[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN113178941A - Standby power supply system for intelligent electric energy meter - Google Patents

Standby power supply system for intelligent electric energy meter Download PDF

Info

Publication number
CN113178941A
CN113178941A CN202110475859.8A CN202110475859A CN113178941A CN 113178941 A CN113178941 A CN 113178941A CN 202110475859 A CN202110475859 A CN 202110475859A CN 113178941 A CN113178941 A CN 113178941A
Authority
CN
China
Prior art keywords
unit
power supply
signal
control unit
switching
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110475859.8A
Other languages
Chinese (zh)
Inventor
侯佳佳
周健
曹凯凯
马亮
薛超
韩本超
李金莲
张静雯
宋丹
夏龙宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Anqiu Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Anqiu Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Anqiu Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN202110475859.8A priority Critical patent/CN113178941A/en
Publication of CN113178941A publication Critical patent/CN113178941A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J9/00Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
    • H02J9/04Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
    • H02J9/06Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems

Landscapes

  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Arrangements For Transmission Of Measured Signals (AREA)

Abstract

The invention provides a standby power supply system for an intelligent electric energy meter, which comprises: the device comprises a control unit, a communication unit, a power supply unit, a clock unit, a standby power supply unit, a switch loop unit and a voltage detection unit; the control unit is respectively in signal connection with the communication unit, the clock unit, the switch loop unit and the voltage detection unit, the voltage detection unit is in signal connection with the switch loop unit, the power supply unit is respectively in electric connection with the control unit and the switch loop unit, the standby power supply unit is respectively in electric connection with the control unit and the switch loop unit, and the switch loop unit is respectively in electric connection with the clock unit and the communication unit. The intelligent electric energy meter can find the power supply abnormality of the switch loop unit in time and instantly switch the standby power supply, thereby ensuring the communication function of the intelligent electric energy meter in the power-off state and avoiding the time abnormality phenomenon of the clock after the power grid recovers the power supply.

Description

Standby power supply system for intelligent electric energy meter
Technical Field
The invention relates to the technical field of electric power, in particular to a standby power supply system for an intelligent electric energy meter.
Background
The intelligent electric energy meter is used as an inlet interface of a power grid and widely applied to electric energy metering, and new energy such as solar energy, wind energy and the like is fed back to the power grid through the intelligent electric energy meter and is connected with the power grid in parallel, so that the metering timeliness and accuracy of the intelligent electric energy meter are very important. At present, a battery is arranged in an intelligent electric energy meter used in the market and used for supplying power to a clock loop in a power-off state so as to ensure that the clock of the electric energy meter is correct. Due to the fact that the service life of the battery is limited, the failure rate is high, and the electric energy meter clock is abnormal in time after the power grid recovers power supply. Because the electric energy meter is packaged when leaving the factory, the battery cannot be replaced after the fault, and inconvenience is caused. The battery of the intelligent meter is only used for maintaining the running of the clock loop, and the communication loop has no power supply, so that the remote communication cannot be realized.
Disclosure of Invention
In view of the above problems, an object of the present invention is to provide a backup power supply system for an intelligent electric energy meter.
In order to achieve the purpose, the invention is realized by the following technical scheme: a backup power supply system for a smart power meter, comprising: the device comprises a control unit, a communication unit, a power supply unit, a clock unit, a standby power supply unit, a switch loop unit and a voltage detection unit; the control unit is respectively in signal connection with the communication unit, the clock unit, the switch loop unit and the voltage detection unit, the voltage detection unit is in signal connection with the switch loop unit, the power supply unit is respectively in electric connection with the control unit and the switch loop unit, the standby power supply unit is respectively in electric connection with the control unit and the switch loop unit, and the switch loop unit is respectively in electric connection with the clock unit and the communication unit;
the control unit is used for sending a switching signal to the switching loop unit, and controlling the switching loop unit to supply power to the clock unit and the communication unit by using the power supply unit or the standby power supply unit;
and the voltage detection unit is used for monitoring the voltage of the switch loop unit in real time, converting the voltage value into a digital signal and sending the digital signal to the control unit.
Furthermore, a first switch module is arranged in the switch loop unit, the first switch module is electrically connected with the power supply unit and used for controlling the power supply unit to be switched on or switched off according to a control signal of the control unit, and the first switch module sends a current switching value signal to the control unit. The first switch module controls the power supply unit to be connected to the switch loop unit, and after the switch loop unit is closed, the power supply unit is adopted to supply power to the control unit, the clock unit and the communication unit.
Furthermore, a second switch module is arranged in the switch loop unit, the second switch module is electrically connected with the standby power supply unit and used for controlling the power supply unit to be switched on or switched off according to the control signal of the control unit, and the second switch module sends the current switching value signal to the control unit. And the second switch module controls the standby power supply unit to be connected into the switch loop unit, and after the standby power supply unit is closed, the standby power supply unit is adopted to supply power to the control unit, the clock unit and the communication unit.
Further, when the voltage detection unit monitors that the voltage of the switch loop unit is lower than a preset threshold value, the voltage value is converted into a digital signal and sent to the control unit, and meanwhile, a low-voltage alarm signal is sent to the control unit; and after receiving the low-voltage alarm signal, the control unit sends a control signal to the switch loop unit according to the power supply switching strategy to carry out power supply switching. The voltage detection unit realizes the working voltage monitoring and low-voltage early warning of the switch loop unit.
Further, the power switching strategy comprises:
the control unit respectively reads the current switching value signals of the first switch module and the second switch module, and if the switching value signal of the first switch module is a closing signal and the switching value signal of the second switch module is an opening signal; the control unit sends an open signal to the first switch module and simultaneously sends a close signal to the second switch module. The power supply switching strategy realizes instantaneous switching of the power supply when the power supply of the switch loop unit is insufficient, and solves the communication problem of the intelligent electric energy meter in the power-off state.
Further, the power switching strategy further comprises:
if the switching value signal of the first switching module is an opening signal and the switching value signal of the second switching module is a closing signal; the control unit generates a first alarm signal and sends the first alarm signal to the communication unit. At present, the system is stand-by power supply unit power supply state, can't carry out the power supply and switch, can think that intelligent ammeter is in the complete insufficient voltage state, need report insufficient voltage information through the network.
Further, if the switching value signal of the first switch module is a closing signal and the switching value signal of the second switch module is a closing signal; the control unit generates a second alarm signal and sends the second alarm signal to the communication unit. At this time, the system determines that the switch loop unit has a fault, and power switching cannot be performed, and abnormal information needs to be reported through the network.
Further, after receiving the first alarm signal, the communication unit converts the first alarm signal into power-shortage alarm information and sends the power-shortage alarm information to a preset monitoring server through a network; and after receiving the second alarm signal, the communication unit converts the second alarm signal into line abnormal alarm information and sends the line abnormal alarm information to the preset monitoring server through the network. The identification and the report of the alarm information are realized through the communication unit.
Furthermore, the standby power supply unit adopts a detachable battery pack, so that the replacement is convenient, and the problem that the battery cannot be replaced after the battery fails is effectively solved.
Compared with the prior art, the invention has the beneficial effects that: the invention provides a standby power supply system for an intelligent electric energy meter, which can find the power supply abnormality of a switch loop unit in time and instantly switch a standby power supply, ensures the communication function of the intelligent electric energy meter in a power failure state and avoids the time abnormality phenomenon of a clock after the power supply of a power grid is recovered. In addition, the invention has the function of circuit diagnosis, can find the fault and the hidden trouble of power supply of the switch loop unit in time and report the fault and the hidden trouble of power supply in time.
In addition, the invention has reliable design principle, simple structure and very wide application prospect.
Therefore, compared with the prior art, the invention has prominent substantive features and remarkable progress, and the beneficial effects of the implementation are also obvious.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the provided drawings without creative efforts.
FIG. 1 is a system block diagram of the present invention;
fig. 2 is a flow diagram of a method of power switching strategy of the present invention.
In the figure, 1 is a control unit, 2 is a communication unit, 3 is a power supply unit, 4 is a clock unit, 5 is a standby power supply unit, 6 is a switch loop unit, 7 is a voltage detection unit, 8 is a first switch module, and 9 is a second switch module.
Detailed Description
The following description of the embodiments of the present invention will be made with reference to the accompanying drawings.
A backup power supply system for an intelligent electric energy meter as shown in fig. 1, comprising: the device comprises a control unit 1, a communication unit 2, a power supply unit 3, a clock unit 4, a standby power supply unit 5, a switch loop unit 6 and a voltage detection unit 7. And the control unit 1 is used for sending a switching signal to the switching loop unit 6, and the switching loop unit 6 is controlled to supply power to the clock unit 4 and the communication unit 2 by using the power supply unit 3 or the standby power supply unit 5. And the voltage detection unit 7 is used for monitoring the voltage of the switch loop unit 6 in real time, converting the voltage value into a digital signal and sending the digital signal to the control unit 1.
The control unit 1 is respectively connected with the communication unit 2, the clock unit 4, the switch loop unit 6 and the voltage detection unit 7 through signals, the voltage detection unit 7 is connected with the switch loop unit 6 through signals, the power supply unit 3 is respectively and electrically connected with the control unit 1 and the switch loop unit 6, the standby power supply unit 5 is respectively and electrically connected with the control unit 1 and the switch loop unit 6, and the switch loop unit 6 is respectively and electrically connected with the clock unit 4 and the communication unit 2.
A first switch module 8 and a second switch module 9 are arranged in the switch circuit unit 6. The first switch module 8 is electrically connected to the power supply unit 3 and is configured to control the power supply unit 3 to be switched on or off according to a control signal of the control unit 1, and the first switch module 8 sends a current switching value signal to the control unit 1. The second switch module 9 is electrically connected to the standby power supply unit 5 and is configured to control the power supply unit 3 to be switched on or off according to a control signal of the control unit 1, and the second switch module 9 sends a current switching value signal to the control unit 1.
The standby power supply system monitors the voltage of the switch loop unit 6 in real time through the voltage detection unit 7 to determine whether to switch the power supply. When the voltage detection unit 7 monitors that the voltage of the switch loop unit 6 is lower than a preset threshold value, the voltage value is converted into a digital signal and is sent to the control unit 1, and meanwhile, a low-voltage alarm signal is sent to the control unit 1; after receiving the low-voltage alarm signal, the control unit 1 sends a control signal to the switch loop unit 6 according to the power switching strategy to perform power switching.
The standby power supply unit of the system adopts a detachable battery pack arranged outside the intelligent electric energy meter machine.
As shown in fig. 2, the adopted power switching strategy specifically includes the following steps:
s1: the control unit respectively reads the switching value signal K1 of the current first switching module and the switching value signal K2 of the second switching module.
S2: according to the specific values of K1 and K2, a control signal of the control unit is triggered and an alarm signal is sent out.
Specifically, the method comprises the following steps:
1. if K1=1 and K2=0, the switching value signal of the first switch module is a close signal and the switching value signal of the second switch module is an open signal; the control unit sends an open signal to the first switch module and simultaneously sends a close signal to the second switch module.
2. If K1=0 and K2=1, the switching value signal of the first switch module is an open signal and the switching value signal of the second switch module is a close signal; the control unit generates a first alarm signal and sends the first alarm signal to the communication unit. At this time, the system determines that the switch loop unit has a fault, and power switching cannot be performed, and abnormal information needs to be reported through the network.
3. If K1=1 and K2=1, the switching value signal of the first switch module is a close signal and the switching value signal of the second switch module is a close signal; the control unit generates a second alarm signal and sends the second alarm signal to the communication unit. At this time, the system determines that the switch loop unit is abnormal, and power supply switching cannot be performed, and abnormal information needs to be reported through the network.
S3: and the communication unit generates alarm information according to the alarm signal and finishes reporting.
Specifically, the method comprises the following steps:
after receiving the first alarm signal, the communication unit converts the first alarm signal into power-shortage alarm information and sends the power-shortage alarm information to a preset monitoring server through a network; and after receiving the second alarm signal, the communication unit converts the second alarm signal into line abnormal alarm information and sends the line abnormal alarm information to the preset monitoring server through the network.
In the embodiments provided by the present invention, it should be understood that the disclosed system, system and method can be implemented in other ways. For example, the above-described system embodiments are merely illustrative, and for example, the division of the units is only one logical functional division, and other divisions may be realized in practice, for example, a plurality of units or components may be combined or integrated into another system, or some features may be omitted, or not executed. In addition, the shown or discussed mutual coupling or direct coupling or communication connection may be an indirect coupling or communication connection through some interfaces, systems or units, and may be in an electrical, mechanical or other form.
The units described as separate parts may or may not be physically separate, and parts displayed as units may or may not be physical units, may be located in one place, or may be distributed on a plurality of network units. Some or all of the units can be selected according to actual needs to achieve the purpose of the solution of the embodiment.
In addition, functional modules in the embodiments of the present invention may be integrated into one processing unit, or each module may exist alone physically, or two or more modules are integrated into one unit.
Similarly, each processing unit in the embodiments of the present invention may be integrated into one functional module, or each processing unit may exist physically, or two or more processing units are integrated into one functional module.
The invention is further described with reference to the accompanying drawings and specific embodiments. It should be understood that these examples are for illustrative purposes only and are not intended to limit the scope of the present invention. Further, it should be understood that various changes or modifications of the present invention may be made by those skilled in the art after reading the teaching of the present invention, and these equivalents also fall within the scope of the present application.

Claims (8)

1. A backup power supply system for an intelligent electric energy meter, comprising: the device comprises a control unit, a communication unit, a power supply unit, a clock unit, a standby power supply unit, a switch loop unit and a voltage detection unit; the control unit is respectively in signal connection with the communication unit, the clock unit, the switch loop unit and the voltage detection unit, the voltage detection unit is in signal connection with the switch loop unit, the power supply unit is respectively in electric connection with the control unit and the switch loop unit, the standby power supply unit is respectively in electric connection with the control unit and the switch loop unit, and the switch loop unit is respectively in electric connection with the clock unit and the communication unit;
the control unit is used for sending a switching signal to the switching loop unit, and controlling the switching loop unit to supply power to the clock unit and the communication unit by using the power supply unit or the standby power supply unit;
and the voltage detection unit is used for monitoring the voltage of the switch loop unit in real time, converting the voltage value into a digital signal and sending the digital signal to the control unit.
2. The standby power supply system for the intelligent electric energy meter according to claim 1, wherein a first switch module is arranged in the switch loop unit, the first switch module is electrically connected with the power supply unit and used for controlling the power supply unit to be switched on or switched off according to a control signal of the control unit, and the first switch module sends a current switching value signal to the control unit.
3. The backup power supply system for intelligent electric energy meter according to claim 2, characterized in that said backup power supply system is configured to supply power to said intelligent electric energy meter
And a second switch module is arranged in the power supply device, is electrically connected with the standby power supply unit and is used for controlling the connection or disconnection of the power supply unit according to the control signal of the control unit, and sends the current switching value signal to the control unit.
4. The standby power supply system for the intelligent electric energy meter according to claim 3, wherein when the voltage detection unit monitors that the voltage of the switch loop unit is lower than a preset threshold value, the voltage detection unit converts the voltage value into a digital signal and sends the digital signal to the control unit, and simultaneously sends a low-voltage alarm signal to the control unit; and after receiving the low-voltage alarm signal, the control unit sends a control signal to the switch loop unit according to the power supply switching strategy to carry out power supply switching.
5. The backup power supply system for an intelligent electric energy meter according to claim 4, wherein the power supply switching strategy comprises:
the control unit respectively reads the current switching value signals of the first switch module and the second switch module, and if the switching value signal of the first switch module is a closing signal and the switching value signal of the second switch module is an opening signal; the control unit sends an open signal to the first switch module and simultaneously sends a close signal to the second switch module.
6. The backup power supply system for an intelligent electric energy meter according to claim 5, wherein the power switching strategy further comprises:
if the switching value signal of the first switching module is an opening signal and the switching value signal of the second switching module is a closing signal; the control unit generates a first alarm signal and sends the first alarm signal to the communication unit.
7. The backup power supply system for intelligent electric energy meter according to claim 6, wherein said power supply switching strategy comprises:
if the switching value signal of the first switching module is a closing signal and the switching value signal of the second switching module is a closing signal; the control unit generates a second alarm signal and sends the second alarm signal to the communication unit.
8. The standby power supply system for the intelligent electric energy meter according to claim 7, wherein the communication unit converts the first alarm signal into power shortage alarm information after receiving the first alarm signal, and sends the power shortage alarm information to a preset monitoring server through a network;
and after receiving the second alarm signal, the communication unit converts the second alarm signal into line abnormal alarm information and sends the line abnormal alarm information to the preset monitoring server through the network.
CN202110475859.8A 2021-04-29 2021-04-29 Standby power supply system for intelligent electric energy meter Pending CN113178941A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110475859.8A CN113178941A (en) 2021-04-29 2021-04-29 Standby power supply system for intelligent electric energy meter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110475859.8A CN113178941A (en) 2021-04-29 2021-04-29 Standby power supply system for intelligent electric energy meter

Publications (1)

Publication Number Publication Date
CN113178941A true CN113178941A (en) 2021-07-27

Family

ID=76925410

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110475859.8A Pending CN113178941A (en) 2021-04-29 2021-04-29 Standby power supply system for intelligent electric energy meter

Country Status (1)

Country Link
CN (1) CN113178941A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114301162A (en) * 2022-01-05 2022-04-08 京东方科技集团股份有限公司 Power supply system and power supply method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106157594A (en) * 2016-08-12 2016-11-23 北京溢美四方软件技术有限公司 The intelligent electric meter communication unit of a kind of built-in stand-by power supply and control method
CN107490706A (en) * 2017-08-15 2017-12-19 国网重庆市电力公司电力科学研究院 A kind of novel intelligent electric energy meter based on super capacitor power supply
CN108270283A (en) * 2016-12-30 2018-07-10 孙麓轩 Prepared auto restart control system
CN109633432A (en) * 2019-01-10 2019-04-16 常熟开关制造有限公司(原常熟开关厂) Automatic change-over failure modes diagnostic method, device and automatic change-over
CN110707809A (en) * 2019-11-25 2020-01-17 国网新疆电力有限公司乌鲁木齐供电公司 Automatic switching alarm device between independent UPS of transformer substation
US20210066959A1 (en) * 2019-08-30 2021-03-04 Schneider Electric It Corporation Uninterruptible power system bypass switch control

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106157594A (en) * 2016-08-12 2016-11-23 北京溢美四方软件技术有限公司 The intelligent electric meter communication unit of a kind of built-in stand-by power supply and control method
CN108270283A (en) * 2016-12-30 2018-07-10 孙麓轩 Prepared auto restart control system
CN107490706A (en) * 2017-08-15 2017-12-19 国网重庆市电力公司电力科学研究院 A kind of novel intelligent electric energy meter based on super capacitor power supply
CN109633432A (en) * 2019-01-10 2019-04-16 常熟开关制造有限公司(原常熟开关厂) Automatic change-over failure modes diagnostic method, device and automatic change-over
US20210066959A1 (en) * 2019-08-30 2021-03-04 Schneider Electric It Corporation Uninterruptible power system bypass switch control
CN110707809A (en) * 2019-11-25 2020-01-17 国网新疆电力有限公司乌鲁木齐供电公司 Automatic switching alarm device between independent UPS of transformer substation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
齐伟 等: "《城市轨道交通通信与信号》", 31 January 2018 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114301162A (en) * 2022-01-05 2022-04-08 京东方科技集团股份有限公司 Power supply system and power supply method

Similar Documents

Publication Publication Date Title
CN102325149B (en) Intelligent network remote terminal unit (RTU) system of electrified railway
CN201466500U (en) Multifunctional intelligent power distribution box
CN209167449U (en) Telegraph circuit in a kind of power failure applied to HPLC carrier communication module
CN201414021Y (en) Intelligent power distribution system for telecommunication room
CN108565960A (en) A kind of DTU distribution terminals super capacitor backup power system
CN102931731A (en) Integrated intelligent monitoring system applicable to substation direct-current power supply
CN203135574U (en) Intelligent monitoring terminal of distribution transformer
CN102611196A (en) 10KV power grid state monitoring and fault process automation system
CN103529290A (en) Three-phase intelligent meter capable of acquiring information of power distribution and power utilization
CN113178941A (en) Standby power supply system for intelligent electric energy meter
CN103941193A (en) Online monitoring system for storage battery set through mobile phone
CN202127287U (en) Automatic remote terminal of distribution line
CN208806479U (en) A kind of power distribution network ring network cabinet of automatic improving
CN201717677U (en) Distribution transformer failure monitoring terminal
CN204465412U (en) A kind of photovoltaic generating system intelligentized control method complete machine device
CN214755720U (en) Differentiation of 5G basic station is equipped with electric intelligent control equipment
CN211209379U (en) Distribution terminal full coverage area distributed self-healing system
CN201234153Y (en) DC electric power cabinet controller
CN208571692U (en) A kind of circuit reporting working power power fail warning automatically
CN111799884A (en) Power supply switching device for user metering and collecting terminal
CN208638329U (en) A kind of intelligent safety monitoring protection system for photovoltaic generating module
CN101552487A (en) Uninterrupted power supply for battery pack vulcanization prevention and online capacity measurement
CN201629603U (en) Battery monitoring management system based on uninterruptible switch power source
CN221103050U (en) Power distribution terminal power supply device
CN212588141U (en) Power supply switching device for user metering and collecting terminal

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210727

RJ01 Rejection of invention patent application after publication