CN214787400U - Mine roadway reservation structure adopting cemented filling mining method - Google Patents
Mine roadway reservation structure adopting cemented filling mining method Download PDFInfo
- Publication number
- CN214787400U CN214787400U CN202022955588.XU CN202022955588U CN214787400U CN 214787400 U CN214787400 U CN 214787400U CN 202022955588 U CN202022955588 U CN 202022955588U CN 214787400 U CN214787400 U CN 214787400U
- Authority
- CN
- China
- Prior art keywords
- tunnel
- roadway
- connecting piece
- passageway
- mining method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
The utility model discloses an adopt cementation filling mining method mine tunnel reserved structure, including the tunnel, the tunnel is laid subaerially and is equipped with the bed course, has placed the passageway on the bed course, is equipped with many stull between the both sides of passageway and the both sides wall in tunnel respectively, is equipped with many erects to prop between the top of passageway and the tunnel top. And a filling body is arranged between the roadway and the channel. The tunnel reservation structure is a steel template false tunnel reserved in the original unsafe tunnel, and the tunnel reservation structure is used as a special tunnel for mine filling, ventilation, air supply, water drainage, mud discharge and the like after the unsafe tunnel is filled. Not only the potential safety hazards of the roadway are treated, but also the functions of the original roadway are kept, and meanwhile, the problem that the roadway is inconvenient to design and re-address is solved; the re-excavation of the tunnel is avoided, and the investment cost of re-excavation of the tunnel is saved.
Description
Technical Field
The utility model belongs to the technical field of cemented filling mining method mine mining, a adopt cemented filling mining method mine tunnel reserved structure is related to.
Background
In a cemented filling mining method mine, in order to manage earth pressure and meet the demand for safe production, a large-deformation and unsafe roadway is sometimes filled. However, the unsafe roadway is sometimes an important roadway of the mine, and is an indispensable important roadway, such as a ventilation roadway, a filling roadway and the like, and important pipelines of mine filling, air supply, water drainage and mud drainage and the like are erected in the roadway, so that the roadway needs to be blasted and tunneled again in or near the original roadway filling body to be used as a special roadway for filling, ventilation, air supply, water drainage and mud drainage and the like. The tunnel excavation construction process is complex, the construction efficiency is low, the excavation investment is high, and the stability of the filling body and the safety of the tunnel are reduced. Therefore, if the roadway can be reserved when the unsafe roadway is filled and is used as a special roadway for mine filling, ventilation, air supply, water drainage, mud drainage and the like, investment can be saved, and the function of a mine auxiliary system is optimized.
Disclosure of Invention
The utility model aims at providing an adopt cementation filling mining method mine tunnel reservation structure, reserve the tunnel when filling unsafe important tunnel, as the mine fill, ventilate, supply with wind water and the special tunnel of drainage mud etc..
In order to achieve the above object, the utility model adopts the following technical scheme: the utility model provides an adopt cementation filling mining method mine tunnel reserved structure, includes the tunnel, including laying the subaerial bed course in tunnel, placed the passageway on the bed course, be equipped with many studdles between the both sides of passageway and the both sides wall in tunnel respectively, be equipped with many erects to prop between the top of passageway and the tunnel top.
The utility model discloses tunnel reservation structure is the false tunnel of steel form that reserves in original unsafe tunnel, and the special tunnel that fills, ventilates, air feed water and drainage mud etc. is arranged as the mine to the back that unsafe tunnel fills. Not only the potential safety hazards of the roadway are treated, but also the functions of the original roadway are kept, and meanwhile, the problem that the roadway is inconvenient to design and re-address is solved; the re-excavation of the tunnel is avoided, and the investment cost of re-excavation of the tunnel is saved.
Drawings
Fig. 1 is the schematic diagram of the tunnel reservation structure of the utility model.
Fig. 2 is the utility model discloses the schematic diagram of prefab among the tunnel reservation structure.
Fig. 3 is a sectional view a-a in fig. 2.
Fig. 4 is the schematic diagram of the first connecting piece in the tunnel reservation structure of the utility model.
Fig. 5 is the utility model discloses the schematic diagram of second connecting piece among the tunnel reservation structure.
In the figure: 1. the novel concrete structure comprises a cushion layer, 2 channels, 3 filling bodies, 4 roadways, 5 cross braces, 6 vertical braces, 7 first connecting pieces, 8 supporting ribs, 9 second connecting pieces, 10 bolts, 11 templates, 12 first through holes, 13 second through holes, 14 first connecting piece bodies and 15 second connecting piece bodies.
Detailed Description
The present invention will be described in detail with reference to the accompanying drawings and specific embodiments.
As shown in fig. 1, the roadway reservation structure of the utility model comprises a cushion layer 1 laid on the ground of a roadway 4, wherein the cushion layer 1 is composed of a plurality of logs arranged side by side; placed passageway 2 on the bed course 1, passageway 2 is connected gradually by a plurality of cylindric prefabs and forms, is equipped with many stulls 5 between the both sides of passageway 2 and the both sides wall of tunnel 4 respectively, is equipped with many erects to prop 6 between the top of passageway 2 and the 4 tops in tunnel.
The cross braces 5 and the vertical braces 6 are both made of wood.
As shown in fig. 2 and 3, the prefabricated member in the tunnel reservation structure of the present invention includes four arc-shaped templates 11, and the four templates 11 form a cylindrical structure; the two end faces of the template 11 are respectively welded with arc-shaped first connecting pieces 7 shown in fig. 4, and the two side walls of the template 11 are respectively welded with second connecting pieces 9 shown in fig. 5.
The first connecting piece 7 and the second connecting piece 9 are both made of angle steel. The form 11 is a steel product.
The first connecting piece 7 comprises an arc-shaped first connecting piece body 14, a plurality of first through holes 12 are processed on one wing plate of the first connecting piece body 14, and the first connecting piece body 14 is fixedly connected to the end face of the template 11 through a plurality of bolts 10 and then welded. The second connecting piece 9 comprises a second connecting piece body 15, a plurality of second through holes 13 are processed on one wing plate of the second connecting piece body 15, and the second connecting piece body 15 is welded with the side wall of the template 11.
Two first connecting pieces 7 and two second connecting pieces 9 on the same template 11 are welded in sequence to form a frame, namely two ends of one first connecting piece 7 are respectively welded with the two second connecting pieces 9.
The first through holes 12 of two adjacent second connecting pieces 9 fixedly connected to two adjacent templates 11 are correspondingly arranged, and the corresponding first through holes 12 of the two second connecting pieces 9 are connected through bolts 10.
At least two supporting ribs 8 are fixedly connected to the inner arc surface of each template 11.
Before filling, the ground of an unsafe roadway 4 is cleaned, a log is placed every 1m along the passing direction of the roadway 4, the length of the log can be the same as the width of the roadway 4 for the purpose of stabilizing the log, and all logs laid on the ground of the roadway 4 form a cushion layer 1. According to the length of the filling roadway 4, a corresponding number of prefabricated members with the length of 1m and the diameter of 2.5m are sequentially placed on the cushion layer 1, and the interiors of all the prefabricated members are communicated to form the channel 2. Arranging vertical braces between the top of the prefabricated part and the top of the roadway to enable the vertical braces 6 to tightly support the top of the roadway 4 and the top of the prefabricated part, and respectively arranging cross braces 5 on two sides of the prefabricated part to enable the cross braces 5 to tightly support the side wall of the roadway 4 and the side wall of the prefabricated part so as to fix the prefabricated part; then, wrapping the outer wall of the channel 2 by plastic cloth, and plastering and compacting the joint of the connecting template 11 and the joint of the adjacent prefabricated parts in the channel 2 by cement; and then, cement mortar is injected into the roadway 4 through the connected filling pipeline, all the space between the channel 2 and the roadway 4 is filled, and the filler is solidified to form a filling body 3.
The support ribs 8 welded inside the formwork 11 can prevent the formwork 11 from sinking due to the impact of the filled cement mortar during the filling process. The wales 5 and the wales 6 can fix the formworks 11 in order not to allow the prefabricated members to move during filling, and prevent the prefabricated members from being damaged by the impact of the filled cement mortar during the filling process.
The plastic cloth is wound to wrap the outside of the channel 2, and the joint between the adjacent templates 11 and the joint between the adjacent prefabricated members are plastered by cement, so that cement mortar can be prevented from entering the channel 2 during filling.
For example:
the second mining area adopts a downward cemented filling horizontal access mining method, and some important roadways 4 of the development system are greatly deformed due to large ground pressure and long service life, and the roadways 4 generate great safety risk when being used continuously, but the roadways 4 have many important functions due to the development roadways and have to be used continuously. Consequently, the decision is reserved in some tunnels the utility model discloses the tunnel reservation structure, then fill, before filling, with unsafe tunnel 4's ground clean up, place a log every 1m along 4 current directions in tunnel, for making the log stable, the length of log can be the same with the width in tunnel 4. All logs on the ground surface of the roadway 4 form a cushion layer 1. According to the length of tunnel 4, place corresponding quantity's diameter 2.5m, length 1 m's prefab on bed course 1 in proper order, the hole intercommunication of all prefabs, passageway 2 is constituteed to all prefabs, tightly props prefab top and tunnel 4 top with vertical braces 6, tightly props prefab lateral wall and tunnel 4 lateral wall with the stull, then wraps the passageway 2 outside with the plastic cloth winding, rubs the department of meeting between the adjacent template 11 and the department of meeting between the adjacent prefab with cement from passageway 2 inside. Cement mortar is injected into the roadway 4 through a filling pipeline which is connected in advance, all the space between the roadway 4 and the channel 2 is filled, and the filling body 3 is formed after the cement mortar is solidified. The channel 2 is a false tunnel arranged in the filling body 3, thereby not only treating the potential safety hazard of the tunnel, but also keeping the function of the original tunnel.
Claims (4)
1. The utility model provides an adopt cementation filling mining method mine tunnel reserved structure, includes tunnel (4), its characterized in that, including laying in tunnel (4) subaerial bed course (1), placed passageway (2) on bed course (1), be equipped with many stull (5) between the both sides of passageway (2) and the both sides wall of tunnel (4) respectively, be equipped with many erects to prop (6) between the top of passageway (2) and tunnel (4) top.
2. The mine roadway reservation structure by cemented filling mining method according to claim 1, characterized in that the channel (2) is formed by connecting a plurality of cylindrical prefabricated members in sequence, the prefabricated members comprise four arc-shaped templates (11), and the four templates (11) form a cylindrical structure.
3. The mine roadway reservation structure by the cemented filling mining method according to claim 2, characterized in that arc-shaped first connecting pieces (7) are welded to both end faces of the template (11), and second connecting pieces (9) are welded to both side walls of the template (11); the first connecting piece (7) and the second connecting piece (9) are both made of angle steel; the second connecting piece (9) comprises a second connecting piece body (15), a plurality of second through holes (13) are processed on one wing plate of the second connecting piece body (15), and the second connecting piece body (15) is welded with the side wall of the template (11); two ends of a first connecting piece (7) positioned on the same template (11) are respectively welded with two second connecting pieces (9); the first through holes (12) of two adjacent second connecting pieces (9) fixedly connected to two adjacent templates (11) are correspondingly arranged, and the corresponding first through holes (12) of the two second connecting pieces (9) are connected through bolts (10).
4. The mine roadway reservation structure by the cemented filling mining method according to claim 2 or 3, characterized in that at least two support ribs (8) are fixedly connected to the intrados of the formwork (11).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022955588.XU CN214787400U (en) | 2020-12-11 | 2020-12-11 | Mine roadway reservation structure adopting cemented filling mining method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022955588.XU CN214787400U (en) | 2020-12-11 | 2020-12-11 | Mine roadway reservation structure adopting cemented filling mining method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN214787400U true CN214787400U (en) | 2021-11-19 |
Family
ID=78710857
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202022955588.XU Active CN214787400U (en) | 2020-12-11 | 2020-12-11 | Mine roadway reservation structure adopting cemented filling mining method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN214787400U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114607417A (en) * | 2022-03-25 | 2022-06-10 | 长沙矿山研究院有限责任公司 | High-safety transportation channel in filling body and construction method thereof |
-
2020
- 2020-12-11 CN CN202022955588.XU patent/CN214787400U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114607417A (en) * | 2022-03-25 | 2022-06-10 | 长沙矿山研究院有限责任公司 | High-safety transportation channel in filling body and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111075454B (en) | Double-arch tunnel five-hole excavation method | |
WO2021120991A1 (en) | Method for reconstructing shield tunnel for mining construction | |
CN106907159B (en) | Shallow-buried underground excavation subway station separated open type structure and construction method thereof | |
CN110630283B (en) | Three-layer supporting structure suitable for double-arch tunnel and construction method | |
CN112228082B (en) | Tunnel collapse treatment method by combined grouting of pipe shed and advanced small guide pipe | |
CN107091101B (en) | Superimposed joint structure of middle mine shield junction tunnel in sea area and construction method | |
CN110159298B (en) | Subway underground excavation station primary support buckling arch construction method | |
CN211038657U (en) | Cover encircles based deeply buries loess tunnel deformation control construction structures | |
CN110195604B (en) | Construction method for tunnel main tunnel TBM (tunnel boring machine) tunneling section | |
CN112627830B (en) | Crossover excavation construction method | |
CN113153308A (en) | Construction method for double arch tunnel collapse section | |
CN111365017B (en) | Construction method of underground intercommunication tunnel | |
CN105256812A (en) | Prefabricated assembly type concrete supporting structure for foundation pit and construction method of prefabricated assembly type concrete supporting structure | |
CN110761808A (en) | Large-section loess tunnel supporting system and supporting construction method | |
CN214787400U (en) | Mine roadway reservation structure adopting cemented filling mining method | |
CN112682048A (en) | Replacement and reinforcement construction method for newly-built tunnel to span existing tunnel at small clear distance | |
CN115717536A (en) | Inclined shaft forward-hole-entering and top-raising construction method for large-section tunnel in weak water-rich stratum | |
CN110735641B (en) | Construction method of transfer passage of underpass pipeline | |
CN110761795B (en) | Construction method of shallow tunnel in loess gully | |
CN211038656U (en) | Large-section loess tunnel supporting system | |
CN112065412A (en) | Shield air-pushing construction method for closed section of mine tunnel and guide platform used by shield air-pushing construction method | |
CN110671132A (en) | Deformation control construction structure and method for deep-buried loess tunnel based on arch sheathing | |
CN215057408U (en) | Reinforcing device for intersection of inclined shaft and main tunnel of highway tunnel | |
CN112127910B (en) | Tunnel construction extra-front supporting sheath arch structure | |
CN111502698B (en) | High-altitude tunnel construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |