[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN112302350A - Construction scheme of engineering helicopter in transportation aspect of high-voltage line tower - Google Patents

Construction scheme of engineering helicopter in transportation aspect of high-voltage line tower Download PDF

Info

Publication number
CN112302350A
CN112302350A CN201910680753.4A CN201910680753A CN112302350A CN 112302350 A CN112302350 A CN 112302350A CN 201910680753 A CN201910680753 A CN 201910680753A CN 112302350 A CN112302350 A CN 112302350A
Authority
CN
China
Prior art keywords
tower
tower section
hoisted
helicopter
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910680753.4A
Other languages
Chinese (zh)
Inventor
璧典寒
赵亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201910680753.4A priority Critical patent/CN112302350A/en
Publication of CN112302350A publication Critical patent/CN112302350A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C25/00Cranes not provided for in groups B66C17/00 - B66C23/00

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Electric Cable Installation (AREA)

Abstract

The invention provides a construction scheme of an engineering helicopter in the aspect of high-voltage line tower transportation, which comprises the following steps: construction preparation; assembling the hoisted tower sections; respectively installing a set of butt joint auxiliary system on the hoisted tower section and the positioned tower section; the outer sides of two adjacent horizontal limiting devices are connected with limiting ropes; the method comprises the following steps that a hanging device is used for hanging a hung tower section below the belly of the helicopter, and then the hung tower section is hoisted to be close to a tower section in place; the engineering helicopter adjusts the position of the hoisted tower section and falls to a certain height from the ground, and ground auxiliary personnel connect the control rope to the connecting plate; the engineering helicopter lifts the hoisted tower section to the position above the tower section, and finds the position center and hovers under the action of the butt joint auxiliary system; the ground auxiliary personnel tighten the four control ropes to enable four sides of the hoisted tower section and the positioning tower section to be aligned in parallel in the overlooking plane; the tower crane section smoothly slides into the installation position by means of the butt joint auxiliary system, the tower crane section is accurately in butt joint with the tower section in place, and finally the tower crane section is placed on a platform of the vertical limiting device.

Description

Construction scheme of engineering helicopter in transportation aspect of high-voltage line tower
Technical Field
The invention belongs to the field of engineering construction. In particular to a construction scheme of an engineering helicopter in the aspect of transportation of a high-voltage line tower.
Background
With the large-scale construction of extra-high voltage transmission line engineering, the demand cannot be met by adopting a cableway transportation mode, the territory of China is wide, the transportation of a plurality of high-voltage line towers needs to pass through dense vegetation, river valleys, plateau deserts and mountains, a plurality of construction sites are located in mountainous areas, the difficulties caused by the territory environment can be overcome by adopting the engineering helicopter transportation, the engineering helicopter transportation becomes the mainstream, and therefore, the construction scheme of the engineering helicopter in the aspect of the high-voltage line tower transportation is developed.
With the large-scale construction of the ultra-high voltage transmission line engineering, the engineering helicopter becomes an important choice for solving the extreme construction problem of the mountain construction in the engineering. However, the usage cost of the helicopter, which is a core device for hoisting and tower assembling operation, is relatively high, and relates to hoisting of multiple crossed operation surfaces such as the helicopter, a ground material assembling yard, an operation tower position and the like, the operation mode of the helicopter must be reasonably planned, personnel and construction resources are effectively allocated, the efficiency of the helicopter is fully exerted, and the operation cost can be further reduced. The invention analyzes the hoisting operation cost of the helicopter and comprehensively optimizes the operation mode.
Disclosure of Invention
Aiming at the defects in the prior art, the construction scheme of the engineering helicopter in the aspect of high-voltage line tower transportation overcomes the transportation difficulty caused by regional environment, and the high-voltage line tower transportation is faster and more efficient.
In order to achieve the purpose, the technical scheme of the invention is as follows:
a construction scheme of an engineering helicopter in the aspect of high-voltage line tower transportation comprises the following steps:
1) construction preparation, namely, carrying out sufficient construction preparation before formally carrying out the tower hoisting of the engineering helicopter, wherein the construction preparation comprises site arrangement, personnel coordination, communication guarantee, meteorological monitoring, iron tower protection and the like; in the process that the hoisting section of the iron tower is gradually hoisted from the horizontal position, the tower material at the root part of the hoisting section is greatly stressed, and the tower material at the root part is possibly abraded due to the fact that the hoisting section is driven by the engineering helicopter to slide on the ground; therefore, round timbers are bound by thin iron wires at the inner sides of the tower materials at the root parts of the hoisting sections, and extend out of the root parts of the tower materials, so that the tower materials can be prevented from being worn in the hoisting process; in addition, the auxiliary material is used for connecting the four main materials at the root of the hoisting section, so that the bearing capacity of the hoisting section is improved;
2) assembling the hoisted tower section in a ground assembly yard, and accurately measuring to ensure that the size of the connecting position of the hoisted tower section and the positioned tower section meets the installation requirement;
3) a set of butt joint auxiliary system is respectively arranged at the four connecting main materials of the hoisted tower section and the positioned tower section, so that the butt joint auxiliary system is ensured to be accurately and stably arranged;
4) a horizontal limiting rope is connected between the outer connecting rings of two adjacent horizontal limiting devices to provide a wider limiting range for the position of the hoisted tower section; the limiting rope can use a turn buckle, and a steel wire rope is connected between the limiting rope and the turn buckle as the limiting rope; the steel wire rope should be slightly loosened so as to prevent the main material of the iron tower from deforming to change the size;
5) the method comprises the following steps that a hanging device is used for hanging a hung tower section below the belly of the engineering helicopter, and then the hung tower section is hoisted to be close to a tower section in place; the hoisting process is stable and slow, and the hoisted tower section is prevented from sliding on the ground or colliding with the ground;
6) the engineering helicopter adjusts the direction of the hoisted tower section, slowly falls to a certain height from the ground, and ground auxiliary personnel quickly connect the control rope which passes through the waist ring of the vertical limiting device to the connecting plate of the horizontal limiting device; because the four corners of the iron tower are provided with the control ropes, four ground auxiliary personnel are required to be connected at the same time; in addition, in order to shorten the connection time, a connection hole is formed in the connection plate, an S-shaped hook is tied at the end of the control rope, and ground auxiliary personnel only need to hook the hook into the connection hole;
7) the engineering helicopter lifts the hoisted tower section to the position above the tower section, and the engineering helicopter finds the position center and hovers under the auxiliary action of the horizontal limiting device in the butt joint auxiliary system; the ascending process is slow, and the control rope is prevented from being wound with the iron tower;
8) the ground auxiliary personnel tighten the four control ropes to enable four sides of the hoisted tower section and the tower section in position to be aligned in parallel in a top plane, so that the situation that the hoisted tower section cannot be accurately positioned due to the fact that the second control rope is twisted at the vertical center of the hanger is avoided;
9) the engineering helicopter driver gradually reduces the hovering height, so that the hoisted tower section smoothly slides into the installation position under the guiding action of the guiding device in the butt joint auxiliary system, the hoisted tower section and the tower section in position are accurately butted in position, and finally the hoisted tower section is placed on a platform of the vertical limiting device;
10) the engineering helicopter flies away after loosening the connection with the hoisted tower section, constructors climb the tower and connect the tower section in place with the connecting angle steel by using bolts, thereby realizing the connection between the hoisted tower section and the tower section in place;
11) dismantling all devices of the butt joint auxiliary system so as to complete the engineering helicopter assembly of the hung tower section;
12) and (4) assembling the subsequent tower sections according to the steps, thereby completing the construction of the engineering helicopter assembly of the whole foundation iron tower.
Furthermore, the engineering helicopter is like a dragonfly, adopts a 6-blade rotor wing with the diameter of 21.95 meters, is used for hoisting external goods through a beam type fuselage, adopts a front three-point landing gear, and is provided with a tail pry at the tail end of a tail beam; the engineering helicopter can bear 200 tons at maximum.
Has the advantages that: the construction scheme of the engineering helicopter in the aspect of high-voltage line tower transportation overcomes the transportation difficulty caused by regional environment, and is quicker and more efficient than cableway transportation.
Drawings
Fig. 1 is a schematic diagram of a construction scheme of an engineering helicopter in the aspect of transportation of a high-voltage line tower.
Detailed Description
The invention is illustrated below with reference to specific examples. It will be understood by those skilled in the art that these examples are for illustrative purposes only and are not intended to limit the scope of the present invention in any way.
A construction scheme of an engineering helicopter in the aspect of high-voltage line tower transportation comprises the following steps:
1) construction preparation, namely, carrying out sufficient construction preparation before formally carrying out the tower hoisting of the engineering helicopter, wherein the construction preparation comprises site arrangement, personnel coordination, communication guarantee, meteorological monitoring, iron tower protection and the like; in the process that the hoisting section of the iron tower is gradually hoisted from the horizontal position, the tower material at the root part of the hoisting section is greatly stressed, and the tower material at the root part is possibly abraded due to the fact that the hoisting section is driven by the engineering helicopter to slide on the ground; therefore, round timbers are bound by thin iron wires at the inner sides of the tower materials at the root parts of the hoisting sections, and extend out of the root parts of the tower materials, so that the tower materials can be prevented from being worn in the hoisting process. In addition, the auxiliary material is used for connecting the four main materials at the root of the hoisting section, so that the bearing capacity of the hoisting section is improved;
2) assembling the hoisted tower section in a ground assembly yard, and accurately measuring to ensure that the size of the connecting position of the hoisted tower section and the positioned tower section meets the installation requirement;
3) a set of butt joint auxiliary system is respectively arranged at the four connecting main materials of the hoisted tower section and the positioned tower section, so that the butt joint auxiliary system is ensured to be accurately and stably arranged;
4) a horizontal limiting rope is connected between the outer connecting rings of two adjacent horizontal limiting devices to provide a wider limiting range for the position of the hoisted tower section; the limiting rope can use a turn buckle, and a steel wire rope is connected between the limiting rope and the turn buckle as the limiting rope; the steel wire rope should be slightly loosened so as to prevent the main material of the iron tower from deforming to change the size;
5) the method comprises the following steps that a hanging device is used for hanging a hung tower section below the belly of the helicopter, and then the hung tower section is hoisted to be close to a tower section in place; the hoisting process is stable and slow, and the hoisted tower section is prevented from sliding on the ground or colliding with the ground;
6) the engineering helicopter adjusts the direction of the hoisted tower section, slowly falls to a certain height from the ground, and ground auxiliary personnel quickly connect the control rope which passes through the waist ring of the vertical limiting device to the connecting plate of the horizontal limiting device; because the four corners of the iron tower are provided with the control ropes, four ground auxiliary personnel are required to be connected at the same time; in addition, in order to shorten the connection time, a connection hole is formed in the connection plate, an S-shaped hook is tied at the end of the control rope, and ground auxiliary personnel only need to hook the hook into the connection hole;
7) the engineering helicopter lifts the hoisted tower section to the position above the tower section, and the engineering helicopter finds the position center and hovers under the auxiliary action of the horizontal limiting device in the butt joint auxiliary system; the ascending process is slow, and the control rope is prevented from being wound with the iron tower;
8) the ground auxiliary personnel tighten the four control ropes to enable four sides of the hoisted tower section and the tower section in position to be aligned in parallel in a top plane, so that the situation that the hoisted tower section cannot be accurately positioned due to the fact that the second control rope is twisted at the vertical center of the hanger is avoided;
9) the engineering helicopter driver gradually reduces the hovering height, so that the hoisted tower section smoothly slides into the installation position under the guiding action of the guiding device in the butt joint auxiliary system, the hoisted tower section and the tower section in position are accurately butted in position, and finally the hoisted tower section is placed on a platform of the vertical limiting device;
10) the engineering helicopter flies away after loosening the connection with the hoisted tower section, constructors climb the tower and connect the tower section in place with the connecting angle steel by using bolts, thereby realizing the connection between the hoisted tower section and the tower section in place;
11) dismantling all devices of the butt joint auxiliary system so as to complete the engineering helicopter assembly of the hung tower section;
12) and (4) assembling the subsequent tower sections according to the steps, thereby completing the construction of the engineering helicopter assembly of the whole foundation iron tower.
The engineering helicopter is similar to a dragonfly, adopts a 6-blade rotor wing with the diameter of 21.95 meters, is used for hoisting external goods through a beam type fuselage, adopts a front three-point landing gear, and is provided with a tail pry at the tail end of a tail beam.

Claims (2)

1. A construction scheme of an engineering helicopter in the aspect of high-voltage line tower transportation is characterized in that: the method comprises the following steps:
1) construction preparation, namely, carrying out sufficient construction preparation before formally carrying out the tower hoisting of the engineering helicopter, wherein the construction preparation comprises site arrangement, personnel coordination, communication guarantee, meteorological monitoring, iron tower protection and the like; in the process that the hoisting section of the iron tower is gradually hoisted from the horizontal position, the tower material at the root part of the hoisting section is greatly stressed, and the tower material at the root part is possibly abraded due to the fact that the hoisting section is driven by the engineering helicopter to slide on the ground; therefore, round timbers are bound by thin iron wires at the inner sides of the tower materials at the root parts of the hoisting sections, and extend out of the root parts of the tower materials, so that the tower materials can be prevented from being worn in the hoisting process; in addition, the auxiliary material is used for connecting the four main materials at the root of the hoisting section, so that the bearing capacity of the hoisting section is improved;
2) assembling the hoisted tower section in a ground assembly yard, and accurately measuring to ensure that the size of the connecting position of the hoisted tower section and the positioned tower section meets the installation requirement;
3) a set of butt joint auxiliary system is respectively arranged at the four connecting main materials of the hoisted tower section and the positioned tower section, so that the butt joint auxiliary system is ensured to be accurately and stably arranged;
4) a horizontal limiting rope is connected between the outer connecting rings of two adjacent horizontal limiting devices to provide a wider limiting range for the position of the hoisted tower section; the limiting rope can use a turn buckle, and a steel wire rope is connected between the limiting rope and the turn buckle as the limiting rope; the steel wire rope should be slightly loosened so as to prevent the main material of the iron tower from deforming to change the size;
5) the method comprises the following steps that a hanging device is used for hanging a hung tower section below the belly of the engineering helicopter, and then the hung tower section is hoisted to be close to a tower section in place; the hoisting process is stable and slow, and the hoisted tower section is prevented from sliding on the ground or colliding with the ground;
6) the engineering helicopter adjusts the direction of the hoisted tower section, slowly falls to a certain height from the ground, and ground auxiliary personnel quickly connect the control rope which passes through the waist ring of the vertical limiting device to the connecting plate of the horizontal limiting device; because the four corners of the iron tower are provided with the control ropes, four ground auxiliary personnel are required to be connected at the same time; in addition, in order to shorten the connection time, a connection hole is formed in the connection plate, an S-shaped hook is tied at the end of the control rope, and ground auxiliary personnel only need to hook the hook into the connection hole;
7) the engineering helicopter lifts the hoisted tower section to the position above the tower section, and the engineering helicopter finds the position center and hovers under the auxiliary action of the horizontal limiting device in the butt joint auxiliary system; the ascending process is slow, and the control rope is prevented from being wound with the iron tower;
8) the ground auxiliary personnel tighten the four control ropes to enable four sides of the hoisted tower section and the tower section in position to be aligned in parallel in a top plane, so that the situation that the hoisted tower section cannot be accurately positioned due to the fact that the second control rope is twisted at the vertical center of the hanger is avoided;
9) the engineering helicopter driver gradually reduces the hovering height, so that the hoisted tower section smoothly slides into the installation position under the guiding action of the guiding device in the butt joint auxiliary system, the hoisted tower section and the tower section in position are accurately butted in position, and finally the hoisted tower section is placed on a platform of the vertical limiting device;
10) the engineering helicopter flies away after loosening the connection with the hoisted tower section, constructors climb the tower and connect the tower section in place with the connecting angle steel by using bolts, thereby realizing the connection between the hoisted tower section and the tower section in place;
11) dismantling all devices of the butt joint auxiliary system so as to complete the engineering helicopter assembly of the hung tower section;
12) and (4) assembling the subsequent tower sections according to the steps, thereby completing the construction of the engineering helicopter assembly of the whole foundation iron tower.
2. The project helicopter of claim 1, wherein the project helicopter is like a dragonfly, and is provided with a 6-blade rotor with a diameter of 21.95 m, a beam body for lifting external goods, a front three-point landing gear, and a tail pry at the tail end of the tail beam.
CN201910680753.4A 2019-07-26 2019-07-26 Construction scheme of engineering helicopter in transportation aspect of high-voltage line tower Pending CN112302350A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910680753.4A CN112302350A (en) 2019-07-26 2019-07-26 Construction scheme of engineering helicopter in transportation aspect of high-voltage line tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910680753.4A CN112302350A (en) 2019-07-26 2019-07-26 Construction scheme of engineering helicopter in transportation aspect of high-voltage line tower

Publications (1)

Publication Number Publication Date
CN112302350A true CN112302350A (en) 2021-02-02

Family

ID=74329610

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910680753.4A Pending CN112302350A (en) 2019-07-26 2019-07-26 Construction scheme of engineering helicopter in transportation aspect of high-voltage line tower

Country Status (1)

Country Link
CN (1) CN112302350A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114319992A (en) * 2021-12-28 2022-04-12 国网天津市电力公司建设分公司 Electric iron tower subsection assembling construction method adopting automatic butt joint device

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005139607A (en) * 2003-11-04 2005-06-02 Kansai Electric Power Co Inc:The Steel tower assembling construction method by helicopter and work tool
AU2006203572A1 (en) * 2005-08-12 2007-03-08 Mack Innovations (Australia) Pty Ltd Cable pulling apparatus for helicopters
CN101054114A (en) * 2007-05-16 2007-10-17 陈复树 Vehicle-ship carrying electric lifter
CN103031978A (en) * 2012-12-12 2013-04-10 中国电力科学研究院 Installation assisting system for erection of power transmission line iron tower and erection method for iron tower
CN105464456A (en) * 2015-12-30 2016-04-06 国家电网公司 Method and lifting sling for assembling extra-high voltage transmission iron tower through helicopter
CN106245986A (en) * 2016-10-11 2016-12-21 国家电网公司 The method for assembling of power network line steel tower and device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005139607A (en) * 2003-11-04 2005-06-02 Kansai Electric Power Co Inc:The Steel tower assembling construction method by helicopter and work tool
AU2006203572A1 (en) * 2005-08-12 2007-03-08 Mack Innovations (Australia) Pty Ltd Cable pulling apparatus for helicopters
CN101054114A (en) * 2007-05-16 2007-10-17 陈复树 Vehicle-ship carrying electric lifter
CN103031978A (en) * 2012-12-12 2013-04-10 中国电力科学研究院 Installation assisting system for erection of power transmission line iron tower and erection method for iron tower
CN105464456A (en) * 2015-12-30 2016-04-06 国家电网公司 Method and lifting sling for assembling extra-high voltage transmission iron tower through helicopter
CN106245986A (en) * 2016-10-11 2016-12-21 国家电网公司 The method for assembling of power network line steel tower and device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
缪谦: "直升机组立输电线路铁塔施工技术", 《施工技术》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114319992A (en) * 2021-12-28 2022-04-12 国网天津市电力公司建设分公司 Electric iron tower subsection assembling construction method adopting automatic butt joint device
CN114319992B (en) * 2021-12-28 2023-06-13 国网天津市电力公司建设分公司 Electric iron tower sectional assembly construction method adopting automatic butt joint device

Similar Documents

Publication Publication Date Title
US10012005B2 (en) Crane system incorporated into a tower
KR20160148682A (en) Method and system for de-erection and re-erection of a blade of a wind turbine
CN100519396C (en) Gin pole integrated dismounting method for tower crane
CN107013038B (en) A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
CN111042540A (en) Construction method for aerial butt joint of ground suspension cables of super-large-span prestressed pipe truss
CN106698208B (en) A kind of hanging device and hanging method for being transported outside high-rise building
US10519687B2 (en) Method of erecting a tethered wind turbine tower
CN112302350A (en) Construction scheme of engineering helicopter in transportation aspect of high-voltage line tower
CN101481903A (en) Method for erecting main truss of suspension bridge in mountain area by reversely assembling cross-cable cranes
CN208932821U (en) A kind of erecting beam construction height leg gantry crane
CN103696569B (en) Overhead steel-beam platform dismounting device and method
CN209081290U (en) Bailey truss pylon and distributing earth anchor CABLEWAY ERECTION SYSTEM that can be traversing
ES2865455T3 (en) A method and set for handling wind turbine blades
CN110184898A (en) The steel skeleton segment of Cable stayed Bridge Main Tower anchorage zone and king-post construction method
CN101818563A (en) Jack-up integral lifting mobile platform and using method
CN204609435U (en) The auxiliary tower that hoists of emergent repairing tower
CN203794505U (en) Internal climbing steel beam conveying device of internal climbing movable arm tower crane
CN201980890U (en) Herringbone hoisting mast for hoisting under special situation of high altitude
CN110512910A (en) A kind of steel-making main building height integrally increases installation method across steel construction
CN210505201U (en) Equipment for hoisting reinforcing steel bars in batches
CN115324416A (en) Integral hoisting construction process for iron tower
CN208966123U (en) A kind of big section lattice steel tube holding pole formal dress lifting device
CN105887701A (en) Suspension bridge superstructure demolition and replacement installation method
WO2016076683A1 (en) Method for mounting a tower support
CN105438971A (en) Precise type pole-tower lifting device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210202

RJ01 Rejection of invention patent application after publication