CN209123408U - A kind of water pollution control sedimentation basin - Google Patents
A kind of water pollution control sedimentation basin Download PDFInfo
- Publication number
- CN209123408U CN209123408U CN201821747755.8U CN201821747755U CN209123408U CN 209123408 U CN209123408 U CN 209123408U CN 201821747755 U CN201821747755 U CN 201821747755U CN 209123408 U CN209123408 U CN 209123408U
- Authority
- CN
- China
- Prior art keywords
- sedimentation basin
- water
- pollution control
- sludge
- water pollution
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Separation Of Suspended Particles By Flocculating Agents (AREA)
Abstract
The utility model discloses a kind of water pollution control sedimentation basins, including No.1 sedimentation basin and stripper plate, water inlet is provided on the right side of No.1 sedimentation basin, and the inside of water inlet is equipped with filter net cloth, No.1 sedimentation basin is internally provided with baffle, and the upper surface of No.1 sedimentation basin is provided with air outlet, suction ventilator is installed above air outlet, and FY2428 airstrainer is installed on the right side of suction ventilator, current limiting plate is provided on the right side of the FY2428 airstrainer, and connecting rod is connected with above current limiting plate, the right end of the connecting rod is connected with kickboard, and No. two sedimentation basins are provided on the right side of kickboard.The water pollution control sedimentation basin can be to be sterilized in sedimentation basin, prevent algae from breeding on a large scale, and sedimentation basin discharge irritative gas can be continuously, and sludge can be squeezed into fast shape processing, facilitate the collection of sludge, and current limiter is mounted between two sedimentation basins, sewage is prevented excessively directly to be discharged from water outlet.
Description
Technical field
The utility model relates to sedimentation basin technical field, specially a kind of water pollution control sedimentation basin.
Background technique
Sedimentation basin is a kind of structures that suspended matter in water removal is removed using precipitation, and sedimentation basin is in the treatment of waste water widely
It uses, present sedimentation basin can be substantially divided into three categories, and one kind is flat flow, and one kind is vertical-flow and radial-flow, vertical-flow
It is more difficult that construction is compared with other two kinds, using minimum, is most widely used that flat flow.
Sedimentation basin on the market all has certain disadvantages now, and existing sedimentation basin, which cannot play, carried out sewage
Filter, it is likely that so that the growth inside of sedimentation basin goes out floating algae etc., the water purification of discharge is polluted, and internal long-time seals, so that heavy
The internal stimulus smell in shallow lake pond gradually increases weight, it is difficult to it removes, existing sedimentation basin cannot control water flow well, and generate
Sludge, which is deposited in storage mud groove, will cause blocking, cause sludge to be difficult to the problem of excluding, for this purpose, it is proposed that a kind of water pollution control
Sedimentation basin.
Summary of the invention
The purpose of this utility model is to provide a kind of water pollution control sedimentation basins, to solve to propose in above-mentioned background technique
Existing sedimentation basin cannot play sewage is filtered, it is likely that so that the growth inside of sedimentation basin goes out floating algae etc., pollution
The water purification of discharge, and internal sealing for a long time, so that the internal stimulus smell of sedimentation basin gradually increases weight, it is difficult to it removes, it is existing
Sedimentation basin cannot control water flow well, and the sludge generated is deposited in storage mud groove will cause blocking, so that sludge is difficult to arrange
Except the problems such as.
To achieve the above object, the utility model provides the following technical solutions: a kind of water pollution control sedimentation basin, including one
Number sedimentation basin and stripper plate are provided with water inlet on the right side of the No.1 sedimentation basin, and the inside of water inlet is equipped with filter screen
Cloth, the No.1 sedimentation basin is internally provided with baffle, and the upper surface of No.1 sedimentation basin is provided with air outlet, the air outlet
Top suction ventilator is installed, and FY2428 airstrainer is installed on the right side of suction ventilator, the bottom of the No.1 sedimentation basin
Face is provided with sludge settling mouth, and storage mud groove is connected with below sludge settling mouth, and the stripper plate is installed on the interior of storage mud groove
Portion, and infrared launcher and infrared receiving device are provided with above stripper plate, the infrared receiving device is installed on infrared
The bottom surface on the right side of emitter, the storage mud groove is equipped with sludge outlet, is connected with hydraulic stem on the left of the stripper plate,
And hydraulic pump is provided on the left of hydraulic stem, it is provided with current limiting plate on the right side of the FY2428 airstrainer, and current limiting plate
Top is connected with connecting rod, and the right end of the connecting rod is connected with kickboard, and No. two sedimentation basins are provided on the right side of kickboard, described
Water outlet is connected on the right side of No. two sedimentation basins.
Preferably, the connection type between the filter net cloth and water inlet is bonding connection, and filter net cloth is about entering
The vertical centerline at the mouth of a river is symmetrical to be provided with 4 groups.
Preferably, the air outlet is through the upper surface of No.1 sedimentation basin, and air outlet passes through suction ventilator and FY2428
Connectivity structure is constituted between airstrainer.
Preferably, the sludge settling mouth is through the bottom surface of No.1 sedimentation basin, and sludge settling mouth is heavy by No.1
Connectivity structure is constituted between shallow lake pond and storage mud groove.
Preferably, the infrared launcher and infrared receiving device are located on same level direction, and stripper plate passes through
Stretching structure is constituted between hydraulic stem and hydraulic pump.
Preferably, the connection type between the current limiting plate and connecting rod is to be fixedly connected, and water outlet is than water inlet
Highly low 10cm.
Compared with prior art, the beneficial effects of the utility model are as follows:
1. the inside for the filter net cloth being arranged can fill in ferric trichloride coagulant and various bactericidal liquids, the purpose done so
It is to avoid the inside bacterium of sedimentation basin from largely breeding and the case where floating algae occur, so that the water of water outlet is cleaner, setting
The gas of the penetrating odor inside sedimentation basin can be discharged in air outlet in real time, convenient for cleanup crew's later period to the clear of sedimentation basin
It is clean, and smell passes through by greatly reducing pollution in draining into air;
2. the purpose for the sludge settling mouth being arranged is that sediment can be made to first flow into sludge settling mouth, avoid due to
The water flow and other reasons of top again roll sediment, and the infrared launcher of setting is used to provide for infrared receiving device
Signal simultaneously passes to hydraulic pump, sludge is squeezed into bulk, sludge is made to be easier to collect, the phenomenon that will not resulting in blockage;
3. the flowing water for the sewage that the purpose limitation No.1 sedimentation basin that current limiting plate is arranged is flowed into No. two sedimentation basins, avoids occurring
The phenomenon that water outlet sewerage, and the device relies on the buoyancy of water, compares other modes and saves a large amount of electric energy, and not
It needs manually to guard.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is partial enlarged view at the utility model A;
Fig. 3 is that the utility model stores up mud groove overlooking structure diagram;
Fig. 4 is utility model works flow chart.
In figure: 1, No.1 sedimentation basin;2, water inlet;3, filter net cloth;4, baffle;5, air outlet;6, suction ventilator;7,
FY2428 airstrainer;8, sludge settling mouth;9, mud groove is stored up;10, stripper plate;11, infrared launcher;12, infrared receiver
Device;13, sludge outlet;14, hydraulic stem;15, hydraulic pump;16, current limiting plate;17, connecting rod;18, kickboard;19, water outlet;
20, No. two sedimentation basins.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-4 is please referred to, the utility model provides a kind of technical solution: a kind of water pollution control sedimentation basin, including No.1
Sedimentation basin 1 and stripper plate 10, the right side of No.1 sedimentation basin 1 is provided with water inlet 2, and the inside of water inlet 2 is equipped with filter screen
Cloth 3, No.1 sedimentation basin 1 is internally provided with baffle 4, and the upper surface of No.1 sedimentation basin 1 is provided with air outlet 5, air outlet 5
Top is equipped with suction ventilator 6, and the right side of suction ventilator 6 is equipped with FY2428 airstrainer 7, the bottom surface of No.1 sedimentation basin 1
It is provided with sludge settling mouth 8, and the lower section of sludge settling mouth 8 is connected with storage mud groove 9, stripper plate 10 is installed on the interior of storage mud groove 9
Portion, and the top of stripper plate 10 is provided with infrared launcher 11 and infrared receiving device 12, infrared receiving device 12 is installed on
The bottom surface on the right side of infrared launcher 11, storage mud groove 9 is equipped with sludge outlet 13, and the left side of stripper plate 10 is connected with hydraulic
Bar 14, and the left side of hydraulic stem 14 is provided with hydraulic pump 15, the right side of FY2428 airstrainer 7 is provided with current limiting plate 16, and
The top of current limiting plate 16 is connected with connecting rod 17, and the right end of connecting rod 17 is connected with kickboard 18, and the right side of kickboard 18 is provided with
No. two sedimentation basins 20, the right side of No. two sedimentation basins 20 are connected with water outlet 19, the connection side between filter net cloth 3 and water inlet 2
Formula is bonding connection, and filter net cloth 3 about water inlet 2 vertical centerline it is symmetrical be provided with 4 groups, effect is setting
The inside of filter net cloth 3 can fill in ferric trichloride coagulant and various bactericidal liquids, the purpose for the arrangement is that avoiding sedimentation basin
Inside bacterium largely breed and the case where floating algae occur so that the water of water outlet 19 is cleaner, air outlet 5 is through No.1
The upper surface of sedimentation basin 1, and air outlet 5 is made by constituting connectivity structure between suction ventilator 6 and FY2428 airstrainer 7
The gas of the penetrating odor inside sedimentation basin can be discharged in real time with the air outlet 5 for being setting, be convenient for cleanup crew's later period
Cleaning to sedimentation basin, and smell passes through by greatly reducing pollution, sludge settling mouth 8 through one in draining into air
The bottom surface of number sedimentation basin 1, and sludge settling mouth 8 is made by constituting connectivity structure between No.1 sedimentation basin 1 and storage mud groove 9
Purpose with the sludge settling mouth 8 for being setting is that sediment can be made to first flow into sludge settling mouth 8, is avoided due to top
Water flow and other reasons sediment is rolled again, infrared launcher 11 and infrared receiving device 12 are located at same level side
Upwards, and stripper plate 10 is by constituting stretching structure between hydraulic stem 14 and hydraulic pump 15, and acting on is the infrared emission being arranged
Device 11 is used to provide signal for infrared receiving device 12 and pass to hydraulic pump 15, and sludge is squeezed into bulk and makes sludge more
It is easy to collect, the phenomenon that will not resulting in blockage, the connection type between current limiting plate 16 and connecting rod 17 is to be fixedly connected, and go out
The mouth of a river 19 is 10cm lower than the height of water inlet 2, and effect is that the purpose limitation No.1 sedimentation basin 1 of setting current limiting plate 16 is heavy to No. two
Shallow lake pond 20 flow into sewage flowing water, avoid occur 19 sewerage of water outlet, and the device by water buoyancy, phase
A large amount of electric energy is saved compared with other modes, and does not need manually to guard.
Working principle:, should first come the major part for learning about it for a kind of this kind of water pollution control sedimentation basin
Device is mainly made of No.1 sedimentation basin 1 and stripper plate 10, and being mainly characterized by for the device can be to be sterilized in sedimentation basin,
It prevents algae from breeding on a large scale, and sedimentation basin discharge irritative gas can be continuously, convenient for cleaning, and can be by sludge
It is squeezed into fast shape processing, facilitates the collection of sludge, and be mounted with current limiter between two sedimentation basins, prevents sewage excessively straight
It connects from water outlet 19 and is discharged, when using the device, insert some ferric trichloride coagulant into filter net cloth 3 first, when entering
After sewage is accessed at the mouth of a river 2, the filtering that sewage first passes through filter net cloth 3 is flowing to No.1 sedimentation basin 1, prevents two sedimentation basin intussusceptions
Raw a large amount of algae, then sewage reaches the inside of No.1 sedimentation basin 1 after baffle 4, one in No.1 sedimentation basin 1
Point sludge and water separation, this partial sludge be fed directly to lower section sludge settling mouth 8 in, prevent top water flow and other
The influence of factor causes sludge to be rolled-up, and then sludge continues to fall in downwards in storage mud groove 9, when sludge saves bit by bit certain height
When, sludge blocks the signal that infrared receiving device 12 receives infrared launcher 11, so that infrared receiving device 12 is to hydraulic
15 transmitting signal of pump, hydraulic pump 15 starts to start and extend hydraulic stem 14, so that two stripper plates 10 start relative motion, and most
A large amount of sludge is squeezed into bulk at last, be flowed into immediately below sludge outlet 13 at leave sedimentation basin, while suction ventilator 6 can be with
Smell inside No.1 sedimentation basin 1 is discharged low-power, and the sludge of another part flows to No. two sedimentation basins 20, process and No.1
The identical step of sedimentation basin 1, which is played, to be precipitated, so that sludge settling is more thorough, if the sludge of No.1 sedimentation basin 1 is excessive, is made
Water level in No. two sedimentation basins 20 increases, in order to avoid to exclude sludge and clean water water outlet 19 is discharged together, out
The kickboard 18 of the top setting at the mouth of a river 19 can be made current limiting plate 16 move up by buoyancy, thus limited flow rate, here it is
The process for using and working principle of the device.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.
Claims (6)
1. a kind of water pollution control sedimentation basin, including No.1 sedimentation basin (1) and stripper plate (10), it is characterised in that: the No.1
It is provided on the right side of sedimentation basin (1) water inlet (2), and the inside of water inlet (2) is equipped with filter net cloth (3), the No.1 is heavy
Shallow lake pond (1) is internally provided with baffle (4), and the upper surface of No.1 sedimentation basin (1) is provided with air outlet (5), the air outlet
(5) it is equipped with above suction ventilator (6), and FY2428 airstrainer (7), the No.1 is installed on the right side of suction ventilator (6)
The bottom surface of sedimentation basin (1) is provided with sludge settling mouth (8), and storage mud groove (9), institute are connected with below sludge settling mouth (8)
State stripper plate (10) be installed on storage mud groove (9) inside, and be provided with above stripper plate (10) infrared launcher (11) and
Infrared receiving device (12), the infrared receiving device (12) are installed on the right side of infrared launcher (11), the storage mud groove
(9) bottom surface is equipped with sludge outlet (13), is connected with hydraulic stem (14) on the left of the stripper plate (10), and hydraulic stem
(14) it is provided on the left of hydraulic pump (15), is provided with current limiting plate (16) on the right side of the FY2428 airstrainer (7), and limit
It is connected with above flowing plate (16) connecting rod (17), the right end of the connecting rod (17) is connected with kickboard (18), and kickboard (18)
Right side be provided with No. two sedimentation basins (20), be connected with water outlet (19) on the right side of No. two sedimentation basins (20).
2. a kind of water pollution control sedimentation basin according to claim 1, it is characterised in that: the filter net cloth (3) with enter
Connection type between the mouth of a river (2) is bonding connection, and filter net cloth (3) symmetrically divides about the vertical centerline of water inlet (2)
Cloth is provided with 4 groups.
3. a kind of water pollution control sedimentation basin according to claim 1, it is characterised in that: the air outlet (5) through
The upper surface of No.1 sedimentation basin (1), and air outlet (5) passes through the company of composition between suction ventilator (6) and FY2428 airstrainer (7)
Logical structure.
4. a kind of water pollution control sedimentation basin according to claim 1, it is characterised in that: the sludge settling mouth (8) is passed through
It is through at the bottom surface of No.1 sedimentation basin (1), and sludge settling mouth (8) between No.1 sedimentation basin (1) and storage mud groove (9) by constituting
Connectivity structure.
5. a kind of water pollution control sedimentation basin according to claim 1, it is characterised in that: the infrared launcher (11)
Be located on same level direction with infrared receiving device (12), and stripper plate (10) by hydraulic stem (14) and hydraulic pump (15) it
Between constitute stretching structure.
6. a kind of water pollution control sedimentation basin according to claim 1, it is characterised in that: the current limiting plate (16) with connect
Connection type between bar (17) is to be fixedly connected, and water outlet (19) is 10cm lower than the height of water inlet (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821747755.8U CN209123408U (en) | 2018-10-26 | 2018-10-26 | A kind of water pollution control sedimentation basin |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821747755.8U CN209123408U (en) | 2018-10-26 | 2018-10-26 | A kind of water pollution control sedimentation basin |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209123408U true CN209123408U (en) | 2019-07-19 |
Family
ID=67232828
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821747755.8U Expired - Fee Related CN209123408U (en) | 2018-10-26 | 2018-10-26 | A kind of water pollution control sedimentation basin |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209123408U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111732280A (en) * | 2020-06-30 | 2020-10-02 | 浙江通恒环保科技有限公司 | Sewage purification process and equipment for producing green environment-friendly PET bottle flakes |
CN112919596A (en) * | 2021-01-29 | 2021-06-08 | 天津市润达金源水务有限公司 | Device and method for recycling magnetic powder in magnetic flocculation system |
-
2018
- 2018-10-26 CN CN201821747755.8U patent/CN209123408U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111732280A (en) * | 2020-06-30 | 2020-10-02 | 浙江通恒环保科技有限公司 | Sewage purification process and equipment for producing green environment-friendly PET bottle flakes |
CN111732280B (en) * | 2020-06-30 | 2023-04-07 | 浙江通恒环保科技有限公司 | Sewage purification process and equipment for producing green environment-friendly PET bottle flakes |
CN112919596A (en) * | 2021-01-29 | 2021-06-08 | 天津市润达金源水务有限公司 | Device and method for recycling magnetic powder in magnetic flocculation system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209123408U (en) | A kind of water pollution control sedimentation basin | |
CN110963645B (en) | Black smelly water integral type clarification plant in river course | |
CN103239905A (en) | Siphon type valveless filtering pool | |
CN211328488U (en) | Mariculture water purification device that grows seedlings | |
CN209361942U (en) | A kind of anti-clogging eddy flow sieve solid-liquid separator for sewage treatment | |
KR100488613B1 (en) | Simple waterworks filtration device | |
CN208244203U (en) | A kind of self-cleaning accurate filter | |
CN203253216U (en) | Siphonic valveless filtering pool | |
CN106186109B (en) | A kind of grid pond tobacco wastewater suspended substance collects separate tank | |
CN214495975U (en) | Drainage equipment for construction management | |
CN108714323A (en) | A kind of water process quartz filter | |
CN209243828U (en) | Skyscraper water feeding tank | |
CN209530307U (en) | A kind of multi-function domestic sewage-treatment plant | |
CN208726944U (en) | A kind of circulation flushing formula filter plant for water filtration | |
CN208120858U (en) | A kind of purification apparatus applied to sanitary sewage | |
CN218596230U (en) | Landscape water purification treatment device | |
CN216703568U (en) | Rice shrimp field tail water purification treatment system | |
CN210934001U (en) | Unpowered filtering tank | |
CN216156746U (en) | A safe reposition of redundant personnel cuts dirty device for on municipal pipe network | |
CN214456948U (en) | Reverse-flow type overflow biochemical filtering system for fancy carp pond | |
CN219681779U (en) | Novel sewage treatment pond | |
CN221513809U (en) | Sedimentation tank equipped with rolling grid separation device | |
CN215224078U (en) | External fish just separation filter equipment of fish bowl | |
CN211596977U (en) | Intelligent rainwater recycling system | |
CN213085705U (en) | Papermaking sewage purification device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190719 Termination date: 20201026 |
|
CF01 | Termination of patent right due to non-payment of annual fee |