is a schematic view of an old turnout hoisting step in a side view in one embodiment of the turnout replacement system operation method of the present invention;
fig. 31 is a schematic view of an old turnout hoisting step at a top view in one embodiment of the turnout replacement system operating method of the present invention;
figure 32 is a schematic view from above of the old switch placement to flat car step in one embodiment of the switch replacement system operating method of the present invention;
fig. 33 is a schematic view of a side view of a step of driving a flatcar to a gantry crane recovery position in an embodiment of the turnout replacement system operating method of the present invention;
fig. 34 is a schematic view of a step of driving the flatcar to the gantry crane recovery position in a top view in one embodiment of the turnout replacement system operation method of the present invention;
FIG. 35 is a schematic view of a side view of a step of recovering a gantry crane to a flat car in an embodiment of a turnout replacement system operation method of the present invention;
fig. 36 is a schematic view of a step of recovering the gantry crane to the flatcar in a top view in an embodiment of the turnout replacement system operation method of the present invention;
fig. 37 is a schematic view of a step of rotating the gantry crane to the longitudinal fixing in a side view in one embodiment of the operation method of the turnout replacement system of the present invention;
fig. 38 is a schematic view of a step of rotating the gantry crane to the longitudinal fixing in the top view in one embodiment of the turnout replacement system operation method of the present invention;
in the figure: 1-beam, 2-sliding frame, 3-sliding driving mechanism, 4-lifting mechanism, 5-supporting leg, 6-threaded cylinder, 7-lifting driving mechanism, 8-adjustable supporting leg, 9-screw, 10-support, 11-supporting leg sleeve, 12-power supply cabinet, 13-bearing, 14-first distance sensor, 15-second distance sensor, 16-force sensor, 17-inclination sensor, 18-wedge locking mechanism, 19-lifting seat, 20-rotary bearing, 21-fixed mounting seat, 22-locking seat, 23-guide column seat, 24-lifting mechanism, 25-guide column, 26-locking mechanism, 27-sliding mechanism, 28-groove, 29-a stopping part, 30-a guide protrusion, 31-a guide groove, 32-a rotary driving mechanism, 33-a hoisting tool, 34-a turnout, 35-a track plate, 36-a bearing beam, 37-a mounting rack, 38-a hoisting ring, 39-a hoisting claw, 40-a railway vehicle, 41-a first transport flat vehicle, 42-a second transport flat vehicle, 43-a power device, 44-a new turnout, 45-a steel rail, 46-a base, 47-a roadbed, 48-a longitudinal moving mechanism, 49-a fixed seat, 50-a chain wheel, 51-a chain, 52-a locking mechanism, 53-a mounting seat, 54-a transverse moving support seat, 55-a lifting hook, 56-an old turnout, 57-a base plate, 100-a gantry crane and 200-a rotary mounting seat.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the drawings in the embodiments of the present invention are combined below to clearly and completely describe the technical solutions in the embodiments of the present invention. It is obvious that the described embodiments are only some of the embodiments of the present invention, and not all of them. Based on the embodiments of the present invention, all other embodiments obtained by a person of ordinary skill in the art without creative efforts belong to the protection scope of the present invention.
Referring to fig. 1 to 38, the present invention provides an embodiment of a switch replacing device and system, and the present invention will be further explained with reference to the accompanying drawings and the embodiment.
Example 1
In order to solve the technical problems of the existing hoisting equipment for the railway line, embodiment 1 provides a turnout replacing device based on hoisting of a gantry crane 100, which has the advantages of simple structure, low cost and convenient and fast operation. The turnout replacing device can utilize skylight time, and a transporting flat car is adopted to transport the gantry crane 100, the hoisting tool 33, objects needing to be operated and the like to an operation site for hoisting operation.
As shown in fig. 1 to fig. 9, an embodiment of the switch replacing device of the present invention specifically includes a gantry crane 100, the gantry crane 100 further includes:
a cross beam 1;
the sliding frames 2 are respectively movably arranged at the left end and the right end of the beam 1, and the sliding frames 2 can transversely move (in the direction W shown in the attached drawing 1) along the beam 1 so as to adjust the transverse span of the gantry crane 100;
the hoisting mechanism 4 is arranged on the cross beam 1, is positioned between the two sliding frames 2 and can transversely move along the cross beam 1 so as to adjust the hoisting position of the turnout 34;
and the supporting legs 5 are respectively arranged below the two sliding frames 2 and can extend and retract along the vertical direction (the direction is H in the attached drawing 1) so as to adjust the height of the cross beam 1 from the roadbed 47.
As shown in fig. 9, when the gantry crane 100 is deployed from the first transport flat car 41 to the railway line, the gantry crane 100 is supported on the roadbed 47 at both sides of the railway line by the support legs 5, the roadbed 47 is provided with the base 46, the base 46 is provided with the track plate 35, and the steel rail 45 is arranged on the track plate 35. The total height H of the gantry crane 100 is more than or equal to the height H1 between the bottom plate 57 of the first transport flat car 41 and the rail surface of the steel rail 45, the height H2 between the rail surface of the steel rail 45 and the roadbed 47 and the clearance H3 of the hoisting mechanism 4. The clearance H3 of the hoisting mechanism 4 is the distance from the hook 55 of the gantry crane 100 to the beam 1 at the highest position.
As shown in fig. 2, the lower part of the supporting leg 5 is further provided with an adjustable supporting leg 8, and the leveling function of the supporting leg 5 and the gantry crane 100 can be realized through the adjustable supporting leg 8. The cross beam 1 is provided with an inclination sensor 17, inclination state data of the gantry crane 100 are obtained through the inclination sensor 17, and the leveling of the cross beam 1 is realized through fine adjustment of the adjustable supporting legs 8.
The lifting mechanism 4 is further provided with a first distance sensor 14, and the first distance sensor 14 is used for acquiring the distance between the lifting mechanism 4 and the supporting leg 5, so as to realize the alignment of the transverse positions when the multiple gantry cranes 100 lift the turnout 34. When the gantry cranes 100 perform lifting operation, the first distance sensor 14 acquires the distance between the lifting mechanism 4 and the supporting legs 5, and the distance difference between the supporting legs 5 and the lifting mechanism 4 on the same side of each gantry crane 100 is controlled to meet the set requirement, so that the multiple gantry cranes 100 can be aligned in the transverse position when synchronously lifting the turnout 34.
And the two sliding frames 2 or the supporting legs 5 of the gantry cranes 100 are further provided with second distance sensors 15, and the second distance sensors 15 are used for acquiring the distance between the adjacent gantry cranes 100 so as to meet the requirement on the parallelism between the beams 1 of the two gantry cranes 100. After the first gantry crane 100 is deployed in place, the later deployed gantry crane 100 acquires the distance between the adjacent gantry cranes 100 through the second distance sensors 15 arranged on the two sliding frames 2 or the supporting legs 5, and the rotation angle of the rotary mounting base 200 is adjusted to meet the requirement of parallelism between the beams 1 of the two gantry cranes 100.
The hoisting mechanism 4 is further provided with a force sensor 16 to realize the stability control of the multiple gantry cranes 100 when hoisting the turnout 34. When the gantry crane 100 starts to hoist the new turnout 44 or the old turnout 56, the hoisting mechanism 4 of each gantry crane 100 takes the acquisition value of the force sensor 16 at that time as a reference value. If the variation value in the subsequent hoisting process exceeds the standard value, the motor rotating speed of the hoisting mechanism 4 is adjusted, so that the acquired value of the force sensor 16 of the hoisting mechanism 4 in the hoisting process is maintained to be basically equivalent to the reference value, and the vertical stability control of the multiple gantry cranes 100 during the synchronous hoisting of the turnout 34 is realized.
The gantry crane 100 further comprises a sliding driving mechanism 3, the sliding frame 2 is sleeved on the beam 1, one end of the sliding driving mechanism 3 is arranged on the beam 1, and the other end of the sliding driving mechanism is connected with the sliding frame 2. The sliding frame 2 is provided with a traversing support 54 with internal threads, and the crossbeam 1 is provided with a mounting seat 53. The sliding driving mechanism 3 adopts a power-driven screw mechanism, a power driving end of the sliding driving mechanism 3 is fixed on the mounting seat 53, a screw end is connected to the transverse moving support 54, and the sliding frame 2 is driven to move transversely by the rotation of the power-driven screw.
As shown in fig. 3 and fig. 4, a wedge-shaped locking mechanism 18 is further arranged in the sliding frame 2, and the wedge-shaped locking mechanism 18 is located between the cross beam 1 and the sliding frame 2 and comprises two wedge-shaped sliding blocks which are in contact with each other. After the locking mechanism 52 penetrates through the sliding frame 2, the two wedge-shaped sliding blocks are pressed tightly to lock the position of the sliding frame 2. When the transverse span of the two support legs 5 is adjusted in place, the position of the sliding frame 2 is locked by the wedge-shaped locking mechanism 18.
The leg 5 further comprises a threaded barrel 6, a screw 9, a seat 10 and a leg sleeve 11. The threaded cylinder 6 is connected below the sliding frame 2, the lower part of the threaded cylinder 6 is sleeved with the supporting leg sleeve 11, and the support 10 is arranged below the supporting leg sleeve 11. The screw rod 9 is arranged in the supporting leg sleeve 11, the upper end of the screw rod 9 is connected with the thread cylinder 6 through threads, and the lower end of the screw rod 9 is connected with the lifting driving mechanism 7. A lifting driving mechanism 7 is arranged in the support 10, and the lifting driving mechanism 7 drives a screw rod 9 to rotate so as to enable the threaded cylinder 6 to move up and down, so that the telescopic function of the support legs 5 is realized.
As shown in fig. 7 and 8, the switch replacing device further comprises a lifting tool 33, and the lifting tool 33 further comprises a load beam 36, a mounting frame 37, a lifting ring 38 and a lifting claw 39. The hoisting mechanism 4 includes a hook 55 capable of vertically moving, and the suspension ring 38 is disposed on the upper portion of the load beam 36, and the hook 55 is connected to the suspension ring 38. The mounting bracket 37 is provided at a lower portion of the load beam 36, and the lifting claws 39 are provided at left and right sides of the mounting bracket 37 in a line direction (direction L shown in fig. 7 and 8). The lifting ring 38 at the upper end of the lifting tool 33 can be connected with a plurality of lifting hooks 55 of the gantry crane 100 through a lifting belt or a hook, and the lower end of the lifting tool can be connected with the turnout 34 through a plurality of lifting points, as shown in fig. 6. The mounting frame 37 has a longitudinal movable function, and can move back and forth along the line direction relative to the carrier beam 36 after the switch 34 is lifted, so as to solve the problem of accurate positioning of the switch 34.
When the gantry crane 100 performs the lifting operation, the switch 34 is lifted by the lifting claw 39. After the turnout 34 is hoisted, the turnout 34 is hoisted to a specified longitudinal position by moving the turnout 34 back and forth on the load beam 36 in the direction of the line through the mounting frame 37. The mounting frame 37 is movably connected with the carrier beam 36, chain wheels 50 are arranged at two ends of the carrier beam 36 along the line direction, and the two chain wheels 50 are connected through a chain 51. The chain 51 is connected with the mounting bracket 37, one of the chain wheels 50 is driven to rotate by the longitudinal movement mechanism 48, and the chain wheel 50 rotates to drive the chain 51 to move back and forth along the line direction, so that the longitudinal movement (the direction shown as L in fig. 7 and 8) of the mounting bracket 37 is realized, and the problem of accurate positioning of the turnout 34 is solved.
The switch changing device described in embodiment 1 has the support legs 5 which are vertically telescopic and can slide on the beam 1 to adjust the span and height of the gantry crane 100 to adapt to different field conditions and the change of switches 34 with different sizes. The supporting legs 5 adopt a rotatable and leveling mechanism and are realized by adopting oil cylinders or electric screw rods and the like. The hoisting mechanism 4 can be a hoist or other hoist.
Example 2
In order to solve the problems of replacement of turnout components of the existing railway line, especially a ballastless track of a high-speed rail, embodiment 2 provides a multi-gantry crane hoisting turnout replacement system based on embodiment 1, which has the advantages of simple structure, low cost and convenience and quickness in operation. The turnout replacing system utilizes skylight time, adopts a transport flat car to transport the gantry crane 100, the hoisting tool 33 and the new turnout 44 to an operation site, and carries out hoisting and replacement of a new turnout after the gantry crane is placed at a proper position, and then transports the old turnout 56 away from the operation site.
As shown in fig. 15 and fig. 16, an embodiment of the switch changing system of the present invention based on the device of embodiment 1 specifically includes:
a rail car 40, a first transport flat car 41 and a second transport flat car 42;
a gantry crane 100 provided on the first transport flat car 41 in a transport state;
a rotary mounting base 200 which is arranged on the first transport flat car 41 in a transport state and is used for fixing the gantry crane 100;
the lifting tool 33 and the turnout 34 are arranged on the second transport flat car 42 in the transport state.
The transportation adopts rail car 40 to haul temporarily, one modified flat car (namely, a first transportation flat car 41) transports a plurality of gantry cranes 100, and two common flat cars (namely, a second transportation flat car 42) transport new and old switches, as shown in the attached fig. 15 and the attached fig. 16. The rail car 40, the first transport flat car 41 or the second transport flat car 42 is further provided with a power device 43 for providing power to the rotary mounting base 200. The power unit 43 can be of different types: the electric motor is driven by a battery or a generator, and the actuating mechanism can be electrically driven or hydraulically driven. A single drive or a centralized unified power drive mode for each rotary mount 200 may be employed.
In the operating state, a plurality of gantry cranes 100 are arranged at intervals along the railway line (as shown by L in fig. 15 and 16) and straddle the roadbed 47 on both sides of the steel rail 45. The upper part of the lifting tool 33 is connected with the lifting hooks 55 of the multiple gantry cranes 100 through the lifting rings 38, and the lower part of the lifting tool 33 is connected with the turnout 34 through the multiple lifting claws 39. After the switch 34 is lifted, the mounting frame 37 is driven by the longitudinal moving mechanism 48 to move back and forth along the line direction relative to the load beam 36, so as to realize accurate positioning of the switch 34 in the longitudinal direction.
The switch replacement system described in embodiment 2 adopts a group-lifting manner of a plurality of (generally 3 to 5) gantry cranes 100, and transports 3 to 5 gantry cranes 100, a lifting tool 33, and a new switch 44 to a working site by a rail flat car (including a rail car 40, a first transport flat car 41, and a second transport flat car 42), and the gantry cranes 100 get off to specified positions in sequence according to positions and sequences. Then, the new turnout 44 is unloaded by the group crane and the special hoisting tool 33 and is placed below the gantry crane 100. The old switch 56 is removed and replaced by the gantry crane 100. After the line is recovered, the old turnout 56 is lifted to the second transport flat car 42, and the multiple gantry cranes 100 are sequentially loaded and fixedly driven away.
Example 3
As shown in fig. 10 to 14, a rotary mounting base 200 applied to the switch changing system of embodiment 2 is used for fixing a plurality of groups of gantry cranes 100 on a first transport flat car 41 and sequentially deploying the gantry cranes at specified positions of a track, and specifically comprises:
a fixed mounting base 21 fixed on the first transport flat car 41, wherein the base of the fixed mounting base 21 is fixed on the bottom plate 57 of the first transport flat car 41;
the lifting seat 19 is used for fixedly mounting the gantry crane 100, and the lifting seat 19 can perform lifting motion relative to the fixed mounting seat 21 so as to realize that the gantry crane 100 goes up and down on the first transport flat car 41;
the swivel bearing 20 is disposed between the fixed mounting base 21 and the lifting base 19, and the lifting base 19 can perform a horizontal rotation motion with respect to the fixed mounting base 21 through the swivel bearing 20, so as to adjust the mounting direction of the gantry crane 100.
When in the transportation state, the gantry crane 100 is longitudinally fixed on the lifting seat 19. When in the deployed state, gantry crane 100 is adjusted to the transverse disposition by rotating slewing bearing 20. The rotation mounting base 200 further comprises a rotation driving mechanism 32, one end of the rotation driving mechanism 32 is fixedly mounted on the fixed mounting base 21, and the other end of the rotation driving mechanism realizes a rotation function through the gear rotation driving slewing bearing 20 with a gear on the outer ring.
The rotary mounting base 200 further comprises a locking base 22 arranged on the lifting base 19, the locking base 22 is provided with a plurality of grooves 28 for fixing the gantry crane 100, and the h-shaped beam 1 of the gantry crane is clamped and fixed through the grooves 28. And locking mechanisms 26 are arranged on the side surfaces of the locking seats 22 and close to each pair of grooves 28, and after the beam 1 of the gantry crane 100 is fixed in the grooves 28, the gantry crane 100 is locked and installed in the grooves 28 through the compression of the beam 1 by the locking mechanisms 26.
The rotary mounting base 200 further includes a guide post base 23 disposed on the rotary bearing 20, an inner ring of the rotary bearing 20 is fixedly mounted on the guide post base 23 through a bolt, and an outer ring of the rotary bearing 20 is fixedly mounted on the fixed mounting base 21 through a bolt. The guide post base 23 is provided with a guide post 25, the guide post 25 passes through a through hole formed on the lifting base 19, and when the lifting mechanism 24 performs telescopic motion, the guide post 25 realizes lifting and guiding of the lifting base 19.
The rotary mounting base 200 further comprises a lifting mechanism 24, one end of the lifting mechanism 24 is fixedly mounted on the guide post base 23, the other end of the lifting mechanism 24 is connected to the lifting base 19, and the lifting function of the gantry crane 100 is realized through the telescopic motion of the lifting mechanism 24. Two sliding mechanisms 27 are arranged on the locking seat 22 opposite to each other, a stopping part 29 is arranged on the lifting seat 19 opposite to the sliding mechanisms 27, and the movable end of the sliding mechanism 27 is contacted with the stopping part 29. When the movable end of one of the sliding mechanisms 27 is stretched, the movable end of the other sliding mechanism 27 is contracted, so that the locking seat 22 is driven to slide relative to the lifting seat 19 along the moving direction of the sliding mechanism 27. Two guide protrusions 30 are formed on the elevating base 19 to face each other in the movement direction of the slide mechanism 27, and two guide grooves 31 corresponding to the guide protrusions 30 are formed on the locking base 22. The guide groove 31 is slid on the guide projection 30 to guide the relative sliding movement between the locking base 22 and the elevating base 19.
Before the transportation of the gantry crane 100, the fixed mounting base 21 is fixed on the bottom plate 57 of the first transport flat car 41, the slewing bearing 20 is disposed between the fixed mounting base 21 and the lifting base 19, and the locking base 22 is disposed on the lifting base 19. The lifting base 19 moves up and down relative to the fixed mounting base 21, so that the gantry crane 100 can move up and down the first transport flat car 41. The elevating base 19 can perform horizontal rotation movement relative to the fixed mounting base 21 through the slewing bearing 20 to adjust the mounting direction of the gantry crane 100.
When in a transportation state, the gantry crane 100 is longitudinally locked and installed in the groove 28 of the fixed installation base 21, and the beam 1 of the gantry crane 100 is pressed and locked through the locking mechanism 26. After the working site is reached, the lifting mechanism 24 drives the gantry crane 100 to ascend to the highest point, the rotary driving mechanism 32 drives the gantry crane 100 to rotate transversely, and the lifting mechanism 24 drives the gantry crane 100 to descend to the working surface. When the support legs 5 of the gantry crane 100 are lowered to the designated positions, the locking mechanisms 26 are released, and the gantry crane 100 is disengaged from the grooves 28, so that the operation and the deployment of the gantry crane 100 are realized.
Before the gantry crane 100 is transported, the opening direction of the groove 28 of the locking seat 22 is consistent with the length direction of the first transport flat car 41, the power device 43 is started, the height of the lifting seat 19 is adjusted, and the gantry crane 100 is fixed in the groove 28. After the gantry crane 100 is transported to an operation site and reaches a designated position, the gantry crane 100 is integrally rotated by 90 ° to be perpendicular to the line direction through the rotary slewing bearing 20. The supporting legs 5 of the gantry crane 100 are descended to the roadbed 46, and the lifting seat 19 is descended to enable the gantry crane 100 to be separated from the groove 28, so that the arrangement of one gantry crane 100 is completed. All the gantry cranes 100 are sequentially deployed to the designated operation positions, the first transport flat car 41 is driven away, and the gantry cranes 100 perform lifting operation.
After the gantry crane 100 finishes the hoisting operation, the first transporting flat car 41 is driven in. The first transport flat car 41 runs to a designated position, the gantry crane 100 is aligned with the groove 28, the lifting seat 19 ascends to enable the groove 28 to approach the gantry crane 100, the locking seat 22 slides forwards and backwards relative to the lifting seat 19 to enable the groove 28 to be completely aligned with the beam 1 of the gantry crane 100, the lifting seat 19 continuously ascends to enable the beam 1 to be fixed in the groove 28, and then the locking mechanism 26 is started to compress the beam 1. The legs 5 of the gantry crane 100 are retracted to the floor 57 of the first transport flat 41. And sequentially recovering the rest of the gantry cranes 100, then rotating the slewing bearing 20 to integrally rotate the gantry cranes 100 by 90 degrees until the gantry cranes are consistent with the length direction of the first transport flat car 41, and then descending the lifting seat 19 to enable the support legs 5 of the gantry cranes 100 to contact the bottom plate 57 of the first transport flat car 41. The first transport flat carriage 41 is driven away from the work site.
Example 4
In this embodiment, save other for example the portal crane strong point and confirm, the strong point flattening, rail fastener dismantles and rail cutting welding is polished supplementary process flows such as leveling, and it is right that the following concrete use switch core changes the flow as the example the utility model discloses switch changes the operation method and carries out the detailed description.
Fig. 17 to 38 show an embodiment of a switch replacement operation method based on the system of embodiment 2, which specifically includes the following steps:
s101) a plurality of gantry cranes 100 are longitudinally fixed on a first transport flat car 41 (to adapt to vehicle limitation) through a rotary mounting base 200 (in the direction L shown in the attached drawings 17 and 18), a new turnout 44 and a lifting tool 33 are placed on a second transport flat car 42 and are transported to a designated position of a working site through traction of a rail car 40, as shown in the attached drawings 17 and 18;
s102) the rail car 40 pulls the first transporting flat car 41 to move to the placing position of the first gantry crane 100, the rotary mounting base 200 rotates for 90 degrees until the gantry crane 100 is vertical to the line direction, and at the moment, the gantry crane 100 is transversely (in the direction W shown in the attached drawing 20) fixed on the first transporting flat car 41 through the rotary mounting base 200, as shown in the attached drawings 19 and 20;
s103) moving the support legs 5 of the gantry crane 100 to an appointed position along the beam 1, and rotating the mounting base 200 to drive the gantry crane 100 to descend; the supporting legs 5 extend downwards to be close to the ground, the locking of the gantry crane 100 by the rotary mounting base 200 is released, the supporting legs 5 continue to extend and level, and the deployment of the gantry crane 100 is completed;
s104) the rail car 40 pulls the first transportation flat car 41 to move sequentially, and step S103) is repeatedly executed until all the gantry cranes 100 are deployed to the designated positions, as shown in fig. 21 and 22;
s105) the rail car 40 pulls the second transportation flat car 42 to move to a specified position, hangs the lifting tool 33 with the gantry crane 100 and the new turnout 44, and lifts the new turnout 44, as shown in fig. 23 and fig. 24;
s106) the rail car 40 pulls the first transport flat car 41 and the second transport flat car 42 to move away from the turnout replacement operation area, and the new turnout 44 is transversely moved to one side close to the supporting leg 5 and stably placed by group hoisting through a plurality of gantry cranes 100, as shown in the attached drawings 25 and 26. The rail car 40 pulls the first transport flat car 41 and the second transport flat car 42 to drive away, as shown in fig. 27.
The following procedure is also included after step S106):
s107) cutting the steel rail 45, removing the fasteners, and removing the old turnout 56;
s108) moving the lifting tool 33 to the old turnout 56 through the gantry crane 100, hanging and lifting the old turnout 56, and stably placing the old turnout 56 on the support leg 5 close to the other side of the gantry crane 100, as shown in the attached figure 28;
s109) moving the lifting tool 33 to the new turnout 44 through the gantry crane 100 and hanging the lifting tool, and smoothly placing the new turnout 44 at the position of the old turnout 56, as shown in fig. 29 and 30. If deviation exists, the position can be accurately adjusted by moving the mounting frame 37 of the lifting tool 33. And then welding the new turnout 44 with the steel rail 45, installing a fastener, and completing the restoration of the line.
The following procedure is also included after step S109):
s110) moving the lifting tool 33 to the old turnout 56 through the gantry crane 100 and hanging and lifting;
s111) the rail car 40 pulls the second transport flat car 42 to drive in;
s112) moving and placing the old turnout 56 at the designated position of the second transport flat car 42 by the lifting tool 33, as shown in fig. 31 and 32.
The following procedure is also included after step S112):
s113) the rail car 40 pulls the first transportation flat car 41 to move to the position below the gantry crane 100 at the last position, and the beam 1 of the gantry crane 100 is aligned with the groove 28 of the rotary mounting seat 200, as shown in fig. 33 and fig. 34;
s114) the supporting legs 5 of the gantry crane 100 are contracted until the cross beam 1 enters the groove 28 of the rotary mounting base 200 and fixed;
s115) the supporting legs 5 of the gantry crane 100 are continuously contracted to the initial position, the supporting legs 5 move to the initial position along the beam 1, and at the moment, the gantry crane 100 is transversely fixed on the first transport flat car 41 (in the direction W shown in the attached drawing 34) through the rotary mounting base 200;
s116) repeating the steps S113) to S115), and finishing the recovery process of the rest gantry cranes 100, as shown in the accompanying drawings 35 and 36;
s117) the rotating installation base 200 is rotated to the gantry crane 100 to be fixed longitudinally (the direction L shown in fig. 37 and 38), and the rail car 40 pulls the first transportation flat car 41 and the second transportation flat car 42 to drive away, as shown in fig. 37 and 38.
The lifting tool 33 further comprises a load beam 36, a mounting frame 37, a lifting ring 38 and a lifting claw 39. The hoisting mechanism 4 further includes a hook 55 capable of vertically moving, and the hoisting ring 38 is disposed on the upper portion of the load beam 36, and the hook 55 is connected to the hoisting ring 38. The mounting bracket 37 is provided at a lower portion of the carrier beam 36, and the hanging claws 39 are provided at left and right sides of the mounting bracket 37 in the line direction. When the gantry crane 100 performs the lifting operation, the switch 34 is lifted by the lifting claw 39. After the turnout 34 is hoisted, the turnout 34 is hoisted to a specified longitudinal position by moving the turnout 34 back and forth on the load beam 36 in the direction of the line through the mounting frame 37. The mounting frame 37 is movably connected with the carrier beam 36, chain wheels 50 are arranged at two ends of the carrier beam 36 along the line direction, and the two chain wheels 50 are connected through a chain 51. The chain 51 is connected with the mounting rack 37, one of the chain wheels 50 is driven to rotate by the longitudinal moving mechanism 48, and the chain wheel 50 rotates to drive the chain 51 to move along the line direction, so that the longitudinal movement of the mounting rack 37 is realized.
The gantry crane 100 further comprises a sliding frame 2 and a hoisting mechanism 4, the sliding frame 2 is movably arranged at the left end and the right end of the cross beam 1, and the sliding frame 2 can move transversely along the cross beam 1. A hoisting mechanism 4 is arranged on the cross beam 1 between the two sliding frames 2, and the hoisting mechanism 4 can move transversely along the cross beam 1. And supporting legs 5 which can stretch out and draw back along the vertical direction are respectively arranged below the two sliding frames 2. A sliding driving mechanism 3 is arranged between the cross beam 1 and the sliding frame 2.
A traverse support 57 with internal threads is provided on the slide frame 2, and a mounting seat 49 is provided on the cross beam 1. The sliding driving mechanism 3 adopts a power-driven screw mechanism, a power driving end of the sliding driving mechanism 3 is fixed on the mounting seat 49, a screw end is connected to the transverse moving support 57, and the sliding frame 2 is driven to move transversely by the rotation of the power-driven screw. The lower parts of the supporting legs 5 are provided with adjustable supporting feet 8, and in the process of deploying the gantry crane 100, the supporting legs 5 and the gantry crane 100 can be leveled through the adjustable supporting feet 8.
A wedge-shaped locking mechanism 18 is arranged in the sliding frame 2, and the wedge-shaped locking mechanism 18 is positioned between the cross beam 1 and the sliding frame 2 and comprises two wedge-shaped sliding blocks which are in mutual contact. The locking mechanism 48 passes through the sliding frame 2 and then compresses the two wedge-shaped sliding blocks to lock the position of the sliding frame 2. When the transverse span of the two support legs 5 is adjusted in place, the position of the sliding frame 2 is locked by the wedge-shaped locking mechanism 18.
The leg 5 further comprises a threaded barrel 6, a screw 9, a seat 10 and a leg sleeve 11. A threaded cylinder 6 is connected below the sliding frame 2, a support leg sleeve 11 is sleeved below the threaded cylinder 6, and a support 10 is arranged below the support leg sleeve 11. A lifting driving mechanism 7 is arranged in the support 10, a screw rod 9 is arranged in the supporting leg sleeve 11, the upper end of the screw rod 9 is connected with the threaded cylinder 6 through threads, and the lower end of the screw rod 9 is connected with the lifting driving mechanism 7. A bearing 13 is arranged between the spindle 9 and the bearing 10. The lifting driving mechanism 7 drives the screw rod 9 to rotate so that the thread cylinder 6 moves up and down, and the telescopic function of the supporting leg 5 is realized.
In the description of the present application, it is noted that when an element is referred to as being "fixed" or "disposed" on another element, it can be directly on the other element or be indirectly disposed on the other element; when an element is referred to as being "connected to" another element, it can be directly connected to the other element or be indirectly connected to the other element.
It will be understood that the terms "central," "longitudinal," "lateral," "length," "width," "thickness," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," and the like, as used herein, refer to an orientation or positional relationship indicated in the drawings for convenience in describing the present application and to simplicity in description, and do not indicate or imply that the referenced device or element must have a particular orientation, be constructed and operated in a particular orientation, and thus should not be construed as limiting the present application.
Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of the present application, "plurality" or "a plurality" means two or more unless specifically limited otherwise.
It should be understood that the structures, ratios, sizes, and the like shown in the drawings are only used for matching the disclosure of the specification, so as to be understood and read by those skilled in the art, and are not used to limit the conditions that the present application can be implemented, so that the present application has no technical significance.
Through implementing the utility model discloses the technical scheme of device and system is changed to switch that concrete embodiment described can produce following technological effect:
(1) The switch replacing device and the switch replacing system described in the specific embodiment of the utility model have the advantages that the support legs of the gantry crane span two sides of a railway line, the adjacent line operation is not needed, the safety risk of operating over a limit is avoided, meanwhile, the device has simple structure, high reliability, convenient maintenance and high operation efficiency, and can realize the lifting of large-size switch parts;
(2) The switch replacing device and the switch replacing system described in the specific embodiment of the utility model are not only suitable for replacing the whole set of switches, but also suitable for replacing single switch rails, switch centers and the like, and can realize the transportation, placement, position adjustment and replacement of various circuit parts with different lengths through the combination of a plurality of gantry cranes, in particular to realize the lifting of large-size switch parts;
(3) The switch replacing device and the switch replacing system described in the specific embodiment of the utility model have the advantages that the gantry crane has the functions of supporting leg transverse movement, lifting and leveling, the transverse span distance and the ground distance of the supporting leg are adjustable, the ground working condition requirements of different lines can be met, the height of the gantry crane is adjustable, and the risk of touching a contact net is avoided in the lifting process;
(4) The utility model discloses device and system are changed to switch that concrete embodiment described, portal crane low in manufacturing cost, operating personnel are few, change swift, efficient, and longitudinal installation does not surpass the vehicle boundary limit on the flatcar during portal crane transportation, and handling frock hanging point can realize that longitudinal movement makes the location of switch more accurate.
The embodiments are described in a progressive manner in the specification, each embodiment focuses on differences from other embodiments, and the same and similar parts among the embodiments are referred to each other.
The above description is only for the preferred embodiment of the present invention, and is not intended to limit the present invention in any way. Although the present invention has been described with reference to the preferred embodiments, it is not intended to limit the present invention. Those skilled in the art can make numerous changes and modifications to the disclosed embodiments, or modify equivalent embodiments, without departing from the spirit and scope of the invention, using the methods and techniques disclosed above. Therefore, any simple modification, equivalent replacement, equivalent change and modification made to the above embodiments by the technical essence of the present invention all still belong to the protection scope of the technical solution of the present invention.

Claims (12)

1. A switch changing apparatus, comprising a gantry crane (100), wherein the gantry crane (100) further comprises:
a cross beam (1);
the sliding frames (2) are respectively and movably arranged at the left end and the right end of the cross beam (1), and the sliding frames (2) can move transversely along the cross beam (1);
the hoisting mechanism (4) is arranged on the cross beam (1), is positioned between the two sliding frames (2) and can move transversely along the cross beam (1);
the supporting legs (5) are respectively arranged below the two sliding frames (2) and can extend and retract along the vertical direction.
2. The switch changing device as claimed in claim 1, wherein: the lower part of landing leg (5) is provided with adjustable stabilizer blade (8), through adjustable stabilizer blade (8) can realize right the leveling function of landing leg (5) and portal crane (100).
3. The switch changing device according to claim 1 or 2, wherein: the gantry crane (100) further comprises a sliding driving mechanism (3), the sliding frame (2) is sleeved on the cross beam (1), one end of the sliding driving mechanism (3) is arranged on the cross beam (1), and the other end of the sliding driving mechanism is connected with the sliding frame (2).
4. The switch changing device as claimed in claim 3, wherein: a transverse support (54) with internal threads is arranged on the sliding frame (2), and a mounting seat (53) is arranged on the cross beam (1); the sliding driving mechanism (3) adopts a power-driven lead screw mechanism, a power driving end of the sliding driving mechanism (3) is fixed on the mounting seat (53), and a lead screw end is connected to the transverse moving support (54).
5. The switch changing device according to claim 4, wherein: a wedge-shaped locking mechanism (18) is arranged in the sliding frame (2), and the wedge-shaped locking mechanism (18) is positioned between the cross beam (1) and the sliding frame (2) and comprises two wedge-shaped sliding blocks which are in mutual contact; after the locking mechanism (52) penetrates through the sliding frame (2), the two wedge-shaped sliding blocks are pressed tightly to lock the position of the sliding frame (2).
6. The switch changing device according to claim 4 or 5, wherein: the supporting leg (5) comprises a threaded cylinder (6), a screw rod (9), a support (10) and a supporting leg sleeve (11); the threaded cylinder (6) is connected below the sliding frame (2), the support leg sleeve (11) is sleeved on the lower portion of the threaded cylinder (6), and the support seat (10) is arranged below the support leg sleeve (11); the screw (9) is arranged in the supporting leg sleeve (11), the upper end of the screw (9) is connected with the thread cylinder (6) through threads, and the lower end of the screw is connected with the lifting driving mechanism (7); and a lifting driving mechanism (7) is arranged in the support (10), and the lifting driving mechanism (7) drives the screw rod (9) to rotate so as to enable the threaded cylinder (6) to move up and down.
7. The switch changing device as claimed in claim 6, wherein: and a bearing (13) is arranged between the screw rod (9) and the support (10).
8. The switch points changing device as claimed in claim 1, 2, 4, 5 or 7, wherein: the lifting tool (33) comprises a bearing beam (36), a mounting frame (37), a lifting ring (38) and a lifting claw (39); the lifting mechanism (4) comprises a lifting hook (55) capable of lifting and moving along the vertical direction, the lifting ring (38) is arranged at the upper part of the bearing beam (36), and the lifting hook (55) is connected with the lifting ring (38); the mounting rack (37) is movably arranged at the lower part of the bearing beam (36), and the lifting claws (39) are arranged at the left side and the right side of the mounting rack (37) along the line direction; when the gantry crane (100) carries out lifting operation, the turnout (34) is lifted through the lifting claw (39); after the turnout (34) is hoisted, the turnout (34) is hoisted to a designated longitudinal position by moving the turnout (34) back and forth on the bearing beam (36) in the line direction through the mounting rack (37).
9. The switch changing device as claimed in claim 8, wherein: the mounting frame (37) is movably connected with the bearing beam (36), chain wheels (50) are arranged at two ends of the bearing beam (36) along the line direction, and the two chain wheels (50) are connected through a chain (51); the chain (51) is connected with the mounting rack (37), one of the chain wheels (50) is driven to rotate through the longitudinal moving mechanism (48), and the chain wheel (50) rotates to drive the chain (51) to move along the line direction.
10. A switch changing system based on the device as claimed in any one of claims 1 to 9, comprising:
a rail car (40), a first transport flat car (41) and a second transport flat car (42);
a gantry crane (100) arranged on the first transport flat car (41) in a transport state;
the rotary mounting seat (200) is arranged on the first transport flat car (41) in a transport state and used for fixing the gantry crane (100);
and the lifting tool (33) and the turnout (34) are arranged on the second transport flat car (42) in a transport state.
11. The switch replacement system as claimed in claim 10, wherein: in an operating state, a plurality of gantry cranes (100) are arranged at intervals along the railway line direction and are arranged on the roadbed (47) at two sides of the steel rail (45) in a spanning manner; the upper portion of handling frock (33) links to each other with lifting hook (55) of a plurality of portal crane (100) through rings (38), the lower part of handling frock (33) is continuous with switch (34) through a plurality of lifting claws (39).
12. The switch replacement system according to claim 10 or 11, wherein: after the turnout (34) is lifted, the longitudinal moving mechanism (48) drives the mounting frame (37) to move back and forth relative to the load-bearing beam (36) along the direction of a line, so that the turnout (34) is accurately positioned in the longitudinal direction.
CN202221087897.2U 2022-05-07 2022-05-07 Switch replacing device and system Active CN217921146U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221087897.2U CN217921146U (en) 2022-05-07 2022-05-07 Switch replacing device and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221087897.2U CN217921146U (en) 2022-05-07 2022-05-07 Switch replacing device and system

Publications (1)

Publication Number Publication Date
CN217921146U true CN217921146U (en) 2022-11-29

Family

ID=84176106

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221087897.2U Active CN217921146U (en) 2022-05-07 2022-05-07 Switch replacing device and system

Country Status (1)

Country Link
CN (1) CN217921146U (en)

Similar Documents

Publication Publication Date Title
CN107642012B (en) Novel track laying machine for urban rail transit engineering and construction method thereof
CN109611112B (en) Multi-head rock drilling machine for tunnel excavation and tunneling
CN211547116U (en) A operation car for railway switch is spread and is traded
CN217499804U (en) Railway line component replacement gantry crane and group hoisting device
CN114941263B (en) Switch replacing operation method
CN112252099A (en) Operating vehicle for railway turnout replacement and operating method thereof
CN114701954A (en) Switch replacing device and system
RU2351497C1 (en) Method and device to change wheel pairs by mobile device
CN217921146U (en) Switch replacing device and system
CN114715797A (en) Track slab replacing device and system
CN114873513A (en) Gantry crane rotation fixing operation method
CN100485128C (en) Longitudinal and transverse moving device for switch and rail row
CN114808567B (en) Railway line part laying and replacing gantry crane device and operation method thereof
CN218665091U (en) Track circuit portal crane transporting device and group crane system
CN217867937U (en) Gantry crane rotary fixing device
CN217708641U (en) Track slab replacing device and system
CN114703705B (en) Intelligent control system for gantry lifting of railway line
CN114017047B (en) Tunnel cast-in-situ inverted arch lining trolley and construction method for inverted arch lining synchronous TBM tunneling
CN114673035A (en) Track slab replacing operation method
CN115467201A (en) Rapid track lifting and lining device for replacing ballastless track plate of high-speed railway and track lifting and lining method thereof
CN212292560U (en) Large-tonnage pipe ring hoisting machine
CN114684721A (en) Rail circuit gantry crane transporting device and group crane system
CN114701975A (en) Gantry crane rotary fixing device
CN114684709A (en) Gantry group-hoisting operation method for track line
CN114775344B (en) Railway line part paving and replacing operation method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant