CN1908969B CN200510084594XA CN200510084594A CN1908969B CN 1908969 B CN1908969 B CN 1908969B CN 200510084594X A CN200510084594X A CN 200510084594XA CN 200510084594 A CN200510084594 A CN 200510084594A CN 1908969 B CN1908969 B CN 1908969B
Authority
CN
China
Prior art keywords
data
project
module
remote job
function service
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200510084594XA
Other languages
Chinese (zh)
Other versions
CN1908969A (en
Inventor
简荣茂
吴振声
张敏雄
陈玫慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Industrial Technology Research Institute ITRI
Original Assignee
Industrial Technology Research Institute ITRI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Industrial Technology Research Institute ITRI filed Critical Industrial Technology Research Institute ITRI
Priority to CN200510084594XA priority Critical patent/CN1908969B/en
Publication of CN1908969A publication Critical patent/CN1908969A/en
Application granted granted Critical
Publication of CN1908969B publication Critical patent/CN1908969B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Telephonic Communication Services (AREA)

Abstract

The engineering data variation management method for remote operation field comprises: (i) building service database for operation field; (ii) by user electric device with real-time camera unit, extracting image data for the doubtable variation; (iii) by the on-line browse module in the device, connecting to an information service platform and its function entrance assembly, then connecting to service module to create topic to be processing, or sending directly by an on-line transmission module; (iv) modifying scheduled data.

Description

Remote job field engineering data change method of control and system thereof
Technical field
The present invention relates to a kind of operation field project data change method of control and system thereof, particularly a kind of management remote job scene, the project data that can shorten engineer operation time-histories, reduction engineering cost changes method of control and system thereof.
Background technology
Because remote scene operations such as engineering construction, assembling, test, in encountering problems or during change in the work, usually can't find relevant information in real time, also can't feedback problem in real time in project manager or project planning personnel, common engineering personnel leave the Hard copy record, but too late because of artificial careless mistake or timeliness, make facility change etc. can't reach real-time; In addition, engineering build put finish after, the Entity Change that the part facility is done, normal and initial planning data (as map file, project data etc.) is drop to some extent, not only influence operation quality,, the shortcoming of wasting man-hour, lowering efficiency, raising the cost is also arranged if remedy or construction again; If can implement the feedback and the inquiry of project data easily, can shorten the activity duration, and guarantee that the facility Entity Change is consistent with the project data of planning, and reduce engineering cost by a method.
See also Taiwan patent announcement No. 580633 " change in the work data maintaining method and system " and No. the 591463rd, Taiwan patent announcement " project engineering control-management system and method thereof ", it all discloses central management and control unit, file management unit and carries out this document administrative unit by network system; But actual job is noted down with Hard copy by the operating personnel, wait to get back to and inform the project manager in company or the system again, change processing by the project manager project planning personnel that plan as a whole to pass on again, these multiple field way to manages often cause delay and the initial planning that the facility change handles and finish the thing that data are not inconsistent; In addition, aforementioned techniques all is applied to enterprises, and works in coordination between manufacturer in conjunction with; Moreover all persons of logining of aforementioned techniques all use the same operation function, and can't provide required function according to user's authority; Further, aforementioned techniques all uses interface must adopt the use interface of customization because of user's device is different, and produces the extra cost burden.
In view of this, the inventor proposes a kind of design to address the above problem.
Summary of the invention
The invention provides a kind of remote job field engineering data change method of control and system thereof, realtime graphic can be provided, solve the engineering data management problem at remote job scene, to shorten the engineer operation time-histories, to reduce engineering cost.
The invention provides a kind of remote job field engineering data change method of control and system thereof, can be applicable to enterprise itself or the further cooperation between manufacturer in conjunction with.
The invention provides a kind of remote job field engineering data change method of control and system thereof, can operate difference in functionality according to user's authority.
The invention provides a kind of remote job field engineering data change method of control and system thereof, the use interface that can customize can be operated with the browser of the existing employing of user.
The invention provides a kind of remote job field engineering data change method of control and system thereof, the engineering staff can pending subject under discussion of feedback engineering in real time and real-time inquiry engineering subject under discussion treatment situation when the on-the-spot execution of remote job operation.
The invention provides a kind of remote job field engineering data change method of control and system thereof, can avoid information gap influence that long distance produces to construct, assemble or during site work such as test and produce and lose time and facility Entity Change problem.
The invention provides a kind of remote job field engineering data change method of control and system thereof, can collect and write down the various information at remote job scene, as construction, assembling and test etc., as historical data, in order to the carrying out of homogeneity operation backward.
The invention provides a kind of remote job field engineering data change method of control, the engineering staff who is applicable to turnkey merchant or following concessionaire is at the remote job scene, when meeting facility or station when the change in the work doubt is not arranged, utilization has the electronic installation of the portable terminal of photography mechanism, facility or stand other position and view data are sent to network information service person's central means, and the electronic installation of central means or terminal just sends news in brief or Email to turnkey merchant's project manager and following concessionaire's project planning personnel; The central means that turnkey merchant's project manager and following concessionaire's project planning personnel utilize the electronic installation of terminal to be online to network information service person is again handled the subject under discussion of this project change, this central means is in handling back transmission news in brief or the Email engineering staff to this turnkey merchant or following concessionaire, and this project personnel utilize the electronic installation query processing result of its terminal.
A kind of remote job field engineering data change method of control of the present invention is applicable to turnkey merchant or following concessionaire's engineering staff, and its method comprises:
This project personnel are in the remote job scene, utilization has the electronic installation of the terminal of photography mechanism, the facility of change in the work doubt will be arranged or central means that stand other position and view data are established as a change in the work subject under discussion and are sent to the tool network information service;
The electronic installation of this central means or terminal notify at least turnkey merchant project manager and following concessionaire planning personnel one of them;
This project manager of turnkey merchant and this planning personnel of following concessionaire utilize the electronic installation of terminal to be online to this central means of the tool network information service to handle this project change subject under discussion;
Central means is handled the information that back this subject under discussion of notice this project personnel has been handled in this subject under discussion; And
The electronic installation of the terminal under this project personnel utilize is inquired about the result of this subject under discussion.
Remote job field engineering data change method of control of the present invention, wherein the electronic installation of this central means or terminal notice turnkey merchant project manager comprises with following concessionaire planning personnel's step:
Automatically send news in brief or Email to this project manager or this planning personnel.
Remote job field engineering data change method of control of the present invention, wherein the step behind the electronic installation of this central means or terminal notice turnkey merchant project manager and the following concessionaire planning personnel comprises:
Automatically startup is followed the mechanism of urging to carry out timing and is notified this project manager or this planning personnel.
Remote job field engineering data change method of control of the present invention, the step of wherein handling this project change subject under discussion comprises:
Start judgment mechanism by this project manager or this planning personnel, judge whether project data needs change.
Remote job field engineering data change method of control of the present invention, wherein this central means notice this project personnel's step comprises:
Send Email notice this project personnel do correction of facility entity and management and control, and this Email comprises the subject under discussion of having handled through revising.
Remote job field engineering data change method of control of the present invention, wherein this central means notice this project personnel's step comprises:
Automatically send news in brief or Email to this project personnel.The invention provides a kind of remote job field engineering data change method of control, comprise: (i) set up the required project planning data of operation field in a function service database; (ii) by user's the electronic installation with real-time camera unit, extracting has the facility of change in the work doubt or other view data of standing; (iii) by being arranged at the online module of browsing of this electronic installation, contact to one information service platform and be arranged at functional entrance assembly in this information service platform is set up pending subject under discussion according to authority in getting in touch to the function service module by this functional entrance assembly; Or directly being connected in the pending subject under discussion of line transmission module transmission storage by one, it comprises this facility that establishes the change in the work doubt or other position code of standing, uploads this view data and stores the function service database of this view data in this function service module; And, revise the pairing project planning data of this operation field (iv) according to this position code and this view data.
Remote job field engineering data change method of control of the present invention, wherein set up this pending subject under discussion step and comprise:
When setting up this pending subject under discussion, automatic real-time informing project manager or initial planning personnel.
Remote job field engineering data change method of control of the present invention, wherein set up this pending subject under discussion step and comprise:
Automatically send news in brief or Email to this project manager or this initial planning personnel by this function service module or the online transmission module of going up.
Remote job field engineering data change method of control of the present invention, wherein set up this pending subject under discussion step and comprise:
Behind real-time informing, the automatic startup of this function service module is carried out timing with the mechanism of urging and is notified this project manager or this initial planning personnel.
Remote job field engineering data change method of control of the present invention, wherein set up this pending subject under discussion step and comprise:
Input has this facility of change in the work doubt or other position of standing; And
This function service module or this online transmission module of going up are converted to position code with this position.
Remote job field engineering data change method of control of the present invention, wherein extract this view data step and comprise:
Extract static image data; And
Indicate this static image data.
Remote job field engineering data change method of control of the present invention, wherein extract this view data step and comprise:
Extract dynamic image data and sound import simultaneously and explain orally data.
A kind of remote job field engineering data change method of control of the present invention comprises:
Set up the function service database of the required project planning data of operation field in a function service module;
In this function service module or this onlinely go up the built-in upright pending subject under discussion of transmission module, store the facility of change in the work doubt or other view data of standing in this function service database, and notify items managerial personnel or initial planning personnel simultaneously;
Judge by this project manager or this initial planning personnel whether project data needs change; And
Revise the unit by the operation field project data that is arranged in this function service module, the user that notice is set up this pending subject under discussion.
Remote job field engineering data change method of control of the present invention, wherein notify the user's who sets up this pending subject under discussion step to comprise:
Send news in brief or Email to the user who sets up this pending subject under discussion.
Remote job field engineering data change method of control of the present invention, wherein this judgement project data change step comprises:
By using the user of electronic type Work flow with the decision judgment mechanism.
Remote job field engineering data change method of control of the present invention wherein comprises after this judgement project data change step:
When not needing to change this project data, the user that this project manager or this initial planning personnel notice are set up this pending subject under discussion.
Remote job field engineering data change method of control of the present invention wherein comprises after this judgement project data change step:
When needs change this project data, this project manager or this initial planning personnel carry out the operation field subject under discussion module query function unit that builds in this function service module;
Confirm whether image information that this pending subject under discussion provides conforms to this operation field planning project data and revise it; And
To upgrade in project data this operation field project data modification unit in this function service module of revising.
Remote job field engineering data change method of control of the present invention, wherein this carries out comprising after the step of updating:
By notifying the related personnel to carry out the entity correction in this operation field project data modification unit.
Remote job field engineering data change method of control of the present invention, wherein this carries out comprising after the step of updating:
The user inquires about the situation and the progress of pending subject under discussion by this operation field subject under discussion module query function unit.The invention provides a kind of remote job field engineering data change management system, comprise online module, online transmission module, information service platform, function service module and the real-time camera unit gone up browsed; Wherein, this online module of browsing is carried out transmission, the access of information by HTTP protocol and is presented; This online transmission module of going up stores by the transmission that network communication protocol carries out information; This information service platform is got in touch this and is onlinely browsed module and network service (WebService) corresponding to this HTTP protocol is provided, and it includes the authority inlet module that authentication and management and control user login and gets in touch this authority inlet module and the functional entrance assembly of selecting corresponding service according to this user's authority; This function service module is got in touch to this functional entrance assembly of this information service platform and is comprised plural function service unit and function service database; This function service database contact is to these function service units and provide these function service units to carry out data access, and each function service unit starts the function service execution according to pairing this user's authority of this functional entrance assembly; This real-time camera unit contact is to online module or the online transmission module of going up browsed; Whereby, this real-time camera unit extracts in the operation field has the facility of change in the work doubt or other view data of standing, by corresponding function service unit in this information service platform and the function service module, this view data is stored in this function service database, or directly this view data is stored in this function service database by the online transmission module of going up.
Remote job field engineering data change management system of the present invention is further built with 3-Tier or N-tier data structure and is put.
Remote job field engineering data change management system of the present invention, further comprise the job platform system, this job platform interconnection is to should be online browsing module, this information service platform and this function service module, and provides this HTTP protocol to make this online module of browsing get in touch to information service platform.
Remote job field engineering data change management system of the present invention, wherein this online browser that electronic installation provided of browsing module for the user.
Remote job field engineering data change management system of the present invention, wherein this online module of browsing provides built-in online browser, and this online browser is online with wireless or wired mechanism.
Remote job field engineering data change management system of the present invention, wherein this functional entrance assembly of this information service platform meets more than the JSR168 or the standard of WSRP.
Remote job field engineering data change management system of the present invention, wherein this information service platform further comprises: get in touch the rights database of this authority inlet module and manage this user's authority and it is embedded in the authority management module of this rights database; Wherein, this rights database stores the user and logins data and permissions data.
Remote job field engineering data change management system of the present invention, wherein this authority inlet module authenticates and manages this user in the single mode (Single Sign On) that logs on.
Remote job field engineering data change management system of the present invention, wherein a plurality of function service units of this of this function service module include: engineering control data are set up functional unit, engineering control data modification functional unit, the pending subject under discussion of engineering sets up functional unit and the engineering subject under discussion is handled the query function unit.
Remote job field engineering data change management system of the present invention, wherein this project control data are set up the project data of being set up when functional unit provides facilities planning, and this project data storing is in this function service database.
Remote job field engineering data change management system of the present invention, wherein this project control data modification functional unit is made amendment and management and control to the project data of desire change.
Remote job field engineering data change management system of the present invention, wherein the pending subject under discussion of this project is set up functional unit input and the management and control for the treatment of the altering engineering data is provided.
Remote job field engineering data change management system of the present invention, wherein this project subject under discussion is handled progress and the situation that the altering engineering data are treated in the inquiry of query function unit.
Remote job field engineering data change management system of the present invention, wherein this function service database of this function service module comprises: the data with database form or e-file archives form.
Remote job field engineering data change management system of the present invention, wherein this function service database of this function service module comprises: engineering programming book, specification, map file, automatically controlled data, and facility position code.
Remote job field engineering data change management system of the present invention, wherein the view data of this real-time camera unit further comprises: have the static image data that image indicates, or comprise the dynamic image data that sound explains orally simultaneously.
Remote job field engineering data change control system of the present invention is further built with 3-Tier or N-tier data structure and is put.
Remote job field engineering data change control system of the present invention, further comprise the job platform system, this job platform interconnection is to should be online browsing module, this information service platform and this function service module, and provides this communications protocol to make this online module of browsing get in touch to information service platform.
Remote job field engineering data change control system of the present invention, wherein this online browser that electronic installation provided of browsing module for the user.
Remote job field engineering data change control system of the present invention, wherein this online browse module with should be online on transmission module online with wireless or wired mechanism.
Remote job field engineering data change control system of the present invention, wherein this functional entrance assembly of this information service platform meets more than the JSR168 or the standard of WSRP.
Remote job field engineering data change control system of the present invention, wherein this information service platform further comprises: get in touch the rights database of this authority inlet module and manage this user's authority and it is embedded in the authority management module of this rights database; Wherein, this rights database stores the user and logins data and permissions data.
Remote job field engineering data change control system of the present invention, wherein this authority inlet module authenticates and manages this user in the single mode (Single Sign On) that logs on.
Remote job field engineering data change control system of the present invention, wherein this plural number function service unit of this function service module includes: engineering control data are set up functional unit, engineering control data modification functional unit, the pending subject under discussion of engineering sets up functional unit and the engineering subject under discussion is handled the query function unit.
Remote job field engineering data change control system of the present invention, wherein this project control data are set up the project data of being set up when functional unit provides facilities planning, and this project data storing is in this function service database.
Remote job field engineering data change control system of the present invention, wherein this project control data modification functional unit is made amendment and management and control to the project data of desire change.
Remote job field engineering data change control system of the present invention, wherein the pending subject under discussion of this project is set up functional unit input and the management and control for the treatment of the altering engineering data is provided.
Remote job field engineering data change control system of the present invention, wherein this project subject under discussion is handled progress and the situation that the altering engineering data are treated in the inquiry of query function unit.
Remote job field engineering data change control system of the present invention, wherein this function service database of this function service module comprises: the data with database form or e-file archives form.
Remote job field engineering data change control system of the present invention, wherein this function service database of this function service module comprises: engineering programming book, specification, map file, automatically controlled data, and device location code.
Remote job field engineering data change control system of the present invention, wherein the view data of this real-time camera unit further comprises: have the static image data that image indicates, or comprise the dynamic image data that sound explains orally simultaneously.
In order further to understand feature of the present invention and technology contents, see also following relevant detailed description of the present invention, yet described content only provides reference and explanation usefulness, is not to be used for the present invention is limited.
Description of drawings
Fig. 1 is the system schematic that the invention provides remote job field engineering data change control system; And
Fig. 2 is the structural representation that the invention provides remote job field engineering data change method of control.
Wherein, description of reference numerals is as follows:
The online group 1 online module 11 of browsing
Online transmission module 12 information service platforms 2 of going up
Authority inlet module 21 rights database 22
Authority management module 23 functional entrance assemblies 24
Function service module 3 function service databases 31
Engineering control data are set up functional unit 32 engineering control data modification functional units 33
The engineering subject under discussion is handled the pending subject under discussion of query function unit 35 engineerings and is set up functional unit 34
Job platform system 4 real-time camera units 51
Engineering staff's 8 central means 7 of turnkey merchant, following concessionaire
Turnkey merchant's project manager, following concessionaire's project planning personnel 6,91,92,93
Embodiment
See also shown in Figure 1, the invention provides the system schematic of remote job field engineering data change management system, this management system can 3-Tier or the N-tier data structure build and put, it comprises the online group 1, information service platform 2, function service module 3 of the electronic installation of terminal, camera unit 51 and job platform system 4 in real time; Wherein, this online group 1 comprises online module 11 and the online transmission module 12 of going up browsed, this online module 11 of browsing is responsible for receiving the input of user's data, pass through HTTP protocol, be online to this information service platform 2 of being located at central means and carry out the transmission, access of information and be presented on the display device that connects facility by the data message that this information service platform 2 is provided, this is online browses the browser that electronic installation provided that module 11 can be the user; In addition, this online module 11 of browsing can provide built-in online browser, and this online browser is online with wireless or wired mechanism.This online transmission module 12 of going up also can be responsible for receiving the input of user's data, by network communication protocol, is online to the transmission storage that function service database 31 carries out information, and this is online, and upward transmission module 12 is online with wireless or wired mechanism.
These information service platform 2 these online modules 11 of browsing of contact, and provide network service (Web Service) that the mechanism of the running and the management and control of service data information is provided corresponding to this HTTP protocol, the information of function service is presented in these online modules 11 of browsing of the electronic installation of terminal, it includes the authority inlet module 21 that authentication and management and control user login in good time, get in touch this authority inlet module 21 and the functional entrance assembly 24 of selecting corresponding service according to this user's authority, get in touch the rights database 22 of this authority inlet module 21, and manage this user's authority and it is recorded in the authority management module 23 of this rights database 22; This rights database 22 is logined the storage that keeps a record of data and permissions data by this authority management module 23 with the user in advance, as store the user and login data and permissions data (can enter spendable which kind of function service in this information service platform 2 of electronic installation of terminal), this authority inlet module 21 authenticates and manages this user in the single mode (Single Sign On) that logs on, this functional entrance assembly 24 meets more than the JSR168 or the standard of WSRP, data according to this rights database 22 are done mandate to the user, its these function service items that can use the information service platform 2 of central means to be provided of management and control.
This function service module 3 contacts of being located at central means are to this functional entrance assembly 24 of this information service platform 2 and comprise a plurality of function service units (32,33,34,35) and function service database 31, and it is carried out service function and comes management and control by this functional entrance assembly 24; This function service database contact is to these function service units and provide these function service units (32,33,34,35) to carry out data access, and each function service unit (32,33,34,35) starts the function service execution according to these functional entrance assembly 24 pairing these user's authorities.This function service database 31 comprises the data with database form or e-file archives form, and it includes engineering programming book, specification, map file, automatically controlled data, reaches electronic types such as facility position code, planning personnel, Email or the portable telephone number record data of planning process.These a plurality of function service units (32,33,34,35) include: engineering control data are set up functional unit 32, engineering control data modification functional unit 33, the pending subject under discussion of engineering sets up functional unit 34 and the engineering subject under discussion is handled query function unit 35, and wherein this project control data are set up the correlation engineering data and the input of being set up when functional unit 32 provides facilities planning and are stored to this function service database 31; When this project control data modification functional unit 33 mainly provides facilities planning, set up modification and management and control to desiring the altering engineering data; The input for the treatment of the altering engineering data and management and control when the pending subject under discussion of this project is set up functional unit 34 engineering construction, assembling, test jobs mainly are provided; Subject under discussion treatment state when this project subject under discussion is handled query function unit 35 inquiry engineering construction, assembling, test jobs mainly are provided is promptly treated the progress and the situation of altering engineering data.
This job platform system 4 gets in touch this online group 1 to the electronic installation of terminal, this information service platform 2 of central means can adopt the different operating system platform with the job platform of this function service module 3, mainly according to the online group 1 of the electronic installation of terminal, the information service platform 2 of central means, select with the electronic installation hardware of 3 construction of function service module, and provide this this online module 11 of browsing of HTTP protocol order to get in touch, and provide this online transmission module 12 of going up of this network communication protocol order to get in touch to function service database 31 to information service platform 2.
These real-time camera unit 51 contacts are to corresponding online module 11 and the online transmission module 12 of going up browsed, the view data of this real-time camera unit 51 is tool image capture function merely, or the static image data that further has the image sign, or comprise the dynamic image data that sound explains orally simultaneously, whereby, this real-time camera unit 51 extracts in the operation field has the facility of change in the work doubt or other view data of standing, by this information service platform 2 and function service module 3 interior corresponding function service units (32,33,34,35), this view data is stored in this function service database 31, or directly this view data is stored in this function service database 31 by the online transmission module 12 of going up.
See also shown in Figure 2, for the invention provides the structural representation of remote job field engineering data change method of control, this method of control is applicable to that turnkey merchant or following concessionaire's engineering staff is at the remote job scene, when meeting facility or station when the change in the work doubt is not arranged, utilization has the electronic installation of the portable terminal of photography mechanism (as this real-time camera unit 51), facility or stand other position and view data are sent to network information service person's central means 7, and the electronic installation of central means 7 or terminal just sends news in brief or Email to turnkey merchant's project manager and following concessionaire's project planning personnel 6,91,92,93; The central means 7 that turnkey merchant's project manager and following concessionaire's project planning personnel 6,91,92,93 utilize the electronic installation of terminal to be online to network information service person is again handled the subject under discussion of this project change, this central means 7 is in handling back transmission news in brief or the Email engineering staff 8 to this turnkey merchant or following concessionaire, and this project personnel 8 utilize the electronic installation query processing result of its terminal; This network information service person can collect the charges by these services, and this fee mode can adopt member system or metering mode to collect; If the turnkey merchant itself has this information service platform 2 of central means, can take member system to serve the following concessionaire that it is pulled together, will make the turnkey merchant effectively manage concessionaire down.
The method of control of remote job field engineering data change system is carried out as follows:
(i) set up the required project planning data of operation field in a function service database, as when the project planning, its related data of setting up is set up function input by the engineering control data of central means and is stored to the function service database, and its data comprise electronic types such as facility position code, planning personnel, Email or the portable telephone number record data of engineering programming book, specification, map file, automatically controlled data and planning process;
(ii) the user provides for oneself and can pass through moving or fixed electronic device of HTTP protocol, for example personal computer, mobile computer, mobile phone or personal digital assistant device electronic installations such as (PDA), at the remote job scene, when carrying out construction, assembling, test jobs, extraction has the facility of change in the work doubt or other view data of standing, its can comprise extract static image data, with indicate this static image data; Or extract dynamic image data and sound import simultaneously and explain orally data, with above-mentioned data storing in the electron storage medium of the electronic installation of terminal;
(iii) start the online function of the electronic installation of terminal, for example wired or wireless, carry out browser,, get in touch to an information service platform and be arranged at functional entrance assembly in this information service platform by being arranged at the online module and the logical agreement of HTTP browsed of this electronic installation;
(iv) the picture of the information service platform of central means is presented on this terminal mat device, the user according to authority (as input user's code or password etc.) in getting in touch to the function service module by this functional entrance assembly;
(v) it by the content of authority inlet module according to user in the rights database and function privilege corresponding data, is examined this user and whether can enter the information service platform of central means earlier;
(vi) if lack of competence or to login data wrong, the original picture of presentation information service platform then, if there is authority to login, then present the spendable function service of the information service platform of central means picture, this function service picture by the mechanism of control of this functional entrance assembly so that the user to be provided required function information on services;
(vii) this information service platform uses it result who carries out (input, modification or inquiry) to be presented on the electronic installation of terminal; And
(viii) the user be if will finish the information service platform of central means, and the online of electronic installation that then stops to carry out terminal browsed module and cut off online; The user is if will continue to use these service functions, and then the online module of browsing of the electronic installation of terminal need keep on line state, and repeating step (vii).
Wherein, if after (ii) finishing, also can start online transmission module and the logical agreement of network of going up that is arranged at this electronic installation, contact is done the data input and is transmitted to the function service database that is arranged at central means.
Wherein, this step of setting up pending subject under discussion is as follows:
(a) remote job scene, carry out construction, assembling, during test jobs, if in the time of need carrying out job facilities changes or the pending subject under discussion of engineering arranged, the electronic installation of the fixed or mobile terminal of engineering staff by having real-time camera unit, extraction has the facility of change in the work doubt or other view data of standing, and with above-mentioned data storing in the electron storage medium of the electronic installation of terminal, entry device position and the simple data of indicating, then the pending subject under discussion of this project is set up function will have this facility of change in the work doubt or station not to transfer position code to, the user uploads this view data and presents the result, and the user confirms and stores this position code and the function service database of view data in this function service module, or directly this equipment of change in the work doubt will be arranged or stand and do not transferred to position code by the online transmission module of going up, the user uploads this view data and presents the result, and the user confirms and stores this position code and view data in this function service database;
(b) this function service module or this online transmission module of going up are when setting up this pending subject under discussion, automatic real-time informing project manager or initial planning personnel, as adopt modes such as automatic transmission news in brief or Email, and behind real-time informing, start simultaneously and carry out timing with the mechanism of urging and notify (all being equipped with) this project manager or this initial planning personnel as news in brief or Email or both;
(c) start judgment mechanism by project manager or this planning personnel after, judge project data whether need the change;
(d) if do not need change, this project manager or this initial planning personnel send news in brief or Email or both and all are equipped with to inform this subject under discussion input in the engineering control data modification function of central means; If need change, this project manager or this initial planning personnel performance of work subject under discussion are handled query function, with facility symbol lookup layout data, confirm to conform to, and do the relevant correction of layout data in engineering control data modification function, to upgrade with electronics one material image; And
(e) the engineering control data modification function send Email of central means is done correction of facility entity and management and control to the related personnel simultaneously, and sends news in brief or Email or both all fully to inform this subject under discussion importer; And
(f) user askes query function in engineering subject under discussion place online with the electronic installation of mobile or fixed terminal and the execution central means, confirms the treatment situation and the progress of this pending subject under discussion.
The invention provides a kind of remote job field engineering data change method of control and system thereof, its advantage is as follows:
(1.) can provide realtime graphic, solve the engineering data management problem at remote job scene, to shorten the engineer operation time-histories, to reduce engineering cost;
(2.) can be applicable to enterprise itself or the further cooperation between manufacturer in conjunction with;
(3.) can operate difference in functionality according to user's authority;
The use interface that (4.) can customize can be operated with the browser of the existing employing of user;
(5.) can be when the engineering staff carry out operation to remote job is on-the-spot, pending subject under discussion of feedback engineering and inquiry engineering subject under discussion treatment situation in real time in real time;
(6.) can avoid information gap influence that long distance produces to construct, assemble or during site work such as test and produce and lose time and facility Entity Change problem; And
(7.) can collect and note down the various information at remote job scene, as construction, assembling and test etc., as historical data, in order to the carrying out of homogeneity operation backward.
The above only is a preferable possible embodiments of the present invention, and non-so promptly inflexible limit claim of the present invention so the equivalent structure that every application instructions of the present invention or accompanying drawing content are done changes, all is contained in claims scope of the present invention.

Claims (52)

1. remote job field engineering data change method of control comprises:
Set up the required project planning data of operation field in a function service database;
By the electronic installation with real-time camera unit, extracting has the facility of change in the work doubt or other view data of standing;
By being arranged at the online module of browsing of this electronic installation, contact to one information service platform and be arranged at functional entrance assembly in this information service platform, set up pending subject under discussion according to authority in getting in touch to the function service module by this functional entrance assembly, it comprises this facility that establishes the change in the work doubt or other position code of standing, uploads this view data and stores the function service database of this view data in this function service module; Or, directly transmit the pending subject under discussion of storage in the function service database by an online transmission module of going up; And
According to this position code and this view data, revise the corresponding project planning data of this operation field.
2. remote job field engineering data change method of control as claimed in claim 1 is characterized in that, sets up this pending subject under discussion step and comprises:
When setting up this pending subject under discussion, automatic real-time informing project manager or initial planning personnel.
3. remote job field engineering data change method of control as claimed in claim 2 is characterized in that, sets up this pending subject under discussion step and comprises:
Automatically send news in brief or Email to this project manager or this initial planning personnel by this function service module or the online transmission module of going up.
4. remote job field engineering data change method of control as claimed in claim 2 is characterized in that, sets up this pending subject under discussion step and comprises:
Behind real-time informing, the automatic startup of this function service module is carried out timing with the mechanism of urging and is notified this project manager or this initial planning personnel.
5. remote job field engineering data change method of control as claimed in claim 1 is characterized in that, sets up this pending subject under discussion step and comprises:
Input has this facility of change in the work doubt or other position of standing; And
This function service module or this online transmission module of going up are converted to position code with this position.
6. remote job field engineering data change method of control as claimed in claim 1 is characterized in that, extracts this view data step and comprises:
Extract static image data; And
Indicate this static image data.
7. remote job field engineering data change method of control as claimed in claim 1 is characterized in that, extracts this view data step and comprises:
Extract dynamic image data and sound import simultaneously and explain orally data.
8. remote job field engineering data change method of control comprises:
Set up the function service database of the required project planning data of operation field in a function service module;
In this function service module or onlinely go up the built-in upright pending subject under discussion of transmission module, store the facility of change in the work doubt or other view data of standing in this function service database, and notify items managerial personnel or initial planning personnel simultaneously;
Judge by this project manager or this initial planning personnel whether project data needs change; And
Revise the unit by the operation field project data that is arranged in this function service module, the user that notice is set up this pending subject under discussion.
9. remote job field engineering data change method of control as claimed in claim 8 is characterized in that, the step that notice is set up the user of this pending subject under discussion comprises:
Send news in brief or Email to the user who sets up this pending subject under discussion.
10. remote job field engineering data change method of control as claimed in claim 8 is characterized in that, this judgement project data change step comprises:
By using the user of electronic type Work flow with the decision judgment mechanism.
11. remote job field engineering data change method of control as claimed in claim 8 is characterized in that, comprises after this judgement project data change step:
When not needing to change this project data, the user that this project manager or this initial planning personnel notice are set up this pending subject under discussion.
12. remote job field engineering data change method of control as claimed in claim 8 is characterized in that, comprises after this judgement project data change step:
When needs change this project data, this project manager or this initial planning personnel carry out the operation field subject under discussion module query function unit that builds in this function service module;
Confirm whether image information that this pending subject under discussion provides conforms to this operation field planning project data and revise it; And
To upgrade in project data this operation field project data modification unit in this function service module of revising.
13. remote job field engineering data change method of control as claimed in claim 12 is characterized in that, this carries out comprising after the step of updating:
By notifying the related personnel to carry out the entity correction in this operation field project data modification unit.
14. remote job field engineering data change method of control as claimed in claim 12 is characterized in that, this carries out comprising after the step of updating:
The user inquires about the situation and the progress of pending subject under discussion by this operation field subject under discussion module query function unit.
15. a remote job field engineering data change management system comprises:
The online module of browsing is carried out transmission, the access of information and is presented by HTTP protocol;
Information service platform, get in touch this and onlinely browse module and network service corresponding to this HTTP protocol is provided, it includes the authority inlet module that authentication and management and control user login and gets in touch this authority inlet module and the functional entrance assembly of selecting corresponding service according to this user's authority;
The function service module, contact is to this functional entrance assembly of this information service platform and comprise a plurality of function service units and function service database; This function service database contact is to these function service units and provide these function service units to carry out data access, and each function service unit starts the function service execution according to pairing this user's authority of this functional entrance assembly; And
Camera unit is got in touch to the corresponding online module of browsing in real time;
Whereby, this real-time camera unit extracts in the operation field has the facility of change in the work doubt or other view data of standing, by corresponding function service unit in this information service platform and the function service module, this view data is stored in this function service database.
16. remote job field engineering data change management system as claimed in claim 15 is characterized in that, further builds with 3-Tier or N-tier data structure and puts.
17. remote job field engineering data change management system as claimed in claim 15, it is characterized in that, further comprise the job platform system, this job platform interconnection is to should be online browsing module, this information service platform and this function service module, and provides this HTTP protocol to make this online module of browsing get in touch to information service platform.
18. remote job field engineering data change management system as claimed in claim 15 is characterized in that, this online browser that electronic installation provided of browsing module for the user.
19. remote job field engineering data change management system as claimed in claim 15 is characterized in that, this online module of browsing provides built-in online browser, and this online browser is online with wireless or wired mechanism.
20. remote job field engineering data change management system as claimed in claim 15 is characterized in that, this functional entrance assembly of this information service platform meets more than the JSR168 or the standard of WSRP.
21. remote job field engineering data change management system as claimed in claim 15, wherein this information service platform further comprises: get in touch the rights database of this authority inlet module and manage this user's authority and it is embedded in the authority management module of this rights database; Wherein, this rights database stores the user and logins data and permissions data.
22. remote job field engineering data change management system as claimed in claim 15 is characterized in that this authority inlet module authenticates and manage this user in the single mode that logs on.
23. remote job field engineering data change management system as claimed in claim 15, it is characterized in that a plurality of function service units of this of this function service module include: engineering control data are set up functional unit, engineering control data modification functional unit, the pending subject under discussion of engineering sets up functional unit and the engineering subject under discussion is handled the query function unit.
24. remote job field engineering data change management system as claimed in claim 23 it is characterized in that this project control data are set up the project data of being set up when functional unit provides facilities planning, and this project data storing is in this function service database.
25. remote job field engineering data change management system as claimed in claim 23 is characterized in that, this project control data modification functional unit is made amendment and management and control to the project data of desire change.
26. remote job field engineering data change management system as claimed in claim 23 is characterized in that the pending subject under discussion of this project is set up functional unit input and the management and control for the treatment of the altering engineering data is provided.
27. remote job field engineering data change management system as claimed in claim 23 is characterized in that, this project subject under discussion is handled progress and the situation that the altering engineering data are treated in the inquiry of query function unit.
28. remote job field engineering data change management system as claimed in claim 15 is characterized in that, this function service database of this function service module comprises: the data with database form or e-file archives form.
29. remote job field engineering data change management system as claimed in claim 15 is characterized in that, this function service database of this function service module comprises: engineering programming book, specification, map file, automatically controlled data, and facility position code.
30. remote job field engineering data change management system as claimed in claim 15, it is characterized in that, the view data of this real-time camera unit further comprises: have the static image data that image indicates, or comprise the dynamic image data that sound explains orally simultaneously.
31. a remote job field engineering data change control system comprises:
The online transmission module of going up, the transmission of carrying out information by communications protocol stores;
The online module of browsing is carried out transmission, the access of information and is presented by communications protocol;
Information service platform, get in touch this and onlinely browse module and network service corresponding to this communications protocol is provided, it includes the authority inlet module that authentication and management and control user login and gets in touch this authority inlet module and the functional entrance assembly of selecting corresponding service according to this user's authority;
The function service module, contact is to this functional entrance assembly of this information service platform and comprise a plurality of function service units and function service database; This function service database contact is to these function service units and provide these function service units to carry out data access, and each function service unit starts the function service execution according to pairing this user's authority of this functional entrance assembly; And
One real-time camera unit, contact is to the online transmission module of going up;
Whereby, this real-time camera unit extracts in the operation field has the facility of change in the work doubt or other view data of standing, and by this online transmission module of going up, this view data is stored in this function service database.
32. remote job field engineering data change control system as claimed in claim 31 is characterized in that, further builds with 3-Tier or N-tier data structure and puts.
33. remote job field engineering data change control system as claimed in claim 31, it is characterized in that, further comprise the job platform system, this job platform interconnection is to should be online browsing module, this information service platform and this function service module, and provides this communications protocol to make this online module of browsing get in touch to information service platform.
34. remote job field engineering data change control system as claimed in claim 31 is characterized in that, this online browser that electronic installation provided of browsing module for the user.
35. remote job field engineering data change control system as claimed in claim 31 is characterized in that, this is online browse module with should be online on transmission module online with wireless or wired mechanism.
36. remote job field engineering data change control system as claimed in claim 31 is characterized in that, this functional entrance assembly of this information service platform meets more than the JSR168 or the standard of WSRP.
37. remote job field engineering data change control system as claimed in claim 31, it is characterized in that this information service platform further comprises: get in touch the rights database of this authority inlet module and manage this user's authority and it is embedded in the authority management module of this rights database; Wherein, this rights database stores the user and logins data and permissions data.
38. remote job field engineering data change control system as claimed in claim 31 is characterized in that this authority inlet module authenticates and manage this user in the single mode that logs on.
39. remote job field engineering data change control system as claimed in claim 31, it is characterized in that this plural number function service unit of this function service module includes: engineering control data are set up functional unit, engineering control data modification functional unit, the pending subject under discussion of engineering sets up functional unit and the engineering subject under discussion is handled the query function unit.
40. remote job field engineering data change control system as claimed in claim 39 it is characterized in that this project control data are set up the project data of being set up when functional unit provides facilities planning, and this project data storing is in this function service database.
41. remote job field engineering data change control system as claimed in claim 39 is characterized in that, this project control data modification functional unit is made amendment and management and control to the project data of desire change.
42. remote job field engineering data change control system as claimed in claim 39 is characterized in that the pending subject under discussion of this project is set up functional unit input and the management and control for the treatment of the altering engineering data is provided.
43. remote job field engineering data change control system as claimed in claim 39 is characterized in that, this project subject under discussion is handled progress and the situation that the altering engineering data are treated in the inquiry of query function unit.
44. remote job field engineering data change control system as claimed in claim 31 is characterized in that, this function service database of this function service module comprises: the data with database form or e-file archives form.
45. remote job field engineering data change control system as claimed in claim 31 is characterized in that, this function service database of this function service module comprises: engineering programming book, specification, map file, automatically controlled data, and device location code.
46. remote job field engineering data change control system as claimed in claim 31, it is characterized in that, the view data of this real-time camera unit further comprises: have the static image data that image indicates, or comprise the dynamic image data that sound explains orally simultaneously.
47. a remote job field engineering data change method of control is applicable to turnkey merchant or following concessionaire's engineering staff, its method comprises:
This project personnel are in the remote job scene, utilization has the electronic installation of the terminal of photography mechanism, the facility of change in the work doubt will be arranged or central means that stand other position and view data are established as a change in the work subject under discussion and are sent to the tool network information service;
The electronic installation of this central means or terminal notify at least turnkey merchant project manager and following concessionaire planning personnel one of them;
This project manager of turnkey merchant and this planning personnel of following concessionaire utilize the electronic installation of terminal to be online to this central means of the tool network information service to handle this project change subject under discussion;
Central means is handled the information that back this subject under discussion of notice this project personnel has been handled in this subject under discussion; And
The electronic installation of the terminal under this project personnel utilize is inquired about the result of this subject under discussion.
48. remote job field engineering data change method of control as claimed in claim 47 is characterized in that, the electronic installation notice turnkey merchant project manager of this central means or terminal comprises with following concessionaire planning personnel's step:
Automatically send news in brief or Email to this project manager or this planning personnel.
49. remote job field engineering data change method of control as claimed in claim 47 is characterized in that, the electronic installation notice turnkey merchant project manager of this central means or terminal and the step behind the following concessionaire planning personnel comprise:
Automatically startup is followed the mechanism of urging to carry out timing and is notified this project manager or this planning personnel.
50. remote job field engineering data change method of control as claimed in claim 47 is characterized in that, the step of handling this project change subject under discussion comprises:
Start judgment mechanism by this project manager or this planning personnel, judge whether project data needs change.
51. remote job field engineering data change method of control as claimed in claim 47 is characterized in that, this central means notice this project personnel's step comprises:
Send Email notice this project personnel do correction of facility entity and management and control, and this Email comprises the subject under discussion of having handled through revising.
52. remote job field engineering data change method of control as claimed in claim 47 is characterized in that, this central means notice this project personnel's step comprises:
Automatically send news in brief or Email to this project personnel.
CN200510084594XA 2005-08-01 2005-08-01 Method and system for remote operation in-site engineering data alteration control and management Expired - Fee Related CN1908969B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200510084594XA CN1908969B (en) 2005-08-01 2005-08-01 Method and system for remote operation in-site engineering data alteration control and management

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200510084594XA CN1908969B (en) 2005-08-01 2005-08-01 Method and system for remote operation in-site engineering data alteration control and management

Publications (2)

Publication Number Publication Date
CN1908969A CN1908969A (en) 2007-02-07
CN1908969B true CN1908969B (en) 2010-07-14

Family

ID=37700075

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200510084594XA Expired - Fee Related CN1908969B (en) 2005-08-01 2005-08-01 Method and system for remote operation in-site engineering data alteration control and management

Country Status (1)

Country Link
CN (1) CN1908969B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101930632B (en) * 2009-06-24 2011-12-07 吴志成 Operation flow image deposit system and method
US9285870B2 (en) * 2013-09-24 2016-03-15 International Business Machines Corporation System locale name management

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6038547A (en) * 1998-01-07 2000-03-14 Casto; Robin L. Construction tracking and payment method and system
TW580633B (en) * 2002-12-27 2004-03-21 Inventec Corp Maintenance method and system for engineering change data
CN1501298A (en) * 2002-11-15 2004-06-02 英业达股份有限公司 Trial run handling system and method for engineering alteration
TW591463B (en) * 2002-09-09 2004-06-11 Topco Scient Co Ltd Project engineering control system and method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6038547A (en) * 1998-01-07 2000-03-14 Casto; Robin L. Construction tracking and payment method and system
TW591463B (en) * 2002-09-09 2004-06-11 Topco Scient Co Ltd Project engineering control system and method thereof
CN1501298A (en) * 2002-11-15 2004-06-02 英业达股份有限公司 Trial run handling system and method for engineering alteration
TW580633B (en) * 2002-12-27 2004-03-21 Inventec Corp Maintenance method and system for engineering change data

Also Published As

Publication number Publication date
CN1908969A (en) 2007-02-07

Similar Documents

Publication Publication Date Title
CN102394875B (en) Method and system for accessing available service on a second network by member of a first network
US7194433B1 (en) System, computer program product and method for managing documents
US7949645B2 (en) Control method for modifying engineering information from a remote work site and a system of the same
CN101490665B (en) Systems, methods and computer program products for performing remote data storage for client devices
CN101132459A (en) Method for computer remote control by mobile phone
CN1474986A (en) System and method for providing supervision of plurality of financial services terminals
CN1200515A (en) Information providing system
CN101998009B (en) Control server and display screen control system of multi-functional peripheral
JP2006338561A (en) Construction progress management system
KR100335669B1 (en) Homepage autometic structuring system and method thereof using webkiosk
JP2004013576A (en) Data input system using wide area network
CN1908969B (en) Method and system for remote operation in-site engineering data alteration control and management
KR100767513B1 (en) System for securely communicating amongst client computer systems
US20050171734A1 (en) Electronic data collection system and method
JP2002366517A (en) Method, system for providing service, processing center device and program
JP2004054655A (en) Schedule management system, program and recording medium
CN201114648Y (en) A mobile online help platform system
JP2002222236A (en) Device and method for providing product information, and program and recording medium for the same
KR100698955B1 (en) Method and system for providing macro service of mobile terminal using script embedded image file
JP2020095692A (en) Information processing system, information processing apparatus, information processing method, and information processing program
KR100511557B1 (en) A system and method for providing electronic calling card service
JP2006244311A (en) Electronic conference system
JP2002024503A (en) Duty control system
JP2007241917A (en) Business support system
KR20020013958A (en) The rental management method and system using internet

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100714

Termination date: 20170801

CF01 Termination of patent right due to non-payment of annual fee