CN111008758B - Design method of excavation time for gob-side coal roadway in extra-thick coal seam based on double index weighting method - Google Patents
Design method of excavation time for gob-side coal roadway in extra-thick coal seam based on double index weighting method Download PDFInfo
- Publication number
- CN111008758B CN111008758B CN201911097786.2A CN201911097786A CN111008758B CN 111008758 B CN111008758 B CN 111008758B CN 201911097786 A CN201911097786 A CN 201911097786A CN 111008758 B CN111008758 B CN 111008758B
- Authority
- CN
- China
- Prior art keywords
- coal
- roadway
- roof
- gob
- index
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000003245 coal Substances 0.000 title claims abstract description 129
- 238000000034 method Methods 0.000 title claims abstract description 33
- 238000013461 design Methods 0.000 title claims abstract description 4
- 238000009412 basement excavation Methods 0.000 title claims description 42
- 239000011435 rock Substances 0.000 claims abstract description 62
- 238000005065 mining Methods 0.000 claims abstract description 26
- 238000011156 evaluation Methods 0.000 claims abstract description 12
- 238000012544 monitoring process Methods 0.000 claims description 21
- 230000007423 decrease Effects 0.000 claims description 7
- 238000011084 recovery Methods 0.000 claims description 7
- 238000004364 calculation method Methods 0.000 claims description 6
- 208000010392 Bone Fractures Diseases 0.000 claims description 5
- 206010017076 Fracture Diseases 0.000 claims description 5
- 238000006073 displacement reaction Methods 0.000 claims description 5
- 238000004519 manufacturing process Methods 0.000 claims description 5
- 238000011161 development Methods 0.000 claims description 4
- 239000011159 matrix material Substances 0.000 claims description 4
- 238000013459 approach Methods 0.000 claims description 3
- 238000002474 experimental method Methods 0.000 claims description 3
- 238000011835 investigation Methods 0.000 claims description 3
- 230000015572 biosynthetic process Effects 0.000 claims description 2
- 230000006835 compression Effects 0.000 claims description 2
- 238000007906 compression Methods 0.000 claims description 2
- 230000006641 stabilisation Effects 0.000 abstract 1
- 238000011105 stabilization Methods 0.000 abstract 1
- 238000005516 engineering process Methods 0.000 description 6
- 238000011160 research Methods 0.000 description 3
- 239000002356 single layer Substances 0.000 description 3
- 230000009977 dual effect Effects 0.000 description 2
- 238000009533 lab test Methods 0.000 description 2
- 239000010410 layer Substances 0.000 description 2
- 238000012423 maintenance Methods 0.000 description 2
- 230000005641 tunneling Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000010339 dilation Effects 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000003203 everyday effect Effects 0.000 description 1
- 238000013332 literature search Methods 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 238000004321 preservation Methods 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0639—Performance analysis of employees; Performance analysis of enterprise or organisation operations
- G06Q10/06393—Score-carding, benchmarking or key performance indicator [KPI] analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F17/00—Digital computing or data processing equipment or methods, specially adapted for specific functions
- G06F17/10—Complex mathematical operations
- G06F17/11—Complex mathematical operations for solving equations, e.g. nonlinear equations, general mathematical optimization problems
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/02—Agriculture; Fishing; Forestry; Mining
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02T—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO TRANSPORTATION
- Y02T90/00—Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Physics & Mathematics (AREA)
- Human Resources & Organizations (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Strategic Management (AREA)
- Mathematical Physics (AREA)
- Economics (AREA)
- Data Mining & Analysis (AREA)
- Pure & Applied Mathematics (AREA)
- Entrepreneurship & Innovation (AREA)
- Educational Administration (AREA)
- Development Economics (AREA)
- Operations Research (AREA)
- General Business, Economics & Management (AREA)
- Tourism & Hospitality (AREA)
- Mathematical Optimization (AREA)
- Marketing (AREA)
- Mathematical Analysis (AREA)
- Computational Mathematics (AREA)
- Algebra (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Marine Sciences & Fisheries (AREA)
- Primary Health Care (AREA)
- Animal Husbandry (AREA)
- Agronomy & Crop Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Engineering & Computer Science (AREA)
- Software Systems (AREA)
- Databases & Information Systems (AREA)
- Game Theory and Decision Science (AREA)
- Quality & Reliability (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
技术领域technical field
本发明涉及煤矿巷道掘进、支护领域,尤其涉及一种基于双指标权重法的特厚煤层沿空煤巷开掘时间设计方法。The invention relates to the field of coal mine roadway excavation and support, in particular to a method for designing the excavation time of a gob-side coal roadway in an extra-thick coal seam based on a double-index weighting method.
背景技术Background technique
窄煤柱沿空掘巷是指在相邻采空区上覆岩层运动终止及其引起的应力重分布趋于稳定的条件下,通过在采空区边缘留设3~5m窄煤柱而保存下来的巷道。当前,窄煤柱沿空掘巷主要在薄煤层及中厚煤层中推广使用,其中薄煤层是指单层厚度小于1.3m的煤层,中厚煤层是指单层厚度大于1.3m小于3.5m的煤层。而在厚及特厚煤层开采过程中,窄煤柱沿空掘巷应用较少,多采用留设20~30m宽煤柱的护巷方式,其中厚煤层是指单层厚度大于3.5m小于8.0m的煤层,特厚煤层是指煤体厚度大于8.0m的煤层。近年来,为了提高煤炭采出率,窄煤柱沿空掘巷技术开始在厚及特厚煤层中使用,然而大量理论研究与工程实践表明,当煤层厚度小于6.0m时,沿空掘巷实施过程的理论、技术、工艺可以借鉴或沿用已有薄及中厚煤层沿空掘巷理论与技术。但随着煤层厚度进一步增大,覆岩运动规律及其引起的应力场开始发生显著变化,特别是当煤层厚度超过15m时,沿空掘巷过程中的岩层移动及应力、位移变化与薄及中厚煤层迥然不同,现有薄及中厚沿空掘巷理论、技术、工艺无法在该条件下使用。Narrow coal pillar roading along the goaf refers to the preservation of coal pillars by leaving 3-5m narrow coal pillars at the edge of the goaf under the condition that the movement of the overlying strata in the adjacent goaf terminates and the stress redistribution caused by it tends to be stable. down the laneway. At present, gob-side entry with narrow coal pillars is mainly used in thin coal seams and medium-thick coal seams. Thin coal seams refer to coal seams with a single layer thickness less than 1.3m, and medium-thick coal seams refer to those with a single layer thickness greater than 1.3m and less than 3.5m. coal seam. However, in the process of mining thick and extra-thick coal seams, narrow coal pillars are rarely used along the gob roadway, and the roadway protection method with 20-30m wide coal pillars is mostly used. The thick coal seam refers to the thickness of a single layer greater than 3.5m and less than 8.0m m coal seam, extra-thick coal seam refers to a coal seam with a coal body thickness greater than 8.0m. In recent years, in order to improve the coal recovery rate, narrow coal pillar gob-side entry technology has been used in thick and extra-thick coal seams. However, a large number of theoretical studies and engineering practices have shown that when the thickness of the coal seam is less than 6.0m, The theory, technology, and process of the process can be used for reference or continue to use the existing theory and technology of gob-side entry in thin and medium-thick coal seams. However, as the thickness of the coal seam further increases, the law of movement of the overlying rock and the stress field caused by it begin to change significantly. Medium-thick coal seams are quite different, and the existing thin and medium-thick gob-side entry theories, technologies, and techniques cannot be used under this condition.
下面以沿空巷道开掘时间为例进行说明,众所周知,沿空掘巷的开掘时间是确保沿空巷道围岩稳定、保证采掘正常接替的关键因素,现有研究多以基本顶下沉量作为沿空巷道开掘时间的单一评价指标,即在顶板下沉量达到最大值时开掘巷道,其中,基本顶下沉量是基于薄及中厚煤层的地质生产条件推导得出的,即煤层可以全部采出的条件下,以冒落的岩石特性计算基本顶下沉量;然而对于15m以上特厚煤层,其多通过综放开采方式进行煤炭回采,由于综放开采技术的局限性,有近四分之一的煤层(厚度大于4m)是无法采出的,其将随着岩石一起冒落到采空区,由于碎裂煤体与冒落岩体在碎胀性、强度方面的显著差异,其将显著减缓的基本顶沉降趋势(约减少35%~45%基本顶下沉量)。若采用已有的理论计算方法,即忽略煤、岩在碎胀性与强度方面的差异性,由此计算出的顶板沉降特征及沿空巷道开掘时间将与生产实践严重不符。因此,亟需提出一种针对特厚煤层沿空巷道开掘时间的理论研究方法。The following takes the excavation time of gob-side roadway as an example to illustrate. As we all know, the excavation time of gob-side roadway is the key factor to ensure the stability of the surrounding rock of the gob-side roadway and the normal replacement of excavation. The single evaluation index of the excavation time of the empty roadway, that is, the roadway is excavated when the roof subsidence reaches the maximum value. Under the given conditions, the basic roof subsidence is calculated based on the characteristics of caving rocks; however, for extra-thick coal seams above 15m, coal recovery is mostly carried out by fully mechanized caving mining. Due to the limitations of fully mechanized caving mining technology, nearly One of the coal seams (thickness greater than 4m) cannot be mined, and it will fall into the gob together with the rock. The basic roof settlement tendency will be significantly slowed down (approximately 35% to 45% reduction in the basic roof sinking amount). If the existing theoretical calculation method is adopted, ie ignoring the differences in crushing and strength of coal and rock, the calculated roof settlement characteristics and gob-side excavation time will be seriously inconsistent with production practice. Therefore, it is urgent to propose a theoretical research method for the excavation time of gob-side roadway in extra-thick coal seam.
通过大量文献检索发现,目前尚未有关于15m以上特厚煤层沿空巷道开掘时间的理论研究及实践报告。在当前15m以上特厚煤层工程实践中,沿空巷道开掘时间常用的两种确定方法:一是待覆岩运动充分稳定后,即12~16个月后开掘巷道,这种做法可保证沿空巷道围岩稳定性,巷道维护状态较好,但严重影响矿井正产接替,造成矿井接续困难、效益骤降。二是沿用传统4~6月掘巷时间,即相邻工作面回采结束后4~6月便开始掘巷,此做法可保证正常采掘接替,但由于覆岩运动尚未充分稳定,将造成下位沿空巷道严重变形失稳。因此,如何确定一种既能保证沿空巷道围岩稳定性,又能实现正常采掘接替的沿空巷道开掘时间确定方法,对于15m以上特厚煤层安全高产高效开采具有重要意义。Through a large number of literature searches, it is found that there are no theoretical research and practical reports on the excavation time of gob-side roadways in extra-thick coal seams above 15m. In the current engineering practice of ultra-thick coal seams above 15m, there are two commonly used methods to determine the excavation time of gob-side roadway: one is to excavate the roadway after 12 to 16 months after the movement of the overlying rock is fully stabilized. The surrounding rock of the roadway is stable, and the maintenance of the roadway is in good condition, but it seriously affects the succession of the normal production of the mine, resulting in difficulties in the succession of the mine and a sharp drop in profitability. The second is to continue to use the traditional 4-6 month digging time, that is, start digging 4-6 months after the mining of the adjacent working face is completed. This method can ensure normal mining succession. The empty roadway is seriously deformed and unstable. Therefore, how to determine a gob-side roadway excavation time determination method that can not only ensure the stability of the surrounding rock of the gob-side roadway but also realize normal mining replacement is of great significance for the safe, high-yield and efficient mining of extra-thick coal seams above 15m.
在考分考虑以往理论研究及工程实践不足的基础上,本专利提出一种基于基本顶沉降规律与巷道变形速率的15m以上特厚煤层沿空巷道开掘时间的双指标综合确定方法,首先以基本顶下沉量作为评价指标,确定一个合理沉降值而非最大沉降值作为覆岩稳定的评价标准,据此计算合理的沿空煤巷开掘时间;其次,当沿空煤巷煤体较为软弱且强度较低时,沿空煤巷开掘后将立即发生位移变形,进而导致煤体裂隙快速发育并破裂,煤体破裂后承载能力显著降低,进而导致应力的深部转移,在这个破坏过程中,位移的发生要远远早于裂隙、应力的演化,即巷道变形(位移)速率是围岩稳定性最为直观、敏感、根本的评价指标,据此,本专利以围岩速率变化为第二评价指标确定沿空煤巷开掘时间;第三,基本顶沉降是沿空煤巷围岩稳定状态的根本力学原因,而巷道位移速率是巷道稳定状态的显现结果,但在不同地质生产条件下,两个指标对于最合理掘巷时间的贡献率是不同的,据此设计不同地质条件下双指标的权重比例,综合确定合理沿空煤巷掘进时间。因此,以基本顶沉降规律、巷道变形速率为评价指标,确定沿空煤巷开掘最合理时间,既能保证煤巷围岩稳定又能缩短巷道准备时间,填补了沿空掘巷开掘时间确定方法的空白。On the basis of considering the lack of previous theoretical research and engineering practice in the test scores, this patent proposes a dual-index comprehensive determination method for the excavation time of gob-side roadways in extra-thick coal seams above 15m based on the basic roof settlement law and roadway deformation rate. The subsidence is used as an evaluation index, and a reasonable settlement value rather than the maximum settlement value is determined as the evaluation standard for the stability of the overlying rock, based on which the reasonable excavation time of the gob-side coal roadway is calculated; secondly, when the coal body of the gob-side coal roadway is relatively weak and the strength When it is lower, the displacement and deformation will occur immediately after the excavation of the goaf coal roadway, which will lead to the rapid development and rupture of coal fissures. It occurs much earlier than the evolution of cracks and stress, that is, the roadway deformation (displacement) rate is the most intuitive, sensitive, and fundamental evaluation index for the stability of surrounding rock. Accordingly, this patent takes the change of surrounding rock rate as the second evaluation index. The excavation time of the gob-side coal roadway; thirdly, the basic roof settlement is the fundamental mechanical reason for the stable state of the surrounding rock of the gob-side coal roadway, and the displacement rate of the roadway is the result of the stable state of the roadway, but under different geological production conditions, the two indicators The contribution rate to the most reasonable tunneling time is different. Based on this, the weight ratio of the dual indicators under different geological conditions is designed to comprehensively determine the reasonable tunneling time along the goaf. Therefore, using the basic roof settlement law and roadway deformation rate as evaluation indicators to determine the most reasonable time for gob-side roadway excavation can not only ensure the stability of the surrounding rock of the coal roadway but also shorten the roadway preparation time, filling the gap in the method of determining the time for gob-side roadway excavation. Whitespace.
发明内容Contents of the invention
本发明为了克服15m以上特厚煤层沿空巷道开掘时间难题,提供了一种基于双指标权重法的特厚煤层沿空煤巷开掘时间设计方法,分为如下步骤:In order to overcome the problem of excavation time of gob-side roadway in extra-thick coal seam above 15m, the present invention provides a design method of excavation time of gob-side roadway in extra-thick coal seam based on double index weight method, which is divided into the following steps:
第一步,以基本顶下沉量为指标,确定沿空掘巷开掘时间T1 The first step is to use the basic roof subsidence as an index to determine the excavation time T 1 of gob-side entry
步骤1.1)现场调研与室内实验Step 1.1) Field investigation and indoor experiment
调研基本顶、直接顶、煤体厚度和煤层采出率;实验室测得直接顶与煤体碎胀系数,基本顶岩层的弹性模量与粘性模量;Investigate the basic roof, direct roof, coal thickness and coal seam recovery rate; the laboratory measures the immediate roof and coal disintegration coefficient, the elastic modulus and viscosity modulus of the basic roof rock layer;
步骤1.2)基本顶最大下沉量计算Step 1.2) Calculation of the maximum subsidence of the basic roof
考虑到特厚煤层开采过程煤体采出率低及煤、岩体碎胀性、强度的差异性,近25%未采出的煤体将随直接顶一起冒落并抑制基本顶下沉,据此确定基本顶的最大下沉量Wmax,其表达式如下:Considering the low recovery rate of the coal body during the mining process of the extra-thick coal seam and the differences in the disintegration and strength of the coal and rock mass, nearly 25% of the unmined coal body will caving along with the direct roof and inhibit the basic roof subsidence. Based on this, the maximum sinking amount W max of the basic roof is determined, and its expression is as follows:
Wmax=M+∑h-∑h·k1-(1-α)M·k2 (1)W max =M+∑h-∑h·k 1 -(1-α)M·k 2 (1)
式中,M为开采煤层厚度,∑h为直接顶岩层厚度,k1为冒落岩体的碎胀系数,k2为碎裂煤体的碎胀系数,α为顶煤放出率,15m以上特厚煤层α=75%;In the formula, M is the thickness of the mining coal seam, ∑h is the thickness of the immediate top rock layer, k 1 is the disintegration coefficient of the caving rock mass, k 2 is the disintegration coefficient of the cracked coal body, and α is the top-coal discharge rate, above 15m Extra thick coal seam α=75%;
特厚煤层开采过程中,基本顶沉降的动态方程表达式如下:During the mining process of extra-thick coal seam, the expression of the dynamic equation of basic roof settlement is as follows:
式中,qZ为基本顶所受到的岩层载荷,lm为基本顶的断裂步距,E和η为基本顶的弹性模量与粘性模量,F为冒落煤岩体的综合抗压强度;F的关系式如下:In the formula, q Z is the rock formation load on the basic roof, l m is the fracture step distance of the basic roof, E and η are the elastic modulus and viscous modulus of the basic roof, and F is the comprehensive compression resistance of caving coal rock mass Intensity; the relationship of F is as follows:
式中,F1为冒落岩体的抗压强度,F2为冒落顶煤的抗压强度;In the formula, F1 is the compressive strength of the caving rock mass, and F2 is the compressive strength of the caving top-coal;
动态方程(2)属于指数函数,其导数表示基本顶下沉速率;由指数函数特点可知,随着时间增大,基本顶下沉速率将逐渐减小,即当基本顶下沉量达到某一临界指标时,基本顶下沉速率将大幅降低并趋近于0;结合大量工程实践经验,以基本顶最大下沉量的70%作为临界指标,当基本顶下沉量达到70%Wmax临界指标时,基本顶下沉运动将趋于缓慢并稳定,运动速率低,不会再发生剧烈结构性运动,对下位岩体稳定性影响小,即The dynamic equation (2) belongs to an exponential function, and its derivative represents the subsidence rate of the basic roof; it can be known from the characteristics of the exponential function that the subsidence rate of the basic roof will gradually decrease as time increases, that is, when the subsidence of the basic roof reaches a certain When the critical index is reached, the subsidence rate of the basic roof will be greatly reduced and approach 0; combined with a large amount of engineering practice experience, 70% of the maximum subsidence of the basic roof is used as the critical index, and when the subsidence of the basic roof reaches 70% W max critical When the index is reached, the subsidence movement of the basic roof will tend to be slow and stable, with a low movement rate, no violent structural movement, and little impact on the stability of the underlying rock mass, that is,
第二步,以巷道围岩变形速率为时间指标,确定合理开掘时间T2 The second step is to determine the reasonable excavation time T 2 by taking the deformation rate of the roadway surrounding rock as the time index
步骤1.1)在特厚煤层工作面前方100m处建立一个监测测站,该监测测站位于相邻工作面生产系统范围内,而非本工作面超前巷道内;Step 1.1) Establish a
步骤1.2)在监测测站断面内安装顶底板与两帮位移监测设备,可以为测量杆、测线或其他监测设备,保证设备可以实时监测围岩移近量;Step 1.2) Install roof, floor and two-side displacement monitoring equipment in the section of the monitoring station, which can be measuring rods, measuring lines or other monitoring equipment, to ensure that the equipment can monitor the amount of surrounding rock movement in real time;
步骤1.3)以测站与工作面推进位置为横坐标,顶底板、两帮移近速率为纵坐标,绘制曲线图,监测工作自测站前方Ym开始,Y≥100m,直至巷道变形速率减小至4mm/d结束;围岩变形速率小于4mm/d,即表明巷道围岩处于基本稳定状态;Step 1.3) Take the propelling position of the measuring station and the working face as the abscissa, and the approaching speed of the roof, floor, and two sides as the ordinate, and draw a graph. The monitoring work starts from Ym in front of the measuring station, and Y≥100m, until the deformation rate of the roadway decreases. It ends at 4mm/d; the deformation rate of the surrounding rock is less than 4mm/d, which means that the surrounding rock of the roadway is in a basically stable state;
步骤1.4)根据工作面平均推进速度,得出变形速率降低至4mm/d所需要的时间T2,Step 1.4) According to the average advancing speed of the working face, the time T 2 required for the deformation rate to decrease to 4mm/d is obtained,
式中,S为变形速率减小至4mm/d时的横坐标值,v为工作面推进速度;In the formula, S is the abscissa value when the deformation rate is reduced to 4mm/d, and v is the advancing speed of the working face;
第三步,确定合理的沿空巷道开掘时间TThe third step is to determine the reasonable excavation time T of gob-side roadway
步骤1.1)确定基本顶当量参数P、煤体当量参数σStep 1.1) Determine the basic top equivalent parameter P and coal body equivalent parameter σ
基本顶当量参数P是对岩体力学性能的综合评价,其表达式如下:The basic top equivalent parameter P is a comprehensive evaluation of the mechanical properties of rock mass, and its expression is as follows:
P=241.3ln(c0)-15.5N+52.6hm (6)P=241.3ln(c 0 )-15.5N+52.6h m (6)
式中,C0为基本顶初次来压步距、N直接顶充填系数、hm为煤层采高;In the formula, C 0 is the initial pressure step distance of the basic roof, N is the filling coefficient of the direct roof, and h m is the mining height of the coal seam;
煤体当量参数σ是对岩体力学性能的综合评价,其表达式如下:The coal equivalent parameter σ is a comprehensive evaluation of the mechanical properties of rock mass, and its expression is as follows:
式中,σc为煤体单轴抗压强度,GSI为煤体裂隙发育程度系数,D为采动影响指数,mi为煤体常量。In the formula, σc is the uniaxial compressive strength of the coal body, GSI is the coefficient of coal fracture development degree, D is the mining influence index, and mi is the constant of the coal body.
步骤1.2)确定权重系数Step 1.2) Determine the weight coefficient
根据基本顶当量参数P与煤体当量参数σ确定两指标相应的权重,具体如表1所示,其中a为T1占的权重,b为T2占的权重;The corresponding weights of the two indicators are determined according to the basic top equivalent parameter P and the coal equivalent parameter σ, as shown in Table 1, where a is the weight occupied by T 1 , and b is the weight occupied by T 2 ;
表1权重影响因子分配表Table 1 Distribution table of weight influencing factors
步骤1.3)计算合理掘进时间Step 1.3) Calculation of reasonable excavation time
将权重因子a、b组成矩阵ACombining weight factors a and b into matrix A
第一、二步得出的沿空煤巷掘巷时间T1,T2组成矩阵BThe time T 1 and T 2 of gob-side coal roadway digging obtained in the first and second steps form a matrix B
计算合理采掘时间TCalculate the reasonable mining time T
有益效果:1)在15m以上特厚煤层开采过程中,有近四分之一的煤层是无法采出的,其将随着直接顶一起冒落到采空区并阻止基本顶下沉,由于碎裂煤体与冒落岩石在碎胀特性、强度特性方面的显著差异,其将显著减缓的覆岩沉降趋势(约减少35%~45%基本顶下沉量)。以往文献忽略冒落煤体的作用,统一视作岩体,由此得到基本顶下沉量与覆岩运动终止时间与实际情况存在较大差异。本发明在充分考虑煤、岩体的差异性的基础上得出基本顶下沉量与覆岩运动稳定时间,更加符合现场实际,结果更加准确。2)以往沿空巷道开掘时间以覆岩运动终止作为单一判定指标,本专利则在基本顶沉降特征指标的基础上,充分考虑煤体软弱与强度低的力学特性及其破坏失稳过程,创新性地引入巷道围岩变形速率作为附加指标,形成了沿空煤巷开掘时间的双指标体系。该双指标既考虑了覆岩运动状况,又能充分考虑了巷道围岩维护状况,更加符合现场实际需要。3)以往沿空巷道开掘时间一般是在相邻工作面覆岩运动完全稳定之后,即基本顶下沉量达到最大值wmax,而本专利在大量现场实践的基础上,创新性地提出了最大基本顶下沉值的70%、围岩变形速率<4mm/天作为巷道开掘时间的评价指标,并根据具体地质条件确定两者所占的权重比例,综合得出沿空巷道开掘时间,既能保证沿空巷道围岩安全稳定,又能有效减少了特厚煤层沿空掘巷时间,保障了采掘正常接替。Beneficial effects: 1) During the mining process of extra-thick coal seams above 15m, nearly a quarter of the coal seam cannot be extracted, and it will cascade down to the gob along with the direct roof and prevent the basic roof from sinking, because Significant differences in crushing properties and strength properties between the fractured coal mass and caving rock will significantly slow down the settlement trend of the overlying rock (about 35% to 45% reduction in the basic roof subsidence). The previous literature ignored the effect of caving coal mass and regarded it as rock mass uniformly, so the basic roof subsidence and overlying rock movement termination time are quite different from the actual situation. The present invention obtains the basic roof subsidence amount and the overlying rock movement stability time on the basis of fully considering the difference of coal and rock mass, which is more in line with the field reality and the result is more accurate. 2) In the past, the excavation time of gob-side roadway was based on the termination of overlying rock movement as a single judgment index. This patent is based on the basic roof settlement characteristic index, fully considers the mechanical properties of weak and low-strength coal and its failure and instability process, and innovates The deformation rate of the surrounding rock of the roadway is introduced as an additional index to form a double-index system for the excavation time of the gob-side coal roadway. The dual index not only takes into account the movement of overlying rock, but also fully considers the maintenance of surrounding rock of the roadway, which is more in line with the actual needs of the site. 3) In the past, the excavation time of the gob-side roadway was usually after the overlying rock movement of the adjacent working face was completely stabilized, that is, the basic roof subsidence reached the maximum value w max , but this patent innovatively proposes 70% of the maximum basic roof subsidence value and the surrounding rock deformation rate <4mm/day are used as the evaluation index of roadway excavation time, and the weight ratio of the two is determined according to the specific geological conditions, and the excavation time of the gob-side roadway is obtained comprehensively. It can ensure the safety and stability of the surrounding rock of the gob-side roadway, and can effectively reduce the time for gob-side roadway digging in extra-thick coal seams, ensuring the normal replacement of mining.
附图说明Description of drawings
图1巷道变形速率测站位置图Figure 1 Location map of roadway deformation rate measuring station
图2监测断面布置图Figure 2 Monitoring Section Layout
图3巷道变形速率曲线图Figure 3 Roadway deformation rate curve
图中,1.工作面;2,监测用巷道;3,测站;4,顶板;5、6,两帮;7,底板;L,测站与停采线距离;a,两帮观测点与底板距离;b,顶底板观测点与两帮距离。In the figure, 1. working face; 2, roadway for monitoring; 3, measuring station; 4, roof; 5, 6, two sides; 7, floor; distance from the bottom plate; b, the distance between the observation point of the roof and the bottom plate and the two sides.
具体实施方式Detailed ways
第一步:以基本顶下沉量为指标,确定沿空掘巷开掘时间T1 Step 1: Determine the excavation time T 1 for gob-side entry with the basic roof subsidence as an index
(1)现场调研与室内实验(1) On-site investigation and indoor experiment
山西某矿201工作面主采2#煤层,平均厚度15.0m,直接顶为砂质泥岩,平均厚度6.0m,基本顶为粉砂岩,平均厚度为9.2m。该矿采用综放开采工艺采煤,采煤高度3m,放煤高度12m,煤炭采出率取75%。The 201 working face of a mine in Shanxi mainly
室内实验得到煤体的碎胀系数为1.3,直接顶碎胀系数为1.2,基本顶弹性模量为4.39GPa,基本顶粘性模量为85.34GPa,冒落直接顶的抗压强度为63MPa,破碎顶煤的抗压强度为17MPa。Laboratory experiments show that the coefficient of disintegration of the coal body is 1.3, the coefficient of dilation of the direct roof is 1.2, the modulus of elasticity of the basic roof is 4.39GPa, the modulus of viscosity of the basic roof is 85.34GPa, and the compressive strength of the caving direct roof is 63MPa. The compressive strength of the top coal is 17MPa.
(2)代入公式(1)得到基本顶最大下沉量wmax (2) Substitute into formula (1) to get the maximum subsidence of the basic roof w max
Wmax=M+∑h-∑h·k1-(1-α)M·k2=15+6-6·1.2-(1-75%)·15·1.3=8.925W max =M+∑h-∑h·k 1 -(1-α)M·k 2 =15+6-6·1.2-(1-75%)·15·1.3=8.925
若不考虑煤体的碎胀性,基本顶最大下沉量为13.8m,远大于实际的8.925m,可见,考虑煤体放出率与碎胀特性更加符合基本顶运动规律。If the disintegration of the coal body is not considered, the maximum subsidence of the basic roof is 13.8m, which is much larger than the actual 8.925m. It can be seen that considering the coal release rate and the disintegration characteristics are more in line with the basic roof movement law.
(3)代入公式(3)得到煤岩体破碎后的综合抗压强度为13.38MPa(3) Substitute into formula (3) to get the comprehensive compressive strength of coal and rock after crushing is 13.38MPa
代入公式(2)得到基本顶运动的动态方程Substitute into formula (2) to get the dynamic equation of the basic top motion
w(t)=6.27·(1-e-0.026t)w(t)=6.27·(1-e -0.026t )
(4)以基本顶下沉到最大值的70%为指标,得到T1为221天。(4) Taking the basic roof sinking to 70% of the maximum value as the index, T1 is obtained as 221 days.
第二步:以巷道围岩变形情况为指标,确定合理开掘时间T2 Step 2: Determine the reasonable excavation time T 2 based on the deformation of surrounding rock in the roadway
(1)在201工作面1的相邻侧开掘用于监测用巷道2;由于特厚煤层覆岩运动剧烈且影响周期较长,测站3距离停采线距离L大于1000m。(1) Excavate the
(2)测站内巷道监测断面,如图2所示,在监测断面顶板4、两帮5、6、底板7、分别设置监测点,监测顶底板中部位置、两帮中部位置的变形情况,a、b为巷道高度与宽度的一半。安排专门技术人员每天对巷道顶底板变形量、两帮变形量进行记录。(2) The roadway monitoring section in the measuring station, as shown in Figure 2, set monitoring points on the
(3)以测站与工作面推进位置为横坐标,顶底板、两帮移近速率为纵坐标,绘制曲线图,如图3所示。监测工作自测站前方100m开始,至工作面推过测站1050m结束。(3) Take the advancing position of the measuring station and the working face as the abscissa, and the approach speed of the roof, floor and two sides as the ordinate, draw a curve, as shown in Figure 3. The monitoring work starts 100m in front of the measuring station and ends when the working face pushes past the measuring station 1050m.
(4)以巷道变形速率减小至4mm/d为指标,由图3可知,当工作面推过工作面875m时,巷道变形速率低至4mm/d。(4) Taking the roadway deformation rate reduced to 4mm/d as an index, it can be seen from Figure 3 that when the working face pushes through the working face for 875m, the roadway deformation rate is as low as 4mm/d.
(5)根据特厚煤层工作面推进速度3m/天,得出变形速率降低至4mm/d所需要的时间T2=258天。(5) According to the advance speed of 3m/day in the working face of extra-thick coal seam, it is obtained that the time T 2 required for the deformation rate to decrease to 4mm/d = 258 days.
第三步:确定合理的沿空巷道开掘时间TStep 3: Determine the reasonable excavation time T of gob-side roadway
(1)确定基本顶当量参数P、煤体当量参数σ(1) Determine the basic top equivalent parameter P and coal body equivalent parameter σ
基本顶初次来压步距C0取30m,直接顶充填系数N取1.3,煤层采高hm取3m,代入(6):The initial pressing step distance C of the basic roof is 30m, the filling coefficient N of the direct roof is 1.3, and the coal seam mining height h m is 3m, which is substituted into (6):
P=241.3ln(c0)-15.5N+52.6hm=958P=241.3ln(c 0 )-15.5N+52.6h m =958
室内实验得到煤体煤体单轴抗压强度σc取24MPa,煤体裂隙发育程度系数GSI取90,采动影响指数D取0.6,煤体常量mi取5,代入公式(7):In laboratory experiments, the uniaxial compressive strength σ c of the coal body is taken as 24 MPa, the coal fracture development degree coefficient GSI is taken as 90, the mining influence index D is taken as 0.6, and the coal body constant mi is taken as 5, which are substituted into the formula (7):
(2)确定权重系数(2) Determine the weight coefficient
P=958,σ=1.994,根据表1,可知a=0.4,b=0.6。P=958, σ=1.994, according to Table 1, it can be seen that a=0.4, b=0.6.
(3)计算合理掘进时间(3) Calculation of reasonable excavation time
将相关参数代入公式(8)Substituting relevant parameters into formula (8)
即最佳合理沿空掘巷时间为263.6天。That is to say, the optimal and reasonable time for gob-side roadway digging is 263.6 days.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911097786.2A CN111008758B (en) | 2019-11-12 | 2019-11-12 | Design method of excavation time for gob-side coal roadway in extra-thick coal seam based on double index weighting method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911097786.2A CN111008758B (en) | 2019-11-12 | 2019-11-12 | Design method of excavation time for gob-side coal roadway in extra-thick coal seam based on double index weighting method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN111008758A CN111008758A (en) | 2020-04-14 |
CN111008758B true CN111008758B (en) | 2023-06-23 |
Family
ID=70111912
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911097786.2A Active CN111008758B (en) | 2019-11-12 | 2019-11-12 | Design method of excavation time for gob-side coal roadway in extra-thick coal seam based on double index weighting method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111008758B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113643603B (en) * | 2021-08-05 | 2022-11-29 | 山东科技大学 | Separated roadway physical experiment model structure, manufacturing auxiliary tool and manufacturing method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104594899A (en) * | 2014-11-24 | 2015-05-06 | 山西潞安环保能源开发股份有限公司 | Method for determining reasonable width of gob-side entrydriving narrow coal pillar |
WO2016041392A1 (en) * | 2014-09-19 | 2016-03-24 | 中国矿业大学 | Water diversion fracture height test method for underwater filling coal mining |
CN106545362A (en) * | 2016-09-14 | 2017-03-29 | 辽宁工程技术大学 | A kind of comprehensive determination method for putting gob side entry driving coal column Size of pillar |
CN110318756A (en) * | 2019-07-18 | 2019-10-11 | 西安科技大学 | A kind of calculation method of shallow thin bedrock gob side entry driving thin coal pillar width |
-
2019
- 2019-11-12 CN CN201911097786.2A patent/CN111008758B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2016041392A1 (en) * | 2014-09-19 | 2016-03-24 | 中国矿业大学 | Water diversion fracture height test method for underwater filling coal mining |
CN104594899A (en) * | 2014-11-24 | 2015-05-06 | 山西潞安环保能源开发股份有限公司 | Method for determining reasonable width of gob-side entrydriving narrow coal pillar |
CN106545362A (en) * | 2016-09-14 | 2017-03-29 | 辽宁工程技术大学 | A kind of comprehensive determination method for putting gob side entry driving coal column Size of pillar |
CN110318756A (en) * | 2019-07-18 | 2019-10-11 | 西安科技大学 | A kind of calculation method of shallow thin bedrock gob side entry driving thin coal pillar width |
Non-Patent Citations (1)
Title |
---|
综放工作面沿空掘巷顶煤挤压破裂机理与控制技术;张广超;吴涛;吴继鲁;戴德胜;申世豹;赵仁宝;;煤炭科学技术(第05期);101-106 * |
Also Published As
Publication number | Publication date |
---|---|
CN111008758A (en) | 2020-04-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108399302B (en) | Method for judging coal wall caving of fully mechanized mining face with shallow coal seam and large mining height | |
CN112446143B (en) | A parameter design method for strip filling and mining under thick loose layer and thin bedrock | |
CN112127909A (en) | An accurate grouting repair and reinforcement method for broken surrounding rock in a tunnel | |
Wu et al. | Failure characteristics and cooperative control strategies for gob-side entry driving near an advancing working face: a case study | |
Liu et al. | Study on overburden failure characteristics in deep thick loose seam and thick coal seam mining | |
CN112901169B (en) | Discrimination and anti-scour mining method for impact instability of asymmetric island face | |
CN111008758B (en) | Design method of excavation time for gob-side coal roadway in extra-thick coal seam based on double index weighting method | |
Zhu et al. | Study on the movement characteristics of the overlying stratum and surrounding rock control in ultraclose coal seams: a case study | |
CN110781597A (en) | A calculation method of roof cutting height based on coal mine roof cutting weakening | |
CN110847913A (en) | A method for determining the optimal driving speed of roadway with outburst dangerous coal seam | |
Guo et al. | Ground control by L-shaped cemented paste backfilling technology in underground coal seam mining: a case study | |
CN111042821B (en) | Double-index method for quantitatively judging excavation time of gob-side roadway of extra-thick coal seam | |
CN110821535B (en) | A method for determining the anchor bolt and cable support of the retraction channel in fully mechanized mining face | |
CN110863828B (en) | Quantitative solution method for gob-side entry driving tension succession of extra-thick coal seam | |
CN117211791A (en) | Hydraulic slotting high-efficiency caving method for suspended top coal at end of top coal caving working surface | |
CN117823044A (en) | A method for improving the gas extraction effect of the working face and the stability of the surrounding rock of the adjacent tunnels by using kilometer-long horizontal drilling and fracturing | |
CN117574646A (en) | A numerical simulation method for the pressure relief characteristics of top coal in fully mechanized caving under the support of anchor bolts and cables | |
Liu et al. | The spatio-temporal evolution law of overlying rock fractures in an experimental working face (N00 mining method) based on microseismic monitoring technology | |
Xiong et al. | Study on the support capacity determination and movement law of overlying strata in a thin-bedrock large-cutting-height longwall panel | |
CN117345237A (en) | Method for lowering suspended top coal at end of coal face by combining hydraulic coal drawing and slotting | |
CN117313485A (en) | Numerical simulation research method for pressure relief characteristics of top coal at end of fully mechanized caving face | |
CN109002919B (en) | Method for predicting gas emission quantity of mine working face | |
Liu et al. | Fracture evolution and accumulation and dissipation law of energy during ascending mining | |
CN110119584A (en) | A kind of work noodles formula interval filling mining design method | |
Fu | Study on Surrounding Rock Control of Gob-Side Entry Retaining in Inclined and Thick Longwall Face |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |