[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN204953074U - Grind grading system of steerable iron mineral derichment - Google Patents

Grind grading system of steerable iron mineral derichment Download PDF

Info

Publication number
CN204953074U
CN204953074U CN201520676206.6U CN201520676206U CN204953074U CN 204953074 U CN204953074 U CN 204953074U CN 201520676206 U CN201520676206 U CN 201520676206U CN 204953074 U CN204953074 U CN 204953074U
Authority
CN
China
Prior art keywords
overflow pipe
grinding
outlet
ore
sand setting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201520676206.6U
Other languages
Chinese (zh)
Inventor
肖骁
张国旺
龙渊
黄礼龙
石立
赵湘
李文明
谢驰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha Research Institute of Mining and Metallurgy Co Ltd
Original Assignee
Changsha Research Institute of Mining and Metallurgy Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha Research Institute of Mining and Metallurgy Co Ltd filed Critical Changsha Research Institute of Mining and Metallurgy Co Ltd
Priority to CN201520676206.6U priority Critical patent/CN204953074U/en
Application granted granted Critical
Publication of CN204953074U publication Critical patent/CN204953074U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Separation Of Solids By Using Liquids Or Pneumatic Power (AREA)
  • Cyclones (AREA)

Abstract

The utility model provides a grind grading system of steerable iron mineral derichment, include for ore deposit ore pulp groove, give the ore deposit pump, double overflow pipe swirler, sand setting ore pulp groove, the mill, a sorting facilities and open -circuit grinding mill, double overflow pipe swirler is equipped with the swirler import, the sand setting export, excessive egress opening and interior overflow export, the export of giving ore deposit ore pulp groove links to each other with the import of giving the ore deposit pump, link to each other for the ore deposit delivery side of pump with the swirler import, the sand setting export links to each other with the mill import, the mill export links to each other with giving ore deposit ore pulp groove, an excessive egress opening and a sorting facilities link to each other, interior overflow export links to each other with the import of open -circuit grinding mill, the export of open -circuit grinding mill links to each other with a sorting facilities, the utility model discloses can reduce derichment, improvement mill throughput, reduction ore grinding energy consumption and the improvement concentrate product quality of iron mineral in the sand setting.

Description

A kind of grinding classification system controlling iron mineral derichment
Technical field
The utility model relates to ore processing facility technical field, is specifically related to a kind of grinding classification system controlling iron mineral derichment.
Background technology
In iron ore processing, ore grinding cost accounts for more than 50% of processing totle drilling cost.And be tapered along with process iron ore disseminated grain size need be processed, usually can adopt two sections or multistage grinding, this makes ore grinding cost increase further.Grind grading technology is as the core process in ore dressing plant, and Grading Overflow granularity and sand return are than the key factor being treating capacity and sorting index when affecting power consume, grinding machine platform.
Current two sections of mill (and multistage mill) ore grindings, chats, coarse concentrate regrinding classification are all the closed circuit grinding loop adopting grinding attachment (ball mill or vertical mill) and hydrocyclone composition substantially: to ore deposit first through hydroclone classification, coarse granule (sand return or title underflow) after classification enters grinding machine, ore milling product returns hydrocyclone again and carries out classification, and the fine grained after classification enters follow-up Beneficiation flowsheet.Wherein, hydrocyclone is a kind of by the equipment of centrifugal force realization by particle sinking speed classification, its classification principle is: ore pulp is entered after cylindrical tube immediately around axis High Rotation Speed by tangential direction by mineral-feeding pipe, produce very large centrifugal force, the centrifugal force difference of the particle that in ore pulp, granularity is different with density owing to being subject to, so their movement velocity, acceleration and directions in cyclone are also different, wherein, the centrifugal force that thick and heavy particle is subject to is large, thrown to barrel, by spiral trajectory backspin to bottom, discharge from sand setting outlet as sand setting; The centrifugal force that thin and light particle is subject to is little, is brought to center, is formed centrally inside spin ore deposit stream and moves upward, discharge as overflow from overflow pipe in conical shell.
In cyclone classification process, because magnetic/bloodstone valuable mineral density is larger, and quartz waits gangue mineral density less, thus can carry out classification according to size and density simultaneously, very easily there is the derichment of iron mineral, the qualified grain size (being mainly the qualified grain size magnetic/bloodstone dissociated) that should be enriched to cyclone overflow is made to enter underflow, return in grinding machine and regrind, and constantly circulate in grind grading loop, make the sand return of grind grading loop than increasing, what granularity was thicker is then easy to enter overflow containing quartzy intergrowth, grinding machine treating capacity is caused to reduce, energy consumption increases, iron mineral is overground, the problems such as mineral processing index reduction.Table 1 is grain class distribution and the iron distribution of certain iron ore power water cyclone overflow and underflow product, as can be seen from table, eddy flow overflow grade only has 62.55%, underflow grade is then 65.48%, particularly in-0.05mm grade, up to 71.06%(, the theoretical grade of magnetic iron ore is 72.4% to underflow grade), this illustrates that cyclone underflow-0.05mm grade product is magnetic iron ore minal, and its productive rate is 64%, mean that the 64% qualified ore milling product that should enter overflow but enters underflow and returns in grinding machine and again grind, namely there occurs comparatively serious iron mineral derichment phenomenon, this not only lowers grinding machine disposal ability, add power consume, iron mineral is also easily caused to cross pulverizing, affect its rate of recovery, simultaneously because coarse granule intergrowth enters overflow, also have impact on concentrate grade.
The grain class distribution of certain iron ore power water cyclone overflow of table 1 and underflow product and iron distribution table
In order to reduce iron mineral derichment in hydrocyclone sand, usually take there are two kinds of modes below: 1) optimize grind grading parameter, improve cyclone classification efficiency, the derichment of iron mineral at cyclone underflow can be reduced to a certain extent by this kind of mode, but because iron mineral and gangue itself exist density contrast, the particulate iron mineral dissociated is due to than great, be easy to enter sand setting, and large scale intergrowth especially lean intergrowth due to proportion little, be easy to enter overflow, therefore the simple derichment effect relying on the classification efficiency improving cyclone to control iron mineral is not too obvious.2) replace cyclone with dusting cover and carry out Inspection graduation.When adopting fine screening classification, because iron mineral is heavier, under being easy to enter sieve, to a certain degree can impel the enrichment of iron ore forward, the effectiveness comparison reducing derichment is obvious, but the screen size due to current dusting cover is minimum is 0.1mm, gradable granularity is minimum can only reach 0.074mm, and most domestic iron ore requires that ore grinding release mesh is all with 0.045mm or following for benchmark now, and the price of dusting cover is higher, screen cloth easily blocks, and therefore the application of this kind of mode is subject to many restrictions.
Utility model content
The technical problems to be solved in the utility model is the deficiency overcoming prior art existence, provides a kind of grinding classification system that can reduce the controlled iron mineral derichment of the derichment of iron mineral in sand setting, raising grinding machine disposal ability, reduction power consume and raising concentrate product quality.
For solving the problems of the technologies described above, the utility model by the following technical solutions:
A kind of grinding classification system controlling iron mineral derichment, comprise to ore deposit pulp tank, to ore deposit pump, double overflow pipe cyclone, sand setting pulp tank, grinding machine, first screening installation and open-circuit grinding grinding machine, described double overflow pipe cyclone is provided with cyclone inlets, sand setting exports, excessive flow export and interior overflow outlet, describedly be connected to the outlet of ore deposit pulp tank with to the import of ore deposit pump, described ore deposit delivery side of pump of giving is connected with cyclone inlets, described sand setting outlet is connected with the import of grinding machine, the outlet of described grinding machine is connected with giving ore deposit pulp tank, described excessive flow export is connected with the import of the first screening installation, described interior overflow outlet is connected with the import of open-circuit grinding grinding machine, the outlet of described open-circuit grinding grinding machine is connected with the import of the first screening installation.
Above-mentioned grinding classification system, preferably, described grinding classification system also comprises the second screening installation, and described interior overflow outlet is also connected with the entrance of the second screening installation, and the mine tailing outlet of described second screening installation is connected with the import of described sand setting pulp tank.
Above-mentioned grinding classification system, preferably, described double overflow pipe cyclone comprises that top is cylindrical shape, bottom is conical cylindrical shell, the top of described cylindrical shell is provided with cover plate, the sidewall of cylindrical shell cylindrical shape part is provided with cyclone inlets, described cyclone inlets near cover plate arrange and importer to tangent with the sidewall of cylindrical shell cylindrical shape part, the bottom centre position of cylindrical shell conical portion is provided with a sand setting outlet; Described cover plate runs through the outer overflow pipe being provided with and stretching into inner barrel, the center of described outer overflow pipe is run through and is provided with interior overflow pipe, and the outlet of described outer overflow pipe is excessive flow export, and the outlet of described interior overflow pipe is interior overflow outlet.
Above-mentioned grinding classification system, preferably, the height that described interior overflow pipe stretches out cover plate is identical with the height that outer overflow pipe stretches out cover plate, and the Way out of interior overflow pipe is contrary with the Way out of outer overflow pipe.
Above-mentioned grinding classification system, preferably, the described interior overflow pipe length stretched in cylindrical shell is greater than outer overflow pipe and stretches into length in cylindrical shell, and the described interior overflow pipe length stretched in cylindrical shell is 60 ~ 90% of barrel lenght.Preferred further, the interior overflow pipe length stretched in cylindrical shell is 70 ~ 85% of barrel lenght.
Above-mentioned grinding classification system, preferably, the diameter of described interior overflow pipe is 60 ~ 90% of described outer overfall tube diameter.Preferred further, the diameter of interior overflow pipe is 70 ~ 80% of described outer overfall tube diameter.
Above-mentioned grinding classification system, preferably, the diameter of described sand setting outlet is 30 ~ 70% of the diameter of outer overflow pipe.Preferred further, described sand setting outlet diameter is 35 ~ 60% of outer overfall tube diameter.Described sand setting outlet diameter is less than common hydrocyclone sand outlet diameter, and its diameter is than common hydrocyclone sand outlet diameter to when young 10%, and preferably little by 20% than common hydrocyclone sand outlet diameter, optimum is 55 ~ 70% of common hydrocyclone sand outlet diameter.
Above-mentioned grinding classification system, preferably, described grinding machine is microfine mining grinding mill, can be ball mill or vertical mill; Described first screening installation is magnetic separator or flotation device; Described open-circuit grinding grinding machine is ball mill or vertical mill; Described second screening installation is weak magnetic separator or fast-flotation machine; Described is Pulp pump to ore deposit pump.Above-mentioned microfine mining grinding mill can be ball mill or vertical mill.
A kind of grind grading method, comprises the following steps:
(1) send into ore deposit pulp tank by iron-bearing mineral ore pulp, pulp density is 20 ~ 45%, then carries out classification with the ore pulp given in the pulp tank of ore deposit being pumped into double overflow pipe cyclone to ore deposit pump, is 0.1 ~ 0.30MPa to the pressure of ore deposit pump;
(2) the sand setting product that obtained by double overflow pipe cyclone classification sends into sand setting pulp tank, then is flow automatically by sand setting pulp tank and send into grinding machine and carry out ore grinding, ore milling product send in step (1) to ore deposit pulp tank;
(3) the excessive miscarriage product that double overflow pipe cyclone classification obtains are sent into the first screening installation and carry out sorting, obtain concentrate product;
(4) double overflow pipe cyclone classification is obtained in overflow product send into open-circuit grinding grinding machine and carry out open-circuit grinding, the excessive miscarriage product of ore milling product and double overflow pipe cyclone merge the first screening installation sent in step (3) and carry out sorting, obtain concentrate product; Or overflow product is sent into the second screening installation and is carried out sorting in being obtained by double overflow pipe cyclone classification, obtain concentrate product, sorting mine tailing is sent into the sand setting pulp tank in step (2) simultaneously, then obtain ore milling product after carrying out ore grinding by grinding machine and send into ore deposit pulp tank.
In above-mentioned steps (1), pulp density more preferably 25 ~ 40%, to the pressure of ore deposit pump more preferably 0.15 ~ 0.25Mpa; Above-mentioned first screening installation and the second screening installation are magnetic separator or flotation device, and when the first screening installation and the second screening installation are magnetic separator, the magnetic field intensity of the second screening installation is 30 ~ 60% of the magnetic field intensity of the first screening installation, are preferably 40 ~ 50%; When the first screening installation and the second screening installation are flotation device, second screening installation collector dosage needed for the first screening installation sorting collector dosage 20 ~ 60%, be preferably 30 ~ 50%, second screening installation flotation time is 15 ~ 60% of the first screening installation flotation time, is preferably 20 ~ 40%.
Above-mentioned grind grading method, preferably, described iron mineral is magnetic iron ore, bloodstone or both composite ore, and described iron-bearing mineral feed preparation unit size accounts for more than 75% for-200 orders, and mog-325 order accounts for more than 80%.
Compared with prior art, the utility model has the advantage of: the grinding classification system that the utility model can control iron mineral derichment adopts double overflow pipe cyclone, ore pulp is after double overflow pipe cyclone classification, dissociated iron mineral and intergrowth of major part particulate enters interior overflow product, discharges grind grading loop.Interior overflow product is primarily of the particulate iron mineral dissociated and a small amount of iron mineral intergrowth composition, the ore grinding intensity required is lower, ore grinding a little is only needed to get final product monomer dissociation, and its narrower particle size distribution, therefore open-circuit grinding can be adopted, reduce ore grinding cost, reduce to have dissociated the overground of iron mineral, improve the rate of recovery of subsequent fine mineral products;
Interior overflow product also directly can carry out magnetic separation or reverse flotation under more weak magnetic field intensity, all can obtain high grade iron concentrate.During magnetic separation, carry out under lower magnetic field intensity, magnetic separation cost can be reduced on the one hand, on the other hand, high-grade iron ore concentrate can be obtained; Time anti-floating, because in interior overflow product, intergrowth content is lower, therefore the dosing such as collecting agent is less, reduce beneficiation cost, simultaneously because the comparatively outer overflow grain graininess of interior overflow grain graininess wants thick, and narrower particle size distribution, can flotation time be shortened, improve the disposal ability of flotation device, and can high grade iron concentrate be obtained.
Therefore, this technology is adopted can greatly to reduce sand setting amount, especially the iron mineral that reduces to have dissociated enters the amount of sand setting, reduce the derichment of iron mineral in sand setting, reduce the overground of iron mineral, reach the object reducing grind grading circuit cycle load, improve grinding machine disposal ability, reduce power consume and raising concentrate product quality.
Accompanying drawing explanation
Fig. 1 is the structural representation that the utility model can control the grinding classification system of iron mineral derichment.
Fig. 2 is the structural representation of double overflow pipe cyclone in grinding classification system.
Marginal data:
1, to ore deposit pulp tank; 2, to ore deposit pump; 3, double overflow pipe cyclone; 31, cyclone inlets; 32, sand setting outlet; 33, excessive flow export; 34, interior overflow outlet; 301, cylindrical shell; 302, outer overflow pipe; 303, interior overflow pipe; 4, sand setting pulp tank; 5, grinding machine; 6, the first screening installation; 7, open-circuit grinding grinding machine; 8, the second screening installation.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the utility model is described in further detail.
As shown in Figure 1, the utility model can control the grinding classification system of iron mineral derichment, comprise to ore deposit pulp tank 1, to ore deposit pump 2, double overflow pipe cyclone 3, sand setting pulp tank 4, grinding machine 5, first screening installation 6 and open-circuit grinding grinding machine 7, double overflow pipe cyclone 3 is provided with cyclone inlets 31, sand setting outlet 32, excessive flow export 33 and interior overflow outlet 34, there is three passages output sand setting respectively, overflow and interior overflow three kinds of graded products, wherein, sand setting product is made up of thick and heavy mineral grain (being generally large iron mineral intergrowth), overflow product is by thin and light mineral grain (being generally dissociate fine grained iron mineral or gangue), interior overflow product is made up of thin and heavy mineral grain (be generally the middle fine iron ore thing that dissociated and in thick iron mineral intergrowth), sand setting product, overflow product and interior overflow product are respectively by sand setting outlet 32, excessive flow export 33 and interior overflow outlet 34 are discharged.Be connected with giving the import of ore deposit pump 2 to the outlet of ore deposit pulp tank 1, be connected with cyclone inlets 31 to the outlet of ore deposit pump 2, sand setting outlet 32 is connected with the import of grinding machine 5, the outlet of grinding machine 5 is connected with giving ore deposit pulp tank 1, excessive flow export 33 is connected with the import of the first screening installation 6, interior overflow outlet 34 is connected with the import of open-circuit grinding grinding machine 7, and the outlet of open-circuit grinding grinding machine 7 is connected with the import of the first screening installation 6.
In the present embodiment, as shown in Figure 2, it is cylindrical shape that double overflow pipe cyclone 3 comprises top, bottom is conical cylindrical shell 301, the top of cylindrical shell 301 is provided with cover plate, the sidewall of cylindrical shell 301 cylindrical shape part is provided with cyclone inlets 31, cyclone inlets 31 near cover plate arrange and importer to tangent with the sidewall of cylindrical shell 301 cylindrical shape part, ore pulp is passed in cylindrical shell 301 along the direction tangent with the inwall of cylindrical shell 301 cylindrical shape part, the sidewall portion of cylindrical shell 301 conical portion is inside gradually by the vertex of a cone, the bottom centre position of cylindrical shell 301 conical portion is provided with a sand setting outlet 32, it is inner that outer overflow pipe 302 inserts cylindrical shell 301 from cover plate, and the outlet of outer overflow pipe 302 is excessive flow export 33, interior overflow pipe 303 is inner through stretching into cylindrical shell 301 from the center of outer overflow pipe 302, and the outlet of interior overflow pipe 303 is interior overflow outlet 34.This double overflow pipe cyclone 3 adds an overflow pipe at the cyclone outlet of routine, and reduces sand setting and export 32 sizes.After improving, double overflow pipe cyclone 3 operation principle is roughly similar to conventional cyclone, carefully and gently the particle of (thinner iron mineral and intergrowth, gangue particle) mainly enters into internal layer spiral flow by fluid drag effect in cylindrical shell 301 cylindrical shape part, and discharge through outer overflow pipe 302, become excessive miscarriage product; Slightly weigh (coarse-particle iron ore thing and intergrowth), carefully weigh (the particulate iron mineral dissociated and intergrowth, coarse granule gangue) particle flow to into the timesharing of cylindrical shell 301 conical portion with outer, intermediate conveyor screw, it is little compared with conventional cyclone sand setting outlet size that sand setting due to double overflow pipe cyclone 3 exports 32 sizes, there is particle aggregation and then form hindered falling, ore pulp particle is restricted by sand setting outlet 32, thick and heavy iron mineral and the main gravitate of intergrowth, export 32 by sand setting fast to discharge, become sand setting product; And the insertion of interior overflow pipe 303, distance between the barrel shortening interior overflow pipe 303 and cylindrical shell 301 conical portion, move distance on its vertical direction is greatly reduced, thin and heavy iron mineral and intergrowth are trapped within the upwelling of center, enter overflow product in interior overflow pipe 303 output.
The height that above-mentioned interior overflow pipe 303 stretches out top blind flange is identical with the height that outer overflow pipe 302 stretches out top blind flange, and the Way out of interior overflow pipe 303 is contrary with the Way out of outer overflow pipe 302.
The length that above-mentioned interior overflow pipe 303 inserts cylindrical shell 301 is longer than the length inserting cylindrical shell 301 for outer overflow pipe 302, is 80% of cylindrical shell 301 length.
The diameter of above-mentioned interior overflow pipe 303 is 75% of above-mentioned outer overflow pipe 302 diameter.
The diameter of above-mentioned sand setting outlet 32 is 30 ~ 70% of the diameter of outer overflow pipe 302.It is less than common hydrocyclone sand outlet diameter that this sand setting exports 32 diameters, is 70% of common hydrocyclone sand outlet diameter.
The double overflow pipe cyclone 3 that the utility model adopts adds an overflow pipe at the cyclone outlet of routine, and reduces sand setting outlet size.Double overflow pipe cyclone operation principle is roughly similar to conventional cyclone, carefully and gently the particle of (thinner iron mineral and intergrowth, gangue particle) mainly enters into internal layer spiral flow by fluid drag effect in cylindrical shape part, and discharge through outer overflow pipe, become excessive miscarriage product; Slightly weigh (coarse-particle iron ore thing and intergrowth), carefully weigh (the particulate iron mineral dissociated and intergrowth, coarse granule gangue) particle when flowing to into conical section with outer, intermediate conveyor screw, because double overflow pipe hydrocyclone sand outlet size is little compared with conventional cyclone sand setting outlet size, there is particle aggregation and then form hindered falling, ore pulp particle is restricted by sand setting outlet, thick and heavy iron mineral and the main gravitate of intergrowth, exported by sand setting fast and discharge, become sand setting product; And the insertion of interior overflow pipe, shorten the distance between interior overflow pipe and conical barrel, the move distance on its vertical direction is greatly reduced, thin and heavy iron mineral and intergrowth are trapped within the upwelling of center, enter overflow product in interior overflow pipe output.
In the present embodiment, grinding classification system also comprises the second screening installation 8, interior overflow outlet 34 is also connected with the entrance of the second screening installation 8, the mine tailing outlet of the second screening installation 8 is connected with the import of sand setting pulp tank 4, interior overflow product can be selected further to be passed in the second screening installation 8 carry out sorting, concentrate after sorting is product concentrate, and sorting mine tailing enters sand setting pulp tank 4 and carries out further ore grinding, and ore milling product enters to ore deposit pulp tank 1 again.
In the present embodiment, grinding machine 5 is ball mill or vertical mill, and the first screening installation 6 is magnetic separator or flotation device, and open-circuit grinding grinding machine 7 is ball mill or vertical mill, and the second screening installation 8 is weak magnetic separator or fast-flotation machine, is Pulp pump to ore deposit pump 2.
During ore grinding, ore pulp is sent into in ore deposit pulp tank 1; Start and carry out classification to ore deposit pump 2 by pumping in double overflow pipe cyclone 3 to the ore pulp in ore deposit pulp tank 1; Sand setting product after the classification of double overflow pipe cyclone 3 enters sand setting pulp tank 4 through sand setting outlet 32, and then enter grinding machine 5 by sand setting pulp tank 4 outlet and carry out grinding operation, ore milling product enters to ore deposit pulp tank 1 again; The overflow product of double overflow pipe cyclone 3 enters the first screening installation 6 through excessive flow export 33 and carries out sorting, obtains concentrate product; The interior overflow product of double overflow pipe cyclone 3 flows out through interior overflow outlet 34, can select that interior overflow product is passed into open-circuit grinding grinding machine 7 and carry out open-circuit grinding, ore milling product enters the first screening installation 6 again to carry out sorting and obtains concentrate product, or interior overflow product is passed into the second screening installation 8 and carries out sorting, divide concentrate selection to be product concentrate, sorting mine tailing enters sand setting pulp tank 4 and carries out further ore grinding.
In the present embodiment, ore pulp is after the classification of double overflow pipe cyclone 3, and dissociated iron mineral and intergrowth of most of particulate enters interior overflow product, discharges grind grading loop.Interior overflow product is primarily of the particulate iron mineral dissociated and a small amount of iron mineral intergrowth composition, the ore grinding intensity required is lower, ore grinding a little is only needed to get final product monomer dissociation, and its narrower particle size distribution, therefore open-circuit grinding can be adopted, reduce ore grinding cost, reduce to have dissociated the overground of iron mineral, improve the rate of recovery of subsequent fine mineral products.
Interior overflow product also directly can carry out magnetic separation or reverse flotation, all can obtain high grade iron concentrate.During magnetic separation, carry out under lower magnetic field intensity, magnetic separation cost can be reduced on the one hand, on the other hand, high-grade iron ore concentrate can be obtained; During reverse flotation, because in interior overflow product, intergrowth content is lower, therefore the dosing such as collecting agent is less, reduce beneficiation cost, simultaneously because the comparatively outer overflow grain graininess of interior overflow grain graininess wants thick, and narrower particle size distribution, can flotation time be shortened, improve the disposal ability of flotation device, and can high grade iron concentrate be obtained.Sorting mine tailing enters the further ore grinding of closed circuit grinding grinding machine through pulp tank.
Grinding classification system of the present utility model is adopted double overflow pipe cyclone 3 to be separated by interior overflow thin and heavy suite and processes separately, sand setting amount can be reduced like this, especially the iron mineral that reduces to have dissociated enters the amount of sand setting, reduce the derichment of iron mineral in sand setting, reduce the overground of iron mineral, reach the object reducing grind grading circuit cycle load, improve grinding machine disposal ability, reduce power consume and raising concentrate product quality.
Control a grind grading method for iron mineral derichment, comprise the following steps:
(1) iron-bearing mineral ore pulp granularity-200 order being accounted for more than 75% is sent into ore deposit pulp tank 1, keep pulp density 20% ~ 45%, carrying out classification with the ore pulp given in ore deposit pulp tank 1 being pumped into double overflow pipe cyclone 3 to ore deposit pump 2 again, keeping to ore deposit pump 2 pressure 0.10 ~ 0.30MPa;
(2) the sand setting product that the classification of double overflow pipe cyclone 3 obtained sends into sand setting pulp tank 4, then is flow automatically by sand setting pulp tank 4 and send into grinding machine 5 and carry out ore grinding, ore milling product send in step (1) to ore deposit pulp tank 1; Grinding machine 5 can be ball mill or vertical mill, and when adopting ball mill to carry out ore grinding, ball mill can be overflowball mill or extended type ball mill, extended type ball mill draw ratio 2.0 ~ 3.5, and ore milling concentration is 60 ~ 80%.Milling medium is the steel section of diameter phi 15 ~ 50mm, and steel section loading is 20 ~ 40% of ball mill barrel volume; When adopting vertical mill to carry out ore grinding, ore milling concentration is 45 ~ 70%, and milling medium is the steel ball of diameter phi 5 ~ 30mm, and steel ball filling rate is 40 ~ 60%;
(3) classification of double overflow pipe cyclone 3 being obtained granularity is that excessive miscarriage product that-325 orders account for more than 80% are sent into the first screening installation 6 and carried out sorting, obtains concentrate product; The performance of the first screening installation 6 device category and operating parameter foundation grind grading material adopts conventional magnetic separation or flotation sorting process;
(4) classification of double overflow pipe cyclone 3 is obtained in overflow product send into open-circuit grinding grinding machine 7 and carry out open-circuit grinding, open-circuit grinding grinding machine adopts vertical mill, ore pulp feeds grinding machine from bottom, and discharge from grinding machine top, open-circuit grinding mortar retention time is short compared with grinding machine 5 time of staying.After the excessive miscarriage product of open-circuit grinding product and double overflow pipe cyclone 3 merge, the first screening installation 6 sent in step (3) carries out sorting, obtains concentrate product; Or overflow product is sent into the second screening installation 8 and is carried out sorting in the classification of double overflow pipe cyclone 3 being obtained, obtain concentrate product, sorting mine tailing is sent into the sand setting pulp tank 4 in step (2) simultaneously, then obtain ore milling product after carrying out ore grinding by grinding machine 5 and send into ore deposit pulp tank 1.Second screening installation 8 type is identical with the first screening installation 6, when first screening installation 6 is magnetic separator, second screening installation 8 is also magnetic separator, but carries out under being sorted on more weak magnetic field intensity, and the magnetic field intensity of the second screening installation 8 is 30 ~ 60% of the first screening installation 6 magnetic field intensity; When first screening installation 6 is flotation device, the second screening installation 8 is also flotation device, collector dosage needed for the first screening installation 6 sorting collector dosage 20 ~ 60%, flotation time is 15 ~ 60% of the first screening installation 6 flotation time.
In the present embodiment, outward, go back the output interior overflow product of 20.7%, the graded index of double overflow pipe cyclone 3 is as shown in table 2 for double overflow pipe cyclone 3 output similar conventional cyclone sand setting and overflow product (excessive miscarriage product).Interior overflow product is regrinded through open-circuit grinding and is entered the first screening installation 6 sorting or directly enter the second screening installation 8 sorting and excessively flow to that to carry out the mineral processing index of sorting into the first screening installation 6 as shown in table 3.Entering the first screening installation 6 with conventional cyclone overflow carries out compared with the mineral processing index of sorting, and concentrate yield, grade, the rate of recovery are all significantly improved.And the grind grading sorting process adopting double overflow pipe cyclone to carry out classification to need to return amount that grinding machine carries out ore grinding also little than adopting conventional cyclone to carry out the amount of grind grading sorting process, namely reduce the energy consumption of ore grinding, specifically contrast in table 4.
Table 2 double overflow pipe cyclone classification index
Table 3 mineral processing index
Table 4 ore grinding amount
The above is only preferred embodiment of the present utility model, and protection domain of the present utility model is also not only confined to above-described embodiment.For those skilled in the art, do not departing from the improvement that obtains under the utility model technical conceive prerequisite and conversion also should be considered as protection domain of the present utility model.

Claims (8)

1. one kind can control the grinding classification system of iron mineral derichment, it is characterized in that: comprise to ore deposit pulp tank (1), to ore deposit pump (2), double overflow pipe cyclone (3), sand setting pulp tank (4), grinding machine (5), first screening installation (6) and open-circuit grinding grinding machine (7), described double overflow pipe cyclone (3) is provided with cyclone inlets (31), sand setting outlet (32), excessive flow export (33) and interior overflow outlet (34), describedly be connected to the outlet of ore deposit pulp tank (1) with to the import of ore deposit pump (2), the described outlet to ore deposit pump (2) is connected with cyclone inlets (31), described sand setting outlet (32) is connected with the import of grinding machine (5), the outlet of described grinding machine (5) is connected with giving ore deposit pulp tank (1), described excessive flow export (33) is connected with the import of the first screening installation (6), described interior overflow outlet (34) is connected with the import of open-circuit grinding grinding machine (7), the outlet of described open-circuit grinding grinding machine (7) is connected with the import of the first screening installation (6).
2. grinding classification system according to claim 1, it is characterized in that: described grinding classification system also comprises the second screening installation (8), described interior overflow outlet (34) is also connected with the entrance of the second screening installation (8), and the mine tailing outlet of described second screening installation (8) is connected with the import of described sand setting pulp tank (4).
3. grinding classification system according to claim 1, it is characterized in that: described double overflow pipe cyclone (3) comprises that top is cylindrical shape, bottom is conical cylindrical shell (301), the top of described cylindrical shell (301) is provided with cover plate, the sidewall of cylindrical shell (301) cylindrical shape part is provided with cyclone inlets (31), described cyclone inlets (31) near cover plate arrange and importer to tangent with the sidewall of cylindrical shell (301) cylindrical shape part, the bottom centre position of cylindrical shell (301) conical portion is provided with sand setting outlet (32); Described cover plate runs through be provided with and stretch into the inner outer overflow pipe (302) of cylindrical shell (301), the center of described outer overflow pipe (302) is run through and is provided with interior overflow pipe (303), the outlet of described outer overflow pipe (302) is excessive flow export (33), and the outlet of described interior overflow pipe (303) is interior overflow outlet (34).
4. grinding classification system according to claim 3, it is characterized in that: the height that described interior overflow pipe (303) stretches out cover plate is identical with the height that outer overflow pipe (302) stretches out cover plate, and the Way out of interior overflow pipe (303) is contrary with the Way out of outer overflow pipe (302).
5. grinding classification system according to claim 3, it is characterized in that: described interior overflow pipe (303) length stretched in cylindrical shell (301) is greater than outer overflow pipe (302) and stretches into length in cylindrical shell (301), and described interior overflow pipe (303) length stretched in cylindrical shell (301) is 60 ~ 90% of cylindrical shell (301) length.
6. grinding classification system according to claim 3, is characterized in that: the diameter of described interior overflow pipe (303) is 60 ~ 90% of described outer overflow pipe (302) diameter.
7. grinding classification system according to claim 3, is characterized in that: the diameter of described sand setting outlet (32) is 30 ~ 70% of the diameter of outer overflow pipe (302).
8. grinding classification system according to claim 2, is characterized in that: described grinding machine (5) is microfine mining grinding mill; Described first screening installation (6) is magnetic separator or flotation device; Described open-circuit grinding grinding machine (7) is ball mill or vertical mill; Described second screening installation (8) is weak magnetic separator or fast-flotation machine; Described is Pulp pump to ore deposit pump (2).
CN201520676206.6U 2015-09-02 2015-09-02 Grind grading system of steerable iron mineral derichment Withdrawn - After Issue CN204953074U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520676206.6U CN204953074U (en) 2015-09-02 2015-09-02 Grind grading system of steerable iron mineral derichment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520676206.6U CN204953074U (en) 2015-09-02 2015-09-02 Grind grading system of steerable iron mineral derichment

Publications (1)

Publication Number Publication Date
CN204953074U true CN204953074U (en) 2016-01-13

Family

ID=55048172

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520676206.6U Withdrawn - After Issue CN204953074U (en) 2015-09-02 2015-09-02 Grind grading system of steerable iron mineral derichment

Country Status (1)

Country Link
CN (1) CN204953074U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105170283A (en) * 2015-09-02 2015-12-23 长沙矿冶研究院有限责任公司 Ore grinding grading system and method capable of controlling derichment of iron minerals
CN114345540A (en) * 2021-12-09 2022-04-15 玉溪大红山矿业有限公司 Low-grade hematite rough concentrate recleaning process

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105170283A (en) * 2015-09-02 2015-12-23 长沙矿冶研究院有限责任公司 Ore grinding grading system and method capable of controlling derichment of iron minerals
CN114345540A (en) * 2021-12-09 2022-04-15 玉溪大红山矿业有限公司 Low-grade hematite rough concentrate recleaning process
CN114345540B (en) * 2021-12-09 2024-05-10 玉溪大红山矿业有限公司 Low-grade hematite rough concentrate recleaning process

Similar Documents

Publication Publication Date Title
CN102430481B (en) Sorting process for high-ash and difficult-separation coal slime
CN104888959B (en) Quality-improving impurity-reducing beneficiation method for ferromagnetic minerals
CN104607296B (en) Ilmenite beneficiation method and equipment
CN104888960B (en) The magnetic of the red composite ore of fine grain teeth cloth magnetic floats sorting process
CN206139326U (en) Ultralow grade vanadium titano -magnetite uses multipurposely system
CN103611623A (en) Process method for hematite dressing to increase gravity concentrate yield
CN108816497B (en) Magnetite beneficiation process
CN105251572A (en) Novel ore grinding classification system and process
CN105536984A (en) Magnetic separation method with both preselection tailing throwing and thick-fine separation and three-product magnetic separator
CN107115959A (en) The method that packed in gangue micro-fine-grained gold in mine tailing is reclaimed with Nelson's gravitational separation equipment
CN105170283B (en) The grinding classification system and method for a kind of controllable iron mineral derichment
CN109201354A (en) MAGNETIC HYDROCYCLONES, magnetic reconnection conjunction separation system and the magnetic reconnection selected for weak magnetic mineral closes the method sorted
CN204672415U (en) Ilmenite combined classification separation system
CN204953074U (en) Grind grading system of steerable iron mineral derichment
CN106378256B (en) A kind of upgrading drop silicon method of the poor ferromagnetic concentrate of mixed type
CN103041911B (en) Quality classifying and grading process for mineral separation and grinding
CN100563838C (en) Mine tailing reclaims sulphur iron separation ore-sorting system and method
CN205361641U (en) It throws tail and thickness three hierarchical product magnet separators to have preliminary election concurrently
CN206304893U (en) A kind of sorting unit of the red mixed type iron ore weakly magnetic tailingses of magnetic
CN210207202U (en) System for collophanite pre-grading, ore grinding grading and separate flotation combined process
CN108927281A (en) A kind of gold mine grinding classification system and grind grading treatment process
CN207169971U (en) A kind of fine graded special hydrocyclone of magnetizing roast
CN218222794U (en) Ore dressing system
CN208161808U (en) A kind of gold mine grinding classification system
CN208018787U (en) A kind of efficient magnetic force classification machine

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20160113

Effective date of abandoning: 20170908

AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20160113

Effective date of abandoning: 20170929

AV01 Patent right actively abandoned