CN206987838U CN201720961829.7U CN201720961829U CN206987838U CN 206987838 U CN206987838 U CN 206987838U CN 201720961829 U CN201720961829 U CN 201720961829U CN 206987838 U CN206987838 U CN 206987838U
Authority
CN
China
Prior art keywords
ripple
slab element
supporting
board component
connecting plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720961829.7U
Other languages
Chinese (zh)
Inventor
马伟斌
张千里
付兵先
郭小雄
邹文浩
李尧
安哲立
王志伟
杜晓燕
牛亚彬
马超锋
赵鹏
张文达
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Academy of Railway Sciences Corp Ltd CARS
Railway Engineering Research Institute of CARS
China State Railway Group Co Ltd
Original Assignee
China Academy of Railway Sciences Corp Ltd CARS
Railway Engineering Research Institute of CARS
China Railway Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Academy of Railway Sciences Corp Ltd CARS, Railway Engineering Research Institute of CARS, China Railway Corp filed Critical China Academy of Railway Sciences Corp Ltd CARS
Priority to CN201720961829.7U priority Critical patent/CN206987838U/en
Application granted granted Critical
Publication of CN206987838U publication Critical patent/CN206987838U/en
Priority to PCT/CN2018/091088 priority patent/WO2019024613A1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F5/00Draining the sub-base, i.e. subgrade or ground-work, e.g. embankment of roads or of the ballastway of railways or draining-off road surface or ballastway drainage by trenches, culverts, or conduits or other specially adapted means
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model proposes a kind of ripple board component of the supporting for tunnel, and it is transversely connected with each other with longitudinal direction by several ripple Slab elements and formed.

Description

Supporting ripple board component
Technical field
It the utility model is related to constructing tunnel field, and in particular to a kind of supporting ripple board component.
Background technology
With the quickening of transport development speed, tunnel Culvert engineering is also developed rapidly.Though for railway tunnel, Vcehicular tunnel or related culvert, its security requirement are high.Therefore, the supporting construction of tunnel or culvert must is fulfilled for safety Reliable and durability requirement.
In the prior art, supporting is usually carried out to tunnel or culvert using concrete composite lining method.As a rule, Its preliminary bracing mainly undertakes the whole load of construction stage and the primary load of operation stage.Secondary supporting is mainly as safety Deposit, undertake load or creep of soft rock, changes in environmental conditions that preliminary bracing may deteriorate and act on secondary lining etc. and draw The additional load risen.
However, concrete support often has the problems such as construction complexity, long construction period.Meanwhile for extremely frigid zones, mix Coagulate native supporting and often there are problem of frost heave, cause concrete to drop, so as to bring safety issue.
Utility model content
For some or all of of the above-mentioned technical problem in the presence of prior art, according to of the present utility model first Aspect, there is provided a kind of supporting for tunnel ripple board component, its by several ripple Slab elements transversely with longitudinal side It is connected to each other and forms.
In one embodiment, two adjacent ripple Slab element lapping one another and phase by corrugated plating cell edges Even, overlapping regions at least accounts for the half crest of the ripple Slab element.
In one embodiment, the first connecting plate is provided with the longitudinal edge of each ripple Slab element, for making each ripple Card unit is connected with each other along longitudinal direction.Wherein, first connecting plate is along extending laterally, and with than the corrugated plating list The bigger height of member.
In one embodiment, two ripple Slab element lapping one another and phase by transverse edge adjacent in transverse direction Even, overlapping regions at least accounts for the half crest of the ripple Slab element.
In one embodiment, the second connecting plate is provided with the transverse edge of each ripple Slab element, for making each ripple Card unit is connected with each other along longitudinal direction.
In one embodiment, second connecting plate is along Longitudinal extending, and in central region and ripple Slab element Transverse end edges connection, wherein, the height of second connecting plate is set greater than the height of the ripple Slab element.
In one embodiment, between the first connecting plate of two neighboring ripple Slab element and/or between the second connecting plate It is provided with the waterproof layer of collision mat or water-swellable.
In one embodiment, it is characterised in that the join domain between two neighboring ripple Slab element offsets one from another.
In one embodiment, the supporting is tight by bolt with the ripple Slab element of the lateral end in ripple board component Firmware is fixed in the pit of tunnel both sides, and the bolt fastener includes the L-shaped angle bar being connected with ripple Slab element, and buries Enter the L-shaped foundation bolt into pit.
According to another aspect of the present utility model, there is provided a kind of tunnel supporting method, including step:Coagulation in tunnel Apply waterproof layer on the inner surface of native lining cutting layer;And apply supporting ripple as described above on the inner surface of the waterproof layer Card component.
In one embodiment, on surface of the supporting with the remote tunnel of ripple board component spraying insulating or Cystosepiment is installed.
In one embodiment, the grout injection directly on a surface in the supporting with the remote tunnel of ripple board component Or concrete.
In one embodiment, the grout injection directly on a surface in the supporting with the remote tunnel of ripple board component Or concrete, and spraying insulating or installation foam on surface of the supporting with the close tunnel of ripple board component Plate.
In one embodiment, in the supporting with being implanted with reinforcing bar on the surface in the close tunnel of ripple board component and hang Bar-mat reinforcement, afterwards fill-before-fire heat-insulation layer.
Brief description of the drawings
Preferred embodiment of the present utility model is described in detail below in conjunction with accompanying drawing, in figure:
Fig. 1 shows the schematic diagram of the application in tunnel according to supporting ripple board component of the present utility model;
Fig. 2 shows that the section being applied to according to supporting of the present utility model with ripple board component on concrete lining course shows It is intended to;
Fig. 3 shows the connection expansion along several adjacent ripple Slab elements on tunnel longitudinal direction and horizontal direction Schematic diagram;
Fig. 4 shows the overlap joint state between two neighboring ripple Slab element;
Fig. 5 shows a ripple Slab element according to one embodiment of the present utility model;
Fig. 6 shows a ripple Slab element according to another embodiment of the present utility model;
Fig. 7 shows the state that multiple ripple Slab elements transversely connect;
Fig. 8 shows multiple ripple Slab elements along longitudinally connected state;
Fig. 9 shows the installment state according to supporting ripple board component of the present utility model in the form of enlarged drawing;
Figure 10 is shown in the form of enlarged drawing to be installed according to the another kind of supporting ripple board component of the present utility model State;
Figure 11 shows another peace according to supporting ripple board component of the present utility model in the form of enlarged drawing Dress state;
Figure 12 shows the foundation bolt for being arranged on ripple board component in pit;
In the accompanying drawings, identical part uses identical reference, and accompanying drawing is not drawn according to the ratio of reality.
Embodiment
The utility model is described further below in conjunction with accompanying drawing.It should be noted that although the following examples By installing supporting of the present utility model in tunnel with being introduced exemplified by ripple board component, but those skilled in the art It is appreciated that culvert or other similar engineer applieds can also be applied to ripple board component according to supporting of the present utility model In, this also belongs to the scope of protection of the utility model.
Fig. 1 shows the schematic diagram applied in tunnel according to supporting ripple board component of the present utility model.Such as Fig. 1 institutes Show, supporting ripple board component 100 is provided with the inwall in tunnel 1.Supporting is with ripple board component 100 generally by multiple ripples Transverse direction (direction X in Fig. 1, or perhaps the width in tunnel, alternatively referred to as ring) and tunnel of the Slab element along tunnel Longitudinal direction (the direction Y in Fig. 1, or perhaps the length direction in tunnel) is spliced, and this will also be seen in greater detail below.Supporting The shape substantially matching with the inwall in tunnel 1 is integrally formed as with ripple board component 100, its both ends passes through foundation bolt respectively Fastener (being discussed in detail hereinafter in conjunction with Fig. 6) is installed to the foundation ditch of tunnel both sides or basis of new work for this It is interior.
According to the utility model, supporting ripple board component 100 is arranged on the inwall in tunnel 1.In general, tunnel 1 Inwall on be usually provided with concrete lining course 10.When installing supporting with ripple board component 100, first in concrete lining Waterproof layer 20 is arranged on layer 10.The waterproof layer 20 for example can be layer of polyurethane, and preferably have the thickness in the range of 2-10mm. In addition, the waterproof layer 20 is for example alternatively cement mortar, special-type grouting material or concrete.And then arranged on waterproof layer 20 Supporting ripple board component 100.
In view of frost failure often occurs in extremely frigid zones, therefore this case is directed to, according to of the present utility model one Individual preferred embodiment, one layer of heat preservation can be set up again on the surface of waterproof layer 20 with ripple board component 100 in supporting Layer (not shown), it is preferably 5-15cm thickness.Heat-insulation layer can for example be made up of polyurethane, cystosepiment or other insulation materials. In another unshowned embodiment, insulation material can also be doped with waterproof layer 20 so that waterproof layer 20 is simultaneously Have heat insulation function concurrently.In this manner it is possible to dispense single heat-insulation layer.
Tunnel is usual long (i.e. Y-direction in Fig. 1), and in short transverse (i.e. Z-direction in Fig. 1) and width side It is also very big to the size in (i.e. X-direction in Fig. 1).Therefore, for convenience, supporting is typically logical with ripple board component 100 Several ripple Slab elements 110 are crossed to be spliced.Only as an example, Fig. 3 shows that six ripple Slab elements 110 are stitched together Situation.That is, width (i.e. X-direction in Fig. 1) of three ripple Slab elements 110 along tunnel links together, Form one group of ripple Slab element.The width in this group of ripple Slab element span transporting road, two ends are respectively installed to tunnel In the foundation ditch of both sides.That is, one group of ripple Slab element has substantially coated the cross section profile in tunnel.Meanwhile two groups of corrugated platings Length direction (i.e. Y-direction in Fig. 1) of the unit along tunnel is linked together, and the other end is extended to from the one end in tunnel.So, It is formed covering the supporting ripple board component 100 of whole tunnel inner wall.Certainly, in practice should be according to actual conditions To determine specifically to need how many ripple Slab elements 110 to be stitched together.
In a preferred embodiment, the bonding pad of the two neighboring ripple Slab element 110 in one group of ripple Slab element Domain 115a and the two neighboring ripple Slab element 110 in another group of ripple Slab element join domain 115b stagger.For example, on edge On length direction Y, the join domain 115a of the two neighboring ripple Slab element 110 in each group of card unit is both with respect to upper one The join domain 115a of two neighboring ripple Slab element 110 in group card unit staggers towards side, i.e., deviation left side or Deviation right side.Situation about deviateing to the right is shown in Fig. 3.Alternatively, along its length on Y, each group of card The join domain 115a of two neighboring ripple Slab element 110 in unit is respectively relative to adjacent two in one group of card unit The join domain 115a of individual ripple Slab element 110 each staggers towards both sides, i.e., the join domain 115a in left-half is inclined To the left, the deviation of the join domain 115 in right half part right side.Thus, the force-bearing situation of supporting ripple board component 100 Optimized, improve it and hold bearing capacity, so as to more effectively play support action.
In order to ensure the fastness of connection, it is attached between adjacent ripple Slab element 110 using overlap joint.Such as Fig. 4 It is shown, it is preferable that the crest of half ripple Slab element is at least overlapped between adjacent ripple Slab element 110.Adjacent Overlapping regions between ripple Slab element 110 is fixed by bolt 117.In order to prevent leak, according to a preferable implementation Example, the overlapping regions between adjacent ripple Slab element 110 are provided with collision mat 118.The collision mat 118 is, for example, rubber Part, and be arranged between two ripple Slab elements by bolt 117 by compression.The collision mat 118 also can be by water-swellable Waterproof material be made.
Fig. 5 shows the construction according to another ripple Slab element of the present utility model.As shown in figure 5, corrugated plating list Member 210 has and the same shape of ripple Slab element 110.Unlike, in two lateral ends of ripple Slab element 210 It is provided with the second connecting plate 211.Herein, the lateral ends of ripple Slab element refer to its direction to be risen and fallen along ripple On end, i.e. X-direction in Fig. 1.Second connecting plate 211 is configured to flange form flat board, but can carry certain elasticity with It is easy to the connection of adjacent corrugations Slab element.The transverse edge of ripple Slab element 210 is connected to the middle region of the second connecting plate 211 Domain.That is, for the transverse edge of ripple Slab element 210, the part of the second connecting plate 211 is in its top and another It is partially in below.In addition, the highly preferred height for being set greater than ripple Slab element of the second connecting plate 211.Pass through this Kind is set, and can optimize stress of the ripple Slab element 210 in junction, improves bonding strength and bearing capacity.In the second connection Some connecting holes are equipped with plate 211, their Longitudinal extendings preferably along ripple Slab element 210.Herein, corrugated plating The longitudinal end of unit refers to it along the end on the direction that ripple rises and falls.So, when two adjacent ripples When Slab element 210 is abutted together by its second connecting plate 211, fastening means known to screw bolt and nut etc. can be used to pass through Two adjacent ripple Slab elements 210 are fixed together by connecting hole.Several ripple Slab elements 210 are each other end to end It is connected by connecting plate, so as to constitute complete one group of ripple Slab element (such as triplets in Fig. 3).Fig. 7 is shown The ripple Slab element being transversely connected with each other using the second connecting plate.
In a preferred embodiment, the second connecting plate 211 is configured to the center profile relative to ripple Slab element 210 Line has a certain degree.Preferably, the angle that the second connecting plate 211 is formed relative to the central border line of ripple Slab element 210 Position in its present tunnel cross section profile is spent to select, in order to realize between adjacent corrugations Slab element 210 Good connection.
Fig. 6 shows the construction according to another ripple Slab element of the present utility model.As shown in fig. 6, corrugated plating list Member 310 has and the same shape of ripple Slab element 210.Unlike, ripple Slab element 310 is except in two transverse direction End is provided with outside the second connecting plate 311, and the first connecting plate 321 is also provided with two longitudinal end.
Similarly, the first connecting plate 321 is also configured as flange form flat board, but can carry certain elasticity in order to adjacent The connection of ripple Slab element.The height for being highly preferable selected larger than ripple Slab element 310 of first connecting plate 321 so that Card unit 310 is on the whole within the first connecting plate 321.Connecting hole is equipped with the first connecting plate 321.So, when Two corresponding ripple Slab elements 310 in two groups of longitudinally adjacent ripple Slab elements are abutted against by the first connecting plate 321 When together, fastening means known to screw bolt and nut etc. can be used to pass through connecting hole by the two adjacent ripple Slab elements 310 are fixed together.Front and rear phase ground connection is connected several ripple Slab elements 310 by the first connecting plate each other, so as to constitute Extended a train wave card unit of whole length of tunnel.Fig. 8 shows the ripple being longitudinally connected with each other using the first connecting plate edge Card unit.
According to the utility model, the first connecting plate and the second connecting plate can be with separately made, then for example, by welding And fixed on ripple Slab element.First connecting plate and the second connecting plate can also be for example by compactings and whole with ripple Slab element Body formula is formed.
In the embodiment shown in Fig. 5 and Fig. 6, the splicing of ripple Slab element is instead of indeed through connecting plate.This Sample, the part at the splicing regions between ripple Slab element can be avoided overlapping, while still ensure enough intensity.
It is readily appreciated that, can be in the first connection of two neighboring ripple Slab element in the embodiment shown in Fig. 5 and Fig. 6 Collision mat as shown in Figure 4 is set between plate and/or between the second connecting plate, thus further strengthens leak preventing effect.
In a unshowned particularly preferred embodiment, ripple Slab element is provided only with the first connecting plate on longitudinal direction, And and the second connecting plate for being not provided with transverse direction.In this case, one group of ripple Slab element in transverse direction or on ring utilizes Overlap joint means as shown in Figure 4 are connected to each other, and a train wave card unit in the vertical is connected to each other using the first connecting plate. This setup has been demonstrated to enable in particular to optimizing stress, raising bonding strength and bearing capacity.
, can be in the outside of ripple board component (i.e. close to the one of tunnel in order to strengthen the mounting stability of ripple board component Side) carry out bar planting.Fig. 9 to 11 respectively illustrates the installment state of ripple board component in the form of enlarged drawing.As shown in figure 9, phase Adjacent two ripple Slab elements 110 are overlapped.Bolt 117 for fastening two neighboring ripple Slab element 110 extends to coagulation In native lining cutting layer 10, bar planting is formed.It is alternately or additional, some bar-mat reinforcements can also be hung as keel.
As shown in Figure 10, two neighboring ripple Slab element 410 is connected by connecting plate.Now, in the ripple of ripple Slab element Bar planting is carried out at peak and trough respectively.Reinforcing bar 127 is extended in concrete lining course 10.In the both sides of ripple Slab element 410 point Waterproof layer 420 and heat-insulation layer 430 are not provided with.
Figure 11 also shows that the installment state of ripple board component.The bar planting scheme that Figure 11 is used is identical with Figure 10. Difference is, in fig. 11, is only provided with the inner side of ripple Slab element 510 (i.e. away from the direction in tunnel) containing insulation The waterproof layer 520 of material.
Figure 12 is shown to be fastened for the bolt being fixed to the ripple Slab element of the least significant end on horizontal direction in pit Part 180.As illustrated, bolt fastener 180 includes L-shaped angle bar 183, the end that its one side passes through bolt 183 and ripple Slab element End is connected.The L-shaped foundation bolt 185 in pit is embedded on the another side of L-shaped angle bar 183.Thus, ripple Slab element It can install securely in place.
According to the utility model, a kind of tunnel supporting method is additionally provided.In the method, it is being arranged at first in tunnel Apply waterproof layer on the surface in the remote tunnel of the concrete lining course on wall.Afterwards, in the table in the remote tunnel of the waterproof layer Apply on face according to supporting of the present utility model ripple board component.
For the tunnel for having frost failure, it can be sprayed in supporting with the surface in the remote tunnel of ripple board component Heat-insulation layer or installation cystosepiment and other insulation materials.Heat-insulation layer can be for example made up of polyurethane.For without frost failure For tunnel, can the grout injection directly on a surface in the remote tunnel of supporting ripple board component, special-type grouting material or Person's concrete.
In another embodiment, can be in the remote of supporting ripple board component for the tunnel for having frost failure From grout injection directly on a surface, special-type grouting material or the concrete in tunnel, and leaning in supporting ripple board component Spraying insulating or installation cystosepiment and other insulation materials on the surface in nearly tunnel.In order to increase insulation material and corrugated plating Caking property, reinforcing bar can be implanted with surface of the supporting by the use of the close tunnel of ripple board component and hang bar-mat reinforcement as dragon Bone, afterwards fill-before-fire heat-insulation layer.
Finally it should be noted that the foregoing is only preferred embodiment of the present utility model, do not form to this Any restrictions of utility model.Although the utility model is described in detail with reference to foregoing embodiments, for For those skilled in the art, the technical scheme described in previous embodiment can still be modified, or to wherein Some technical characteristics carry out equivalent substitution.All any modifications within the spirit and principles of the utility model, made, equally replace Change, improve, should be included within the scope of protection of the utility model.

Claims (9)

1. for tunnel supporting ripple board component, be transversely connected with each other by several ripple Slab elements with longitudinal direction and Into.
2. supporting according to claim 1 ripple board component, it is characterised in that two adjacent ripple Slab elements pass through Corrugated plating cell edges lap one another and are connected, and overlapping regions at least accounts for the half crest of the ripple Slab element.
3. supporting according to claim 1 ripple board component, it is characterised in that at the longitudinal edge of each ripple Slab element The first connecting plate is provided with, for making each ripple Slab element be connected with each other along longitudinal direction, wherein, first connecting plate is along horizontal stroke To extension, and there is the height bigger than the ripple Slab element.
4. supporting according to claim 3 ripple board component, it is characterised in that two adjacent corrugated plating lists in transverse direction Member is lapped one another to be connected by transverse edge, and overlapping regions at least accounts for the half crest of the ripple Slab element.
5. supporting according to claim 4 ripple board component, it is characterised in that at the transverse edge of each ripple Slab element The second connecting plate is provided with, for making each ripple Slab element be connected with each other along longitudinal direction.
6. supporting according to claim 5 ripple board component, it is characterised in that second connecting plate prolongs along longitudinal direction Stretch, and be connected in central region with the transverse end edges of ripple Slab element, wherein, the height of second connecting plate is set Into the height more than the ripple Slab element.
7. the supporting ripple board component according to claim 5 or 6, it is characterised in that two neighboring ripple Slab element Collision mat is provided between first connecting plate and/or between the second connecting plate.
8. the supporting ripple board component according to any one of claim 1 to 6, it is characterised in that two neighboring ripple Join domain between Slab element offsets one from another.
9. the supporting ripple board component according to any one of claim 1 to 6, it is characterised in that the supporting ripple The ripple Slab element of lateral end in card component is fastened by bolts in pit of the part fixed to tunnel both sides, the bolt Fastener includes the L-shaped angle bar being connected with ripple Slab element, and the L-shaped foundation bolt being embedded in pit.
CN201720961829.7U 2017-08-03 2017-08-03 Supporting ripple board component Active CN206987838U (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201720961829.7U CN206987838U (en) 2017-08-03 2017-08-03 Supporting ripple board component
PCT/CN2018/091088 WO2019024613A1 (en) 2017-08-03 2018-06-13 Corrugated plate assembly for supporting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720961829.7U CN206987838U (en) 2017-08-03 2017-08-03 Supporting ripple board component

Publications (1)

Publication Number Publication Date
CN206987838U true CN206987838U (en) 2018-02-09

Family

ID=61418129

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720961829.7U Active CN206987838U (en) 2017-08-03 2017-08-03 Supporting ripple board component

Country Status (2)

Country Link
CN (1) CN206987838U (en)
WO (1) WO2019024613A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107435547A (en) * 2017-08-03 2017-12-05 中国铁道科学研究院铁道建筑研究所 Supporting ripple board component and tunnel supporting method
WO2019024613A1 (en) * 2017-08-03 2019-02-07 中国铁道科学研究院铁道建筑研究所 Corrugated plate assembly for supporting

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR960000768B1 (en) * 1990-04-09 1996-01-12 도꼬 떽꼬 가부시끼가이샤 Arch type builking structure
US5833394A (en) * 1996-06-12 1998-11-10 Michael W. Wilson Composite concrete metal encased stiffeners for metal plate arch-type structures
CN202298488U (en) * 2011-09-27 2012-07-04 衡水益通金属制品有限责任公司 Internal supporting structure of bridges, culverts and tunnels
JP6399695B2 (en) * 2014-11-14 2018-10-03 新日鉄住金マテリアルズ株式会社 Tunnel peeling prevention method
CN205024716U (en) * 2015-06-16 2016-02-10 曹宁宁 Metal corrugated plate with connection structure
WO2017099304A1 (en) * 2015-12-09 2017-06-15 평산에스아이 주식회사 Reinforcing structure for large corrugated steel plate and tunnel using same
CN205223876U (en) * 2015-12-15 2016-05-11 衡水奇佳工程材料有限公司 Supporting structure of in strenghthened type bridges and culverts, tunnel
CN107435547B (en) * 2017-08-03 2021-01-22 中国铁道科学研究院铁道建筑研究所 Corrugated plate assembly for supporting and tunnel supporting method
CN206987838U (en) * 2017-08-03 2018-02-09 中国铁道科学研究院铁道建筑研究所 Supporting ripple board component

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107435547A (en) * 2017-08-03 2017-12-05 中国铁道科学研究院铁道建筑研究所 Supporting ripple board component and tunnel supporting method
WO2019024613A1 (en) * 2017-08-03 2019-02-07 中国铁道科学研究院铁道建筑研究所 Corrugated plate assembly for supporting

Also Published As

Publication number Publication date
WO2019024613A1 (en) 2019-02-07

Similar Documents

Publication Publication Date Title
CN107435547A (en) Supporting ripple board component and tunnel supporting method
CN104831617B (en) Steel-ultra-high performance concrete combination beam based on fin-plate type bridge floor and construction method
CN201172796Y (en) Steel box girder bridge deck structure with upper longitudinal ribs
CN104790974A (en) City subway overlapped shield tunnel segment structure adopting special longitudinal connecting pieces
CN104594191B (en) Seamless expansion-contraction devices and construction method thereof between the girder of built-in corrugated steel plate and abutment
CN104674650B (en) Based on bridge floor seamless process retractor device and the construction method thereof of the type transverse joint plate of putting more energy into
PT2126243E (en) Sloping roof system and insulating board for sloping roof systems
CN108729564A (en) Assembled architecture system
CN206987838U (en) Supporting ripple board component
CN104762873B (en) A kind of Abutment implicit expression retractor device and construction method thereof
CN105970800B (en) The abutment connecting structure and its construction method of monoblock type combination beam is seamless bridge
CN105178177B (en) Highway bridge self-adaptation multidirection deformation displacement composite structure retractor device
CN106760036B (en) A kind of prefabricated steel-combined concrete shear wall
CN102108675B (en) Bridge deck expansion joint structure
CN201924277U (en) Expansion joint structure of bridge deck
CN214362806U (en) Connecting device for splicing width of new bridge and old bridge
CN109056796A (en) A kind of full prefabrication and assembly construction superposed type piping lane comprehensive waterproof structure and construction method
KR100949570B1 (en) Waterproof sheet and the construction method thereby
CN111255101A (en) Flush joint waterproof construction of roofing movement joint
CN105908623A (en) Expansion and contraction device with lower supporting platform
CN114319000B (en) Thin asphalt pavement bonding layer capable of absorbing stress and construction method thereof
CN206298821U (en) Simply supported girder bridge composite connection board is constructed
CN205775825U (en) There is the retractor device of lower support platform
CN215055624U (en) Steel structural member for reinforcing concrete structure
CN109024249A (en) A kind of connector uses the spigot-and-socket construction precast assembly bridge pier of cast-in-place UHPC material

Legal Events

Date Code Title Description
GR01 Patent grant