CN206667424U CN201720017105.7U CN201720017105U CN206667424U CN 206667424 U CN206667424 U CN 206667424U CN 201720017105 U CN201720017105 U CN 201720017105U CN 206667424 U CN206667424 U CN 206667424U
Authority
CN
China
Prior art keywords
wall
rain pipe
cofferdam
ground
concrete foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720017105.7U
Other languages
Chinese (zh)
Inventor
蒋锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Kejia Engineering Design Co Ltd
Original Assignee
Jiangsu Kejia Engineering Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Kejia Engineering Design Co Ltd filed Critical Jiangsu Kejia Engineering Design Co Ltd
Priority to CN201720017105.7U priority Critical patent/CN206667424U/en
Application granted granted Critical
Publication of CN206667424U publication Critical patent/CN206667424U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a kind of rain pipe to bury structure, its drip irrigation device is to include shore protection, rain pipe is set in the shore protection, the shore protection is provided with precast square pile close to waters side, the two corral weirs for isolating wall and precast square pile with waters are provided with around the wall, connected between the wall and cofferdam by concrete foundation, the rain pipe is provided with earth excavation groove away from ground side, and the earth excavation groove extends from wall to away from waters side.It is arranged such, precast square pile had both enough improved the self-strength of wall, connected between cofferdam and wall by concrete foundation, concrete foundation by cofferdam and wall connecting it is integral after, cofferdam, concrete foundation, wall form an entirety, after the impact by water flow impact pressure and ship wave, compared to the cofferdam set independently of each other, constructing structure is more firm, not easily damaged.Earth excavation groove reduces the pressure of the submerged structure to rain pipe and its periphery, reduces the possibility that underwater foundation is surprisingly damaged.

Description

Rain pipe buries structure
Technical field
Hydraulic engineering harbour safeguarding structure field is the utility model is related to, more particularly to a kind of rain pipe buries structure.
Background technology
Rain pipe is embedded in shore protection, is easy to a kind of water conservancy structure for importing rain water or other fluid in the waters such as river.
At present, common rain pipe constructing structure is typically provided with cofferdam in shore protection towards the side in the waters such as river, encloses Weir is arranged to separate with shore protection mostly, and cofferdam is built up using the single sandy gravel of structure or soil, and worker is in cofferdam Constructed in the space crossed, but in the waters outside cofferdam, there is rushing for ship wave when impulsive force, the vessel motion of current Brush, is easily impacted to cofferdam, makes it impaired.
Utility model content
The purpose of this utility model is to provide a kind of rain pipe and buries structure, and it has stabilized structure, in work progress, The facilities such as underwater foundation are protected, the advantages of reducing constructing structure impaired possibility.
Above-mentioned technical purpose of the present utility model technical scheme is that:
A kind of rain pipe buries structure, including shore protection, and rain pipe is set in the shore protection, it is characterised in that:The shore protection Precast square pile is provided with close to waters side, two corrals for isolating wall and precast square pile with waters are provided with around the wall Weir, connected between the wall and cofferdam by concrete foundation, the rain pipe is provided with the second box cut, institute away from the side on ground The second box cut is stated from wall to away from waters side to extend.
It is arranged such, after setting cofferdam, cofferdam isolates from the current in waters outside, and slot milling is constructed for worker. Precast square pile had both enough improved the self-strength of wall, was connected between cofferdam and wall by concrete foundation, and concrete foundation is by cofferdam and wall After body links into an integrated entity, cofferdam, concrete foundation, wall form an entirety, after the impact by water flow impact pressure and ship wave, Compared to the cofferdam set independently of each other, the constructing structure with concrete foundation is more firm, not easily damaged.Earth excavation groove is set Afterwards, the space that can have abundance is used for embedded rain pipe of constructing.And in work progress, it can reduce to rain pipe and its week The pressure of the submerged structure on side, reduce the possibility that rain pipe and underwater foundation are surprisingly damaged.
Further set:The concrete foundation from wall to tilting extension at cofferdam, the concrete foundation close to wall one Side vertical height is higher than its vertical height at cofferdam.
It is arranged such, inclined plane can bear bigger impact compared to vertical plane or horizontal plane when by impulsive force Power;And after construction terminates, the structure comes into operation, the current that inclined plane can be easy to discharge in rain pipe flow into river course.
Further set:Connected between the concrete foundation and ground by earthwork group, the earthwork group includes recessed in ground The first box cut, protrude the first backfill earthwork on ground, first box cut and the first the backfill earthwork and ground form rank Scalariform.
It is arranged such, the step structure that the first box cut and the first backfill earthwork are formed can increase cubic metre of earth group and concrete Connection area between basis, after increasing connection area, bonding strength between the two improves, and makes total more firm.
Further set:The rain pipe includes being embedded in the first pipeline at shore protection, deviates from waters side positioned at shore protection Second pipe, docked between first pipeline and second pipe.
It is arranged such, after rain pipe is divided into some segment pipes, is shortened per the length of segment pipe, is readily transported and work progress In operation.
Further set:Marked time away from ground side provided with concrete one end that the rain pipe stretches out wall.
It is arranged such, concrete, which is marked time, to be covered on rain pipe, and certain protective effect can be played to rain pipe.Work as rain pipe When the earthwork of top has pedestrian or vehicle contact, applies pressure to ground, the pressure suffered by rain pipe is marked time uniformly by concrete It is scattered, reduce the possibility of rain pipe local pressure cracking.
Further set:The concrete is provided with reinforced mesh in marking time.
It is arranged such, reinforced mesh plays a part of reinforcement, it is possible to increase the intensity that concrete is marked time, the stress even if concrete is marked time Crack is produced, can be also connected by reinforced mesh, not easy to break is two separate individuals.
In summary, the utility model has the advantages that:Concrete foundation, precast square pile can set isostructural Under the premise of, make whole constructing structure stable;The setting in two layers of cofferdam can reduce infringement caused by water impact, with these structures To ensure the reliable and stable of constructing structure underwater foundation.
Brief description of the drawings
Fig. 1 is the structural representation for being used to embody integral construction structure in embodiment 1;
Fig. 2 is the structural representation for being used to embody two corral weirs in embodiment 1;
Fig. 3 is the structural representation for being used to embody cofferdam in embodiment 1.
In figure, 1, shore protection;1-1, wall;1-2, front toe;2nd, rain pipe;3rd, precast square pile;4th, cofferdam;5th, concrete body;6th, steel Pipe;7th, concrete foundation;8th, earthwork group;9th, the first box cut;10th, the second box cut;11st, the first backfill earthwork;12nd, the second backfill Side;13rd, the first pipeline;14th, second pipe;15th, concrete wall body;16th, concrete is marked time;17th, reinforced mesh;18th, antiseepage film;19th, it is geotechnological Cloth;20th, bamboo curtain splint;21st, horizontal tube.
Embodiment
The utility model is described in further detail below in conjunction with accompanying drawing.
Embodiment 1:A kind of rain pipe buries structure, as shown in figure 1, including shore protection 1, shore protection 1 is set towards the side in waters There are two corral weirs 4.As shown in Fig. 2 two corral weirs 4 to be arranged concentrically, include concrete body 5 per corral weir 4, the side of concrete body 5 is set Steel pipe 6 is to improve intensity.
As shown in figure 1, shore protection 1 includes the wall 1-1 set perpendicular to ground, set in wall 1-1 towards waters side Front toe 1-2, connected between front toe 1-2 and cofferdam 4 by concrete foundation 7.Connected between concrete foundation 7 and ground by earthwork group 8.Ground Face gradually reduces to be obliquely installed from wall 1-1 to height at cofferdam 4.Dig on the ground recessed in the first of sloping floor Box cut 9, the entirety of the first backfill earthwork 11, the first box cut 9 and the first backfill earthwork 11 is set in the both sides heap of the first box cut 9 External structure pours concrete foundation 7 to be stepped on stair-stepping ground, and concrete foundation 7 is likewise provided as skewed, and it is close to wall Body 1-1 side is higher than away from wall 1-1 side.
As shown in figure 1, connected between wall 1-1 and ground by precast square pile 3, the side in wall 1-1 towards waters The precast square pile 3 separate with wall 1-1 is additionally provided with, its length is significantly greater than the precast square pile being fixedly connected with wall 1-1 3, precast square pile 3 is encapsulated completely by concrete foundation 7.Concrete foundation 7 is in addition to the part poured above earthwork group 8, in addition to enveloping The part of precast square pile 3, the part for encapsulating precast square pile 3 extends to wall 1-1 away from waters side, until being located at wall 1-1 Lower section.
As shown in figure 1, the second box cut 10, the second box cut 10 are also dug away from the side in waters in wall 1-1 At the top of wall 1-1, rain pipe 2 runs through wall body, and is stretched out to wall body towards waters side.Rain pipe 2 is buried including the later stage The first pipeline 13 and original second pipe 14 for being just embedded in underground, the first pipeline 13 and second pipe 14 dock.
As shown in figure 1, pouring concrete wall body 15 on rain pipe 2, having poured concrete away from waters side in rain pipe 2 marks time 16.Spilled water hole is additionally provided with wall 1-1.Wall 1-1 has also dug the second box cut 10 away from the side in waters, is burying Into after rain pipe 2, the backfill of filling second earthwork 12, makes its surface still smooth in the second box cut 10.
As shown in figs. 1 and 3, antiseepage film 18, geotextiles are sequentially provided with to steel pipe 6 between steel pipe 6 and concrete body 5, from concrete body 5 19th, bamboo curtain splint 20, it is close between concrete body 5 and steel pipe 6.Horizontal tube 21 is additionally provided with the both sides in cofferdam 4.
The above embodiments are only that it is not to limitation of the present utility model, ability to explanation of the present utility model Field technique personnel can make the modification of no creative contribution to the present embodiment as needed after this specification is read, but As long as all protected in right of the present utility model by Patent Law.

Claims (6)

1. a kind of rain pipe buries structure, including shore protection(1), the shore protection(1)Interior setting rain pipe(2), it is characterised in that:Institute State shore protection(1)Precast square pile is provided with close to waters side(3), shore protection(1)Including the wall set perpendicular to ground(1-1), institute State wall(1-1)Surrounding is provided with wall(1-1)And precast square pile(3)The two corral weirs isolated with waters(4), the wall (1-1)With cofferdam(4)Between pass through concrete foundation(7)Connection, the rain pipe(2)The second box cut is provided with away from the side on ground (10), second box cut(10)From wall(1-1)Place extends to away from waters side.
2. rain pipe according to claim 1 buries structure, it is characterised in that:The concrete foundation(7)From wall(1-1)Place To cofferdam(4)Place tilts extension, the concrete foundation(7)Close to wall(1-1)Side vertical height higher than its close to cofferdam(4) The vertical height at place.
3. rain pipe according to claim 2 buries structure, it is characterised in that:The concrete foundation(7)Lead between ground Cross earthwork group(8)Connection, the earthwork group(8)Including recessed the first box cut in ground(9), protrusion ground the first backfill Side(11), first box cut(9)With the first backfill earthwork(11)Formed with ground stepped.
4. rain pipe according to claim 3 buries structure, it is characterised in that:The rain pipe(2)Including being embedded in shield Bank(1)First pipeline at place(13), positioned at shore protection(1)Second pipe away from waters side(14), first pipeline(13) With second pipe(14)Between dock.
5. rain pipe according to claim 4 buries structure, it is characterised in that:The rain pipe(2)Stretch out wall(1-1) One end marked time away from ground side provided with concrete(16).
6. rain pipe according to claim 5(2)Embedded structure, it is characterised in that:The concrete is marked time(16)In be provided with Reinforced mesh(17).
CN201720017105.7U 2017-01-06 2017-01-06 Rain pipe buries structure Active CN206667424U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720017105.7U CN206667424U (en) 2017-01-06 2017-01-06 Rain pipe buries structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720017105.7U CN206667424U (en) 2017-01-06 2017-01-06 Rain pipe buries structure

Publications (1)

Publication Number Publication Date
CN206667424U true CN206667424U (en) 2017-11-24

Family

ID=60357057

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720017105.7U Active CN206667424U (en) 2017-01-06 2017-01-06 Rain pipe buries structure

Country Status (1)

Country Link
CN (1) CN206667424U (en)

Similar Documents

Publication Publication Date Title
CN1837511B (en) Double-rowed cofferdam and method for manufacturing the same
CN105040595B (en) Bridge main pier bearing platform foundation pit supporting structure on gentle slope riverbed bedrock and construction method thereof
CN106801424A (en) A kind of cofferdam construction method
CN205134193U (en) Bridge main pier cushion cap foundation pit supporting structure on gentle slope riverbed bedrock
CN206204880U (en) A kind of side slope comprehensive regulation structure of prevention river channel erosion
CN106400744A (en) Comprehensive side-slope treatment structure for preventing river channel erosion and construction method thereof
US20240229410A1 (en) Drainage pressure relief anti-floating system suitable for weakly permeable soft stratum
CN207143981U (en) 3rd is rich water half diagenesis Sandstone Section Metro station excavation discharge structure
CN206204972U (en) A kind of prefabricated tubular pile as well-points dewatering
CN105862659B (en) High-frequency debris flow shore protection and diversion method
CN111270698A (en) Protective structure for exposed diseases of bridge pile foundation in sand-mining river channel in mountainous area and construction method of protective structure
CN103614988A (en) Flexible scour-preventing protective cushion and construction method thereof
CN106703053A (en) Construction method for reinforced soil drainage composite revetment structure
CN103898915A (en) Anti-floating and waterstop construction method for small-area deep foundation pit of building
CN203821306U (en) Flexible anti-scour protection pad
CN206667424U (en) Rain pipe buries structure
CN206916686U (en) A kind of subgrade protection system in debris flow gully
CN216615927U (en) Emergency structure system applied to single-row enclosure of foundation pit
CN213926284U (en) Foundation pit supporting and foundation treatment synergistic structure
CN112282766B (en) Treatment method for surface collapse pit caused by sudden water burst of tunnel
CN212223936U (en) A protective structure that is used for mountain area to adopt sand river course inner bridge pile foundation to expose disease
CN209975545U (en) Earth-rock cofferdam adapting to high flow velocity
CN210658236U (en) Slag stacking structure
CN210636421U (en) Underwater hollowing defect repairing device for navigation wall pile foundation of ship lock on gravel layer foundation
CN110468837B (en) Underwater hollowing defect repairing method and device for ship lock navigation wall pile foundation on gravel layer basis

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant