CN204089350U - The electric emergency treatment device of circuit breaker - Google Patents
The electric emergency treatment device of circuit breaker Download PDFInfo
- Publication number
- CN204089350U CN204089350U CN201420578614.3U CN201420578614U CN204089350U CN 204089350 U CN204089350 U CN 204089350U CN 201420578614 U CN201420578614 U CN 201420578614U CN 204089350 U CN204089350 U CN 204089350U
- Authority
- CN
- China
- Prior art keywords
- time delay
- circuit breaker
- relay
- binding posts
- utility
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000013461 design Methods 0.000 abstract description 2
- 238000012423 maintenance Methods 0.000 description 6
- 230000001681 protective effect Effects 0.000 description 4
- 238000007689 inspection Methods 0.000 description 3
- 238000004891 communication Methods 0.000 description 2
- 230000003247 decreasing effect Effects 0.000 description 2
- 238000002955 isolation Methods 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 238000004458 analytical method Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000005265 energy consumption Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000009191 jumping Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
Landscapes
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Abstract
The utility model discloses the electric emergency treatment device of a kind of circuit breaker, comprise power supply, circuit breaker, time delay return relay, time delay exit relay, the fast switch-dividing of DC bipolar and some binding posts, time delay return relay is connected with power supply via two binding posts by the fast switch-dividing of DC bipolar again; The normally closed switch of time delay return relay is connected with the coil of time delay exit relay, and the normal open switch of time delay exit relay is also connected with circuit breaker by two binding posts.The utility model patching operations is easy, and general operations staff all can operate safely and fast, and device action reliability is high simultaneously, course of action is clear, control loop design brief and practical.The utility model can excise the faulty equipment that protection supervisory equipment damage or circuit breaker trip coil or control loop damage in shorter time, has good actual application value.
Description
Technical field
The utility model relates to the electric emergency treatment device of a kind of circuit breaker.
Background technology
At present, due to the protection supervisory equipment of circuit breaker damage after namely lose remote operation function, after the control loop of circuit breaker internal or component wear (as point, closing coil damages, auxiliary contact is obstructed) make circuit breaker lose electric operating function on the spot.When protection, observing and controlling, communication device or breaking coil damage, cause circuit breaker can not remote operation, bring larger security risk to personnel and equipment.Sometimes even needing has a power failure whole section of bus just can process, and adds grid switching operation task and operational risk.If generating region internal short-circuit fault, may cause overstep tripping accident when circuit breaker failure, bring not little pressure to electric power netting safe running and quality supply service.
Utility model content
The purpose of this utility model is to provide a kind of after circuit breaker loses remote operation function or local operation function, can carry out the electric emergency treatment device of circuit breaker that electric automatic operation realizes excision load fast to circuit breaker.
The electric emergency treatment device of this circuit breaker that the utility model provides, comprise power supply, circuit breaker, time delay return relay, time delay exit relay, the fast switch-dividing of DC bipolar and some binding posts, time delay return relay is connected with power supply via two binding posts by the fast switch-dividing of DC bipolar again, and these two binding posts are power input; The normally closed switch of time delay return relay is connected with the coil of time delay exit relay, and the normal open switch of time delay exit relay is also connected with circuit breaker by two binding posts, and these two binding posts are time delay output.
This device also comprises signal lamp, and the series circuit that signal lamp and the normal open switch of time delay return relay form is connected between the two ends be not connected with power supply of the fast switch-dividing of DC bipolar.
Described time delay return relay and described time delay exit relay all adopt the time relay, and its delay time all can be arranged and adjustment, and the delay adjustments value of time delay return relay is greater than the delay adjustments value of time delay exit relay.
Described power acquisition DC control supply in described circuit breaker control cabinet.
The utility model patching operations is easy, and general operations staff all can operate safely and fast, and device action reliability is high simultaneously, course of action is clear, control loop design brief and practical.The utility model can excise the faulty equipment that protection supervisory equipment damage or circuit breaker trip coil or control loop damage in shorter time, has good actual application value.Application of the present utility model makes circuit breaker unprotect running time and failure operation time significantly reduce, and makes electrical network, the security reliability of equipment obtains effective raising.The use of the utility model when breaker open operation fault simultaneously avoids the execute-in-place of personnel, effectively protects the safety of operation and repair and maintenance personnel, plays a good role to raising fortune inspection safety in production level.
Accompanying drawing explanation
Fig. 1 is principle schematic of the present utility model.
Fig. 2 is a kind of execution mode control drawing of the present utility model.
Embodiment
Damage at protection supervisory equipment or communication device; circuit breaker is made to lose remote operation function; but when circuit breaker self control loop is intact, according to the principle of electric automatic operation, the utility model realizes controlling the automatic trip of circuit breaker by its external electric loop.
The utility model solves after circuit breaker loses behaviour far away or local operation function, realizes excising load fast to the electric automatic operation of circuit breaker, realizes circuit breaker on-load operation problem on the spot.
Application scenario of the present utility model is two second part at transformer.
As shown in Figure 1, the utility model comprises power supply, circuit breaker, time delay return relay, time delay exit relay, the fast switch-dividing of DC bipolar and some binding posts.Time delay return relay is connected with power supply via two binding posts by the fast switch-dividing of DC bipolar again, and these two binding posts are power input; The normally closed switch of time delay return relay is connected with the coil of time delay exit relay, and the normal open switch of time delay exit relay is also connected with circuit breaker by two binding posts, and these two binding posts are time delay output.
The utility model also comprises signal lamp, and the series circuit that signal lamp and the normal open switch of time delay return relay form is connected between the two ends be not connected with power supply of the fast switch-dividing of DC bipolar.
As shown in Figure 2, the utility model comprises time delay return relay SJ1, time delay exit relay SJ2, signal lamp XD, the fast switch-dividing DK of DC bipolar, binding post JXZ1, binding post JXZ2, binding post JXZ3, binding post JXZ4, protective resistance R, circuit breaker and power supply.
The utility model comprises time delay involution start-up circuit, time delay outlet start-up circuit, device working indicating and time delay outlet trip circuit.Time delay involution start-up circuit is composed in series by the coil of time delay return relay SJ1 and protective resistance R.Time delay outlet start-up circuit is composed in series by the coil of time delay exit relay SJ2 and the normally closed switch of time delay return relay SJ1.Device working indicating is composed in series by the normal open switch of signal lamp XD and time delay return relay SJ1.Time delay outlet trip circuit is composed in series via binding post JXZ3 and circuit breaker by the normally closed switch of time delay exit relay SJ2.
Binding post JXZ1 is connected between No. 1 switch of power positive end and the fast switch-dividing DK of DC bipolar, and binding post JXZ2 is connected between No. 2 switches of power supply negative terminal-KM and the fast switch-dividing DK of DC bipolar.No. 2 switches of the fast switch-dividing DK of DC bipolar are connected between binding post JXZ2 and binding post JXZ4.Time delay involution start-up circuit, time delay are connected to after exporting start-up circuit, device working indicating three parallel connection between No. 1 switch of binding post JXZ4 and the fast switch-dividing DK of DC bipolar.Time delay outlet trip circuit is connected between binding post JXZ4 and power supply negative terminal-KM.
In Power Selection, the utility model adopts DC control supply in breaker cabinet, in order to avoid introduce interference, it is wired that coincidence circuit connects use, avoids radio to interference of the present utility model.The utility model only need access two direct current supply lines and (conjunction) brake cable is jumped in an outlet, can realize the electric emergency operation to circuit breaker.
Time delay return relay and time delay exit relay all can adopt the time relay.The utility model freely can arrange outlet operate time (as shown in time delay exit relay SJ2 in Fig. 2), can be set according to distance the suitable time, convenient operation personnel evacuate to safety zone, this device is also provided with the adjustable auto-returned time (as shown in time delay return relay SJ1 in Fig. 2) simultaneously, in order to avoid circuit breaker can not burn out circuit breaker jumping (conjunction) brake cable coil element during correct operation.The delay time of these two relays all can carry out arranging and adjust, but needs the delay adjustments value guaranteeing time delay return relay to be greater than the delay adjustments value of time delay exit relay, in order to avoid device failure.
Indicator light in electric operation loop of the present utility model, not only can the input of Monitor and Control power supply whether normal, also can judgment means element manipulation whether normal.
Use of the present utility model can excise the faulty equipment that protection supervisory equipment damage or circuit breaker trip coil or control loop damage in shorter time, has good actual application value.
(1) safety benefit.Application of the present utility model reduces about 70% before circuit breaker unprotect running time and failure operation time are comparatively used, and makes electrical network, the security reliability of equipment obtains effective raising.
The use of this emergency treatment device when breaker open operation fault simultaneously avoids the execute-in-place of personnel, effectively protects the safety of operation and repair and maintenance personnel, plays a good role to raising fortune inspection safety in production level.
(2) management benefit.Device fails can not telemechanical or on the spot electric operating time, according to the analysis to real work flow process, need the processing time of 2 to 4 hours; Use after the utility model, at most only need the isolation that can realize for 30 minutes faulty equipment, greatly reduce equipment fault running time.After a failure on grid switching operation; after use the utility model; there is interconnected breaker operator time decreased 76.2%; without interconnected breaker operator time decreased 71.7%, significantly decrease equipment unprotect running time, effectively prevent the generation of accident of bypassing the immediate leadership; improve the security reliability of electrical network; ensure that and the fast and reliable of user is powered, improve the power supply quality of company, achieve the promise to social good service.
Application of the present utility model also can impel the management development of fortune inspection lean.With the statistics of certain electric company's substation equipment maintenance and repair room for certificate, the protective device and the breaking coil that within 2013, affect breaker operator damage 52 times for example, originally during needs 39 × 6 people/platform × 2.1 during+13 x6 people/platform x3.6=772 people time, when needing 39 × 2 people/platform × 0.52 after the use by substation breakers emergency treatment device during+13 x2 people/platform x1.06=68 people time; When reducing by 704 people, increase work efficiency 91.19%.To in the isolation of fault, the Efficiency of Switching Operation promotes more than 70%.Strong lifting company fortune is examined lean managerial skills after promoting the use of by the utility model.
(3) economic benefit.The raising of operating efficiency significantly can promote company's operating maintenance benefit, also with above-mentioned electric company's substation equipment maintenance and repair room in the past statistics for certificate, the protective device and the breaking coil that affect breaker operator damage 52 times for example, with reference to 2013 Nian Mou city energy consumption per person 33662 yuan of calculating, when can save human cost 33662 yuan/people/(250 day * 8 times/sky) * 704 people/1588 * 3564=26593 yuan; Take and loss 300 yuan/time for vehicle oil, vehicle cost 300 yuan/platform * 52/1588 * 3564=35011 yuan can be saved; The annual circuit breaker of this electric company safeguards that reducing cost subtotal is 26593 yuan+35011 yuan=61604 yuan.As promoted the use of the whole province at this place, city, this province 10kV circuit breaker amounts to 19,316 ten thousand at present, then estimate to save maintenance cost 19,316 ten thousand/3564 * 61604 yuan=33.4 ten thousand yuan every year.
Claims (4)
1. the electric emergency treatment device of circuit breaker, comprise power supply and circuit breaker, it is characterized in that, this device also comprises time delay return relay, time delay exit relay, the fast switch-dividing of DC bipolar and some binding posts, time delay return relay is connected with power supply via two binding posts by the fast switch-dividing of DC bipolar again, and these two binding posts are power input; The normally closed switch of time delay return relay is connected with the coil of time delay exit relay, and the normal open switch of time delay exit relay is also connected with circuit breaker by two binding posts, and these two binding posts are time delay output.
2. the electric emergency treatment device of circuit breaker according to claim 1, it is characterized in that, this device also comprises signal lamp, and the series circuit that signal lamp and the normal open switch of time delay return relay form is connected between the two ends be not connected with power supply of the fast switch-dividing of DC bipolar.
3. the electric emergency treatment device of circuit breaker according to claim 1, it is characterized in that, described time delay return relay and described time delay exit relay all adopt the time relay, its delay time all can be arranged and adjustment, and the delay adjustments value of time delay return relay is greater than the delay adjustments value of time delay exit relay.
4. the electric emergency treatment device of circuit breaker according to claim 1, is characterized in that, described power acquisition DC control supply in described circuit breaker control cabinet.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420578614.3U CN204089350U (en) | 2014-10-09 | 2014-10-09 | The electric emergency treatment device of circuit breaker |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420578614.3U CN204089350U (en) | 2014-10-09 | 2014-10-09 | The electric emergency treatment device of circuit breaker |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204089350U true CN204089350U (en) | 2015-01-07 |
Family
ID=52182021
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420578614.3U Expired - Fee Related CN204089350U (en) | 2014-10-09 | 2014-10-09 | The electric emergency treatment device of circuit breaker |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204089350U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106130182A (en) * | 2016-07-07 | 2016-11-16 | 广州普瑞电力控制系统设备有限公司 | Switch local operation safety device |
CN106451749A (en) * | 2016-11-21 | 2017-02-22 | 铁道第三勘察设计院集团有限公司 | Emergency protection device and method under malfunctioning condition of traction substation control protection system |
-
2014
- 2014-10-09 CN CN201420578614.3U patent/CN204089350U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106130182A (en) * | 2016-07-07 | 2016-11-16 | 广州普瑞电力控制系统设备有限公司 | Switch local operation safety device |
CN106451749A (en) * | 2016-11-21 | 2017-02-22 | 铁道第三勘察设计院集团有限公司 | Emergency protection device and method under malfunctioning condition of traction substation control protection system |
CN106451749B (en) * | 2016-11-21 | 2023-08-18 | 中国铁路设计集团有限公司 | Emergency protection device and protection method for traction substation control protection system under abnormal working condition |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103236737B (en) | A kind of Domestic intelligent distribution box | |
CN204481568U (en) | A kind of power plant is standby throws protective device | |
CN102447298B (en) | Mobile intelligent direct current power supply device | |
CN206575222U (en) | Waste-to-energy plant low pressure emergency security power system | |
CN204089350U (en) | The electric emergency treatment device of circuit breaker | |
CN106451749B (en) | Emergency protection device and protection method for traction substation control protection system under abnormal working condition | |
CN201725007U (en) | Portable power frequency insulation test device with functions of voltage waveform analysis and filtration | |
CN202748425U (en) | Residual current protection uninterrupted testing device | |
CN105551842B (en) | A kind of method and device preventing breaker energy storage motor failure | |
CN205123236U (en) | Distribution lines protection device | |
CN204144158U (en) | Circuit breaker emergency treatment device | |
CN102938558A (en) | Low-voltage distribution system with leakage protection device | |
CN207518284U (en) | A kind of accident disconnection device of small power incorporating into power network | |
CN202721433U (en) | Leakage protection and power supply recovery apparatus | |
CN204303227U (en) | Body sense real training formula Intelligent electric leakage protection system | |
CN201757073U (en) | Safe & intelligent type explosionproof air blower electric control box | |
CN203039356U (en) | 10kV inlet wire protection monitoring device | |
CN202906451U (en) | Low-voltage distribution system with electrical leakage protection apparatus | |
CN208508525U (en) | A kind of grid-connected power generation system arc light protecting device | |
CN204441871U (en) | A kind of portable route protection dolly | |
CN103532093A (en) | Leakage protector capable of monitoring | |
CN206076925U (en) | Secondary circuit of transformer protection interlocking cutting generator matched line | |
CN201556935U (en) | Automatic control aftercurrent protector | |
CN204633303U (en) | A kind of rural power grids that are used for leak electricity intelligent coincidence arrangement for radio area | |
CN204179984U (en) | A kind of three-phase power supply phase sequence detects and automatic conversioning controling circuit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |