[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN216142043U - Foundation pit support system - Google Patents

Foundation pit support system Download PDF

Info

Publication number
CN216142043U
CN216142043U CN202121498190.6U CN202121498190U CN216142043U CN 216142043 U CN216142043 U CN 216142043U CN 202121498190 U CN202121498190 U CN 202121498190U CN 216142043 U CN216142043 U CN 216142043U
Authority
CN
China
Prior art keywords
adjustable baffle
foundation pit
sleeve
adjustable
support system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121498190.6U
Other languages
Chinese (zh)
Inventor
陈进
周林
郭建岐
李君�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhenzhong Construction Group Co ltd
Original Assignee
Zhenzhong Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhenzhong Construction Group Co ltd filed Critical Zhenzhong Construction Group Co ltd
Priority to CN202121498190.6U priority Critical patent/CN216142043U/en
Application granted granted Critical
Publication of CN216142043U publication Critical patent/CN216142043U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a foundation pit support system which comprises an adjustable baffle, a sleeve connected with the adjustable baffle, a pile column for fixing the sleeve and a fixing piece fixed on the adjustable baffle, wherein the sleeve is sleeved on the pile column to enable the adjustable baffle connected with the pile column to move up and down in the height range of the pile column; the mounting is equipped with the fixed part and can dismantle the bail, and the bail of dismantling passes adjustable stop to be connected with the fixed part, is equipped with the grout passageway on the fixed part, and the space sclerosis around the fixed part is passed through the concrete to the grout passageway. The foundation pit support system is scientific and reasonable in design, the adjustable baffle can be recycled by designing the adjustable baffle and the sleeve, the adjustable baffle can be locked on the adjustable baffle while the rear part of the adjustable baffle is hardened by the fixing piece, only the pile is driven and sleeved into the sleeve during construction, and then the fixing piece is constructed, so that the foundation pit support system is simple and convenient to use and can be recycled.

Description

Foundation pit support system
Technical Field
The utility model relates to the technical field of buildings, in particular to a foundation pit support system.
Background
The foundation pit enclosure is a method for developing and utilizing underground space and building various underground buildings such as multi-layer basements, underground railways, underground commercial streets and the like. There are gravity type mixing pile retaining wall, underground continuous wall, pile row retaining wall, etc. The stability of the foundation pit and the safety and convenience of operation in the pit are ensured, and the displacement of the soil body at the bottom of the pit and outside the pit is controlled within a certain range, so that the normal use of adjacent buildings and municipal facilities is ensured.
However, the existing foundation pit support system has the problems of inconvenient construction and unrecyclable and recyclable use.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a foundation pit support system which is simple in construction and can be recycled.
In order to overcome the defects in the prior art, the utility model adopts the following technical scheme:
a foundation pit support system comprises an adjustable baffle (1), a sleeve (2) connected with the adjustable baffle (1), a pile (3) for fixing the sleeve (2) and a fixing piece (4) fixed on the adjustable baffle (1), wherein the sleeve (2) is sleeved on the pile (3) to enable the adjustable baffle (1) connected with the sleeve to move up and down in the height range of the pile (3); fixing piece (4) are equipped with fixed part (41) and can dismantle bail (42), and can dismantle bail (42) and pass adjustable fender (1) and be connected with fixed part (41), are equipped with grout passageway (411) on fixed part (41), and space hardening around fixed part (41) is passed through the concrete in grout passageway (411).
As an improvement of the scheme, the fixing part (41) is further provided with a clamping position (412), the clamping position (412) is located inside the fixing part (41) and communicated with the grouting channel (411), and the detachable clamping nail (42) is clamped with the clamping position (412).
As an improvement of the scheme, the sleeve (2) is provided with symmetrical fixing lugs (21), one fixing lug (21) is connected with the steel bars of the adjustable baffle (1) into a whole, the other fixing lug (21) is provided with a connecting hole, and the connecting hole is fixedly connected with the connecting block (11) on the other side of the adjustable baffle (1).
As an improvement of the scheme, the foundation pit support system is formed by sleeving a plurality of adjustable baffles (1) on a pile (3) through sleeves (2), and then reinforcing and locking the adjustable baffles (1) through fixing pieces (4).
The foundation pit support system is scientific and reasonable in design, the adjustable baffle can be recycled by designing the adjustable baffle and the sleeve, the adjustable baffle can be locked on the adjustable baffle while the rear part of the adjustable baffle is hardened by the fixing piece, only the pile is driven and sleeved into the sleeve during construction, and then the fixing piece is constructed, so that the foundation pit support system is simple and convenient to use and can be recycled.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without inventive exercise:
FIG. 1 is a schematic view of an embodiment of a foundation pit bracing system of the present invention;
FIG. 2 is a schematic cross-sectional view of a pile portion of a foundation pit support system;
FIG. 3 is a schematic view of a fixture of a foundation pit support system;
fig. 4 is a schematic view of the effect of the fixing part of the foundation pit support system.
Detailed Description
The present invention will be described in detail with reference to the drawings and specific embodiments, which are illustrative of the present invention and are not to be construed as limiting the present invention.
As shown in fig. 1 to 4, a foundation pit support system comprises an adjustable baffle 1, a sleeve 2 connected with the adjustable baffle 1, a pile 3 for fixing the sleeve 2, and a fixing member 4 fixed on the adjustable baffle 1, wherein the sleeve 2 is sleeved on the pile 3 to enable the adjustable baffle 1 connected with the sleeve to move up and down in the height range of the pile 3; the fixing part 4 is provided with a fixing part 41 and a detachable staple 42, the detachable staple 42 penetrates through the adjustable baffle plate 1 to be connected with the fixing part 41, a grouting channel 411 is arranged on the fixing part 41, and the grouting channel 411 hardens the space around the fixing part 41 through concrete.
In use the adjustable baffle 1 is integrally formed with the sleeve 2 and the adjustable baffle 1 is divided into 5 gauges of 500 x 800mm, 800 x 800mm, 1000 x 800mm, 1200 x 800mm and 1500 x 800mm (where 800 is the height in each gauge).
In use the half diameter of the sleeve 2 is much larger than the half diameter of the pile 3 or there must be clearance between the sleeve 2 and the pile 3.
In use the adjustable blind 1 is a precast concrete slab.
The construction steps and the working principle are described in detail: during construction, firstly, the pile 3 is vertically dug according to the specification distance of the adjustable baffle 1, a foundation pit is dug downwards, and when the height reaches the specification height of the adjustable baffle 1, the crane sleeves the adjustable baffle 1 on the pile 3. After the adjustable baffle plate 1 is fixed, the fixing part 41 is inserted into the position of the adjustable baffle plate 1, then high-pressure pouring (a pouring head is different from the detachable clamping nail 42, as shown in fig. 4) concrete is poured for hardening, finally, the detachable clamping nail 42 is used for locking the adjustable baffle plate 1, and the adjustable baffle plate 1 is mutually locked and fixed. When the foundation pit is dug continuously, the detachable clamping nails 42 are loosened to lower the adjustable baffle 1, and then the adjustable baffle 1 is added; the steps of constructing the fixing portion 41 and detaching the staples 42 are repeated.
When the adjustable baffle plate is reused, the adjustable baffle plate 1 can be detached for secondary use only by loosening the detachable clamping nails 42 (the fixing parts 41 can not be detached) and hoisting the adjustable baffle plate 1.
Furthermore, the fixing portion 41 is further provided with a fastening position 412, the fastening position 412 is located inside the fixing portion 41 and is communicated with the grouting channel 411, and the detachable staple 42 is fastened with the fastening position 412. During grouting, the detachable staple 42 is replaced with a grouting head, the grouting head is locked at the locking position 412, and high-pressure concrete enters the grouting channel 411 from the grouting head and is sprayed to the periphery of the fixing portion 41 from the grouting channel 411 to be hardened.
Specifically, sleeve 2 is equipped with the fixed ear 21 of symmetry, and a fixed ear 21 is as an organic whole with 1 steel bar connection of adjustable fender, is equipped with the connecting hole on another fixed ear 21, and the connecting hole is connected fixedly with the connecting block 11 of 1 opposite side of adjustable fender. The fixing lug 21 increases the contact area for convenient installation.
The foundation pit support system is characterized in that a plurality of adjustable baffles 1 are sleeved on a pile 3 through sleeves 2, and then the adjustable baffles 1 are reinforced and locked by fixing pieces 4.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the utility model, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (4)

1. The utility model provides a foundation pit enclosure system, includes adjustable baffle (1), sleeve (2) be connected with adjustable baffle (1), stake (3) of fixed sleeve (2) and fix mounting (4) at adjustable baffle (1), its characterized in that:
the sleeve (2) is sleeved on the pile (3) so that the adjustable baffle (1) connected with the pile into a whole can move up and down in the height range of the pile (3); fixing piece (4) are equipped with fixed part (41) and can dismantle bail (42), and can dismantle bail (42) and pass adjustable fender (1) and be connected with fixed part (41), are equipped with grout passageway (411) on fixed part (41), and space hardening around fixed part (41) is passed through the concrete in grout passageway (411).
2. The foundation pit support system of claim 1, wherein:
the fixing portion (41) is further provided with a clamping position (412), the clamping position (412) is located inside the fixing portion (41) and communicated with the grouting channel (411), and the detachable clamping nail (42) is clamped with the clamping position (412).
3. The foundation pit support system of claim 1, wherein:
the sleeve (2) is provided with symmetrical fixing lugs (21), one fixing lug (21) is connected with the steel bar of the adjustable baffle plate (1) into a whole, the other fixing lug (21) is provided with a connecting hole, and the connecting hole is fixedly connected with the connecting block (11) on the other side of the adjustable baffle plate (1).
4. The foundation pit support system of claim 1, wherein:
the foundation pit support system is characterized in that a plurality of adjustable baffles (1) are sleeved on a pile (3) through sleeves (2), and then the adjustable baffles (1) are reinforced and locked by fixing pieces (4).
CN202121498190.6U 2021-07-01 2021-07-01 Foundation pit support system Active CN216142043U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121498190.6U CN216142043U (en) 2021-07-01 2021-07-01 Foundation pit support system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121498190.6U CN216142043U (en) 2021-07-01 2021-07-01 Foundation pit support system

Publications (1)

Publication Number Publication Date
CN216142043U true CN216142043U (en) 2022-03-29

Family

ID=80802858

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121498190.6U Active CN216142043U (en) 2021-07-01 2021-07-01 Foundation pit support system

Country Status (1)

Country Link
CN (1) CN216142043U (en)

Similar Documents

Publication Publication Date Title
KR100775767B1 (en) Top-down method using the vertical steel bar for the src column
CN212503601U (en) Installation die for unit sections of vertical pipes of pipe well
CN211257007U (en) A supporting construction for building foundation ditch construction
KR200212743Y1 (en) Reinforcement structure for a foundation pile
CN216142043U (en) Foundation pit support system
KR20160000702A (en) Fastening member used in concrete filled steel tube and its using concrete filled steel tube mounting structure and method and its includes build underground structure and method
CN206667933U (en) A kind of assembled construction wall
CN212270962U (en) Foundation pit supporting and construction road integrated structure
CN211446999U (en) Foundation bolt positioning die
CN111501782A (en) Foundation pit supporting and construction road integrated structure and construction method
JP6328359B1 (en) Retaining wall construction method
KR20120122024A (en) Uniting Method of Temporary earth wall with basement exterior Wall using Couplers and Bolts.
CN215715401U (en) Can dismantle soil nailing wall structure
CN211256986U (en) Concrete pile head breaking device
JP3133615U (en) Exterior wall concrete formwork panel
CN209941733U (en) Retaining wall
CN211368733U (en) Prefabricated assembled concrete pipe props structure
KR100626326B1 (en) concrete structure
CN210003017U (en) But adopt prefabricated construction of concrete prefabricated section to enclose fender
KR200205800Y1 (en) A reinforcement structure for a foundation pile
CN219604341U (en) Bored concrete pile construction equipment
CN221798505U (en) Prefabricated cantilever type barricade of assembling
CN219993352U (en) Side protection railing of foundation pit supporting beam
KR100590178B1 (en) Fixing apparatus of cast using a dirt wall
CN217325395U (en) Steel constructs installation device in foundation ditch

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant