CN205200445U - Material feeding unit for forging press - Google Patents

Material feeding unit for forging press Download PDF

Info

Publication number
CN205200445U
CN205200445U CN201521067016.0U CN201521067016U CN205200445U CN 205200445 U CN205200445 U CN 205200445U CN 201521067016 U CN201521067016 U CN 201521067016U CN 205200445 U CN205200445 U CN 205200445U
Authority
CN
China
Prior art keywords
heating furnace
forging press
pay
cradle
rising arm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201521067016.0U
Other languages
Chinese (zh)
Inventor
亓连文
葛希佩
纪宝华
许善军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG WENLING PRECISION FORGING TECHNOLOGY Co Ltd
Original Assignee
SHANDONG WENLING PRECISION FORGING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG WENLING PRECISION FORGING TECHNOLOGY Co Ltd filed Critical SHANDONG WENLING PRECISION FORGING TECHNOLOGY Co Ltd
Priority to CN201521067016.0U priority Critical patent/CN205200445U/en
Application granted granted Critical
Publication of CN205200445U publication Critical patent/CN205200445U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forging (AREA)

Abstract

The utility model discloses a material feeding unit for forging press, including the storage platform, pass through the heating furnace that carries the long heating chamber of band -pass that material platform and level set up of slide intercommunication with the storage platform, carry material platform one end set up in heating furnace import, the other end are provided with along the flexible propelling movement cylinder of heating furnace heating chamber direction, the heating furnace exit end sets gradually the conveying frame that has the running roller, articulated first pay -off frame and the articulated second pay -off frame that has the 2nd lifting arm that has a lifting arm, be fixed with a piston rod and a lifting arm articulated lift cylinder on the first pay -off frame, be fixed with the 2nd lift cylinder of piston rod and the 2nd lifting arm articulated on the second pay -off frame, the device has replaced ram material loading mode, has alleviateed intensity of labour.

Description

A kind of forging press pay-off
Technical field
The utility model relates to a kind of feeder equipment for forge plant, particularly a kind of forging press pay-off.
Background technology
At present, most forging producer gear blank part heating, forge with rolling ring process in be all the mode adopting rod and slideway to combine carry out inter process turn material, although simple to operate, but labor strength is large, rod takes up room greatly, and expends time in, and affects production efficiency.
Summary of the invention
The purpose of this utility model is just to provide a kind of forging press pay-off, can not only alleviate workman labour, and has saved the space of production scene, for 6S management is given security.
For achieving the above object, the technical scheme that the utility model adopts is: a kind of forging press pay-off, comprise the heating furnace of storing platform, the material carrier platform be communicated with by slideway with storing platform and horizontally disposed band heating chamber, the heating chamber of heating furnace is through the export and import of heating furnace, material carrier platform one end is arranged at heating furnace import department, and the other end is provided with the propelling movement cylinder flexible along heating furnace heating chamber direction, and pushing cylinder can advance in heating furnace by the blank on material carrier platform, furnace outlet end is disposed with the conveyer frames with running roller, be hinged with the first cradle of the first rising arm and be hinged with the second cradle of the second rising arm, described first cradle is fixed with piston rod and hinged the first lifting cylinder of the first rising arm, described second cradle is fixed with piston rod and hinged the second lifting cylinder of the second rising arm, first rising arm, second rising arm is respectively in the first lifting cylinder, around the first cradle under the drive of the second lifting cylinder, second cradle rotates, first rising arm and the second rising arm are provided with guide rail along its length, slide for workpiece.
As preferably, described heating furnace is electric furnace, adopt heating in medium frequency, two elongated conduits be arranged in parallel are provided with in its heating chamber, for the slip of blank, conduit two ends are communicated with cooling water recirculation system, and conduit is cooled by the recirculated water of its inside, to prevent high temperature billet material and conduit adhesion.
As preferably, at slide egress, place is provided with stirrer, described stirrer comprises the back shaft be laterally fixed on bottom slideway, described back shaft is socketed with baffle plate, described baffle plate one end is connected with the upset cylinder driving its upset, the piston rod of upset cylinder when stretching out baffle plate turning to slideway bottom flush position, the blank in slideway can slip into material carrier platform along slideway; When piston rod is regained, baffle plate rotates to the position exceeded bottom slideway, and the blank in slideway is blocked by baffle plate.
As the optimization of above-mentioned preferred version, described slideway is downward-sloping from feeding platform, and angle of inclination is 3 °-5 °, facilitates blank to slip in material carrier platform under Gravitative Loads.
As optimization, the running roller height on described conveyer frames reduces backward successively from furnace outlet, and in heating furnace, blank out can be rolled into the conveyer frames other end along running roller automatically.
As optimization, running roller both sides are provided with the guardrail be fixedly connected with described conveyer frames, prevent blank from dropping and hurt sb.'s feelings.
The beneficial effects of the utility model are: what replace rod turns material mode, at material loading end, only need manually the blank on storing stand to be dialled in slideway, the material that turns between each operation does not need moved by hand, greatly saves labour intensity, reduces cost of labor, shorten and turn the material time, improve production efficiency, and this device cost of manufacture is low, simple to operate.
Accompanying drawing explanation
Fig. 1 is the utility model structural representation.
Fig. 2 be in Fig. 1 C to.
Fig. 3 is A direction view in Fig. 2.
Fig. 4 is B direction view in Fig. 1.
In figure, 1, storing platform, 2, material carrier platform, 3, slideway, 4, heating furnace, 4.1, heating chamber, 4.2, conduit, 5, conveyer frames, 6, guardrail, 7, running roller, the 8, first rising arm, the 9, first lifting cylinder, 10, the first cradle, the 11, second lifting cylinder, the 12, second rising arm, 13, the second cradle, 14, push cylinder, 15, stirrer, 15.1, baffle plate, 15.2, back shaft, 15.3, upset cylinder.
Detailed description of the invention
Forging press pay-off as a kind of in accompanying drawing, comprise storing platform 1, heating furnace 4, the material carrier platform 2 that is communicated with by slideway 3 with storing platform 1, slideway 3 is obliquely installed, and angle of inclination is 4 °, and lower end extends to the side of material carrier platform 2, and upper end is communicated with storing platform 1; Heating furnace 4 is electric furnace, adopt heating in medium frequency, the heating chamber 4.1 of heating furnace 4 is through the import of heating furnace 4 to outlet, and it is horizontally disposed, two elongated conduits 4.2 be arranged in parallel also are provided with in heating chamber 4.1, conduit 4.2 two ends are communicated with cooling water recirculation system, and conduit 4.2 is cooled by the cooling water flow through in its pipe, to prevent conduit 4.2 and the adhesion of high temperature blank; One end of material carrier platform 2 is arranged at the import department of heating furnace 4, and the other end is provided with the propelling movement cylinder 14 flexible along heating furnace heating chamber 4.1 direction; The port of export of heating furnace 4 is disposed with conveyer frames 5, first cradle 10 and the second cradle 13, conveyer frames 5 is horizontally arranged with the running roller 7 of parallel arrangement, the height of running roller 7 reduces backward successively from the outlet of heating furnace 4, and the both sides of running roller 7 are provided with the guardrail 6 be fixedly connected with conveyer frames 5; First rising arm 8 by bearing pin and the first cradle 10 hinged, the first cradle 10 is also fixed with piston rod and hinged the first lifting cylinder 9 of the first rising arm 8; Second rising arm 12 by bearing pin and the second cradle 13 hinged, the second cradle 13 is also fixed with piston rod and hinged the second lifting cylinder 11 of the second rising arm 12; In order to control material loading speed, the exit position of slideway 3 arranges stirrer 15, and stirrer 15 comprises the back shaft 15.2 be laterally fixed on bottom slideway 3, back shaft 15.2 is socketed with baffle plate 15.1, and described baffle plate one end is connected with the cylinder 15.3 driving its upset.
Before start, can first blank be dialled in slideway 3 from storing stand 1, the piston rod now overturning cylinder 15.3 is in retracted mode, blank is static in slideway, after start, overturn the action that the piston rod of cylinder 15.3 is spaced, baffle plate 15.1 is driven to turn down and erect, blank slips on material carrier platform 2 successively, pushing cylinder 14 is spaced action equally, blank on material carrier platform is sent in heating furnace 4, the conduit 4.2 of blank in heating chamber 4.1 is arranged successively, after having heated, under the effect pushing cylinder 14, landing is on conveyer frames 5 successively, be rolled on the workbench below press along running roller 7 under the effect of self gravitation, forge, after having forged, workpiece is dialled on the first rising arm 8, first lifting cylinder 9 drives the first lift arm 8 to raise up, workpiece slides to ring rolls along the slide rail on the first lift arm 8, after rolling ring completes, workpiece is allocated on the second lift arm 12, second lifting cylinder 11 drives the second lift arm 12 to raise up, workpiece slided to next procedure or slide to material frame.
The above is only the preferred embodiment of the application, those skilled in the art is understood or realizes the application.To be apparent to one skilled in the art to the multiple amendment of these embodiments, General Principle as defined herein can when not departing from the spirit or scope of the application, realize in other embodiments, therefore, any this kind of form is the equivalent replacement form of the invention, do not depart from the flesh and blood of the invention, the application also can not be restricted to these embodiments shown in this article, but will meet the widest scope consistent with principle disclosed herein and features of novelty.

Claims (6)

1. a forging press pay-off, is characterized in that: the heating furnace comprising storing platform, the material carrier platform be communicated with by slideway with storing platform and the elongated heating chamber of horizontally disposed band; Described material carrier platform one end is arranged at described heating furnace import, and the other end is provided with the propelling movement cylinder flexible along heating furnace heating chamber direction; Furnace outlet end be disposed with running roller conveyer frames, be hinged with the first cradle of the first rising arm and be hinged with the second cradle of the second rising arm, described first cradle is fixed with piston rod and hinged the first lifting cylinder of the first rising arm, described second cradle is fixed with piston rod and hinged the second lifting cylinder of the second rising arm, the first rising arm and the second rising arm is provided with guide rail along its length.
2. a kind of forging press pay-off according to claim 1, it is characterized in that: described heating furnace is electric furnace, be provided with two elongated conduits be arranged in parallel in its heating chamber, described conduit two ends are communicated with cooling water recirculation system.
3. a kind of forging press pay-off according to claim 1, it is characterized in that: described slide egress is provided with stirrer, described stirrer comprises the back shaft be laterally fixed on bottom slideway, described back shaft is socketed with baffle plate, and described baffle plate one end is connected with the upset cylinder driving its upset.
4. a kind of forging press pay-off according to claim 1 or 3, is characterized in that: described slideway is downward-sloping from storing platform, and angle of inclination is 3 °-5 °.
5. a kind of forging press pay-off according to claim 1, is characterized in that: the running roller height on described conveyer frames reduces backward successively from furnace outlet.
6. a kind of forging press pay-off according to claim 1 or 5, is characterized in that: described running roller both sides are provided with the guardrail be fixedly connected with described conveyer frames.
CN201521067016.0U 2015-12-21 2015-12-21 Material feeding unit for forging press Active CN205200445U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201521067016.0U CN205200445U (en) 2015-12-21 2015-12-21 Material feeding unit for forging press

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201521067016.0U CN205200445U (en) 2015-12-21 2015-12-21 Material feeding unit for forging press

Publications (1)

Publication Number Publication Date
CN205200445U true CN205200445U (en) 2016-05-04

Family

ID=55838186

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201521067016.0U Active CN205200445U (en) 2015-12-21 2015-12-21 Material feeding unit for forging press

Country Status (1)

Country Link
CN (1) CN205200445U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108889896A (en) * 2018-08-16 2018-11-27 江西科明铜业有限公司 A kind of Gas stove component forging equipment
CN109848346A (en) * 2019-03-04 2019-06-07 青岛宏联电器有限公司 A kind of steel plate hot forging continuous producing apparatus
CN110000326A (en) * 2019-03-28 2019-07-12 青岛中天鹏锻压制造有限公司 A kind of heating system for forging
CN112338129A (en) * 2020-10-22 2021-02-09 德清恒升管件有限公司 Pipe fitting forging and pressing device

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108889896A (en) * 2018-08-16 2018-11-27 江西科明铜业有限公司 A kind of Gas stove component forging equipment
CN109848346A (en) * 2019-03-04 2019-06-07 青岛宏联电器有限公司 A kind of steel plate hot forging continuous producing apparatus
CN110000326A (en) * 2019-03-28 2019-07-12 青岛中天鹏锻压制造有限公司 A kind of heating system for forging
CN110000326B (en) * 2019-03-28 2024-08-23 青岛中天鹏锻压制造有限公司 Heating system for be used for forging
CN112338129A (en) * 2020-10-22 2021-02-09 德清恒升管件有限公司 Pipe fitting forging and pressing device

Similar Documents

Publication Publication Date Title
CN205200445U (en) Material feeding unit for forging press
CN107775787B (en) A kind of insulating fire brick automatic casting molding base system and method
CN205221914U (en) Automatic charging and discharging device
CN203806529U (en) Conveying device of fully-automatic multi-station three-dimensional pipe punching equipment
CN204713144U (en) Weaving winding up roller transport trolley
CN201990270U (en) Automatic or semiautomatic steamer of solid brewing grains
CN207645211U (en) Automate section bar conveying appliance
CN104001725A (en) Roller replacement trolley
CN205576221U (en) Bearing quenching furnace
CN102616574B (en) Automatic pipe arrangement device for steel pipes
CN204182692U (en) A kind of milling train automatic feeding frame
CN204018444U (en) Quick veneer reeling machine
CN103937938B (en) A kind of charging temperature regulating device being applied to continuous isothermal hardening and producing
CN103306698A (en) In-position machine for hydraulic support
CN203820066U (en) Aluminum profile automatically loading frame structure
CN202452837U (en) Electrode-conveying device for calcinatory
CN201530842U (en) Steel bottle output and turnover device of steel bottle quenching and tempering heat treatment production line
CN201907853U (en) Loading-unloading device of single-position equipment
CN211645361U (en) Feeding and discharging system of aluminum plate quenching furnace
CN204824985U (en) High temperature gyration elevating system
CN212291625U (en) Cooling device for partitioned and layered operation of multiple boxes
CN203638715U (en) Improved aluminum profile conveying device
CN203997767U (en) A kind of feedway immersing continuously in dryer
CN103824708B (en) A kind of prepare the automatic chemical conversion of aluminium electrolutic capacitor, carbonization, cleaning all-in-one
CN204325434U (en) A kind of composite insulator hardware thermal treatment dedicated tunnel stove

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant