CN201500533U - Furnace tube connecting device of reforming furnace - Google Patents

Furnace tube connecting device of reforming furnace Download PDF

Info

Publication number
CN201500533U
CN201500533U CN2009201766192U CN200920176619U CN201500533U CN 201500533 U CN201500533 U CN 201500533U CN 2009201766192 U CN2009201766192 U CN 2009201766192U CN 200920176619 U CN200920176619 U CN 200920176619U CN 201500533 U CN201500533 U CN 201500533U
Authority
CN
China
Prior art keywords
boiler tube
pigtail
arc
pipe
furnace
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009201766192U
Other languages
Chinese (zh)
Inventor
张惊涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Sepmem Sci & Tech Co Ltd
Original Assignee
Chengdu Sepmem Sci & Tech Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Sepmem Sci & Tech Co Ltd filed Critical Chengdu Sepmem Sci & Tech Co Ltd
Priority to CN2009201766192U priority Critical patent/CN201500533U/en
Application granted granted Critical
Publication of CN201500533U publication Critical patent/CN201500533U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Devices And Processes Conducted In The Presence Of Fluids And Solid Particles (AREA)

Abstract

The utility model relates to connecting structures of hydrogen producing reforming furnaces, ammonia synthesizing reforming furnaces, methanol device reforming furnaces and the like, in particular to a furnace tube connecting device of a reforming furnace, which consists of a cannula (1), an arc porous baffle (2), a furnace tube (3) and a pigtail tube (4), and is characterized in that the cannula (1) is arranged at the upper part and inner side of the furnace tube (3), the arc porous baffle (2) is arranged at the lower part of the cannula (1) and inside the furnace tube (3), and the furnace tube (3) is connected with another furnace tube (3) through the pigtail tube (4).

Description

The converting furnace jockey
Technical field
The utility model relates to the syndeton of hydrogen manufacturing conversion furnace, synthetic ammonia converting, methanol device reburner etc., is specially a kind of converting furnace jockey.
Background technology
Reburner is the key equipment of device for producing hydrogen, synthetic ammonia installation, methanol device, and boiler tube and pigtail are the important component parts of reburner, and boiler tube mainly is the filling reforming catalyst, absorbs the medium generation chemical reaction that heat Gong passes through; And pigtail plays the effect that connects two boiler tubes, not only will transmit processing medium, and will effectively absorb because boiler tube at high temperature is out of shape; In actual production, our common converting furnace connected mode is single independence, the boiler tube upper end links to each other with last discharge by pigtail, down pigtail pipe links to each other with outlet manifold, this kind structure lower inlet and outlet are respectively at the equipment two ends, for guaranteeing that medium has the enough reaction time, boiler tube just must have enough length, and the length of boiler tube is the principal element that influences the reburner height, and boiler tube is long more, the reburner height is just high more, be not quite reasonable just also economically, because conversion tube is longer, swell increment is bigger simultaneously, the welding position of down pigtail pipe and boiler tube is easy to generate stress and concentrates, thereby increases the risk of weld cracking.
Summary of the invention
The utility model is just at above technical problem, and purpose is to provide a kind of reduction reburner height, but whole Transporting and the little converting furnace jockey of investment when transforming on a small scale.
Concrete technical scheme of the present utility model is as follows:
The converting furnace jockey, form by sleeve pipe, arc perforated baffle, boiler tube and pigtail, sleeve pipe is arranged on the top of boiler tube and in the inboard, the arc perforated baffle is arranged on the bottom of sleeve pipe and in boiler tube, boiler tube is connected with another root boiler tube by pigtail.
Boiler tube can be two or many connections.
Pigtail is a symmetrical structure, stay straight-run of pipe with the boiler tube junction, straight length is parallel with axis, curved left again one section arc stays straight-run of pipe after shape has a certain degree, again to the axis direction bend pipe, stay the certain-length straight length parallel with axis, bend 90 ° of arcs more to the right, stay certain straight length coaxial line vertical again, become the symmetrical structure of sealing.
The arc perforated baffle is pressed into arc, and the size of baffle plate can be blocked outlet opening fully, the close pore that drills through above it.
Technique effect of the present utility model shows: adopted the cascaded structure of boiler tube, effectively reduced the length of boiler tube, guaranteed the enough reaction time simultaneously again; Can also effectively reduce the reburner height, more reasonable economically.
Description of drawings
Fig. 1 is a structural representation of the present utility model
Wherein, 1---sleeve pipe, 2---lonely shape perforated baffle, 3---boiler tube, 4---pigtail
The specific embodiment
The utility model is described in further detail below in conjunction with the specific embodiment and Figure of description
Embodiment:
The converting furnace jockey, form by sleeve pipe 1, arc perforated baffle 2, boiler tube 3 and pigtail 4, sleeve pipe 1 is arranged on the top of boiler tube 3 and in the inboard, arc perforated baffle 2 is arranged on the bottom of sleeve pipe 1 and in boiler tube 3, boiler tube 3 is connected with another root boiler tube 3 by pigtail 4.
Boiler tube 3 can be two or many connections.
Pigtail 4 is a symmetrical structure, stay straight-run of pipe with the boiler tube junction, straight length is parallel with axis, curved left again one section arc stays straight-run of pipe after shape has a certain degree, again to the axis direction bend pipe, stay the certain-length straight length parallel with axis, bend 90 ° of arcs more to the right, stay certain straight length coaxial line vertical again, become the symmetrical structure of sealing.
Arc perforated baffle 2 is pressed into arc, and the size of baffle plate can be blocked outlet opening fully, the close pore that drills through above it.
Boiler tube 3 tops are fixed on the reburner by bearing, and under actual condition, medium enters in the boiler tube 3 by boiler tube 3 imports, and boiler tube absorbs the radiations heat energy of burner, causes medium generation chemical reaction; In this process, boiler tube 3 expands because be heated, this just needs pigtail 4 to absorb the stress that boiler tube 3 temperature distortions produce, boiler tube 3 connects by pigtail 4, and when medium enters the boiler tube 3 of outlet side, air-flow can drive catalyst and enter in the outlet, stop up for preventing that catalyst from forming in the exit, arc porous plate 2 is set in the exit, and arc porous plate 2 is welded on the sleeve pipe 1, and the size specification of arc porous plate 2 is according to the size decision of the outlet mouth of pipe.

Claims (4)

1. converting furnace jockey, form by sleeve pipe (1), arc perforated baffle (2), boiler tube (3) and pigtail (4), it is characterized in that: sleeve pipe (1) is arranged on the top of boiler tube (3) and in the inboard, arc perforated baffle (2) is arranged on the bottom of sleeve pipe (1) and in boiler tube (3), boiler tube (3) is connected with another root boiler tube (3) by pigtail (4).
2. boiler tube according to claim 1 (3) is characterized in that: boiler tube (3) can be two or many connections.
3. pigtail according to claim 1 (4), it is characterized in that: pigtail (4) is a symmetrical structure, stay straight-run of pipe with the boiler tube junction, straight length is parallel with axis, curved left again one section arc, after having a certain degree, shape stays straight-run of pipe, to the axis direction bend pipe, stay the certain-length straight length parallel again, bend 90 ° of arcs more to the right with axis, stay certain straight length coaxial line vertical again, become the symmetrical structure of sealing.
4. arc perforated baffle according to claim 1 (2) is characterized in that: arc perforated baffle (2) is pressed into arc, and the size of baffle plate can be blocked outlet opening fully, the close pore that drills through above it.
CN2009201766192U 2009-09-07 2009-09-07 Furnace tube connecting device of reforming furnace Expired - Fee Related CN201500533U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009201766192U CN201500533U (en) 2009-09-07 2009-09-07 Furnace tube connecting device of reforming furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009201766192U CN201500533U (en) 2009-09-07 2009-09-07 Furnace tube connecting device of reforming furnace

Publications (1)

Publication Number Publication Date
CN201500533U true CN201500533U (en) 2010-06-09

Family

ID=42451475

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009201766192U Expired - Fee Related CN201500533U (en) 2009-09-07 2009-09-07 Furnace tube connecting device of reforming furnace

Country Status (1)

Country Link
CN (1) CN201500533U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103785333A (en) * 2014-02-20 2014-05-14 刘建国 Energy-saving steam-reforming furnace pipe
CN108786666A (en) * 2017-04-28 2018-11-13 中国石化工程建设有限公司 Burn reburner in side
CN108786667A (en) * 2017-04-28 2018-11-13 中国石化工程建设有限公司 U-tube reburner

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103785333A (en) * 2014-02-20 2014-05-14 刘建国 Energy-saving steam-reforming furnace pipe
CN108786666A (en) * 2017-04-28 2018-11-13 中国石化工程建设有限公司 Burn reburner in side
CN108786667A (en) * 2017-04-28 2018-11-13 中国石化工程建设有限公司 U-tube reburner
CN108786666B (en) * 2017-04-28 2021-12-10 中国石化工程建设有限公司 Side burning converter

Similar Documents

Publication Publication Date Title
CN207153662U (en) A kind of isothermal change furnace
CN201500533U (en) Furnace tube connecting device of reforming furnace
CN210012585U (en) Sleeve type hydrocarbon gas heat exchange type converter
CN206950989U (en) A kind of VOCs exhaust fume catalytics oxidation furnaces
CN201401951Y (en) Electric heating element of water heater
CN203411320U (en) Converter device
CN203944358U (en) A kind of saturated hot-water moves the isothermal radial shift-converter of the full self-unloading of heat
CN218642476U (en) Airflow diversion part, heat exchange assembly and steam reforming hydrogen production conversion pipe
CN107285277B (en) Device and method for preparing synthesis gas by hydrocarbon steam conversion
CN102723514B (en) Solid oxide fuel cells power generating system and methane vapor reforming unit thereof
CN202253695U (en) Movable smoke hood for waste heat boiler
CN2810737Y (en) Self-heating, heat-exchanging type reborner furnace tube
CN102345872A (en) Movable gas hood for exhaust-heat boiler
CN203479028U (en) Reformer device using product gas waste heat
CN204247178U (en) The water bed reactor of beam tube type
CN201980995U (en) Heat transferring reformer
CN210393751U (en) Two low catalyst intensification reduction systems that become based on ammonia process
CN203605202U (en) Efficient waste heat boiler
CN105126708A (en) Hydrogen deoxidation isothermal multitubular reactor
CN205878969U (en) Tower air preheater goes into with high flow rate and high heat transfer ability
CN201058809Y (en) A Reforming Gas Outlet System of a Hydrocarbon Steam Reformer
CN216662483U (en) Heat exchange type conversion device utilizing converted flue gas
CN118359169B (en) Electric steam reformer for producing hydrogen-rich synthetic gas from natural gas
CN223096744U (en) A double-pass door type furnace tube
CN219032239U (en) Hydrogen metallurgy device based on methyl alcohol hydrogen production

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100609

Termination date: 20140907

EXPY Termination of patent right or utility model