A kind of wet desulphurization chimney simulation test apparatus Download PDF

Info

Publication number
CN207703683U
CN207703683U CN201720975878.6U CN201720975878U CN207703683U CN 207703683 U CN207703683 U CN 207703683U CN 201720975878 U CN201720975878 U CN 201720975878U CN 207703683 U CN207703683 U CN 207703683U
Authority
CN
China
Prior art keywords
gas
chimney
test apparatus
wet desulphurization
simulation test
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720975878.6U
Other languages
Chinese (zh)
Inventor
张林俊
蔡婷玉
冀运东
黄敏
彭领新
梁天生
任念毛
张�林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Sinogy Electric Engineering Co Ltd
Original Assignee
China Sinogy Electric Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Sinogy Electric Engineering Co Ltd filed Critical China Sinogy Electric Engineering Co Ltd
Priority to CN201720975878.6U priority Critical patent/CN207703683U/en
Application granted granted Critical
Publication of CN207703683U publication Critical patent/CN207703683U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Treating Waste Gases (AREA)

Abstract

The utility model belongs to thermal power generation flue gas harmless treatment research field, is related to a kind of wet desulphurization chimney simulation test apparatus.Including fume extractor, airflow apparatus, spray equipment, waste gas collection device, condensation liquor collecting device and central control system;The fume extractor includes the horizontal flue and vertical gas pass of inside lining anti-corrosive material, and the vertical gas pass is vertically installed in the end of horizontal flue, for simulating practical chimney;The airflow apparatus is set to the initiating terminal of horizontal flue, including pneumatic box, and the pneumatic box is mixed to form simulation air-flow with air and is conveyed to fume extractor for generating sulfur oxide gas;The wet desulphurization chimney simulation test apparatus of the utility model, it is simple in structure, smoke transportation of the coal-fired flue-gas in power plant after wet desulphurization can be simulated, emulation investigation corrosion for chimney lining anti-corrosion material, it also is used as research on environmental issues caused by coal-fired flue-gas, including gas pollution, water pollution, heavy metal pollution etc. simultaneously.

Description

A kind of wet desulphurization chimney simulation test apparatus
Technical field
The utility model belongs to thermal power generation flue gas harmless treatment research field, is related to a kind of wet desulphurization chimney emulation Experimental rig.
Background technology
The wet desulfurizing process of power-plant flue gas changed dramatically humiture and ambient condition in chimney.By FGD wet methods After desulfurization, about 90%~99% SO2 is removed from flue gas in flue gas, but due to being introduced in the flue gas after desulfurization A large amount of moisture, and flue-gas temperature is down to 50 DEG C or so.Inner wall of stack under this operating mode generates condensed water, therefore claims For " Wet chimney ".There are washing to corrode two technical barriers with chimney emission cylinder liner under misty rain, the former protects Wet chimney from environment Shield limitation, the latter is from the requirement of chimney stack safety and durability.Both of these problems solution is bad, may be raw in environmental assessment or safety Thermal power plant's project, which can not check and accept, in terms of production puts into operation.So all carrying out in-depth study and practice to both of these problems both at home and abroad.
All it is needle generally for the investigation corrosion of chimney lining anti-corrosion material due to experimental condition is limited etc. Smaller test block is carried out, the actual conditions of material large-area applications in the more difficult true engineering of reflection of test result;And And experiment is carried out using certain single corrosive medium mostly, is not consistent with the etching condition of Practical Project.
In view of the small test block test of above-mentioned material has limitation, the problems such as chimney lining material antiseptic and chimney rain Research, researcher must not less than in each operation or maintenance in chimney go the work that conducts a research on the spot.This method expense It is high, inconvenient, dangerous;In addition the chimney service condition of different engineerings is different, so the data being collected into are difficult to be compared It analyzes, therefore the theoretical research value based on these data is low, persuades force difference.
Utility model content
For the above deficiency, the wet desulphurization chimney simulation test apparatus of the utility model can simulate the combustion in power plant Smoke transportation (flow velocity, pressure etc.) of the flue-gas after wet desulphurization, the emulation corrosion examination for chimney lining anti-corrosion material Research is tested, while also being used as research on environmental issues caused by coal-fired flue-gas, including gas pollution, water pollution, heavy metal pollution etc..
The technical solution of the utility model is:
A kind of wet desulphurization chimney simulation test apparatus, including fume extractor, airflow apparatus, spray equipment, gas sampling Device, condensation liquor collecting device and central control system;The fume extractor includes the horizontal flue of inside lining anti-corrosive material and vertical cigarette Road, the vertical gas pass are vertically installed in the end of horizontal flue, for simulating practical chimney;The airflow apparatus is set to water The initiating terminal of flat flue, including pneumatic box, the pneumatic box are mixed to form mould for generating sulfur oxide gas with air Quasi- air-flow is conveyed to fume extractor;The spray equipment is set to the top of the close initiating terminal of horizontal flue, including tank body and Spray tube, the tank body are used to desulfurizing agent making simulation air-flow to simulation air-flow sprinkling for storing desulfurizing agent, the spray tube Desulfurization;The waste gas collection device is set to the upper end of the vertical gas pass, including exhaust gas collector, for collecting simulation air-flow The exhaust gas of generation after desulfurization;The condensation liquor collecting device is set to the lower end of the vertical gas pass, including pipeline is connected Catch tray and collecting tank, the condensate liquid for collecting the generation after simulating airflow desulphurization;The monitoring system includes monitoring device And controller, the monitoring device be it is multiple, be respectively arranged on the inner wall of horizontal flue and vertical gas pass, and with controller phase Even, the parameters for monitoring set position, and monitored results are transferred to the controller, the controller is for connecing Receive simultaneously display monitoring data.
The airflow apparatus further includes wind turbine, and the wind turbine is for promoting the simulation air-flow in horizontal flue and vertical cigarette It is flowed in road.
The monitoring device includes flowmeter, thermometer, pressure gauge, and the controller is PLC controller.
The controller is also connected with airflow apparatus and spray equipment, and pneumatic box is automatically adjusted according to the monitored results The spray rate for simulating air-flow conveying speed, the running speed of wind turbine and spray tube, by gas flow rate, temperature, pressure in flue Control is within the scope of certain parameter.
The parameter area is gas flow rate 15m/s-30m/s, and temperature is 40-50 DEG C, pressure 200kPa- 1000kPa。
Pneumatic box gas processed by the way of sulfur burning, gas obtained are SO2 and SO3.
The vertical gas pass height and actual stack height ratio are 1: 40, the vertical gas pass and horizontal flue diameter and reality Border Diameter of chimney ratio is 1: 3.
The vertical gas pass height is 5 meters, a diameter of 2 meters of vertical gas pass and horizontal flue.
The vertical gas pass top is provided with vibration fan.
The exhaust gas collector is connected with pneumatic box, and the exhaust gas of collection is reused for forming simulation gas back to pneumatic box Stream.
The technical solution of the utility model has the following advantages:
1. excellent corrosion research platform:After coal-fired flue-gas humidifying, acid condensate liquid is formed, the corruption for cylinder material of discharging fume Erosion is very serious.After China has occurred and that a lot of smoke exhaust barrels are corroded, strength deterioration leads to the accident collapsed.For smoke exhaust barrel Anti-corrosion methods, China also form upsurge, and various technical methods emerge in large numbers one after another, but most of actual effect one As.With high costs, or effect is bad or even cost high effect is also bad.Main problem be most researchers and Chemical Problem in the excessive attention corrosion of the producer, and ignore the physical problem in corrosion.The complex working condition of chimney is to lead Cause the immediate cause of most of anti-corrosion measure failures.And this simulator can provide relatively straightforward anti-corrosion certificate authenticity, It is an excellent corrosion research platform.It can carry out all kinds of Wet chimney correlation corrosion protection system experimental studies.
2. multipurpose:The simulator is mainly used for the emulation investigation corrosion of chimney lining anti-corrosion material, simultaneously It also is used as research on environmental issues caused by coal-fired flue-gas, including gas pollution, water pollution, heavy metal pollution etc..
3. feasibility, convenience, economy:The simulator passes through micro, not only has simulation quality, but also be easily placed, So that l-G simulation test more safely, conveniently, has been greatly reduced testing expenses.
4. device flexibility:It simulates air-flow in the simulator to require to allocate according to different tests, chimney internal cylinder is anti- Rotten liner scheme is replaced also according to test requirements document, therefore can meet very more test requirements documents, has flexibility.
Description of the drawings
Fig. 1 is the schematic diagram of the utility model wet desulphurization chimney simulation test apparatus.
Specific implementation mode
The technique effect of the design of the utility model, concrete structure and generation is made furtherly below with reference to attached drawing It is bright, to be fully understood from the purpose of this utility model, feature and effect.
Fig. 1 is the embodiments of the present invention.
With reference to figure 1, the wet desulphurization chimney simulation test apparatus of the utility model, including fume extractor, airflow apparatus, spray Shower device, waste gas collection device, condensation liquor collecting device and central control system.
The fume extractor includes the horizontal flue 21 and vertical gas pass 22 of inside lining anti-corrosive material, and the vertical gas pass 22 hangs down The straight end for being set to horizontal flue 21, for simulating practical chimney;22 height of vertical gas pass is 1 with actual stack height ratio: 40, the vertical gas pass 22 and 21 diameter of horizontal flue and practical Diameter of chimney ratio are 1: 3.For example, common chimney actual height It it is 200 meters, a diameter of 6 meters, then 22 height of vertical gas pass is 5 meters, a diameter of 2 meters of vertical gas pass 22 and horizontal flue 21.It hangs down Straight 22 top of flue is provided with vibration fan 23, and vibration fan 23 generates vibration, simulates horizontal when practical chimney wind-engaging or earthquake The operating mode of oscillating or vibrating, to generate the operating mode of more proper head.
The airflow apparatus is set to the initiating terminal of horizontal flue 21, including pneumatic box 11 and wind turbine 12, the pneumatic box 11 for generating sulfur oxide gas, and is mixed to form simulation air-flow with air and is conveyed to fume extractor, and pneumatic box 11 uses The mode gas of sulfur burning, gas obtained are SO2 and SO3, and the wind turbine 12 is for promoting the simulation air-flow in level Flowing in flue 21 and vertical gas pass 22.Simulated flue gas is the sulfur contained high temoperature flue gas simulated thermal power plant and generated.
The spray equipment is set to the top of the close initiating terminal of horizontal flue 21, including tank body 31 and spray tube 32, The tank body 31 is used to keep simulation air-flow de- to simulation air-flow sprinkling desulfurizing agent for storing desulfurizing agent, the spray tube 32 Sulphur;Desulfurizing agent can use with thermal power plant same preparation, preferably to imitate the situation of flue gas after desulfurization, generally lime The slurries of stone or lime, after desulfurization, about 90%~95% SO in high-temperature flue gas2It is removed from flue gas, temperature drop To 50 ± 5 DEG C or so
The waste gas collection device is set to the upper end of the vertical gas pass 22, including exhaust gas collector 41, for collecting Simulate the exhaust gas of the generation after airflow desulphurization;Due to still containing the SO not removed in time in exhaust gas2Gas, in order to avoid discharge To causing environmental pollution, the exhaust gas collector 41 to be connected with pneumatic box 11 in air, the exhaust gas of collection is returned into pneumatic box 11 are reused for forming simulation air-flow.
The condensation liquor collecting device is set to the lower end of the vertical gas pass 22, including 51 He of catch tray that pipeline is connected Collecting tank 52, the condensate liquid for collecting the generation after simulating airflow desulphurization, and measure condensate liquid gathering speed and efficiency.
The monitoring system includes monitoring device 61 and controller 62, the monitoring device 61 be it is multiple, including flowmeter, Thermometer, pressure gauge are respectively arranged on the inner wall of horizontal flue 21 and vertical gas pass 22, and are connected with controller 62, are used for The parameters at the set position of monitoring, and monitored results are transferred to the controller 62, the controller 62 controls for PLC Device, for receiving simultaneously display monitoring data.
This monitoring system may be designed in Automatic monitoring systems, i.e., controller 62 also with airflow apparatus and spray equipment It is connected, simulation air-flow conveying speed, the running speed of wind turbine 12 and the spray of pneumatic box 11 is automatically adjusted according to the monitored results The spray rate of shower pipe 32, by gas flow rate, temperature, pressure control in flue within the scope of certain parameter.The parameter area For gas flow rate 15m/s-30m/s, temperature is 40-50 DEG C, pressure 200kPa-1000kPa.
When the utility model wet desulphurization chimney simulation test apparatus operation after a period of time, can measure in flue The anti-corrosion material thickness of lining, the degree and speed corroded with knowing desulfurization fume to it.The anti-corrosion material of flue lining can root It is arranged according to demand or regularly replaces, compares the rate and degree that various anti-corrosion materials are corroded.
Disclosed above is only the embodiments of the present invention, and still, the utility model is not limited to this, any ability What the technical staff in domain can think variation should all fall into the scope of protection of the utility model.

Claims (10)

1. a kind of wet desulphurization chimney simulation test apparatus, which is characterized in that including fume extractor, airflow apparatus, spray equipment, Waste gas collection device, condensation liquor collecting device and central control system;The fume extractor includes the horizontal flue of inside lining anti-corrosive material (21) and vertical gas pass (22), the vertical gas pass (22) is vertically installed in the end of horizontal flue (21), for simulating reality Chimney;The airflow apparatus is set to the initiating terminal of horizontal flue (21), including pneumatic box (11), and the pneumatic box (11) is used for Sulfur oxide gas is generated, and is mixed to form simulation air-flow with air and is conveyed to fume extractor;The spray equipment is set to The top of the close initiating terminal of horizontal flue (21), including tank body (31) and spray tube (32), the tank body (31) is for storing Desulfurizing agent, the spray tube (32) are used to desulfurizing agent making simulation airflow desulphurization to simulation air-flow sprinkling;The gas sampling dress The upper end for being placed in the vertical gas pass (22), including exhaust gas collector (41) are installed, for collecting the production after simulating airflow desulphurization Raw exhaust gas;The condensation liquor collecting device is set to the lower end of the vertical gas pass (22), including the catch tray that pipeline is connected (51) and collecting tank (52), the condensate liquid for collecting the generation after simulating airflow desulphurization;Monitoring system includes monitoring device (61) and controller (62), the monitoring device (61) are multiple, are respectively arranged at horizontal flue (21) and vertical gas pass (22) Inner wall on, and be connected with controller (62), parameters for monitoring set position, and monitored results are transferred to institute Controller (62) is stated, the controller (62) is for receiving simultaneously display monitoring data.
2. wet desulphurization chimney simulation test apparatus as described in claim 1, which is characterized in that the airflow apparatus further includes Wind turbine (12), the wind turbine (12) is for promoting simulation air-flow flowing in horizontal flue (21) and vertical gas pass (22).
3. wet desulphurization chimney simulation test apparatus as described in claim 1, which is characterized in that monitoring device (61) packet Flowmeter, thermometer, pressure gauge are included, the controller (62) is PLC controller.
4. wet desulphurization chimney simulation test apparatus as described in claim 1, which is characterized in that the controller (62) also with Airflow apparatus is connected with spray equipment, according to the monitored results automatically adjust pneumatic box (11) simulation air-flow conveying speed, The spray rate of the running speed and spray tube (32) of wind turbine (12), by gas flow rate, temperature, pressure control in flue certain In parameter area.
5. wet desulphurization chimney simulation test apparatus as claimed in claim 4, which is characterized in that the parameter area is gas Body flow velocity is 15m/s-30m/s, and temperature is 40-50 DEG C, pressure 200kPa-1000kPa.
6. wet desulphurization chimney simulation test apparatus as described in claim 1, which is characterized in that the pneumatic box (11) uses The mode gas of sulfur burning, gas obtained are SO2And SO3
7. wet desulphurization chimney simulation test apparatus as described in claim 1, which is characterized in that the vertical gas pass (22) is high Degree is 1: 40 with actual stack height ratio, and the vertical gas pass (22) and horizontal flue (21) diameter are with practical Diameter of chimney ratio 1∶3。
8. wet desulphurization chimney simulation test apparatus as described in claim 1, which is characterized in that the vertical gas pass (22) is high Degree is 5 meters, a diameter of 2 meters of vertical gas pass (22) and horizontal flue (21).
9. wet desulphurization chimney simulation test apparatus as described in claim 1, which is characterized in that vertical gas pass (22) top End is provided with vibration fan (23).
10. wet desulphurization chimney simulation test apparatus as described in claim 1, which is characterized in that the exhaust gas collector (41) it is connected with pneumatic box (11), the exhaust gas of collection is reused for forming simulation air-flow back to pneumatic box (11).
CN201720975878.6U 2017-08-07 2017-08-07 A kind of wet desulphurization chimney simulation test apparatus Expired - Fee Related CN207703683U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720975878.6U CN207703683U (en) 2017-08-07 2017-08-07 A kind of wet desulphurization chimney simulation test apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720975878.6U CN207703683U (en) 2017-08-07 2017-08-07 A kind of wet desulphurization chimney simulation test apparatus

Publications (1)

Publication Number Publication Date
CN207703683U true CN207703683U (en) 2018-08-07

Family

ID=63020120

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720975878.6U Expired - Fee Related CN207703683U (en) 2017-08-07 2017-08-07 A kind of wet desulphurization chimney simulation test apparatus

Country Status (1)

Country Link
CN (1) CN207703683U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107290273A (en) * 2017-08-07 2017-10-24 中机国能电力工程有限公司 A kind of wet desulphurization chimney simulation test apparatus
CN109324157A (en) * 2018-11-15 2019-02-12 华电电力科学研究院有限公司 Priming apparatus is used in a kind of simulated flue gas preparation method and simulated flue gas test
CN113295601A (en) * 2021-05-13 2021-08-24 上海长肯试验设备有限公司 Corrosion testing machine for chimney pipeline
CN114486944A (en) * 2021-12-14 2022-05-13 中国原子能科学研究院 Modular chimney gaseous effluent mixing uniformity research device

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107290273A (en) * 2017-08-07 2017-10-24 中机国能电力工程有限公司 A kind of wet desulphurization chimney simulation test apparatus
CN107290273B (en) * 2017-08-07 2023-11-17 中机国能电力工程有限公司 Wet flue gas desulfurization chimney simulation test device
CN109324157A (en) * 2018-11-15 2019-02-12 华电电力科学研究院有限公司 Priming apparatus is used in a kind of simulated flue gas preparation method and simulated flue gas test
CN109324157B (en) * 2018-11-15 2023-08-18 华电电力科学研究院有限公司 Simulated smoke preparation method and water adding device for simulated smoke test
CN113295601A (en) * 2021-05-13 2021-08-24 上海长肯试验设备有限公司 Corrosion testing machine for chimney pipeline
CN114486944A (en) * 2021-12-14 2022-05-13 中国原子能科学研究院 Modular chimney gaseous effluent mixing uniformity research device
CN114486944B (en) * 2021-12-14 2023-11-10 中国原子能科学研究院 Modularized chimney gaseous effluent mixing uniformity research device

Similar Documents

Publication Publication Date Title
CN207703683U (en) A kind of wet desulphurization chimney simulation test apparatus
CN106000007B (en) A kind of simulation system and analogy method in wet desulphurization flow field
CN110102139B (en) Method for removing white in boiler flue gas through multi-stage heat exchange
CN203231960U (en) Reinforced concrete and coating corrosion monitoring device in smoke-tower syncretic technology
CN106092796A (en) It is applicable to polishing machine test equipment and the method for testing of SCR denitration
CN105536490B (en) The automatic desulphurization system of one kind sintering flue gas and its method
CN204758358U (en) Directly extract flue gas sampling device of formula CEMS system
CN112540158B (en) Method for testing utilization rate of limestone wet desulphurization forced oxidation air
CN204789275U (en) Test sprays experimental system to sulfur dioxide corrosive effects influence
CN111564184A (en) Limestone-gypsum wet desulphurization SO of coal-fired power plant3Collaborative removal efficiency prediction method
CN108014610A (en) Ammonia desulfurizing process and its desulfurizer
CN204502786U (en) A kind of novel ultra-clean desulfurizer
CN208091786U (en) A kind of fume extraction system applied to the escaping of ammonia detection
CN203941088U (en) Filtrate corrosion simulated experiment device
CN107290273A (en) A kind of wet desulphurization chimney simulation test apparatus
CN208287715U (en) A kind of helical blade type even gas distribution device
CN108303280A (en) A kind of wet method fume desulfurizing system demister performance test experimental system and experimental method
CN204758459U (en) Experimental device for simulation wet flue gas desulfurization chimney inner wall flue gas dew point corrode
CN202725011U (en) Desulfurization chimney anti-corrosion simulation test device
CN209085677U (en) Chimney gypsum rain real-time monitoring system of the thermal power plant based on water balance
CN203772611U (en) Mixer for measuring flue gas ingredients of power station boiler
CN108079777A (en) A kind of coal-fired plant flue gas low-temperature denitration method and its device
CN208694683U (en) Semidry method removes the pilot-plant of fluorine chlorine in coal-fired flue-gas
CN203458971U (en) Novel desulfurization tower
CN208076173U (en) A kind of wet method fume desulfurizing system demister performance test experimental system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180807

Termination date: 20210807

CF01 Termination of patent right due to non-payment of annual fee