CN201803046U - Low pressure pipeline corrodes lacing film linkage - Google Patents
Low pressure pipeline corrodes lacing film linkage Download PDFInfo
- Publication number
- CN201803046U CN201803046U CN2010205051967U CN201020505196U CN201803046U CN 201803046 U CN201803046 U CN 201803046U CN 2010205051967 U CN2010205051967 U CN 2010205051967U CN 201020505196 U CN201020505196 U CN 201020505196U CN 201803046 U CN201803046 U CN 201803046U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- screw rod
- pipeline
- fixed
- sealing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 26
- 238000007789 sealing Methods 0.000 claims abstract description 26
- 239000010959 steel Substances 0.000 claims abstract description 26
- 238000005260 corrosion Methods 0.000 claims abstract description 24
- 230000007797 corrosion Effects 0.000 claims abstract description 23
- 210000004907 gland Anatomy 0.000 claims abstract description 19
- 238000012856 packing Methods 0.000 claims abstract description 16
- 239000000725 suspension Substances 0.000 claims abstract description 12
- 230000000694 effects Effects 0.000 abstract description 2
- 238000001514 detection method Methods 0.000 abstract 1
- 239000003921 oil Substances 0.000 description 4
- 238000000034 method Methods 0.000 description 2
- 238000012544 monitoring process Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000010779 crude oil Substances 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000003628 erosive effect Effects 0.000 description 1
Images
Landscapes
- Testing Resistance To Weather, Investigating Materials By Mechanical Methods (AREA)
Abstract
A low-pressure pipeline corrosion coupon hanging device is applied to the testing of oil field pipeline corrosion-resistant coupons. A gate valve is fixed in the middle of the steel pipe; the steel pipe is fixed with an emptying pipe plug, the top of the steel pipe is provided with a sealing cavity, a sealing packing is arranged in the sealing cavity, the top of the sealing cavity is provided with an internal thread, the top of the sealing cavity is fixed with a sealing gland through a thread, the sealing gland is provided with a central hole, and the cylindrical suspension rod penetrates through the sealing gland and the sealing packing; a support is fixed at the top of the steel pipe, a top plate is fixed at the top of the support, the top plate is provided with a central screw hole, and a screw rod is arranged in the central screw hole of the top plate; the top of the screw rod is a hexagonal cylinder, and the lower end of the screw rod is connected with the top end of the suspension rod. The effect is as follows: the corrosion hanging piece for detecting the low-pressure pipeline is safely and quickly installed and taken out under the condition that the normal operation of the pipeline is not affected. The labor intensity of on-site data acquisition operation is reduced, and the accuracy and the effectiveness of pipeline operation detection are enhanced.
Description
Technical field
The utility model relates to oil field pipe conveying technology field, and the device of particularly a kind of pipeline corrosion protection test is oil, feed channel is lower than the device that low pressure pipeline that 1.6MPa, temperature be lower than 100 ℃ hangs corrosion coupon at operating pressure.
Background technique
In the daily production run in oil field, often influence production run because of oil, letter shoot road inner wall corrosion or fouling, for effective inner-walls of duct prevents the burn into scale removal, interior media comprises fouling thickness, the component of inner-walls of duct to the influence of pipeline in the understanding pipeline running earlier.Thereby shoot the arrow at the target, deal with problems targetedly; Check the effect of various anti-corrosion measures in addition for convenience, need seek a kind of can be in the pipeline normal course of operation convenient, directly carry out the device of online suspension corrosion coupon, thereby detect pipeline running medium at any time to Corrosion of Pipeline.
The model utility content
The purpose of this utility model is: a kind of low pressure pipeline corrosion coupon suspension arrangement is provided, detect pipeline internal medium to the wall erosion situation at realizing in the pipeline running, adopt novel sealing structure, realize in the low pressure pipeline normal course of operation, finish conveniently, flexibly and hang the corrosion monitoring lacing film in the pipeline.
The technical solution adopted in the utility model is: low pressure pipeline corrosion coupon suspension arrangement, mainly form by top board, screw rod, support, sealing gland, sealed packing, steel pipe, VENT PLUG, boom stick and gate valve, be fixed with gate valve at the steel pipe middle part, the lower end of steel pipe can be welded on the crude oil pipeline.It is characterized in that: screw is arranged on steel pipe walls, a VENT PLUG is arranged at the screw internal fixation.Seal cage is arranged at the top at steel pipe, and sealed packing is arranged in Seal cage, at the top of Seal cage internal thread is arranged, and is fixed with sealing gland at the top of Seal cage by screw thread.Sealing gland has center hole, and cylindrical boom stick is passed sealing gland and sealed packing.Roof anchorage at steel pipe has support, and the roof anchorage of support has top board, and top board has center screw, and a screw rod is arranged in the top board center screw; The top of screw rod is the hexagonal prism body, can use the spanner rotating screw bolt.The lower end of screw rod connects the top of boom stick.
The using process of summary low pressure pipeline corrosion coupon suspension arrangement.Consult Fig. 1.At first, boom stick 8 is passed sealing gland 4 and sealed packing 5, hung lacing film 11 in the lower end of boom stick 8, under the closed condition of gate valve 9, boom stick 8 is inserted in the steel pipe 6, screwing hermetic gland 4 makes sealed packing 5 sealings; Tighten VENT PLUG 7.Secondly, support 3 is fixed on the top of steel pipe 6.Screw rod 2 lower ends are connected with boom stick 8 tops.Then, open bottom gate valve 9, be communicated with pipeline 10, last, the back drives boom stick 8 by rotary screw 2 and lacing film 11 moves down, and corrosion coupon 11 is sent to position in the predetermined pipeline 10, the test of beginning lacing film.Remove top top board 1, screw rod 2 and support 3.
When taking out lacing film 11, install top top board 1, screw rod 2 and support 3.Screw rod 2 is connected with boom stick 8 tops, and rotary screw 2 is closed gate valve 9 with the top of corrosion coupon 11 proposition gate valves 9; Open VENT PLUG 7 pressure releases, sealing gland 4 and sealed packing 5 are pulled down together with boom stick 8, lacing film 11 integral body, detect the corrosion situation of corrosion coupon 11.
The beneficial effects of the utility model: the utility model low pressure pipeline corrosion coupon suspension arrangement, not answer under the situation of the normal operation in speaking pipe road, safety, quick mounting, taking-up low-pressure line detect uses corrosion coupon.In time get accurate basic data, the operation of grasp low pressure oil-gas pipeline dynamically, avoid because of the stopping production of installing, monitoring pipeline operation conditions is brought, get angry, workload such as dismounting large-sized flange, data manipulation labor intensity is got at the reduction scene, strengthens accuracy and validity that the pipeline operation detects.
Description of drawings
Fig. 1 is the utility model low pressure pipeline corrosion coupon suspension arrangement structural profile schematic representation.
Among the figure, 1. top board, 2. screw rod, 3. support, 4. sealing gland, 5. sealed packing, 6. steel pipe, 7. VENT PLUG, 8. boom stick, 9. gate valve, 10. pipeline, 11. lacing films.
Embodiment
Embodiment 1: with a low pressure pipeline corrosion coupon suspension arrangement is example, and the utility model is described in further detail.
Consult Fig. 1.The utility model low pressure pipeline corrosion coupon suspension arrangement mainly is made up of top board 1, screw rod 2, support 3, sealing gland 4, sealed packing 5, steel pipe 6, VENT PLUG 7, boom stick 8 and gate valve 9.Steel pipe 6 has two sections, is fixed with a gate valve 9 between two sections steel pipes 6.The lower end of steel pipe 6 is vertically welded on pipeline 10 outer walls, steel pipe 6 and pipeline 10 UNICOMs.A screw is arranged on the preceding paragraph steel pipe 6 walls, a VENT PLUG 7 is arranged at the screw internal fixation.At the top of steel pipe 6 a columniform Seal cage is arranged, sealed packing 5 is arranged in Seal cage, sealed packing 5 rubber seal.Internal thread is arranged at the top at Seal cage, is fixed with sealing gland 4 at the top of Seal cage by screw thread.Sealing gland 4 has center hole, and cylindrical boom stick 8 is passed sealing gland 4 and sealed packing 5.Roof anchorage at steel pipe 6 has support 3, and the roof anchorage of support 3 has top board 1, and top board 1 has center screw, and a screw rod 2 is arranged in top board 1 center screw; The top of screw rod 2 is hexagonal prism bodies.The lower end of screw rod 2 connects the top of boom stick 8.
Claims (1)
1. low pressure pipeline corrosion coupon suspension arrangement, mainly form, be fixed with gate valve (9) at steel pipe (6) middle part by top board (1), screw rod (2), support (3), sealing gland (4), sealed packing (5), steel pipe (6), VENT PLUG (7), boom stick (8) and gate valve (9); It is characterized in that: on steel pipe (6) wall, screw is arranged, at the screw internal fixation VENT PLUG (7) is arranged, Seal cage is arranged at the top at steel pipe (6), sealed packing (5) is arranged in Seal cage, internal thread is arranged at the top at Seal cage, top at Seal cage is fixed with sealing gland (4) by screw thread, and sealing gland (4) has center hole, and cylindrical boom stick (8) is passed sealing gland (4) and sealed packing (5); Roof anchorage at steel pipe (6) has support (3), and the roof anchorage of support (3) has top board (1), and top board (1) has center screw, in top board (1) center screw a screw rod (2) is arranged; The top of screw rod (2) is the hexagonal prism body, and the lower end of screw rod (2) connects the top of boom stick (8).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010205051967U CN201803046U (en) | 2010-08-25 | 2010-08-25 | Low pressure pipeline corrodes lacing film linkage |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010205051967U CN201803046U (en) | 2010-08-25 | 2010-08-25 | Low pressure pipeline corrodes lacing film linkage |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201803046U true CN201803046U (en) | 2011-04-20 |
Family
ID=43872544
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010205051967U Expired - Lifetime CN201803046U (en) | 2010-08-25 | 2010-08-25 | Low pressure pipeline corrodes lacing film linkage |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201803046U (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103335938A (en) * | 2013-07-10 | 2013-10-02 | 陕西延长石油(集团)有限责任公司研究院 | Pipe conveying medium multi-flow-velocity corrosion determination apparatus and determination method thereof |
CN103644423A (en) * | 2013-09-24 | 2014-03-19 | 西安石油大学 | Pipeline online hanging piece device |
CN104316454A (en) * | 2014-11-10 | 2015-01-28 | 东北石油大学 | Test device for picking and placing corroded or scaled test piece on container under pressure |
CN105891100A (en) * | 2016-07-05 | 2016-08-24 | 天津亿利科能源科技发展股份有限公司 | Corrosion detecting method for petroleum pipeline without stopping production |
CN108387690A (en) * | 2018-03-20 | 2018-08-10 | 盐城力得能源科技有限公司 | A kind of fetching device with pressure of corrosion monitoring hanger and pick and place method |
CN110594552A (en) * | 2018-06-12 | 2019-12-20 | 本钢板材股份有限公司 | Closed water system corrosion rate detection pipeline hanging rack device |
CN111982793A (en) * | 2020-07-29 | 2020-11-24 | 中国石油集团工程股份有限公司 | Experimental method for evaluating corrosion resistance of inner top of pipeline and application of experimental method |
-
2010
- 2010-08-25 CN CN2010205051967U patent/CN201803046U/en not_active Expired - Lifetime
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103335938A (en) * | 2013-07-10 | 2013-10-02 | 陕西延长石油(集团)有限责任公司研究院 | Pipe conveying medium multi-flow-velocity corrosion determination apparatus and determination method thereof |
CN103335938B (en) * | 2013-07-10 | 2015-07-15 | 陕西延长石油(集团)有限责任公司研究院 | Pipe conveying medium multi-flow-velocity corrosion determination apparatus and determination method thereof |
CN103644423A (en) * | 2013-09-24 | 2014-03-19 | 西安石油大学 | Pipeline online hanging piece device |
CN104316454A (en) * | 2014-11-10 | 2015-01-28 | 东北石油大学 | Test device for picking and placing corroded or scaled test piece on container under pressure |
CN105891100A (en) * | 2016-07-05 | 2016-08-24 | 天津亿利科能源科技发展股份有限公司 | Corrosion detecting method for petroleum pipeline without stopping production |
CN108387690A (en) * | 2018-03-20 | 2018-08-10 | 盐城力得能源科技有限公司 | A kind of fetching device with pressure of corrosion monitoring hanger and pick and place method |
CN110594552A (en) * | 2018-06-12 | 2019-12-20 | 本钢板材股份有限公司 | Closed water system corrosion rate detection pipeline hanging rack device |
CN111982793A (en) * | 2020-07-29 | 2020-11-24 | 中国石油集团工程股份有限公司 | Experimental method for evaluating corrosion resistance of inner top of pipeline and application of experimental method |
CN111982793B (en) * | 2020-07-29 | 2024-03-15 | 中国石油集团工程股份有限公司 | Experimental method for evaluating corrosion resistance of inner top of pipeline and application thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201803046U (en) | Low pressure pipeline corrodes lacing film linkage | |
CN201803936U (en) | Medium-pressure pipeline corrosion hanging piece hanger | |
CN204187288U (en) | A kind of high-pressure metal pipeline does not stop production corrosion monitor | |
CN204314033U (en) | Pipe flange compactedness test macro | |
CN216559591U (en) | Be used for fire hose valve detection device | |
CN207570987U (en) | A kind of corrosion testing device for gas wellhead equipment | |
CN202251239U (en) | Looseness-proof device for hydrocylinder | |
CN203083911U (en) | Low-pressure pipeline corrosion hanging piece hanging device | |
CN203023730U (en) | Pipeline rapid-plugging device | |
CN204302109U (en) | The pressure testing device of inspection tubing | |
CN202383025U (en) | Full-size outside extrusion collapse testing device for petroleum casing pipe | |
CN204374046U (en) | A kind of negative-pressure air-flow that utilizes detects the aging device of curtain wall fluid sealant | |
CN218180799U (en) | Marine oil gas pipeline corrosion monitoring device | |
CN206683962U (en) | One kind visualization external pressure unstability experimental provision | |
CN111208055A (en) | Dynamic corrosion rate testing system for high temperature and high pressure | |
CN210311845U (en) | Anticorrosive inner wall structure of oil storage tank | |
CN205073747U (en) | From basket pipe -line filter of blowdown | |
CN201177163Y (en) | Pipeline leak detection device | |
CN101839792A (en) | Novel pneumatic hydraulic system for detection | |
CN201083592Y (en) | Continuous casting crystallizer soft clamping system oil cylinder detection device | |
CN202074960U (en) | Floating ball valve seat testing device | |
CN105508880A (en) | Corrosion monitoring device for high-pressure metal pipeline without production halts | |
CN220398818U (en) | Valve tightness detection device | |
CN220750827U (en) | Nitrogen protection mechanism for pushed slab kiln | |
CN217927381U (en) | Valve protection box |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term | ||
CX01 | Expiry of patent term |
Granted publication date: 20110420 |