CN110700453A - Curtain wall mounting process from top to bottom - Google Patents
Curtain wall mounting process from top to bottom Download PDFInfo
- Publication number
- CN110700453A CN110700453A CN201910825296.3A CN201910825296A CN110700453A CN 110700453 A CN110700453 A CN 110700453A CN 201910825296 A CN201910825296 A CN 201910825296A CN 110700453 A CN110700453 A CN 110700453A
- Authority
- CN
- China
- Prior art keywords
- wall
- structural
- mounting
- structural frame
- curtain wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/88—Curtain walls
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/88—Curtain walls
- E04B2/96—Curtain walls comprising panels attached to the structure through mullions or transoms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/88—Curtain walls
- E04B2/96—Curtain walls comprising panels attached to the structure through mullions or transoms
- E04B2/965—Connections of mullions and transoms
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Load-Bearing And Curtain Walls (AREA)
Abstract
The invention discloses a curtain wall mounting process from top to bottom, which relates to the technical field of curtain wall mounting processes and aims to solve the technical problem that the mounted curtain wall is easy to damage when being mounted from bottom to top, and the technical scheme is characterized by comprising the following steps: s1, designing the size of the structural frame and the corresponding decorative plate according to the size of the external wall of the building; s2, producing the structural frame and the decorative plate in a factory; s3, transporting the structural frame and the decorative plate to a construction site; s4, mounting and fixing the structural frame and the decorative plate from top to bottom on a construction site; the structural frames and the decorative plates are installed from top to bottom, so that even if the structural frames or the decorative plates which are installed fall off due to an accident in the installation process, the structural frames or the decorative plates which fall off cannot scratch or rub the installed structural frames or the installed decorative plates, and the safety coefficient of the installed structural frames and the installed decorative plates is higher.
Description
Technical Field
The invention relates to the technical field of curtain wall installation processes, in particular to a curtain wall installation process from top to bottom.
Background
The curtain wall is a light wall for decorating buildings.
The curtain wall installation mode among the prior art is shown with reference to fig. 5, and it includes the structural framework 2 who sets firmly in building 1 lateral wall and sets firmly decorative board 3 in structural framework 2, during the installation among the prior art, often installs structural framework 2 and decorative board 3 from bottom to top, finally accomplishes holistic curtain wall installation.
However, in the process of installing the structural frame 2 and the decorative plate 3 from bottom to top, if the operator mistakenly operates to cause the structural frame 2 or the decorative plate 3 being installed to fall down, the structural frame 2 or the decorative plate 3 which is located below and is installed is easily damaged, and the curtain wall which is installed is damaged, so that improvement is needed.
Disclosure of Invention
Aiming at the defects in the prior art, the invention aims to provide a curtain wall mounting process from top to bottom, which has the advantage that the mounted curtain wall cannot be damaged even if a structural frame or a decorative plate which is being mounted falls off.
In order to achieve the purpose, the invention provides the following technical scheme:
a curtain wall mounting process from top to bottom comprises the following steps:
s1, designing the size of the structural frame and the corresponding decorative plate according to the size of the external wall of the building;
s2, producing the structural frame and the decorative plate in a factory;
s3, transporting the structural frame and the decorative plate to a construction site;
s4, mounting and fixing the structural frame and the decorative plate from top to bottom on a construction site;
the step S4 specifically includes the following steps:
s41, accurately ejecting the installation position line of the structural frame to the outer wall of the building body according to the size of the outer wall of the building body and a design construction drawing;
s42, fixing the structural frame in an installation position line of the building outer wall through expansion bolts;
and S43, fixing the decorative plate on the inner side of the structural frame through structural adhesive.
By adopting the technical scheme, the structural frames and the decorative plates are installed from top to bottom, so that even if the structural frames or the decorative plates which are being installed fall off due to an accident situation in the installation process, the falling structural frames or the falling decorative plates cannot scratch or rub the installed structural frames and the installed decorative plates, and the safety coefficient of the installed structural frames and the installed decorative plates is higher.
Further, structural framework includes a pair of montant and a horizontal pole, the both ends of horizontal pole have all set firmly the inserted block, the both ends of montant have all set firmly the slot, inserting of inserted block adaptation is established to the slot in, the slot lateral wall is equipped with the preformed hole along the horizontal direction, slidable wears to be equipped with mounting bolt in the preformed hole, the inserted block lateral wall is equipped with the mounting hole that supplies mounting bolt threaded connection.
By adopting the technical scheme, during installation, the insertion blocks at the end parts of the two cross rods are respectively inserted into the insertion grooves at the two ends of the installed vertical rod, and the two installation bolts are respectively screwed into the two installation holes to complete the fixation of the two cross rods; installing the vertical rod on the other side to the end parts of the two cross rods, respectively inserting the insertion blocks at the other ends of the two cross rods into the slots at the two ends of the vertical rod which is not installed, respectively screwing the two installation bolts into the two installation holes, and then fixing the vertical rod with the outer wall of the building body through the expansion bolts; the structural frame is formed by assembling a pair of vertical rods and a pair of transverse rods, and compared with a traditional integrated square frame body, the structural frame occupies a smaller space during transportation, the vertical rods and the transverse rods after production and forming can be transported separately, and the structural frame can be directly assembled on site and is convenient to assemble.
Further, the step S42 specifically includes the following steps:
s421, fixing the vertical rod on one side with the outer wall of the building body through an expansion bolt;
s422, inserting the insertion blocks at the end parts of the two cross rods into the insertion grooves at the two ends of the installed vertical rod respectively, and screwing the two installation bolts into the two installation holes respectively to complete the fixation of the two cross rods;
s423, installing the vertical rod on the other side to the end parts of the two cross rods, respectively inserting the inserting blocks at the other ends of the two cross rods into the inserting grooves at the two ends of the vertical rod which is not installed, respectively rotating the two installation bolts into the two installation holes, and then fixing the vertical rod with the outer wall of the building body through the expansion bolts.
Through adopting above-mentioned technical scheme, can realize the equipment of structural frame itself to can realize the whole installation with the building body of structural frame, convenient operation.
Furthermore, two the montant and horizontal pole inner wall all are equipped with the mounting groove along its length direction, the edge of decorative board is inserted and is established to the mounting groove in.
Through adopting above-mentioned technical scheme, after the installation of accomplishing one side montant and both sides horizontal pole, can insert the three sides edges of decorative board and establish to the mounting groove in, can tentatively accomplish decorative board and structural frame's installation, after the installation of opposite side montant, can finally realize decorative board and structural frame's installation, and make the decorative board difficult take place not hard up with structural frame, effectively restricted the activity space of decorative board through the mounting groove, improved the stability after the decorative board installation is accomplished.
Further, the edge of decorative board is equipped with buffering package strip, buffering package strip and mounting groove interference fit, buffering package strip is equipped with the spread groove along its length direction, the edge of decorative board is inserted and is established to the spread groove in.
By adopting the technical scheme, the edge of the decorative plate is not easy to be collided and damaged by the buffer wrapping strip; and the buffering package strip can make decorative board and buffering package strip insert and establish to the mounting groove in the back, and decorative board and mounting groove direct contact not can make decorative board can receive certain cushioning effect under adverse circumstances such as strong wind through buffering package strip, avoids decorative board and mounting groove inner wall violent collision to lead to the decorative board to damage, has prolonged the life of decorative board.
Furthermore, two opposite side walls of the buffering wrapping strip are respectively provided with a butt joint strip and a butt joint groove.
Through adopting above-mentioned technical scheme, during the transportation decorative board, can insert the butt strip and establish to the butt inslot of adjacent buffering package strip, can make the state that a plurality of decorative boards piled up more stable, be convenient for carry out stable, safe transportation to the decorative board more.
Further, the step S43 includes: and filling structural adhesive at the notch of the mounting groove.
Through adopting above-mentioned technical scheme, glue the structure and coat in the notch department of mounting groove, glue through the structure and can promote the joint strength of decorative board and mounting groove, and the structure is glued ageing-resistant, corrosion-resistant, and longe-lived, has further prolonged the life-span of decorative board and structural framework.
Further, the structural adhesive comprises an inner layer adhesive and an outer layer adhesive, the thickness of the inner layer adhesive and the thickness of the outer layer adhesive are both 1.5mm, after the inner layer adhesive is laid, hot air with the temperature higher than 90 ℃ is used for heating, and after 1.5h, the outer layer adhesive is laid.
By adopting the technical scheme, the inner layer adhesive can be cured more quickly under the action of hot air with the temperature of more than 90 ℃ for 1.5 hours, so that the decorative plate which is just installed and the structural frame are stably connected, and the safety coefficient of constructors positioned below the decorative plate which is just installed and the structural frame is higher; and then coating the outer layer glue, and slowly curing the outer layer glue in a natural state to ensure that the structural strength of the outer layer glue is higher.
Furthermore, a gap which is larger than the length of the insertion block is reserved between the adjacent structural frames.
Through adopting above-mentioned technical scheme, when the decorative board damages and needs to be changed, can glue the structure and clear away the back, rotate construction bolt for construction bolt takes out from the mounting hole, demolishs expansion bolts, can demolish one side montant and two horizontal poles after this, can change the decorative board that damages, makes when needs maintain, and the dismouting is accomplished to the frame of structure also.
Further, building body outer wall is located and is connected with the packing strip between the continuous structure frame detachable, the packing strip is laminated with adjacent structure frame outer wall mutually.
Through adopting above-mentioned technical scheme, when need not the maintenance, insert the clearance department of establishing to adjacent structure frame with the packing strip to make the surface of a plurality of structure frame dorsad building body and the surface of packing strip dorsad building body be in the coplanar, avoid animals such as birds to nest in the clearance department of adjacent structure frame, when needs maintenance, take out the packing strip, can flow the region that supplies montant and horizontal pole to remove, be convenient for follow-up maintenance.
In conclusion, the invention has the following beneficial effects:
1. the following steps are adopted: s1, designing the size of the structural frame and the corresponding decorative plate according to the size of the external wall of the building; s2, producing the structural frame and the decorative plate in a factory; s3, transporting the structural frame and the decorative plate to a construction site; s4, mounting and fixing the structural frame and the decorative plate from top to bottom on a construction site; step S4 specifically includes the following steps: s41, accurately ejecting the installation position line of the structural frame to the outer wall of the building body according to the size of the outer wall of the building body and a design construction drawing; s42, fixing the structural frame in an installation position line of the building outer wall through expansion bolts; s43, fixing the decorative plate on the inner side of the structural frame through structural adhesive; the structural frames and the decorative plates are installed from top to bottom, so that even if the structural frames or the decorative plates which are installed fall off due to an accident in the installation process, the structural frames or the decorative plates which fall off cannot scratch the installed structural frames or the installed decorative plates, and the safety coefficient of the installed structural frames and the installed decorative plates is higher;
2. the structure frame comprises a pair of vertical rods and a cross rod, the two ends of the cross rod are fixedly provided with inserting blocks, the two ends of each vertical rod are fixedly provided with inserting grooves, the inserting blocks are inserted into the inserting grooves in a matching mode, the side walls of the inserting grooves are provided with reserved holes in the horizontal direction, mounting bolts can penetrate through the reserved holes in a sliding mode, and the side walls of the inserting blocks are provided with mounting holes for the mounting bolts to be in threaded connection; during installation, the insertion blocks at the end parts of the two cross rods are respectively inserted into the insertion grooves at the two ends of the installed vertical rod, and the two installation bolts are respectively screwed into the two installation holes to complete the fixation of the two cross rods; installing the vertical rod on the other side to the end parts of the two cross rods, respectively inserting the insertion blocks at the other ends of the two cross rods into the slots at the two ends of the vertical rod which is not installed, respectively screwing the two installation bolts into the two installation holes, and then fixing the vertical rod with the outer wall of the building body through the expansion bolts; the structural frame is formed by assembling a pair of vertical rods and a pair of transverse rods, and compared with a traditional integrated square frame body, the structural frame occupies a smaller space during transportation, the vertical rods and the transverse rods after production and forming can be transported separately, and the structural frame can be directly assembled on site and is convenient to assemble.
Drawings
FIG. 1 is a schematic structural diagram of the present embodiment;
FIG. 2 is a cross-sectional view of the embodiment showing the connection relationship between the cross bar and the vertical bar;
FIG. 3 is a sectional view of the present embodiment for illustrating the connection relationship between the decorative plate and the installation groove;
FIG. 4 is a cross-sectional view of the present embodiment showing the positional relationship between the structural frame and the filler strip;
fig. 5 is a background art drawing.
In the figure: 1. a building body; 2. a structural frame; 21. a vertical rod; 22. a cross bar; 23. inserting a block; 230. a slot; 24. installing a bolt; 240. reserving a hole; 2400. mounting holes; 3. a decorative plate; 30. mounting grooves; 31. buffering the wrapping strips; 310. connecting grooves; 32. an abutment bar; 320. a butt joint groove; 4. structural adhesive; 41. inner glue layer; 42. outer layer glue; 5. filling the strip; 51. a nylon hook tape; 52. nylon velvet belt.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Example 1:
a curtain wall mounting process from top to bottom comprises the following structural parts: referring to fig. 1, it includes the building body 1, and 1 outer wall equipartition of building body has a plurality of structural frame 2, and structural frame 2 passes through expansion bolts and 1 outer wall fixed connection of building body. A decorative plate 3 is fixedly arranged in the structural frame 2.
Referring to fig. 2, structural framework 2 includes a pair of montant 21 and a pair of horizontal pole 22, the homogeneous body shaping in both ends of horizontal pole 22 has inserted block 23, the both ends of montant 21 all set firmly slot 230, inserting of inserted block 23 adaptation is established to the slot 230 in, the slot 230 lateral wall is equipped with preformed hole 240 along the horizontal direction, slidable wears to be equipped with mounting bolt 24 in the preformed hole 240, inserted block 23 lateral wall is equipped with mounting hole 2400, mounting bolt 24's screw rod portion and mounting hole 2400 threaded connection.
Referring to fig. 3, the edge of the decorative plate 3 is provided with a cushion wrap strip 31, and the cushion wrap strip 31 is preferably made of rubber. The two opposite side walls of the buffering wrapping strip 31 are respectively and integrally formed with an abutting strip 32 and an abutting groove 320, and the abutting strip 32 is matched with the abutting groove 320. The buffer packing strip 31 is provided with a connecting groove 310 along the length direction thereof, and the edge of the decorative plate 3 is inserted into the connecting groove 310.
Referring to fig. 3, the inner walls of the two vertical bars 21 and the cross bar 22 are provided with mounting grooves 30 along the length direction thereof, the edges of the decorative plate 3 and the buffering wrapping strips 31 are integrally inserted into the mounting grooves 30, and the buffering wrapping strips 31 are in interference fit with the mounting grooves 30. The notch department of mounting groove 30 has laid the structure and has glued 4, and the structure is glued 4 and is glued 41 and outer layer including the inlayer and glue 42, and the thickness that inlayer was glued 41 and outer layer and is glued 42 is 1.5 mm.
Referring to fig. 4, a gap larger than the length of the insert block 23 is left between the adjacent structural frames 2. The outer wall of the building body 1 is provided with a filling strip 5 between the connected structural frames 2, and the preferred hollow light plastic for the filling strip 5. The intrinsic nylon pile belt 52 of lateral wall adhesion of 5 orientation buildings 1 of packing strip, 1 outer wall of buildings is located and has nylon hook area 51 through the fix with screw between the adjacent structural frame 2, and nylon hook area 51 is attached mutually with nylon pile belt 52 to realize packing strip 5 and buildings 1's dismantling and be connected. The surface of the filling strip 5 back to the building body 1 and the surface of the structural frame 2 back to the building body 1 are located in the same plane, and the filling strip 5 is attached to the side wall of the adjacent structural frame 2.
A curtain wall mounting process from top to bottom comprises the following steps:
s1, designing the sizes of the structural frame 2 and the corresponding decorative plate 3 according to the size of the outer wall of the building body 1, and enabling the structural frames 2 to be matched with the outer wall of the building body 1 after being pre-assembled.
S2, the structural frame 2 and the decorative plate 3 are produced in a factory, and the error is controlled within +/-1 mm.
S3, transporting the structural frame 2 and the decorative plates 3 to a construction site, bundling and transporting a plurality of vertical rods 21 and a plurality of horizontal rods 22 respectively, stacking the edge cladding buffering wrapping strips 31 of a plurality of decorative plates 3 in sequence, and inserting the abutting strips 32 into the abutting grooves 320 of the adjacent decorative plates 3.
And S4, mounting and fixing the structural frame 2 and the decorative plate 3 from top to bottom on the construction site.
Step S4 specifically includes the following steps:
and S41, accurately ejecting the installation position line of the structural frame 2 to the outer wall of the building body 1 according to the size of the outer wall of the building body 1 and a design construction drawing.
And S42, fixing the structural frame 2 in the installation position line of the outer wall of the building body 1 through expansion bolts.
Step S42 specifically includes the following steps:
s421, fixing the vertical rod 21 on one side with the outer wall of the building body 1 through an expansion bolt.
S422, the insertion blocks 23 at the ends of the two cross bars 22 are respectively inserted into the insertion slots 230 at the two ends of the installed vertical bars 21, the two installation bolts 24 are respectively screwed into the two installation holes 2400 to complete the fixation of the two cross bars 22, and the edge of the decorative plate 3 and the cushion wrapping strip 31 are inserted into the installation slot 30.
S423, mounting the vertical rod 21 at the other side to the end of the two horizontal rods 22, so that the insertion blocks 23 at the other end of the two horizontal rods 22 are respectively inserted into the insertion slots 230 at the two ends of the vertical rod 21, respectively screwing the two mounting bolts 24 into the two mounting holes 2400, and then fixing the vertical rod 21 to the outer wall of the building 1 through the expansion bolts.
S43, fixing the decorative plate 3 on the inner side of the structural frame 2 through structural adhesive 4, namely coating the notch of the mounting groove 30 by dogs, wherein the structural adhesive 4 comprises inner layer adhesive 41 and outer layer adhesive 42, firstly laying the inner layer adhesive 41, heating by hot air with the temperature of more than 90 ℃ to promote the curing of the inner layer adhesive 41, and laying the outer layer adhesive 42 after 1.5 h.
The working principle is as follows: the structural frames 2 and the decorative plates 3 are installed from top to bottom, so that even if the structural frames 2 or the decorative plates 3 which are being installed fall off due to an accident in the installation process, the structural frames 2 or the decorative plates 3 which fall off cannot scratch the structural frames 2 and the decorative plates 3 which are installed, and the safety coefficient of the structural frames 2 and the decorative plates 3 which are installed is higher.
In addition, the structural frame 2 is formed by assembling a pair of vertical rods 21 and a pair of cross rods 22, and compared with a traditional integrated square frame body, the transportation space is smaller, the vertical rods 21 and the cross rods 22 after production and forming can be transported separately, the site can be directly assembled, and the assembly is convenient.
In addition, buffering package strip 31 cladding in the edge of decorative board 3, can be so that the edge of decorative board 3 is difficult for receiving to collide with and damage, and the cladding has the decorative board 3 that cushions package strip 31 to superpose in proper order, and the butt strip 32 butt that will cushion package strip 31 to the butt groove 320 of adjacent buffering package strip 31 in, can be so that the structure of a plurality of decorative boards 3 that stack is more stable, the further decorative board 3 of being convenient for carries out the steady transportation, and the decorative board 3 is difficult impaired in the transportation.
In addition, the inner layer glue 41 can be cured more quickly under the action of hot air with the temperature of more than 90 ℃ for 1.5 hours, so that the decorative plate 3 which is just installed and the structural frame 2 are stably connected, and the safety factor of constructors positioned below the decorative plate 3 which is just installed and the structural frame 2 is higher; after that, the outer layer glue 42 is coated, and the outer layer glue 42 is slowly cured in a natural state, so that the structural strength of the outer layer glue 42 is higher.
The present embodiment is only for explaining the present invention, and it is not limited to the present invention, and those skilled in the art can make modifications of the present embodiment without inventive contribution as needed after reading the present specification, but all of them are protected by patent law within the scope of the claims of the present invention.
Claims (10)
1. The curtain wall mounting process from top to bottom is characterized by comprising the following steps of:
s1, designing the sizes of the structural frame (2) and the corresponding decorative plate (3) according to the size of the outer wall of the building body (1);
s2, producing the structural frame (2) and the decorative plate (3) in a factory;
s3, transporting the structural frame (2) and the decorative plate (3) to a construction site;
s4, mounting and fixing the structural frame (2) and the decorative plate (3) from top to bottom on a construction site;
the step S4 specifically includes the following steps:
s41, accurately bouncing the installation position line of the structural frame (2) to the outer wall of the building body (1) according to the size of the outer wall of the building body (1) and a design construction drawing;
s42, fixing the structural frame (2) in an installation position line of an outer wall of the building body (1) through expansion bolts;
s43, fixing the decorative plate (3) on the inner side of the structural frame (2) through structural adhesive (4).
2. The curtain wall mounting process from top to bottom as claimed in claim 1, wherein: structural frame (2) include a pair of montant (21) and a pair of horizontal pole (22), the both ends of horizontal pole (22) have all set firmly insert piece (23), slot (230) have all set firmly at the both ends of montant (21), insert piece (23) adaptation insert establish to slot (230) in, slot (230) lateral wall is equipped with preformed hole (240) along the horizontal direction, slidable wears to be equipped with construction bolt (24) in preformed hole (240), insert piece (23) lateral wall is equipped with mounting hole (2400) that supply construction bolt (24) threaded connection.
3. The curtain wall mounting process from top to bottom as claimed in claim 2, wherein: the step S42 specifically includes the following steps:
s421, fixing the vertical rod (21) on one side with the outer wall of the building body (1) through an expansion bolt;
s422, inserting blocks (23) at the end parts of the two cross rods (22) into slots (230) at the two ends of the installed vertical rod (21) respectively, and screwing the two mounting bolts (24) into the two mounting holes (2400) respectively to fix the two cross rods (22);
s423, installing the vertical rod (21) on the other side to the end parts of the two cross rods (22), respectively inserting the inserting blocks (23) at the other ends of the two cross rods (22) into the inserting grooves (230) at the two ends of the vertical rod (21) which is not installed, respectively screwing the two mounting bolts (24) into the two mounting holes (2400), and then completing the fixation of the vertical rod (21) with the outer wall of the building body (1) through the expansion bolts.
4. The curtain wall mounting process from top to bottom as claimed in claim 3, wherein: two the montant (21) and horizontal pole (22) inner wall all are equipped with mounting groove (30) along its length direction, the edge of decorative board (3) is inserted and is established to mounting groove (30) in.
5. The curtain wall mounting process from top to bottom as claimed in claim 4, wherein: the edge of decorative board (3) is equipped with buffering package strip (31), buffering package strip (31) and mounting groove (30) interference fit, buffering package strip (31) are equipped with spread groove (310) along its length direction, the edge of decorative board (3) is inserted and is established to spread groove (310) in.
6. The curtain wall mounting process from top to bottom as claimed in claim 5, wherein: two opposite side walls of the buffer wrapping strip (31) are respectively provided with a butt joint strip (32) and a butt joint groove (320).
7. The curtain wall mounting process from top to bottom as claimed in claim 5, wherein: the step S43 includes: and structural adhesive (4) is filled in the notch of the mounting groove (30).
8. The process for installing the curtain wall from top to bottom as claimed in claim 7, wherein: the structural adhesive (4) comprises an inner layer adhesive (41) and an outer layer adhesive (42), the thickness of the inner layer adhesive (41) and the thickness of the outer layer adhesive (42) are both 1.5mm, after the inner layer adhesive (41) is laid, hot air with the temperature higher than 90 ℃ is used for heating, and after 1.5h, the outer layer adhesive (42) is laid.
9. The curtain wall mounting process from top to bottom as claimed in claim 2, wherein: a gap which is longer than the length of the inserting block (23) is reserved between the adjacent structural frames (2).
10. The process for installing the curtain wall from top to bottom as claimed in claim 9, wherein: building body (1) outer wall is located detachable and is connected with packing strip (5) between continuous structure frame (2), packing strip (5) and adjacent structure frame (2) outer wall laminate mutually.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910825296.3A CN110700453A (en) | 2019-09-03 | 2019-09-03 | Curtain wall mounting process from top to bottom |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910825296.3A CN110700453A (en) | 2019-09-03 | 2019-09-03 | Curtain wall mounting process from top to bottom |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110700453A true CN110700453A (en) | 2020-01-17 |
Family
ID=69194275
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910825296.3A Pending CN110700453A (en) | 2019-09-03 | 2019-09-03 | Curtain wall mounting process from top to bottom |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110700453A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3282026B2 (en) * | 1997-10-22 | 2002-05-13 | ワイケイケイアーキテクチュラルプロダクツ株式会社 | Projection unit of curtain wall |
CN2642962Y (en) * | 2003-04-26 | 2004-09-22 | 王业兴 | Combined door or window made of woody shaped material |
CN201074300Y (en) * | 2007-08-06 | 2008-06-18 | 北京利建恒高新技术有限公司 | Fending handrail |
CN103397726A (en) * | 2013-08-16 | 2013-11-20 | 中国建筑第八工程局有限公司 | Construction method for distorted glass curtain wall |
CN203782945U (en) * | 2014-04-10 | 2014-08-20 | 常泰建筑装璜工程有限公司 | Semi-exposed framing glass curtain wall |
CN105155686A (en) * | 2015-09-18 | 2015-12-16 | 北京恒通创新赛木科技股份有限公司 | House beam column and profile connection structure and sleeper integration house |
CN107882220A (en) * | 2017-10-31 | 2018-04-06 | 广州市恒盛建设工程有限公司 | A kind of construction method of L-shaped biplane hyperbolic aluminum facade |
-
2019
- 2019-09-03 CN CN201910825296.3A patent/CN110700453A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3282026B2 (en) * | 1997-10-22 | 2002-05-13 | ワイケイケイアーキテクチュラルプロダクツ株式会社 | Projection unit of curtain wall |
CN2642962Y (en) * | 2003-04-26 | 2004-09-22 | 王业兴 | Combined door or window made of woody shaped material |
CN201074300Y (en) * | 2007-08-06 | 2008-06-18 | 北京利建恒高新技术有限公司 | Fending handrail |
CN103397726A (en) * | 2013-08-16 | 2013-11-20 | 中国建筑第八工程局有限公司 | Construction method for distorted glass curtain wall |
CN203782945U (en) * | 2014-04-10 | 2014-08-20 | 常泰建筑装璜工程有限公司 | Semi-exposed framing glass curtain wall |
CN105155686A (en) * | 2015-09-18 | 2015-12-16 | 北京恒通创新赛木科技股份有限公司 | House beam column and profile connection structure and sleeper integration house |
CN107882220A (en) * | 2017-10-31 | 2018-04-06 | 广州市恒盛建设工程有限公司 | A kind of construction method of L-shaped biplane hyperbolic aluminum facade |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP1296004B1 (en) | A cladding board mounting system | |
EP2492408A1 (en) | Joint structure for building frame | |
US20130312352A1 (en) | Prefabricated Cladding Assembly | |
CN104453152B (en) | Detachable wood hanging plate hanging piece system and mounting method thereof | |
CN110792227A (en) | Structure and installation method of extruded material ceiling | |
CN211597508U (en) | Outer wall decorative board convenient to installation | |
CN112144807A (en) | Wallboard mounting structure and mounting method thereof | |
CN110700453A (en) | Curtain wall mounting process from top to bottom | |
US20170081849A1 (en) | Facade construction | |
CN113550515A (en) | Assembly type wall surface system with plug-in wall top closing-up structure and installation method | |
CN109930944B (en) | Mounting method of hidden auxiliary sleeve | |
CN112095853A (en) | Assembled bathroom wallboard system and installation method | |
CN111305404A (en) | Assembled composite building insulation board and installation method thereof | |
CN113550516B (en) | Assembled wall system with wall top closing-in structure and installation method thereof | |
CN110821071A (en) | A plastic-aluminum board erection joint structure for outer wall installation | |
CN215889027U (en) | Assembled wall system with wallboard capable of being installed transversely and vertically in two directions | |
CN211286204U (en) | Aluminum veneer curtain wall with mounting structure | |
CN213477506U (en) | Indoor overhead ground system | |
CN201943216U (en) | External corner fixing device of heat insulation board | |
CN201943205U (en) | Internal corner fixing device for insulation board | |
CN102031856B (en) | Installing base for clamping floor system without using nails | |
CN115370087B (en) | Assembled porcelain plate dry-hanging system | |
CN215759985U (en) | Novel multifunctional keel structure | |
CN211691241U (en) | Assembled wall panel structure | |
CN210380105U (en) | Novel cross arm anchoring ultra-strong thin plate cable bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200117 |
|
RJ01 | Rejection of invention patent application after publication |