[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN208121804U - A kind of combined steel template for municipal administration synthesis pipe gallery - Google Patents

A kind of combined steel template for municipal administration synthesis pipe gallery Download PDF

Info

Publication number
CN208121804U
CN208121804U CN201820097588.0U CN201820097588U CN208121804U CN 208121804 U CN208121804 U CN 208121804U CN 201820097588 U CN201820097588 U CN 201820097588U CN 208121804 U CN208121804 U CN 208121804U
Authority
CN
China
Prior art keywords
plate unit
pipe gallery
municipal administration
template
synthesis pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820097588.0U
Other languages
Chinese (zh)
Inventor
金淦
张浙舟
任玉友
翁厚涛
杨磊
易若晨
陈巍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 4 Group Co Ltd
Original Assignee
Shanghai Construction No 4 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 4 Group Co Ltd filed Critical Shanghai Construction No 4 Group Co Ltd
Priority to CN201820097588.0U priority Critical patent/CN208121804U/en
Application granted granted Critical
Publication of CN208121804U publication Critical patent/CN208121804U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a kind of combined steel templates for municipal administration synthesis pipe gallery, belong to municipal administration synthesis pipe gallery technical field, solve traditional plank sheathing and expend big, the low problem of construction efficiency for municipal administration synthesis pipe gallery construction material.The steel form includes the punching block plate unit formed along the longitudinal direction of municipal administration synthesis pipe gallery at least two groups arranged side by side by backform plate unit and side form plate unit, side template cell distribution in backform plate unit two sides and pass through horizontal support elements connection;The backform plate unit includes top template and column, and the bottom of column is equipped with walking mechanism, and it is mobile that walking mechanism is able to drive side form plate unit.

Description

A kind of combined steel template for municipal administration synthesis pipe gallery
Technical field
The utility model belongs to municipal administration synthesis pipe gallery technical field, and in particular to a kind of combination for municipal administration synthesis pipe gallery Formula steel form.
Background technique
Currently, China is in the High Speed Construction phase of municipal administration synthesis pipe gallery, compared with conventional line, municipal administration synthesis pipe gallery energy Urban underground space is enough efficiently used, is economized the land resource, zipper road is avoided, reduces pipeline maintenance cost, improves urban environment. The city integrated piping lane construction in China is just rapidly carried out with the construction speed of annual 2000km, and China has been that city of the world is comprehensive Piping lane builds big country.
Plank sheathing is mainly used in municipal administration synthesis pipe gallery engineering construction.Conventional construction is mainly first constructing structure bottom plate, Then one-off construction side wall and top plate.However, formwork and the top plate framed bent of side wall are set up in conventional side wall and top board construction It is mused together, increases the complexity of entire framed bent and template system, construction efficiency is low.Moreover, municipal administration synthesis pipe gallery Underground Construction belongs to construction continuous over long distances, and according to traditional plank sheathing, reusable number is few, work progress The material of middle generation is thrown aside more, and stacking takes up a large area.
Utility model content
The utility model is not aiming at the problem that traditional plank sheathing adapts to municipal administration synthesis pipe gallery underground construction, the utility model A kind of combined steel template for municipal administration synthesis pipe gallery is provided, according to municipal administration synthesis pipe gallery design feature, by single box double room Structure is divided into two-step pouring, pours the side wall of bottom plate and the above 50cm of bottom plate for the first time, pours the high side wall of remainder for the second time And top plate, the selected of steel die and main rib arrangement form is carried out according to construction merogenesis and sidewall structure pattern.By selecting this The combined steel template that utility model provides, not only may be reused, but also improve the architecture quality of municipal administration synthesis pipe gallery.
In order to solve the above technical problems, the utility model provides the following technical solutions:
A kind of combined steel template for municipal administration synthesis pipe gallery, sets side by side including the longitudinal direction along municipal administration synthesis pipe gallery At least two groups punching block plate unit set, the punching block plate unit include backform plate unit and side form plate unit, the side template list Member is distributed in the two sides of the backform plate unit and is connect by horizontal support elements with the backform plate unit;The top template Unit includes top template and column, and the column is tightly supportted in the lower section of the backform plate unit, and the bottom of the column is equipped with row Mechanism is walked, the walking mechanism is able to drive the side form plate unit along the longitudinal direction of municipal administration synthesis pipe gallery under power drive It is mobile.
Further, the walking mechanism is movable pulley, and the walking mechanism is detachable to be installed on close to the side form On the column of plate unit.
Further, the side form plate unit includes the rectangular frame structure of top panel, supporting rod and collet composition.
Further, the top template is the bamboo slab rubber with a thickness of 15mm, and the bamboo slab rubber is layed on longitudinal flitch, institute Longitudinal flitch is stated vertically to be layed in the horizontal support elements.
Further, the crossbeam of the supporting member, stringer and support frame Formation cross-section are the hollow structure of rectangle.
Further, the length of the side form plate unit is 6m.
Compared with prior art, the beneficial technical effect of the utility model is as follows:
(1) the side form plate unit of the utility model is process using the steel plate factory regularization of wall thickness 8mm or more, material Rigidity is big, is unlikely to deform.
(2) the side template element length of the utility model is 6m, can pass through the reserved connection in bottom between side form plate unit Point assembled installation, quick construction, positioning are quasi-, can not only improve the apparent mass of municipal administration synthesis pipe gallery concrete, Er Qieneng It is enough to repeat to have enough to meet the need, the utilization rate of steel form is improved, construction cost is saved.
(3) the column bottom end of the side template of the utility model is equipped with the walking mechanism of detachable connection, facilitates steel form Longitudinal movement, improve construction efficiency.
Detailed description of the invention
Fig. 1 is side form plate unit in the combined steel template for municipal administration synthesis pipe gallery of an embodiment of the present invention Structural schematic diagram;
Fig. 2 is the punching block plate unit of the combined steel template for municipal administration synthesis pipe gallery of an embodiment of the present invention Structural schematic diagram;
Fig. 3 is walked in the application method for the combined steel template for municipal administration synthesis pipe gallery of an embodiment of the present invention Rapid one with reference to figure;
Fig. 4 is walked in the application method for the combined steel template for municipal administration synthesis pipe gallery of an embodiment of the present invention Rapid two with reference to figure
In figure:
11- top template, 12- column, 13- collet, the longitudinal direction 14- flitch, 15- steel pipe stull;21- top panel, 22- support rod Part;30- horizontal support elements;The above 50cm side wall of 40- bottom plate;50- steel pipe lock;60- split bolt.
Specific embodiment
Below in conjunction with the drawings and specific embodiments to the utility model proposes the combined steel for municipal administration synthesis pipe gallery Template is described in further detail.According to following explanation and claims, will be become apparent from feature the advantages of the utility model. It should be noted that attached drawing is all made of very simplified form and using non-accurate ratio, only conveniently, lucidly to assist Illustrate the purpose of the utility model embodiment.For sake of convenience, the upper and lower side of "upper" described below, "lower" and attached drawing To consistent, but this can't be the limitation of technical solutions of the utility model.
Embodiment one
The combined steel template for municipal administration synthesis pipe gallery of the utility model is described in detail below with reference to Fig. 1 to Fig. 4 Composition.
As shown in Figures 1 to 4, present embodiment discloses a kind of combined steel templates for municipal administration synthesis pipe gallery, including At least two groups punching block plate unit (not shown) arranged side by side along the longitudinal direction of municipal administration synthesis pipe gallery, punching block plate unit include top Modular unit (not shown) and side form plate unit (not shown), side template cell distribution in backform plate unit two sides and pass through water Flat supporting member 30 is connect with backform plate unit;Backform plate unit includes top template 11 and column 12, and column 12 is tightly supportted in backform The bottom of the lower section of plate unit, column 12 is equipped with walking mechanism (not shown), and walking mechanism is able to drive side under power drive Modular unit is moved along the longitudinal direction of municipal administration synthesis pipe gallery.
Specifically, according to municipal administration synthesis pipe gallery structure formwork way corresponding with the selection of the spacing of building enclosure, according to Usual manner construction only can be carried out single side formwork now due to operating space if spacing is smaller therebetween, and piping lane knot Structure height of side wall is generally up to 4m, and single side formwork operation difficulty is big, and template system is difficult to fix, and stability is poor, causes side wall mixed The apparent mass for coagulating soil is poor.When spacing between the two is larger, is suitble to inside and outside bilateral formwork, structure side wall form is often adopted It is fixed with Screw arbor with nut at both-ends, in this way, template system is secured, architecture quality is secure, but the repairing of Screw arbor with nut at both-ends and more table Face piece seriously constrains the waterproof performance of structure and the apparent mass of concrete.
For foregoing problems, the utility model pours municipal administration synthesis pipe gallery " day in the form of two-step method step-by-step construction Font " single box double room structure.Bottom plate and bottom plate above section side wall are constructed using set shaped steel formwork for the first time, second will Remaining side wall and top plate are constructed using knockdown steel form, to effectively improve concrete apparent mass, are avoided using to drawing Screw rod enhances waterproof effect, to achieve the purpose that improve construction efficiency and improve construction quality.
Preferably, walking mechanism is movable pulley, the detachable installation of the movable pulley as walking mechanism in order to draw materials conveniently In on the column 12 of side form plate unit.When side form plate unit is mobile, the installation of 12 bottom end of column be can be in power drive The walking mechanism of lower movement, side form plate unit installation and when concreting, the installation of 12 bottom end of column is collet 13, collet 13 can be used as the support of side template, after collet 13 is removed, can be used as the jacking operating space for changing side template cell height. Column 12 is made by the steel pipe that diameter is 48mm.
Particularly, side form plate unit includes top panel 21, supporting rod 22 and collet 13, and top panel 21 is 8mm thick Steel plate is made, main rib, secondary rib and the diagonal brace that supporting rod 22 is made for 8# channel steel, the i.e. crossbeam of supporting rod 22, Stringer and support frame Formation cross-section are the hollow structure of rectangle.
Preferably, steel form reserved location change in size is more in view of municipal administration synthesis pipe gallery chamber structure size is different, top Template 11 is the bamboo slab rubber with a thickness of 15mm, and bamboo slab rubber is layed in longitudinal flitch, and longitudinal flitch is vertically layed in horizontally-supported structure On part 30.Wherein, the bracing reinforcement system of bamboo slab rubber is that the crossbeam of the 10# channel steel production of lower part and spacing 300mm are vertically spread The horizontal support elements 30 that the flitch of 10mm*10mm above crossbeam is formed.Certainly, it can be carried out according to engineering practice The spacing adjustment of reserved spacing and crossbeam, and decide whether to increase support among horizontal support elements 30.That is, choosing The transverse width of inner side template can be adjusted as top template by selecting bamboo slab rubber, can be used for the combined steel template of the present embodiment In the chamber structure of more different inner diameters sizes.
Please continue to refer to Fig. 1 to Fig. 4, the utility model additionally provides the combined steel template for municipal administration synthesis pipe gallery Application method, municipal administration synthesis pipe gallery are " font of falling day " single box double room structure, and the municipal administration synthesis pipe gallery is divided into several construction sections It is continuously constructed, each construction section is constructed in two times, is included the following steps:
Step 1: the set shaped steel formwork of the above 50cm side wall 40 of mounting base, integration pour bottom plate and bottom plate or more 50cm side wall 40;
Step 2: installing several length is 6m, highly for the side form plate unit of 2.65m until complete entire bottom plate 50cm with The installation of upside wall form;The level that setting is formed by vertical transverse support bar and longitudinal flitch on the top of side form plate unit Supporting member 30, laying depth is the bamboo slab rubber of 15mm above horizontal support elements 30;It is arranged below bamboo slab rubber simultaneously vertical Column 12 and collet 13, until completing the installation of top template.
Preferably, the top that step 1 includes set shaped steel formwork is fixed by the steel pipe lock 50 that diameter is 50mm, sizing The lower part of steel form is fixed by steel pipe stull 15, to guarantee normally pouring for the above 50cm side wall of bottom plate.
Particularly, side wall template includes intermediate internal partition wall template and inner side of outer wall template, wherein intermediate internal partition wall template is logical It crosses the split bolt 60 that plastics through diameter is 14mm to reinforce, to realize reuse, the every side of spiro rod length is than corresponding The long 30cm of wall thickness.
In conclusion the combined steel template provided by the embodiment of the utility model for municipal administration synthesis pipe gallery and traditional Plank sheathing, which is compared, has following advantage:
(1) side form plate unit is process using the steel plate factory regularization of wall thickness 8mm or more, and material stiffness is big, is not easy Deformation.
(2) side template element length is 6m, can reserve the installation of tie point assembled between side form plate unit by bottom, Quick construction, positioning are quasi-, can not only improve the apparent mass of municipal administration synthesis pipe gallery concrete, and can repeat to have enough to meet the need, and mention The high utilization rate of steel form, saves construction cost.
(3) the column bottom end of side template is equipped with the walking mechanism of detachable connection, facilitates the longitudinal movement of steel form, mentions High construction efficiency.
Foregoing description is only the description to the utility model preferred embodiment, not to any limit of the scope of the utility model Fixed, any change, the modification that the those of ordinary skill in the utility model field does according to the disclosure above content belong to right and want Seek the protection scope of book.

Claims (6)

1. a kind of combined steel template for municipal administration synthesis pipe gallery, which is characterized in that including the depth along municipal administration synthesis pipe gallery Direction at least two groups punching block plate unit arranged side by side, the punching block plate unit includes backform plate unit and side form plate unit, institute Side template cell distribution is stated to connect in the two sides of the backform plate unit and by horizontal support elements with the backform plate unit; The backform plate unit includes top template and column, and the column is tightly supportted in the lower section of the backform plate unit, the column Bottom is equipped with walking mechanism, and the walking mechanism is able to drive the side form plate unit along municipal administration synthesis pipe gallery under power drive Longitudinal direction it is mobile.
2. being used for the combined steel template of municipal administration synthesis pipe gallery as described in claim 1, which is characterized in that the walking mechanism For movable pulley, the walking mechanism is detachable to be installed on the column of the side form plate unit.
3. being used for the combined steel template of municipal administration synthesis pipe gallery as described in claim 1, which is characterized in that the side template list Member includes the rectangular frame structure of top panel, supporting rod and collet composition.
4. being used for the combined steel template of municipal administration synthesis pipe gallery as described in claim 1, which is characterized in that the top template is With a thickness of the bamboo slab rubber of 15mm, the bamboo slab rubber is layed on longitudinal flitch, and the longitudinal direction flitch is vertically layed in the level On supporting member.
5. being used for the combined steel template of municipal administration synthesis pipe gallery as claimed in claim 3, which is characterized in that the supporting member Crossbeam, stringer and support frame Formation cross-section be rectangle hollow structure.
6. being used for the combined steel template of municipal administration synthesis pipe gallery as described in claim 1, which is characterized in that the side template list The length of member is 6m.
CN201820097588.0U 2018-01-19 2018-01-19 A kind of combined steel template for municipal administration synthesis pipe gallery Active CN208121804U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820097588.0U CN208121804U (en) 2018-01-19 2018-01-19 A kind of combined steel template for municipal administration synthesis pipe gallery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820097588.0U CN208121804U (en) 2018-01-19 2018-01-19 A kind of combined steel template for municipal administration synthesis pipe gallery

Publications (1)

Publication Number Publication Date
CN208121804U true CN208121804U (en) 2018-11-20

Family

ID=64206112

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820097588.0U Active CN208121804U (en) 2018-01-19 2018-01-19 A kind of combined steel template for municipal administration synthesis pipe gallery

Country Status (1)

Country Link
CN (1) CN208121804U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108265749A (en) * 2018-01-19 2018-07-10 上海建工四建集团有限公司 A kind of combined steel template and application method for municipal administration synthesis pipe gallery

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108265749A (en) * 2018-01-19 2018-07-10 上海建工四建集团有限公司 A kind of combined steel template and application method for municipal administration synthesis pipe gallery

Similar Documents

Publication Publication Date Title
CN102561681B (en) Casting molding template and casting molding process for constructional columns of infilled walls
CN108265749A (en) A kind of combined steel template and application method for municipal administration synthesis pipe gallery
CN107327050B (en) Disassembly-free basement exterior wall flanging unilateral formwork supporting device and construction method
CN110158394B (en) Joint-cutting-free construction structure of concrete super-flat terrace
CN110761402A (en) Concrete pouring construction method for hysteresis synchronization construction of same floor of building floor slab
CN206438529U (en) Beam and slab type raft foundation formwork support structure
CN208121804U (en) A kind of combined steel template for municipal administration synthesis pipe gallery
CN112709430A (en) Template device based on BIM
CN107916677A (en) Piping lane construction formwork system and its construction method
CN114575593A (en) Adjustable plate buckling formwork support frame for super-load small-clearance beam and construction method thereof
CN109518938A (en) Steel formwork system without split bolts and using method thereof
CN106968366B (en) Construction method for pouring constructional column without dismantling formwork
CN210289118U (en) Tower concrete structure sharp roof template system
CN203429868U (en) Construction structure of unbonded pre-stressed cast-in-place reinforced concrete hollow slabs
CN217734853U (en) Adjustable plate buckling template support frame for super-load small-clear-distance beam
CN202596161U (en) Combined formwork device of HR heavy type gantry and reinforced concrete temporary structural column
CN105442737A (en) Novel composite heat insulation floor board and construction method thereof
CN115075613B (en) Assembled building supporting system and construction method thereof
CN102691409A (en) HR (height regulation) heavy portal frame and temporary reinforced concrete column jointed formwork erecting device and construction method
CN214530768U (en) Cast-in-place utility tunnel template bearing structure
CN214219929U (en) Unilateral formwork reinforced structure of basement outer wall
CN209443767U (en) Steel template system without split bolts
CN212689559U (en) Concrete pouring template with thin-wall structure
CN207727843U (en) A kind of glomeration assembled architecture collar tie beam
CN203531380U (en) Size-adjustable formwork system with local supports arranged bellow beam and no support arranged below plate

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant