CN110820993A - Connecting process of reserved open-hole type partially-coated concrete combined shear wall - Google Patents

Connecting process of reserved open-hole type partially-coated concrete combined shear wall Download PDF

Info

Publication number
CN110820993A
CN110820993A CN201910958684.9A CN201910958684A CN110820993A CN 110820993 A CN110820993 A CN 110820993A CN 201910958684 A CN201910958684 A CN 201910958684A CN 110820993 A CN110820993 A CN 110820993A
Authority
CN
China
Prior art keywords
wall limb
plate
bottom plate
limb
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910958684.9A
Other languages
Chinese (zh)
Inventor
潘庆华
蒋路
杨宇焜
回之正
邵琪琳
张莉莉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Green Building Integration Technology Co Ltd
Original Assignee
Zhejiang Green Building Integration Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Green Building Integration Technology Co Ltd filed Critical Zhejiang Green Building Integration Technology Co Ltd
Priority to CN201910958684.9A priority Critical patent/CN110820993A/en
Publication of CN110820993A publication Critical patent/CN110820993A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to the field of buildings, in particular to a connection process of a reserved open-hole type partially-coated concrete combined shear wall, which comprises the steps of welding a web plate and a wing plate in a factory to form an I shape as a steel skeleton of a long wall limb and a short wall limb, welding a bottom plate and side edges to form a U-shaped channel as a connecting beam, vertically arranging one side plate of the connecting beam and the web plate of the short wall limb and welding and fixing the side plate and the web plate of the long wall limb, arranging bolt holes on the wing plate of the side edge of the long wall limb and the bottom plate of the connecting beam after multiple times of calibration, transporting the long wall limb, the short wall limb and the connecting beam to a construction site, carrying out site hoisting and splicing, aligning connecting holes between the wing plate of the long wall limb and the bottom plate of the connecting beam, fastening through bolts, finally spot-welding and. After the scheme is adopted, the processing production and the field splicing are convenient, and the structural design performance requirements are met.

Description

Connecting process of reserved open-hole type partially-coated concrete combined shear wall
Technical Field
The invention relates to the field of buildings, in particular to a connection process of a reserved open-hole type partially-coated concrete composite shear wall.
Background
China vigorously pushes the traditional building to be transformed into an industrialized building. In the traditional building, most of work needs to be finished on a construction site, and the problems of long construction period, serious environmental pollution, large stacking field, shortage of constructors and the like become barriers for inhibiting the progress of the building industry. The partially-coated concrete composite shear wall (PEC shear wall) is produced by an industrial production line, concrete is directly poured into a semi-open cavity defined by a steel flange and a steel web, no additional template is needed for pouring on a mold table, and the construction speed is high. The straight shear wall has weaker external stability, so that the shear walls adopted in practical engineering are mostly L-shaped and T-shaped, so that the wall limbs mutually provide external constraint to ensure the stability, and the PEC combined shear wall limb splicing part with the special shape can bring greater difficulty for pouring if an integral prefabrication process that all the wall limbs are welded firstly and then poured is adopted. In order to solve the processing difficulty of the special-shaped PEC composite shear wall and avoid the weak point of the external stability of the wall surface of the straight shear wall, so that the special-shaped PEC composite shear wall is convenient to process, produce and splice on site and meets the structural design performance requirements, therefore, the inventor further researches the special-shaped PEC composite shear wall and develops a connection process of a reserved open-cell type partially-coated concrete composite shear wall, and the scheme is generated.
Disclosure of Invention
In order to achieve the purpose, the technical scheme of the invention is as follows:
a reserved hole type connecting process of a partially-coated concrete combined shear wall comprises the steps of welding a web plate and a wing plate to form an I shape serving as a long wall limb and a steel skeleton of a short wall limb in a factory, welding a bottom plate and side edges to form a U-shaped channel steel serving as a connecting beam, vertically arranging one side plate of the connecting beam and the web plate of the short wall limb and welding and fixing the side plate and the web plate of the short wall limb, arranging bolt holes in the long wall limb side wing plate and the connecting beam bottom plate after multiple times of calibration, transporting the long wall limb, the short wall limb and the connecting beam to a construction site, carrying out site hoisting and splicing, aligning connecting holes between the wing plate of the long wall limb and the bottom plate of the connecting beam, fastening bolts, spot-welding and reinforcing at a splicing part and a contact part, and finally pouring.
The long wall, the short wall and the connecting beam can be prefabricated in a factory, then the wing plates of the long wall and the connecting holes between the bottom plates of the connecting beams are aligned when the site construction is carried out, the bolts are fastened, the weak point of external stability of the straight-line-shaped shear wall is avoided, the straight-line-shaped shear wall is convenient to process, produce and splice on site, the structural design performance requirements are met, and the straight-line-shaped wall can be kept lying flat and stacked for transportation during transportation.
Furthermore, the connecting holes on the wing plate of the long wall limb are uniformly distributed on two sides of the web plate.
Too close spacing between the attachment holes will reduce the strength of the panels themselves, while too few attachment holes will reduce the strength of the attachment between the panels.
Furthermore, the reserved open-hole type partially-coated concrete combined shear wall comprises a long wall limb, a short wall limb and a connecting beam, wherein the long wall limb and the short wall limb comprise a web plate and wing plates, the wing plates are vertically and fixedly arranged on two sides of the web plate to form an I shape, and a cell formed by the wing plates and the web plate is filled by pouring concrete; the connecting beam comprises a bottom plate and side plates, the bottom plate and the side plates on the two sides form a U-shaped structure, connecting holes which correspond to each other are formed in the bottom plate of the connecting beam and the wing plates on the side edges of the long wall limbs, and the bottom plate of the connecting beam and the connecting holes in the wing plates on the side edges of the long wall limbs are connected through connecting pieces; one side plate of the connecting beam and the web plate of the short wall limb are vertically arranged and welded and fixed.
After adopting the scheme, compared with the prior art, the invention has the following advantages:
the processing difficulty of the special-shaped combined shear wall is solved, the outer stability weakness of the wall surface of the straight shear wall is avoided, the processing production and the field splicing are facilitated, and the structural design performance requirement is met.
Drawings
FIG. 1 is a schematic diagram of an embodiment of the present invention;
FIG. 2 is an unstitched schematic view of FIG. 1;
description of the reference symbols
The wall comprises a long wall limb 1, a short wall limb 2, a connecting beam 3, a web plate 4, wing plates 5, a bottom plate 6, side plates 7 and connecting holes 8.
Detailed Description
The invention is further described with reference to the following figures and specific embodiments.
As shown in the figure, the connection process of the reserved open-hole type partially-coated concrete composite shear wall comprises a long wall limb 1, a short wall limb 2 and a connecting beam 3, wherein the long wall limb 1 and the short wall limb 2 both comprise a web plate 4 and wing plates 5, the wing plates 5 are vertically and fixedly arranged (or formed by welding or integral pouring and forging forming) to form I shapes on two sides of the web plate 4, the wing plates 5 and the web plate 4 form a plurality of cells, and the cells are filled with concrete through pouring.
The connecting beam 3 comprises a bottom plate 6 and side plates 7, the bottom plate 6 and the side plates 7 on two sides form a U-shaped structure, connecting holes 8 which correspond to each other are formed in the bottom plate 6 of the connecting beam 3 and the wing plates 5 on the side edge of the long wall limb 1, and the bottom plate 6 of the connecting beam 3 and the connecting holes 8 on the wing plates 5 on the side edge of the long wall limb 1 are connected through bolts; one side plate 7 of the connecting beam 3 and the web 4 of the short wall limb 2 are vertically arranged and welded, so that the long wall limb 1 and the short wall limb 2 form an L-shaped structure. The connecting holes 8 on the wing plates 5 of the long wall limbs 1 are uniformly distributed on two sides of the web plates 4, the strength of the plates is reduced when the connecting holes 8 are spaced too close, and the connecting strength between the plates is reduced when the connecting holes 8 are too few.
A construction method of a reserved open-hole type combined shear wall comprises the following steps:
weld web 4 and pterygoid lamina 5 in proper order and form long wall limb 1, the I-shaped steel skeleton of short wall limb 2, the steel skeleton is many cell structures, regard the channel-section steel as tie-beam 3, one of them curb plate 7 of tie-beam 3 and web 4 of short wall limb 2 set up perpendicularly and welded fastening, reserve the bolt hole on 1 side pterygoid lamina 5 of long wall limb and 3 bottom plates 6 of tie-beam, through calibration many times, after transporting to the job site, during on-the-spot hoist and mount concatenation, align the pterygoid lamina 5 of long wall limb 1 and connecting hole 8 between the bottom plate 6 of tie-beam 3, to wearing the bolt fastening, at last splice department and contact site spot welding reinforcement.
The special-shaped PEC combined shear wall solves the processing difficulty of the special-shaped PEC combined shear wall, avoids the weak point of external stability of the wall surface of the straight shear wall, is convenient to process, produce and splice on site, and meets the requirement of structural design performance.
The above description is only an embodiment of the present invention, and all the terms such as "upper", "lower", "left", "right", "middle", etc. in the present invention are used as reference and not absolutely limited, and all the insubstantial modifications made by the present invention shall fall within the scope of infringing the present invention.

Claims (3)

1. A connection process for a reserved open-cell type partially-coated concrete combined shear wall is characterized in that: through forming the I-shaped as long wall limb with web and pterygoid lamina welding in the mill, the steel skeleton of short wall limb, with the bottom plate, the side welding forms U style of calligraphy channel-section steel as the tie-beam, perpendicular setting and welded fastening of the web of one of them curb plate of tie-beam and short wall limb, set up the bolt hole through on long wall limb side pterygoid lamina and tie-beam bottom plate after calibration many times, with long wall limb, short wall limb, the tie-beam transports the job site, carry out on-the-spot hoist and mount concatenation, align the connecting hole between the pterygoid lamina of long wall limb and the bottom plate of tie-beam, to wearing the bolt fastening, at last splice department and contact site spot welding reinforcement, pour at last can.
2. The connection process of the open-cell type partially-coated concrete composite shear wall as claimed in claim 1, wherein: the connecting holes on the wing plate of the long wall limb are uniformly distributed on two sides of the web plate.
3. The connection process of the open-cell type partially-coated concrete composite shear wall as claimed in claim 1, wherein: the reserved open-hole type partially-coated concrete combined shear wall comprises long wall limbs, short wall limbs and connecting beams, wherein the long wall limbs and the short wall limbs comprise webplates and wing plates, the wing plates are vertically and fixedly arranged on two sides of the webplates to form an I shape, and cells formed by the wing plates and the webplates are filled by pouring concrete; the connecting beam comprises a bottom plate and side plates, the bottom plate and the side plates on the two sides form a U-shaped structure, connecting holes which correspond to each other are formed in the bottom plate of the connecting beam and the wing plates on the side edges of the long wall limbs, and the bottom plate of the connecting beam and the connecting holes in the wing plates on the side edges of the long wall limbs are connected through connecting pieces; one side plate of the connecting beam and the web plate of the short wall limb are vertically arranged and welded and fixed.
CN201910958684.9A 2019-10-10 2019-10-10 Connecting process of reserved open-hole type partially-coated concrete combined shear wall Pending CN110820993A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910958684.9A CN110820993A (en) 2019-10-10 2019-10-10 Connecting process of reserved open-hole type partially-coated concrete combined shear wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910958684.9A CN110820993A (en) 2019-10-10 2019-10-10 Connecting process of reserved open-hole type partially-coated concrete combined shear wall

Publications (1)

Publication Number Publication Date
CN110820993A true CN110820993A (en) 2020-02-21

Family

ID=69548977

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910958684.9A Pending CN110820993A (en) 2019-10-10 2019-10-10 Connecting process of reserved open-hole type partially-coated concrete combined shear wall

Country Status (1)

Country Link
CN (1) CN110820993A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4046594B2 (en) * 2002-09-10 2008-02-13 ミサワホーム株式会社 Mounting structure of steel partition
CN107190886A (en) * 2017-06-28 2017-09-22 浙江绿筑集成科技有限公司 A kind of faced wall corner structure

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4046594B2 (en) * 2002-09-10 2008-02-13 ミサワホーム株式会社 Mounting structure of steel partition
CN107190886A (en) * 2017-06-28 2017-09-22 浙江绿筑集成科技有限公司 A kind of faced wall corner structure

Similar Documents

Publication Publication Date Title
CN108360721B (en) Prefabricated concrete ultra-thin type bidirectional stress assembly type steel bar truss composite floor slab
CN109518858B (en) Assembled beam plate connecting structure and construction method thereof
CN108301545A (en) A kind of big module overlapping contignation of the assembled with space truss temporary support
CN113152764A (en) Prefabricated composite floor slab adopting riveting C-shaped steel and steel plate and construction method thereof
CN108222347A (en) A kind of big module welding overlapping beam slab of the assembled with plane girder temporary support
CN103397727A (en) Connection structure of building steel beam and composite floor slab
CN211499378U (en) Closely piece together two-way rib superimposed sheet node structure that does not go out
CN211499312U (en) Bolt type connection structure of partially-coated concrete combined shear wall
CN112832415A (en) Partially-coated steel-concrete combined shear wall member
CN201176366Y (en) Hook structure for suspensing transportation device added in buildings
CN216920791U (en) T-shaped shear wall assembly and building structure
CN114164976B (en) Support-free U-shaped composite floor slab and construction method thereof
CN214461399U (en) Prefabricated wallboard
CN211114081U (en) Z-shaped double-splint node assembly type H-shaped steel beam square steel pipe column steel structure system
CN213978596U (en) Thin-wall steel box concrete combined bridge tower
CN113215948A (en) Assembled combined box girder and construction method thereof
CN211143440U (en) Assembled bidirectional steel bar truss floor
CN210530024U (en) Vertical concatenation tempering node of partial cladding shaped steel concrete shear force wall
CN211499310U (en) Connection structure of reserved open-hole type partially-coated concrete combined shear wall
CN110820993A (en) Connecting process of reserved open-hole type partially-coated concrete combined shear wall
CN113530051B (en) Prefabricated rib-free laminated slab
CN214785031U (en) Partially-coated steel-concrete combined shear wall member
CN213927078U (en) Prefabricated assembly type steel concrete mixed beam with angle steel connecting piece prefabricated plate part
CN211762332U (en) Concrete box mould
CN111608311B (en) Large-span horizontal combined plate structure and preparation method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200221