[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN112302209A - Steel and concrete shear wall mixed structure and manufacturing method thereof - Google Patents

Steel and concrete shear wall mixed structure and manufacturing method thereof Download PDF

Info

Publication number
CN112302209A
CN112302209A CN202011130788.XA CN202011130788A CN112302209A CN 112302209 A CN112302209 A CN 112302209A CN 202011130788 A CN202011130788 A CN 202011130788A CN 112302209 A CN112302209 A CN 112302209A
Authority
CN
China
Prior art keywords
plate
steel
bearing surface
connecting plate
shear wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011130788.XA
Other languages
Chinese (zh)
Other versions
CN112302209B (en
Inventor
马全涛
周绪红
刘界鹏
许光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Rizhao Daxiang House Construction Co ltd
Original Assignee
Rizhao Daxiang House Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rizhao Daxiang House Construction Co ltd filed Critical Rizhao Daxiang House Construction Co ltd
Priority to CN202011130788.XA priority Critical patent/CN112302209B/en
Publication of CN112302209A publication Critical patent/CN112302209A/en
Application granted granted Critical
Publication of CN112302209B publication Critical patent/CN112302209B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/58Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/08Forms, which are completely dismantled after setting of the concrete and re-built for next pouring
    • E04G11/085End form panels for walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Abstract

A steel and concrete shear wall mixed structure and a manufacturing method thereof relate to the technical field of building toughening structures, and particularly belong to a steel and concrete shear wall mixed structure and a manufacturing method thereof. The steel structure comprises a vertical column which is vertically communicated, wherein a plurality of beam supports are arranged outside the vertical column at intervals along the length direction, each beam support is a vertically communicated steel structure body, a fixing plate, a connecting plate and a side sealing plate are arranged on the side surface of each steel structure body, the fixing plates are fixedly connected with the vertical column, and the connecting plates are fixedly connected with a connecting plate at the end part of a cross beam; the upper part of the side sealing plate is connected with a tooth plate; the upper edges of the fixed plate, the connecting plate and the side sealing plates form an upper bearing surface, the lower edges of the fixed plate, the connecting plate and the side sealing plates form a lower bearing surface, and the upper bearing surface and the lower bearing surface are respectively matched with the lower end surface and the upper end surface of the cast-in-place wallboard template; the beam support and the cast-in-place wallboard template are matched and connected in sequence. The concrete connecting layer is poured into the cavity formed by the upright columns and the wall body after being connected with the connecting beams, and the upright columns and the wall body are integrally poured, so that the overall strength of the shear wall is increased.

Description

Steel and concrete shear wall mixed structure and manufacturing method thereof
Technical Field
The invention relates to the technical field of building toughened structures, in particular to a steel and concrete shear wall mixed structure and a manufacturing method thereof.
Background
Compared with the traditional concrete building, the steel structure building has the advantages of energy conservation, material conservation, environmental protection, good economic benefit and the like, and gradually becomes a new building system for replacing a brick-concrete structure. The existing steel structure building uses a cold-bending thin-wall steel frame structure, and has poor strength and complex assembly.
Disclosure of Invention
The invention aims to provide a steel and concrete shear wall mixed structure and a manufacturing method thereof, so as to achieve the purposes of improving the overall strength and safety of a building and optimizing an assembly process.
The invention provides a steel and concrete shear wall mixed structure which is characterized by comprising a vertical column which is vertically through, wherein a plurality of beam supports are arranged outside the vertical column at intervals along the length direction, each beam support is a steel structure body which is through up and down, a fixing plate, a connecting plate and a side sealing plate are arranged on the side surface of the steel structure body, the fixing plate is fixedly connected with the vertical column, and the connecting plate is fixedly connected with a connecting plate at the end part of a cross beam; the upper part of the side sealing plate is connected with a tooth plate; the upper edges of the fixed plate, the connecting plate and the side sealing plates form an upper bearing surface, the lower edges of the fixed plate, the connecting plate and the side sealing plates form a lower bearing surface, and the upper bearing surface and the lower bearing surface are respectively matched with the lower end surface and the upper end surface of the cast-in-place wallboard template; the beam support and the cast-in-place wallboard template are matched and connected in sequence.
Furthermore, through holes are formed in the positions, corresponding to the fixing plates of the upright posts and the beam supports, of the fixing plates.
Furthermore, the cast-in-place wallboard template is formed by splicing a plurality of U-shaped templates, and the U-shaped templates can be repeatedly used.
The invention provides a manufacturing method of a steel and concrete shear wall mixed structure, which is characterized by comprising the following steps of:
a) selecting a steel plate, blanking according to the number of drawings by using a laser cutting machine, and preparing a stand column side plate, a fixed plate, a connecting plate and a side sealing plate according to the sizes of the drawings; processing through holes, mounting holes and tooth plates at corresponding positions;
b) conveying the U-shaped template to an assembly site;
c) mounting the side plate of the upright column on a fixture, welding a nut at the mounting hole at the inner side of the side plate, aligning the edges of the side plate of the upright column on the fixture, and welding to manufacture the upright column;
d) welding a nut to the mounting hole on the inner side of the connecting plate in advance on a nut projection welding machine;
e) placing the fixing plate, the connecting plate and the side sealing plate which are subjected to laser cutting on corresponding welding fixtures, clamping the parts by using a manual clamping device, and welding the abutted seams to form a beam support;
f) hoisting and moving the beam support to a clamp provided with an upright column, matching a bolt with a nut welded in advance, and fixedly connecting the beam support to the upright column through a fixing plate;
g) binding a steel bar frame in the upper and lower through areas of the beam support;
h) and mutually splicing and installing and fixing the U-shaped formworks between the lower bearing surface and the upper bearing surface of the beam support, and fixing the U-shaped formworks by using auxiliary fixing equipment to finish the assembly of the steel and concrete shear wall mixed structure.
The steel and concrete shear wall mixed structure and the manufacturing method thereof provided by the invention have the advantages that the beam support with a special structure is provided, the strength and the shock resistance of the wall are increased, the U-shaped template can be repeatedly utilized, the resources are saved, the installation mode is optimized, the assembly and the construction are convenient, and the working efficiency is improved. The concrete connecting layer is poured into the cavity formed by the upright columns and the wall body after being connected with the connecting beams, and the upright columns and the wall body are integrally poured, so that the overall strength of the shear wall is increased.
Drawings
The accompanying drawings disclose, in part, specific embodiments of the present invention, wherein,
figure 1 is a schematic structural view of the present invention,
figure 2 is a schematic structural view of the beam support of the present invention,
FIG. 3 is a schematic diagram of the present invention.
Detailed Description
As shown in fig. 1-3, the invention provides a steel and concrete shear wall mixed structure, which comprises a vertically through square upright post 3, wherein a plurality of beam supports 1 are arranged on the outer side surface of the upright post at intervals along the length direction, through holes and through holes are arranged on the matching surface of the upright post and the beam supports, and nuts are welded on the inner side of the through holes in advance. The beam support is a vertically-through steel structure body which is formed by welding a fixing plate 1-1, a connecting plate 1-2 and side sealing plates 1-3, through holes and through holes 1-5 are formed in corresponding positions on the fixing plate, and the fixing plate is fixedly connected with nuts welded on the inner sides of the upright columns in advance through bolts; a through hole is formed in the connecting plate, a nut is welded in advance at the corresponding position of the through hole, and the end part of the cross beam 4 is fixedly connected with the through hole through a bolt; the upper part of the matching plate is connected with dental plates 1-4, the upper edge of the fixing plate, the connecting plate and the side sealing plate forms an upper bearing surface, the lower edge of the fixing plate, the connecting plate and the side sealing plate forms a lower bearing surface, the upper bearing surface and the lower bearing surface are matched with a cast-in-place wallboard template and fixed through an auxiliary fixing structure, and the beam support and the cast-in-place wallboard template are sequentially connected.
In a specific embodiment, the manufacturing method of the steel and concrete shear wall mixed structure comprises the following steps:
a) selecting a steel plate, blanking according to the number of drawings by using a laser cutting machine, and preparing a stand column side plate, a fixed plate, a connecting plate and a side sealing plate according to the sizes of the drawings; processing through holes, mounting holes and tooth plates at corresponding positions;
b) conveying the U-shaped template to an assembly site;
c) mounting the side plate of the upright column on a fixture, welding a nut at the mounting hole at the inner side of the side plate, aligning the edges of the side plate of the upright column on the fixture, and welding to manufacture the upright column;
d) welding a nut to the mounting hole on the inner side of the connecting plate in advance on a nut projection welding machine;
e) placing the fixing plate, the connecting plate and the side sealing plate which are subjected to laser cutting on corresponding welding fixtures, clamping the parts by using a manual clamping device, and welding the abutted seams to form a beam support;
f) hoisting and moving the beam support to a clamp provided with an upright column, matching a bolt with a nut welded in advance, and fixedly connecting the beam support to the upright column through a fixing plate;
g) binding a steel bar frame in the upper and lower through areas of the beam support;
h) and mutually splicing and installing and fixing the U-shaped formworks between the lower bearing surface and the upper bearing surface of the beam support, and fixing the U-shaped formworks by using auxiliary fixing equipment to finish the assembly of the steel and concrete shear wall mixed structure.
The manufacturing of the steel and concrete shear wall mixed structure is completed through the steps, the beam and the beam support are fixedly connected through bolts in the following construction, floor reinforcing steel bars are uniformly tied on the beam, the tying of the reinforcing steel bars at the beam support passes through the reserved gaps of the tooth plates, a floor pouring template is well installed, concrete mortar is poured from the stand column, the concrete mortar overflows into the cavity at the beam support through the through holes formed in the stand column and the fixing plate and continues to overflow into the floor pouring template, so that the concrete is filled in the beam support, the steel bar lap joints of the upper wallboard and the lower wallboard and the groove, the concrete is solidified to form a whole, and the integral structure is firmer.

Claims (4)

1. The steel and concrete shear wall mixed structure is characterized by comprising a vertical column (3) which is vertically through, wherein a plurality of beam supports (1) are arranged outside the vertical column at intervals along the length direction, each beam support is a steel structure body which is through up and down, a fixing plate (1-1), a connecting plate (1-2) and a side sealing plate (1-3) are arranged on the side surface of the steel structure body, the fixing plate is fixedly connected with the vertical column, and the connecting plate is fixedly connected with a connecting plate at the end part of a cross beam (4); the upper part of the side sealing plate is connected with a dental lamina (1-4); the upper edges of the fixed plate, the connecting plate and the side sealing plates form an upper bearing surface, the lower edges of the fixed plate, the connecting plate and the side sealing plates form a lower bearing surface, the upper bearing surface and the lower bearing surface are respectively matched with the lower end surface and the upper end surface of the cast-in-place wallboard template to form a box body, and a steel bar frame is bound in the box body; the beam support and the cast-in-place wallboard template are matched and connected in sequence.
2. The steel and concrete shear wall hybrid structure according to claim 1, further characterized in that through holes (1-5) are provided at positions corresponding to the fixing plates of the columns and the beam supports.
3. A steel and concrete shear wall hybrid construction according to claim 1, further characterized in that said cast-in-place wall panel form is formed by splicing a plurality of U-shaped forms, the U-shaped forms being reusable.
4. A method of making a steel and concrete shear wall hybrid structure according to claim 1, comprising the steps of:
a) selecting a steel plate, blanking according to the number of drawings by using a laser cutting machine, and preparing a stand column side plate, a fixed plate, a connecting plate and a side sealing plate according to the sizes of the drawings; processing through holes, mounting holes and tooth plates at corresponding positions;
b) conveying the U-shaped template to an assembly site;
c) mounting the side plate of the upright column on a fixture, welding a nut at the mounting hole at the inner side of the side plate, aligning the edges of the side plate of the upright column on the fixture, and welding to manufacture the upright column;
d) welding a nut to the mounting hole on the inner side of the connecting plate in advance on a nut projection welding machine;
e) placing the fixing plate, the connecting plate and the side sealing plate which are subjected to laser cutting on corresponding welding fixtures, clamping the parts by using a manual clamping device, and welding the abutted seams to form a beam support;
f) hoisting and moving the beam support to a clamp provided with an upright column, matching a bolt with a nut welded in advance, and fixedly connecting the beam support to the upright column through a fixing plate;
g) binding a steel bar frame in the upper and lower through areas of the beam support;
h) and mutually splicing and installing and fixing the U-shaped formworks between the lower bearing surface and the upper bearing surface of the beam support, and fixing the U-shaped formworks by using auxiliary fixing equipment to finish the assembly of the steel and concrete shear wall mixed structure.
CN202011130788.XA 2020-10-21 2020-10-21 Steel and concrete shear wall mixed structure and manufacturing method thereof Active CN112302209B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011130788.XA CN112302209B (en) 2020-10-21 2020-10-21 Steel and concrete shear wall mixed structure and manufacturing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011130788.XA CN112302209B (en) 2020-10-21 2020-10-21 Steel and concrete shear wall mixed structure and manufacturing method thereof

Publications (2)

Publication Number Publication Date
CN112302209A true CN112302209A (en) 2021-02-02
CN112302209B CN112302209B (en) 2021-12-24

Family

ID=74328623

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011130788.XA Active CN112302209B (en) 2020-10-21 2020-10-21 Steel and concrete shear wall mixed structure and manufacturing method thereof

Country Status (1)

Country Link
CN (1) CN112302209B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112302189A (en) * 2020-10-21 2021-02-02 日照大象房屋建设有限公司 Steel and precast concrete combined structure and manufacturing method thereof
CN112302195A (en) * 2020-10-21 2021-02-02 日照大象房屋建设有限公司 Lateral force resistant damper and steel frame combined structure and manufacturing method thereof

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1650371A1 (en) * 2003-07-18 2006-04-26 Pedro Nel Ospina Cabezas Integral, mixed, structural construction system
CN203716339U (en) * 2014-03-02 2014-07-16 山东建筑大学 Steel reinforced concrete combined shearing wall
JP2015129426A (en) * 2014-01-09 2015-07-16 株式会社大林組 Method and structure for joining reinforced concrete beam and steel column or column with steel frame together
CN105040810A (en) * 2015-07-28 2015-11-11 广东省建筑设计研究院 Connecting node suitable for framed shear wall structure reverse construction method
CN105780923A (en) * 2016-05-04 2016-07-20 福建工程学院 Assembly structure of prefabricated concrete beam and concrete-filled steel tube column
CN205530819U (en) * 2016-04-18 2016-08-31 杭州铁木辛柯钢结构设计有限公司 Steel frame structure of embedded precast concrete shear force wall bending resistance simultaneously
CN106703212A (en) * 2016-11-18 2017-05-24 宁波锐德建筑设计咨询有限公司 Device for connecting shear wall and concrete floor in building structure and setting method of device
CN107700667A (en) * 2017-09-26 2018-02-16 中南大学 A kind of precast floor slab and girder steel lower flange connecting node
CN207063140U (en) * 2017-07-17 2018-03-02 浙江越宫钢结构有限公司 A kind of shear wall house for the shear wall slab assembling being made up of steel square tube and steel plate
CN107989227A (en) * 2017-12-20 2018-05-04 中冶建筑研究总院有限公司 A kind of assembled steel reinforced concrete shear walls structure and its preparation and installation method
CN207794303U (en) * 2017-12-06 2018-08-31 新昌县远轴工业设计有限公司 A kind of high strength beam Column border node
CN211228890U (en) * 2019-09-29 2020-08-11 福州大学 Novel steel-concrete-FRP combined structure

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1650371A1 (en) * 2003-07-18 2006-04-26 Pedro Nel Ospina Cabezas Integral, mixed, structural construction system
JP2015129426A (en) * 2014-01-09 2015-07-16 株式会社大林組 Method and structure for joining reinforced concrete beam and steel column or column with steel frame together
CN203716339U (en) * 2014-03-02 2014-07-16 山东建筑大学 Steel reinforced concrete combined shearing wall
CN105040810A (en) * 2015-07-28 2015-11-11 广东省建筑设计研究院 Connecting node suitable for framed shear wall structure reverse construction method
CN205530819U (en) * 2016-04-18 2016-08-31 杭州铁木辛柯钢结构设计有限公司 Steel frame structure of embedded precast concrete shear force wall bending resistance simultaneously
CN105780923A (en) * 2016-05-04 2016-07-20 福建工程学院 Assembly structure of prefabricated concrete beam and concrete-filled steel tube column
CN106703212A (en) * 2016-11-18 2017-05-24 宁波锐德建筑设计咨询有限公司 Device for connecting shear wall and concrete floor in building structure and setting method of device
CN207063140U (en) * 2017-07-17 2018-03-02 浙江越宫钢结构有限公司 A kind of shear wall house for the shear wall slab assembling being made up of steel square tube and steel plate
CN107700667A (en) * 2017-09-26 2018-02-16 中南大学 A kind of precast floor slab and girder steel lower flange connecting node
CN207794303U (en) * 2017-12-06 2018-08-31 新昌县远轴工业设计有限公司 A kind of high strength beam Column border node
CN107989227A (en) * 2017-12-20 2018-05-04 中冶建筑研究总院有限公司 A kind of assembled steel reinforced concrete shear walls structure and its preparation and installation method
CN211228890U (en) * 2019-09-29 2020-08-11 福州大学 Novel steel-concrete-FRP combined structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112302189A (en) * 2020-10-21 2021-02-02 日照大象房屋建设有限公司 Steel and precast concrete combined structure and manufacturing method thereof
CN112302195A (en) * 2020-10-21 2021-02-02 日照大象房屋建设有限公司 Lateral force resistant damper and steel frame combined structure and manufacturing method thereof

Also Published As

Publication number Publication date
CN112302209B (en) 2021-12-24

Similar Documents

Publication Publication Date Title
CN106703306B (en) Precast concrete parapet component and connection structure thereof
CN110409811B (en) Non-dismantling forming column template containing reinforcement cage, template structure and building process
CN112302209B (en) Steel and concrete shear wall mixed structure and manufacturing method thereof
CN113818562A (en) Construction method of assembled frame structure
CN110107023B (en) Rigid connection prefabricated frame beam for assembly type building
CN209227836U (en) Prefabricated concrete structure wall-column all steel is keyed structure
CN114319977B (en) Steel pipe concrete row column type connection precast shear wall structure and construction method
CN111218983A (en) Lattice formula structure concrete frame house
KR100865133B1 (en) A fixing device, a pre-fabricating forms for concrete-structure and the construction method thereof
CN108104310B (en) Assembled frame shear structure column staggered connection structure and assembling method
CN109281422A (en) Prefabricated concrete structure wall-column all steel key connection structure and assembling method
KR100731593B1 (en) A pre-fabricating forms for concrete-structure and the construction method thereof
CN210597794U (en) Connecting device of prefabricated plate
CN113021603A (en) Construction method for prefabricated assembled diamond type bent cap
CN112302195B (en) Lateral force resistant damper and steel frame combined structure and manufacturing method thereof
CN112302189B (en) Steel and precast concrete combined structure and manufacturing method thereof
CN214245382U (en) Stainless steel-wood combined template applied to bare concrete
CN215105454U (en) Prefabricated and cast-in-place piled raft foundation that combines together
CN115233813A (en) Beam with clamping connection plate
CN214116312U (en) Socket type longitudinal connecting device suitable for bridge is assembled to festival segmentation cantilever
CN212642113U (en) Formwork support system and construction structure
KR100695491B1 (en) A fixing device, a pre-fabricating forms for concrete-structure and the construction method thereof
CN210288825U (en) Assembled and cast-in-situ combined beam plate structure
KR100626326B1 (en) concrete structure
CN109386167B (en) Construction method of square wave-shaped guardrail on road retaining wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant