CN203716495U - Column-body formwork flat-iron type column hoop - Google Patents

Column-body formwork flat-iron type column hoop Download PDF

Info

Publication number
CN203716495U
CN203716495U CN201320887338.4U CN201320887338U CN203716495U CN 203716495 U CN203716495 U CN 203716495U CN 201320887338 U CN201320887338 U CN 201320887338U CN 203716495 U CN203716495 U CN 203716495U
Authority
CN
China
Prior art keywords
cushion block
band
hole
hoop
iron formula
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320887338.4U
Other languages
Chinese (zh)
Inventor
刘红贤
李跃成
宿亚
张艳华
连斌海
张亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Construction Group Tianchen Construction Engineering Co ltd
Hebei Construction Group Corp Ltd
Original Assignee
HEBEI CONSTRUCTION GROUP TIANCHEN CONSTRUCTION ENGINEERING Co Ltd
Hebei Construction Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HEBEI CONSTRUCTION GROUP TIANCHEN CONSTRUCTION ENGINEERING Co Ltd, Hebei Construction Group Corp Ltd filed Critical HEBEI CONSTRUCTION GROUP TIANCHEN CONSTRUCTION ENGINEERING Co Ltd
Priority to CN201320887338.4U priority Critical patent/CN203716495U/en
Application granted granted Critical
Publication of CN203716495U publication Critical patent/CN203716495U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a column-body formwork flat-iron type column hoop. The column-body formwork flat-iron type column hoop comprises a flat-iron type hoop strap, hoop strap through holes are formed in the two ends of the flat-iron type hoop strap, the two sides of each hoop strap through hole are bent into the shape of a right angle to form a cushion block groove, a cushion block is placed in each cushion block groove, a cushion block through hole is formed in each cushion block and coincides with the corresponding hoop strap through hole, and a fastening bolt penetrates through the hoop strap through holes in the two sides of the flat-iron type hoop strap and the cushion block through holes to be fastened through a nut. Only one end of the column hoop needs to be fastened, and the hoop is convenient to operate and firm in use.

Description

A kind of cylinder template band iron formula tie
Technical field
The utility model relates to a kind of civil engineering appurtenance, in particular to a kind of cylinder template band iron formula tie.
Background technology
In the building operations in bridge, house etc., need to adopt cylinder template to carry out moulding, then build to pouring into steel concrete in cylinder template.The firm degree of cylinder template has material impact to construction, therefore needs to adopt multiple means to reinforce cylinder template.Now currently do the tie that fado adopts steel pipe to set up, adopt steel pipe to overlap in the surrounding of cylinder template, in order to make template stressed evenly, need constantly to change the position at steel tube lapping place, therefore finally outside cylinder template, steel pipe is spiral overlap joint propradation, and this construction technology is loaded down with trivial details, need encryption especially in bottom for tall and big concrete column, labor intensive material resources, and concrete appearance effect there will be the indenture of arc one by one, also expends a large amount of steel pipes simultaneously.Utility model patent 201020139080.6 discloses a kind of tie for bridge construction, after being connected with bolt by two hoop bodies, carry out fastening to cylinder template, although this tie has improved operating efficiency to a certain extent, save steel pipe, but carry out fastening in both sides, General Requirements operates simultaneously, or goes fastening cylinder template after first hoop body one end being connected again, and it is convenient not enough to use.
Utility model content
The purpose of this utility model is to provide a kind of cylinder template band iron formula tie, and this tie only needs one end fastening, easy to operate, uses firmly.
For achieving the above object, the utility model is taked following technical scheme:
A kind of cylinder template band iron formula tie, comprise band iron formula band, it is characterized in that, be provided with band through hole at band iron formula band two ends, each band through hole both sides are at right angles bent to form cushion block groove, in each cushion block groove, be placed with cushion block, have cushion block through hole and coincide with band through hole on described cushion block, fastening bolt passes band through hole, the cushion block through hole of band iron formula band both sides and uses fastening nuts.
Described cushion block groove below is provided with supporting plate, and described cushion block is placed on supporting plate.
The outer of described supporting plate is upwards at right angles bending, and described cushion block is between described outer and band through hole.
Described band iron formula band inner surface is provided with array of protrusions.
Described array of protrusions is circular protrusions array or tapered protrusion array.
In technique scheme, band iron formula band is in two ends bolton, once-through operation, and cushion block is placed in cushion block groove and is conducive to increase load-bearing, and the array of protrusions that band iron formula band internal layer is provided with can strengthen the frictional force of band iron formula band, and anti-skidding gets loose.
Brief description of the drawings
Fig. 1 is the utility model one embodiment package assembly schematic diagram;
Fig. 2 is another embodiment package assembly schematic diagram of the utility model;
Fig. 3 is that the utility model uses view.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model is described further:
Fig. 1 is the utility model one example structure schematic diagram, and band iron formula band 1 is made by band iron, has toughness, leave band through hole 3 at two ends, right angle bending is carried out respectively in both sides at band through hole 3, forms cushion block groove 4 and cushion block groove 5, and cushion block groove 4 and cushion block groove 5 have outer edge 2.Cushion block 7 and cushion block 8 are cuboid iron block, have respectively cushion block through hole 14 and cushion block through hole 15, and cushion block 7 is put into cushion block groove 4, and cushion block 8 is put into cushion block groove 5, and cushion block through hole 14, cushion block through hole 15 overlap with band through hole 3 respectively.Bolt 6 is through cushion block through hole 14, cushion block through hole 15 and band through hole 3 fastening with nut 9 and nut 10 at two ends.
Fig. 2 is another embodiment schematic diagram of the utility model, in this example, band iron formula band 1 inner surface has array of protrusions 11, array of protrusions 11 is circular protrusions array or tapered protrusion array, being raised with in this array of protrusions helps strengthen the frictional force of band iron formula band 1 and cylinder template, prevents slippage distortion.Below cushion block groove 4 and cushion block groove 5, be respectively equipped with supporting plate 12 and supporting plate 13, supporting plate 12 and supporting plate 13 can also upwards bend right angle, outer, to be conducive to block cushion block 7 and cushion block 8.
Use state as shown in Figure 3, the cylindrical or oval cylinder of locating template 16, outside row establishes flitch 18 for load, at one end fastening after band iron formula band 1 entangles, also interval is established and is carried out fastening with steel pipe 18.
The present embodiment is an explanation to the utility model design and realization just, is not limited, and under the utility model design, the technical scheme converting without essence is still in protection domain.

Claims (5)

1. a cylinder template band iron formula tie, comprise band iron formula band, it is characterized in that, be provided with band through hole at band iron formula band two ends, each band through hole both sides are at right angles bent to form cushion block groove, in each cushion block groove, be placed with cushion block, have cushion block through hole and coincide with band through hole on described cushion block, fastening bolt passes band through hole, the cushion block through hole of band iron formula band both sides and uses fastening nuts.
2. cylinder template band iron formula tie as claimed in claim 1, is characterized in that, described cushion block groove below is provided with supporting plate, and described cushion block is placed on supporting plate.
3. cylinder template band iron formula tie as claimed in claim 2, is characterized in that, the outer of described supporting plate is upwards at right angles bending, and described cushion block is between described outer and band through hole.
4. the cylinder template band iron formula tie as described in claim 1 or 2 or 3, is characterized in that, described band iron formula band inner surface is provided with array of protrusions.
5. cylinder template band iron formula tie as claimed in claim 4, is characterized in that, described array of protrusions is circular protrusions array or tapered protrusion array.
CN201320887338.4U 2013-12-31 2013-12-31 Column-body formwork flat-iron type column hoop Expired - Fee Related CN203716495U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320887338.4U CN203716495U (en) 2013-12-31 2013-12-31 Column-body formwork flat-iron type column hoop

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320887338.4U CN203716495U (en) 2013-12-31 2013-12-31 Column-body formwork flat-iron type column hoop

Publications (1)

Publication Number Publication Date
CN203716495U true CN203716495U (en) 2014-07-16

Family

ID=51155661

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320887338.4U Expired - Fee Related CN203716495U (en) 2013-12-31 2013-12-31 Column-body formwork flat-iron type column hoop

Country Status (1)

Country Link
CN (1) CN203716495U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105442837A (en) * 2015-12-14 2016-03-30 何景洲 House cylindrical pouring formwork and construction method
CN107023165A (en) * 2017-04-20 2017-08-08 上海建工集团股份有限公司 The sealing system and construction method of Fiberglass in Round Column Formwork
CN107023163A (en) * 2017-04-20 2017-08-08 上海建工集团股份有限公司 Fiberglass in Round Column Formwork system and its construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105442837A (en) * 2015-12-14 2016-03-30 何景洲 House cylindrical pouring formwork and construction method
CN107023165A (en) * 2017-04-20 2017-08-08 上海建工集团股份有限公司 The sealing system and construction method of Fiberglass in Round Column Formwork
CN107023163A (en) * 2017-04-20 2017-08-08 上海建工集团股份有限公司 Fiberglass in Round Column Formwork system and its construction method
CN107023163B (en) * 2017-04-20 2023-11-07 上海建工集团股份有限公司 Glass fiber reinforced plastic cylindrical template system and construction method thereof
CN107023165B (en) * 2017-04-20 2023-11-07 上海建工集团股份有限公司 Sealing system and construction method of glass fiber reinforced plastic cylindrical template

Similar Documents

Publication Publication Date Title
CN203716495U (en) Column-body formwork flat-iron type column hoop
CN203654295U (en) Single-leg inclined strut reinforced foundation pit supporting structure
CN103993893A (en) Underground construction three-dimensional reinforcing steel bar polypropylene fiber concrete support
CN203373735U (en) Prefabricated concrete tubular pile with external longitudinal webs
CN203821381U (en) Rectangular pre-stressed filling pile
CN203160227U (en) U-shaped concrete composite sheet pile
CN204456068U (en) Box-shaped steel plate occlusion diaphragm wall
CN203613795U (en) Band device for annularly reinforcing cylindrical formwork
CN202347844U (en) Steel-wood combined mould for casting circular cup rim foundation for factory building column
CN203393904U (en) Reinforcement fabric hoop
CN203270561U (en) Uplift prestressed tubular pile
CN203613532U (en) Square pile connector
CN203307798U (en) Steel pipe pile connecting base
CN103866865B (en) The pre-buried fixing means of a diameter of 48mm foundation bolt
CN202467224U (en) Crotch type steel component installing anchor ear
CN203420274U (en) Prestress loading device of pit supporting and protecting inner support system
CN204456164U (en) A kind of spliced pedestal of communication tower
CN204282920U (en) A kind of communication tower being furnished with spliced pedestal
CN207919905U (en) Hoop for anchoring reinforcing steel bars
CN206233260U (en) The coaxial piling bar offshore wind turbine foundation of reducing
CN202500328U (en) Side mould supporting structure
CN203514252U (en) Ecological-type river channel bank
CN203160228U (en) Semicircular concrete composite sheet pile
CN204982873U (en) Install composite foundation PHC pile support plate fast
CN205100565U (en) But steel pipe concrete jacking of superelevation layer is with retractable pump pipe

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 071051, No. 54 West 139, new urban district, Hebei, Baoding

Co-patentee after: HEBEI CONSTRUCTION GROUP Corp.,Ltd.

Patentee after: HEBEI CONSTRUCTION GROUP TIANCHEN CONSTRUCTION ENGINEERING Co.,Ltd.

Address before: 071051, No. 54, 139 West Road, Xinshi District, Baoding, Hebei, Baoding

Co-patentee before: HEBEI CONSTRUCTION GROUP Co.,Ltd.

Patentee before: HEBEI CONSTRUCTION GROUP TIANCHEN CONSTRUCTION ENGINEERING Co.,Ltd.

CP03 Change of name, title or address
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140716

CF01 Termination of patent right due to non-payment of annual fee