CN110485468A - 一种富水地层预设顶管门洞的永久性圆形工作井及其施工方法 - Google Patents
一种富水地层预设顶管门洞的永久性圆形工作井及其施工方法 Download PDFInfo
- Publication number
- CN110485468A CN110485468A CN201910731042.5A CN201910731042A CN110485468A CN 110485468 A CN110485468 A CN 110485468A CN 201910731042 A CN201910731042 A CN 201910731042A CN 110485468 A CN110485468 A CN 110485468A
- Authority
- CN
- China
- Prior art keywords
- round
- push pipe
- seal reservoir
- door opening
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 88
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 38
- 239000004567 concrete Substances 0.000 claims abstract description 68
- 238000013461 design Methods 0.000 claims abstract description 24
- 238000000034 method Methods 0.000 claims abstract description 20
- 238000007689 inspection Methods 0.000 claims abstract description 16
- 238000009434 installation Methods 0.000 claims abstract description 16
- 238000007789 sealing Methods 0.000 claims abstract description 15
- 238000003825 pressing Methods 0.000 claims abstract description 12
- 238000009412 basement excavation Methods 0.000 claims abstract description 10
- 239000000463 material Substances 0.000 claims description 8
- 238000012423 maintenance Methods 0.000 claims description 7
- 239000002861 polymer material Substances 0.000 claims description 7
- 239000002689 soil Substances 0.000 claims description 7
- 238000004364 calculation method Methods 0.000 claims description 6
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 238000005260 corrosion Methods 0.000 claims description 4
- 238000012545 processing Methods 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 238000005266 casting Methods 0.000 claims description 3
- 238000012937 correction Methods 0.000 claims description 3
- 238000007667 floating Methods 0.000 claims description 3
- 238000009415 formwork Methods 0.000 claims description 3
- 239000000203 mixture Substances 0.000 claims description 3
- 230000035515 penetration Effects 0.000 claims description 3
- 238000002360 preparation method Methods 0.000 claims description 3
- 230000003014 reinforcing effect Effects 0.000 claims description 3
- 238000004088 simulation Methods 0.000 claims description 3
- 239000000758 substrate Substances 0.000 claims description 3
- 238000012360 testing method Methods 0.000 claims description 3
- 238000012795 verification Methods 0.000 claims description 3
- 230000008595 infiltration Effects 0.000 claims description 2
- 238000001764 infiltration Methods 0.000 claims description 2
- 238000004891 communication Methods 0.000 abstract description 7
- 238000010438 heat treatment Methods 0.000 abstract description 7
- 230000008901 benefit Effects 0.000 abstract description 4
- 239000004576 sand Substances 0.000 abstract description 3
- 201000010099 disease Diseases 0.000 abstract 1
- 208000037265 diseases, disorders, signs and symptoms Diseases 0.000 abstract 1
- 238000005516 engineering process Methods 0.000 description 9
- 230000000694 effects Effects 0.000 description 3
- 238000003780 insertion Methods 0.000 description 2
- 230000037431 insertion Effects 0.000 description 2
- 230000002411 adverse Effects 0.000 description 1
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 238000003908 quality control method Methods 0.000 description 1
- 238000004064 recycling Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 239000010865 sewage Substances 0.000 description 1
- 230000001360 synchronised effect Effects 0.000 description 1
- 238000004078 waterproofing Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/08—Lowering or sinking caissons
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/16—Jointing caissons to the foundation soil, specially to uneven foundation soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
- E02D29/125—Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the lining of the shaft
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/16—Arrangement or construction of joints in foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
- E02D31/025—Draining membranes, sheets or fabric specially adapted therefor, e.g. with dimples
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Revetment (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910731042.5A CN110485468B (zh) | 2019-08-08 | 2019-08-08 | 一种富水地层预设顶管门洞的永久性圆形工作井及其施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910731042.5A CN110485468B (zh) | 2019-08-08 | 2019-08-08 | 一种富水地层预设顶管门洞的永久性圆形工作井及其施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110485468A true CN110485468A (zh) | 2019-11-22 |
CN110485468B CN110485468B (zh) | 2021-04-16 |
Family
ID=68550299
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910731042.5A Active CN110485468B (zh) | 2019-08-08 | 2019-08-08 | 一种富水地层预设顶管门洞的永久性圆形工作井及其施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110485468B (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US11143027B2 (en) * | 2019-08-08 | 2021-10-12 | Infrastructure Renewal Institute of Southern China | Rectangular working well with preset pipe jacking hole and sliding back wall in water-rich stratum and construction method thereof |
CN113668585A (zh) * | 2021-09-03 | 2021-11-19 | 中建安装集团南京建设有限公司 | 一种高压水地区深大取水沉井结构及施工方法 |
CN114278306A (zh) * | 2021-12-13 | 2022-04-05 | 中铁上海工程局集团市政环保工程有限公司 | 一种微型顶管作业工井支护结构及其施工工艺 |
CN114703899A (zh) * | 2022-03-16 | 2022-07-05 | 上海市政工程设计研究总院(集团)有限公司 | 预制管状构件、顶管工作井及其施工方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2006065923A2 (en) * | 2004-12-14 | 2006-06-22 | Raytheon Utd | Centralizer-based survey and navigation device and method |
CN102537517A (zh) * | 2011-12-16 | 2012-07-04 | 马鞍山钢铁建设集团有限公司 | 一种向江、河、湖中顶管施工工艺 |
CN103195158A (zh) * | 2013-04-03 | 2013-07-10 | 济南城建集团有限公司 | 一种市政排水管线泥水平衡顶管施工方法 |
CN106958256A (zh) * | 2017-03-22 | 2017-07-18 | 中建四局第五建筑工程有限公司 | 一种分层浇筑、多次下沉的沉井施工工艺 |
CN109356183A (zh) * | 2018-11-26 | 2019-02-19 | 武汉市市政建设集团有限公司 | 一种沉井预留洞口封堵结构及其施工方法 |
CN109826630A (zh) * | 2019-02-02 | 2019-05-31 | 上海城建水务工程有限公司 | 一种用于顶管施工的预制混凝土沉井装置及其施工方法 |
CN109898535A (zh) * | 2019-01-10 | 2019-06-18 | 刘建华 | 预制装配式顶管工作井预应力沉井及拼装方法 |
-
2019
- 2019-08-08 CN CN201910731042.5A patent/CN110485468B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2006065923A2 (en) * | 2004-12-14 | 2006-06-22 | Raytheon Utd | Centralizer-based survey and navigation device and method |
CN102537517A (zh) * | 2011-12-16 | 2012-07-04 | 马鞍山钢铁建设集团有限公司 | 一种向江、河、湖中顶管施工工艺 |
CN103195158A (zh) * | 2013-04-03 | 2013-07-10 | 济南城建集团有限公司 | 一种市政排水管线泥水平衡顶管施工方法 |
CN106958256A (zh) * | 2017-03-22 | 2017-07-18 | 中建四局第五建筑工程有限公司 | 一种分层浇筑、多次下沉的沉井施工工艺 |
CN109356183A (zh) * | 2018-11-26 | 2019-02-19 | 武汉市市政建设集团有限公司 | 一种沉井预留洞口封堵结构及其施工方法 |
CN109898535A (zh) * | 2019-01-10 | 2019-06-18 | 刘建华 | 预制装配式顶管工作井预应力沉井及拼装方法 |
CN109826630A (zh) * | 2019-02-02 | 2019-05-31 | 上海城建水务工程有限公司 | 一种用于顶管施工的预制混凝土沉井装置及其施工方法 |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US11143027B2 (en) * | 2019-08-08 | 2021-10-12 | Infrastructure Renewal Institute of Southern China | Rectangular working well with preset pipe jacking hole and sliding back wall in water-rich stratum and construction method thereof |
CN113668585A (zh) * | 2021-09-03 | 2021-11-19 | 中建安装集团南京建设有限公司 | 一种高压水地区深大取水沉井结构及施工方法 |
CN114278306A (zh) * | 2021-12-13 | 2022-04-05 | 中铁上海工程局集团市政环保工程有限公司 | 一种微型顶管作业工井支护结构及其施工工艺 |
CN114703899A (zh) * | 2022-03-16 | 2022-07-05 | 上海市政工程设计研究总院(集团)有限公司 | 预制管状构件、顶管工作井及其施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN110485468B (zh) | 2021-04-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110485470A (zh) | 一种富水地层预设顶管门洞与滑移式后靠墙的矩形工作井及其施工方法 | |
CN101139838B (zh) | 高承压水地区超深基坑的施工方法 | |
CN110485468A (zh) | 一种富水地层预设顶管门洞的永久性圆形工作井及其施工方法 | |
CN108442382B (zh) | 横穿深基坑的压力管线原位保护及围护挡土结构及施工方法 | |
CN109723065A (zh) | 加固装置及富水砂砾地层中深基坑局部冷冻加固施工方法 | |
CN107190752B (zh) | 一种柔性复合防渗装配式可回收矩形截面排桩支护结构的设计施工方法 | |
CN111236957B (zh) | 机械顶管施工工艺 | |
CN108547639B (zh) | 隧道临近既有构筑物的超前同孔多导管分层注浆施工方法 | |
CN107762535A (zh) | 复杂地质环境下隧道明洞暗做施工工艺 | |
CN110043264A (zh) | 一种顶进预制矩形竖井结构型式的施工方法 | |
CN105735322A (zh) | 一种刚柔复合防渗可回收支护结构的设计施工方法 | |
CN102966108A (zh) | 紧临既有建筑物以地下结构为内支撑的深基坑施工方法 | |
CN102758458B (zh) | 地下连续墙修复方法 | |
CN103993885A (zh) | 一种暗挖隧道侧向开洞支撑体系构建方法 | |
CN107130611A (zh) | 一种柔性复合防渗装配式可回收圆截面排桩支护结构的设计施工方法 | |
CN110485467A (zh) | 一种预设可拆卸门洞、滑移式后靠墙的装配式可回收矩形工作井及其施工方法 | |
CN109578014A (zh) | 一种抗突涌封底结构及施工方法 | |
CN211500658U (zh) | 一种适用于砂土地基的浅埋近接隧道支护结构 | |
CN106480891B (zh) | 一种竖井施工方法 | |
CN107023021B (zh) | 一种柔性复合地下连续墙支护结构的设计施工方法 | |
CN107059904A (zh) | 一种地下管廊积水井开挖方法 | |
CN109853604A (zh) | 一种静压水力冲吸沉井施工方法 | |
CN213143117U (zh) | 一种装配式键槽基础挡土墙结构 | |
CN109356589A (zh) | 一种柔性复合阶梯状深圆竖井装配式可回收支护结构的设计施工方法 | |
CN110485465A (zh) | 一种富水地层预设顶管门洞的圆形工作井及其施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20240902 Address after: No. 2 Daxue Road, Tangjiawan Town, Xiangzhou District, Zhuhai City, Guangdong Province 519000 Patentee after: Wang Fuming Country or region after: China Address before: 516029 District 9 of Daxin group, luoqun District, Chenjiang village, Chenjiang sub district office, Zhongkai high tech Zone, Huizhou City, Guangdong Province Patentee before: NANFANG ENGINEERING DETECTION RESTORATION TECHNOLOGY CO.,LTD. Country or region before: China |
|
TR01 | Transfer of patent right |